Contents
1.2 Alignment Options and Construction Method....................................... 1 3 KEY FINDINGS OF THE Environmental Impact Assessment 3 3.2 Environmentally
Friendly Design........................................................... 3 3.3.1 Construction Phase................................................................................................... 5 3.3.2 Operational Phase.................................................................................................... 5 3.4.1 Construction Phase................................................................................................... 6 3.4.2 Operational Phase.................................................................................................... 6 3.5.1 Construction Phase................................................................................................... 7 3.5.2 Operational Phase.................................................................................................... 7 3.6.1 Construction Phase................................................................................................... 7 3.6.2 Operational Phase.................................................................................................... 7 3.10 Waste Management
Implication and Land Contamination........ 9 3.10.1 Waste Management................................................................................................... 9 3.10.2 Contaminated Land................................................................................................. 10 3.11 Environmental
Monitoring and Audit................................................. 10 |
Figures
Figure 1.1 General
Layout Plan
TABLES
1.1.1 The overall Kai Tak
Development (KTD) was a designated project under Schedule 3 of the
Environmental Impact Assessment Ordinance (EIAO). The Schedule 3 EIA Report for the overall Kai
Tak Development (EIAO Register No. AEIAR-130/2009) was carried out under the
Kai Tak Development Engineering Study (KTDES, Agreement No. CE35/2006(CE)) and
was approved by Environmental Protection Department under the EIAO on 4 March
2009. As a part of the strategic road network within the KTD, Route 6 forms an
east west express link between
1.1.2 The Trunk Road T2 project (the Project) is a designated project under Schedule 2 of the EIAO and previously broadly assessed in the KTD Schedule 3 EIA. The Civil Engineering and Development Department (CEDD) (Project Proponent) submitted the Project Profile (No. PP-379/2009) for application for an EIA study brief for the Trunk Road T2 Project under the EIAO on 24 March 2009. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2 Project was issued on 30 April 2009.
1.1.3 The main element of the Trunk Road T2 works comprise the construction of a trunk road connecting with the CKR at the South Apron area and the TKO-LTT at the Cha Kwo Ling (CKL) area. Figure 1.1 shows the demarcation between the Trunk Road T2, CKR and TKO-LTT, which will form the basis of respective environmental impact assessments (EIAs). This Executive Summary highlights the key findings of the EIA for the Trunk Road T2 project to comply with the EIA Ordinance (EIAO).
1.2
Alignment Options and Construction Method
1.2.1 A number of alignment options were identified and considered based upon project constrains. Also, construction methods including the immersed tube (IMT) method and the tunnel boring machine (TBM) method were considered for the major part of T2 i.e. the subsea tunnel. It is concluded that the selected option in Figure 1.1, which is based on the TBM method, is preferred from overall environmental and engineering considerations.
1.2.2 Compared with the
subsea tunnel from the IMT method in the KTDES, the subsea tunnel’s horizontal alignment of the selected option generally follows the horizontal alignment in the KTDES except that the overall width of two tunnel tubes, plus
the separation in-between, is wider than that of the IMT method of the subsea
tunnel in the KTDES. The subsea tunnel’s vertical alignment
of the selection option is generally deeper than the vertical alignment
of the subsea tunnel in the KTDES because the TBM method requires a deeper
vertical alignment than the IMT method due to technical reasons.
1.2.3 For the land
section at the South Apron, the selected option’s tunnel alignment, after entering the seawall at South Apron, rises at a gradient of up to about 5%. The westbound carriageway of the tunnel,
under this gradient, has added
a climbing lane to ensure smooth traffic flows.
The carriageway rises up through a depressed road and becomes at-grade
at the location of Jordan Valley Box Culvert.
1.2.4 For the land
section at the Cha Kwo Ling, the selected option’s tunnel alignment connects
with the TKO-LTT near the waterfront at about the same location in the
KTDES. The vertical alignment at this
short section of tunnel is considerably deeper than that in the KTDES due to
the adjustment in level of the TKO-LTT compared with its vertical alignment at
that time.
2.1.1 Further to the recommendations of the
option assessment and subsequent alignment developments, the preferred Trunk
Road T2 is shown in Figure
1.1 and will comprise:
l
a dual two-lane trunk road of approximately 3.0km long with about 2.7km
of the trunk road in the form of a tunnel;
l
ventilation and administration buildings and a traffic control and
surveillance system; and
l
associated civil, electrical, mechanical, landscaping and environmental
protection and mitigation works.
2.2.1 The Trunk Road T2 project construction works are anticipated to commence at the end of 2015 with completion of
the project by end 2020.
2.3.1 The Trunk Road T2,
together with the proposed CKR and TKO-LTT, will form the Route 6 alignment, a
strategic road network. Route 6 will
provide an east-west express link between West Kowloon and Tseung Kwan O (TKO)
and provide the necessary relief to the existing heavily utilised road network
in the central and eastern
2.3.2 The CKR is planned
to be completed in 2020 to avoid serious traffic congestion in major east-west
road links, such as Gascoigne Road Flyover and Chatham Road North. The TKO-LTT
is also planned to be completed in 2020 to meet the anticipated traffic demand
generated from further development of Tseung Kwan O (TKO). The Trunk Road T2, being the middle section
of Route 6 connecting the CKR and TKO-LTT, is, therefore, also, targeted to be
completed in 2020 to tie in with the completion of the remaining sections of
Route 6.
2.3.3 On an
independently-operated basis, that is without Trunk Road T2, CKR
functions primarily as a link between West Kowloon and Kowloon Bay. The TKO-LTT, also, under an independently-operated basis, functions primarily as a link between Tseung Kwan O and Kwun
Tong. Traffic from
3 KEY FINDINGS OF THE Environmental Impact Assessment
3.1.1 The EIA Study has been conducted in accordance with the EIAO Study Brief No. ESB-203/2009, following the guidelines on assessment methodologies in the Technical Memorandum on Environmental Impact Assessment (EIAO-TM).
3.1.2 The Trunk Road T2 is middle part of Route 6 connecting CKR and TKO-LTT. In this regard, relevant environmental impacts of the Trunk Road T2 have been assessed as part of the cumulative impacts in the CKR and TKO-LTT EIA Reports, both of which have already been submitted under the EIAO and have been approved for consultation by the Director of Environmental Protection (DEP).
3.2 Environmentally Friendly Design
3.2.1 As noted above, a thorough option assessment has been undertaken into to define and select the best environment scheme both from a construction and operational perspective.
3.2.2 The vertical alignment has been selected on the basis that it will avoid impacts to large areas of existing and future sensitive receivers in the Kai Tak Runway and Kowloon Bay area. While the Trunk Road T2 will pass through the future Kai Tak Development on the South Apron, the Trunk road T2 project is largely in tunnel and the planned developments that would be sensitive to air and noise impacts are being suitably planned with measures including setbacks and centralised air conditioning.
3.2.3 While the number and locations of the ventilation buildings are driven by functional requirements, both have been reviewed to minimise and avoid environmental impacts. Two ventilation buildings at either end of the alignment are preferred on environmental grounds having air, noise and landscape and visual benefits over a much larger single building or more buildings. The location of the western ventilation building on the South Apron is highly constrained but has been located as far as practical from the future developments in the Kai Tak development. At the Cha Kwo Ling (CLK) end, it is proposed to locate the eastern ventilation building within the Lam Tine Interchange. This arrangement reduces visual impact on the CKL seafront, is further away from the CKL village and, is, also, on land that is already developed or will be disturbed for the TKO-LTT project and as such, would not affect any natural resources.
3.2.4 In respect of the horizontal alignment, the adoption of a deep tunnel to be constructed by Tunnel Boring Machine (TBM) has notable environmental advantages over the other feasible construction methods, particularly compared to a cut and cover and immersed tube tunnel method of construction. The use of TBM has resulted in the following environmental and marine benefits:
· involves no dredging operations;
· no impacts to marine ecology and fisheries resources;
· due to the deeper depth of boring, the excavated material will be mainly alluvial or rock suitable for recycle/ re-use (on site or offsite) as public fill;
· minimises above ground works and, hence, noise, air quality and landscape and visual impacts;
· minimises operational noise and air emissions from traffic;
· avoid the reconstruction of the existing sewage submarine outfall and breakwaters and disturbance to the marine operations in the Kwun Tong Typhoon Shelter (KTTS); and
· avoid permanent and temporary reclamations and disturbance to the harbour area.
3.2.5 The Works Areas for the Trunk Road T2 construction have been selected carefully with a view reducing the impact of transporting materials to and from the site and reducing the impacts on the natural environment. Based upon this, the current locations are all located on already disturbed or developed land and are not vegetated and are located as close to the construction works as possible to reduce transportation and its associated visual, air and noise impacts.
3.2.6 In terms of transportation of materials for the Trunk Road T2 project, marine transport for removal of the spoil materials generated has been selected to minimise environmental impacts, minimise disruption to current projects on the KTD and minimise impacts on the Kwun Tong area, in particular the local road network. A barging point with conveyor system is planned to be located close to the TBM launching shaft to minimise the distance for the transport of spoil. The barging point location has recently been used as a cargo handling point and, thus, would have no impact on existing vegetated areas. There would, also, be no marine impacts as works below the water to prepare the barging point for use would not be required.
3.2.7 In
summary, the preferred alignment for the Trunk Road T2 as it is
seen to provide:
·
A technically feasible alignment;
·
The best environmental option resulting in
significantly less environmental impacts, including reduced quantities of
excavated material, no dredging of potentially contaminated of marine deposits,
reduced impacts on fisheries, water quality and marine ecology and operational
noise and air quality benefits and avoidance of vegetated areas;
·
Significantly less impact on the users of
the KTTS;
·
Minimised impacts to KTD;
·
Avoidance of impacts on the existing
sewage submarine outfall and breakwater; and
·
Avoidance of temporary reclamation in the
3.2.8 Based on above and the adopted tunnel alignment for the Truck Road T2, notable environmental impacts would be avoided or minimised.
3.2.9 The major findings of the EIA study are summarised below.
3.3.1
Construction Phase
3.3.1.1 The major sources of dust of the Trunk Road T2 project will be from construction activities such as site preparation, excavation, road works, foundation works, construction of road and superstructures, the barging point and conveyor system, TBM launching and receiving shafts, mucking out point for TBM process and wind erosion from open works site/areas and stockpiling areas.
3.3.1.2 With the implementation of specific mitigation, including watering 12 times per day, the predicted dust impacts at the Air Sensitive Receivers (ASRs) would comply with the dust criteria stipulated by the EIAO Technical Memorandum.
3.3.1.3 With these proposed mitigation measures, no irreversible adverse residual impacts on air quality will be anticipated during the construction phase.
3.3.2.1
Potential air quality impact
during the operational phase of Trunk Road T2 and other major existing road
networks would be dominated by vehicle gaseous emissions, mainly NO2
and RSP, either from open roads, or via the proposed tunnel portals and
ventilation buildings. The
Trunk Road T2 air assessment has adopted a conservative approach, utilising the
long term average ( last five years) of the most recent air quality monitoring
data obtained from the EPD’s Kwun Tong Air Quality Monitoring Station. This approach may be replaced by a
modelling approach using the PATH (Pollutants in the Atmosphere and their
Transport over
3.3.2.2 Because of the above reason, the overall predicted cumulative levels in this EIA report appear higher than some other EIAs based on the PATH method. However, it should be noted that the contribution of Trunk Road T2 project is low and in the region of only 0% to 8.8% for NO2, with the majority of the contributions being below 0.5%, and 0 to 1.5% for RSP.
3.3.2.3 Notwithstanding the conservative approach adopted, the operational air quality modelling results did not predict any exceedance of the hourly, 24 hourly and annual NO2 or the 24 hourly and annual RSP AQOs are predicted. Therefore, no mitigation measures are required. No adverse residual impacts are expected to occur during the operation phase.
3.4.1.1
Noise Sensitive Receivers
(NSRs) identified within proximity of the Trunk Road T2 project include a
future hospital development and residential development at the South Apron in
Kai Tak, and village houses at
3.4.1.2 Assessments for construction airborne noise and ground-borne noise from the use of the Tunnel Boring Machine (TBM) have been completed at the identified NSRs. The assessment results for air borne noise show that the Trunk Road T2 project would not cause significant impacts to the nearby NSRs with proper implementation of mitigation measures, including quiet equipment and temporary noise barriers, and adverse residual impacts would not be expected. No impacts are predicted for the daytime ground-borne noise and no mitigation measures are required.
3.4.2.1 Potential NSRs identified within proximity of the projects included four future hospital developments and a residential development at the South Apron, and village houses at Cha Kwo Ling Village and two future residential developments at ex-Cha Kwo Ling Kaolin Mine Site and Yau Tong Bay.
3.4.2.2 Assessments for operation traffic noise and operation fixed plant noise have been completed at the identified NSRs. The proposed fixed plant on the proposed ventilation buildings at the South Apron and Cha Kwo Ling (TKO-LTT Interchange) are not predicted to cause adverse noise impacts during the operational stage at the nearby NSRs. For traffic noise impact, the future NSRs identified at the South Apron have been confirmed as being noise insulated and will, therefore, not rely on openable windows for ventilation and hence, no direct mitigation measures are required. There will be no traffic noise contribution at Cha Kwo Ling by the Trunk Road T2 Project during operation phase as the road will be contained within tunnel along this section.
3.5.1.1 The subsea tunnel will be constructed by TBM and as such, no disturbance to the marine waters or seabed will occur and the marine transportation of Construction and Demolition (C&D) materials, will not result in any significant disturbance. Potential water pollution sources have been identified as construction run-off, wastewater discharge from tunnelling and excavation, contaminated groundwater, sewage effluent, accidental spillages and waste construction materials. Mitigation measures including providing perimeter drains, sand/silt removal facilities and oil interceptors, covering excavated and construction materials and spill response plans have been recommended to mitigate any adverse water quality impacts. Routine audit of the implementation of the mitigation measures is recommended during the construction phase EM&A. No adverse water quality impacts are predicted.
3.6.1.1
As the Trunk Road
T2 project is largely in tunnel and the TBM construction method of tunnelling has
been adopted, habitat losses in the marine environment have been avoided. The potential site run-off from land based
works may lead to temporary water quality issues and an increase in local
suspended solids for a short period of time.
However, these impacts are predicted to be minor and can be further
controlled by the implementation of the recommendations in the Water Quality
Impact Assessment and ProPECC PN 1/94 Construction Site Drainage and, thus,
they would be temporary and negligible with good site practices in place. Given that the ecological value of the
surrounding marine habitats are generally considered to be low to very low, the
impact would be considered to be of minor significance and acceptable.
3.6.2.1 Minor impacts to marine ecological resources due to potential accident spillages of chemical/oil and road surface run-off have been predicted as a result of the operation of the Trunk Road T2 project and no ecological specific mitigation measures are required. The implementation of the mitigation measures recommended for the protection of water quality, including provision of adequate drainage system with silt traps and oil interceptors, will help to minimise any impacts further.
3.7.1 The Port Survey of 2006 did not record any adult fish or fry production in the existing KTTS (AFCD, 2006). In addition, the assessment area is not a major operating area for large trawler trawling vessels (>15m), with a ban on trawling activities effective from December 2012, the impact on the construction works on fishing vessels would be limited and only small vessels, such as sampans, are used by fishermen in the KTTS which would be only temporarily affected by the Trunk Road T2 construction works.
3.7.2 Based on this, the lack of adult fish and fry in the area and the small size of the temporary barging point, it is predicted that no significant impacts in respect to the loss of fishing grounds would occur. As such, the construction and operation of the project would not give rise to any significant impacts to fisheries.
3.7.3 No mitigation measures are required for fisheries resources given that the water quality mitigation measures will be implemented as necessary.
3.8.1 As the
majority of Trunk Road T2 (the Project) will be in tunnel, landscape and visual
impacts will be concentrated on three buildings at the western end, namely the
Ventilation and Tunnel Portal Buildings.
3.8.2 Based on the
Tree Survey, 67 trees are recommended to be felled and 31 trees are recommended
to be transplanted by the Project. No Old and Valuable Trees, Wall Trees or
Significant Trees will be affected. In the Western Works Area a temporary loss
of 75,300 square metres of hard standing which will be temporarily lost in the
construction phase, and an permanent loss of 8500 square meters of hard
standing, 5029 square meters of planting areas and loss of 66 trees will be
mitigated by 15,740 square meters of planting areas and 4,900 square meters of
Amenity Area as referred to in the report as RE10 Kai Tak South Apron: Amenity
Area. Extensive compensatory planting will include 152 trees in accordance with
ETWB TCW No. 3/2006. In the Eastern Works Area one tree and an approximate area
of 21,500 square metres of hard standing will be lost. Mitigation for the
felled tree has been included within the compensatory trees for the Western
Works Area. The site will be reinstated and handed over for future development
of Cha Kwo Ling Promenade Park under a separate project. Details of the landscape
proposals for the Western Works Area will be reviewed within the detail design
stage. It is considered there will be no substantial adverse landscape impacts
by the Project during the operation phase.3.8.3 Through
careful design consideration the long term affects will be minimised and a
series of greening solutions will be implemented to the development as a whole.
Provisions have been made for community green spaces, architectural greening
measures, street trees, and planting areas. These are envisioned to blend the
Project into the proposed surrounding landscape.
3.8.3 The Ventilation and Tunnel Portal Buildings will be mitigated by
sensitive and contemporary architectural detailing, including vertical
greening, green roofs, textual and tonal finishes, and screen planting. These
are envisioned to blend the Project into the proposed surrounding landscape and
will be no more than 17mPD in height. In addition to the landscape mitigation
measures, the buildings will be in close proximity to the elevated Kwun Tong
Bypass, and therefore partially screened to northern VSRs. As a large area of
the KTD Runway Precinct and South Apron will also be under construction at the
same time, the residual impacts within the western area are not viewed as
adverse and cumulative impacts are not considered to be unacceptable within
such a context. The overall visual impacts on the surrounding VSRs would not be
significant and could be considered positive to a certain extent. There are considered to be no residual visual
impacts after mitigation to VSRs in the Eastern Works Area.
3.8.4 Due to the intended 2021 completion dates of the Kai Tak development
including the Metro Park, Runway Residential and Hotel Precinct, the Cruise
Terminal and Tourism and Leisure Hub, three hospital sites and other government
buildings, views from the Victoria Harbour and Southern Kowloon areas will be
screened and covered. Substantial
adverse visual impacts are not expected.
3.8.5 Overall, it is considered that the residual landscape and visual impacts
of the Project are acceptable with mitigation measures during construction and
operation phases.
3.9.1 The archaeology assessment did not
identify any areas of terrestrial or marine archaeological potential and no impacts
are predicted. However, any antiquity or
supposed antiquity discovered during the course of the excavation works will be
reported to the AMO immediately.
3.9.2 The built heritage
survey has identified 11 buildings in Cha Kwo Ling. However, no adverse impacts
to any of the buildings have been identified during either the construction or
operational phases of the project and no mitigation will be required.
3.10 Waste Management Implication and Land Contamination
3.10.1.1
The construction of the
Trunk Road T2 will involve a number of activities which will generate waste
that can be broadly be classified into distinct categories based on its nature
and the options for disposal. These
include:
l
Excavated marine deposit (sediment) buried underneath the South Apron and
Cha Kwo Ling works areas for the construction of cut-and-cover tunnel sections;
l
Excavated C&D materials suitable for public fill, including the
alluvium from the sub-marine tunnel construction;
l
C&D waste which is not suitable for public fill;
l
Chemical waste;
l
Sewage; and
l
General refuse.
3.10.1.2 The majority of the soft C&D material comprising sand fill, Grade III rock and below and alluvium, making up approximately 1.15Mm3, will be suitable for reuse or transfer to the public fill, in some cases, after treatment as required. The predicted surplus amount of this C&D material, in addition to the Grade II or above rock from the subsea tunnel, totally approximately 0.98Mm3, will be transferred to the Tseung Kwan O Area 137 Fill Bank and Chai Wan Public Fill Barging Point by barge. This principle of disposal for the surplus C&D material has been agreed in principle with the CEDD’s Vetting Committee on 28 February 2013.
3.10.1.3 With the implementation of the recommended mitigation measures, there would be no adverse residual impacts associated with the handling, storage, transportation or disposal of the waste generated by the Trunk Road T2 project during the construction and operation phases of the Trunk Road T2 Project.
3.10.2.1
The land contamination
assessment at the concerned previously developed land lot is currently occupied
by PCCW and a short section of
There were 2 locations at Cheung Yip Street, namely EH1 and EH3, at which the site investigation (SI) works for the land contamination assessment were not practically accessible. As such, in future, if the concerned locations are confirmed to be acquired as part of the works sites for the Trunk Road T2 construction contract and access is permitted, a supplementary SI to complete the land contamination assessment for EH1 and EH3 and further reconnaissance visits to inaccessible Works Area WA2 would be conducted when these sites become accessible in accordance with the requirements as set out in the endorsed CAP prior to the commencement of construction works so as to verify if any potential land contamination issues exist in these remaining areas. The findings of such supplementary SI works would be submitted as supplementary information to the CAR. If land contamination is determined, the necessary remediation works will be proposed in a RAP for implementation. Following the completion of remaining SI works at locations EH1 and EH3, a supplementary CAR and/or RAP will be submitted to EPD for approval before the commencement of construction works.
3.11 Environmental Monitoring and Audit
3.11.1
An
environmental monitoring and audit (EM&A) programme will be implemented
during the construction and operation of the Project, to check the
effectiveness of the recommended mitigation measures and compliance with relevant
statutory criteria. The EM&A
procedures are required during construction and operational phases of the
project implementation. The EM&A
requirements are divided into environmental monitoring and/or project auditing
in the form of site inspection and supervision.
Only monitoring for air and noise has been recommended but regular
auditing for air, noise, water quality, ecology, LVIA and waste would be required.
Table 3.1 Scope
of Environmental Monitoring
Environmental Aspects |
Phase |
Monitoring Parameter |
Dust |
Construction |
TSP |
Airborne Noise |
Construction |
Leq(30mins) |
Fixed Noise |
Operational |
Leq(30mins) |
4.1 This EIA study has identified and assessed potential environmental impacts of the Project, in accordance with the EIA study brief and EIAO-TM guidelines. Overall, the EIA study has concluded that the Trunk Road T2 project would be environmentally acceptable, in compliance with environmental legislation and standards. With the implementation of environmental control measures during the construction and operational phases, there would be no significant adverse residual impacts from the Trunk Road T2 project.