Contents |
Chapter Title Page
13.1 General__________________________________________________________________ 13-1 |
Table 13.1: Implementation Schedule
|
|
|
|
|
Implementation Stage1 |
|
|||||||||||
EIA Ref. |
EM&A Ref. |
Environmental Protection Measures |
Location / Duration of measures / Timing of completion of measures |
Implementation Agent |
Des |
Con |
Op |
Dec |
Relevant Legislation & Guidelines |
||||||||
Air Quality Impact (Construction) |
|||||||||||||||||
3.7.1.1 |
|
General Dust Control Measures Frequent water spraying for active construction areas (12 times a day or once every one hour), including Heavy construction activities such as construction of buildings or roads, drilling, ground excavation, cut and fill operations (i.e., earth moving) |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA Recommendation and Air Pollution Control (Construction Dust) Regulation |
||||||||
3.7.1.2 |
|
Best Practice For Dust Control The relevant best
practices for dust control as stipulated in the Air Pollution Control
(construction Dust) Regulation should be adopted to further reduce the
construction dust impacts from the Project. These best practices include: Good Site
Management ¡ Good
site management is important to help reducing potential air quality impact
down to an acceptable level. As a general guide, the Contractor should
maintain high standard of housekeeping to prevent emission of fugitive dust.
Loading, unloading, handling and storage of raw materials, wastes or
by-products should be carried out in a manner so as to minimise the release
of visible dust emission. Any piles of materials accumulated on or around the
work areas should be cleaned up regularly. Cleaning, repair and maintenance
of all plant facilities within the work areas should be carried out in a
manner minimising generation of fugitive dust emissions. The material should
be handled properly to prevent fugitive dust emission before cleaning. Disturbed
Parts of the Roads ¡ Each
and every main temporary access should be paved with concrete, bituminous
hardcore materials or metal plates and kept clear of dusty materials; or ¡ Unpaved
parts of the road should be sprayed with water or a dust suppression chemical
so as to keep the entire road surface wet. Exposed Earth ¡ Exposed
earth should be properly treated by compaction, hydroseeding, vegetation
planting or seating with latex, vinyl, bitumen within six months after the
last construction activity on the site or part of the site where the exposed
earth lies. Loading,
Unloading or Transfer of Dusty Materials ¡ All
dusty materials should be sprayed with water immediately prior to any loading
or transfer operation so as to keep the dusty material wet. Debris
Handling ¡ Any
debris should be covered entirely by impervious sheeting or stored in a
debris collection area sheltered on the top and the three sides. ¡ Before
debris is dumped into a chute, water should be sprayed so that it remains wet
when it is dumped. Transport of
Dusty Materials ¡ Vehicle
used for transporting dusty materials/spoils should be covered with tarpaulin
or similar material. The cover should extend over the edges of the sides and
tailboards. Wheel washing
¡ Vehicle
wheel washing facilities should be provided at each construction site exit.
Immediately before leaving the construction site, every vehicle should be
washed to remove any dusty materials from its body and wheels. Use of
vehicles ¡ The
speed of the trucks within the site should be controlled to about ¡ Immediately
before leaving the construction site, every vehicle should be washed to
remove any dusty materials from its body and wheels. ¡ Where
a vehicle leaving the construction site is carrying a load of dusty
materials, the load should be covered entirely by clean impervious sheeting
to ensure that the dusty materials do not leak from the vehicle. Site hoarding ¡ Where a site boundary adjoins a road, street, service lane or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length of that portion of the site boundary except for a site entrance or exit. |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA Recommendation and Air Pollution Control (Construction Dust) Regulation |
||||||||
3.7.1.3 |
|
Best
Practicable Means for Cement Works (Concrete Batching Plant) The relevant best practices for dust control as stipulated in the Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) should be followed and implemented to further reduce the construction dust impacts of the Project. These best practices include: Exhaust from
Dust Arrestment Plant ¡ Wherever possible the final
discharge point from particulate matter arrestment plant, where is not
necessary to achieve dispersion from residual pollutants, should be at low
level to minimise the effect on the local community in the case of abnormal
emissions and to facilitate maintenance and inspection Emission
Limits ¡ All emissions to air, other
than steam or water vapour, shall be colourless and free from persistent mist
or smoke Engineering
Design/Technical Requirements ¡ As
a general guidance, the loading, unloading, handling and storage of fuel, raw
materials, products, wastes or by-products should be carried out in a manner
so as to prevent the release of visible dust and/or other noxious or
offensive emissions |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA recommendation; Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) |
||||||||
Air Quality Impact (Operation) |
|||||||||||||||||
3.7.2 |
|
Vehicular
and Marine Emissions No mitigation measure is required. |
|
|
|
|
|
|
|
||||||||
3.7.3.1 |
|
Improvement works
for New Yau Ma Tei Typhoon Shelter (NYMTTS) for Odour Mitigation |
|
|
|
|
|
|
|
||||||||
|
|
¡ Implementation of
the DSD’s project to
install new Dry Weather Flow Interceptor (DWFI) for Cherry Street Box
Culvert. |
New Yau Ma Tei Typhoon Shelter / Early 2014 to 2nd
half of 2018 (subject
to successful bid for funding) |
DSD |
|
|
P |
|
EIA recommendation |
||||||||
|
|
¡ Improvement of three
existing DWFIs upstream of Cherry Street Box Culvert and/or two existing DWFIs
upstream of Jordan Road Box Culvert as part of the project titled “Upgrading
of West Kowloon and Tsuen Wan Sewerage”. |
New Yau Ma Tei Typhoon Shelter / 2016 to end 2023 (subject to successful bid for funding) |
DSD |
|
|
P |
|
EIA recommendation |
||||||||
3.7.3.2 |
|
Optional Waste facilities This facility will be located at basement levels. In addition, the odour containment and control measures to be implemented include: ¡ The
waste facilities will be totally enclosed. Negative pressure ventilation will
be provided within the enclosures to avoid any fugitive odorous emission from
the facilities. In addition, any waste storage tanks will be connected to
deodorisation facilities directly to eliminate the odour problem. ¡ Air
inside the enclosures will be collected by air handling equipment for
containing and directing odorous gases to deodorisation facilities. ¡ Deodorisation
facilities by chemical, biological or physical methods (e.g. adsorption by
activated carbon) with a minimum odour removal efficiency of 95% will be
provided to treat potential odorous emissions from the facilities so as to
minimise any potential odour impact to the nearby ASRs. |
Within WKCD site / Duration and timing to be determined |
WKCDA |
|
|
P |
|
EIA recommendation |
||||||||
Noise Impact (Construction) |
|||||||||||||||||
4.7.1 |
|
Good Site Practice Good site
practice and noise management can significantly reduce the impact of
construction site activities on nearby NSRs. The following package of
measures should be followed during each phase of construction: ¡ only
well-maintained plant to be operated on-site and plant should be serviced
regularly during the construction works; ¡ machines
and plant that may be in intermittent use to be shut down between work
periods or should be throttled down to a minimum; ¡ plant
known to emit noise strongly in one direction, should, where possible, be
orientated to direct noise away from the NSRs; ¡ mobile
plant should be sited as far away from NSRs as possible; and ¡ material
stockpiles and other structures to be effectively utilised, where
practicable, to screen noise from on-site construction activities. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
4.7.1 |
|
Adoption of Quieter PME The recommended quieter PME adopted in the assessment were taken from
the EPD’s QPME Inventory and “Sound
Power Levels of Other Commonly Used PME”. It
should be noted that the silenced PME selected for assessment can be found in
|
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
4.7.1 |
|
Use of Movable Noise Barriers Movable noise
barriers can be very effective in screening noise from particular items of
plant when constructing the Project. Noise barriers located along the active
works area close to the noise generating component of a PME could produce at
least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant
provided the direct line of sight between the PME and the NSRs is blocked. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
4.7.1 |
|
Use of Noise Enclosure/ Acoustic Shed The use of
noise enclosure or acoustic shed is to cover stationary PME such as air
compressor and concrete pump. With the adoption of the noise enclosure, the
PME could be completely screened, and noise reduction of 15 dB(A) can be achieved according to the EIAO Guidance Note
No.9/2010. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
4.7.1 |
|
Use of Noise Insulating Fabric Noise
insulating fabric can also be adopted for certain PME (e.g. drill rig,
pilling machine etc). The fabric should be lapped such that there are no
openings or gaps on the joints. According to the approved Tsim Sha Tsui
Station Northern Subway EIA report (AEIAR-127/2008), a noise reduction of 10 dB(A) can be achieved for the PME lapped with the noise
insulating fabric. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
4.7.1 |
|
Scheduling of Construction Works outside School Examination Periods During construction phase, the contractor
should liaise with the educational institutions (including NSRs LCS and
CRGPS) to obtain the examination schedule and avoid the noisy construction
activities during school examination periods. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||||
Noise Impact (Operation) |
|||||||||||||||||
4.7.2 |
|
Road Traffic Noise At-receiver mitigation measures should be considered in terms of self-protecting building design such as shielding by balcony. The balcony shall be designed with depth more than 1m with solid parapet of about 1.5m high and ceiling lined with absorptive material to face the noise source at Parcels 3, 5, 9, 24, 27, 28 & 29. |
Along parts of |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO |
||||||||
4.7.2 |
3.2 |
Road
Traffic Noise Sound-absorbing materials should be
installed on inner walls and ceilings of the underpass at the portals at the
junction of Lin Cheung Road and Austin Road West, interim access of Austin
Road West and permanent access at Canton Road. The sound-absorbing materials
would be extended at least 30m into the underpass at the portals. |
Portal at the junction of Lin Cheung Road and Austin Road West, Interim Access at Austin Road West and Permanent access at Canton Road / Before commencement of operation of road project |
Contractor appointed by WKCDA / Highways Department |
P |
P |
P |
|
EIAO |
||||||||
4.7.3 |
|
Fixed Plant Noise Specification of the maximum allowable sound power levels of the
proposed fixed plants during daytime and night-time should be followed. The
following noise reduction measures should be considered as far as practicable
during operation: ¡ Choose
quieter plant such as those which have been effectively silenced; ¡ Include
noise levels specification when ordering new plant (including chillier and
E/M equipment); ¡ Locate
fixed plant/louvre away from any NSRs as far as
practicable; ¡ Locate
fixed plant in walled plant rooms or in specially designed enclosures; ¡ Locate
noisy machines in a basement or a completely separate building; ¡ Install
direct noise mitigation measures including silencers, acoustic louvres and acoustic enclosure where necessary; and ¡ Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain a controlled level of noise. |
Within WKCD site / During operation phase / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO and Noise Control Ordinance |
||||||||
4.7.5 |
|
Ground-borne Noise Given stringent
acoustic performance requirement for this world-class venues, noise and vibration
control measures such as building isolation and or box-in-box installation
would be required by the acoustic and theatre designers of to the Xiqu
Centre, M+ (Phase I & II), Lyric Centre and CCP. The exact measures to be
adopted are subject to the later detailed structural and foundation designs
of the art performance venues. |
Within WKCD site / During operation phase / Prior to commencement of operation |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO |
||||||||
4.7.7 |
|
Marine Traffic Noise At-receiver mitigation measures by designing the buildings so as to avoid any sensitive façades with openable window facing the noise source at Parcels 2, 3, 10, 11, 13, 21, 26 and 32 are proposed. |
Within WKCD site / During operation phase / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO |
||||||||
Water Quality Impact (Construction) |
|||||||||||||||||
5.7.1.1 |
|
Construction site runoff and drainage The site practices outlined in ProPECC Note PN 1/94 should be followed as far as practicable in order to minimise surface runoff and the chance of erosion. The following measures are recommended to protect water quality and sensitive uses of the coastal area, and when properly implemented should be sufficient to adequately control site discharges so as to avoid water quality impacts: ¡ At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels, earth bunds
or sand bag barriers should be provided on site to direct storm water to silt
removal facilities. The design of the temporary on-site drainage system
should be undertaken by the WKCDA’s Contractor prior to the commencement of
construction; ¡ Sand/silt
removal facilities such as sand/silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements
of the TM standards under the WPCO.
The design of efficient silt removal facilities should be based on the
guidelines in Appendix A1 of ProPECC Note PN 1/94. Sizes may vary depending upon the flow
rate. The detailed design of the sand/silt traps should be undertaken by the WKCDA’s
Contractor prior to the commencement of construction. ¡ All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation
at all times and particularly during rainstorms. Deposited silt and grit
should be regularly removed, at the onset of and after each rainstorm to
ensure that these facilities are functioning properly at all times. ¡ Measures
should be taken to minimize the ingress of site drainage into excavations. If
excavation of trenches in wet periods is necessary, they should be dug and
backfilled in short sections wherever practicable. Water pumped out from
foundation excavations should be discharged into storm drains via silt
removal facilities. ¡ All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An
adequately designed and sited wheel washing facility should be provided at
construction site exit where practicable. Wash-water should have sand and
silt settled out and removed regularly to ensure the continued efficiency of
the process. The section of access road leading to, and exiting from, the
wheel-wash bay to the public road should be paved with sufficient backfall
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains. ¡ Open
stockpiles of construction materials or construction wastes on-site should be
covered with tarpaulin or similar fabric during rainstorms. Measures should
be taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system. ¡ Manholes
(including newly constructed ones) should be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris
being washed into the drainage system and stormwater runoff being directed
into foul sewers. ¡ Precautions
should be taken at any time of the year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecasted and actions to be
taken during or after rainstorms are summarized in Appendix A2 of ProPECC
Note PN 1/94. Particular attention
should be paid to the control of silty surface runoff during storm events,
especially for areas located near steep slopes. ¡ Bentonite
slurries used in piling or slurry walling should be reconditioned and reused
wherever practicable. Temporary enclosed storage locations should be provided
on-site for any unused bentonite that needs to be transported away after all
the related construction activities are completed. The requirements in
ProPECC Note PN 1/94 should be adhered to in the handling and disposal of
bentonite slurries. |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||||
5.7.1.2 |
|
Modification of seawall and Construction of
landing steps and possible piers/viewing platform To minimise any adverse water quality impact
during modification of seawalls for construction of cooling water
discharges/outfalls and landing steps and installation of marine piles for
construction of the possible piers, silt curtains should be deployed to
completely enclose the modification of seawalls and marine pile installation
works. The Contractor should be responsible for the design, installation and
maintenance of the silt curtains to minimize the impacts on water quality.
The design and specification of the silt curtains should be submitted by the
Contractor to the Engineer for approval. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
WPCO |
||||||||
5.7.1.3 |
|
Barging facilities and activities Recommendations for good site practices
during operation of the proposed barging point include: ¡ All
vessels should be sized so that adequate clearance is maintained between
vessels and the seabed in all tide conditions, to ensure that undue turbidity
is not generated by turbulence from vessel movement or propeller wash; ¡ Loading
of barges and hoppers should be controlled to prevent splashing of material
into the surrounding water. Barges or
hoppers should not be filled to a level that will cause the overflow of
materials or polluted water during loading or transportation; ¡ All
hopper barges should be fitted with tight fitting seals to their bottom
openings to prevent leakage of material; and ¡ Construction
activities should not cause foam, oil, grease, scum, litter or other
objectionable matter to be present on the water within the site. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
WPCO |
||||||||
5.7.1.4 |
|
Sewage
effluent from construction workforce Temporary sanitary facilities, such as
portable chemical toilets, should be employed on-site where necessary to
handle sewage from the workforce. A licensed contractor should be employed to
provide appropriate and adequate portable toilets and be responsible for
appropriate disposal and maintenance. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||||
5.7.1.5 |
|
General
construction activities Construction
solid waste, debris and refuse generated on-site should be collected, handled
and disposed of properly to avoid entering any nearby storm water drain.
Stockpiles of cement and other construction materials should be kept covered
when not being used. Oils and fuels should only be stored in
designated areas which have pollution prevention facilities. To prevent
spillage of fuels and solvents to any nearby storm water drain, all fuel
tanks and storage areas should be provided with locks and be sited on sealed
areas, within bunds of a capacity equal to 110% of the storage capacity of
the largest tank. The bund should be drained of rainwater after a rain event. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||||
Water Quality Impact (Operation) |
|||||||||||||||||
5.7.2.1 |
|
Road and surface runoff For operation of the proposed WKCD development and
associated local road network, a surface water drainage system would be
provided to collect road and surface runoff.
It is recommended that the road drainage should be provided with
adequately designed silt trap and oil interceptors, as necessary. The design
of the operation stage mitigation measures for the proposed WKCD development
and associated local road network should take into account the guidelines
published in the Practice Note for
Professional Persons on Drainage Plans Subject to Comment by the
Environmental Protection Department (ProPECC
Note PN 5/93) and Highways Department Guidance
Notes RD/GN/035 – Road Pavement Drainage Design. |
Within WKCD site / During operation phase / Throughout operation phase |
HyD (for exclusive road drains) |
|
|
P |
|
ProPECC Note PN 5/93, Highways Department Guidance Notes RD/GN/035 |
||||||||
5.7.2.2 |
|
Sewage
and wastewater effluents from the proposed WKCD development Domestic sewage
generated during operation phase of the proposed WKCD development should be
diverted to the foul sewer. Sewage and sewerage impact assessment had
identified that the proposed WKCD development would not cause adverse impact
to the local sewerage network which should have sufficient capacity to cater
for the sewage flow generated from the proposed WKCD development. No
mitigation measures and upgrading works to the existing local sewer are
necessary for the proposed WKCD development. Recommendations for the design,
operation and maintenance for the sewerage system are detailed below in the
same table. |
Within WKCD site / During operation phase / Throughout operation phase |
WKCDA |
|
|
P |
|
WPCO |
||||||||
5.7.2.4 |
|
Emergency
effluent bypass from optional sewage pump sump The following mitigation measures are
proposed to be incorporated in the design of the optional sewage pumping
station: ¡ A two hour emergency storage capacity should be provided
within the optional sewage pump sump accordingly to EPD Environmental
Guidance Note for Sewage Pumping Stations (NOT a designated project); ¡ Dual power supply or emergency generator with
sufficient capacity (100%) should be provided to the optional sewage pump
sump to secure electrical power supply; ¡ Standby pumps with sufficient capacity (100%) should
be provided to the optional sewage pump sump to ensure smooth operation of
the optional sewage pumping station during maintenance of the duty pumps; ¡ An alarm should be installed to signal emergency high
water level in the wet well of the optional sewage pump sump; and ¡ Should the optional sewage pump sump is unmanned, a
remote monitor system connecting the optional sewage pump sump with the
control station through telemetry system should be provided to ensure swift
actions to be taken in case of malfunction of the optional sewage pump sump. |
Within WKCD site / During design and operation phases / Throughout operation phase |
WKCDA |
P |
|
P |
|
DSD’s Sewerage Manual; EPD Environmental Guidance Note for Sewage Pumping Stations |
||||||||
5.7.2.5 |
|
Improvement works for New Yau Ma Tei Typhoon Shelter (NYMTTS) for Odour Mitigation |
|
|
|
|
|
|
|
||||||||
|
|
¡ Implementation of the DSD’s project to install new
Dry Weather Flow Interceptor (DWFI) for Cherry Street Box Culvert; and |
New Yau Ma Tei Typhoon Shelter / Early 2014 to 2nd
half of 2018 (subject
to successful bid for funding) |
DSD |
|
|
P |
|
EIA recommendation |
||||||||
|
|
¡ Improvement of three existing DWFIs upstream of
Cherry Street Box Culvert and/or two existing DWFIs upstream of Jordan Road
Box Culvert as part of the project titled “Upgrading of West Kowloon and
Tsuen Wan Sewerage”. |
New Yau Ma Tei Typhoon Shelter / 2016 to end 2023 (subject to successful bid for funding) |
DSD |
|
|
P |
|
EIA recommendation |
||||||||
5.7.2.6 |
|
Water reuse facilities Regarding
collection and treatment of rainwater, individual venue operators should
follow Architectural Services Department (ASD) Design Guideline for Rainwater
Recycling Installation with typical schematic design of a rainwater recycling
installation and recommended recycled rainwater standard with reference to
the international standards, such as EPA of USA etc. as detailed in Table 5.11
in the EIA Report during design
and operation of the facilities. Disinfection by chemical treatment and
monitoring should be implemented for reuse of condensate from air
conditioning systems. As the demand for reclaimed water is significant,
discharge of surplus reclaimed water is not anticipated. |
Within WKCD site / During design and operation phases / Throughout operation phase |
Individual venue operators; Detailed
Design Consultant appointed by WKCDA |
P |
|
P |
|
ASD Design Guideline for Rainwater Recycling Installation; USEPA Guidelines for water reuse |
||||||||
5.7.2.7 |
|
Thermal / Cooled Water Discharge from
District Cooling System ¡ Monitoring for the spent cooling water discharge from
DCWS during operation should follow the requirements as specified in the
discharge license to be issued under the WPCO. Details
of the water quality monitoring and audit programme and the Event and Action
Plan are provided in the stand-alone EM&A Manual. |
Within WKCD site / During design and operation phases / Throughout operation phase |
Individual venue operators; Detailed
Design Consultant appointed by WKCDA |
P |
|
P |
|
WPCO |
||||||||
Sewerage and Sewage Treatment
Implications (Design) |
|||||||||||||||||
6.7.1.1 |
|
General Requirements The detailed design of the proposed sewerage
system should be circulated to DSD, EPD and other relevant parties for
comment during planning and detailed design stage to ensure acceptance by
relevant parties. Access for plant, equipment and personnel for maintenance
of the works should be adequately provided. A plan showing the maintenance
access to the proposed sewers has been provided in Figure
6.5. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Stormwater Drainage Manual; DSD’s Sewerage Manual Part 1 & Part 2; DSD Standard Drawings; and HyD’s Structures Design Manual for Highways and Railways |
||||||||
6.7.1.2 |
|
Gravity Sewers The design of
gravity sewers should be according to the guidelines stipulated in Sewerage
Manual Part 1. The general requirements are summarized below: ¡ Pipe size: The minimum
pipe size of gravity sewer is 225mm in diameter. ¡ Capacity: The gravity
sewer should be designed to avoid under surcharge condition. 1m freeboard
should be provided if surcharge condition cannot be avoided. ¡ Flow velocity: The flow
velocity should be not less than 1m/s under full bore flow for self-cleansing
purpose. The maximum velocity should be limited to 3m/s. ¡ Alignment: The alignment
of the proposed sewer should be reviewed to avoid conflicting with existing
utilities and affecting traffic flow as far as possible. ¡ Hydraulic Design: The
detailed hydraulic design should follow the guidelines provided under Section
5.2 of Sewerage Manual Part 1. ¡ Pipe Material: Selection
of pipe material shall be based on its suitability for the proposed
application. The selection process includes an evaluation of the possible
conditions to which the pipes may be exposed in order to specify the
appropriate material and installation requirements for the specific
application. ¡ Pipe Joints: In order to
accommodate differential settlement that may occur between sewers and
adjacent structures (including manholes), two flexible joints shall be
provided in accordance with the latest amendment of General Specification for
Civil Engineering Works 2006 Edition Volume 1 Clause 5.71 – Connections to
structures in providing the flexible joints to structures. ¡ Pipeline Structural
Design: The structural checking and bedding design should in accordance with
Section 6 of Sewerage Manual Part 1. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Sewerage Manual Part 1 |
||||||||
6.7.1.3 |
|
Manholes Design The design of manholes should be in accordance
with Section 7 of Sewerage Manual Part 1. ¡ Location: Manholes should
be provided at all changes in direction, at intersections and to suit
property connections. The maximum spacing between manholes should be as
follows:
¡ Access Openings/Shafts:
Desilting opening should not be smaller than 750mm by 900mm and should be
placed in the line of the sewer. The man access opening with minimum size of
675mm x 750mm should be provided at manholes. Man access openings should be
placed off the line of the sewer for deep manhole and along the line of the
sewer for manholes shallower than 1.2m. ¡ Working Chambers: Working
Chambers should be provided to manholes deeper than 1.2m. ¡ Intermediate Platforms:
When the invert of a manhole is more than 4.25m from the cover level,
intermediate platforms should be provided at regular intervals. The headroom
between platforms should not be less than 2m nor greater than 4m. Hand
railing and safety chains should be provided at the edge of platform to
protect persons from falling down. The minimum size of platform should is
800mm by 1350mm. ¡ Covers: The manhole cover
should be designed strong enough to take the design loading and should not
rock when initially placed in position or develop a rock with wear. The
design of manhole covers should make reference to DSD standard drawings. ¡ Backdrop Manhole: When the
level difference between the inlet pipe and the invert level of manhole is
greater than 600mm, backdrop manhole should be used. The design of backdrop
manhole should follow guidelines under Section 7.1.9 in Sewerage Manual Part
1. ¡ Step-irons/Cat Ladder:
Step-irons should be securely fixed in position and should be equally spaced
and staggered about a vertical line at 300mm centres. Cat ladders should be
used in manholes deeper than 4.25m or where manholes are frequently entered.
Set-irons and ladders should be start at not more than 600mm below the cover
level and continue to the platform or benching. Corrosion resistance
materials should be used if step-irons and ladders are constantly in a damp
atmosphere and prone to corrosion. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Sewerage Manual Part 1 |
||||||||
6.7.1.4 |
|
Sump Pumps Design The design of
sewage sump pumps should follow the requirements stipulated in the Sewerage
Manual Part 2. ¡ The number of pumps to be
installed depends on the sump capacity. Standby pumps should be provided to
ensure the operation can still be maintained during maintenance or mechanical
failure. ¡ The selected electrical
equipment shall be suitable to operate under high humidity, high temperature
and presence of corrosive gases. ¡ Appropriate mitigation
measures to control noise and odour problems should be designed under
detailed design stage. The typical methods for noise and odour control could
refer to the Sewerage Manual Part 2. ¡ In order to control the
septicity of sewage due to operation of sewage pumping facilities, the
retention time of sewage should be minimized. Pumps with different small rate
should be considered for reducing the time of retention of sewage. Direct
injection of oxygen could also be used to control septicity. The mitigation
methods should be considered under detailed design stage. ¡
Fresh water should be provided for the operation and maintenance staff
for hygienic reasons. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Sewerage Manual Part 2 |
||||||||
6.7.1.5 |
|
Rising Mains Design The design of
rising main should follow the requirement stipulated in the Sewerage Manual
Part 2. Twin rising mains
should be provided as far as possible because of the following reasons: ¡ To accommodate a wide
range of flow conditions such that the velocity in the mains can be kept
within acceptable limits; ¡ To provide continued
operation when one of the mains is damaged; and ¡ To facilities future
inspection and maintenance while the normal sewage flow
can be maintained. The maximum
velocity at peak flow should not exceed 3m/s. The desirable range of velocity
should be 1m/s to 2m/s with due consideration given to the various
combinations of number of duty pumps in operation. Air relief valves,
check valves, isolating valves and discharge sumps shall be provided in
accordance to the Sewerage Manual Part 2. Septicity control methods for rising mains, such as oxygen injection
and reducing retention time of sewage, should be designed under detailed
design stage. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Sewerage Manual Part 2 |
||||||||
6.7.1.6 |
|
Thrust Blocks for
Rising Mains Thrust blocks should be provided to rising
mains to prevent pipes from being moved by forces exerted within the pipe by
the flow of water hitting bends, tapers, and closed or partially closed
valves. The size of a thrust block is dependent
upon the deflection of the flow and the head of water inside the pipe. Design of thrust block should refer to DSD
Sewerage Manual Part 2. |
Within WKCD site / During detailed design stage / Prior to commencement of construction |
Detailed Design Consultant appointed by WKCDA |
P |
|
|
|
DSD’s Sewerage Manual Part 2 |
||||||||
Sewerage and Sewage Treatment Implications
(Operation) |
|||||||||||||||||
6.7.1.7 |
|
Inspection
and General Maintenance Operations All gravity sewers and rising mains shall be
tested in accordance with relevant General Specification sections as
appropriate in the presence and to the satisfaction of the staff of DSD upon
completion of the installation. Records of
satisfactory testing on the completed works shall be submitted to DSD after
the testing. CCTV survey records, as-built drawings and hydraulic and
structural design calculations should be submitted to DSD for records. |
Within WKCD site / From several days to several weeks / Upon completion of installation |
WKCDA |
|
|
P |
|
CEDD’s General Specification for Civil Engineering Works |
||||||||
Waste Management Implications
(Construction) |
|||||||||||||||||
7.5.1.1 |
|
Good
Site Practices Recommendations
for good site practices during the construction activities include: ¡ Nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for
collection and effective disposal to an appropriate facility, of all wastes
generated at the site ¡ Training of site personnel in proper waste management
and chemical handling procedures ¡ Provision of sufficient waste disposal points and
regular collection of waste ¡ Appropriate measures to minimise windblown litter and
dust/odour during transportation of waste by either covering
trucks or by transporting wastes in enclosed containers ¡ Provision of wheel washing
facilities before the trucks leaving the works area so as to minimise dust
introduction to public roads ¡ Well planned delivery
programme for offsite disposal such that adverse environmental impact from
transporting the inert or non-inert C&D materials is not anticipated |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance; Waste Disposal (Chemical Wastes) (General) Regulation; and Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site |
||||||||
7.5.1.2 |
|
Waste
Reduction Measures Recommendations
to achieve waste reduction include: ¡ Sort inert C&D materials to recover any
recyclable portions such as metals ¡ Segregation and storage of different types of waste
in different containers or skips to enhance reuse or
recycling of materials and their proper disposal ¡ Encourage collection of recyclable waste such as
waste paper and aluminium cans by providing separate labelled bins to enable
such waste to be segregated from other general refuse generated by the work
force ¡ Proper site practices to minimise the potential for
damage or contamination of inert C&D materials ¡ Plan the use of construction materials carefully to
minimise amount of waste generated and avoid unnecessary generation of waste |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance |
||||||||
7.5.1.3 |
|
Inert and Non-inert C&D Materials In
order to minimise impacts resulting from collection and transportation of inert
C&D materials for off-site disposal, the excavated materials should be
reused on-site as fill material as far as
practicable. In addition, inert C&D materials generated from excavation
works could be reused as fill materials in local projects that require public fill for reclamation. ¡ The surplus inert C&D materials will be disposed
of at the Government’s PFRFs for beneficial use by other projects in ¡ Liaison with the CEDD Public Fill Committee (PFC) on
the allocation of space for disposal of the inert C&D materials at PFRF
is underway. No construction work is
allowed to proceed until all issues on management of inert C&D materials
have been resolved and all relevant arrangements have been endorsed by the
relevant authorities including PFC and EPD. ¡ The C&D materials generated from general site
clearance should be sorted on site to segregate any inert materials for reuse
or disposal of at PFRFs whereas the non-inert materials will be disposed of
at the designated landfill site. ¡ In order to monitor the disposal of inert and
non-inert C&D materials at respectively PFRFs and the designated landfill
site, and to control fly-tipping, it is recommended that the Contractor
should follow the Technical Circular (Works) No.6/2010 for Trip Ticket System
for Disposal of Construction & Demolition Materials issued by Development
Bureau. In addition, it is also
recommended that the Contractor should prepare and implement a Waste
Management Plan detailing their various waste arising and waste management
practices in accordance with the relevant requirements of the Technical
Circular (Works) No. 19/2005 Environmental Management on Construction Site. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance ; Technical Circular (Works) No.6/2010 for Trip Ticket System for Disposal of Construction & Demolition Materials; and Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site |
||||||||
7.5.1.4 |
|
Chemical
Waste If chemical
wastes are produced at the construction site, the Contractor will be required to register with the EPD as a chemical
waste producer and to follow the guidelines stated in the “Code of Practice on the
Packaging Labelling and Storage of Chemical Wastes”. Good quality containers compatible with the
chemical wastes should be used, and incompatible chemicals should be stored
separately. Appropriate labels should be securely attached on each chemical
waste container indicating the corresponding chemical characteristics of the
chemical waste, such as explosive, flammable, oxidizing, irritant, toxic,
harmful, corrosive, etc. The Contractor should use a licensed collector to
transport and dispose of the chemical wastes at the approved Chemical Waste
Treatment Centre or other licensed recycling facilities, in accordance with
the Waste Disposal (Chemical Waste) (General) Regulation. Potential environmental impacts arising from the handling activities (including
storage, collection, transportation and disposal of chemical waste) are
expected to be minimal with the implementation of appropriate
mitigation measures as recommended. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Code of Practice on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General) Regulation |
||||||||
7.5.1.5 |
|
General
Refuse General refuse should be stored in enclosed
bins or compaction units separated from inert C&D materials. A reputable
waste collector should be employed by the Contractor to remove general refuse from the site, separately from inert
C&D materials. Preferably an enclosed and covered area should be provided
to reduce the occurrence of 'wind blown' light material. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance and Public Health and Municipal Services Ordinance - Public Cleansing and Prevention of Nuisances Regulation |
||||||||
Waste Management Implications (Operation) |
|||||||||||||||||
7.5.2.1 |
|
General Refuse General refuse should be collected on daily basis and delivered to the refuse collection point accordingly. A reputable waste collector should be employed to remove general refuse regularly to avoid odour nuisance or pest/vermin problem. Sufficient recycling containers are recommended to be provided at suitable locations of the WKCD site to encourage recycling of such waste as aluminium cans, plastics and waste paper. |
WKCD site / On a regular basis / Throughout operation stage |
Private Developer (for land sale lots); Relevant Government Departments e.g. FEHD / LCSD (for Government / public facilities) WKCDA (for WKCDA facilities) |
|
|
P |
|
Waste Disposal Ordinance and Public Health and Municipal Services Ordinance - Public Cleansing and Prevention of Nuisances Regulation |
||||||||
7.5.2.2 |
|
Chemical Waste If chemical wastes are expected to be produced during the operation phase, the Project Proponent should register with the EPD as a chemical waste producer and follow the guidelines stated in the “Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes”. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. Licensed collector should be deployed to transport and dispose of the chemical wastes at the approved Chemical Waste Treatment Centre or other licensed recycling facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. |
WKCD site / On a regular basis / Throughout operation stage |
Private Developer (for land sale lots); Relevant Government Departments e.g. FEHD / LCSD (for Government / public facilities) WKCDA (for WKCDA facilities) |
|
|
P |
|
Code of Practice on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General) Regulation |
||||||||
Land Contamination (Construction) |
|||||||||||||||||
8.6 |
|
The
potential for land contamination issues at the TST Fire Station due to its future relocation will be confirmed by site investigation after land
acquisition. Where necessary, mitigation measures for minimising potential
exposure to contaminated materials (if any) or remediation measures will be
identified. If contaminated land is identified (e.g., during decommissioning of
fuel oil storage tanks) after the commencement of works, mitigation measures
are proposed in order to minimise the potentially adverse effects on the
health and safety of construction workers and impacts arising from the
disposal of potentially contaminated materials. The
following measures are proposed for excavation and transportation of
contaminated material: ¡ To minimize the chance for construction workers to
come into contact with any contaminated materials, bulk
earth-moving excavation equipment should be employed; ¡ Contact with contaminated materials can be minimised
by wearing appropriate clothing and personal protective equipment such as
gloves and masks (especially when interacting directly with contaminated
material), provision of washing facilities and prohibition of smoking and
eating on site; ¡ Stockpiling of contaminated excavated materials on
site should be avoided as far as possible; ¡ The use of contaminated soil for landscaping purpose
should be avoided unless pre-treatment was carried out; ¡ Vehicles containing any contaminated excavated
materials should be suitably covered to reduce dust emissions and/or release
of contaminated wastewater; ¡ Truck bodies and tailgates should be sealed to stop
any discharge; ¡ Only licensed waste haulers should be used to collect
and transport contaminated material to treatment/disposal site and should be equipped with tracking system to
avoid fly tipping; ¡ Speed control for trucks carrying contaminated
materials should be exercised; ¡ Observe all relevant regulations in relation to waste
handling, such as Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 354) and obtain all necessary
permits where required; and ¡ Maintain records of waste generation and disposal
quantities and disposal arrangements. |
Site of the existing Tsim Sha Tsui Fire Station / During excavation activities / Prior to construction of WKCD facilities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance; and Waste Disposal (Chemical Waste) (General) Regulation |
||||||||
Land Contamination (Operation) |
|||||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||||
Ecological Impact (Construction) |
|||||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||||
Ecological Impact (Operation) |
|||||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||||
Landscape and Visual Impact
(Construction) |
|||||||||||||||||
Table 10.18 (CM1) |
|
Trees should be retained in situ on site as far as possible. Should tree removal be unavoidable due to construction impacts, trees will be transplanted or felled with reference to the stated criteria in the Tree Removal Applications to be submitted to relevant government departments for approval in accordance to ETWB TCW No. 29/2004 and 3/2006. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
P |
P |
|
|
ETWB TCW No. 29/2004 and 3/2006 |
||||||||
Table 10.18 (CM2) |
|
Compensatory tree planting shall be incorporated to the proposed project and maximize the new tree, shrubs and other vegetation planting to compensate tree felled and vegetation removed. Also, implementation of compensatory planting should be of a ratio not less than 1:1 in terms of quality and quantity within the site. |
|
Contractor appointed by WKCDA |
P |
P |
|
|
ETWB TCW No. 3/2006 |
||||||||
Table 10.18 (CM3) |
|
Buffer trees for screening purposes to soften the hard architectural and engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM4) |
|
Softscape treatments such as vertical green wall panel / planting of climbing and/or weeping plants, etc, to maximize the green coverage and soften the hard architectural and engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Detailed Design Consultant / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM5) |
|
Roof greening by means of intensive and extensive green roof to maximize the green coverage and improve aesthetic appeal and visual quality of the building / structure. |
WKCD structures / After completion of superstructure construction / Prior to operation stage |
Detailed Design Consultant / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM6) |
|
Sensitive streetscape design should be incorporated along all new roads and streets. |
Alongside roads and streets within WKCD / After completion of road and street construction / Prior to operation stage |
Detailed Design Consultant / Contractor
appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM7) |
|
Structure, ornamental planting shall be provided along amenity strips to enhance the landscape quality. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM8) |
|
Landscape design shall be incorporated to architectural and engineering structures in order to provide aesthetically pleasing designs. |
WKCD structures / After completion of structure construction / Prior to operation stage |
Detailed Design Consultant / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
Table 10.18 (CM9) |
|
Minimize the structure of marine facilities to build on the seabed and foreshore in order to minimize the affected extent to the waterbody. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Detailed Design Consultant / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
(MCP1) |
|
Use of decorative screen hoarding/boards |
WKCD construction sites / Throughout construction stage / Prior to operation stage |
Contractor appointed by WKCDA |
|
P |
|
|
ETWB TCW No. 3/2006 |
||||||||
(MCP2) |
|
Early introduction of landscape treatments |
WKCD construction sites / Towards the end of construction stage / Prior to operation stage |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO-TM |
||||||||
(MCP3) |
|
Adoption of light colour for the temporary ventilation shafts for the basement during the transition period. |
WKCD basement construction sites / After completion of ventilation shaft superstructure / Prior to operation stage |
Design Architect / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||||
(MCP4) |
|
Control of night time lighting such as avoidance of lighting from spilling onto nearby residential developments. |
WKCD construction sites / During night time / Throughout construction stage |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO-TM |
||||||||
(MCP5) |
|
Use of greenery such as grass cover for the temporary landscaped areas will reduce the visual impacts derived by the construction works in the surroundings within the WKCD site. |
WKCD temporary landscaped areas / Throughout construction stage / Prior to operation stage |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO-TM |
||||||||
Landscape and Visual Impact (Operation) |
|||||||||||||||||
Table 10.19 (OM1) |
|
Provide proper planting establishment works, including watering, pruning, weeding, pest control, replacement of dead plant, etc, on the new planting areas to enhance the aesthetic design degree |
WKCD open areas / Throughout operation phase / As-needed basis |
Private Developer (for land sale lots); LCSD (for roadside planting) WKCDA (for all other WKCD areas) |
|
|
P |
|
EIAO-TM |
||||||||
Table 10.19 (OM2) |
|
Provision of open space in various forms
and at different levels on or above ground, including park, waterfront
promenade, piazzas and terrace garden and associated green connections for public
enjoyment. |
WKCD open areas / Throughout operation phase / As-needed basis |
Private Developer (for land sale lots); LCSD (for roadside planting) WKCDA (for all other WKCD areas) |
P |
|
P |
|
EIAO-TM |
||||||||
(GDF1) |
|
Control of With well designed low to medium-rise buildings, the proposed WKCD development is anticipated to be highly compatible with the surroundings. |
WKCD buildings / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(GDF2) |
|
Creation of View Corridor The buildings on
the WKCD site are designed to allow visual permeability from the WKT to |
WKCD buildings / During design stage / Throughout operation phase |
Design Architect appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(GDF3) |
|
Preservation of Open An open vista and
green corridor from the heritage sites consisting of the declared monuments
of St. Andrew’s Church, former |
WKCD open areas / During design stage / Throughout operation phase |
Design Consultant appointed by WKCDA / WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(GDF4) |
|
Provision of Open Space The open space will be provided in various forms at grade in the WKCD, including piazzas, a landscaped waterfront promenade and various green spaces. |
WKCD open areas / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(GDF5) |
|
Provision of The unique designed terrace gardens are considered as a good design feature to lessen the visual impacts and provide new visual resources when viewed from the VSRs at higher levels. |
WKCD open areas / During design stage / Throughout operation phase |
Private Developer (for land sale lots); WKCDA (for WKCD facilities) |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP1) |
|
Undulating berms and the trees planted in the surroundings of the existing WHC and MTR ventilation buildings. |
Around existing
ventilation buildings within WKCD / During construction of |
Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||||
(MOP2) |
|
Clusters of shade
planting and appropriate landscaping are designed to provide a relaxing
waterfront environment,
soften the water edge and helps
mitigate the visual impacts associated with the existing MTR & WHC ventilation
buildings. |
WKCD waterfront / During design stage / Throughout operation phase |
Landscape Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP3) |
|
The unique designed roof top gardens and green roof are considered as mitigation measures to lessen the visual impacts and provide new visual resources when viewed from the VSRs at higher levels. |
WKCD open areas / During design stage / Throughout operation phase |
Private Developer (for land sale lots); WKCDA (for WKCD facilities) |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP4) |
|
Buffer trees for screening purposes or other softscape treatments such as vertical green wall /climber /green roof /vertical greening shall be incorporated to soften the hard architectural and engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Throughout operation stage |
Private Developer (for land sale lots); WKCDA (for WKCD facilities) |
|
|
P |
|
EIAO-TM |
||||||||
(MOP5) |
|
Use of natural colour tones (e.g. green colour) for wind turbines located along the waterfront, to make them visually more compatible with the surroundings. |
WKCD waterfront / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP 6) |
|
Appropriate positioning and angling of the solar panels to avoid significant visual impacts on the VSRs located at upper levels in close proximity. |
WKCD building rooftops / During daytime / Throughout operation stage |
Private Developer (for land sale lots); WKCDA (for WKCD facilities) |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP 7) |
|
Aesthetic design of roads
and streetscapes |
Along WKCD roads and streets / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP 8) |
|
Human scale design for
the |
|
Design Architect / Contractor appointed by WKCDA / MTRC |
P |
|
P |
|
EIAO-TM |
||||||||
(MOP 9) |
|
Night time lighting control measures such as the use of sensors and timers could help reduce usage after hours. |
WKCD building exterior and open areas / During night time / Throughout operation stage |
Private Developer (for land sale lots); WKCDA (for WKCD facilities) |
|
|
P |
|
EIAO-TM |