Contents |
Chapter Title Page
Figures
Figure 15.2.1 Proposed
Austin Road Flyover Profile of Layout Plan (Sheet 1 of 4)
Figure 15.2.2 Proposed
Austin Road Flyover Profile of Layout Plan (Sheet 2 of 4)
Figure 15.2.3 Proposed
Austin Road Flyover Profile of Layout Plan (Sheet 3 of 4)
Figure 15.2.4 Proposed
Austin Road Flyover Profile of Layout Plan (Sheet 4 of 4)
Figure 15.3.1 Locations
of Air Sensitive Receivers (outside WKCD Site)
Figure 15.3.2 Locations
of Air Sensitive Receivers (within WKCD Site)
Figure 15.4.1 Locations
of Noise Sensitive Receivers for Flyover
Figure 15.5.1 Locations
of Water Control Zones
Figure 15.5.2 Locations
of Key Water Sensitive Receivers
Figure 15.9.2 Transect
Route for Ecological Survey
Figure 15.10.1 Baseline
Landscape Resources within the Assessment Area of Austin Road Flyover
Figure
15.10.2 (not used)
Figure 15.10.3a Baseline
Landscape Resources Photo Record (Sheet 1 of 6)
Figure 15.10.3b Baseline
Landscape Resources Photo Record (Sheet 2 of 6)
Figure 15.10.3c Baseline
Landscape Resources Photo Record (Sheet 3 of 6)
Figure 15.10.3d Baseline
Landscape Resources Photo Record (Sheet 4 of 6)
Figure 15.10.3e Baseline
Landscape Resources Photo Record (Sheet 5 of 6)
Figure 15.10.3f Baseline
Landscape Resources Photo Record (Sheet 6 of 6)
Figure 15.10.4 Broad
Brush Tree Survey Plan
Figure 15.10.5 Baseline
Landscape Character Area within the Assessment Area of Austin Road Flyover
Figure
15.10.6 (not used)
Figure 15.10.7a Baseline
Landscape Character Area Photo Record (Sheet 1 of 6)
Figure 15.10.7b Baseline
Landscape Character Area Photo Record (Sheet 2 of 6)
Figure 15.10.7c Baseline
Landscape Character Area Photo Record (Sheet 3 of 6)
Figure 15.10.7d Baseline
Landscape Character Area Photo Record (Sheet 4 of 6)
Figure 15.10.7e Baseline
Landscape Character Area Photo Record (Sheet 5 of 6)
Figure 15.10.7f Baseline
Landscape Character Area Photo Record (Sheet 6 of 6)
Figure 15.10.8 Locations
of the VSRs located within the Primary Zone of Visual Influence
Figure 15.10.9 Photos
of VSR 1 to VSR 4
Figure 15.10.10 Photos
of VSR 5 to VSR 8
Figure 15.10.11a Photomontages
1A & 1B - Viewpoint 1 (International Commerce Centre at Podium Level)
Figure 15.10.11b Photomontages
1C & 1D - Viewpoint 1 (International Commerce Centre at Podium Level)
Figure 15.10.12a Photomontages
2A & 2B - Viewpoint 5 (Western Harbour Crossing Toll Plaza)
Figure 15.10.12b Photomontages
2C & 2D - Viewpoint 5 (Western Harbour Crossing Toll Plaza)
Figure 15.10.14 List
of Landscape Mitigation Measures for Austin Road Flyover
Figure 15.10.15 Proposed
Landscape Concept Plan
Figure 15.10.16 Landscape
Concept Plan for Park
Figure 15.10.17 Landscape
Concept for Austin Road West Section A – A
Appendices
Appendix 15.4.2 Unmitigated
Road Traffic Noise Impact (Year 2032) – Permanent Access at Canton Road
Appendix 15.4.3 Unmitigated
Road Traffic Noise Impact (Year 2032 – without Project)
Appendix 15.4.4 Peak
Hour Flow (2032) – without Proposed Flyover
15.
|
15.1.1 Background
The idea and form
of developing a site of approximately 40 ha on the northern shore of the
magnificent Victoria Harbour of Hong Kong for arts and cultural facilities has
had a rich history of discussion in the
In terms of
planning, the community remarked that the WKCD should not be seen as an
isolated development. Accessibility from and connectivity to the neighbouring
community should be carefully thought through to help integrate the arts and
cultural facilities in the WKCD with its neighbouring areas with a view to
cultivate cultural ambience in the district and its immediate vicinity. Ample
open space and a vibrant harbour-front should be provided to respond to the
growing trend towards lowering building density, greater public awareness about
good harbour-front planning and rising public aspiration for quality of life.
The
West Kowloon Cultural District Authority (WKCDA), empowered by the WKCDA
Ordinance (Cap. 601), was set up by the Government with the full support of the
Legislative Council (LegCo) in October 2008 to take forward the WKCD project.
The WKCDA is
responsible for the preparation of a comprehensive Development Plan (DP). The DP was submitted to the Town Planning
Board (TPB) on 20 December 2011 in accordance with the WKCDA Ordinance (Cap.
601). The draft DP (No. S/K20/WKCD/1) was gazetted under sectin 5 of the Town Planning Ordinance
(Cap. 131) on 20 March 2012. On 8 January 2013, the Chie Executive in Council,
under section 9(1)(a) of the Town Planning Ordinance
(Cap. 131), approved the draft DP. The approved DP (No.
S/K/WKCD/2) now serves as the basis for
implementation. The project area and project layout to be taken forward in this
Schedule 2
15.1.2 Designated Projects under the
The Project referred to in this chapter is the individual Schedule 2 Designated Project “a flyover more than 100m in length between abutments over the Western Harbour Crossing toll plaza (Item A.8, Part I, Schedule 2)”, which forms part of the Schedule 3 project for the WKCD development.
15.1.3 Objectives of the
In accordance with the
(i) the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project and associated works, and their staged implementation;
(ii) the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences; and
(iii) the acceptability of residual impacts after the proposed mitigation measures are implemented.
Section 2.1 of the
(i) to describe the Project and associated works together with the requirements and environmental benefits for carrying out the Project;
(ii) to identify and describe elements of community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including natural and man-made environment and the associated environmental constraints;
(iii) to
provide
(iv) to identify and quantify emission sources, including air and gaseous emission, noise emission, sewage and wastewater emission, waste generation, contaminated materials, and determine the significance of impacts on sensitive receivers and potential affected uses;
(v) to identify and quantify any potential losses or damage to flora, fauna and natural habitats;
(vi) to identify and systematically evaluate any potential landscape and visual impacts and to propose measures to mitigate these impacts;
(vii) to propose the provision of infrastructure or mitigation measures so as to minimize pollution, environmental disturbance and nuisance during construction and operation of the Project;
(viii) to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
(ix) to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;
(x) to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;
(xi) to
investigate the extent of the secondary environmental impacts that may arise
from the proposed mitigation measures and to identify constraints associated
with the mitigation measures recommended in the
(xii) to
identify, within the study area, any individual project(s) that fall under
Schedule 2 of the
(xiii) to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.
15.1.4 Key Environmental Issues
The
(i) the potential air quality impact on sensitive receivers from the construction and operation of the Project and associated works, and the potential air quality impact on the Project from the air pollutant emission sources (such as vehicular emission, exhaust gas from ventilation buildings, emission from marine vessels); the potential odour impacts and nuisances from New Yau Ma Tei Typhoon Shelter, with a view to assessing and recommending sound engineered mitigation proposal(s) to avoid or minimize such impacts and nuisances to the maximum extent practicable;
(ii) the potential noise impact on sensitive receivers caused by the Project and associated works, including the impact from construction equipments during construction and operational noise impacts from road traffic, fixed noise sources, marine traffic, railways and helicopter (if applicable);
(iii) the potential water quality impact caused by the Project and associated works, such as works associated with modification of seawalls, drainage and sewerage provisions, spent cooling water discharges, overflow bypass of sewage pumping stations (if applicable) and dredging works of other marine structures (if applicable);
(iv) the potential sewerage and sewage treatment implications, taking into account the staged implementation of planned developments within the Project;
(v) the potential impacts of various types of wastes, including excavated materials from construction works, construction and demolition wastes, and chemical wastes generated from the construction and operation of the Project and associated works;
(vi) the potential land contamination issue within the Project site;
(vii) the potential landscape and visual impacts caused by the construction and operation of the Project, which involves the introduction of a new urban development at a prominent location of the Victoria Harbour, including day-time and night-time visual impact from the Project;
(viii) the potential impact on ecological sensitive areas, the assessment of which shall be based on a field survey of at least 4 months covering the wet and dry seasons;
(ix) the potential fisheries impacts, if the dredging works associated with the construction of the possible piers/viewing platform will be involved in the Project; and
(x) potential cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed and planned projects in the vicinity of the Project (such as Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link, Road Works at West Kowloon, Proposed Road Improvement Works in West Kowloon Reclamation Development Phases I and II, Central Kowloon Route), and that those impacts may have a bearing on the environmental acceptability of the Project.
15.1.5 Use of Relevant Studies
This Schedule
2
¡ Hong Kong Section of the
¡ Road Works at
15.1.6 Structure of the Schedule 2
This Schedule
2
¡ Section 15.2 – Project Description presents a description of the project including consideration of alternative options and concurrent projects
¡ Section 15.3 – Air Quality Impact presents the approach, findings and recommendations from the air quality impact assessment
¡ Section 15.4 – Noise Impact presents the approach, findings and recommendations from the noise impact assessment
¡ Section 15.5 – Water Quality Impact presents the approach, findings and recommendations from the water quality impact assessment
¡ Section 15.6 – Sewerage and Sewage Treatment Implication presents the approach, findings and recommendations from the sewerage and sewage assessment
¡ Section 15.7 – Waste Management Implication presents the approach, findings and recommendations from the waste assessment
¡ Section 15.8 – Land Contamination presents the approach, findings and recommendations from the land contamination assessment
¡ Section 15.9 – Ecological (Terrestrial) Impact presents the approach, findings and recommendations from the terrestrial ecology impact assessment
¡ Section 15.10 – Landscape and Visual Impact presents the approach, findings and recommendations from the landscape and visual impact assessment
¡ Section 15.11 – Environmental Monitoring and Audit Requirements summarises the environmental monitoring and audit requirements specified in Section 15.3 to 15.10
¡ Section 15.12 – Conclusions summarises the findings and recommendations from the environmental impact assessment
¡ Section 15.13 – Implementation Schedule of Mitigation Measures summarises the schedule for implementation of mitigation measures specified in Section 15.3 to 15.10
15.2.1 Existing Site Conditions
The site for the Austin Road flyover is located outside the proposed WKCD site as shown in Figure 15.1.1. The site is currently occupied mainly by the Western Harbour Crossing (WHC) and its toll plaza, and part of the existing West Kowloon Waterfront Promenade on either side of the WHC.
15.2.2 Project Components
This Schedule 2 Project is for extension of
the existing elevated deck at the junction of
As shown in Figures 15.2.1 to 15.2.4,
the proposed flyover will be a single two-lane two-way elevated highways
structure supported by four piers (which had already been constructed under two
previous projects as explained in Section
15.2.4); and its approach ramps span between piers and conventional
abutments. The abutments will be located at the two ends of the bridge deck. The
flyover is about 200m long and 7.3m width with 1m marginal strip at each side.
A new approach ramp adjacent to the existing
WHC administration building is also proposed to connect with the elevated roundabout
junction of
15.2.3.1 Purpose and Objective of the Project
The main purpose of the flyover is to serve as one of the key measures to meet the ‘accessibility and connectivity’ aspect of the overall WKCD development objectives mentioned in Section 15.1.1.
Specifically, the purpose of the flyover is to provide a second access for the proposed WKCD Mega Performance Venue (MPV) and Exhibition Centre (EC). This access can be used by general traffic under normal conditions and will provide flexibility for event management at the MPV/EC as well as enhance the accessibility and robustness of the arrangements including post event traffic dispersal for serving the MPV and second emergency vehicle route.
15.2.3.2 Environmental Benefits of the Project
Traffic congestion will inevitably cause
deterioration of air quality arising from vehicular traffic emissions and noise
impact. The Project will allow free flow traffic condition,
evenly dispersed vehicular traffic and better transportation efficiency in the
future such that the potential of air quality impact of traffic emissions on
the
15.2.3.3 Scenario with the Project
The MPV has been designed to cater for over 15,000 seating capacity. For time-specific events, such as concerts, the arrival or departure of over 15,000 visitors may be expected within a one hour timeframe. This has the potential to create a significant pressure on the vehicular access to MPV, where private cars and some public transportation modes (buses and taxis) compete and queue for space to dropoff/pickup at the MPV entrance. With the provision of a second vehicular access to the MPV via the flyover, vehicular traffic arriving at or departing from the MPV can be more evenly dispersed, allowing better transportation efficiency and greater flexibility for handling unexpected or emergency situations.
15.2.3.4 Scenario without the Project
In the absence of the flyover, there will be only one vehicular access to the MPV and EC (via the at grade road between the Park and the WHC tunnel entrance) and the road around the WHC portal will become a dead-end road. In case of any blockage/accident at the road around the WHC portal, there would be no alternative vehicular route to/from the MPV, the EC and the hotel/office development around the WHC portal. From a transport planning view point, provision of the Austin Road flyover is considered to be essential such that traffic can be diverted via the Austin Road flyover to/from WKCD in case of emergency situations. In addition, it is considered desirable to provide an alternative vehicular route to cater for unexpectedly high vehicular travel demands to/from the MPV and EC during special events, which could otherwise result in significant traffic congestion during the drop off/pick up hours of such events.
15.2.4 Consideration of Alternative Development Options
Unlike
most other new ‘flyover’ projects, this proposed flyover has technically
already been planned and provisioned for by two predecessor projects, namely, Contract
No. WK25/96 Remaining Road Works Stage 1, and the WHC project, whereby
construction of the latter has included piled foundations and stub columns at
the WHC toll plaza to allow for a future 6-lane
Given these predefined conditions, the proposed flyover is virtually the only alignment option for provision of the essential alternative vehicular access to MPV and EC. Nevertheless, for comparison purposes the provision of this alternative vehicular access in the form of at-grade or underground road has been preliminarily reviewed as follows:
¡ At-grade – not possible due to direct conflict with the existing WHC operation
¡ Underground – would not be technically viable due to insufficient space
and obstruction by existing piled foundations below the WHC toll plaza, as well
as conflict with the design for
In view of the predefined conditions and the preliminary review results, the proposed flyover is the preferred and viable development option.
15.2.5 Consideration of Alternative Construction Methods and Sequences of Works
For construction of the superstructures for vehicular and pedestrian bridges, the following methods may be adopted:
¡ Cast in-situ deck – scaffolding/falsework is erected for the placement of formwork before in-situ concreting of deck structure;
¡ Single span lifting method – the entire span precast deck will be lifted into position;
¡ Steel truss with concrete deck – this method involves lifting the prefabricated steel truss followed by construction of the concrete deck; and
¡ Precast segmental method - the bridge deck will be constructed as
precast segments (each a few metres long), which are lifted into position and
then tied together with pre-stressing cables. This method has been extensively
adopted in
The aforementioned methods do not differ significantly in terms of environmental impacts. The selection of method is, rather, driven by consideration on site constraints such as avoiding disturbance to existing traffic, providing sufficient headroom between the road and falsework during the construction stage, design form of the proposed bridges and also the individual contractors’ available equipment/resources in-hand. Construction of the flyover is severely constrained by the Western Harbour Crossing (WHC) and the location of the existing piled foundations and stub columns. A comparison of the different construction methods is presented below.
15.2.5.1 Cast in-situ deck
In-situ cast concrete bridges are
particularly suited to construction of bridge decks with alignments that have
sharp curves, tapered shapes and sharp skewed angles. This method requires
extensive false-work, temporary support from ground level, and would create
significant disturbance to the existing traffic and operation of the WHC.
15.2.5.2 Single Span Lifting
For spans less than 75m in length,
lifting the entire pre-cast may be appropriate. However, it requires a large
crane area with necessary access and available space to locate the crane. The
flyover will comprise of a triple span bridge and is within limits for lifting,
however, the key concern is the availability of space to locate the crane. It
is anticipated that the Contractor will adopt the precast spans method but this
also depends on the availability of plant and space for lifting the precast
spans. Similar concerns exist with the single lift of a steel truss and
concrete deck method.
15.2.5.3 Steel Truss with Concrete Deck
This method also involves pre-fabrication of the whole steel truss span, which is then lifted into position by a crane. The concrete deck formwork is then laid prior to casting the concrete slab in-situ. This method also requires a large crane area, which will need to occupy a large part of the WHC area during the lifting operation.
15.2.5.4 Pre-cast Segmental Launching
In view of site constraints, pre-cast
segmental launching method is considered the most appropriate method for the
construction of the flyover. It has the benefit of requiring no scaffolding and
quick erection, thereby limiting disturbance to the WHC and the surrounding
environment. The launching gantry is designed to cross the existing roads
without disturbing existing traffic (i.e. traffic may pass underneath the
partially launched bridge structure during non-active construction periods
without any direct obstruction from the launching gantry). This method has been
adopted extensively in other parts of
Given
the aforementioned comparison of construction methods, it is anticipated that
construction of the vehicular bridge will adopt the precast segmental method in
the form of box girders subject to detailed design.
Based on the considerations described in Section 15.2.5, the preferred
construction scenario for the flyover is the precast segmental method, as this
method is associated with less environmental impacts compared to other options,
and is considered to be best able to meet the technical requirements and site constraints.
15.2.7 Proposed Project Programme
The flyover is a supplementary component of the WKCD development project, proposed mainly to support certain WKCD facilities. Implementation of the flyover is subject to factors such as funding and associated arrangements, as well as interface with and restrictions imposed by the operators of the existing WHC tunnel entrance and toll plaza. Despite such factors and restrictions, it is tentatively scheduled to complete construction of this flyover by 2017 (see Appendix 2.4).
The
following major projects under planning and/or construction are likely to
interface with this Schedule 2
¡
¡ Hong Kong Section of the
¡ Road Works at
¡ Road Improvement Works in
¡ Central
A summary of the concurrent projects for which potential cumulative impacts have been considered is shown in Table 15.2.1.
Table 15.2.1: List of concurrent projects for cumulative impact assessment
|
Potential Cumulative Impacts |
|
Concurrent
Project |
Construction Phase |
Operation Phase |
|
All Areas |
All Areas |
Hong Kong Section of the |
Fugitive Dust Airborne Noise |
n/a |
Road Works at |
Fugitive Dust Airborne Noise Landscape & Visual |
Vehicular Emissions Traffic Noise Landscape & Visual |
Road Improvement Works in |
Fugitive Dust Airborne Noise Landscape & Visual |
Vehicular Emissions Traffic Noise Landscape & Visual |
Central |
Fugitive Dust |
Vehicular Emissions |
This section presents the assessment of potential air quality impacts associated with the construction and operational phase of the proposed flyover road within the WKCD site. Dust generated from various construction activities is the primary concern during the construction phase. During the operation phase the major sources of air pollution include, but are not limited to; vehicular emissions in the vicinity of and within the project area including from open roads, ventilation shafts, tunnel portals and from the nearby Western Harbour Crossing (WHC) portal; marine emissions from the nearby China Ferry Terminal, Ocean Terminal and New Yau Ma Tei Public Cargo Working Area (NYPCWA). Representative Air Sensitive Receivers (ASRs) within 500 m of the subject site have been identified and the worst case impacts on these receivers will be assessed. Suitable mitigation measures, where necessary, have been recommended to protect the nearby sensitive receivers and to achieve the legislative criteria and guidelines.
15.3.1 Air Quality Legislations, Standards and Guidelines
The following legislation and regulations provide the standards and guidelines for evaluation of air quality impacts and the type of works that are subject to air pollution control:
¡ Environmental Impact
Assessment Ordinance (
¡ Air Pollution Control
Ordinance (APCO) (Cap. 311) and the Air Quality Objectives (AQO);
¡ Air Pollution Control
(Construction Dust) Regulation;
¡ Control of Air Pollution in
Car Parks (ProPECC PN 2/96);
¡ Practice Note on Control of
Air Pollution in Vehicle Tunnels, and;
¡ Guidance Note on the Best
Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2
15.3.1.1 Technical Memorandum on Environmental Impact Assessment Process
The
criteria and guidelines for evaluation of air quality impacts are laid out in
Annex 4 and Annex 12 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM). Annex 4
stipulates the criteria for evaluating air quality impacts. This includes
meeting the Air Quality Objectives and other standards established under the Air Pollution Control Ordinance, as well
as meeting the hourly Total Suspended Particulate concentration of 500 µg/m3. Annex 12 provides the
guidelines for conducting air quality assessments under the
15.3.1.2 Air Pollution Control Ordinance
The principal legislation for the management of air quality is the Air Pollution Control Ordinance (APCO) (Cap 311). The APCO specific Air Quality Objectives (AQOs) which stipulate the statutory limits of air pollutants and the maximum allowable numbers of exceedance over specific periods. The AQOs are summarised in Table 15.3.1.
Table 15.3.1: Hong Kong Air Quality Objectives
Pollutant |
Averaging
Time |
AQO concentration (µg/m³) |
Allowable exceedances |
Sulfur Dioxide (SO2) |
1 hour |
800 |
3 |
24 hour |
350 |
1 |
|
Annual |
80 |
0 |
|
Total Suspended Particulates (TSP) |
1 hour(1) |
500(1) |
|
24 hour |
260 |
1 |
|
Annual |
80 |
0 |
|
Respirable Suspended Particulates (RSP) |
24 hour |
180 |
1 |
Annual |
55 |
0 |
|
Nitrogen Dioxide (NO2) |
1 hour |
300 |
3 |
24 hour |
150 |
1 |
|
Annual |
80 |
0 |
|
Carbon Monoxide (CO) |
1 hour |
30,000 |
3 |
8 hour |
10,000 |
1 |
|
Ozone (O3) |
1 hour |
240 |
3 |
Lead |
3 month |
1.5 |
0 |
Note (1) The
criterion under EIAO-TM not an AQO
15.3.1.3 Air Pollution Control (Construction Dust) Regulation
The Air Pollution Control (Construction Dust) Regulation enacted under the APCO defines notifiable and regulatory works activities that are subject to construction dust control, as listed below:
Notifiable Works:
1. Site formation
2. Reclamation
3. Demolition of a building
4. Work carried out in any part of a tunnel that is within 100 m of any exit to the open air
5. Construction of the foundation of a building
6. Construction of the superstructure of a building
7. Road construction work
Regulatory Works:
1. Renovation carried out on the outer surface of the external wall or the upper surface of the roof of a building
2. Road opening or resurfacing work
3. Slope stabilisation work
4. Any work involving any of the following activities:
a. Stockpiling of dusty materials
b. Loading, unloading or transfer of dusty materials
c. Transfer of dusty materials using a belt conveyor system
d. Use of vehicles
e. Pneumatic or power-driven drilling, cutting and polishing
f. Debris handling
g. Excavation or earth moving
h. Concrete production
i. Site clearance
j. Blasting
Notifiable works require that advance notice of activities shall be given to EPD. The Regulation also requires the works contractor to ensure that both notifiable works and regulatory works are conducted in accordance with the Schedule of the Regulation, which provides dust control and suppression measures.
15.3.1.4 Practice Note on Control of Air Pollution in Car Parks and in Vehicle Tunnels
These practice note for professional persons ProPECC PN 2/96 and the Practice Note on Control of Air Pollution in Vehicle Tunnels prepared by EPD provide guidance on the control of air pollution in car parks and vehicle tunnels respectively. These two practice notes include air quality guidelines required for the protection of public health and factors that should be considered in the design and operation of car parks and vehicle tunnels in order to achieve the required air quality. The limits for air pollutants as recommended by the two practice notes are summarised in Table 15.3.2.As there will be fully enclosed vehicle roads and car parks inside the proposed WKCD basement, the air quality within the basement will need to comply with the relevant air pollutant limits as given in the Table.
Table 15.3.2: Limits of air pollutant concentrations inside car parks and vehicle tunnes
Air Pollutant |
Averaging Time |
Maximum Concentration (μg/m3)* |
Parts Per Million (ppm) |
Remarks |
Carbon Monoxide (CO) |
5 minutes |
115,000 |
100 |
Applicable to both car parks and vehicle tunnels |
Nitrogen Dioxide (NO2) |
5 minutes |
1,800 |
1 |
Ditto |
Sulfur Dioxide (SO2) |
5 minutes |
1,000 |
0.4 |
Applicable to vehicle tunnels only |
*Concentrations at reference conditions of 289k and 101.325kPa.
15.3.1.5 Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2
This note lists the minimum requirement for meeting the best practicable means for Cement Works (Concrete Batching Plant). The guidance note includes: emission limits; fugitive emission control recommendations; monitoring requirements; commissioning details, and; operation and maintenance provisions. This guidance note is relevant because concrete batching plant currently used by the adjacent XRL project would be handed over to and used by the WKCD Project during the construction phase.
The
flyover road lies within the WKCD site on the south-western tip of the
Land
uses surrounding the proposed flyover road are mainly comprised of residential,
commercial and government/institution/community (GIC) use. The flyover road is flanked by primary
distributor roads:
The site for the proposed flyover road is flat to undulating with a ground level of 5 to 23 mPD, the surrounding terrain is flat.
15.3.2.2 Meteorology
The PATH (Pollutants in the Atmosphere and
their Transport over
Features of the wind profile that are significant
for the site are both the wind speed and wind direction. Low wind speeds are
significant for dispersion of non buoyant area sources. At high wind speeds,
dust emissions can become significant.
At the site, winds from the northeast are
frequent in the autumn and winter. Significant sources that lay to the
northeast of the site include
Graph
15.1 shows seasonal
windroses for the site from PATH data at grid (28, 27). PATH uses wind data
based on meteorology
Graph
15.1: Seasonal
windroses for the flyover road site from 2010 PATH data at grid (28, 27)
|
15.3.2.3 Air Sensitive Receivers
The existing and planned representative Air Sensitive Receivers (ASRs) that could be effected by the flyover road Project within 500 m from its site boundary have been identified and are summarised in Table 15.3.3. The final use of each of the parcels may change in the future; therefore, ASRs have been assessed at a variety of intervals up to the proposed maximum height of the buildings that are currently planned. Receptors are located every four metres from 4 m to 20 m and every 10 metres from 20 m to the maximum height of the proposed building. A bias is generated towards the lower levels as this is where the maximum pollutant concentrations are expected to occur.
A
field study of the selected
existing ASRs external to the flyover road boundary was undertaken and
the fresh air intake and residential levels were estimated based on a visual
survey. Fresh air intakes for low level commercial property were assumed to be
at podium level or where ventilation ducts were identified. Residential
receptors were assessed every four metres from the lowest residential level up
to 20 metres and then every 10 metres above that.
All the ASRs as listed in Table 15.3.3 are subject to air quality impact during the operation phase of the flyover road. Construction of the flyover road forms part of the WKCD Project. The flyover road is scheduled to be constructed between 2013 and 2017. The planned ASRs representing facilities/buildings within the WKCD site that will be completed at the early stage of the Project will be subject to air quality impact due to construction of the facilities/buildings at a later stage. Hence, the years in which the planned ASRs will be subject to the construction phase air quality impacts are detailed in Table 15.3.3 and shown in Figures 15.3.1 and 15.3.2. Shaded cells are indicative of residential ASRs.
Table 15.3.3: Representative ASRs Identified for the Assessment
No. |
ASR |
Description |
Horizontal
distance from WKCD site boundary (m) |
Height (mPD) |
Height above ground (m) |
No. of storeys |
Year
subject to construction phase impact |
Notes |
1 |
SRT-1 |
(Existing ASR) |
404 |
24 |
19 |
65 |
2013 – 2017 |
4m above podium |
2 |
SRT-2 |
28 |
23 |
8m above podium |
||||
3 |
SRT-3 |
32 |
27 |
12m above podium |
||||
4 |
SRT-4 |
36 |
31 |
16m above podium |
||||
5 |
SRT-5 |
40 |
35 |
20m above podium |
||||
6 |
SRT-6 |
50 |
45 |
30 m above podium |
||||
7 |
SRT-7 |
60 |
55 |
40 m above podium |
||||
8 |
SRT-8 |
70 |
65 |
50 m above podium |
||||
9 |
SRT-9 |
80 |
75 |
60 m above podium |
||||
10 |
SRT-10 |
90 |
85 |
70 m above podium |
||||
11 |
SRT-11 |
100 |
95 |
80 m above podium |
||||
12 |
SRT-12 |
110 |
105 |
90 m above podium |
||||
13 |
SRT-13 |
120 |
115 |
100 m above podium |
||||
14 |
SRT-14 |
130 |
125 |
110 m above podium |
||||
15 |
SRT-15 |
140 |
135 |
120 m above podium |
||||
16 |
SRT-16 |
150 |
145 |
130 m above podium |
||||
17 |
SRT-17 |
160 |
155 |
140 m above podium |
||||
18 |
SRT-18 |
170 |
165 |
150 m above podium |
||||
19 |
SRT-19 |
180 |
175 |
160 m above podium |
||||
20 |
SRT-20 |
190 |
185 |
170 m above podium |
||||
21 |
SRT-21 |
200 |
195 |
180 m above podium |
||||
22 |
SRT-22 |
210 |
205 |
190 m above podium |
||||
23 |
SRT-23 |
220 |
215 |
200 m above podium |
||||
24 |
SRT-24 |
230 |
225 |
210 m above podium |
||||
25 |
SRT-25 |
240 |
235 |
220 m above podium |
||||
26 |
SRT-26 |
250 |
245 |
230 m above podium |
||||
27 |
SRT-27 |
260 |
255 |
240 m above podium |
||||
28 |
CLS-1 |
The Cullinan – Lunar Sky (Existing ASR) |
194 |
59.8 |
54.8 |
33 |
2013 – 2017 |
lowest possible fresh air intake (1st floor above podium) |
29 |
CLS-2 |
62.6 |
57.6 |
2nd lowest possible fresh air intake (2nd floor above podium) |
||||
30 |
CLS-3 |
127.0 |
122 |
24th floor inlet |
||||
31 |
CLS-4 |
129.8 |
124.8 |
25th floor inlet |
||||
32 |
CLS-5 |
163.4 |
158.4 |
37th floor inlet |
||||
33 |
CLS-6 |
166.2 |
161.2 |
38th floor inlet |
||||
34 |
WF3-1 |
The Waterfront – Tower 3 (Existing ASR) |
158 |
36.2 |
31.2 |
|
2013 – 2017 |
4m above podium |
35 |
WF3-2 |
40.2 |
35.2 |
8m above podium |
||||
36 |
WF3-3 |
44.2 |
39.2 |
12m above podium |
||||
37 |
WF3-4 |
48.2 |
43.2 |
16m above podium |
||||
38 |
WF3-5 |
58.2 |
53.2 |
20m above podium |
||||
39 |
WF3-6 |
68.2 |
63.2 |
30 m above podium |
||||
40 |
WF3-7 |
78.2 |
73.2 |
40 m above podium |
||||
41 |
WF3-8 |
88.2 |
83.2 |
50 m above podium |
||||
42 |
WF3-9 |
98.2 |
93.2 |
60 m above podium |
||||
43 |
WF3-10 |
108.2 |
103.2 |
70 m above podium |
||||
44 |
WF3-11 |
118.2 |
113.2 |
80 m above podium |
||||
45 |
WF3-12 |
128.2 |
123.2 |
90 m above podium |
||||
46 |
WF3-13 |
138.2 |
133.2 |
100 m above podium |
||||
47 |
WF6-1 |
The Waterfront – Tower 6 (Existing ASR) |
309 |
36.1 |
31.1 |
|
2013 – 2017 |
4m above podium |
48 |
WF6-2 |
40.1 |
35.1 |
8m above podium |
||||
49 |
WF6-3 |
44.1 |
39.1 |
12m above podium |
||||
50 |
WF6-4 |
48.1 |
43.1 |
16m above podium |
||||
51 |
WF6-5 |
58.1 |
53.1 |
20m above podium |
||||
52 |
WF6-6 |
68.1 |
63.1 |
30 m above podium |
||||
53 |
WF6-7 |
78.1 |
73.1 |
40 m above podium |
||||
54 |
WF6-8 |
88.1 |
83.1 |
50 m above podium |
||||
55 |
WF6-9 |
98.1 |
93.1 |
60 m above podium |
||||
56 |
WF6-10 |
108.1 |
103.1 |
70 m above podium |
||||
57 |
WF6-11 |
118.1 |
113.1 |
80 m above podium |
||||
58 |
WF6-12 |
128.1 |
123.1 |
90 m above podium |
||||
59 |
WF6-13 |
138.1 |
133.1 |
100 m above podium |
||||
60 |
ICC-1 |
International Commerce Centre(i) (Existing ASR) |
142 |
61.3 |
56.3 |
>100 |
2013 – 2017 |
5th floor inlet |
61 |
ICC-2 |
64.1 |
59.1 |
6th floor inlet |
||||
62 |
ICC-3 |
66.9 |
61.9 |
7th floor inlet |
||||
63 |
ICC-4 |
69.7 |
64.7 |
8th floor inlet |
||||
64 |
ICC-5 |
72.5 |
67.5 |
9th floor inlet |
||||
65 |
ICC-6 |
75.3 |
70.3 |
10th floor inlet |
||||
66 |
ICC-7 |
145.3 |
140.3 |
35th floor inlet |
||||
67 |
ICC-8 |
148.1 |
143.1 |
36th floor inlet |
||||
68 |
ICC-9 |
150.9 |
145.9 |
37th floor inlet |
||||
69 |
ICC-10 |
153.7 |
148.7 |
38th floor inlet |
||||
70 |
ICC-11 |
156.5 |
151.5 |
39th floor inlet |
||||
71 |
ICC-12 |
159.3 |
154.3 |
40th floor inlet |
||||
72 |
ICC-13 |
220.9 |
215.9 |
62nd floor inlet |
||||
73 |
ICC-14 |
223.7 |
218.7 |
63rd floor inlet |
||||
74 |
ICC-15 |
226.5 |
221.5 |
64th floor inlet |
||||
75 |
ICC-16 |
229.3 |
224.3 |
65th floor inlet |
||||
76 |
ICC-17 |
285.3 |
280.3 |
85th floor inlet |
||||
77 |
ICC-18 |
288.1 |
283.1 |
86th floor inlet |
||||
78 |
ICC-19 |
290.9 |
285.9 |
87th floor inlet |
||||
79 |
ICC-20 |
293.7 |
288.7 |
88th floor inlet |
||||
80 |
ICC-21 |
302.1 |
297.1 |
91st floor inlet |
||||
81 |
ICC-22 |
335.7 |
330.7 |
103rd floor inlet |
||||
82 |
HT2-1 |
The HarbourSide – Tower 2 (Existing ASR) |
47 |
30.8 |
25.8 |
63 |
2013 – 2017 |
4m above podium |
83 |
HT2-2 |
34.8 |
29.8 |
8m above podium |
||||
84 |
HT2-3 |
38.8 |
33.8 |
12m above podium |
||||
85 |
HT2-4 |
42.8 |
37.8 |
16m above podium |
||||
86 |
HT2-5 |
46.8 |
41.8 |
20m above podium |
||||
87 |
HT2-6 |
56.8 |
51.8 |
30 m above podium |
||||
88 |
HT2-7 |
66.8 |
61.8 |
40 m above podium |
||||
89 |
HT2-8 |
76.8 |
71.8 |
50 m above podium |
||||
90 |
HT2-9 |
86.8 |
81.8 |
60 m above podium |
||||
91 |
HT2-10 |
96.8 |
91.8 |
70 m above podium |
||||
92 |
HT2-11 |
106.8 |
101.8 |
80 m above podium |
||||
93 |
HT2-12 |
116.8 |
111.8 |
90 m above podium |
||||
94 |
HT2-13 |
126.8 |
121.8 |
100 m above podium |
||||
95 |
HT2-14 |
136.8 |
131.8 |
110 m above podium |
||||
96 |
HT2-15 |
146.8 |
141.8 |
120 m above podium |
||||
97 |
HT2-16 |
156.8 |
151.8 |
130 m above podium |
||||
98 |
HT2-17 |
166.8 |
161.8 |
140 m above podium |
||||
99 |
HT2-18 |
176.8 |
171.8 |
150 m above podium |
||||
100 |
HT2-19 |
186.8 |
181.8 |
160 m above podium |
||||
101 |
HT2-20 |
196.8 |
191.8 |
170 m above podium |
||||
102 |
HT2-21 |
206.8 |
201.8 |
180 m above podium |
||||
103 |
HT2-22 |
216.8 |
211.8 |
190 m above podium |
||||
104 |
HT2-23 |
226.8 |
221.8 |
200 m above podium |
||||
105 |
HT2-24 |
236.8 |
231.8 |
210 m above podium |
||||
106 |
HT2-25 |
246.8 |
241.8 |
220 m above podium |
||||
107 |
HT2-26 |
256.8 |
251.8 |
230 m above podium |
||||
108 |
HT2-27 |
266.8 |
261.8 |
240 m above podium |
||||
109 |
AMT-1 |
The Arch – (Existing ASR) |
95 |
42.0 |
37 |
52 |
2013 – 2017 |
4m above podium |
110 |
AMT-2 |
46.0 |
41 |
8m above podium |
||||
111 |
AMT-3 |
50.0 |
45 |
12m above podium |
||||
112 |
AMT-4 |
54.0 |
49 |
16m above podium |
||||
113 |
AMT-5 |
58.0 |
53 |
20m above podium |
||||
114 |
AMT-6 |
68.0 |
63 |
30 m above podium |
||||
115 |
AMT-7 |
78.0 |
73 |
40 m above podium |
||||
116 |
AMT-8 |
88.0 |
83 |
50 m above podium |
||||
117 |
AMT-9 |
98.0 |
93 |
60 m above podium |
||||
118 |
AMT-10 |
108.0 |
103 |
70 m above podium |
||||
119 |
AMT-11 |
118.0 |
113 |
80 m above podium |
||||
120 |
AMT-12 |
128.0 |
123 |
90 m above podium |
||||
121 |
AMT-13 |
138.0 |
133 |
100 m above podium |
||||
122 |
AMT-14 |
148.0 |
143 |
110 m above podium |
||||
123 |
AMT-15 |
158.0 |
153 |
120 m above podium |
||||
124 |
AMT-16 |
168.0 |
163 |
130 m above podium |
||||
125 |
AMT-17 |
178.0 |
173 |
140 m above podium |
||||
126 |
AMT-18 |
188.0 |
183 |
150 m above podium |
||||
127 |
AMT-19 |
198.0 |
193 |
160 m above podium |
||||
128 |
AMT-20 |
208.0 |
203 |
170 m above podium |
||||
129 |
AMT-21 |
218.0 |
213 |
180 m above podium |
||||
130 |
AMT-22 |
228.0 |
223 |
190 m above podium |
||||
131 |
P16-1 |
Parcel 16 Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
8 |
none |
See Note (vi) |
132 |
P16-2 |
17.4 |
8.0 |
|
||||
133 |
P16-3 |
21.4 |
12.0 |
|
||||
134 |
P16-4 |
25.4 |
16.0 |
|
||||
135 |
P16-5 |
29.4 |
20.0 |
|
||||
136 |
P16-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
137 |
P16-7 |
49.4 |
40.0 |
|
||||
138 |
P16-8 |
59.4 |
50.0 |
|
||||
139 |
P17-1 |
Parcel 17 Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
15 |
none |
See Note (vi) |
140 |
P17-2 |
17.4 |
8.0 |
|
||||
141 |
P17-3 |
21.4 |
12.0 |
|
||||
142 |
P17-4 |
25.4 |
16.0 |
|
||||
143 |
P17-5 |
29.4 |
20.0 |
Lowest residential floor |
||||
144 |
P17-6 |
39.4 |
30.0 |
|
||||
145 |
P17-7 |
49.4 |
40.0 |
|
||||
146 |
P18a-1 |
Parcel 18 (iv) (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
8 |
none |
See Note (vi) |
147 |
P18a-2 |
17.4 |
8.0 |
|
||||
148 |
P18a-3 |
21.4 |
12.0 |
|
||||
149 |
P18a-4 |
25.4 |
16.0 |
|
||||
150 |
P18a-5 |
29.4 |
20.0 |
|
||||
151 |
P18a-6 |
39.4 |
30.0 |
|
||||
152 |
P18a-7 |
49.4 |
40.0 |
|
||||
153 |
P18b-1 |
Parcel 18 (iv) (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
8 |
none |
See Note (vi) |
154 |
P18b-2 |
17.4 |
8.0 |
|
||||
155 |
P18b-3 |
21.4 |
12.0 |
|
||||
156 |
P18b-4 |
25.4 |
16.0 |
|
||||
157 |
P18b-5 |
29.4 |
20.0 |
|
||||
158 |
P18b-6 |
39.4 |
30.0 |
|
||||
159 |
P18b-7 |
49.4 |
40.0 |
|
||||
160 |
P18c-1 |
Parcel 18 (iv) (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
8 |
none |
See Note (vi) |
161 |
P18c-2 |
17.4 |
8.0 |
|
||||
162 |
P18c-3 |
21.4 |
12.0 |
|
||||
163 |
P18c-4 |
25.4 |
16.0 |
|
||||
164 |
P18c-5 |
29.4 |
20.0 |
|
||||
165 |
P18c-6 |
39.4 |
30.0 |
|
||||
166 |
P18c-7 |
49.4 |
40.0 |
|
||||
167 |
P18d-1 |
Parcel 18 (iv) (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
8 |
none |
See Note (vi) |
168 |
P18d-2 |
17.4 |
8.0 |
|
||||
169 |
P18d-3 |
21.4 |
12.0 |
|
||||
170 |
P18d-4 |
25.4 |
16.0 |
|
||||
171 |
P18d-5 |
29.4 |
20.0 |
|
||||
172 |
P18d-6 |
39.4 |
30.0 |
|
||||
173 |
P18d-7 |
49.4 |
40.0 |
|
||||
174 |
P18e |
Parcel 18 (iv) (Planned ASR from 2030 onwards) |
N/A |
49.4 |
40.0 |
8 |
none |
|
175 |
P19-1 |
Parcel 19 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
14 |
none |
See Note (vi) |
176 |
P19-2 |
17.4 |
8.0 |
|
||||
177 |
P19-3 |
21.4 |
12.0 |
|
||||
178 |
P19-4 |
25.4 |
16.0 |
|
||||
179 |
P19-5 |
29.4 |
20.0 |
|
||||
180 |
P19-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
181 |
P19-7 |
49.4 |
40.0 |
|
||||
182 |
P19-8 |
59.4 |
50.0 |
|
||||
183 |
P20-1 |
Parcel 20 + Retail/ Dining/ Entertainment (iv) (Planned ASR from 2017 onwards) |
N/A |
13.4 |
4.0 |
|
2017 |
See Note (vi) |
184 |
P20-2 |
17.4 |
8.0 |
|
||||
185 |
P20-3 |
21.4 |
12.0 |
|
||||
186 |
P20-4 |
25.4 |
16.0 |
|
||||
187 |
P20-5 |
29.4 |
20.0 |
|
||||
188 |
P20-6 |
39.4 |
30.0 |
|
||||
189 |
P20-7 |
49.4 |
40.0 |
|
||||
190 |
P20-8 |
59.4 |
50.0 |
|
||||
191 |
P21-1 |
Parcel 21 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2017 onwards) |
N/A |
13.4 |
4.0 |
13 |
2017 |
See Note (vi) |
192 |
P21-2 |
17.4 |
8.0 |
|
||||
193 |
P21-3 |
21.4 |
12.0 |
|
||||
194 |
P21-4 |
25.4 |
16.0 |
|
||||
195 |
P21-5 |
29.4 |
20.0 |
|
||||
196 |
P21-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
197 |
P21-7 |
49.4 |
40.0 |
|
||||
198 |
P22-1 |
Parcel 22 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
13 |
none |
See Note (vi) |
199 |
P22-2 |
17.4 |
8.0 |
|
||||
200 |
P22-3 |
21.4 |
12.0 |
|
||||
201 |
P22-4 |
25.4 |
16.0 |
|
||||
202 |
P22-5 |
29.4 |
20.0 |
Lowest residential floor |
||||
203 |
P22-6 |
39.4 |
30.0 |
|
||||
204 |
P22-7 |
49.4 |
40.0 |
|
||||
205 |
P22-8 |
59.4 |
50.0 |
|
||||
206 |
P23a-1 |
Parcel 23 (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
8 |
2017 |
See Note (vi) |
207 |
P23a-2 |
17.4 |
8.0 |
|
|
|||
208 |
P23a-3 |
21.4 |
12.0 |
|
|
|||
209 |
P23a-4 |
25.4 |
16.0 |
|
|
|||
210 |
P23a-5 |
29.4 |
20.0 |
|
|
|||
211 |
P23a-6 |
39.4 |
30.0 |
|
|
|||
212 |
P23a-7 |
49.4 |
40.0 |
|
|
|||
213 |
P23b-1 |
Parcel 23 (Planned ASR from 2020 onwards) |
|
13.4 |
4.0 |
8 |
none |
See Note (vi) |
214 |
P23b-2 |
17.4 |
8.0 |
|
||||
215 |
P23b-3 |
21.4 |
12.0 |
|
||||
216 |
P23b-4 |
25.4 |
16.0 |
|
||||
217 |
P23b-5 |
29.4 |
20.0 |
|
||||
218 |
P23b-6 |
39.4 |
30.0 |
|
||||
219 |
P23b-7 |
49.4 |
40.0 |
|
||||
220 |
P23c-1 |
Parcel 23 (Planned ASR from 2020 onwards) |
|
13.4 |
4.0 |
8 |
none |
See Note (vi) |
221 |
P23c-2 |
17.4 |
8.0 |
|
||||
222 |
P23c-3 |
21.4 |
12.0 |
|
||||
223 |
P23c-4 |
25.4 |
16.0 |
|
||||
224 |
P23c-5 |
29.4 |
20.0 |
|
||||
225 |
P23c-6 |
39.4 |
30.0 |
|
||||
226 |
P23c-7 |
49.4 |
40.0 |
|
||||
227 |
P23d-1 |
Parcel 23 (Planned ASR from 2020 onwards) |
|
13.4 |
4.0 |
8 |
none |
See Note (vi) |
228 |
P23d-2 |
17.4 |
8.0 |
|
||||
229 |
P23d-3 |
21.4 |
12.0 |
|
||||
230 |
P23d-4 |
25.4 |
16.0 |
|
||||
231 |
P23d-5 |
29.4 |
20.0 |
|
||||
232 |
P23d-6 |
39.4 |
30.0 |
|
||||
233 |
P23d-7 |
49.4 |
40.0 |
|
||||
234 |
P23e |
Parcel 23 (Planned ASR from 2020 onwards) |
|
49.4 |
40.0 |
8 |
none |
|
235 |
P24-1 |
Parcel 24 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
14 |
none |
See Note (vi) |
236 |
P24-2 |
17.4 |
8.0 |
|
||||
237 |
P24-3 |
21.4 |
12.0 |
|
||||
238 |
P24-4 |
25.4 |
16.0 |
|
||||
239 |
P24-5 |
29.4 |
20.0 |
|
||||
240 |
P24-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
241 |
P24-7 |
49.4 |
40.0 |
|
||||
242 |
P24-8 |
59.4 |
50.0 |
|
||||
243 |
P25-1 |
Parcel 25 (Planned ASR from 2017 onwards) |
N/A |
13.4 |
4.0 |
1 |
2017 |
See Noted (vi) |
244 |
P25-2 |
17.4 |
8.0 |
|
||||
245 |
P25-3 |
21.4 |
12.0 |
|
||||
246 |
P25-4 |
25.4 |
16.0 |
|
||||
247 |
P25-5 |
29.4 |
20.0 |
|
||||
248 |
P26-1 |
Parcel 26 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
15 |
none |
See Note (vi) |
249 |
P26-2 |
17.4 |
8.0 |
|
||||
250 |
P26-3 |
21.4 |
12.0 |
|
||||
251 |
P26-4 |
25.4 |
16.0 |
|
||||
252 |
P26-5 |
29.4 |
20.0 |
|
||||
253 |
P26-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
254 |
P26-7 |
49.4 |
40.0 |
|
||||
255 |
P26-8 |
59.4 |
50.0 |
|
||||
256 |
P27-1 |
Parcel 27 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
15 |
none |
See Note (vi) |
257 |
P27-2 |
17.4 |
8.0 |
|
||||
258 |
P27-3 |
21.4 |
12.0 |
|
||||
259 |
P27-4 |
25.4 |
16.0 |
|
||||
260 |
P27-5 |
29.4 |
20.0 |
|
||||
261 |
P27-6 |
39.4 |
30.0 |
|
||||
262 |
P27-7 |
49.4 |
40.0 |
Lowest residential floor |
||||
263 |
P27-8 |
59.4 |
50.0 |
|
||||
264 |
P28-1 |
Parcel 28 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
21 |
none |
See Note (vi) |
265 |
P28-2 |
17.4 |
8.0 |
|
||||
266 |
P28-3 |
21.4 |
12.0 |
|
||||
267 |
P28-4 |
25.4 |
16.0 |
|
||||
268 |
P28-5 |
29.4 |
20.0 |
|
||||
269 |
P28-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
270 |
P28-7 |
49.4 |
40.0 |
|
||||
271 |
P28-8 |
59.4 |
50.0 |
|
||||
272 |
P28-9 |
69.4 |
60.0 |
|
||||
273 |
P28-10 |
79.4 |
70.0 |
|
||||
274 |
P29-1 |
Parcel 29 + Retail/ Dining/ Entertainment (v) Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
23 |
none |
See Note (vi) |
275 |
P29-2 |
17.4 |
8.0 |
|
||||
276 |
P29-3 |
21.4 |
12.0 |
|
||||
277 |
P29-4 |
25.4 |
16.0 |
|
||||
278 |
P29-5 |
29.4 |
20.0 |
|
||||
279 |
P29-6 |
39.4 |
30.0 |
Lowest residential floor |
||||
280 |
P29-7 |
49.4 |
40.0 |
|
||||
281 |
P29-8 |
59.4 |
50.0 |
|
||||
282 |
P29-9 |
69.4 |
60.0 |
|
||||
283 |
P29-10 |
79.4 |
70.0 |
|
||||
284 |
P30a-1 |
Parcel 30 (Planned ASR from beyond 2020) |
N/A |
13.4 |
4.0 |
6 |
none |
See Note (vi) |
285 |
P30a-2 |
17.4 |
8.0 |
|
||||
286 |
P30a-3 |
21.4 |
12.0 |
|
||||
287 |
P30a-4 |
25.4 |
16.0 |
|
||||
288 |
P30a-5 |
29.4 |
20.0 |
|
||||
289 |
P30b-1 |
Parcel 30 (Planned ASR from beyond 2020) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
290 |
P30b-2 |
17.4 |
8.0 |
|
||||
291 |
P30b-3 |
21.4 |
12.0 |
|
||||
292 |
P30b-4 |
25.4 |
16.0 |
|
||||
293 |
P30b-5 |
29.4 |
20.0 |
|
||||
294 |
P30c-1 |
Parcel 30 (Planned ASR from beyond 2020) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
295 |
P30c-2 |
17.4 |
8.0 |
|
||||
296 |
P30c-3 |
21.4 |
12.0 |
|
||||
297 |
P30c-4 |
25.4 |
16.0 |
|
||||
298 |
P30c-5 |
29.4 |
20.0 |
|
||||
299 |
P30d-1 |
Parcel 30 (Planned ASR from beyond 2020) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
300 |
P30d-2 |
17.4 |
8.0 |
|
||||
301 |
P30d-3 |
21.4 |
12.0 |
|
||||
302 |
P30d-4 |
25.4 |
16.0 |
|
||||
303 |
P30d-5 |
29.4 |
20.0 |
|
||||
304 |
P30e |
Parcel 30 (Planned ASR from beyond 2020) |
|
29.4 |
20.0 |
6 |
none |
|
305 |
P31-1 |
Parcel 31 Office(iv) (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
22 |
none |
See Note (vi) |
306 |
P31-2 |
17.4 |
8.0 |
|
||||
307 |
P31-3 |
21.4 |
12.0 |
|
||||
308 |
P31-4 |
25.4 |
16.0 |
|
||||
309 |
P31-5 |
29.4 |
20.0 |
|
||||
310 |
P31-6 |
39.4 |
30.0 |
|
||||
311 |
P31-7 |
49.4 |
40.0 |
|
||||
312 |
P31-8 |
59.4 |
50.0 |
|
||||
313 |
P31-9 |
69.4 |
60.0 |
|
||||
314 |
P31-10 |
79.4 |
70.0 |
|
||||
315 |
P31-11 |
89.4 |
80.0 |
|
||||
316 |
P32-1 |
Parcel 32 Residential (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
15 |
none |
|
317 |
P32-2 |
17.4 |
8.0 |
|
||||
318 |
P32-3 |
21.4 |
12.0 |
Lowest residential floor |
||||
319 |
P32-4 |
25.4 |
16.0 |
|
||||
320 |
P32-5 |
29.4 |
20.0 |
|
||||
321 |
P32-6 |
39.4 |
30.0 |
|
||||
322 |
P32-7 |
49.4 |
40.0 |
|
||||
323 |
P34-1 |
Parcel 34 + Planned Performance Art Venues within WKCD (iv) (Planned ASR from 2018 onwards) |
N/A |
13.4 |
4.0 |
21 |
none |
See Note (vi) |
324 |
P34-2 |
17.4 |
8.0 |
|
||||
325 |
P34-3 |
21.4 |
12.0 |
|
||||
326 |
P34-4 |
25.4 |
16.0 |
|
||||
327 |
P34-5 |
29.4 |
20.0 |
|
||||
328 |
P34-6 |
39.4 |
30.0 |
|
||||
329 |
P34-7 |
49.4 |
40.0 |
|
||||
330 |
P34-8 |
59.4 |
50.0 |
|
||||
331 |
P34-9 |
69.4 |
60.0 |
|
||||
332 |
P34-10 |
79.4 |
70.0 |
|
||||
333 |
P35a-1 |
Parcel 35 (Planned ASR from 2017 onwards) |
N/A |
13.4 |
4.0 |
7 |
2017 |
See Note (vi) |
334 |
P35a-2 |
17.4 |
8.0 |
|
||||
335 |
P35a-3 |
21.4 |
12.0 |
|
||||
336 |
P35a-4 |
25.4 |
16.0 |
|
||||
337 |
P35a-5 |
29.4 |
20.0 |
|
||||
338 |
P35b-1 |
Parcel 35 (Planned ASR from 2017 onwards) |
|
13.4 |
4.0 |
7 |
2017 |
See Note (vi) |
339 |
P35b-2 |
17.4 |
8.0 |
|
||||
340 |
P35b-3 |
21.4 |
12.0 |
|
||||
341 |
P35b-4 |
25.4 |
16.0 |
|
||||
342 |
P35b-5 |
29.4 |
20.0 |
|
||||
343 |
P35c-1 |
Parcel 35 (Planned ASR from 2017 onwards) |
|
13.4 |
4.0 |
7 |
2017 |
See Note (vi) |
344 |
P35c-2 |
17.4 |
8.0 |
|
||||
345 |
P35c-3 |
21.4 |
12.0 |
|
||||
346 |
P35c-4 |
25.4 |
16.0 |
|
||||
347 |
P35c-5 |
29.4 |
20.0 |
|
||||
348 |
P35d-1 |
Parcel 35 (Planned ASR from 2017 onwards) |
|
13.4 |
4.0 |
7 |
2017 |
See Note (vi) |
349 |
P35d-2 |
17.4 |
8.0 |
|
||||
350 |
P35d-3 |
21.4 |
12.0 |
|
||||
351 |
P35d-4 |
25.4 |
16.0 |
|
||||
352 |
P35d-5 |
29.4 |
20.0 |
|
||||
353 |
P35e-1 |
Parcel 35 (Planned ASR from 2017 onwards) |
|
29.4 |
20.0 |
7 |
2017 |
|
354 |
P36-1 |
Parcel 36 (Planned ASR from 2018 onwards) |
N/A |
11.4 |
4.0 |
15 |
none |
See Note (vi) |
355 |
P36-2 |
15.4 |
8.0 |
|
||||
356 |
P36-3 |
19.4 |
12.0 |
|
||||
357 |
P36-4 |
23.4 |
16.0 |
|
||||
358 |
P36-5 |
27.4 |
20.0 |
|
||||
359 |
P36-6 |
37.4 |
30.0 |
|
||||
360 |
P36-7 |
47.4 |
40.0 |
|
||||
361 |
P36-8 |
57.4 |
50.0 |
|
||||
362 |
P36-9 |
67.4 |
60.0 |
|
||||
363 |
P36-10 |
77.4 |
70.0 |
|
||||
364 |
P37-1 |
Parcel 37 (Planned ASR from 2017 onwards) |
N/A |
11.4 |
4.0 |
15 |
2017 |
See Note (vi) |
365 |
P37-2 |
15.4 |
8.0 |
|
||||
366 |
P37-3 |
19.4 |
12.0 |
|
||||
367 |
P37-4 |
23.4 |
16.0 |
|
||||
368 |
P37-5 |
27.4 |
20.0 |
|
||||
369 |
P37-6 |
37.4 |
30.0 |
|
||||
370 |
P37-7 |
47.4 |
40.0 |
|
||||
371 |
P37-8 |
57.4 |
50.0 |
|
||||
372 |
P37-9 |
67.4 |
60.0 |
|
||||
373 |
P37-10 |
77.4 |
70.0 |
|
||||
374 |
P38-1 |
Parcel 38 Planned Performance Art Venues within WKCD (iv) (Planned ASR from 2017 onwards) |
N/A |
13.4 |
4.0 |
21 |
2017 |
See Note (vi) |
375 |
P38-2 |
17.4 |
8.0 |
|
||||
376 |
P38-3 |
21.4 |
12.0 |
|
||||
377 |
P38-4 |
25.4 |
16.0 |
|
||||
378 |
P38-5 |
29.4 |
20.0 |
|
||||
379 |
P38-6 |
39.4 |
30.0 |
|
||||
380 |
P38-7 |
49.4 |
40.0 |
|
||||
381 |
P38-8 |
59.4 |
50.0 |
|
||||
382 |
P38-9 |
69.4 |
60.0 |
|
||||
383 |
P38-10 |
79.4 |
70.0 |
|
||||
384 |
P39-1 |
Parcel 39 Planned Performance Art Venues within WKCD (iv) (Planned ASR from 2020 onwards) |
N/A |
13.4 |
4.0 |
11 |
none |
See Note (vi) |
385 |
P39-2 |
17.4 |
8.0 |
|
||||
386 |
P39-3 |
21.4 |
12.0 |
|
||||
387 |
P39-4 |
25.4 |
16.0 |
|
||||
388 |
P39-5 |
29.4 |
20.0 |
|
||||
389 |
P39-6 |
39.4 |
30.0 |
|
||||
390 |
P39-7 |
49.4 |
40.0 |
|
||||
391 |
P39-8 |
59.4 |
50.0 |
|
||||
392 |
P39-9 |
69.4 |
60.0 |
|
||||
393 |
P39-10 |
79.4 |
70.0 |
|
||||
394 |
P40a-1 |
Parcel 40 (Planned ASR from 2018 onwards( |
N/A |
13.4 |
4.0 |
6 |
none |
See Note (vi) |
395 |
P40a-2 |
17.4 |
8.0 |
|
||||
396 |
P40a-3 |
21.4 |
12.0 |
|
||||
397 |
P40a-4 |
25.4 |
16.0 |
|
||||
398 |
P40a-5 |
29.4 |
20.0 |
|
||||
399 |
P40a-6 |
39.4 |
30.0 |
|
||||
400 |
P40a-7 |
49.4 |
40.0 |
|
||||
401 |
P40b-1 |
Parcel 40 (Planned ASR from 2018 onwards) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
402 |
P40b-2 |
17.4 |
8.0 |
|
||||
403 |
P40b-3 |
21.4 |
12.0 |
|
||||
404 |
P40b-4 |
25.4 |
16.0 |
|
||||
405 |
P40b-5 |
29.4 |
20.0 |
|
||||
406 |
P40b-6 |
39.4 |
30.0 |
|
||||
407 |
P40b-7 |
49.4 |
40.0 |
|
||||
408 |
P40c-1 |
Parcel 40 (Planned ASR from 2018 onwards) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
409 |
P40c-2 |
17.4 |
8.0 |
|
||||
410 |
P40c-3 |
21.4 |
12.0 |
|
||||
411 |
P40c-4 |
25.4 |
16.0 |
|
||||
412 |
P40c-5 |
29.4 |
20.0 |
|
||||
413 |
P40c-6 |
39.4 |
30.0 |
|
||||
414 |
P40c-7 |
49.4 |
40.0 |
|
||||
415 |
P40d-1 |
Parcel 40 (Planned ASR from 2018 onwards) |
|
13.4 |
4.0 |
6 |
none |
See Note (vi) |
416 |
P40d-2 |
17.4 |
8.0 |
|
||||
417 |
P40d-3 |
21.4 |
12.0 |
|
||||
418 |
P40d-4 |
25.4 |
16.0 |
|
||||
419 |
P40d-5 |
29.4 |
20.0 |
|
||||
420 |
P40d-6 |
39.4 |
30.0 |
|
||||
421 |
P40d-7 |
49.4 |
40.0 |
|
||||
422 |
P40e |
Parcel 40 (Planned ASR from 2018 onwards) |
|
49.4 |
40.0 |
6 |
none |
|
423 |
P41-1 |
Parcel 41 (Planned ASR from 2030 onwards) |
N/A |
13.4 |
4.0 |
1 |
none |
See Note (vi) |
424 |
P41-2 |
17.4 |
8.0 |
|
||||
425 |
P41-3 |
21.4 |
12.0 |
|
||||
426 |
P41-4 |
25.4 |
16.0 |
|
||||
427 |
P41-5 |
29.4 |
20.0 |
|
||||
428 |
P43a-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
N/A |
16.5 |
4.0 |
13 |
none |
See Note (vi) |
429 |
P43a-2 |
20.5 |
8.0 |
|
||||
430 |
P43a-3 |
24.5 |
12.0 |
|
||||
431 |
P43a-4 |
28.5 |
16.0 |
|
||||
432 |
P43b-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
433 |
P43b-2 |
20.5 |
8.0 |
|
||||
434 |
P43b-3 |
24.5 |
12.0 |
|
||||
435 |
P43b-4 |
28.5 |
16.0 |
|
||||
436 |
P43b-5 |
32.5 |
20.0 |
|
||||
437 |
P43c-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
438 |
P43c-2 |
20.5 |
8.0 |
|
||||
439 |
P43c-3 |
24.5 |
12.0 |
|
||||
440 |
P43c-4 |
28.5 |
16.0 |
|
||||
441 |
P43c-5 |
32.5 |
20.0 |
|
||||
442 |
P43d-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
443 |
P43d-2 |
20.5 |
8.0 |
|
||||
444 |
P43d-3 |
24.5 |
12.0 |
|
||||
445 |
P43d-4 |
28.5 |
16.0 |
|
||||
446 |
P43d-5 |
32.5 |
20.0 |
|
||||
447 |
P43d-6 |
42.5 |
30.0 |
|
||||
448 |
P43d-7 |
52.5 |
40.0 |
|
||||
449 |
P43e-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
450 |
P43e-2 |
20.5 |
8.0 |
|
||||
451 |
P43e-3 |
24.5 |
12.0 |
|
||||
452 |
P43e-4 |
28.5 |
16.0 |
|
||||
453 |
P43e-5 |
32.5 |
20.0 |
|
||||
454 |
P43e-6 |
42.5 |
30.0 |
|
||||
455 |
P43e-7 |
52.5 |
40.0 |
|
||||
456 |
P43e-8 |
62.5 |
50.0 |
|
||||
457 |
P43f-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
458 |
P43f-2 |
20.5 |
8.0 |
|
||||
459 |
P43f-3 |
24.5 |
12.0 |
|
||||
460 |
P43f-4 |
28.5 |
16.0 |
|
||||
461 |
P43f-5 |
32.5 |
20.0 |
|
||||
462 |
P43f-6 |
42.5 |
30.0 |
|
||||
463 |
P43f-7 |
52.5 |
40.0 |
|
||||
464 |
P43f-8 |
62.5 |
50.0 |
|
||||
465 |
P43g-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
466 |
P43g-2 |
20.5 |
8.0 |
|
||||
467 |
P43g-3 |
24.5 |
12.0 |
|
||||
468 |
P43g-4 |
28.5 |
16.0 |
|
||||
469 |
P43g-5 |
32.5 |
20.0 |
|
||||
470 |
P43g-6 |
42.5 |
30.0 |
|
||||
471 |
P43g-7 |
52.5 |
40.0 |
|
||||
472 |
P43h-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
473 |
P43h-2 |
20.5 |
8.0 |
|
||||
474 |
P43h-3 |
24.5 |
12.0 |
|
||||
475 |
P43h-4 |
28.5 |
16.0 |
|
||||
476 |
P43h-5 |
32.5 |
20.0 |
|
||||
477 |
P43h-6 |
42.5 |
30.0 |
|
||||
478 |
P43h-7 |
52.5 |
40.0 |
|
||||
479 |
P43i-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
480 |
P43i-2 |
20.5 |
8.0 |
|
||||
481 |
P43i-3 |
24.5 |
12.0 |
|
||||
482 |
P43i-4 |
28.5 |
16.0 |
|
||||
483 |
P43i-5 |
32.5 |
20.0 |
|
||||
484 |
P43i-6 |
42.5 |
30.0 |
|
||||
485 |
P43j-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
486 |
P43j-2 |
20.5 |
8.0 |
|
||||
487 |
P43j-3 |
24.5 |
12.0 |
|
||||
488 |
P43j-4 |
28.5 |
16.0 |
|
||||
489 |
P43j-5 |
32.5 |
20.0 |
|
||||
490 |
P43k-1 |
Parcel 43 (Planned ASR from 2020 onwards) |
|
16.5 |
4.0 |
13 |
none |
See Note (vi) |
491 |
P43k-2 |
20.5 |
8.0 |
|
||||
492 |
P43k-3 |
24.5 |
12.0 |
|
||||
493 |
P43k-4 |
28.5 |
16.0 |
|
||||
499 |
P46a-1 |
Parcel 46 (Planned ASR from 2020 onwards) |
N/A |
16.4 |
4.0 |
5 |
none |
See Note (vi) |
500 |
P46a-2 |
20.4 |
8.0 |
|
||||
501 |
P46a-3 |
24.4 |
12.0 |
|
||||
502 |
P46a-4 |
28.4 |
16.0 |
|
||||
503 |
P46a-5 |
32.4 |
20.0 |
|
||||
504 |
P46a-6 |
42.4 |
30.0 |
|
||||
505 |
P46b-1 |
Parcel 46 (Planned ASR from 2020 onwards) |
|
16.4 |
4.0 |
5 |
none |
See Note (vi) |
506 |
P46b-2 |
20.4 |
8.0 |
|
||||
507 |
P46b-3 |
24.4 |
12.0 |
|
||||
508 |
P46b-4 |
28.4 |
16.0 |
|
||||
509 |
P46b-5 |
32.4 |
20.0 |
|
||||
510 |
P45b-6 |
42.4 |
30.0 |
|
||||
511 |
P46c-1 |
Parcel 46 (Planned ASR from 2020 onwards) |
|
16.4 |
4.0 |
5 |
none |
See Note (vi) |
512 |
P46c-2 |
20.4 |
8.0 |
|
||||
513 |
P46c-3 |
24.4 |
12.0 |
|
||||
514 |
P46c-4 |
28.4 |
16.0 |
|
||||
515 |
P46c-5 |
32.4 |
20.0 |
|
||||
516 |
P45c-6 |
42.4 |
30.0 |
|
||||
517 |
P46d-1 |
Parcel 46 (Planned ASR from 2020 onwards) |
|
16.4 |
4.0 |
5 |
none |
See Note (vi) |
518 |
P46d-2 |
20.4 |
8.0 |
|
||||
519 |
P46d-3 |
24.4 |
12.0 |
|
||||
520 |
P46d-4 |
28.4 |
16.0 |
|
||||
521 |
P46d-5 |
32.4 |
20.0 |
|
||||
522 |
P46d-6 |
42.4 |
30.0 |
|
||||
523 |
P46e-1 |
Parcel 46 (Planned ASR from 2020 onwards) |
|
42.4 |
30.0 |
5 |
none |
|
524 |
P50-1 |
Parcel 50 (Planned ASR from 2020 onwards) |
N/A |
9.0 |
4.0 |
NA |
none |
See Note (vi) |
525 |
P50-2 |
13.0 |
8.0 |
|
||||
526 |
P50-3 |
17.0 |
12.0 |
|
||||
527 |
P50-4 |
21.0 |
16.0 |
|
||||
528 |
P50-5 |
25.0 |
20.0 |
|
||||
529 |
P51-1 |
Parcel 51 (Planned ASR from 2016 onwards) |
N/A |
9.0 |
4.0 |
NA |
2016 – 2017 |
See Note (vi) |
530 |
P51-2 |
13.0 |
8.0 |
|
||||
531 |
P51-3 |
17.0 |
12.0 |
|
||||
532 |
P51-4 |
21.0 |
16.0 |
|
||||
533 |
P51-5 |
25.0 |
20.0 |
|
||||
534 |
P52-1 |
Parcel 52 (Planned ASR from 2016 onwards) |
N/A |
9.0 |
4.0 |
2 |
2016 – 2017 |
See Note (vi) |
535 |
P52-2 |
13.0 |
8.0 |
|
||||
536 |
P52-3 |
17.0 |
12.0 |
|
||||
537 |
P52-4 |
21.0 |
16.0 |
|
||||
538 |
P52-5 |
25.0 |
20.0 |
|
||||
539 |
P53-1 |
Parcel 53 (Planned ASR from 2014 onwards) |
N/A |
9.0 |
4.0 |
2 |
2014 – 2017 |
See Note (vi) |
540 |
P53-2 |
13.0 |
8.0 |
|
||||
541 |
P53-3 |
17.0 |
12.0 |
|
||||
542 |
P53-4 |
21.0 |
16.0 |
|
||||
543 |
P53-5 |
25.0 |
20.0 |
|
||||
544 |
OP |
Open space (Planned ASR from 2017 onwards) |
N/A |
6.5 |
1.5 |
0 |
2017 |
|
Notes (i) Estimated locations of the fresh air takes of these developments are
taken as the ASRs.
(ii) The locations and no. of storeys of the planned ASRs representing the topside development at West Kowloon Terminus
(WKT) Site A are based on the approved
(iii) According
to the approved
(iv) The planned ASRs represent the indicative fresh air
intake locations of these planned developments.
(v) Selected assessment height
is the indicative location of fresh air intake at podium level.
(vi)
The planned ASR at 4m above ground level are assessment points for
reference only, but are not fresh air intake or openable window locations.
15.3.3 Identification of Pollution Sources
15.3.3.1 Background Air Quality
The flyover road is located on the
With reference to EPD’s Air Quality Annual Report, the EPD’s general air quality monitoring stations in urban areas that can be considered as an indication of the background concentration include Central/Western, Kwun Tong, Sham Shui Po, Tsuen Wan and Kwai Chung. The average TSP concentration of all these five monitoring stations is detailed in Table.15.3.4.
Table.15.3.4 Average
Background TSP Air Pollutant Concentrations (Year 2007-2011)
Urban Stations |
Annual Average TSP Concentration (μg/m3) |
TSP Background Concentration (μg/m3) |
||||
2007 |
2008 |
2009 |
2010 |
2011 |
||
Tsuen Wan |
79 |
67 |
63 |
63 |
69 |
68.2 |
Kwai Chung |
85 |
79 |
70 |
71 |
71 |
75.2 |
Sham Shui Po |
79 |
81 |
77 |
76 |
79 |
78.4 |
Kwun Tong |
82 |
72 |
70 |
67 |
74 |
73.0 |
Central/Western |
77 |
78 |
73 |
76 |
78 |
76.4 |
|
|
|
|
|
Average |
74.2 |
Note: Monitoring results that exceeded AQO are shown
in bold characters.
Dust monitoring has been undertaken in the vicinity of the proposed West Kowloon Terminus (WKT) from March 2010 to December 2012 inclusive as part of the environmental monitoring and audit (EM&A) works for XRL project. The air monitoring stations considered to be most relevant to WKCD area are AM16 and AM17, as both stations are in close proximity to the WKCD site (see Figure 3.2). The annual average TSP concentration during that construction period of WKT has been calculated, as shown in Table 15.3.5 (see Appendix 3.27 for details).
Table 15.3.5: Air Quality Monitoring Results for Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail Link relevant to WKCD (March 2010 – December 2012)
Monitoring Station |
Location |
Annual Average TSP Concentration (μg/m3) |
3-year Average Concentration (μg/m3) |
||
|
2010(1) |
2011 |
2012 |
||
AM16 |
Tower
3, The Waterfront |
74.2 |
73.4 |
54.3 |
67.1 |
AM17 |
The
Victoria Towers |
74.7 |
79.3 |
55.5 |
69.7 |
|
|
|
|
Average
|
68.4 |
Note: (1) Monitoring
results from March 2010 to December 2010.
As the air quality monitoring stations AM16
and AM17 border the XRL site boundary, it is reasonable to assume that the
average TSP concentration of these two stations can represent XRL
generated dust concentrations plus
prevailing background dust concentrations at the WKCD area. While the 5‑year
average TSP concentration in urban
areas as obtained from EPD’s urban air quality monitoring stations (74.2
µg/m3 from Table.15.3.4)
is comparable to that from the XRL data (68.4 µg/m3 from Table
15.3.5),
it is considered that using the XRL monitoring data is a
more reasonable estimate for the WKCD area TSP assessment. This is because there is a sufficient amount
of XRL data (about 3 years’ data) and the XRL monitoring stations are in close
proximity to the WKCD site whereas the EPD’s monitoring stations are at much
larger distances (1.91 km to 8.65 km) from the site.
Operational air quality contaminants of significance to the Project area include: SO2, from marine; NO2, from vehicles and marine; RSP, from vehicles and marine. The 5-year average concentrations for these pollutants are detailed in Table 15.3.6.
Table
15.3.6: Average Background Air Pollutant
Concentrations from EPD’s Urban Air Monitoring Stations (Year 2007-2011)
Pollutant |
Urban Stations and 5-year Average Concentration (μg/m3) |
AQO criteria (μg/m3) |
5-year Average Concentration (μg/m3) |
||||
Tsuen Wan |
Kwai Chung |
Sham Shui Po |
Kwun Tong |
Central/ Western |
|||
Sulfur Dioxide (SO2) |
19.8 |
24.4 |
17.4 |
13.8 |
17.6 |
80 |
18.6 |
Nitrogen Dioxide (NO2) |
63.2 |
64.6 |
68.4 |
60.4 |
52.8 |
80 |
61.9 |
Respirable Suspended Particulate (RSP/PM10) |
51.2 |
50.4 |
51.2 |
48.8 |
49.6 |
55 |
50.2 |
In addition to the urban air quality
monitoring stations, EPD had operated a local air quality monitoring station at
the WKCD site to record background air pollutant concentrations from September
2011 to August 2012. Although the monitoring data is only for a single year,
the recorded
Table
15.3.7: Average Background Air Pollutant
Concentrations from EPD’s Local Monitoring Station at WKCD Site (September 2011
– August 2012)
Pollutant |
Annual Average Concentration (μg/m3) |
AQO criteria (μg/m3) |
Sulfur Dioxide (SO2) |
11.4 |
80 |
Nitrogen Dioxide (NO2) |
46.7 |
80 |
Respirable Suspended Particulate (RSP/PM10) |
45.0 |
55 |
By comparing the EPD’s onsite monitoring results at WKCD with the 5-year average from
the urban monitoring stations, it can be seen that the onsite monitoring
results are significantly lower – approximately 39% lower for SO2,
25% lower for NO2, and 10% lower for RSP.
The future background air pollutant concentrations
to be used for predicting the total air quality impact due to operational phase
for NO2 RSP and SO2 are as extracted from the PATH model
(for year 2015) released by EPD in December 2012.
15.3.3.2 Construction Phase
Construction
of the WKCD basement will be carried out in zones, with construction of Zone 1
aimed at commencement in 2013 for completion of Zones 1 to 3 in 2017 (see Appendix 2.4 for the assumed construction
programme). During construction, the major activities that would
generate construction dust emissions include the following:
¡ Excavation activities;
¡ Foundation works;
¡ Concrete batching plant and barging points (assumed to be handed over from the XRL project to WKCD);
¡ Site Formation, and;
¡ Movement of mobile plant and vehicles on haul roads.
Based on a review of
the construction methods adopted for the WKCD Project, construction dust will
be potentially generated from the aforementioned land-based construction
activities and is therefore identified as the representative pollutants. Therefore,
it is considered appropriate to adopt total suspended particulate (TSP) as the key pollutant during the construction
phase. According to the “2011 Hong Kong
Emission Inventory Report” published by EPD[1] in March 2013, which is the latest available
Due to construction of concurrent projects in the vicinity, cumulative impacts are expected. Table 15.3.8 summarises the concurrent projects that may contribute to cumulative construction dust impacts.
Table 15.3.8: Summary of concurrent projects during construction phase
Project |
Construction Period |
Possible Cumulative Impact |
Included in Cumulative Impact Assessment |
Hong Kong Section of the |
Jan 2010 – 2015 |
Dust emissions from construction of the West Kowloon Terminus and operation of the concrete batching plant and barging points |
Yes |
Road Works at |
2011 – 2014 |
According to the |
No |
Road Improvement Works in |
Late 2013 / early 2014 – end 2015 |
Dust emissions from the roadworks construction and movement of mobile plant and vehicles |
Yes |
Central |
2015 – end 2020 |
Dust emissions from construction works |
Yes |
As an updated schedule of construction works for the WKT of the XRL project is not available for 2013-2015, it is not possible to incorporate realistic dust emission sources of WKT into the FDM model for assessment of cumulative impacts. As such, relevant EM&A monitoring data of the XRL project is used to assess the potential cumulative impacts as described below.
With reference to the dust monitoring results from the two air quality monitoring stations (AM16 and AM17) in the vicinity of the WKCD site from March 2010 to December 2012 inclusive, the average TSP concentration during that construction period of WKT has been calculated, as shown in Appendix 3.27. It is reasonable to assume that the average TSP concentration from these two dust monitoring stations can represent XRL generated dust concentrations plus prevailing background dust concentrations at the WKCD area. The background concentration used for the TSP assessment for the flyover road is therefore taken as 68.4 µg/m3 (Table 15.3.5).
For the Central Kowloon Route (CKR) project,
its construction dust impact assessment area overlaps part of the corresponding
assessment area for the flyover road.
Therefore, the relevant TSP modelling results from the published
15.3.3.3 Operation Phase – Vehicular Emissions
During the operation phase, there will be cumulative air quality impacts on the ASRs due to vehicular emissions from:
¡ Existing and proposed open roads outside the flyover road area but within the 500 m assessment area;
¡ Proposed underpasses/landscape decks along the Austin Road West and Lin Cheung Road and the associated top openings under the Road Works at West Kowloon project, which is within the 500 m assessment area; and
¡ Portal of the existing Western Harbour Crossing (WHC) which is in the vicinity of the flyover road site.
¡ Ventilation exhausts and portals serving the planned underground roads within the WKCD area.
It should be noted that all of the above
vehicular emission sources, except the planned underground roads within WKCD,
are due to the current and planned road networks serving the
The air quality inside the WKCD basement where the underground vehicle roads are located should meet the air pollutant standards as recommended by the EPD’s Practice Note on Control of Air Pollution in Vehicle Tunnels (see Table 15.3.2).. Therefore, the basement ventilation system should be properly designed by WKCDA’s consultant/engineer to adequately remove or dilute vehicle emissions and the basement air quality should be monitored to ensure compliance with the relevant air quality standards.
15.3.3.4 Operation Phase – Marine Traffic Emissions
There are existing marine activities within the 500 m assessment area that will contribute to the background emissions, which include:
¡ Fast ferry traffic movements, based on scheduled sailings, of up to 170 daily movements (ferry going to is one movement, ferry leaving is a second movement) at the China Ferry Terminal;
¡ Tugs associated with Derrick lighter barge movements in the NYMTTS;
¡ Derrick lighter barges operating at the New Yau Ma Tei Public Cargo Working Area (NYPCWA), and;
¡ Ocean Cruise Ship berthing at the Ocean Terminal.
Although emissions from all the above
current marine activities are not attributable to the flyover road development,
the WKCD development would be subject to potential air quality impacts caused
by such marine emissions.
Under
the current development of marine traffic planning at the WKCD site, it is
intended that marine services at WKCD will primarily be provided for visitor or
leisure activities. In terms of traffic volume, the support on the need of the possible
piers has been a key outcome from the public consultation in view of general
public's opinions and needs. No precedence case or similar scale of development
as the WKCD has been developed in the
15.3.3.5 Operation Phase – Industrial Emissions
Chimney survey and desktop study have been conducted to identify any existing or planned chimneys of industrial operations within the 500m assessment area. Based on the survey and desktop study findings, no existing or planned chimneys were identified within the assessment area.
15.3.3.6 Operation Phase – Identification of Key Air Pollutants of Concern
As presented in Section 15.3.1.2, under the APCO, AQOs are stipulated for seven criteria air pollutants, namely, nitrogen
dioxide (NO2), sulphur dioxide (SO2), total suspended
particulates (TSP), respirable suspended particulates (RSP), carbon monoxide (CO),
ozone and lead. As identified in Sections 15.3.3.3 and 15.3.3.4,
during the operation phase, the existing/planned ASRs within 500m assessment would
be subject to potential air quality impacts due to emissions from the flyover and the nearby road traffic as well as the surrounding marine
traffic/vessels. Each of the seven
criteria pollutants has been reviewed for its relevance to such major air
pollution sources of the Project as follows.
Nitrogen Dioxide (NO2)
According to the “2011 Hong Kong Emission Inventory Report” published by EPD in March 2013, navigation and road transport
are the top two major sources of nitrogen
oxides (NOx) generated in
Respirable Suspended Particulates
(RSP)
According to the latest statistics
of “2011 Hong Kong Emission Inventory Report”, navigation and road transport are the top two major sources of RSP in
According to the latest statistics
of “2011 Hong Kong Emission Inventory Report”, 54% of total SO2 emission in
Ozone
According to the “Air
Quality in Hong Kong 2011” published by EPD[2], ozone is a
major constituent of photochemical smog. It is not a pollutant directly emitted from
man-made sources but formed by photochemical reactions of primary pollutants such
as NOx and volatile organic compounds (VOCs) under sunlight. As
it takes several hours for these photochemical reactions to take place, ozone recorded in
one place could be attributed to VOC and NOx emissions from places afar. Hence, ozone
is a regional air pollution problem. In
other words, unlike such air pollutants as NOx,,RSP and SO2, ozone is not a pollutant directly attributable to
emissions from nearby marine or road traffic.
As a result, ozone is not identified as a key air pollutant for air quality
impact assessment for this Project, though it is one of the criteria pollutants
under the AQO.
Carbon Monoxide (CO)
According to the latest statistics of “2011 Hong Kong Emission
Inventory Report”, road transport and navigation are the top two major
sources of CO emissions in
Lead
Since leaded petrol was banned in Hong Kong on 1 April 1999, it is
no longer considered as a primary source in
Identified Key Air Pollutants
Based on the above review results, the
following key air pollutants of concerns are identified for the purpose of air
quality impact assessment during the operation phase:
· For road traffic emissions – NO2 and RSP; and
· For marine traffic/vessel emissions – SO2, NO2 and RSP.
15.3.4 Assessment Methodology
Introduction
To assess the construction phase through air quality modelling, use of the air quality model Fugitive Dust Model (FDM) was required. In accordance with the EPD’s Guidelines on Choice of Models and Model Parameters, FDM was used to predict the air pollutant concentrations due to fugitive and open dust source impacts, which are shown in Figures 3.3a-h and 3.4a-e. Details of the emission rates from the activities are given in Appendices 3.1 to 3.3.
Model Description – FDM
FDM is a computerised air quality model
specifically designed for computing the concentration and deposition impacts
from fugitive dust sources. The model is generally based on the well-known
Gaussian Plume formulation for computing concentrations, but the model has been
specifically adapted to incorporate an improved gradient transfer deposition
algorithm. FDM is one of the air quality models listed as commonly used for
It should be
noted that FDM and all Gaussian based dispersion models have limited ability to
predict dispersion in the following situations:[4]
¡ Causality effects
Gaussian plume models assume pollutant material is transported in a straight line instantly (like a beam of light) to receptors that may be several hours or more in transport time away from the source. The model takes no account for the fact that the wind may only be blowing at 1 m/s and will have only travelled 3.6 km in the first hour. This means that Gaussian models cannot account for causality effects, where the plume may meander across the terrain as the wind speed or direction changes. This effect is not considered to be significant for the WKCD site as the site is small.
¡ Low wind speeds
Gaussian-plume models ‘break down’ during low wind speed or calm conditions due to the inverse speed dependence of the steady state plume equation. These models usually set a minimum wind speed of 0.5 m/s or 1.0 m/s and ignore or overwrite data below this limit.
¡ Straight-line trajectories
Gaussian models will typically overestimate terrain impingement effects during stable conditions because they do not account for turning or rising wind caused by the terrain itself. This effect is not considered to be important for WKCD as the site and surrounding terrain is flat.
¡ Spatially uniform meteorological conditions
Gaussian models assume that the atmosphere is uniform across the entire modelling domain, and that transport and dispersion conditions exist unchanged long enough for the material to reach the receptor even if this is several kilometres away. In the atmosphere, truly uniform conditions rarely occur. As the WKCD site and surrounding assessment area is sufficiently small with no significant terrain features, uniform meteorological conditions are considered appropriate.
¡ No memory of previous hour’s emissions
In calculating each hour’s ground-level concentrations, Gaussian models have no memory of the contaminants released during the previous hours. This limitation is especially important for the proper simulation of morning inversion break-up, fumigation and diurnal recycling of pollutants.
Assumptions and Inputs – FDM
During
the construction stage, the study area will not have many tall buildings. As
such, the "Guideline on Air Quality
model (revised), EPA - 450/2-78-027R, July 1986" is used to calculate
the roughness length for use in FDM.
The
EPD guideline on "Choice of Models
and Model Parameters" states: the selection of rural or urban
dispersion coefficients in a specific application should follow a land use
classification procedure. If the land use types including industrial,
commercial and residential uses account for 50% or more of an area within a
3 km radius from the source, the site is classified as urban; otherwise it
is classified as rural. The surface roughness height is closely related to the
land use characteristics of a study area and associated with the roughness
element height. As a first approximation, the surface roughness can be
estimated as 3 to 10 percent of the average height of physical structures.
Typical values used for urban and new development areas are 370 cm and 100 cm,
respectively.
Within a three kilometre radius of the site 55% is classified as urban and the remaining 45% is sea. As the sea roughness is typically given a value of 0.01 cm and urban is assumed to be 370 cm, an area averaged roughness height of 205 cm is used. This is to take account of the low turbulence over the sea water, and also the very large turbulence generated due to nearby large structures.
Hourly meteorological data for a full year as extracted from PATH model released by EPD in December 2012 (metrological data year 2010, grid 28, 27) has been adopted for use in FDM and is considered to be the most up to date data available. PATH data has been observed to have a lower mixing height for some hours, when compared to the measured mixing height. The minimum mixing height recorded by HKO in 2010 is 121.3 m, whereas the PATH minimum mixing height is 40 m. The HKO minimum mixing height of 121.3 m is used to replace any PATH mixing height below this value. This approach is considered appropriate as it will minimise over-estimation due to lower mixing heights and also will minimise under-estimation due to high stacks being excluded in the mixing volume. The PATH data with the above modification is considered to be representative of the site wind data at the flyover road site.
Prediction of dust emissions is
based on emissions factors from the Compilation of Air Pollution Emission
Factors (AP-42), 5th Edition published by the US Environmental
Protection Agency (USEPA). The emission factor for a typical heavy construction
activity is 2.69 megagrams (Mg)/hectare/month according to Section 13.2.3.3 of AP-42.
The number of working days for a month and number of working hours per day of
the project are anticipated to be 26 days and 12
hours respectively. No construction work is anticipated to be carried out on
Sundays. Based on Table 11.9-4 of AP-42, the emission factor of wind
erosion is 0.85 megagrams (Mg)/hectare/year. The
locations of assumed dust sources are given in Figures 3.3a to 3.3h.
The key dust emission factors adopted in FDM are summarised in Table
15.3.9.
For the mitigated
scenario, the active construction areas have ground watering applied once per
hour or 12 times per day. This gives rise to dust suppression of 91.7%, as
estimated in Appendix 3.8. The
unmitigated scenario does not employ any watering for dust suppression.
For the concrete
batching plant, it is assumed that the plant will be handed over from the XRL
project to the WKCD (including flyover road) Project, and therefore the
emissions from the plant will be the same as those given in the approved
No stockpile is modelled as excavated material is anticipated to
be transported out of the site immediately after generation. Barging points are
assumed to be handed over from the XRL project to the WKCD Project, and
therefore the emissions from the plant will be the same as those given in the
approved
The emission inventory and calculation of emission factors for the
construction activities are detailed in Appendices 3.1 to 3.3.
Table
15.3.9: Key Dust Emission Factors Adopted in the Assessment
Activities |
Emission Factors |
Reference |
Heavy construction activities including all above ground and open construction works, excavation and slope cutting works |
2.69 Mg/hectare/month |
Section 13.2.3.3 AP-42, 5th Edition |
Wind erosion from heavy construction |
0.85 Mg/hectare/year |
Table 11.9-4 AP-42, 5th Edition |
Paved haul road within concrete batching plant |
Emission Factor = k x (sL) 0.91 x (W) 1.02 g/VKT where k is particle size multiplier * sL is road surface silt loading W is average truck weight |
Section 13.2.1 AP-42, 5th Edition (Jan 2011 edition) |
* The particle size distribution was made reference to
Section 13.2.1(Table 13.2.1-1) of the USEPA Compilation of Air Pollution
Emission Factors (AP-42), 5th Edition (Jan 2011 edition).
With addition of the average background TSP concentration of five urban monitoring stations as described in Section 15.3.3.1, i.e., 68.4 μg/m3, the hourly, daily and annual TSP concentrations at the identified ASRs have been predicted and compared with the hourly, daily and annual average TSP criteria of 500 µg/m3, 260 µg/m3 and 80 µg/m3 respectively.
Methodology – FDM
Construction
of the flyover road is to be completed in stages; as such the FDM assessment
has been completed for each construction year from 2013 to 2017, when the
majority of the site works are expected to be completed.
For hourly and daily TSP, a tiered modelling
approach has been adopted. Tier 1 assumes 100% active area for
a given year is emitting TSP. This Tier 1 scenario (i.e. assuming 100%
active area for the Project and the concurrent project) is hypothetical and for
screening purposes to identify which ASRs may be subject to TSP
concentrations above the relevant standards. For
the purpose of the Tier 1 screening, the dust mitigation measures, including
frequent water spraying, are taken into account when estimating the dust
emission rates from the construction activities. Details of the Tier 1 dust
sources including their coordinates, dimensions and estimated emission rates
are detailed in Appendix 3.4.
Locations of the assumed dust sources for Tier 1 assessment are shown in Figure 3.3a to 3.3k.
The Tier 1 hourly and daily TSP levels at all the ASRs are then predicted for
both scenarios of with and without the dust mitigation measures in place.
The ASRs identified with hourly or daily TSP non-compliance under Tier 1 screening, where mitigation measures are in place, are selected for the subsequent Tier 2 assessment.
The
entire works area is broken into a number of zones for construction timetabling
purposes. Based on the assumed construction plant inventory of individual zones
and planned construction activities for each year, the percentage active areas
for different zones are calculated, as summarised in Table 15.3.10.
The maximum percentage active area for each year is taken from all zones and
applied to the entire site.
It is
assumed in the Tier 2 assessment that the maximum percentage active area of the
flyover road excavation site for each zone and the corresponding active areas
of the relevant concurrent project would be located closest to the ASR being
assessed. The Tier 2 hourly or daily TSP levels at each of these ASRs are then
predicted with the dust mitigation measures in place.
Under
normal circumstances, construction activities for the proposed Project and the
concurrent projects would likely spread over the whole work sites and zones. As
such, the maximum percentage active area calculated from all zones, applied to
the entire WKCD site, and the corresponding active areas of the relevant
concurrent project to be located closest to a particular ASR at any one time
during the Tier 2 assessment is a conservative approach. Details of the
Tier 2 dust sources including their coordinates, dimensions and estimated
emission rates are given in Appendix
3.5. Locations
of the assumed dust sources
for Tier 2 assessment are shown in Figures 3.4a to 3.4f.
For the assessment
of annual TSP concentrations, the active work area over the entire year would
be less than that for a typical working hour or a typical working day. The
percentage active area averaged over each construction year has been estimated
for each zone as summarised in Table 15.3.10. The annual
TSP assessment is based on the percentage active areas for individual zones.
The annual TSP levels are predicted at all the ASRs for both scenarios of with and
without the dust mitigation measures in place. Details of the dust sources for
annual TSP assessment including their coordinates, dimensions and estimated
emission rates are given in Appendix 3.6. Locations
of assumed dust sources for annual assessment are shown in Figure 3.3a to 3.3k.
Based on
project-specific
Table 15.3.10: Summary of tentative active area calculations for Tier 2 and Annual TSP assessment
Construction Year |
Zone |
Percentage Active Area |
||
Hourly |
Daily |
Annually |
||
2013 |
1 |
47.1% |
47.1% |
18.4% |
|
2a |
0.0% |
0.0% |
0.0% |
|
2b |
17.8% |
17.8% |
6.1% |
|
3 |
21.1% |
21.1% |
3.5% |
|
4 |
0.0% |
0.0% |
0.0% |
|
5 |
0.0% |
0.0% |
0.0% |
|
The Park (A, B, C) |
1.4% |
1.4% |
0.8% |
|
Maximum |
47.1% |
47.1% |
18.4% |
2014 |
1 |
3.7% |
3.7% |
1.3% |
|
2a |
66.1% |
66.1% |
44.6% |
|
2b |
13.4% |
13.4% |
9.0% |
|
3 |
16.1% |
16.1% |
9.6% |
|
4 |
0.0% |
0.0% |
0.0% |
|
5 |
0.0% |
0.0% |
0.0% |
|
The Park (A, B, C) |
9.9% |
9.9% |
9.9% |
|
Maximum |
66.1% |
66.1% |
44.6% |
2015 |
1 |
0.9% |
0.9% |
0.8% |
|
2a |
6.5% |
6.5% |
5.7% |
|
2b |
4.5% |
4.5% |
3.9% |
|
3 |
5.1% |
5.1% |
2.2% |
|
4 |
0.0% |
0.0% |
0.0% |
|
5 |
0.0% |
0.0% |
0.0% |
|
The Park (A, B, C) |
0.3% |
0.3% |
0.3% |
|
Maximum |
6.5% |
6.5% |
5.7% |
2016 |
1 |
0.6% |
0.6% |
0.6% |
|
2a |
1.3% |
1.3% |
0.7% |
|
2b |
0.6% |
0.6% |
0.3% |
|
3 |
0.2% |
0.2% |
0.2% |
|
4 |
22.9% |
22.9% |
16.7% |
|
5 |
0.0% |
0.0% |
0.0% |
|
The Park (A, B, C) |
0.5% |
0.5% |
0.5% |
|
Maximum |
22.9% |
22.9% |
16.7% |
2017 |
1 |
0.0% |
0.0% |
0.0% |
|
2a |
3.2% |
3.2% |
3.2% |
|
2b |
0.7% |
0.7% |
0.7% |
|
3 |
0.2% |
0.2% |
0.2% |
|
4 |
13.0% |
13.0% |
3.7% |
|
5 |
3.1% |
3.1% |
1.8% |
|
The Park (A, B, C) |
2.4% |
2.4% |
1.6% |
|
Maximum |
13.0% |
13.0% |
3.7% |
Note: (a) The Tier 2 assessment for hourly and daily TSP uses the maximum percentage active area for all zones.
(b) The assessment of annual TSP uses zone specific percentage active area.
15.3.4.2 Operation Phase – Vehicular Emissions
Introduction
To assess the operational air quality, a
variety of models were required. In accordance with the EPD’s
Guidelines on Choice of Models and Model
Parameters, the
following air dispersion models have been employed to predict the cumulative NO2
and RSP levels at the identified ASRs:
¡ EMFAC-HK V2.5.1 (I and M) model has been used to determine the fleet average emission factors, for all the planned and existing roads within the 500 m assessment area, including planned flyover roads within WKCD site, and the proposed Central Kowloon Route (CKR). The model has included the effect of Inspection and Maintenance (I/M) program and is applicable for calendar years between 2013 and 2040.
¡ CALINE4 has been used to predict the air pollutant concentrations due to vehicular emissions from all open road links within the 500 m assessment area, which are as shown in Figures 3.5.1a to 3.5.1y.
¡ ISCST3 has been used to predict the air pollutant concentrations due to vehicular emissions from the Western Harbour Crossing (WHC) portal (modelled as volume sources); the proposed underpasses/landscape deck portals (modelled as volume sources) and the associated top openings (modelled as area source) under the Road Works at West Kowloon project; as well as from the assumed ventilation serving the planned underground roads within the WKCD site (modelled as volume or point sources). The locations of all such pollution sources are as shown in Figure 3.6.
¡ Pollutants in the Atmosphere and the Transport over Hong Kong
(PATH) has been used to predict the current background air pollution due to
sources outside the project boundary. Sources include, but are not limited to,
the Pearl River Deltas Economic Zone (PRDEZ), the
The localised impacts due to the vehicle
emissions within the 500 m assessment area of flyover road have been
separately modelled by the near-field models (CALINE4 and ISCST3) in which the
vehicular emission factors have been calculated from the EMFAC-HKV2.5.1 model.
The cumulative hourly maximum NOx
and RSP concentrations are predicted by the above models by using the
corresponding MM5 hourly meteorological data in 2010 as extracted from the PATH
model released by EPD in December 2012.
Model Description
– EMFAC-HKV2.5.1
EMFAC-HKV2.5.1
is an emissions inventory model that calculates emissions inventories for motor
vehicles operating on roads in
Assumptions and
Inputs – EMFAC-HK
For all the planned and existing roads
within the 500 m assessment
area including those planned underpass roads within WKCD site and the proposed
CKR, the EMFAC-HK V2.5.1 model (I and M), which is the latest version
at the time of preparing this report, has been used to determine the fleet
average emission factors.
The Burden mode, used for calculating area-specific
emission factors, has been selected in the model. Under this mode, the total
emissions of pollutants such as RSP and NOx were computed for each
type of vehicle class based on temperature, relative humidity, speed corrected
emission factors and vehicle activity. Hourly output was selected.
The
assumptions and input parameters on modelling of vehicle emission factors
are presented in the following sections. The traffic data used for the assessment
includes the hourly traffic flows of 16 vehicle classes at various road links
and the speed fractions of various vehicle classes in four model years. The model years are: 2015 (the year when operation
of the Project was originally planned to commence); intermediate years 2020 and
2025, and 2030 (15 years after commencement of operation of the Project). According to the recently updated Project
programme (see Appendix 2.4), the planned commencement of
operation of the Project has been changed to 2017. Despite the change, the EMFAC results as
presented in Graph 15.2 show that year 2015 represents the worst case
scenario where the total traffic emission is the highest among all model years
of 2015, 2020, 2025 and 2030. In other
words, the total traffic emission in year 2017 when the Project is planned to
commence operation is anticipated to be lower than that in year 2015. Therefore,
use of the emission estimates in 2015 for air quality impact assessment is a
conservative approach.
Traffic data is provided by the Traffic Consultant,
and are presented in the following sections.
The traffic forecast data has been submitted
to the Transport
Department (TD) for review. TD has no objection in principle to the traffic
data. The correspondence from TD is provided in Appendix 3.9 for reference. The
24-hour traffic patterns are given in Appendix 3.10.
Vehicle Emission
Standards
The emission standards, according to the latest
implementation programme (as of November 2012) have been adopted in EMFAC-HK
V2.5.1 model for vehicles registered in Hong Kong. In this model, the latest
European Union (EU) emission standard, Euro VI, for all vehicle classes can be
applied, with the exception of motorcycles which do not have applicable new EU
emission standards.
Road Grouping
The road links for assessment have been grouped
into five types. Emission factors for the following
five road types have been calculated:
¡ Road Type 1 - Expressway (Design speed limit: 100kph);
¡ Road Type
¡ Road Type
¡ Road Type 4 - Local Roads (Design speed limit: 50kph), and;
¡ Road Type
The
five road types are characterised by continuous and interrupted flow with
different design speed limits. It is assumed that there is continuous traffic
flow in Expressway and Trunk Roads (Road Types 1, 2, 3 & 5), whereas there
is interrupted flow in Local Roads (Road Type 4). The road type classification of
individual road links in the assessment
area are
as shown in Figures
3.5.1a to 3.5.1y. Road Type 5 is associated with the CKR and
will not be present in 2015 or 2020, but will be present in 2025 and 2030, as
CKR is anticipated to be in operation in 2021.
Vehicle Classes
Vehicles operating on open roads have been
categorised into 16 vehicle classes according to the Guideline on Modelling Vehicle Emission – Appendix I for EMFAC-HK
V2.5.1, and is presented in Table 15.3.11.
Table 15.3.11: Vehicle Classification in the EMFAC-HK Model
Index |
Description |
Notation in EMFAC-HK Model |
Fuel Type |
Gross Vehicle Weight |
1 |
Private Cars (PC) |
PC |
ALL |
ALL |
3 |
Taxi |
taxi |
ALL |
ALL |
4 |
Light Goods Vehicles (<=2.5t) |
LGV3 |
ALL |
<=2.5ton |
5 |
Light Goods Vehicles (2.5-3.5t) |
LGV4 |
ALL |
>2.5-3.5ton |
6 |
Light Goods Vehicles (3.5-5.5t) |
LGV6 |
ALL |
>3.5ton |
7 |
Medium & Heavy Goods Vehicles (5.5-15t) |
HGV7 |
ALL |
>5.5ton-15ton |
8 |
Medium & Heavy Goods Vehicles (>=15t) |
HGV8 |
ALL |
>15ton |
11 |
Public Light Buses |
PLB |
ALL |
ALL |
12 |
Private Light Buses (<=3.5t) |
PV4 |
ALL |
<=3.5ton |
13 |
Private Light Buses (>3.5t) |
PV5 |
ALL |
>3.5ton |
14 |
Non-franchised Buses (<6.4t) |
NFB6 |
ALL |
<=6.4ton |
15 |
Non-franchised Buses (6.4-15t) |
NFB7 |
ALL |
>6.4ton – 15ton |
16 |
Non-franchised Buses (>15t) |
NFB8 |
ALL |
<=15ton |
17 |
Single Deck Franchised Buses |
FBSD |
ALL |
ALL |
18 |
Double Deck Franchised Buses |
FBDD |
ALL |
ALL |
19 |
Motor Cycles |
MC |
ALL |
ALL |
Exhaust /
Evaporation Technology Fraction
Vehicle classes are grouped with
different exhaust technology indexes and technology fractions. Each technology
group represent a distinct emission control technologies. The EMFAC-HK V2.5.1 model has a set of default
exhaust technology fractions which best represents the scheduled implementation
of new vehicle emission standards as of November 2012. As there is no update to
the planned emission control measures since the release of the guideline in
November 2012, the default exhaust technology fractions are considered to be
applicable in this assessment.
Vehicle
Population
According to the Guideline on Modelling Vehicle Emissions, the vehicle population forecast function in
EMFAC-HKV2.5.1 used 2010 as the base year. Natural replacement of vehicles and
a set of annual growth rates and survival rates for different vehicles are
assumed for 2011 to 2040. In particular, vehicles including private cars,
motorcycles, and goods vehicles are assumed to grow by a varying percentage
(from 0% - 2.5% annual) during the period whereas the number of franchised
buses, public light buses and taxis are assumed to have no growth.
There have
been some minor policy changes from April 2012 to November 2012. The changes
include moving two diesel taxis (TAXI) to the private car (PC) category and
moving 4 LPG Private light buses (PV4) to the PV5 category. These changes,
however, are considered to be insignificant and therefore have been excluded
from the assessment. The default populations from the April 2012 population
The use of
electric vehicles (EVs), which do not have tailpipe emissions, has been
promoted by the government in the recent years. By April 2012, there were more
than 310 EVs in
Accrual Rate
Default values and compositions have
been adopted with reference to in the EMFAC-HKV2.5.1 Guideline.
Diurnal Variation
of Daily Vehicle Kilometres Travelled (VKT)
For each vehicle class, the Vehicle
Kilometres Travelled (VKT) of individual hours is calculated by multiplying the
hourly number of vehicles with the length of the corresponding road link (in
kilometres). Diurnal (24-hour) traffic pattern has been provided by Traffic
Consultant. The lengths of individual road links of the connecting road are
given in Appendix 3.12. The 24-hour
VKT values for all vehicle classes in each of the model years 2015, 2020, 2025
and 2030 together with a graphical plot, are provided in Appendix 3.13.
Daily Trips
The daily trips were used to estimate
the cold start emissions of the petrol and LPG vehicles only, as is prescribed
by the model. Therefore, trips for vehicles other than petrol or LPG type vehicles
would be assumed to be zero. Different road types have different number of
trips as follows.
Expressway and Trunk Road (Road Types 1, 2 & 3)
Zero trips are assumed in Expressway
and Trunk Roads since there will be no cold start under normal circumstances.
Local Road (Road Type 4)
For Local Roads, the number of trips in the assessment area,
Trip within assessment area, has been estimated as:
Trip within assessment area = (Trip within HK/VKT
within HK) x VKT within assessment area
Trip within HK is the
default data of EMFAC-HKV2.5.1 model. VKT within HK is the VKT of
local roads in Hong Kong, which is estimated based on the default VKT data of EMFAC-HKV2.5.1
model and the relevant data as published in the Annual Traffic Census 2010 by TD. Details of
the trip estimation are as shown in Appendix 3.14.
According to the Mobile Source Group of EPD, the default VKT and trips in the
model are based on EPD’s estimated data for
While the
number of trips is dependent on vehicle population, no project-specific vehicle
population data can be identified for the assessment area according to the
Traffic Consultants. However, project-specific VKT has been estimated based on
the traffic forecast in the assessment area. Moreover, it can be argued that
VKT is related to vehicle population in such a way that a higher vehicle
population would generally result in a higher VKT. As a result, it has been
proposed to estimate the number of trips in the assessment area on the basis of
the project-specific VKT and the assumption that the number of trips per VKT in the assessment area would be similar to
the number of trips per VKT in
Hourly
Temperature and Relative Humidity Profile
Annual
and monthly hourly average ambient temperature and relative humidity (Appendix 3.15)
obtained from the
meteorological data as extracted from the 2010 HKO’s, King’s Park meteorology
station (with at least 90% valid data) have been adopted. The
24-hour variations of the annual averages of temperature and relative humidity
are presented graphically in Appendix 3.15.
Speed Fractions
The
24-hour speed fractions for different road types and individual vehicle classes
are provided by the Traffic Consultant, and are calculated based on the 24-hour
traffic flow in each model year and the volume/capacity ratio of different road
types. For each vehicle class, the VKT of each road link was grouped into
sub-groups with speed bins of 8 km/h (0 - 8 km/h, 8 - 16 km/h, 16 - 24
km/h, etc.). The speed fraction of each sub-group was derived by the summation
of the total VKT of road link within this sub-group divided by the total VKT of
all road links. The estimated speed fractions provided by the Traffic
Consultant are given in Appendix 3.16.
Predicted
Emission Factors by EMFAC-HKV2.5.1 model
To
determine the emissions with 15 years after commencement of the Project,
emission rates are modelled for years 2015, 2020, 2025 and 2030. Upon modelling
with EMFAC-HKV2.5.1, the emissions for each vehicle class at different hours
are then divided by the corresponding VKT to obtain 24-hr emission factors in
grams/vehicle-kilometre (g/veh-km). The calculation of emission factors for each model year are
shown in Appendix
3.17. By comparing the total emissions in different model years as
shown in Graph
15.2,
year 2015 represents the worst case scenario where the total emission is the highest among all model years. Even with
addition of the traffic due to the CKR project after 2020, the worst-case year
is still predicted to be 2015. This is
because despite the increased traffic volume, the total emissions are expected
to decrease as a result of the retirement of older and more polluting vehicles
in the fleet, which would be replaced with newer vehicles with lower emissions.
Therefore, it is proposed to use the emission factors of this worst case year
2015 for the prediction of air quality impacts due to vehicular emissions in
order to arrive at conservative impact assessment results.
Although the planned commencement year of operation
of the Project has been updated from 2015 to 2017, use of the emission factors
in 2015 represents conservative emissions for the assessment. This is because
the total traffic emission in year 2017 is anticipated to be lower than that in
year 2015 as illustrated in Graph 15.2.
Graph 15.2: Comparison of RSP and NOx EMFAC
results for 2015, 2020, 2025 and 2030
|
Model Description – ISCST3
The Industrial Source Complex – Short Term version 3 (ISCST3) dispersion model was used to model the air pollutant concentrations due to vehicular emissions from the Western Harbour Crossing (WHC) portal (modelled as volume sources); the proposed underpasses/landscape deck portals (modelled as volume sources) and the associated top openings (modelled as area source) under the Road Works at West Kowloon project; as well as from the assumed ventilation serving the planned underground roads within the WKCD site (modelled as point or volume sources).
ISCST3 is a steady state Gaussian plume model which can be used to assess pollutant concentrations from sources associated with an industrial source complex. ISCST3 is one of the models prescribed by the EPD Guidelines on Choice of Models and Model Parameters. ISCST3 is considered an appropriate model to use for this situation as meteorological conditions will not vary greatly over the site, as the site is relatively flat and small and no significant effects are expected due to terrain variations.
It should be noted that ISCST3 and all Gaussian based dispersion models have limited ability to predict dispersion in the situations as described previously in Section 15.3.4.1.
Assumptions and Inputs – ISCST3
The operational sources for ISCST3 modelling (shown in Figure 3.6) include:
¡ Proposed underpasses/landscape decks along the Austin Road West and Lin Cheung Road and the associated top openings under the Road Works at West Kowloon project, which is within the 500 m assessment area;
¡ Portal of the existing WHC which is in the vicinity of the WKCD site; and
¡ Ventilation exhausts and portals serving the planned underground roads within the WKCD area.
EMFAC-HKV2.5.1 and the traffic modelling data from the Traffic Consultants were used to generate the inputs for use in ISCST3.
Hourly meteorological data for a full year as extracted from the PATH model released by EPD in December 2012 (meteorological data year 2010, grid 28, 27) has been adopted for use in ISCST3. The data is considered to be the most up to date data available, PATH data has been observed to have a lower mixing height for some hours, when compared to the measured mixing height. The minimum mixing height recorded by HKO in 2010 is 121.3 m, whereas the PATH minimum mixing height is 40 m. The HKO minimum mixing height of 121.3 m is used to replace any PATH mixing height below this value. This approach is considered appropriate as it will minimise over-estimation due to lower mixing heights and also will minimise under-estimation due to high stacks being excluded in the mixing volume. The PATH data with the above modification is considered to be representative of the site wind data at WKCD.
Ventilation Exhausts/Portals Serving WKCD
Basement
The basement will be ventilated through stacks; however the proportion released through stacks and through the portals cannot be determined until a comprehensive ventilation study is carried out during the detailed design phase. Two scenarios were therefore considered for the ventilation of the WKCD basement:
Scenario I – 100% of the vehicle emissions
generated within the basement is ventilated through a series of stack exhausts
and 0% through the basement entry and exit points
Under this Scenario, the exhausts are
assumed to be attached to buildings within the WKCD and were modelled as
6 m tall point sources with an exit air velocity of 2.0 m/s. The
stack diameter was dependant on the ventilation area. The basement is broken
into three areas, namely
Standard practice is to model ventilation
shafts as point sources. As the final dimensions of the exhaust louvres are yet
to be known at this stage, it is considered appropriate to model the basement
ventilation louvres as stacks. A single stack is used at approximately the
horizontal centre of the proposed louvre area to allow the greatest flexibility
in the final stack location.
The Practice Note ADM-2 recommends MTR
ventilation exhausts shall be located not closer than 5 m to any opening
such as an openable or fixed window, doorway, building ventilation system
intake or exhaust and the like in any building irrespective of whether such
vent shaft is freestanding or is accommodated in a building. Although there is
no such practice note for underground roads and tunnels, this basis has been
used to adopt a minimum stack height of 6 m. This is considered to give
worst case results at the ground level and allows for flexibility of the final
design and the ventilation to be located at this level.
There are several ventilation exhausts for
the XRL/WKT basement carpark, however this basement does not include an
underground road and therefore does not need to be considered as a concurrent
source.
Scenario II – 100% of the vehicle emissions
generated within the basement is ventilated through the basement entry and exit
points and 0% through a series of stack exhausts
Under this Scenario, the basement emissions
were considered as a total of the three roads (basements roads A, B and C) as shown in Figures 3.5.1n, 3.5.1r, 3.5.1s and 3.5.1t. The detailed design of the basement and
its ventilation
system is not yet complete; therefore it has been broadly assumed that the
emissions would be evenly distributed among the three entry/exit points to
approximate the scenario. Therefore, one
third of the total basement emissions were assumed to be emitted from the
western portal near the western tunnel, one third through the eastern portal
onto
The basement entry and exit point are not
treated as a standard portal as the traffic does not exit directly from the
portal, that is the vehicles come to a T-intersection at the entry and exit
point for Location A and C as shown in Figure 3.6. The entry and exit points are modelled
as volume sources based on the dimensions of the opening.
Underpasses/landscape decks
along the
The portal emissions are the worst case
emissions from portals and other openings of
¡ Scenario 1 - 10% of tunnel
emissions released through short top openings, the remainder released through
the tunnel portal;
¡ Scenario 2 - 20% of tunnel
emissions released through short top openings, the remainder released through
the tunnel portal;
¡ Scenario 3 - 30% of tunnel
emissions released through short top openings, the remainder released through
the tunnel portal, and;
¡ Scenario 4 - Maximum emissions
according to PIARC recommendations (which are dependent on top opening lengths
– 66% of emissions through top opening if the length is 50m and 100% through
top opening if the length is 100m), the remainder released through the top openin are
released through the
tunnel portal.
By adopting the traffic forecast in the
worst case year of 2015, rhe emission rates for Scenarios 1 to 4, with 100% of
the WKCD basement emission through its portals (Scenario II) are given in Appendix 3.18a
– Appendix 3.18d whereas the emission rates for Scenarios 1 to 4, with
100% of the WKCD basement emissions through its stack exhausts (Scenario I) are
given in Appendix 3.18e
– Appendix 3.18h. All scenarios were modelled to determine the worst
case effects.
By adopting the traffic forecast in 2020,
the emission rates for the combination of Scenario I and Scenario 1 are also estimated, as presented in Appendix 3.19. Based on the comparison of the modeling
results for all eight combinations of Scenarios I & II with Scenarios 1-4
for the worst case year of 2015, the results for different combinations differ
by a small amount (less than 2%) and yet the combination of Scenario I with
Scenario 1 tends to give relatively more conservative results. Therefore, this combination has been used to
estimate the emission rates for year 2020, which are then used to refine the
NO2 modelling results for those planned ASRs that will be in operation from
2020 onwards (see Section 15.3.5.2).
EMFAC-HKV2.5.1 model results and the traffic
modelling data from the Traffic Consultants were used to generate the inputs
for use in ISCST3.
Existing WHC Portal
The portal emissions are modelled according
to EPD’s Guidelines on Choice of Models
and Model Parameters, which recommends portals and similar openings are
modelled as volume sources according to the
Model Description – CALINE4
CALINE4 is a line source air quality model developed by the California Department of Transportation and is one of the models prescribed by the EPD Guidelines on Choice of Models and Model Parameters. It is based on the Gaussian diffusion equation and employs a mixing zone concept to characterise pollutant dispersion over the roadway.
The purpose of the model is to assess air quality impacts near transportation facilities. Given source strength, meteorology and site geometry, CALINE4 can predict pollutant concentrations for receptors located within 500 m of a given roadway. As with all Gaussian models, CALINE4 has some limitations, as described in Section 15.3.4.1.
Assumptions and Inputs – CALINE4
The predicted traffic flows have taken into
account the development of the four concurrent projects, namely: Road Works at
Hourly meteorological data for a full year as extracted from the PATH model released by EPD in December 2012 (meteorological data year 2010, grid 28, 27) has been adopted for use in CALINE4. The data is considered to be the most up to date data available. PATH data has been observed to have a lower mixing height for some hours, when compared to the measured mixing height. The minimum mixing height recorded by HKO in 2010 is 121.3 m, whereas the PATH minimum mixing height is 40 m. The HKO minimum mixing height of 121.3 m is used to replace any PATH mixing height below this value. This approach is considered appropriate as it will minimise over-estimation due to lower mixing heights and also will minimise under-estimation due to high stacks being excluded in the mixing volume. The PATH data with the above modification is considered to be representative of the site wind data at the flyover road site. A roughness coefficient of 370cm is used, as the area is considered to be urban
Based on the worst case emission factors and the 24-hour traffic flow in 2015, the composite fleet emission factors have been calculated for the road links, as detailed in Appendix 3.23.
By adopting the traffic forecast in 2020, the composite fleet emission factors have also been calculated for the road links, as detailed in Appendix 3.24. These emission factors have been used to refine the NO2 modelling results for those planned ASRs that will be in operation from 2020 onwards (see Section 15.3.5.2).
15.3.4.3 Operation
Phase – Marine Emissions
Introduction
To assess the operational air quality from
marine sources ISCST3 was used to predict the cumulative NOx, RSP
and SO2 levels at the identified ASRs in accordance with the EPD’s Guidelines on Choice of Models and Model
Parameters.
Marine emissions considered to be important for the assessment are: fast ferry traffic movements, based on scheduled sailings at the China Ferry Terminal; cargo-handling vessel traffic movements along the Yau Ma Tei Fairway at the western edge waterfront of the WKCD site; derrick lighter barges operating at the New Yau Ma Tei Public Cargo Working Area (NYPCWA), and; ocean cruise ship emissions at berth at the Ocean Terminal. As the marine emissions are all from existing marine activities within the surrounding waters and the WKCD development itself does not contribute to any marine traffic emissions, the cumulative SO2 levels due to the various surrounding sources are assessed for the proposed ASRs within the WKCD site only. ISCST3 has been used to predict the air pollutant concentrations due to marine sources. The locations of all such pollution sources are as shown in Figure 3.7. Details of the emissions rates for individual sources are given in Appendix 3.25.
The cumulative hourly maximum NOx,
RSP and SO2 concentrations are predicted by the above models by
using the corresponding MM5 hourly meteorological data in 2010 as extracted
from the PATH model released by EPD in December 2012.
Model Description – ISCST3
Gaussian model ISCST3 has been used for modelling potential impacts from the above-mentioned nearby marine emission sources. Refer to Section 15.3.4.2 for model description and limitations.
Assumptions and Inputs – ISCST3
The operational sources for the ISCST3 modelling
(shown in Figure
3.7) include:
¡ Fast ferry traffic movements, based on scheduled sailings, of up to 170 daily movements (ferry going to is one movement, ferry leaving is a second movement) at the China Ferry Terminal;
¡ Tugs associated with derrick lighter barge movements in the NYMTTS;
¡ Derrick lighter barges operating at the New Yau Ma Tei Public Cargo Working Area (NYPCWA), and;
¡ Ocean Cruise Ship movements at the Ocean Terminal.
Hourly meteorological data for a full year as extracted from the PATH model released by EPD in December 2012 (meteorological data year 2010, grid 28, 27) has been adopted for use in CALINE4. The data is considered to be the most up to date data available. PATH data has been observed to have a lower mixing height for some hours, when compared to the measured mixing height. The minimum mixing height recorded by HKO in 2010 is 121.3 m, whereas the PATH minimum mixing height is 40 m. The HKO minimum mixing height of 121.3 m is used to replace any PATH mixing height below this value. This approach is considered appropriate as it will minimise over-estimation due to lower mixing heights and also will minimise under-estimation due to high stacks being excluded in the mixing volume. The PATH data with the above modification is considered to be representative of the site wind data at flyover site.
New Yau Ma
Tei Public Cargo Working Area (NYPCWA)
The NYPCWA is located on the north-south
shoreline of the NYMTTS to the north of WKCD. The area is mainly used for
loading and unloading cargo from derrick lighter barges. The shoreline is
approximately 1,250 metres long. According to the Merchant Shipping (Local Vessels) (Typhoon Shelters) Regulation –
Chapter 548E the maximum permitted length for local vessels in the typhoon
shelter is 50 metres. For manoeuvring purposes it was assumed that each vessel
would need 5 metres at bow and stern. The maximum number of vessels operating
at any one time was therefore assumed to be the shoreline length divided by
vessel and manoeuvring length, which gives 20 vessels. Although this does not
take into account a larger possible vessel density should smaller barges being
used, it is still considered realistic estimate, as a visual survey identified
a similar number of vessels along the shore front.
The emission rates
were estimated with reference to the USEPA
Non-Road Diesel Standards and USEPA
Current Methodologies in Preparing Mobile Source Port-Related Emission
Inventories (April 2009), hereafter referred to as “USEPA Methodology”. The barges were assumed to have an engine size
of 314.6 kW, which is based on average engine size
Marine diesel engines are assumed to have an
average operating lifetime of 10,000 hours. Derrick lighter barges are assumed
to operate during the same period as the NYPCWA, i.e., 7:00 am to
9:00 pm daily or 14 hours per day (Monday to Saturday), with a time-in
mode of 25%. Based on these assumptions, it can be estimated that the average
life span of the marine engine on a derrick lighter barge is approximately 10
years, which is used to
determine the emission rate for the
engines by making reference to the emission
standards for non-road diesel engines. This estimated engine
life span is considered to give a conservative emission rate as the average age of engines is likely to
be less
than 10 years. Based on a visual survey, the exhaust height of the derrick lighter
engine is assumed to be 8.7m (approximately the height of three shipping containers).
Details of estimating the engine emission can be found in Appendix 3.25.
Information provided by the marine
sub-consultant estimates 130 small craft movements in the NYMTTS (both entering
and leaving). It is assumed that all the vessels are tugs and are restricted to
the same operation period as the NYPCWA, that is
7:00 am to 9:00 pm daily.
The NOx emission rates for tugs
were estimated by using actual engine data sourced from maritime sales
Engine loading factor for tugs was assumed
to be 31% as described in the “USEPA
Methodology”. The movements were divided evenly among the operating hours
and so for modelling purposes there are nine tug movements per operating hour of
NYPCWA.
As the tugs are moving, the emissions are
modelled as a series of area sources. To allow for variation in the actual
vessel route, a width of 30 m is applied. The average hourly area emission
rate was calculated by the instantaneous emission rate (g/s) multiplied by the time
that it takes for the vessel to move over the length of the route (based on the
reported average speed), and then divided by the total route area and
3600 seconds (one hour).
The estimated emission rates are summarised
in Table 15.3.12
and details of the estimation are given in Appendix 3.25.
Table 15.3.12: Estimated Emission Rates of Barges at NYPCWA
Pollutant |
Vessel type |
Estimated Emission Rates |
NOx |
Barge |
0.0799 g/s for each barge |
|
Tug |
2.30 x 10-6 g/m2.s for each tug |
RSP |
Barge |
0.0022 g/s for each barge |
|
Tug |
8.81 x 10-8 g/m2.s for each tug |
SO2 |
Barge |
0.0136 g/s for each barge |
|
Tug |
6.07 x 10-7 g/m2.s for each tug |
The China Ferry Terminal is located to the
south-east of WKCD. Three main companies operate at the Terminal, which are:
CotaiJet, TurboJet and Chu Kong Passenger Transport Limited. Sailing timetables
were reviewed for each of the companies and total vessel unloading/loading to
the terminal calculated. The total unloading/loading was from one to 14 vessels
per hour, between the hours of 7:00am and 11:00pm. Outside of these hours there
are no scheduled ferry services and therefore no emissions modelled.
The emission rates were calculated based on the “Institute for the Environment, The Hong Kong
University of Science & Technology: Study on Marine Vessels Emission
Inventory”, hereafter
referred to as the “HK Inventory”.
During berthing it is assumed that only auxiliary engines are operational. An
overall average emission rate for all ferries was calculated for berthing based
on the average auxiliary engine
From
Emissions for the movement of fast ferries
to and from the terminal were also modelled. Separate emission factors were
calculated for Macau ferries (i.e., fast ferries travelling to/from Macau) and
China ferries (i.e., fast ferries travelling to/from cities in Mainland China).
Emissions are estimated based on the “HK
Inventory”. Slow cruise is defined as 8 – 12 knots, but the marine speed limit within Victoria Harbour
is 10 knots. Therefore, all fast ferries are assumed to travel at 10
knots within the study area for the purpose of estimating the engine emission
rates.
For Macau ferries,
the largest engine power as stated in the “HK Inventory” is
9,280kW and the maximum design cruise speed is 45 knots. For China ferries, the largest engine power as stated in the “HK Inventory” is
5,490kW and the maximum design cruise speed is 32 knots. In order to estimate the ferry
engine power at the cruise speed of 10 knots, it is assumed that the engine
power, which can be estimated as hydrodynamic drag force multiplied by cruise
speed, is directly proportional to the cruise speed. In other words,
the hydrodynamic drag force is
assumed to be at a constant level that equals to the highest hydrodynamic drag
force at maximum engine power. This is a conservative assumption for estimating the engine power at reduced cruise speed conditions where the hydrodynamic drag force would be lower. With such a conservative
assumption, it can be estimated that the engine power levels for Macau ferries and China ferries travelling at 10
knots are respectively 0.22 (i.e., 10knots / 45knots) x 9,280kW and 0.31 (i.e., 10knots / 32knots) x 5,490kW. Each scheduled travel of a fast ferry is considered to have two vessel
trips along the ferry route (one to and one from). The estimated emission rates are summarised in
Table 15.3.13
and details of the estimation are given in Appendix 3.25.
As the marine traffic emissions are included
as part of the emission inventory of the PATH model, there is a certain amount
of double counting. The modelling results for the fast ferries are therefore
considered to be conservative.
Table 15.3.13: Estimated Emission Rates of Fast Ferries at China Ferry Terminal
Pollutant |
Mode |
Estimated Emission Rates |
NOx |
Berth |
0.12 g/s for each ferry* |
|
|
8.84 x 10-6 g/m2.s for each ferry |
|
|
1.01 x 10-5 g/m2.s for each ferry |
RSP |
Berth |
0.004 g/s for each ferry* |
|
|
2.79 x 10-7 g/m2.s for each ferry |
|
|
3.21 x 10-7 g/m2.s for each ferry |
SO2 |
Berth |
0.026 g/s for each ferry* |
|
|
1.88 x 10-6 g/m2.s for each ferry |
|
|
2.15 x 10-6 g/m2.s for each ferry |
*Assumed to
last for 30 minutes during each hour of operation
Ocean Terminal
The Ocean
Terminal is located to the south-east of WKCD. A 40,000-ton ship is berthed at
the Ocean Terminal during day-time but leaves for the sea during night-time. This 40,000-ship is hereafter referred to as the
day-time ship. Other cruise ships are also periodically berthed at the Ocean
Terminal. There are totally two berths available at the Ocean Terminal. Therefore, it is assumed for the worst-case scenario
that both the day-time ship and another 70,000-ton ship are berthed at the Terminal simultaneously, with the
70,000-ton ship berthing for 24 hours of a day (hereafter referred to as the
24-hour ship). The day-time ship is generally berthed between about 8:00am and 8:00pm,
and has been modelled as such. The
24-hour ship is assumed to be berthed for 24 hours at the Terminal, as when
visiting it can be berthed at the Terminal for more than a day. This modelling approach
is considered to have captured the worst-case scenario when both cruise ships
are at the berths.
Emission rates of the ships berthing at the
Ocean Terminal were estimated by using the “USEPA
Methodology”, MARPOL regulations, as stated in Merchant Shipping (Prevention of Air Pollution) Regulation – Chapter
413M, Section 27 (3) (b) and engine
To prevent over-estimation of the SO2 emissions from the ships berthing at the Ocean Terminal, a calibration exercise was performed with reference to the on-site SO2 data recorded at the EPD’s WKCD monitoring station (see Section 15.3.1.2). Historic berthing timetable at the Ocean Terminal during the monitoring period of the WKCD monitoring station (i.e., from Sep 2011 to Aug 2012) was identified. As there are many day-time marine traffic emission sources (e.g., Star Ferries, China ferries, Macau ferries, recreational and cargo vessels) during day-time, the calibration exercise was carried out only for night-tme periods between 9pm and 8am when the 24-hour ship alone is berthed at the Ocean Terminal (the day-time ship is at cruise during night-time) and the emissions from fast ferries and other marine traffic are minimal. The calibration results were then used to adjust the SO2 emission rate for the 24-hour ship to provide more realistic estimates of the maximum SO2 concentrations at the ASRs. The SO2 emission rate for the day-time ship, which is smaller in tonnage than the 24-hour ship, is conservatively assumed to be the same as the adjusted emission rate for the 24-hour ship. Details of the calibration results for estimation of SO2 emission rates are given in Appendix 3.25.
Based on a visual survey and
Table 15.3.14: Estimated Emission Rates of Cruise Ships at Ocean Terminal
Pollutant |
Vessel |
Estimated Emission Rates (g/s) |
NOx |
Day-time ship |
12.97 |
|
24-hour ship |
14.55 |
RSP |
Day-time ship |
1.88 |
|
24-hour ship |
1.97 |
SO2 |
Day-time ship |
7.62 |
|
24-hour ship |
7.62 |
15.3.4.4 Operation Phase – General Emissions
To assess the operational air
quality, a variety of models were required. In
accordance with the EPD’s Guidelines
on Choice of Models and Model Parameters.
Model Description - PATH
The
PATH model is a
numerical air quality modelling system developed specifically for use in
Assumptions and Inputs – PATH
An updated version of PATH was released by
the EPD for general use in December 2012. As there is no significant policy
change or inventory update since the release of the latest PATH and the
submission of this report, use of the 2012 PATH model in its current state is
considered appropriate.
For EIA applications, PATH simulates wind field, pollutant emissions,
transportation and chemical transformation and outputs pollutant concentrations
over Hong Kong and the Pearl River Delta (PRD) region at a fine grid size of
1.5km.
During the 12th Hong Kong-Guangdong Joint Working Group
Meeting on Sustainable Development and Environmental Protection (Nov 2012), the
Hong Kong and Guangdong Governments jointly endorsed a Major Air Pollutant
Emission Reduction Plan for the Pearl River Delta Region up to year 2020. A
comprehensive emission inventory for
Table 15.3.15: Summary of 2015 and 2020 Hong Kong Emission Inventory for the PATH Model
Pollutant |
Total Emission in 2015
(ton/year) |
Total Emission in 2020
(ton/year) |
SO2 |
26,625 |
23,075 |
NOx |
98,100 |
87,200 |
RSP |
5,706 |
5,389 |
PATH
model was used to quantify the background air quality during the operational
phase of the Project. Emission sources including roads, marine, airports, power
plants and industries within the Pearl River Delta Economic Zone and Hong Kong
were considered in the PATH model. Details of the PATH Model and related
emission inventory can be found in EPD’s web site.
The
hourly SO2, NOx and RSP concentrations as extracted from
the PATH for year 2015 are adopted as the background air pollutant
concentrations in the estimation of cumulative impact for the Project during
the worst case year of 2015. The
hourly pollutant concentrations as extracted from the PATH for year 2020 have
also been used to refine the NO2 modelling results for those planned
ASRs that will be in operation from 2020 onwards (see Section 15.3.5.2).
Since the vehicular and marine traffic emissions at local scale (i.e.
within the 500m assessment area) have been modeled by near-field dispersion
models, namely, CALINE4 and ISCST (see Sections
15.3.4.2 and 15.3.4.3), adding
the PATH background concentrations to the near-field modeling results would
lead to certain amount of double counting, and hence conservative cumulative
modeling results.
Other Assumptions
According to Entec UK Limited: Defra
The Ozone Limiting Method (OLM) as described
in EPD’s Guidelines on Choice of Models and Model Parameters has been adopted to estimate the conversion
of NOx to NO2 from both marine and vehicular emissions.
The ozone concentrations are based on the future hourly background ozone
concentrations for year 2015 or 2020, which were extracted from grid (28, 27)
of the most up to date PATH. Grid (28, 27) of the PATH model is used because
the majority of the WKCD area falls within this grid (see Figure 3.8).
The NOx/NO2 conversion
for vehicular and marine emissions is therefore estimated as follows:
[NO2]
= 0.075 x [NOx]vehicle + minimum
of {0.925 x [NOx]vehicle or (46/48) x [O3]PATH}
+ 0.10 x [NOx]marine + minimum
of {0.90 x [NOx]marine or (46/48) x [O3]PATH}
where
[NO2] is the
estimated hourly vehicular NO2 concentration (predicted by CALINE4
and ISCST);
[NOx]vehicle is
the hourly NOx concentration as predicted by CALINE4 and ISCST3 for
vehicular emissions at the receptor;
[O3]PATH is
the hourly ozone concentrations as extracted from the aforementioned grid of the PATH model for year 2015 or 2020, and;
[NOx]marine is
the hourly NOx concentration as predicted by ISCST3 for marine
emissions at the receptor;
To estimate the total hourly concentrations, the hourly pollutant
concentrations as predicted by CALINE4 and ISCST3 (vehicular and marine) are
added together with the future hourly background pollutant concentrations as
extracted from the relevant grid of the PATH model. Therefore, the total hourly
concentrations of NO2 are calculated as follows:
[NO2]total = [NO2]
+ [NO2]PATH
where
[NO2]total is
the total hourly NO2 concentration;
[NO2] is the
hourly vehicular and marine NO2 concentration which is first
predicted by CALINE4 and ISCST3 as NOx and then converted to NO2
by using OLM; and
[NO2]PATH is
the hourly NO2 concentrations as extracted from the aforementioned
grid of the PATH model for year 2015 or 2020.
Similarly, the total hourly RSP (vehicular
and marine) and SO2 (marine emissions only) concentrations are also
calculated by adding together the hourly results predicted by CALINE4, ISCST3
and PATH.
With the total hourly NO2, RSP
and SO2 estimated, the daily results are obtained by taking the
arithmetic mean of the 24 hourly results. Similarly, the annual concentrations
are calculated as the arithmetic mean of the whole year of hourly results.
15.3.5 Evaluation and Assessment of the Air Quality Impacts
Tier 1 Results
The Tier 1 screening results for unmitigated and mitigated scenarios including the background contribution are tabulated in Appendix 3.28. The unmitigated and mitigated results are summarised as follows.
Hourly
The Tier 1 hourly TSP results under both unmitigated and mitigated scenarios are summarized in Table 15.3.16. There would be exceedances of the hourly TSP limit of 500 µg/m3 under the Tier 1 unmitigated scenario from 2014 to 2017. However, under the Tier 1 mitigated scenario, exceedances of the hourly TSP limit would only occur from 2015 to 2017, but no exceedances in 2014.
The locations of the dust sources are shown in Figures 3.3a to 3.3k. Figures 3.11a to 3.11h and 3.12a to 3.12h show the Tier 1 hourly TSP concentration contours for unmitigated and mitigated scenarios, respectively.
Table 15.3.16: Summary of Predicted Cumulative Hourly Average TSP Concentrations for All ASRs (Tier 1 Unmitigated & Mitigated)
Year |
Tier 1
Unmitigated Scenario Range of Maximum Hourly TSP (μg/m3) [Criterion - 500 µg/m3] |
Tier 1
Mitigated Scenario Range of Maximum Hourly TSP (μg/m3) [Criterion - 500 µg/m3] |
2014 |
97 – 1992 |
75 – 420 |
2015 |
150 – 4731 |
79 – 580 |
2016 |
175 – 5296 |
79 – 623 |
2017 |
203 – 5108 |
81 – 543 |
Table 15.3.17 shows the receptors that would breach the hourly TSP limit of 500 µg/m3 under the Tier 1 mitigated scenario for years 2015 to 2017. ASRs that were predicted to exceed the hourly TSP limit of 500 µg/m3 for the Tier 1 mitigated scenario were modelled further under Tier 2 conditions, as described in Section 15.3.4.1.
Table 15.3.17: Predicted Cumulative Hourly Average TSP Concentrations for ASRs with Exceedance (Tier 1 Mitigated)
ASR |
Height above ground (m) |
Maximum Hourly TSP (μg/m3) [Criterion - 500 µg/m3] |
Remark |
2015 |
|||
P53-1 |
4 |
575 |
Planned Performance Art
Venues within WKCD. It is a possible open area. Exceedance subject to
Tier 2 assessment. |
2016 |
|||
P53-1 |
4 |
623 |
Planned Performance Art
Venues within WKCD. It is a possible open area. Exceedance subject to
Tier 2 assessment. |
2017 |
|||
P52-1 |
4 |
543 |
Planned Performance Art
Venues within WKCD. It is a possible open area. Exceedance subject to
Tier 2 assessment |
Daily
The daily TSP results for Tier 1 unmitigated and mitigated scenario including the background contribution are tabulated in Appendix 3.28. Table 15.3.18 summarises the Tier 1 results for daily TSP under both unmitigated and mitigated scenarios. There would be exceedances of the daily TSP limit of 260 µg/m3 under the Tier 1 unmitigated scenario from 2014 to 2017. However, under the Tier 1 mitigated scenario, no ASRs are predicted to exceed the daily TSP limit for any of the assessment years.
The locations of the dust sources are shown in Figures 3.3a to 3.3k. Figures 3.13a to 3.13h and Figures 3.14a to 3.14h show the daily TSP concentration contours for unmitigated and mitigated scenarios, respectively.
Table 15.3.18: Summary of Predicted Cumulative Daily Average TSP Concentrations for All ASRs (Tier 1 Unmitigated & Mitigated)
Year |
Tier 1
Unmitigated Scenario Range of Maximum Daily TSP (μg/m3) [Criterion - 260 µg/m3] |
Tier 1
Mitigated Scenario Range of Maximum Daily TSP (μg/m3) [Criterion - 260 µg/m3] |
2014 |
74 – 433 |
69 –132 |
2015 |
80 – 1110 |
70 – 223 |
2016 |
86 –1844 |
70 – 257 |
2017 |
84 –1278 |
70 – 204 |
Tier 2 Results
The Tier 2 results including the background contribution, as described in Section 15.3.4.1 are tabulated in Appendix 3.29, and are discussed below.
Hourly
Tier 2 scenario was performed for those ASR subject to exceedance of the hourly TSP limit under the Tier 1 mitigated scenario. Under the Tier 2 mitigated scenario no ASRs were subject to exceedance of the hourly TSP limit of 500 µg/m³ as summarised in Table 15.3.19
. Detailed results can be found in Appendix 3.29. The locations of the dust sources are shown in Figures 3.3a to 3.3h. Figures 3.15a to 3.15e show the hourly TSP concentration contours under the Tier 2 mitigated scenario.Table15.3.19: Summary of Predicted Cumulative Hourly Average TSP Concentrations (Tier 2 Mitigated)
ASR |
Height above ground (m) |
Maximum Hourly TSP (μg/m3) [Criterion - 500 µg/m3] |
2015 |
|
|
P53-1 |
4 |
265 |
2016 |
|
|
P53-1 |
4 |
413 |
2017 |
|
|
P52-1 |
4 |
247 |
Daily
There are no ASRs that would be subject to exceedance of the daily TSP limit under the Tier 1 mitigated scenario. Therefore, it is not necessary to run the Tier 2 mitigated scenario for daily TSP.
Annual Results
The annual results for mitigated and unmitigated scenarios including the background contribution are tabulated in Appendix 3.30 and are also summarised in Table 15.3.20. There would be exceedances of the annual TSP limit of 80 µg/m3 under the unmitigated scenario for years 2014 and 2016 only. However, under the mitigated scenario, no ASRs would exceed the annual TSP limit for any of the assessment years.
The
locations of the dust sources are shown in Figures 3.3a
to 3.3k. Figures 3.17a to 3.17h and Figures 3.18a to 3.18h
show the annual TSP concentration contours for unmitigated and mitigated
scenarios, respectively.
Table15.3.20: Summary of Predicted Cumulative Annual Average TSP Concentrations for All ASRs (Unmitigated & Mitigated)
Year |
Unmitigated Scenario Range of Maximum Annual TSP (μg/m3) [Criterion
- 80 µg/m3] |
Mitigated Scenario Range of Maximum Annual TSP (μg/m3) [Criterion - 80 µg/m3] |
2014 |
69 - 81 |
68 - 75 |
2015 |
68 - 79 |
68 - 79 |
2016 |
69 - 84 |
68 - 78 |
2017 |
68 - 79 |
68 - 71 |
Operation
Phase – Vehicular and Marine Emissions
The predicted air quality results have
included the background pollutant levels as extracted from the PATH model for
year 2015 based on the latest released model and the cumulative impacts of the
following emissions:
§ Existing and proposed open roads within the 500 m assessment area;
§ Proposed underpasses/landscape decks along the Austin Road West and Lin Cheung Road and the associated top openings under the Road Works at West Kowloon project;
§ Existing WHC portal in the vicinity of the WKCD site;
§ Ventilation exhausts/portals serving the planned underground roads within the WKCD area;
§ Emissions from stationary marine sources at NYPCWA, China Ferry Terminal and Ocean Terminal, and;
§ Fast ferry and tug movements within the 500 m assessment area.
Comparison of the predicted cumulative NO2,
RSP and SO2 concentrations and any exceedances for individual ASRs
under all modelled scenarios during the worst case year of 2015 (see Sections 15.3.4.2) can be found in Appendix 3.31.
For the planned ASRs that will only be in
operation in or after 2020, however, the modelling results that are based on
the worst case year of 2015 with the highest total road traffic emissions would
be overly conservative because those planned ASRs are yet to exist in 2015. As a result, the relevant modelling works for
road traffic emissions have been refined for such planned ASRs by adopting the
traffic forecast in 2020 and the background concentrations as extracted from
the PATH for year 2020 in order to obtain more realistic estimates of the
predicted maximum cumulative NO2 levels. Details of the modelling results using the
traffic forecast and background concentrations in 2020 are given in Appendix 3.32. The contours for cumulative NO2, SO2 and RSP at
1.5m, 12m, 40m, 50m and 60m above ground are shown in Figure 3.19 to Figure 3.93.
According to the modelling
results as summarised in Table 15.3.21, all the ASRs would be in compliance with
the corresponding AQOs for daily and annual RSP; for hourly, daily and annual
SO2; as well as for hourly, daily and annual NO2. However, the predicted maximum hourly or
daily NO2 concentrations at some of the ASRs would exceed the
corresponding AQO for up to once per year, which is within the allowable
numbers of exceedance for hourly NO2 (3 times per year) and for
daily NO2 (once per year). Details of such hourly and daily NO2
exceedances, together with the breakdown of NO2 contributions due to
different sources, are summarised in Table 15.3.22.
Table 15.3.21: Summary of Predicted Cumulative RSP, SO2 and NO2 Concentrations for All ASRs
Air
Pollutant |
Averaging
Time |
AQO (μg/m3) |
Allowable
Exceedances in a Year |
Range of
Maximum Concentrations (μg/m3) |
Maximum No.
of Exceedance in a Year |
RSP Note (1) |
24 hours |
180 |
1 |
114.5 – 117.7 |
0 |
1 year |
55 |
0 |
42.8 – 51.7 |
0 |
|
SO2 Note (1) |
1 hour |
800 |
3 |
84.7 – 619.1 |
0 |
24 hours |
350 |
1 |
31.5 – 89.0 |
0 |
|
1 year |
80 |
0 |
7.9 – 16.2 |
0 |
|
NO2 Note (2) |
1 hour |
300 |
3 |
259.7 – 314.9 |
0 – 1 |
24 hours |
150 |
1 |
108.0 – 150.2 |
0 – 1 |
|
1 year |
80 |
0 |
45.0 – 79.7 |
0 |
Notes:
(1)
The predicted SO2 and RSP concentrations for all existing and
planned ASRs are based on the traffic forecast during the worst-case year of 2015
and the background concentrations as extracted from the PATH for year 2015.
(2)
The predicted NO2 concentrations for existing ASRs and
planned ASRs that will
be in operation before 2020 are based on the traffic forecast
during the worst-case year of 2015 and the background concentrations as
extracted from the PATH for year 2015 whereas the predicted NO2
concentrations for planned ASRs that will be in operation in/after 2020 have
been refined based on the traffic forecast in 2020 and the background concentrations
as extracted from the PATH for year 2020.
From Table 15.3.22, two existing ASRs,
namely, SRT-1 and SRT-2, would be subject to
exceedance of the AQO for hourly NO2 for once a year, which is, however,
below the allowable number of exceedances (3 times per year). At a planned ASR, namely, P37-1, the
cumulative maximum daily NO2 concentrations would marginally exceed
the AQO for daily NO2 by only 0.2 μg/m3 (about 0.1% of the AQO for daily NO2) for once per year,
which is still within the allowable number of exceedance under the AQO for
daily NO2 (once per year).
Therefore, these two existing ASRs and one planned ASRs would still be
in compliance with the AQO for hourly NO2 and daily NO2
respectively. As noted in Table
15.3.3: Representative
ASRs Identified for the Assessment, ASR P37-1
is at 4m above ground level, and is therefore an assessment point for reference
only but not fresh air intake or openable window location.
It can also be seen from Table 15.3.22 that majority (some 78%-81%) of the hourly/daily
NO2 concentrations would be from the background concentration and
the remaining 19%-22% would be due to nearby marine traffic/vessel plus road
traffic emissions. Of these 19%-22% contributions, the percentage contributions
from nearby road traffic emissions for the two existing ASRs would be around 9%-12%,
which are lower than the corresponding percentage (some 18%) for the one planned
ASR. As the flyover project would only
contribute to some road traffic emissions, the flyover project is not the key
contributor to the exceedance of hourly or daily NO2 limits (only
once in a year) at the three ASRs.
Table 15.3.22: Breakdown of Predicted Cumulative NO2 Concentrations by Sources for ASRs with Potential
Exceedance
ASR |
Height
above ground (m) |
Description |
Maximum Cumulative Hourly/Daily NO2
Concentrations (μg/m3)* |
||||||
|
Background
Contribution |
Marine
Traffic Contribution |
Road
Traffic Contribution |
Total
Concentration# |
|||||
Hourly NO2 (AQO: 300 μg/m3, not to be exceeded for more than 3
times per year) |
|||||||||
SRT-1 |
19 |
Sorrento – Tower 1 Residential (Existing ASR) |
246.2 |
78.2% |
30.0 |
9.5% |
38.7 |
12.3% |
314.9 [1] |
SRT-2 |
23 |
246.2 |
81.1% |
29.9 |
9.8% |
27.6 |
9.1% |
303.7 [1] |
|
Daily NO2 (AQO: 150 μg/m3, not to be exceeded for more than
once per year) |
|||||||||
P37-1 |
4 |
Retail/
Dining/ Entertainment (Planned
from 2017 onwards) |
118.9 |
79.2% |
3.7 |
2.5% |
27.6 |
18.4% |
150.2 [1] |
*Percentages in shaded cells represent the percentage
share of the total concentrations.
#Numbers in bracket
refer to the numbers of exceedance per year.
As explained in Sections 15.3.3.3 and
15.3.3.4, majority of the vehicular emission sources and all marine
emission sources are due to respectively the nearby current/planned road
networks serving the West Kowloon area and the existing marine activities in
the surrounding waters, but not due to the WKCD development itself. To illustrate this, breakdown of the
predicted maximum hourly NO2 contributions due to different sources
has been identified at a number of selected ASRs during the worst case year of
2015, as presented in Table
15.3.23. These selected ASRs
cover existing ASRs close to but outside the WKCD boundary and planned ASRs
representing the various types of future developments (to be operated before
2020) scattering within the entire WKCD area.
It can be seen from the Table that 88%-100% of NO2 contributions
would be due to the background concentration plus the surrounding marine
traffic emissions, with 12% or less from the nearby road traffic emissions. As the flyover project would only result in
some road traffic emissions, the project itself would have very minor
contribution to the predicted air quality impacts at the ASRs.
Table 15.3.23: Breakdown of Predicted Cumulative Hourly NO2 Concentrations by Sources for Selected ASRs (for the Worst Case Year of 2015)
ASR |
Height above ground (m) |
Description |
Maximum
Cumulative Hourly NO2 Concentrations (μg/m3)* (AQO: 300 μg/m3, not to be exceeded for more than 3 times per
year) |
|||||||
|
Background Contribution |
Marine Traffic Contribution |
Road Traffic Contribution |
Total Concentration# |
||||||
SRT-1 |
19 |
Sorrento – Tower 1 Residential (Existing ASR) |
246.2 |
78.2% |
30.0 |
9.5% |
38.7 |
12.3% |
314.9 [1] |
|
SRT-2 |
23 |
246.2 |
81.1% |
29.9 |
9.8% |
27.6 |
9.1% |
303.7 [1] |
||
P16-1 |
4 |
Retail/
Dining/ Entertainment Residential (Planned ASR from 2018 onwards) |
277.2 |
99.4% |
1.8 |
0.6% |
0.0 |
0.0% |
279.0 |
|
P16-3 |
12 |
277.2 |
99.4% |
1.7 |
0.6% |
0.0 |
0.0% |
278.9 |
||
P16-5 |
20 |
277.2 |
99.4% |
1.7 |
0.6% |
0.0 |
0.0% |
278.9 |
||
P16-8 |
50 |
277.2 |
99.5% |
1.3 |
0.5% |
0.0 |
0.0% |
278.5 |
||
P29-1 |
4 |
Office +
Retail/ Dining/ Entertainment Residential (Planned ASR from 2018 onwards) |
277.2 |
99.8% |
0.5 |
0.2% |
0.1 |
0.0% |
277.8 |
|
P29-3 |
12 |
277.2 |
99.8% |
0.5 |
0.2% |
0.0 |
0.0% |
277.7 |
||
P29-5 |
20 |
277.2 |
99.8% |
0.5 |
0.2% |
0.0 |
0.0% |
277.7 |
||
P29-10 |
70 |
277.2 |
99.9% |
0.4 |
0.1% |
0.0 |
0.0% |
277.6 |
||
P35c-1 |
4 |
Planned performance art venue (Planned ASR from 2017 onwards) |
277.2 |
99.6% |
1.1 |
0.4% |
0.0 |
0.0% |
278.3 |
|
P35c-3 |
12 |
277.2 |
99.6% |
1.1 |
0.4% |
0.0 |
0.0% |
278.3 |
||
P35c-5 |
20 |
277.2 |
99.6% |
1.1 |
0.4% |
0.0 |
0.0% |
278.3 |
||
P37-1 |
4 |
Retail/
Dining/ Entertainment (Planned ASR from 2017 onwards) |
246.2 |
88.1% |
6.7 |
2.4% |
26.6 |
9.5% |
279.5 |
|
P37-3 |
12 |
277.2 |
99.6% |
0.1 |
0.0% |
1.0 |
0.4% |
278.3 |
||
P37-5 |
20 |
277.2 |
99.7% |
0.1 |
0.0% |
0.8 |
0.3% |
278.1 |
||
P37-10 |
70 |
277.2 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
277.2 |
||
P51-1 |
4 |
Freespace (Planned ASR from 2016 onwards) |
277.2 |
99.9% |
0.2 |
0.1% |
0.0 |
0.0% |
277.4 |
|
P51-3 |
12 |
277.2 |
99.9% |
0.2 |
0.1% |
0.0 |
0.0% |
277.4 |
||
P51-5 |
20 |
277.2 |
99.9% |
0.2 |
0.1% |
0.0 |
0.0% |
277.4 |
||
P52-1 |
4 |
Pavilion (Planned ASR from 2016 onwards) |
277.2 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
277.2 |
|
P52-3 |
12 |
277.2 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
277.2 |
||
P52-5 |
20 |
277.2 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
277.2 |
||
OP |
1.5 |
Open Space (Planned ASR from 2017 onwards) |
277.2 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
277.2 |
|
*Percentages in shaded cells represent the percentage
share of the total concentrations.
#Numbers in bracket
refer to the numbers of exceedance per year.
To illustrate the predicted air quality impacts in 2020, breakdown of
the predicted maximum hourly NO2 contributions due to different
sources has also been identified by adopting the traffic forecast and
background concentrations for the year of 2020 at selected ASRs, as presented
in Table 15.3.24. The selected ASRs cover existing ASRs close
to but outside the WKCD boundary and planned ASRs representing the future
developments within WKCD, particularly those in the vicinity of the WHC portal. It can be seen from the Table that 73%-100%
of NO2 contributions would be due to the background concentration
plus the surrounding marine traffic emissions, with 27% or less from the nearby
road traffic emissions. The NO2
contributions from nearby road traffic for P43d and P43e at not more than 12m
above ground (21%-27%) are much higher than those for other ASRs (0.0%-8.9%),
chiefly because of their proximity to the WHC portal. Another observation is
that the cumulative maximum hourly NO2 concentrations of the
existing ASRs in 2020 would be considerably lower than those in 2015 (i.e.,Table
15.3.23), indicating an appreciable extent of improvement in air
quality from 2015 to 2020.
Table
15.3.24: Breakdown of Predicted Cumulative Hourly NO2 Concentrations by Sources for Selected ASRs (for Year
2020)
ASR |
Height above ground (m) |
Description |
Maximum
Cumulative Hourly NO2 Concentrations (μg/m3)* (AQO: 300 μg/m3, not to be exceeded for more than 3 times per
year) |
||||||
|
Background Contribution |
Marine Traffic Contribution |
Road Traffic Contribution |
Total Concentration |
|||||
SRT-1 |
19 |
Sorrento – Tower 1 Residential (Existing ASR) |
214.5 |
79.9% |
30.0 |
11.2% |
23.8 |
8.9% |
268.3 |
SRT-2 |
23 |
259.7 |
98.8% |
0.0 |
0.0% |
3.1 |
1.2% |
262.8 |
|
P37-1 |
4 |
Retail/ Dining/
Entertainment (Planned ASR from 2017 onwards) |
259.7 |
98.8% |
0.1 |
0.0% |
3.0 |
1.1% |
262.8 |
P37-3 |
12 |
259.7 |
98.9% |
0.1 |
0.0% |
2.7 |
1.0% |
262.5 |
|
P37-5 |
20 |
259.7 |
99.0% |
0.1 |
0.0% |
2.4 |
0.9% |
262.2 |
|
P37-10 |
70 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P39-1 |
4 |
Office + Planned performance art venues (Planned ASR from 2020 onwards) |
259.7 |
99.0% |
0.1 |
0.0% |
2.6 |
1.0% |
262.4 |
P39-3 |
12 |
259.7 |
99.4% |
0.1 |
0.0% |
1.5 |
0.6% |
261.3 |
|
P39-5 |
20 |
259.7 |
99.7% |
0.1 |
0.0% |
0.7 |
0.3% |
260.5 |
|
P39-10 |
70 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43a-1 |
4 |
Hotel + Retail/ Dining/ Entertainment (Planned ASR from 2020 onwards) |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
P43a-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43a-4 |
16 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43b-1 |
4 |
Ditto |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
P43b-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43b-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43c-1 |
4 |
Ditto |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
P43c-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43c-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43d-1 |
4 |
Ditto |
202.8 |
72.6% |
2.7 |
1.0% |
73.9 |
26.4% |
279.4 |
P43d-3 |
12 |
202.8 |
77.3% |
2.7 |
1.0% |
56.7 |
21.6% |
262.2 |
|
P43d-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43d-7 |
40 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43e-1 |
4 |
Ditto |
202.8 |
72.2% |
3.2 |
1.1% |
74.9 |
26.7% |
280.9 |
P43e-3 |
12 |
202.8 |
77.5% |
3.2 |
1.2% |
55.8 |
21.3% |
261.8 |
|
P43e-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43e-8 |
50 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43f-1 |
4 |
Ditto |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
P43f-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43f-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43f-8 |
50 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43g-1 |
4 |
Ditto |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
P43g-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43g-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43g-7 |
40 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43h-1 |
4 |
Ditto |
259.7 |
100.0% |
0.0 |
0.0% |
0.1 |
0.0% |
259.8 |
P43h-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.1 |
0.0% |
259.8 |
|
P43h-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43h-7 |
40 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43i-1 |
4 |
Ditto |
259.7 |
99.9% |
0.0 |
0.0% |
0.2 |
0.1% |
259.9 |
P43i-3 |
12 |
259.7 |
100.0% |
0.0 |
0.0% |
0.1 |
0.0% |
259.8 |
|
P43i-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43i-6 |
30 |
259.7 |
100.0% |
0.0 |
0.0% |
0.0 |
0.0% |
259.7 |
|
P43j-1 |
4 |
Ditto |
259.7 |
99.9% |
0.0 |
0.0% |
0.3 |
0.1% |
260.0 |
P43j-3 |
12 |
259.7 |
99.9% |
0.0 |
0.0% |
0.2 |
0.1% |
259.9 |
|
P43j-5 |
20 |
259.7 |
100.0% |
0.0 |
0.0% |
0.1 |
0.0% |
259.8 |
|
P43k-1 |
4 |
Ditto |
259.7 |
99.9% |
0.0 |
0.0% |
0.3 |
0.1% |
260.0 |
P43k-3 |
12 |
259.7 |
99.9% |
0.0 |
0.0% |
0.2 |
0.1% |
259.9 |
|
P43k-4 |
16 |
259.7 |
100.0% |
0.0 |
0.0% |
0.1 |
0.0% |
259.8 |
*Percentages in shaded cells represent the percentage
share of the total concentrations.
To ensure compliance with the TSP criteria during the construction phase, the relevant requirements stipulated in the Air Pollution Control (Construction Dust) Regulation and EPD’s Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) as well as the good practices for dust control should be implemented to reduce the dust impact. The dust control measures are detailed as follows:
Dust emissions could be suppressed by regular water spraying on site. In general, water spraying twice a day could reduce dust emission from active construction area by 50%. However, for this flyover road Project, more frequent water spraying, i.e., 12 times a day or once every one hour, is required for heavy construction activities at all active works area in order to achieve a higher dust suppression efficiency of 91.7% to reduce the dust impacts to acceptable levels. A watering intensity of 3.75 L/m2, 12 times a day or once every hour, is predicted to achieve 91.7% dust suppression efficiency. Detailed calculations can be found in Appendix 3.8. Heavy construction activities include construction of roads, drilling, ground excavation, cut and fill operations (i.e., earth moving), etc.
Best Practices for Dust Control
In addition to implementing the recommended dust control measures mentioned above, it is recommended that the relevant best practices for dust control as stipulated in the Air Pollution Control (Construction Dust) Regulation should also be adopted to further reduce the construction dust impacts of the Project. These best practices include:
Good Site Management
¡ Good site management is important to help reducing potential air quality impact down to an acceptable level. As a general guide, the Contractor should maintain high standard of housekeeping to prevent emission of fugitive dust. Loading, unloading, handling and storage of raw materials, wastes or by-products should be carried out in a manner so as to minimise the release of visible dust emission. Any piles of materials accumulated on or around the work areas should be cleaned up regularly. Cleaning, repair and maintenance of all plant facilities within the work areas should be carried out in a manner minimising generation of fugitive dust emissions. The material should be handled properly to prevent fugitive dust emission before cleaning.
Disturbed Parts of the Roads
¡ Each and every main temporary access should be paved with concrete, bituminous hardcore materials or metal plates and kept clear of dusty materials; or
¡ Unpaved parts of the road should be sprayed with water or a dust suppression chemical so as to keep the entire road surface wet.
Exposed Earth
¡ Exposed earth should be properly treated by compaction, hydroseeding, vegetation planting or seating with latex, vinyl, bitumen within six months after the last construction activity on the site or part of the site where the exposed earth lies.
Loading, Unloading or Transfer of Dusty Materials
¡ All dusty materials should be sprayed with water immediately prior to any loading or transfer operation so as to keep the dusty material wet.
Debris Handling
¡ Any debris should be covered entirely by impervious sheeting or stored in a debris collection area sheltered on the top and the three sides.
¡ Before debris is dumped into a chute, water should be sprayed so that it remains wet when it is dumped.
Transport of Dusty Materials
¡ Vehicle used for transporting dusty materials/spoils should be covered with tarpaulin or similar material. The cover should extend over the edges of the sides and tailboards.
Wheel washing
¡ Vehicle wheel washing facilities should be provided at each construction site exit. Immediately before leaving the construction site, every vehicle should be washed to remove any dusty materials from its body and wheels.
Use of vehicles
¡ The speed of the trucks within the site should be controlled to
about
¡ Immediately before leaving the construction site, every vehicle should be washed to remove any dusty materials from its body and wheels.
¡ Where a vehicle leaving the construction site is carrying a load of dusty materials, the load should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle.
Site hoarding
¡ Where a site boundary adjoins a road, street, service lane or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length of that portion of the site boundary except for a site entrance or exit.
Best Practices for Concrete Batching Plant
It is recommended that the relevant best
practices for dust control as stipulated in the Guidance Note on the Best Practicable Means for Cement Works (Concrete
Batching Plant) BPM 3/2 should also be adopted to further reduce the
construction dust impacts of the Project. These include:
Exhaust from Dust Arrestment Plant
¡ Wherever possible the final discharge point from particulate matter arrestment plant, where is not necessary to achieve dispersion from residual pollutants, should be at low level to minimise the effect on the local community in the case of abnormal emissions and to facilitate maintenance and inspection.
Emission Limits
¡ All emissions to air, other than steam or water vapour, shall be colourless and free from persistent mist or smoke
Engineering Design/Technical Requirements
¡ As a general guidance, the loading, unloading, handling and storage of fuel, raw materials, products, wastes or by-products should be carried out in a manner so as to prevent the release of visible dust and/or other noxious or offensive emissions
Detailed mitigation
methods and guidance can be found in the stand-alone EM&A Manual.
15.3.6.2 Operation Phase – Vehicular and Marine Emissions
Since
it has been assessed that all the ASRs would be in compliance with all the relevant
AQOs for SO2, NO2 and RSP, no mitigation measures for
vehicular or marine traffic emissions are required during the operation phase.
15.3.7 Evaluation of Cumulative and Residual Impacts
15.3.7.1 Construction Phase
It has been assessed that there would neither be exceedance of the hourly TSP limit under the Tier 2 mitigated scenario nor exceedance of the AQO for daily TSP under the Tier 1 mitigated scenario at any of the ASRs throughout the entire construction period. Similarly, no exceedance of the AQO for annual TSP was predicted at any of the ASRs for the entire construction period under the mitigated scenario. Hence no residual impacts are anticipated during the construction phase.
15.3.7.2 Operation Phase – Vehicular and
Marine Emissions
According to the modelling results,
all the identified ASRs would be in compliance with the corresponding AQO for
hourly, daily and annual SO2; for hourly, daily and annual NO2
as well as for daily and annual RSP. However, during the worst case
year of 2015, two existing ASRs, namely, SRT-1 and SRT-2, would be subject to
exceedance of the AQO for hourly NO2 (i.e., 300 μg/m3) by about 3.7-14.9 μg/m3 (or about 1.2%-5.0% of the relevant AQO)
for once a
year, and one planned ASR, namely, P37-1, would be subject to marginal exceedance
of the AQO for daily NO2 (i.e., 150 μg/m3) by about 0.2 μg/m3 (or about 0.1% of the relevant
AQO) for once a year. Since the numbers
of such hourly and daily NO2 exceedances are within the respective allowable
numbers of exceedances (3 times per year for hourly NO2 and once per
year for daily NO2), the AQO for hourly and daily NO2
would still be complied with at the three ASRs.
Hence, no residual impacts are anticipated during the operation phase
due to vehicular and marine emissions.
15.3.8 Environmental Monitoring and Audit
15.3.8.1 Construction Phase
Regular dust monitoring is considered necessary during the construction phase of the Project and regular site audits are also required to ensure the dust control measures are properly implemented. Details of the environmental monitoring and audit (EM&A) programme will be presented in the stand-alone EM&A Manual.
15.3.8.2 Operation Phase
Since it has been assessed that all the ASRs would be in compliance with all the relevant AQOs for SO2, NO2 and RSP, no residual air quality impacts due to vehicular or marine traffic emissions are anticipated. Therefore, no monitoring is considered necessary for vehicular or marine traffic emissions.
15.3.9 Conclusion
Construction
Phase
With implementation of the recommended
mitigation measures as well as the relevant control requirements as stipulated
in the Air Pollution Control
(Construction Dust) Regulation and EPD’s Guidance Note on the Best Practicable Means for Cement Works (Concrete
Batching Plant) BPM 3/2(93), it has been assessed that there
would neither be exceedance of the hourly TSP limit under
the Tier 2 mitigated scenario nor exceedance of the AQO for daily TSP under
the Tier 1 mitigated scenario at any of the ASRs throughout the entire
construction period. For annual TSP results, no exceedance of the
corresponding AQO was predicted at any of the ASRs during the construction phase
provided the recommended mitigation measures are in place.
Operation
Phase
Majority
of the vehicular emission sources and all marine emission sources are due to
respectively the nearby current/planned road networks serving the
According to the modelling results, all the
identified ASRs would be in compliance with the corresponding AQO for hourly,
daily and annual SO2; for hourly, daily and annual NO2 as
well as for daily and annual RSP. However, during
the worst case year of 2015, two existing ASRs, namely, SRT-1 and SRT-2, would
be subject to exceedance of the AQO for hourly NO2 (i.e., 300 μg/m3) by about 3.7-14.9 μg/m3 (or about 1.2%-5.0% of the relevant AQO) for once a year, and one planned ASR, namely, P37-1,
would be subject to marginal exceedance of the AQO for daily NO2 (i.e.,
150
μg/m3) by about 0.2 μg/m3
(or about 0.1% of the relevant AQO) for once
a year. Since the numbers of such hourly
and daily NO2 exceedances are within the respective allowable numbers
of exceedances (3 times per year for hourly NO2 and once per year
for daily NO2), the AQO for hourly and daily NO2 would
still be complied with at the three ASRs.
In conclusion, no adverse air quality impacts due to vehicular or marine traffic emissions are anticipated during the operation phase of the WKCD Project.
This
section presents the assessment of the potential noise impacts associated with the construction and operation
phases of the proposed Austin Road Flyover in WKCD. Noise generated from
various construction activities is the primary concern during the construction
phase. Road traffic noise is the major noise impact during the operation phase.
Representative Noise Sensitive Receivers (NSRs) within
15.4.1 Noise Legislations, Standards and Guidelines
15.4.1.1 Construction Phase
Control
over the generation of construction noise in
¡ TM on Environmental Impact Assessment Process (
¡ TM on Noise from Construction Work other than Percussive Piling (GW-TM)
¡ TM on Noise from Construction Work in Designated Areas (DA-TM)
15.4.1.2 General Construction Activities during Non-Restricted Hours
Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) are assessed against the noise standards tabulated in Table 15.4.1 below.
Table 15.4.1: Noise Standards for Daytime Construction Activities
Noise Sensitive Uses |
0700 to 1900
hours on any day not being a Sunday or general holiday, Leq (30
min), dB(A) |
All domestic premises including
temporary housing accommodation |
75 |
Hotels and hostel |
|
Educational institutions
including kindergarten, nurseries and all others where unaided voice
communication is required |
70 65 during examination |
Source:
Note: The above noise standards apply to uses,
which rely on opened windows for ventilation
The
above standards shall be viewed as the maximum permissible noise levels
assessed at
The
above standards shall be met as far as possible. All practicable mitigation measures shall be
exhausted and the residual impacts are minimised
15.4.1.3 General Construction Activities during Restricted Hours
Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the NCO.
For carrying out of any general construction activities involving the use of any Powered Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in the GW-TM under the NCO.
The use of Specified PME (SPME) and/or the carrying out of Prescribed Construction Work (PCW) within a Designated Area (DA) under the NCO during the restricted hours are also prohibited without a CNP. The relevant technical details in Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO can be referred.
Designated
areas, in which the control of SPME and PCW shall apply, are established
through the Noise Control (Construction Work Designated Areas) Notice made
under Section
Regardless of any description or assessment made in this section, in assessing a filed application for a CNP the Authority will be guided by the relevant Technical Memoranda. The Authority will consider all the factors affecting their decision taking contemporary situations/ conditions into account. Nothing in this Report shall pre-empt the Authority in making their decisions, and there is no guarantee that a CNP will be issued. If a CNP is to be issued, the Authority may include any conditions they consider appropriate and such conditions are to be followed while the works covered by the CNP are being carried out. Failing to do so may lead to cancellation of the permit and prosecution action under the NCO.
According to the construction programme, the proposed construction works would be carried out during non-restricted hours. In case of any construction activities during restricted hours, it is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs. The Contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.
15.4.1.4 Operation Phase - Road Traffic Noise
The
Table 15.4.2: Relevant Road Traffic Noise Standards for Planning Purposes
Uses |
L10
(1hour), dB(A) |
|
All domestic premises including
temporary housing accommodation |
70 |
|
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
65 |
|
Notes: (i) The above standards apply to uses which rely on opened windows for ventilation
(ii) The above standards should be viewed as the
maximum permissible noise levels assessed at
15.4.2 Baseline Conditions
15.4.2.1 Assessment Study Area
The Assessment
Study Area is defined as within
15.4.2.2 Description of the Environment
Site
visits were conducted in June, July
and August 2011 to understand
the existing environment in the vicinity of the Project site. This Project site
is surrounded by the areas with residential, commercial and recreational uses.
The existing noise environment is dominated by the road traffic noise from
15.4.2.3 Identification of Noise Sensitive Receivers
Noise
Sensitive Receivers (NSRs) have been identified in accordance with Annex 13 of
the
For the purpose of noise assessment, the first layer of residential premises located close to the site boundary have been selected as assessment points/ identified representative NSRs within the Assessment Area for prediction of noise impact levels.
According
to the Outline Zoning Plans (“the Approved South
As residential development is expected within the WKCD, planned NSRs are also identified within the 300m area for assessment of the potential noise impact to the residential premises within the WKCD development.
Descriptions of selected representative NSRs are tabulated in Table 15.4.3. The representative NSRs for construction noise impact assessment are shown in the Figures 4.2a to 4.2j. The representative NSRs for road traffic noise impact assessment are shown in the Figure 4.3. Photos of existing noise sensitive receivers are shown in Figures 4.5.
Table 15.4.3: Representative Noise Sensitive Receivers
No. |
NSR ID |
Description |
Use |
Existing/ Planned |
No. of Storeys (Sensitive use only) |
1st Assessment Level (mPD) |
Area Sensitivity Rating |
Noise Impact Assessment |
|
Construction |
Road Traffic |
||||||||
1 |
HT1 |
The |
Residential |
Existing |
65 |
40 |
N/A |
√ |
√ |
2 |
HT3 |
The |
Residential |
Existing |
65 |
40 |
N/A |
√ |
√ |
3 |
P29* |
Parcel 29 in WKCD |
Residential |
Planned |
16 |
37 |
B |
|
√ |
Note: (N/A) Not Applicable
* P29 is a planned NSR within the WKCD and is scheduled for occupation in 2019 while the construction period of Flyover is completed. Therefore, this NSR is not included in construction noise impact assessment.
15.4.3 Identification of Pollution Sources
15.4.3.1 Construction Noise
The major construction activities involved in the Project are site formation, construction of basement structures and construction of flyover. The construction period of the flyover is scheduled between July of 2014 and June of 2017.
As mentioned in Section 15.2.8, the construction programme of this WKCD Project would overlap with other several construction projects including Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL), Road Works at West Kowloon and Proposed Road Improvement Works in West Kowloon Reclamation Development Phase 1. Construction noise from these projects was also identified as key noise sources to the identified NSRs under this Project.
15.4.3.2 Road Traffic Noise
During the operational phase, noise sensitive facades may be impacted by road traffic noise from roads surrounding WKCD. Austin Road West, the proposed flyover, other existing roads and roads of other committed projects are potential sources of the road traffic noise impact.
15.4.4 Assessment Methodology
15.4.4.1 Construction Noise
Assessment approach to the noise impact is in line with the Guidance Note titled “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2010).
In addition, the assessment of construction noise impact is based on standard acoustic principles, and the guidelines given in GW-TM issued under the NCO where appropriate. Where no sound power level (SWL) can be found in the relevant TM, reference has been made to BS 5228 Part 1:2009 or noise emission levels measured for PME used in previous projects in Hong Kong. The general approach is summarized below:
i. Formulate a typical construction schedule/ programme;
ii. Identify a typical project-specific equipment inventory for each work stage together with the number;
iii. Obtain from GW-TM, the Sound Power Level (SWL) for each PME assumed in the equipment inventory;
ii. Select representative NSRs for the construction noise impact assessment;
iii. Calculate the unmitigated Predicted Noise Level (PNL) and correct it for facade reflection to obtain the Corrected Noise Level (CNL) at any NSRs;
iv. If necessary, re-select typical project-specific silenced equipment and calculate the mitigated noise impact;
v. Compare the mitigated CNL with the noise standards to determine acceptability and the need for further mitigation.
The calculation methodology is estimated with the following standard formula (1):
SPL = SWL – DC + FC (1)
where
Sound Pressure Levels, SPL in dB(A)
Sound Power Levels, SWL in dB(A)
Distance Attenuation, DC in dB(A) = 20∙log(D)+8 (where D is the distance between
NSRs and noise source in meters)
Façade Correction, FC in dB(A)
= 3dB(A)
For the cumulative noise impact during
construction phase, projects which included Express Rail Link, Road Works at West Kowloon and Road Improvement
Works in West Kowloon Reclamation Development were considered in the noise
assessment. The
In addition, a current concrete batching plant (CBP) of XRL at east of Project area as shown in Figures 4.2b to 4.2e will be handed over to WKCDA in year 2014. The operation, demolition and relocation of that CBP have been taken into account in the construction noise impact assessment accordingly. It is assumed that the CBP will be relocated to the west of Project area in year 2017 for worst case scenario consideration as shown in Figures 4.2f to 4.2i.
15.4.4.2 Road Traffic Noise
Road
traffic noise levels at the representative assessment points will be calculated
based on the peak hour traffic flow within a 15 years period upon commencement
of operation of the Project i.e. the assessment year. Traffic noise will be predicted using the
model “RoadNoise”, which has been used before in other similar
The
planned noise sensitive use facades within WKCD and vicinity NSRs may have
potential road traffic noise impact from major roads surrounding WKCD. The peak hour traffic flows of the
surrounding road links and the locations of the road links are shown in Appendix 4.2a for the scenario with the proposed
flyover in place. As the PM peak hour traffic flows of those dominant
surrounding road links are higher than that during the AM peak hour, the PM
peak hour traffic flow will be adopted in the assessment. The key plans for
WKCD external road links and the flyover are shown in Appendices 4.2b and 4.2c
respectively.
An assessment of the unmitigated road traffic
noise levels at the representative NSRs in the assessment year has been carried
out. If exceedance of the relevant road
traffic noise criteria is predicted, direct noise mitigation measures will be
considered. In case the proposed direct noise
mitigation measures could not be implemented due to site constraints and other uncertainties, indirect noise
mitigation measures have also been
considered.
Other than the existing road sections paved with low noise surfacing, the extent of low noise road surfacing, barriers and semi-enclosures proposed in the Road Works at West Kowloon project have also been considered in the unmitigated scenario of the road traffic noise impact assessment.
15.4.5 Evaluation and Assessment of the Noise Impacts
The type and quantity of Powered Mechanical Equipment (PME) likely to be used for the site formation works and construction of the proposed flyover and their Sound Power Levels (SWLs) are shown in Appendices 4.4a to 4.4i.
According to the tentative construction
programme, it is likely that there will be an overlap of this Project with some
other potentially concurrent projects including “Express Rail Link”, and
“Road Works at West Kowloon”, and
“Road Improvement Works in West Kowloon Reclamation Development”. These projects are described in Section 15.2.8. MTRCL has recently confirmed that the
assumptions adopted in the approved Road Works at West Kowloon and XRL
The unmitigated predicted noise levels are
presented in Table 15.4.4
below. Details of the construction noise impact at the representative NSRs are
shown in Appendices 4.4a to 4.4i.
The prediction results indicate that the noise impact of unmitigated construction activities from the flyover would not cause exceedance of the relevant daytime construction noise criteria. However, upon the inclusion of cumulative noise impact from concurrent projects, the overall construction noise level will exceed the relevant criteria. It is noted that construction noise from WKCD is the dominant noise source. Mitigation measures are expected to be implemented during the construction of WKCD, and it is predicted that all NSRs will comply with the relevant noise level after mitigation. Details of mitigated construction noise impact are shown in Appendices 4.10a to 4.10i.
Table 15.4.4: Unmitigated Construction Airborne Noise
Impact
NSR ID |
Use |
Noise Source |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Mitigation Measure required? |
||||
|
2014 |
2015 |
2016 |
2017 |
Overall |
|||||
HT1 |
Residential |
Flyover |
61 |
61 |
61 |
61 |
61 |
75 |
No |
No |
|
|
Flyover and Other Projects including WKCD |
80-85 |
79-84 |
79-81 |
77-79 |
77-85 |
75 |
Yes |
Yes |
HT3 |
Residential |
Flyover |
65 |
65 |
65 |
65 |
65 |
75 |
No |
No |
|
|
Flyover and Other Projects including WKCD |
79-83 |
79-83 |
79-80 |
76-78 |
76-83 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
The operation of the proposed flyover is scheduled to be commenced in 2017. According to the projection of the traffic impact assessment, the year with maximum traffic flow within a 15-year period upon commencement of operation of the proposed flyover is determined to be 2032. Therefore, the peak hour traffic data for year 2032 has been adopted for the assessment. After reviewing the morning and afternoon peak hour flow data, the afternoon peak hour flow data was chosen for the assessment as greater noise impact shall be predicted at the NSRs in WKCD.
The potential unmitigated road traffic noise impacts on the NSRs for the Project at Year 2032 due to operation of the proposed flyover, as well as the overall noise impacts cumulating with other existing and planned road sections nearby have been assessed. The proposed underpass will be connected to the Austin Road West in the interim scheme before permanently connected to the Canton Road after the relocation of TST Fire station. The worst traffic noise impact to the identified NSRs within a 15 year period upon commencement of the operation proposed flyover will be assessed under these two schemes.
The assessment results are summarised in Table 15.4.5 and Table 15.4.6 below for the scenario with interim access to the proposed underpass of the WKCD Project at Austin Road West and the scenario with permanent access to the proposed underpass of the
WKCD Project at Canton Road respectively. Detailed breakdowns of road traffic noise
impacts are shown in Appendices 15.4.1
and 15.4.2.
Locations
of road plots are shown in Appendix 4.5e.
Table 15.4.5: Unmitigated Road Traffic Noise Impact in Year 2032 – Scenario with Interim
Access to the Proposed Underpass of the WKCD Project at Austin Road West
NSR ID |
Noise Criteria, L10(1
hr) dB(A) |
Predicted Road Traffic Noise Level, L10 (1hr) dB(A) |
||
Proposed Flyover |
Overall |
Contribution from Proposed Flyover |
||
HT1 |
70 |
N/A* |
69 - 72 |
0.0 |
HT3 |
70 |
21 - 35 |
69 - 71 |
0.0 |
P29 |
70 |
45 - 47 |
72 |
0.0 - 0.1 |
Note: * Road traffic noise level of Project road is
negligible.
Bold figures denotes the predicted noise level is exceeded the relevant traffic noise criteria.
Table 15.4.6: Unmitigated Road Traffic Noise Impact in Year 2032 – Scenario with Permanent Access to
the Proposed Underpass of the WKCD Project at Canton Road
NSR ID |
Noise Criteria, L10(1
hr) dB(A) |
Predicted Road Traffic Noise Level, L10 (1hr) dB(A) |
||
Proposed Flyover |
Overall |
Contribution from Proposed Flyover |
||
HT1 |
70 |
N/A* |
69 - 72 |
0.0 |
HT3 |
70 |
21 - 35 |
69 - 71 |
0.0 |
P29 |
70 |
45 - 47 |
72 |
0.0 - 0.1 |
Note: * Road traffic noise level of Project road is
negligible.
Bold figures denotes the predicted noise level is exceeded the relevant traffic noise criteria.
Noise
levels of the selected representative NSRs were found exceeding the relevant
noise criteria. However, the exceedances were found dominated by the
contributions of the noise from the surrounding
existing and committed Road Works at West Kowloon road sections. The
noise contributions from the Project’s proposed flyover are estimated to be
less than 1.0 dB(A) and the road traffic noise levels of
the proposed roads are all below the noise criterion of 70 dB(A). Direct noise
mitigation measures on the Project road sections are deemed not necessary as
they would be ineffective in improving the noise environment at the NSRs. Therefore,
the proposed flyover of this Project is not expected to have a significant
contribution to the overall road traffic noise impact and no noise mitigation
measure is required.
An assessment of the scenario without the proposed flyover has been conducted and the results with detailed breakdown of road traffic noise impacts are shown in Appendix 15.4.3 for reference. The peak hour traffic flows of the surrounding road links and the locations of the road links are shown in Appendix 15.4.4 for the scenario without the proposed flyover.
15.4.6 Mitigation Measures
15.4.6.1 Construction Noise
As discussed in Section 15.4.5.1, no exceedance of construction noise level is predicted from the flyover. Nevertheless, the contractor is recommended to implement the following measures to reduce the potential noise impact from construction activities:
¡ good site practice to limit noise emissions at source;
¡ selection of quieter plant;
¡ use of movable noise barrier;
¡ use of noise enclosure/ acoustic shed, and
¡ use of noise insulating fabric.
While it is recognised that the Contractor may develop a different package of mitigation measures to meet the required noise standards, the following suite of practical and implementable measures demonstrate an approach that would be feasible to reduce noise levels.
Good Site Practice
Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs. The following package of measures should be followed during each phase of construction:
¡ only well-maintained plant to be operated on-site and plant should be serviced regularly during the construction works;
¡ machines and plant that may be in intermittent use to be shut down between work periods or should be throttled down to a minimum;
¡ plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
¡ mobile plant should be sited as far away from NSRs as possible; and
¡ material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities.
Selecting Quieter Plant
The Contractor may be able to obtain particular models of plant that are quieter than the standards given in the GW-TM. This is one of the most effective measures and is increasingly practicable because of the availability of quiet equipment.
Quiet
plant whose actual SWL is less than the value specified in GW-TM for the same
piece of equipment. SWLs for specific silenced PME can be referenced from EPD’s
QPME Inventory and “Sound Power Levels of
Other Commonly Used PME”. It should
be noted that various types of silenced equipment can be found in
Use of Movable Noise Barriers
Movable noise barriers can be very effective in screening noise from particular items of plant when constructing the Project. Noise barriers located along the active works area close to the noise generating component of a PME could produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided the direct line of sight between the PME and the NSRs is blocked. A schematic configuration of a single movable noise barrier for PME is shown in Figure 4.9.
Use of Noise Enclosure/ Acoustic Shed
The
use of noise enclosure or acoustic shed is to cover stationary PME such as air
compressor and concrete pump. With the
adoption of the noise enclosure, the PME could be completely screened, and
noise reduction of 15 dB(A) can be achieved according
to the
Use of Noise Insulating Fabric
Noise
insulating fabric can also be adopted for certain PME (e.g. drill rig, pilling
machine etc). The fabric should be
lapped such that there are no openings or gaps on the joints. According to the approved Tsim Sha Tsui
Station Northern Subway
These enclosures and noise barriers should be free of gaps and made of materials having a surface mass density in excess of 10 kg/m2. To improve the effectiveness of noise reduction, non-flammable absorptive lining can be adhered on the inner surface of the noise barriers. The barrier can be in the form of vertical or bend top barrier with an effective height to block the line of sight to NSRs.
Mitigated Construction Noise Impacts
With
the incorporation of quiet plant and the use of movable noise barriers,
enclosure and insulating fabric, the results indicated that the mitigated noise
impact associated with the construction of the Project would comply with the daytime construction noise
criterion at all representative NSRs.
The effect of the use of quiet plant and using movable barriers, enclosure and insulating fabric has been investigated for the practicable construction activities. The mitigated noise levels from the construction of the flyover and overall cumulative construction noise levels with other projects are presented in Table 15.4.7. Mitigated Construction Plant Inventory and details of the mitigated construction noise impact are shown in Appendices 4.10a to 4.10i.
Table 15.4.7: Cumulative Mitigated Construction Airborne
Noise Impact
NSR ID |
Use |
Noise Source |
Predicted Noise Level dB(A) |
|
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Mitigation Measure required? |
|||
|
2014 |
2015 |
2016 |
2017 |
Overall |
|||||
HT1 |
Residential |
Flyover |
52 |
52 |
52 |
52 |
52 |
75 |
No |
No |
|
|
Flyover and Other Projects including WKCD |
70-75 |
68-70 |
69-70 |
68-70 |
68-75 |
75 |
No |
No |
HT3 |
Residential |
Flyover |
55 |
55 |
55 |
55 |
55 |
75 |
No |
No |
|
|
Flyover and Other Projects including WKCD |
69-74 |
67-69 |
69-70 |
67-70 |
69-74 |
75 |
No |
No |
15.4.6.2 Road Traffic Noise
The noise contributions from the Project’s proposed flyover are estimated to be less than 1.0 dB(A) and the road traffic noise levels of the proposed roads are all below the noise criterion of 70 dB(A). No adverse noise impacts arising from the proposed flyover would be predicted at any of the representative NSRs and hence no mitigation measure is required.
15.4.7 Evaluation of Cumulative and Residual Impacts
15.4.7.1
Construction Phase
No exceedance of relevant noise level from the flyover is predicted. With the implementation of mitigation measures during WKCD construction, the cumulative construction noise impact is expected to comply with the relevant noise level. Therefore, residual construction noise impact is not anticipated.
15.4.7.2 Operation Phase
Exceedance of the road traffic noise criteria was predicted at three representative sensitive receivers, two are existing residential development and the other is a planned residential use. However, the road noise contributions from the flyover to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the road noise levels of the flyover would all be below the relevant noise criteria. Adverse impact arising from the flyover is not anticipated at any of representative NSR.
15.4.8 Environmental Monitoring and Audit
15.4.8.1 Construction Phase
Though no residual noise impact is predicted during the construction of the flyover, an Environmental Monitoring and Audit (EM&A) programme is recommended to ensure that nearby NSRs will not be subjected to unacceptable construction noise impact. Details of the noise monitoring requirements, methodology and action plans would be described in a separate EM&A Manual.
15.4.8.2 Operation Phase
No adverse noise impact is anticipated from the operation of the flyover, hence no monitoring is considered necessary.
15.4.9 Conclusion
15.4.9.1 Construction Phase
The construction phase noise impact
assessment has been made based on the best available information. The
construction noise levels at all representative NSRs are predicted to comply
with the noise standards stipulated in the
15.4.9.2 Operation Phase
The
potential road traffic noise impacts have been assessed based on the peak
traffic flows in 2032. The noise levels predicted at the representative NSRs
would range from 69 to 72 dB(A). Road traffic noise is
predicted to be dominant by the existing and committed Road Works at
This
section presents an assessment of potential water quality impacts which may
arise from the construction and operational stages of proposed
15.5.1 Water Quality Legislations, Standards and Guidelines
The criteria for evaluating water quality impacts include the following:
¡ Water Pollution Control Ordinance (WPCO) Cap. 358;
¡ Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS); and
¡ Practice Note for Professional Persons on Construction Site Drainage (ProPECC Note PN 1/94).
15.5.1.1 Water Pollution Control Ordinance (WPCO)
The Water Pollution Control Ordinance (WPCO) (Cap. 358) provides
the statutory framework for the protection and control of water quality in
Table
15.5.1: Water Quality
Objectives for
Parameters |
Objectives |
Sub-Zone |
Offensive Odour, Tints |
Not to be present |
Whole zone |
Colour |
Not to exceed 50 Hazen units, due to human activity |
Inland waters |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E. coli |
Not to exceed 1000 per 100mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days |
Inland waters |
Dissolved Oxygen (DO) within 2 m of the seabed |
Not less than 2
mg L-1 for 90% of the
sampling occasions during the whole year |
Marine waters |
Depth-averaged DO |
Not less than 4
mg L-1 for 90% of the
sampling occasions during the whole year; values should be calculated as the
annual water column average (expressed normally as the arithmetic mean of at
least 3 measurements at 1m below surface, mid depth and 1m above the seabed.
However in water of a depth of 5m of less the mean shall be that of 2
measurements – 1m below surface and 1m above seabed,
and in water of less than 3m the 1m below surface sample only shall apply.) |
Marine waters |
Dissolved Oxygen (DO) |
Not less than 4 mg L-1 |
Inland waters |
pH |
To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended Solids (SS) |
Not to raise the ambient level by 30% caused by human activity |
Marine waters |
|
Annual median not to exceed 25 mgL-1 due to human activity |
Inland waters |
Unionised Ammonia (UIA) |
Annual mean not to exceed 0.021 mg L-1 as unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
|
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1 |
Marine waters |
BOD5 |
Not to exceed 5 mg L-1 |
Inland waters |
|
Not to exceed 30 mg L-1 |
Inland waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
|
Human activity should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (
Table 15.5.2: Water Quality Objectives for the Western Buffer WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive Odour, Tints |
Not to be present |
Whole zone |
Colour |
Not to exceed 30 Hazen units, due to human activity |
Water gathering ground subzones |
|
Not to exceed 50 Hazen units, due to human activity |
Other inland waters |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E. coli |
Not to exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in a calendar year |
Secondary contact recreation subzones and Fish culture subzones |
|
Not to exceed 180
per 100 mL, calculated as the geometric mean of all samples collected from
March to October inclusive in 1 calendar year. Samples should be taken at
least 3 times in 1 calendar month at intervals of between 3 and 14 days |
Recreation subzones |
|
Less than 1 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days |
Water gathering ground subzones |
|
Not to exceed 1000 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days |
Other Inland waters |
Depth-averaged Dissolved Oxygen (DO) |
Not less than 4
mg L-1 for 90% of the
sampling occasions during the whole year; values should be calculated as
water column average (arithmetic mean of at least 3 measurements at 1m below
surface, mid-depth and 1m above seabed) |
Marine waters except Fish culture subzones |
|
Not less than 5 mg L-1 for 90% of the sampling occasions during the year; values should be calculated as water column average (arithmetic mean of at least 3 measurements at 1m below surface, mid-depth and 1m above seabed) |
Fish culture subzones |
Dissolved Oxygen (DO) within 2 m of the seabed |
Not less than 2
mg L-1 for 90% of the
sampling occasions during the whole year |
Marine waters and Fish culture subzones |
Dissolved Oxygen (DO) |
Not less than 4 mg L-1 |
Water gathering ground subzones and other inland waters |
pH |
To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
|
Not to exceed the range of 6.0 – 8.5 due to human activity |
Water gathering ground subzones |
|
Not to exceed the range of 6.0 - 9.0 due to human activity |
Other inland waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended Solids (SS) |
Not to raise the
ambient level by 30% caused by human activity and shall not accumulate
to affect aquatic communities |
Marine waters |
|
Annual median not to exceed 20 mg L-1 due to human activity |
Water gathering ground subzones |
|
Annual median not to exceed 25 mg L-1 due to human activity |
Other inland waters |
Unionised ammonia (UIA) |
Annual mean not to exceed 0.021 mg L-1 as unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
|
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1 |
Marine waters |
5-day
biochemical oxygen demand (BOD5) |
Not to exceed 3 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 5 mg L-1 |
Other inland waters |
Chemical Oxygen Demand (COD) |
Not to exceed 15 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 30 mg L-1 |
Other inland waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
|
Human activity should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (Western Buffer Water Control Zone).
Table 15.5.3: Water Quality Objectives for the Eastern Buffer WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive Odour, Tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within |
Not less than 2 mg L-1 for 90% of the sampling occasions during the whole year |
Marine waters and Fish culture subzones |
Depth-averaged DO |
Not less than 4 mg L-1 for 90% of the sampling occasions during the whole year; values should be calculated as water column average (arithmetic mean of at least 3 measurements at 1m below surface, mid-depth and 1m above seabed) |
Marine waters excepting fish culture subzones |
|
Not less than 5 mg L-1 for 90% of the sampling occasions during the year; values should be calculated as water column average (arithmetic mean of at least 3 measurements at 1m below surface, mid-depth and 1m above seabed) |
Fish culture subzones |
|
Not less than 4 mg L-1 |
Water gathering ground subzone and other inland waters |
5-day biochemical oxygen demand (BOD5) |
Not to exceed 3 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 5 mg L-1 |
Other inland waters |
Chemical oxygen demand (COD) |
Not to exceed 15 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 30 mg L-1 |
Other inland waters |
pH |
To be in the range of 6.5 – 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
|
To be in the range of 6.5 – 8.5 |
Water gathering ground subzones |
|
To be in the range of 6.0 – 9.0 |
Other inland waters |
Salinity |
Change due to waste discharges not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to waste discharges not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human activity and shall not accumulate to affect aquatic communities |
Marine waters |
|
Change due to human activity not to exceed 20 mg L-1 of annual median |
Water gathering ground subzones |
|
Change due to human activity not to exceed 25 mg L-1 of annual median |
Other inland waters |
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021mg L-1 as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
|
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1 |
Marine waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
|
Human activity should not cause a risk to any beneficial use of the aquatic environment |
Whole zone |
E. coli |
Not exceed 610 per 100mL, calculated as the geometric mean of all samples collected in one calendar year |
Fish culture subzones |
|
Less than 1 per 100mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days |
Water gathering ground subzones |
|
Not exceed 1000 per 100mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days |
Other inland waters |
Colour |
Change due to human activity not to exceed 30 Hazen units |
Water gathering ground |
|
Change due to human activity not to exceed 50 Hazen units |
Other inland waters |
Source: Statement of
Water Quality Objectives (Eastern Buffer Water Control Zone).
Discharges
of effluents are subject to control under the WPCO. The Technical Memorandum on Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) sets
limits for effluent discharges. Specific limits apply for different areas and
are different between surface waters and sewers. The limits vary with the rate
of effluent flow. Sewage from the proposed construction activities should
comply with the standards for effluent discharged into foul sewers, inshore
waters or marine waters of the
15.5.1.3 Practice Note for Professional
Persons on Construction Site Drainage (ProPECC Note PN 1/94)
A practice note for professional persons was issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The Practice Note for Professional Persons on Construction Site Drainage (ProPECC Note PN 1/94) provides good practice guidelines for dealing with various types of discharge from a construction site. Practices outlined in ProPECC Note PN 1/94 should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.
15.5.2 Assessment Area, Water Sensitive Receivers and Baseline Conditions
15.5.2.1 Assessment Area
Water
quality impact assessment had been carried out in the
15.5.2.2 Water Sensitive Receivers
Key water sensitive receivers that may potentially be affected by the proposed flyover include:
¡ Yau Ma Tei Typhoon Shelter;
¡ WSD
¡ Cooling Water Intakes; and
¡ Fish Culture Zones.
Locations of the key water sensitive receivers are shown in Figure 15.5.2.
15.5.2.3 Baseline Conditions
Marine Water Quality in
A summary of marine water quality data for EPD monitoring stations at Victoria Harbour (VM6 and 7), and Stonecutters Island (VM15) extracted from EPD’s publication “Marine Water Quality in Hong Kong 2010” are presented in Table 15.5.4. Locations of these monitoring stations are shown in Figure 15.5.1.
Table 15.5.4: Marine Water Quality at
Parameter |
Monitoring Station |
||
|
|
(West) |
|
|
VM6 |
VM7 |
VM15 |
Temperature (oC) |
23.2 (16.6 – 27.7) |
23.0 (17.9 – 27.2) |
23.4 (16.8 – 27.6) |
Salinity |
31.4 (28.8 – 33.4) |
31.2 (26.1 – 33.3) |
31.0 (26.7 – 33.5) |
Dissolved Oxygen (mg/L) |
5.2 (3.6 – 6.5) |
5.8 (4.5 – 7.5) |
5.5 (3.9 – 6.3) |
Dissolved Oxygen (Bottom) (mg/L) |
4.2 (1.9 – 5.2) |
5.6 (3.4 – 7.0) |
4.8 (1.3 – 6.4) |
pH |
7.9 (7.6 – 8.2) |
7.9 (7.6 – 8.2) |
7.9 (7.6 – 8.2) |
Secchi Disc Depth (m) |
2.7 (1.0 – 5.2) |
2.7 (1.7 – 4.0) |
2.4 (1.2 – 3.6) |
Turbidity (NTU) |
3.1 (1.0 – 5.5) |
3.5 (1.0 – 6.6) |
3.7 (1.3 – 7.5) |
Suspended Solids (mg/L) |
3.5 (1.0 – 6.9) |
3.8 (1.6 – 5.6) |
4.2 (1.3 – 8.7) |
BOD5 (mg/L) |
1.0 (0.6 – 1.7) |
1.0 (0.5 – 1.8) |
0.9 (0.5 – 2.0) |
Ammonia Nitrogen (mg/L) |
0.177 (0.109 – 0.310) |
0.163 (0.090 – 0.293) |
0.199 (0.114 – 0.333) |
Unionised Ammonia (mg/L) |
0.006 (0.002 – 0.018) |
0.005 (0.002 – 0.014) |
0.007 (0.002 – 0.021) |
Nitrite Nitrogen (mg/L) |
0.031 (0.009 – 0.053) |
0.034 (0.016 – 0.078) |
0.034 (0.012 – 0.057) |
Nitrate Nitrogen (mg/L) |
0.141 (0.051 – 0.270) |
0.157 (0.068 – 0.347) |
0.147 (0.046 – 0.307) |
Total Inorganic Nitrogen (mg/L) |
0.35 (0.19 – 0.51) |
0.35 (0.20 – 0.49) |
0.38 (0.18 – 0.62) |
Total
Kjeldahl Nitrogen (mg/L) |
0.32 (0.23 – 0.47) |
0.35 (0.25 – 0.48) |
0.34 (0.23 – 0.47) |
Total Nitrogen (mg/L) |
0.49 (0.30 – 0.67) |
0.55 (0.45 – 0.65) |
0.53 (0.29 – 0.73) |
Orthophosphate Phosphorus (mg/L) |
0.030 (0.017 – 0.048) |
0.025 (0.008 – 0.039) |
0.031 (0.016 – 0.046) |
Total Phosphorus (mg/L) |
0.05 (0.03 – 0.06) |
0.05 (0.04 – 0.06) |
0.05 (0.04 – 0.06) |
Silica (SiO2) (mg/L) |
0.91 (0.36 – 1.80) |
0.81 (0.13 – 2.13) |
0.93 (0.16 – 1.87) |
Chlorophyll-a (µg/L) |
3.3 (0.3 – 15.6) |
5.0 (0.4 – 13.7) |
4.1 (0.2 – 21.8) |
E.coli (count/100mL) |
4400 (550 – 13000) |
2800 (520 – 16000) |
1800 (430 – 5900) |
Faecal Coliforms (count/100mL) |
11000 (1300 – 29000) |
6100 (1000 – 28000) |
4600 (880 – 28000) |
Notes: Unless otherwise specified, data represented are depth-averaged (A) values calculated by taking the means of three depths: Surface (S), Mid-depth (M), Bottom (B) Data presented are annual arithmetic means the depth-averaged results except for E.coli and faecal coliforms which are annual geometric means. Data in brackets indicated the ranges. |
Marine Water Quality in Yau Ma Tei Typhoon Shelter
A summary of marine water quality data for EPD monitoring stations at Yau Ma Tei Typhoon Shelter (VT10) extracted from EPD’s publication “Marine Water Quality in Hong Kong 2010” are presented in Table 15.5.5. Location of this monitoring station is shown in Figure 15.5.1.
Table 15.5.5: Marine Water Quality at Yau Ma Tei Typhoon Shelter in 2010
Parameter |
Yau Mei Tei |
|
VT10 |
Temperature (oC) |
23.6 (18.2 – 27.9) |
Salinity |
30.8 (29.1 – 31.8) |
Dissolved Oxygen (mg/L) |
4.1 (1.6 – 5.1) |
Dissolved Oxygen (Bottom) (mg/L) |
4.5 (3.1 – 5.6) |
pH |
7.7 (7.5 – 7.8) |
Secchi Disc Depth (m) |
1.8 (1.0 – 2.7) |
Turbidity (NTU) |
5.9 (1.3 – 13.6) |
Suspended Solids (mg/L) |
6.9 (2.8 – 15.5) |
BOD5 (mg/L) |
1.3 (1.0 – 1.8) |
Ammonia Nitrogen (mg/L) |
0.309 (0.193 – 0.450) |
Unionised Ammonia (mg/L) |
0.006 (0.003 – 0.011) |
Nitrite Nitrogen (mg/L) |
0.038 (0.023 – 0.050) |
Nitrate Nitrogen (mg/L) |
0.147 (0.097 – 0.200) |
Total Inorganic Nitrogen (mg/L) |
0.49 (0.37 – 0.64) |
Total
Kjeldahl Nitrogen (mg/L) |
0.50 (0.41 – 0.66) |
Total Nitrogen (mg/L) |
0.68 (0.59 – 0.85) |
Orthophosphate Phosphorus (mg/L) |
0.040 (0.024 – 0.051) |
Total Phosphorus (mg/L) |
0.06 (0.04 – 0.07) |
Silica
(as SiO2) (mg/L) |
0.83 (0.12 – 1.23) |
Chlorophyll-a (µg/L) |
6.6 (0.8 – 21.3) |
E.coli (count/100mL) |
2800 (1500 – 35000) |
Faecal Coliforms (count/100mL) |
7400 (2700 – 71000) |
Notes: Unless otherwise specified, data represented are depth-averaged (A) values calculated by taking the means of three depths: Surface (S), Mid-depth (M), Bottom (B) Data presented are annual arithmetic means the depth-averaged results except for E.coli and faecal coliforms which are annual geometric means. Data in brackets indicated the ranges. |
15.5.3 Identification of Water Quality Impact
15.5.3.1 Construction Phase
Potential sources of water quality impact associated with the construction activities for the proposed flyover for the WKCD development had been identified. These include:
¡ Construction site runoff and drainage;
¡ Sewage effluent from construction workforce; and
¡ General construction activities.
15.5.3.2 Operation Phase
During operation phase, the only potential source of water quality impact associated with operation of the proposed flyover is road and surface runoff.
15.5.4 Evaluation of Water Quality Impact
15.5.4.1 Construction Phase
Construction site runoff and drainage
Runoff
from the surface construction works areas may contain increased loads of
sediments, other suspended solids (SS) and contaminants. Potential sources of
pollution from site drainage include:
¡ Runoff
from and erosion from site surfaces, drainage channels, earth working areas and
stockpiles;
¡ Release
of any bentonite slurries, concrete washings and other grouting materials with
construction run-off and storm water;
¡ Wash
water from dust suppression sprays and wheel wash facilities; and
¡ Fuel,
oil, solvents and lubricants from maintenance of construction vehicles and
mechanical equipment.
Sediment
laden runoff particularly from works areas subjected to excavation or earth
works, if uncontrolled, may carry pollutants (adsorbed onto the particle
surfaces) into any nearby storm water drains. Bentonite and chemical grouting
may be required for diaphragm walling works and as a result may pollute surface
runoff.
As
a good site practice, mitigation measures should be implemented to control
construction site runoff and drainage from the works areas, and to prevent
runoff and drainage water with high levels of SS from entering any nearby storm
water drains. With the implementation of adequate construction site drainage
and provision of sediment removal facilities, unacceptable water quality
impacts are not anticipated. The construction phase discharge would be
collected by the temporary drainage system installed by the Contractor and then
treated or desilted on-site before discharge to storm water drains. The
Contractor would be required to obtain a license from EPD under the WPCO for
discharge to the public drainage system.
Sewage effluent from construction workforce
Domestic
sewage would be generated from the workforce during construction phase.
However, portable chemical toilets should be installed within the construction
site. The Contractor has the responsibility to ensure that chemical toilets are
used and properly maintained, and that licensed Contractors are employed to
collect and dispose of the waste off-site at approved locations. Therefore,
water quality impact is not anticipated.
General construction activities
On-site
construction activities may result in water pollution from the following:
¡ Uncontrolled
discharge of debris and rubbish such as packaging, construction materials and
refuse; and
¡ Spillages
of liquids stored on-site, such as oil, diesel and solvents etc.
Good
construction and site management practices should be observed to ensure that
litter, fuels and solvents do not enter the public drainage system.
15.5.4.2 Operation Phase
Road and surface runoff
Surface runoff from the flyover
proposed under the WKCD development may be contaminated by oils leaked from
passing vehicles. It is considered that impacts upon water quality would
be minimal provided that the proposed flyover is designed with adequate drainage
systems and appropriate oil interceptors, as required.
15.5.5 Mitigation of Adverse Impacts
15.5.5.1 Construction Phase
Construction site runoff and drainage
The
site practices outlined in ProPECC Note PN 1/94 should be followed as far as
practicable in order to minimise surface runoff and the chance of erosion. The
following measures are recommended to protect water quality and sensitive uses
of the coastal area, and when properly implemented should be sufficient to
adequately control site discharges so as to avoid water quality impacts:
¡ At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels, earth bunds
or sand bag barriers should be provided on site to direct storm water to silt
removal facilities. The design of the temporary on-site drainage system should
be undertaken by CEDD’s Contractor prior to the commencement of construction;
¡ Sand/silt
removal facilities such as sand/silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements of
the TM standards under the WPCO. The
design of efficient silt removal facilities should be based on the guidelines
in Appendix A1 of ProPECC Note PN 1/94.
Sizes may vary depending upon the flow rate. The detailed design of the
sand/silt traps should be undertaken by CEDD’s Contractor prior to the
commencement of construction.
¡ All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation at
all times and particularly during rainstorms. Deposited silt and grit should be
regularly removed, at the onset of and after each rainstorm to ensure that
these facilities are functioning properly at all times.
¡ Measures
should be taken to minimize the ingress of site drainage into excavations. If
excavation of trenches in wet periods is necessary, they should be dug and
backfilled in short sections wherever practicable. Water pumped out from
foundation excavations should be discharged into storm drains via silt removal
facilities.
¡ All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An
adequately designed and sited wheel washing facility should be provided at
construction site exit where practicable. Wash-water should have sand and silt
settled out and removed regularly to ensure the continued efficiency of the
process. The section of access road leading to, and exiting from, the
wheel-wash bay to the public road should be paved with sufficient backfall
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains.
¡ Open
stockpiles of construction materials or construction wastes on-site should be
covered with tarpaulin or similar fabric during rainstorms. Measures should be
taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system.
¡ Manholes
(including newly constructed ones) should be adequately covered and temporarily
sealed so as to prevent silt, construction materials or debris being washed
into the drainage system and stormwater runoff being directed into foul sewers.
¡ Precautions
should be taken at any time of the year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecasted and actions to be
taken during or after rainstorms are summarized in Appendix A2 of ProPECC Note
PN 1/94. Particular attention should be
paid to the control of silty surface runoff during storm events, especially for
areas located near steep slopes.
¡ Bentonite
slurries used in piling or slurry walling should be reconditioned and reused
wherever practicable. Temporary enclosed storage locations should be provided
on-site for any unused bentonite that needs to be transported away after all
the related construction activities are completed. The requirements in ProPECC
Note PN 1/94 should be adhered to in the handling and disposal of bentonite
slurries.
Sewage effluent from construction workforce
Temporary
sanitary facilities, such as portable chemical toilets, should be employed
on-site where necessary to handle sewage from the workforce. A licensed contractor
should be employed to provide appropriate and adequate portable toilets and be
responsible for appropriate disposal and maintenance.
General construction activities
Construction
solid waste, debris and refuse generated on-site should be collected, handled
and disposed of properly to avoid entering any nearby storm water drain.
Stockpiles of cement and other construction materials should be kept covered
when not being used.
Oils
and fuels should only be stored in designated areas which have pollution prevention
facilities. To prevent spillage of fuels and solvents to any nearby storm water
drain, all fuel tanks and storage areas should be provided with locks and be
sited on sealed areas, within bunds of a capacity equal to 110% of the storage
capacity of the largest tank. The bund should be drained of rainwater after a
rain event.
15.5.5.2 Operational Phase
Road and surface runoff
For operation of the proposed flyover, a surface water drainage system would be provided to collect road and surface runoff. It is recommended that the road drainage should be provided with adequately designed silt trap and oil interceptors, as necessary. The design of the operation stage mitigation measures for the flyover should take into account the guidelines published in the Practice Note for Professional Persons on Drainage Plans Subject to Comment by the Environmental Protection Department (ProPECC Note PN 5/93) and Highways Department Guidance Notes RD/GN/035 – Road Pavement Drainage Design.
15.5.6 Evaluation of Cumulative and Residual Impacts
Provided that proper mitigation measures would be implemented by each of the concurrent projects such as XRL, no adverse cumulative land-based and marine-based water quality impacts would be expected.
With the implementation of the recommended mitigation measures for the construction and operation phases of the proposed flyover, no residual water quality impact is anticipated.
15.5.7 Water Quality Monitoring and Audit
Adverse
water quality impact was not predicted during the construction and operation
phases of the proposed flyover.
Nevertheless, appropriate mitigation measures are recommended to minimize
potential water quality impacts.
Water
quality monitoring is recommended to obtain a robust, defensible database of
baseline
Regular
audit of the implementation of the recommended mitigation measures during the
construction phase at the work areas should also be undertaken to ensure the
recommended mitigation measures are properly implemented.
Details of the water quality monitoring and audit programme and the Event and Action Plan are provided in the stand-alone EM&A Manual.
15.5.8 Conclusion
15.5.8.1 Construction Phase
The key issue in terms of water quality during the construction phase of the flyover would be the potential for release of wastewater into coastal waters from construction site runoff and drainage.
Deterioration in water quality could be minimised to acceptable levels through implementing adequate mitigation measures such as control measures on suspended solids release, on-site runoff and drainage from the works areas to minimise suspended solids spillage and construction runoff prior to discharge. Proper site management and good housekeeping practices would also be required to ensure that construction wastes and other construction-related materials would not enter the public drainage system and coastal waters. Sewage effluent arising from the construction workforce would also be handled through provision of portable toilets.
With the implementation of these recommended mitigation measures, no unacceptable impacts on water quality from the construction works for the flyover are anticipated. Water quality monitoring and site inspections during construction phase should be undertaken routinely to inspect the construction activities and works areas to ensure the recommended mitigation measures are properly implemented.
15.5.8.2 Operation Phase
Surface runoff from the proposed
flyover may be contaminated by oils leaked from passing vehicles. It is
considered that impacts upon water quality will be acceptable provided that the
proposed flyover is designed with adequate drainage systems and appropriate oil
interceptors, as required in accordance with Highways Department Guidance Notes RD/GN/035 – Road Pavement Drainage
Design.
15.6 Sewerage and Sewage Treatment Implication
The flyover is part of a network of infrastructure within the WKCD development to meet the connectivity and accessibility requirements of the WKCD. This Schedule 2 Designated Project does not require or generate any sewage or sewerage related facilities. Consequently, there are no sewerage and sewage treatment implications associated with the flyover.
Sewerage and sewage treatment implications associated with the other WKCD facilities is presented in Section 6.
15.7 Waste Management Implication
This section identifies the potential waste
arising from the construction and operation activities of the
15.7.1 Waste Management Legislations, Standards and Guidelines
The criteria and guidelines for assessing
waste management implications are outlined respectively in Annexes 7 and 15 of
the Technical Memorandum on Environmental Impact Assessment Process (
The following legislation relates to the
handling, treatment and disposal of wastes in
¡ Waste Disposal Ordinance (Cap. 354)
¡ Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C)
¡ Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354)
¡ Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation
¡ Land (Miscellaneous Provisions) Ordinance (Cap. 28)
The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes. Construction waste is defined as any substance, matter or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works. Under the WDO, wastes can be disposed of only at designated waste disposal facilities.
Under the WDO, the Chemical Waste (General) Regulation provides regulations for chemical waste control, and administers the possession, storage, collection, transport and disposal of chemical wastes. The Environmental Protection Department (EPD) has also issued a ‘guideline’ document, the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which details how the Contractor should comply with the regulations on chemical wastes.
The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal tipping of wastes on unauthorised (unlicensed) sites.
15.7.1.2 Inert Construction and Demolition (C&D) Materials
The current policy related to the dumping of inert C&D materials is documented in the Works Branch Technical Circular No. 2/93, ‘Public Dumps’. Construction and demolition materials that are wholly inert, namely public fill, should not be disposed of to landfill, but taken to public filling areas, which usually form part of reclamation schemes. The Land (Miscellaneous Provisions) Ordinance requires that dumping licences be obtained by individuals or companies who deliver public fill to public filling areas. The Civil Engineering & Development Department (CEDD) issues the licences under delegated powers from the Director of Lands.
Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material. Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material.
15.7.2 Assessment Methodology
The
criteria for assessing waste management implications are outlined in Annex 7 of
the
¡ Identify the quantity, quality and timing of waste arising as a result of the construction and operation activities of the Project.
¡
Assessment of potential impacts from the management
of solid waste with respect to potential hazards, air and odour emissions,
noise, wastewater discharges and public transport.
¡
Assessment of impacts on the capacity of waste
collection, transfer and disposal facilities.
15.7.3 Identification, Prediction and Evaluation of Environmental Impact
15.7.3.1 Construction Phase
The
activities to be carried out for construction of the
¡ Inert Construction and demolition (C&D) materials;
¡ C&D materials from site clearance;
¡ Chemical waste; and
¡ General refuse.
Each type of the above waste arising is described below, together with an evaluation of the potential environmental impacts associated with the waste generation, handling, storage, transport and disposal. Table 15.7.1 presents a summary of all key types of waste arising during the construction phase of the flyover.
Inert Construction and
Demolition (C&D) Materials
Construction
of the
Tentatively, the inert C&D materials (not
more than 3,000 m3) would
be generated during the construction period of the flyover project, i.e., 2014
to 2017. Therefore, such inert materials
will be handled together with those generated from the WKCD Project, i.e.,
reuse on-site or off-site as far as practicable. As the estimated amount of inert C&D
materials that would be reused on-site as fill materials for the Park from 2014
to 2017 is about 138,470 m3 (see Table 7.2), it is
reasonable to assume that all the inert C&D materials generated by the
flyover project would be reused on-site.
In case there is any surplus inert C&D materials that could not
reused on-site, disposal of such inert C&D materials to the Government’s Public Fill
Reception Facilities (PFRFs) for beneficial use by other projects in
C&D Materials from Site Clearance Works
General
site clearance at the western and eastern end of the flyover (where the bridge
ramps down to ground level) may be required, which would generate a small
amount of C&D materials comprising mainly topsoil and vegetation. Assuming
the top 0.3m soil layer of the bridge ramp down construction area (covering
approximately 2,000m2) would be removed, approximately 600m3
of C&D materials would be
generated. These C&D materials would mainly be a mixture of topsoil
and vegetative material, and are considered as not suitable for direct reuse by
any earthworks on site due to its non-inert contents. However, the inert materials should be segregated from the C&D materials
on site for reuse as far as practicable, subject to constraints of the site
area. The segregated inert materials
that cannot be reused on site will
be disposed of at the Government’s PFRFs for beneficial use by other projects
in
Chemical Waste
Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:
¡ Toxic effects to workers;
¡ Adverse impacts on water quality from spills and associated adverse impacts on marine biota; and
¡ Fire hazards.
The maintenance and servicing of construction plant and equipment may generate some chemical wastes such as used solvents, contaminated rags and waste lubricating oil. It is difficult to quantify the amount of chemical waste that will arise from the construction activities since it will be dependent on the Contractor’s on-site maintenance requirements and the amount of plant utilised. However, it is anticipated that the quantity of chemical waste, such as waste lubricating oil and solvents produced from plant maintenance, will be small and in the order of less than one cubic metre per month. The amount of chemical waste to be generated will be quantified in the Waste Management Plan to be prepared by the Contractor for the site.
Materials classified as chemical wastes will require special handling and storage arrangements before removal for off-site disposal at the approved Chemical Waste Treatment Facility or recycling by licensed facilities. Mitigation and control requirements for chemical wastes are detailed in Section 15.7.4.1. Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts are not expected.
General Refuse
The construction workforce will generate refuse comprising food scraps, waste paper and empty containers etc. Such refuse will be properly managed so that intentional or accidental release to the surrounding environment will be avoided. Disposal of refuse at sites other than approved waste transfer or disposal facilities will be prohibited. Effective collection of site wastes will be required to prevent waste materials being blown around by wind, flushed or leached into the marine environment, or creating an odour nuisance or pest/vermin problem. Waste storage areas will be well maintained and cleaned regularly. The daily arising of general refuse from the construction workforce can be estimated based on a generation rate of 0.65 kg per worker per day.
The maximum number of construction workers to be employed for the flyover is likely to be less than 100 workers per day. Based on a generation rate of 0.65 kg per worker per day, the maximum daily arising of general refuse during the construction period would be approximately 65 kg and this waste can be effectively controlled by normal measures. With the implementation of good waste management practices at the site as detailed in Section 15.7.4.1, adverse environmental impacts are not expected to arise from the storage, handling and transportation of the general refuse from construction workforce.
Table 15.7.1 Summary of Waste Arisings during Construction Phase
Waste Type |
Key Sources of Waste Generation |
Timing of Waste Generation |
Estimated Quantity of Waste Generation |
Waste Reuse or Disposal |
Waste Handling |
Inert C&D Materials |
Minority from excavation at bridge piers and abutments, and from construction of the flyover superstructure |
Tentatively
from 2014 to 2017 |
Up to 3,000
m3 in total |
All inert C&D
materials would be reused on-site
as fill materials for the Park. In case of
any surplus inert C&D materials, such materials may be disposed of at the Government’s PFRFs for
beneficial use by other projects in |
Segregate inert C&D materials to avoid contamination from other waste arising |
C&D Materials
from Site Clearance |
General site clearance |
Tentatively
from 2014 to 2017 |
About
600 m3 in total |
Any inert materials segregated from the C&D
materials to be reused on-site as far as practicable or disposed of at the
Government’s PFRFs for beneficial use
by other projects in Non-inert materials segregated from the C&D materials to be disposed of at the designated landfill sites |
Segregate on site the C&D materials into inert and non-inert materials |
General Refuse |
Waste paper, discarded containers, etc. generated from the site workforce |
Tentatively from 2014 to 2017 |
0.65 kg per worker per day, the maximum daily arising of general refuse during the construction period would be approximately 65 kg
|
Refuse station for compaction and containerisation
and then to landfill for disposal |
Provide on-site refuse collection points |
Chemical Waste |
Used solvents, contaminated rags, waste lubricating oil, etc., from maintenance and servicing of construction plant and equipment |
Tentatively from 2014 to 2017 |
Less than one cubic metre per month (preliminary estimate) |
Disposal of at the Chemical Waste Treatment Centre or other licensed recycling facilities |
Stored on-site by suitably designed containers for off-site disposal or recycling |
15.7.3.2 Operation Phase
During
operation phase, the
15.7.4 Mitigation of Adverse Environmental Impact
15.7.4.1 Construction Phase
Good Site Practices
Adverse impacts related to waste management such as dust, odour, noise and wastewater discharge will not be expected to arise, provided that good site practices will be strictly followed. Recommendations for good site practices during the construction activities include:
¡ Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site
¡ Training of site personnel in proper waste management and chemical handling procedures
¡ Provision of sufficient waste disposal points and regular collection of waste
¡ Appropriate measures to minimise windblown litter and dust/odour during transportation of waste by either covering trucks or by transporting wastes in enclosed containers
¡ Provision of wheel washing facilities before the trucks leaving the works area so as to minimise dust introduction to public roads
¡ Well planned delivery programme for offsite disposal such that adverse environmental impact from transporting the inert or non-inert C&D materials is not anticipated
Waste Reduction Measures
Good management and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include:
¡ Sort inert C&D materials to recover any recyclable portions such as metals;
¡ Segregation and storage of different types of waste in different containers or skips to enhance reuse or recycling of materials and their proper disposal;
¡ Encourage collection of recyclable waste such as waste paper and aluminium cans by providing separate labelled bins to enable such waste to be segregated from other general refuse generated by the work force;
¡ Proper site practices to minimise the potential for damage or contamination of inert C&D materials; and
¡ Plan the use of construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.
In addition to the above measures, specific mitigation measures are recommended below for the identified waste arising to minimise environmental impacts during handling, transportation and disposal of these wastes.
Inert and Non-inert C&D Materials
In order
to minimise impacts resulting from collection and transportation of inert C&D
materials for off-site disposal, the excavated materials should be reused
on-site as fill material as far
as practicable. In addition, inert C&D materials generated from construction
of the flyover would be combined with inert C&D materials generated from
the WKCD development for reuse as fill materials in local
projects that require public fill for reclamation.
The
surplus inert C&D materials, if any, may be disposed of at the Government’s PFRFs for beneficial use
by other projects in
The C&D materials
generated from general site clearance
should be sorted on site to segregate any inert materials for reuse or disposal
of at PFRFs whereas the non-inert materials will be disposed of at the designated
landfill site.
In order to monitor the disposal of inert and non-inert C&D materials at respectively PFRFs and the designated landfill site, and to control fly-tipping, it is recommended that the Contractor should follow the Technical Circular (Works) No.6/2010 for Trip Ticket System for Disposal of Construction & Demolition Materials issued by Development Bureau. In addition, it is also recommended that the Contractor should prepare and implement a Waste Management Plan detailing their various waste arising and waste management practices in accordance with the relevant requirements of the Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site.
Chemical Waste
If chemical wastes are produced at the construction site, the Contractor will be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the “Code of Practice on the Packaging Labelling and Storage of Chemical Wastes”. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor should use a licensed collector to transport and dispose of the chemical wastes at the approved Chemical Waste Treatment Centre or other licensed recycling facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.
Potential environmental impacts arising from the handling activities (including storage, collection,
transportation and disposal of chemical waste) are expected to be minimal with the implementation of appropriate mitigation measures as
recommended.
General Refuse
General refuse should be stored in enclosed bins or compaction units separated from inert C&D materials. A reputable waste collector should be employed by the Contractor to remove general refuse from the site, separately from inert C&D materials. Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material.
15.7.4.2 Operation Phase
During
operation phase, the
15.7.5 Evaluation of Residual Impact
With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, residual impacts are not expected for both construction and operation phases.
15.7.6 Environmental Monitoring and Audit
It will be the Contractor’s responsibilities to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and the relevant regulations and requirements. The recommended mitigation measures shall form the basis of the Waste Management Plan to be developed by the Contractor in the construction phase.
During construction phase, regular site inspection as part of the EM&A procedures should be carried out to determine if various types of waste are being managed in accordance with approved procedures and the Waste Management Plan. It should cover different aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal.
15.7.7 Conclusion
15.7.7.1
Construction Phase
The major waste types generated by the construction activities will include inert C&D materials from minor excavation at piers and abutments as well as from construction of superstructures and substructures; C&D materials from general site clearance; chemical waste from maintenance and servicing of construction plant and equipment; and general refuse from the workforce. Provided that all these identified wastes are handled, transported and disposed of in strict accordance with the relevant legislative and recommended requirements and that the recommended good site practices and mitigation measures are properly implemented, no adverse environmental impact is expected during the construction phase.
15.7.7.2 Operation Phase
During
operation phase, the
According to the land contamination assessment for the WKCD site (see Section 8), the only location within the WKCD site with potential land contamination is the site of the existing Tsim Sha Tsui Fire Station, located at the east side of the WKCD site. This Schedule 2 Designated Project is located at the west side of the WKCD site, where no previous evidence of land contamination was found. Consequently, there is no potential land contamination issues associated with the flyover.
Land contamination issues associated with the other WKCD facilities is presented in Section 8.
The ecological impact assessment has been
conducted in accordance with the requirements of Annexes 8 and 16 of the
Technical Memorandum on Environmental Impact Assessment Process (
15.9.1 Ecological Legislations, Standards and Guidelines
A number of
international conventions, local legislation and guidelines provide the framework
for protection of species and habitats of ecological importance. Those of
relevance include:
¡ Forests and Countryside Ordinance (Cap. 96), which protects the rare plant
species from selling, offering for sale, or possession illegally;
¡ Wild Animals Protection Ordinance (Cap. 170), which protects wild animals
listed under the second schedule from being hunted, possession, sale or export,
disturbance of their nest or egg without permission by authorized officer;
¡ Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586), which regulates the
import, introduction from the sea, export, re-export, and possession of
specimens of a scheduled species, including the live, dead, parts or
derivatives. The Ordinance applies to all activities involving endangered
species which include the parties of traders, tourists and individuals;
¡ Environmental Impact Assessment Ordinance (
¡ Annexes 8 and 16 of the Technical Memorandum on Environmental Impact
Assessment Process (
¡
¡
¡ Town Planning Ordinance (Cap. 131), which gives designation to country parks, conservation
area, green belts, sites of special scientific interest, coastal protection
area and other specified uses to promote conservation , protection and
education of the valuable environment; and
¡ Hong Kong Planning Standards and Guidelines Chapter 10 (HKPSG) provides the
guidelines on landscape and conservation to achieve a balance between the need
for development and the need to minimise disruption of the landscape and
natural resources.
15.9.2 Assessment Methodology
15.9.2.1
Study Area
The Study Area for impact assessment of
terrestrial ecology covers all the areas within 500m from the flyover site
boundary and the areas likely to be affected by the flyover. The study was firstly
conducted by literature review and supplemented by on site ecological baseline
surveys where it is found necessary.
15.9.2.2 Literature
Review
The ecological baseline condition of the
Study Area was collected through a combination of both literature review and
updated field survey. Preliminary desktop study and literature review were
conducted to investigate the existing condition within the Study Area and
identify habitats or species with conservation concern. Available sources of
15.9.2.3 Ecological
Baseline Surveys
Since previous literature for this urban
area is very limited, ecological baseline survey was conducted to supplement
the literature review finding. The ecological baseline condition was updated through
ecological field surveys, which were conducted in accordance with the
requirements stated in the
Habitat and vegetation
surveys were conducted for 4
months (during July to December 2011) covering both wet and dry seasons within the ecological Study Area. Special
attention was paid on species of conservation concern and habitats within the
proposed works area where the vegetation will be directly impacted.
Habitat map of
suitable scale showing the type and location of habitats recorded within the Study
Area, with the overlay plot of the Project boundary was produced, as shown in Figure 15.9.1.
Fauna surveys were conducted within the Study Area for 4 months (during July to December 2011) covering both wet
and dry seasons. Since the
Project Area are newly created through reclamation and enclosed by developed
area, the colonization of flora and fauna species are of low ecological importance.
Only the highly mobile bird species would have better chance of colonization of
the newly created habitat and also use the habitat for stopover ground during
migration; so, the baseline survey is mainly focused on avifauna. Transect count surveys were adopted with the aid
by a pair of binoculars to assist the identification of species.
The transect route is indicated in Figure 15.9.2.
15.9.3 Baseline Conditions
15.9.3.1
Terrestrial Habitat and Vegetation
The Project Area is located at the
There are 4 types of terrestrial habitat identified in the Study Area, namely:
¡
¡ Open Field;
¡ Artificial Seawall; and
¡ Developed Area.
A habitat map showing the location of each
type of habitat is presented in Figure 15.9.1. Representative photographs of each type of habitats are
illustrated in Appendix 9.1. Brief descriptions of these habitat types and the dominant floral
species assemble of the habitat are described as follows:
¡
Open Field
¡ Open field refers to bare ground
or wasteland. This type of habitat is mainly identified close to West Kowloon
Waterfront Promenade. It is sparsely vegetated with a few common self-seeded
species, e.g. Rhynchelytrum repens,
Imperata koenigii and Bidens alba.
Artificial
Seawall
¡ The artificial seawall refers to
the sloping waterfront formed by large boulders for protection of shoreline and
typhoon shelter. It happens in the southwest of the WKCD site boundary and the
breakwaters in the New Yau Ma Tei Typhoon Shelter. Owing to the short history
of the artificial habitat, the intertidal habitat is mainly colonized by
pioneer species which are common and widespread in
Developed Area
¡ Developed areas are artificial
habitats. This man-made habitat comprises the existing buildings, sitting-out
area, work site, paths and roads within the Project Area for the flyover. This
urbanised land use is of negligible ecological importance.
¡ To the northwest of the Project
Area for the flyover is a New Yau Ma Tei Typhoon Shelter, which is enclosed by
artificial breakwater structure. It is generally of low ecological value due to
high level of marine traffic but sometimes used by ardeid species for foraging.
Within the Project Area for the flyover,
both open field and plantation habitats are of limited ecological value owing
to the high level of anthropogenic disturbance, low vegetation cover, high
commonness of the flora and fauna species and short history of the vegetated
habitat. The fauna species associated with these two habitats are mostly common
species adapted to urbanized areas. The bird species found in the site is
dominated by generalist species such as Tree Sparrow, Chinese Bulbul and
Black-collared Starling, which are common in urban areas.
The
15.9.3.2
Terrestrial Fauna
The fauna species inhabiting the Project Area
for the flyover are mostly generalist species adapted to urban area, with some
migratory bird species which sometimes use the fragmented vegetated habitat in
urban area as temporary stopover point during their migratory journey. It is
noted that open field and plantation in urban area are generally not the prime
habitats for wild birds. Field surveys were conducted during July to December
2011 to verify the ecological status of the habitats.
Field surveys for avifauna were conducted on
18 July, 26 September, 30 November and 28 December 2011 covering
both summer and winter periods, which also include bird’s breeding and
wintering season. The checklist of avifauna recorded within the Project Area
for the flyover is presented in Appendix 9.2. It was observed that the open
field and plantation habitats within the Project Area were inhabited by a
number of generalist species, such as Black-collared Starling, Eurasian Tree
Sparrow, Spotted Dove, Chinese Bulbul, Red-whiskered Bulbul and Crested Myna. All
of them are very common in urban area. Long-tailed Shrike and Plain Prinia are
less common in urban area; both were seen in the open field area. A few
migratory species including Brown Shrike, Blackbird, Blue Rock Thrush and
Yellow-browed Warbler were seen during the surveys conducted in September to
December 2011, in the period of migratory season. The low number of migratory
species recorded indicates that the habitats within the Study Area are not the
prime habitat for migratory birds, probably due to lack of mature vegetation
and proximity to high rise buildings. With regard to raptor species, only Black
Kite, which is of conservation concern, was recorded during the survey. The
wintering population of Black Kite forage along
The southern part of the New Yau Ma Tei
Typhoon Shelter lies within the 500m Study Area. Typhoon shelter is generally
not an optimal habitat for avifauna but a few seashore associated species such
as ardeids and Black Kite are often found foraging in the typhoon shelter.
Also, a passage migrant species Whiskered Tern was recorded in autumn migration
period.
To the south of the project area is
15.9.3.3
Habitat Evaluation
Habitats identified within the Ecological
Study Area are evaluated in accordance with the guidelines set forth in the
Annex 8 of the
¡ High
¡ High-moderate
¡ Moderate
¡ Moderate-low
¡ Low
¡ Very Low
Evaluation of these habitats is given in Table 15.9.1. Each
habitat is evaluated in accordance with the requirements stipulated in Annex 8,
Table (2) of the
Table
15.9.1: Habitat
Evaluation
Criteria |
Developed Area |
Open Field |
|
Artificial
Seawall |
Naturalness |
Man-made habitat |
Man-made habitat |
Man-made habitat |
Man-made
habitat |
Size |
Large (49.01 ha) |
Small (11.84 ha) |
Small (1.90 ha) |
Small (1.59 ha) |
Diversity |
Low in both fauna and flora species diversity |
Low in both fauna and flora species diversity;
self-seeded flora species are common and widespread |
Low in both fauna and flora species diversity |
Low
diversity of coastal fauna in new artificial habitat |
Rarity |
Habitat not rare |
Common habitat |
Common
habitat |
Common
artificial habitat |
Re-creatability |
Readily re-creatable |
Readily re-creatable |
Readily re-creatable |
Readily re-creatable |
Fragmentation |
N/A |
N/A |
These habitats are patchily created/ modified for urban land use |
N/A |
Ecological linkage |
No ecological linkage |
Low ecological linkage with other habitats |
Low ecological linkage with other habitats |
Ecological
linkage to marine habitat |
Potential value |
Low potential value |
Low potential value |
Low potential value as the habitat is being maintained for urban landscaping |
Low potential value |
Nursery/ breeding ground |
Not significant nursery/ breeding ground |
Not significant nursery/ breeding ground |
Not significant nursery/ breeding ground |
Not significant nursery/ breeding ground |
Age |
N/A |
5 – 10 years |
Mostly around 10 years |
Mostly around 10 years |
Abundance/ Richness of wildlife |
Low |
Low |
Low |
Low |
Overall Ecological Value |
Very Low |
Very low |
Low |
Low |
15.9.4 Evaluation and Assessment of Ecological Impacts
In view of the developments proposed in
Section 2, ecological impact on habitat, flora and fauna species are predicted
and evaluated in accordance with Annex 16 of the
The potential ecological impact due to the construction
and operation of the Project include following:
¡ Habitat Loss
¡ Indirect Impact
¡ Habitat Fragmentation
¡ Operation Phase Impact
Evaluation of the impacts is given below and
a summary of the ecological impact is presented in Table 15.9.2.
15.9.4.1
Habitat Loss
The construction and operation of the flyover
would cause the loss of existing habitat in the West Kowloon Reclamation area.
Owing to the low ecological value of the artificial habitat, the ecological
impact due to the loss of open field and plantation is considered to be insignificant.
With regard to avifauna, since the habitats are used by very common generalist
species, the impact on avifauna due to loss of open field and plantation is
also insignificant.
15.9.4.2
Indirect Impact
Indirect impact through construction
activities may cause local disturbance to off-site habitats. Excessive noise,
vibrations, dust generation and increased human activities may all contribute
to disturbance impact during construction and operation phases. The fauna
species occurring in urban areas can generally tolerate a high level of human
disturbance, so the impact on fauna species is considered to be minimal. Given
that the West Kowloon Reclamation and adjacent area are predominately urbanized
area with low to very low ecological value, the impact of indirect off-site
disturbance is also considered to be insignificant.
New Yau Ma Tei
Typhoon Shelter
As observed in the field survey, Black Kite
was commonly seen soaring high above the New Yau Ma Tei Typhoon Shelter.
Although it is the only raptor of conservation concern recorded, no impact on
this species is predicted as it is adapted to urbanized area along the
Also commonly recorded in the New Yau Ma Tei
Typhoon Shelter is the ardeid species, foraging at the breakwater or standing
on boats. The New Yau Ma Tei Typhoon Shelter is not particularly important to
the ardeids as this species is common along the coastline in
During the survey in September, a group of
Whiskered Tern were observed foraging over the sea around the typhoon shelter.
This species is an uncommon passage migrant in
Little Egret were
commonly found passing and sometimes foraging along the coast of
15.9.4.3
Habitat Fragmentation
Given that the Project Area neighbours with
urban area and no habitat of conservation concern is identified in the Study
Area, there is no ecological linkage identified in the Study Area. As such,
there is no habitat fragmentation impact.
15.9.4.4
Potential Impacts during Operation Phase
No ecological impacts are anticipated during
the operation of the proposed flyover.
Table
15.9.2: Summary
of the potential ecological impact
Criteria |
Habitat Loss |
Indirect Impact (disturbance) |
Habitat
Fragmentation |
Operation Phase |
Duration |
Construction Phase |
Construction Phase |
Construction
and operation phase |
Operation Phase |
Reversibility |
Not Reversible |
Reversible |
Reversible |
Not Reversible |
Magnitude |
Moderate-low for loss of open field of large size but of very low ecological value |
Moderate |
Low |
Low |
Impact Severity |
Insignificant, the habitat to be lost is of low to very low ecological value |
Insignificant, the ecological value of the urbanized area is very low |
Negligible |
Insignificant
/ potentially positive |
15.9.5 Mitigation Measures
Since no significant ecological impact due to the flyover was identified, no specific ecological mitigation measures other than good site practice is required.
15.9.6 Residual Impacts
Since no significant ecological impact will
arise from the proposed flyover, no residual impact is expected without
specific ecological mitigation measures.
15.9.7 Environmental Monitoring and Audit
The implementation of good site practices
would avoid and minimize any ecological impacts to an acceptable level. No
specific ecological monitoring programme is thus required for the flyover.
15.9.8 Conclusion
The findings from the field survey and
desktop review indicated that the major terrestrial habitats in the Study Area
are developed area, open field and plantation, with small amount of sloping
seawall along the coastline. All these habitats are with low vegetation cover,
short planting history and of low to very low ecological value. Therefore,
direct ecological impact on loss of habitat is considered to be of
insignificant. The indirect disturbance impact to offsite habitat is considered
to be of insignificant in both construction and operation phases, since the proposed
flyover is surrounded by urbanized area. The plantation and landscape planting
included in the development plan would have potential positive contribution to
the local ecology.
15.9.9 References
AECOM
(2009). Consultancy Agreement No. NOL/ERL-300 Environmental Impact Assessment
of Hong Kong Section of
AECOM (2009). Consultancy
Agreement No. NOL/ERL-300 Environmental
Impact Assessment of Road Works at
Carey,
G.J., Chalmers, M.L., Diskin, D.A., Kennerley, P.R., Leader, P.J., Leven, M.R.,
Lewthwaite, R.W., Melville, D.S., Turnbull, M., and Young, L. (2001). The Avifauna of
Carey, G.J. and
Lockey, Helen (Ed.) (2010) The Hong Kong Bird Report 2005-06. The Hong Kong
Bird Watching Society Limited,
Fellowes, J.R., Lau,
M.W.N., Dudgeon, D., Reels, G.T., Ades, G.W.J., Carey,G.J., Chan, B.P.L.,
Kendrick, R.C., Lee, K.S., Leven, M.R., Wilson, K.D.P. and Yu, Y.T. (2002).
Wild Animals to Watch: Terrestrial and Freshwater Fauna of Conservation Concern
in
Ove Arup (2005).
15.10 Landscape and Visual Impact
15.10.1 Introduction
The landscape and visual impact assessment (LVIA)
has been conducted in accordance with the requirements of Annexes 10 and 18 of the Technical Memorandum on Environmental Impact
Assessment Process (
The purpose of this LVIA is to:
¡ Define the existing landscape and
visual quality of the Assessment Area;
¡ Identify key landscape and visual
resources as well as landscape and visually sensitive receivers (VSRs);
¡ Identify and evaluate the
potential landscape and visual impacts associated with the Project during both
the construction and operation phases;
¡ Define significance and magnitude
of the landscape and visual impacts before and after mitigation;
¡ Propose mitigation measures to
reduce the impacts on the existing landscape character and visual quality; and
¡ Describe the implementation, maintenance and management of these recommended mitigation measures.
15.10.2 Landscape and Visual Legislations, Standards and Guidelines
The
following legislation, standards and guidelines are applicable to the
evaluation of landscape and visual impacts associated with the construction and
operation phases of the
¡ Environmental Impact Assessment Ordinance (Cap. 499, Section 16);
¡
¡
¡ Approved South West Kowloon Outline Zoning Plan no. S/K/20/28 gazetted
on 08/01/2013;
¡ Approved West Kowloon Cultural District Development Plan No.S/K20/WKCD/2
gazetted on 08/01/2013,;
¡ Landscape Value Mapping
Study in
¡ WBTC No. 7/2002 – Tree Planting in Public Works;
¡ WBTC No. 14/2002 –
Management and Maintenance of Natural Vegetation and Landscape Works, and Tree
Preservation;
¡ ETWB TCW No. 11/2004 on
Cyber Manual for Greening;
¡ ETWB TCW No. 3/2006 – Tree Preservation;
¡ ETWB TCW No. 2/2004 – Maintenance of Vegetation and Hard Landscape
Features;
¡ ETWBTCW No. 29/2004 –
Registration of Old and Valuable Trees, and Guidelines for their Preservation
¡ Planning Study on the
Harbour and its Waterfront Areas (February 2003);
¡ Environmental Impact
Assessment Study Brief No. ESB-197/2008 – Hong Kong Section of
Guangzhou-Shenzhen-Hong Kong Express Rail link (XRL) (November 2008);
¡ Environmental Impact
Assessment Study Brief No. ESB-202/2009 – Road Works at
¡ Environmental Impact
Assessment of Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail
Link (May 2009)
¡ Environmental Impact
Assessment of Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail
Link – Environmental Impact Assessment Report Executive Summary (May 2009);
¡ Greening Master Plan for
Mong Kok and Yau Ma Tei; and
¡ Greening Master Plan for
Tsim Sha Tsui.
15.10.2.1
Review of Relevant Guidelines on Landscape Strategies and Framework and
Land Use Zoning
Relevant planning documents have been reviewed to gain an insight to the planning intentions of the site and its surroundings so as to assess whether the project can fit into the setting of the site and its surroundings as a whole.
The review of the relevant guidelines on landscape strategies and framework, and urban design for the proposed WKCD development is useful to gain an understanding of the planning and design intention of the surrounding areas and this is provided in Section 10.2.1.
In order to have a better understanding of the envisaged future landscape and visual characters/ context of the project site, the land use zoning and planning intentions of the project site has also been examined.
The
site for the Austin Road flyover is located outside the WKCD site as shown in Figure 15.1.1.
The site is currently occupied mainly by the Western Harbour Crossing (WHC)
toll plaza. The site is surrounded by the WKCD to the south, CDA site to the
east and Yau Ma Tei Typhoon Shelter to the west. The site is currently zoned as
“Other Specified Uses” annotated “West Harbour Crossing Toll Plaza” under Approved West Kowloon Cultural District
Development Plan No.S/K20/WKCD/2. The planning intention of this zone is
primarily to provide land for the use of
With the existing “transport corridor” landscape setting of and planning intention, it is anticipated that the construction of this road infrastructure (i.e. flyover) is in line with the planning intention of the project site.
15.10.3 Assessment Methodology
The
preparation of this LVIA follows the criteria stated in the Annexes 10 and 18 of the Technical
Memorandum to the Environmental Impact Assessment Ordinance (
Relevant planning documents have been reviewed to gain an insight to the planning intentions of the site and its surroundings so as to assess whether the project can fit into the setting of the site and its surroundings as a whole.
15.10.3.1 Assessment Area
The scope for defining the Assessment Areas for Landscape Impact Assessment and Visual Impact Assessment are as follows:
Landscape
Impact Assessment (LIA): In accordance with the Study Brief and
Visual
Impact Assessment (VIA): According to
the
15.10.3.2 Baseline Survey and Assessment of Landscape Impacts
1: Identification of Key Landscape Resources and Landscape Character Areas (LCAs) within the Assessment Area
A baseline survey of the existing landscape resources (LRs) and
landscape character areas (LCAs), comprising a desktop study of relevant
background reports and a comprehensive field study, is undertaken. This aims to
obtain information on topography and existing vegetation for further analysis.
Two categories of Landscape Resources,
including Physical and Human
Landscape Resources, are classified within the Assessment Area. Physical Landscape
Resources include physical topography, water body (i.e.
The conditions of the landscape resources
and resources contribute to the overall character of the site and its surroundings.
The LCAs represent broad tracts of landscape which have been determined with
consideration of topography, vegetation types and land use patterns. The “Landscape Value Mapping Study in Hong Kong”
will be reviewed to get an understanding of the landscape characters within the
Assessment Area.
2: Assessment of the Sensitivity of the Landscape Resources (LRs) and Landscape Character Areas (LCAs)
The individual LRs /LCAs that have been
identified are described qualitatively and quantitatively. Their sensitivities
are then evaluated and rated as low, medium or high based on the following
factors:
¡ Quality of landscape
characters/resources;
¡ Importance and rarity of special
landscape resources;
¡ Ability of the landscape to
accommodate change;
¡ Significance of the change in
local and regional context; and
¡ Maturity of the landscape.
The sensitivity rating for each LR / LCA are determined based on
the following:
Low |
Landscape
or landscape resource, the nature of which is largely tolerant to change |
Medium |
Landscape
or landscape resource of moderately valued landscape characteristics
reasonably tolerant to change |
High |
Important
landscape or landscape resource of particularly distinctive character or high
importance, sensitive to relatively small changes |
3:
Identification of Potential
Source
and Type
of Impacts
Various elements of the construction works and operation procedures
that would generate landscape impacts are identified.
4:
Assessment of the Magnitude
of Landscape
Impacts
The factors affecting the magnitude of change in assessing landscape impacts are as follows:
¡ Compatibility of the project with
the surrounding landscape;
¡ Duration of impacts under
construction and operation phases;
¡ Scale of development; and
¡ Reversibility of change.
The magnitude of change
rating for each LR / LCA are determined
based on the following:
Negligible |
The
LRs/LCAs would suffer no discernible change by the proposed development |
Small |
The
LRs/LCAs would suffer slight or barely perceptible changes by the proposed
development |
Intermediate |
The
LRs/LCAs would suffer a moderate change by the proposed development |
Large |
The
LRs/LCAs would suffer a major change by the proposed development |
5: Identification of Potential Landscape Mitigation
Measures
Potential mitigation measures are developed to avoid or reduce the adverse landscape impacts derived from the WKCD development, which also includes
enhancement of the landscape and visual quality. Remedial measures will be
recommended such as tree preservation measures, and compensatory measures such
as the implementation of landscape design measures (e.g. compensatory planting,
landscape treatment, creation of new open space etc.) to compensate for
unavoidable adverse impacts and/or generate potentially beneficial long term
impacts.
6: Prediction of the Significance of Landscape Impacts
Before and After the Implementation of the Mitigation Measures
Landscape impacts will be classified depending on whether the impacts
are adverse/beneficial, and irreversible/reversible. Significance threshold of
residual impact before and after
mitigation (Day 1 and Year 10) will
be assessed under the following categories:
Insubstantial |
No
discernible change to the existing landscape quality |
Slight |
Adverse/
beneficial impact where the proposed development would cause a barely
perceptible deterioration/improvement to existing landscape quality |
Moderate |
Adverse/
beneficial impact where the proposed development would cause a noticeable
deterioration/improvement to existing landscape quality |
Substantial: |
Adverse/
beneficial impact where the proposed development would cause significant
deterioration/improvement to existing landscape quality |
The impact significance will also be determined. Table 15.10.1
shows the relationship between sensitivity and magnitude of change.
Table 15.10.1: Impact significance –
relationship between sensitivity and magnitude of change
Magnitude of Change caused by the
proposed development |
Sensitivity |
||
Low |
Medium |
High |
|
Large |
Moderate |
Moderate/Substantial |
Substantial |
Intermediate |
Slight/Moderate |
Moderate |
Moderate/ Substantial |
Small |
Slight |
Slight/Moderate |
Moderate |
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
7: Residual Impacts Assessment
Residual impacts are those impacts remaining after the proposed
mitigation measures have been implemented. This often refers to 10 to 15 years
of operation, when the planting mitigation measures are considered to have
reached a level of maturity, which allow them to perform the intended design
objectives.
In accordance with Annex 10 of the
Table 15.10.2: Assessment categories for residual impact
Beneficial |
Acceptable |
Acceptable with mitigation measures |
Unacceptable |
Undetermined |
The impacts are beneficial if the proposed development will complement the landscape character of its setting, follow the relevant planning objectives and improve overall and visual quality. |
The impacts are acceptable if the assessment indicates that there will be no significant impacts on the landscape, no significant adverse visual impacts caused by the appearance of the proposed development, or no interference with key views. |
The impacts are acceptable with mitigation measures, if there will be some adverse impacts, but these can be eliminated, reduced or offset to a large extent by specific mitigation measures. |
The impacts are unacceptable if the adverse impacts are considered too excessive and are unable to mitigate practically. |
The impacts are undetermined if the significant adverse impacts are likely, but the extent to which they may occur or may be mitigated or cannot be determined from the study. Further detailed study will be required for the individual impact in question. |
15.10.3.3 Baseline Survey and Assessment of Visual Impacts
1:
Identification of Visual
Resources
and Visually Sensitive Receivers (VSRs)
Visual resources and key visually sensitive receivers (VSRs) within the visual envelope and primary zone
of visual influence which would
be affected by the Project will be
identified. The Notes, Schedule of Uses
and Explanatory Statement of the Approved
West Kowloon Cultural District Development Plan No.S/K20/WKCD/2 and the Hong
Kong Planning Standards and Guidelines – Chapter 11 Urban Design Guidelines for
Hong Kong are reviewed to
determine the vantage VSRs. Minimum
viewing distance of each VSRs are also determined.
2:
Assessment of Sensitivity
of Visually
Sensitive Receivers (VSRs)
Visual sensitivity considers the impact on views to the site from
potential VSRs and the nature/type of the VSR. A number of factors
affecting the sensitivity of receivers for evaluation of visual impacts are as
follows:
1 |
Value
and quality of exiting views |
2 |
Availability
and amenity of alternative views |
3 |
Type
and estimated number of receiver population (many, medium and few) |
4 |
Duration
(long/ medium/ short) and frequency of view (frequent/ occasional/ rare) |
5 |
Degree
of visibility (no view, glimpse, partial view, vista, open view, and
panoramic view) |
The sensitivity rating for the VSR are determined as follows:
High: |
The
VSR is highly sensitive to any changes in their viewing experience. |
Medium: |
The
VSR is moderately sensitive to any changes in their viewing experience. |
Low: |
The
VSR is only slightly sensitive to any changes in their viewing experience. |
3:
Identification of Potential Sources
of Visual Impacts
Various elements located within the site that would generate visual impacts during the construction and operation phases are identified.
4: Assessment of Potential
Magnitude of Visual Impacts
Visual impacts are determined by evaluating the conditions of the existing landscape and the visual
character of the site and its surroundings,
as well as the degree of integration of the Project’s components with the
existing landscape. Other major factors affecting the magnitude of changes for
assessing visual impacts are:
1 |
Scale
of development |
2 |
Compatibility
of the project with the surrounding landscape |
3 |
Reversibility
of change |
4 |
Viewing
distance |
5 |
Potential
blocking of view |
6 7 |
Duration
of impacts under construction and operation phases Night
glare effect |
The potential magnitude of change is classified into four categories:
Negligible |
The
VSRs are likely to suffer no discernible change in their viewing experience |
Small |
The
VSRs are likely to suffer a slight change in their viewing experience |
Intermediate |
The
VSRs are likely to suffer a moderate change in their viewing experience |
Large |
The
VSRs are likely to suffer a significant change in their viewing experience |
5: Determination of the Visual Impacts during Construction and Operation Phases before Implementation of Mitigation Measures
The significance of the visual impacts
is categorised as follows:
Insubstantial |
No discernible change to the existing
visual quality |
Slight |
Adverse / beneficial impact where the Project
would cause a barely perceptible deterioration/ improvement to existing
visual quality |
Moderate |
Adverse/beneficial impact where the Project
would cause a noticeable deterioration/ improvement to existing visual
quality |
Substantial |
Adverse/beneficial impact where the Project
would cause significant deterioration/ improvement to existing visual quality |
The impact significance will be also be determined.
Table 15.10.3 shows
the relation between sensitivity and magnitude of change.
Table
15.10.3: Impact significance – relationship
between sensitivity and magnitude of change
Magnitude
of Change |
Sensitivity of the VSR |
||
Low |
Medium |
High |
|
Large |
Moderate |
Moderate/Substantial |
Substantial |
Intermediate |
Slight/Moderate |
Moderate |
Moderate/ Substantial |
Small |
Slight |
Slight/Moderate |
Moderate |
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
6: Examination of Alternative Design(s) and
Construction Method(s)
Before adopting other mitigation measures to
alleviate the impacts, alternative design(s) and construction method(s) that
would avoid or reduce the impacts on landscape, or that would make the Project
visually more compatible with the setting has been examined.
7. Recommendation of Mitigation
Measures to Minimize Adverse Visual Impacts
Mitigation strategies will be developed to reduce the overall visual impacts derived from the Austin Road Flyover during the construction and operation phases.
8: Residual Impacts
Assessment
Residual
impacts from the Project are assessed
based on the 5 categories for residual visual impacts including “Beneficial”, “Acceptable”,
“Acceptable with Mitigation Measures”, “Unacceptable” and “Undetermined”
(see Table 15.10.2).
9: Assessment of Cumulative
Impacts
Cumulative impacts of the concurrent
projects on landscape resources, landscape character areas and visual amenity
will be assessed.
Graphics Presentation
The findings of this LVIA are presented and supported by a range of illustrative materials such as computer-generated photomontages, aerial photograph, photographs and plans etc. Flyover structure together with any mitigation measures are illustrated the overall appearance of the Austin Road Flyover.
15.10.3.4 Scope and Content of the Project
Scope and descriptions of the
Project is provided in Section 15.2. The flyover is a supplementary component of the WKCD
development, proposed mainly to support certain WKCD facilities.
It is
noted that the baseline conditions are not static and may change over time. The
Project will be completed before completing most of the other future
developments within the WKCD. It is assumed that construction will occur at the
same time as construction of WKCD facilities.
15.10.3.5 Benefits of the Project
The
main purpose of the flyover is to serve as one of the key measures to meet the
accessibility and connectivity objective
of the WKCD development mentioned in Section 15.1.1. Specifically, the purpose of the flyover is to provide
a second access for the proposed WKCD Mega Performance Venue (MPV) and
Exhibition Centre (EC), and
provide flexibility for event management as a route to enhance the
accessibility and robustness of the arrangements including post event traffic
dispersal for serving the MPV and second emergency vehicle route.
Economic and social benefits provided by the
Project are considered to be associated with the proposed WKCD development,
since the flyover is a
supporting component of the WKCD development.
The proposed WKCD development should
not be considered alone. The support of the connections with the surrounding
areas is equally important.
In
addition to fulfilling the future demand, the construction of the flyover helps
alleviate the traffic congestions generated by the WKCD and current congestions,
and also provide better infrastructural support to various current and upcoming
developments in the West Kowloon Reclamation Area. In turn, it enhances the
accessibility and the use of the facilities particularly those located in the
western part of the WKCD. This is an important planning criteria contributing
to the success of the WKCD. It is anticipated that the proposed WKCD
development will bring numerous economic and social benefits to
15.10.3.6 Major Limitations of the Assessment
To
meet the requirements of the TM of the
As the programme for construction and completion of this flyover is not available at this moment in time, for the purpose of assessing the potential worse case environment impacts associated with the construction of the flyover, it is assumed that construction of flyover will occur at the same time as construction of WKCD facilities stated in Section 2.7 (i.e. between 2013 and 2020).
15.10.4 Baseline Study
Currently, the landscaping setting of the site is mainly comprised
roadside amenity plantings at the junction of
Landscape Resources are
classified into two categories including Physical Landscape Resources and Human
Landscape Resources. The
surrounding landscape resources mainly consist of developed area and a water
body (i.e.
15.10.4.1 Physical Landscape Resources
Topography
The landform of the landscape impact assessment area which is the West Kowloon Cultural District comprises flat reclaimed land with no features of topographical interest or value.
Open Space
The
site currently comprises 1.6 ha of temporary open space including a waterfront
promenade along the
15.10.4.2 Human Landscape Resources
Cultural Heritage and Historical Features
The site
is a reclaimed land that does not contain any cultural heritage features or
landscape with important history. No cultural/religious
built heritage features are found
within the assessment area.
15.10.4.3
Existing Trees within the Assessment Area
A broad brush tree/vegetation survey has
been carried out within the assessment area as shown in Figure 15.10.4.
Within the study area, there are approximately 1194 no. of trees. Many of the trees are found within public
open spaces or are roadside trees or trees with amenity planting area. They are
mostly exotic and common species with low to medium amenity value and poor to
good condition. Tree species
include Acacia auriculiformis, Acacia confusa,
Albizia lebbeck, Araucaria heterophylla, Archontophoenix alexandrae, Bauhinia x
blakeana, Casuarina equisetifolia, Carica papaya, Celtis sinensis, Cinnamomum
camphora, Caryota mitis, Crateva unilocularis, Delonix regia, Eucalyptus
calophyllaoi, Ficus benjamina, Ficus microcarpa, Ficus virens, Grevillea robusta,
Hibiscus tiliaceus, Koelreuteria bipinnata, Lagerstroemia speciosa, Leucaena
leucocephala, Livistona chinensis, Melaleuca leucadendron, Melia azedarach,
Morus alba, Peltophorum pterocarpum, Phoenix roebelenii, Phoenix sylvestris,
Roystonea regia, Senna siamea, Senna surattensis, Syzygium cumini, ,Terminalia
mantaly, and Washingtonia robusta. Many of the trees are found within
public open spaces or are street trees.
There are approximately 80 affected trees
due to the construction of Austin Road Flyover. 50 affected trees are found
within the site boundary of WKCD and other are found outside the site boundary
of WKCD. Trees are mostly roadside planting. Dominant tree species within the
site boundary include Acacia
auriculiformis, ,Cassia siamea, Casuarina equisetfolia, Celtis sinensis, Ficus microcarpa, Ficus
virens, Hibiscus tiliaceus, Leucaena leucocephala, Melia azedarach, Morus alba, etc. Trees found within the WKCD site are self seeded
species of low to medium amenity value. There are considerable numbers of Leucaena leucocephala, which is a self
seeded weed species are found on the site. No Old and Valuable Trees (OVT) is
recorded within the site and the assessment area. Nevertheless, the proposed
development would not pose any disturbance to any of the recorded OVTs
A list of landscape
resources and their sensitivity is shown in Table
15.10.4. Lists of baseline landscape resources are mapped in Figure 15.10.1. Photo records are shown in Figure 15.10.3a to Figure 15.10.3f.
Table
15.10.4: Landscape resources and sensitivity
Ref. No. |
Baseline Landscape Resources |
Sensitivity (High,
Medium and Low) |
Existing Landscape Resources |
||
Physical Landscape Resources LR1: Open Space |
||
LR1.7 |
Temporary
open space along the waterfront promenade within the site boundary This is a temporary open space (~1.6 ha) located along the waterfront promenade within the
site boundary. It consists of a
cycling track, children’s play equipment and seating areas under trellis primarily for passive
recreation purposes. There are main
shrub planting (Brassia actinophylla,
Lantana camara, Hibiscus
rosa-sinensis, Alternanthera
paronychioides and Juniperus
chinensis cv. Kaizuka),
groundcover (Ophipogon japonicus and Hymenocallis speciosa) and lawn area
with lighting along pedestrian path. This area is well-maintained and the condition
of the plants is fair. The amenity
value is medium as most plant species are flowering species. |
Medium |
LR1.15 |
Public
Open Space at the podium of This is a public open space (~0.37 ha) within the private development
at the podium of Kowloon Station. It includes a large piazza area with some
water features. There are approximately 30 young to semi-mature trees located
at the public open space, with height around 4-6m, crown 4-5m and DBH around
95-100mm. Amenity value is medium. The tree condition is fair. Species consists of |
Medium |
Physical Landscape Resources LR2:
Amenity Planting |
||
LR2.26 |
Trees along There are approximately 30
young
and semi-mature trees with
shrubs and lawn area (~.004ha) located along Hoi Po Road and within West Kowloon
Highway area, with height
around
4-16m, crown spread 2-7m and DBH 95-300mm. Amenity value is considered to be low to medium with a considerable amount of Leucaena leucocephala which is a weed
species. Species mainly consist of Leucaena
leucocephala, Roystonea regia, Acacia
auriculiformis, Araucaria
heterophylla, Bauhinia spp., Delonix regia, Melia azedarach, Acacia confusa,
Casuarina equisetifolia, Albizia lebbeck, Melaleuca quinquenervia, Ficus
microcarpa, Hibiscus tiliaceus,
Eucalyptus calophyllaoi and Livistona chinensis. The condition of
the trees range from poor to fair. |
Low |
LR2.27 |
Amenity
Planting within the Private Development at There are amenity planting areas (~0.96ha) within
the private development at the podium of the Kowloon Station, such as the
podium garden, private open space playground (~1.10ha) and along the access
road within the private development area. There are approximately 70 young to semi-mature trees with
shrubs located within the private development, with height around 4-8m, crown
4.5-8m and DBH around 120-210mm. Amenity value is considered to be medium. Predominant
species consists of Phoneix sylvestris, Bauhinia spp., Ficus microcarpa and
Roystonea regia. The
condition of the trees range from poor to fair. |
Medium |
LR2.28 |
Roadside
Plantation along Western Harbour Crossing Bus Stop near Elements There are approximately 54 young to
semi-mature roadside trees with shrub in raised planter (~0.65ha) between WHC Bus
Stop and Elements with height around 3-8m, crown spread 1-4m
and DBH 150-300mm. Some trees grow under
the shade of the Ngo Cheung Road Flyover. Amenity value is considered to be
medium. All trees are in fair condition. Tree species mainly consist of Crateva unilocularis, Ficus
benjamina, Caryota mitis and Archontophoenix
alexandrae. |
Medium |
LR2.29 |
Roadside
There are approximately 96 young to semi-mature roadside trees with shrubs along Austin Road West with height ranging from 8-11m, crown spread
2-4m and DBH 100-350mm. Amenity value is considered as medium. Species
include Bauhinia x blakeana, Celtis sinensis, Cinnamomum
camphora, Crateva unilocularis, Ficus benjamina, Ficus microcarpa, Ficus
virens, Grevillea robusta, Lagerstroemia speciosa, Peltophorum pterocarpum, Senna siamea, Senna surattensis, Syzygium cumini and Terminalia
mantaly. The condition of the trees range from poor to fair. |
Medium |
LR2.30 |
Roadside
There are approximately 24 young trees with shrub in raised
planter (~0.04ha) around the Administration Building with height around
8-11m, crown spread around 2m and DBH around 200mm. Amenity value is
considered to be medium. Predominant tree species is Archontophoenix
alexandrae. The condition of the trees is fair. |
Medium |
LR2.31 |
Trees Buffering This is a tree buffer area (~1.67ha) located at the entrance of
Western Harbour Tunnel. The tree buffer was developed when the former Urban
Council instituted planting measures at the eastern edge of the site abutting
the portal of the Western Harbour Crossing. There are approximately 250 young to
semi-mature trees, of which 150
no. of trees are found within the site boundary, with height around 8-10m, crown spread
around 4-5m and DBH around 250-400mm. Amenity value is considered to be low
to medium. Tree species include Acacia
auriculiformis, Acacia confusa, Hibiscus
tiliaceus, Casuarina equisetifolia, Ficus benjamina, Ficus microcarpa,
and a considerable amount of self-seeded weed Leucaena leucocephala. The condition of the trees range from poor
to fair. |
Medium |
LR2.32 |
Roadside
Plantation along Western Harbour Crossing Bus Stop
next to New Yau Ma Tei Typhoon Shelter There are approximately 22 young to semi-mature trees with shrub in at grade planter
(~0.03ha) next to the New Yau Ma Tei Typhoon Shelter with height around
8-10m, crown spread 4-5m and DBH 150-300mm. Amenity value is considered to be
medium. Predominant tree species is Acacia confusa. The conditition
of the trees range from poor to fair. |
Medium |
LR2.33 |
Trees along New Yau Ma Tei
Typhoon Shelter Pier There are approximately 20 young to semi-mature trees with shrubs and grassland (~0.15ha) along
the typhoon shelter pier with height around 4-5m, crown spread 3-4m and DBH
150-300mm. Amenity value is considered to be medium. Predominant species are Carica papaya, Ficus microcarpa,
Koelreuteria bipinnata and self-seeded weed species Leucaena leucocephala. Note that there are more than 30
undersized self-seeded weed Leucaena
leucocephala. The conditition of the trees range from poor to fair. |
Medium |
LR2.34 |
Amenity
Planting within Salt Water Pumping Station There are total 65 young to mature trees with
grassland (~0.08ha) located within and next to the Salt Water Pumping Station
with height around 2-10m, crown spread 2-5m and DBH around 95-300mm.
Approximately 30 trees are located in planter boxes (1m X 1mX 1m) and
planting area within the pumping station and 35 trees with grassland
(~0.08ha) are located near the pump station. Amenity value is
considered to be low since most of the trees are self-seeded weed species.
Predominant tree species are Leucaena leucocephala, Livistona chinensis,
Bauhinia spp., Ficus microcarpa, Hibiscus tiliaceus and Washingtonia robusta.
The condition of the trees range from poor to fair. |
Low |
LR2.35 |
Tree Cluster in the Western Part within
the Boundary Area There are approximately 161 young to semi-mature trees with grassland (~1.41ha) located
in the western part of the site with height around 6-10m, crown spread 3-10m
and DBH 95-200mm. Amenity value is considered to be low since most of the
trees are self-seeded species with a considerable amount of Leucaena leucocephala which is a weed
species. Tree species mainly
consist of Leucaena leucocephala, Hibiscus tiliaceus, Acacia auriculiformis,
Caryota mitis and Morus alba. The condition of the trees range from
poor to fair. |
Low |
LR2.36 |
Tree Cluster in the Eastern
Part within the Boundary Area There are approximately 372 young to semi-mature trees with grassland located in the eastern
part of the site with height around 5-10m, crown spread 3-10m and DBH around 95-200mm.
Amenity value is considered to be medium. A considerable amount of Leucaena leucocephala, which is a weed
species, is surveyed. Tree species
mainly consist of Leucaena
leucocephala, Casuarina equisetifolia, Melia azedarach, Hibiscus tiliaceus,
Acacia auriculiformis, Ficus microcarpa, Ficus virens, Morus alba and Celtis sinensis. The condition of the trees range from poor
to fair. |
Medium |
Physical Landscape Resources LR3:
Waterbody |
||
LR3.1 |
Lying in the middle of the territory's dense urban region, the harbour
is famous for its deep and sheltered waters. It is a valuable natural asset of
|
High |
15.10.4.4 Landscape Character of the Assessment Area
Landscape character
zones have been identified within the Assessment Area in accordance to the “Landscape
Character Map of
The project site is
characterised by linear landscape, whose major features are highway, flyovers,
footbridges and toll plaza as well as associated miscellaneous roadside land
uses. Between the highway and flyover, there are landscape embankments and
islands, generally with semi-matures amenity vegetation of trees, palms and
shrubs.
The landscape
character of the surrounding areas to the east and north of the site is
classified as an Urban Landscape type “Late 20 Century/Early 21 Century
Commercial/Residential Complex Landscape”, comprising
Accordingly, the landscape character of the surrounding assessment
area varies from contemporary urban landscape, transportation corridor
landscape and coastal waters landscape.
As
WKCD is further sub-divided in a number of sub-district in accordance with the
land use and district identity. Therefore, during operation phase, the LCA01&
LCA03 will be further subdivided into a number of small LCAs in accordance with
the sub-district identity, and impact on these LCAs due to Austin Road flyover
is assessed.
15.10.4.5 Baseline Landscape Character Areas (LCAs)
The Landscape Character Areas are zoned with reference to the “Study of Landscape Value Mapping of Hong Kong”. Table 15.10.5 summarises the baseline LCAs and their sensitivity. The locations and photo records of the Landscape Character Areas during operation and construction period can be referred to in Figure 15.10.5, and Figure 15.10.7a to 15.10.7f.
Table 15.10.5: Landscape character areas and sensitivity
Ref. No. |
Baseline Landscape Character Areas |
Sensitivity (Low, Medium, High) |
LCA01 |
The approximate size of this LCA is 13.4ha. This area is where
the Park would be located in the proposed development. The topography is
generally flat. This area is open with clusters of trees. Tree plantation at
the eastern edge of the area abutting the portal of the Western Harbour
Crossing was planted by the former Urban Council. Elsewhere trees in this
area are mostly self-seeded weed species. This area has held some temporary
exhibitions such as the |
Low |
LCA02 |
The approximate size of this LCA is 14.62ha. This area is currently under site formation and underground structure works. The landscape character is changing from time to time with construction operations. This LCA has no district or regional significance. |
Low |
LCA03 |
The approximate size of this LCA is 4.07ha. This area is currently opened to the public and allows activities along the waterfront. The temporary waterfront promenade provides basic recreation structures like seating area, children’s play area, bicycle track and kiosk to the public. Generally hard paved with shrub plantings, some facilitates in the area can easily be demolished, replaced or reused. The DHL Hong Kong Balloon is temporarily located in the area. The maximum floating height is 100m, forming an icon of the area. As this LCA is temporary, it has no district or regional significance. |
Low |
LCA04 |
New Yau Ma Tei Typhoon Shelter Landscape The approximate size of this LCA is 20.78ha. This is an area
for typhoon shelter use in New Yau Ma Tei. It is substantially enclosed by
offshore breakwater. It is located
at the northern part of the WKCD and the coastal edges of Yau Ma Tei District.
It is an inshore aquatic landscape formed by the armourstone breakwaters
constructed to protect large numbers of moored vessels, such as freights,
fishing vessels and sampans. They consist primarily of water, which
incorporate the jetties, pontoons and navigational features resulting in a
landscape that is a transitional one between the coastal land and sea. It is
a vibrant and active landscape characterised by a variety of form and colour
and often by a significant sense of enclosure. This LCA has no district
or regional significance. |
Low |
LCA05 |
The approximate size of this LCA is 11.67ha. This side of the
water is facing west of the |
High |
LCA06 |
The approximate size of this LCA is 14.68ha. The |
High |
LCA07 |
New Yau Ma Tei Container Terminal Landscape The approximate size of this LCA is 2ha. This is a container terminal for container barges. The height of the container barges can be up to 30m which forms vertical elements towards the skyline. This LCA has no district or regional significance. |
Low |
LCA08 |
The approximate size of this LCA is 9.1ha. This is one of the 3
cross harbour tunnel in |
Medium |
LCA09 |
Tsim Sha Tsui Late 20C / Early 21C Commercial / Residential Complex
Landscape The approximate size of this LCA is 18.02ha. This area includes
the Elements mall and the |
Medium |
LCA10 |
Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) Terminus Construction
Site and Austin Station The approximate size of this LCA is 2.43ha. The XRL is part of
the strategic national express rail network that connects |
Low |
15.10.4.6 Baseline Visual Resources and Visually Sensitive Receivers
Visual Envelope
The baseline for the Visual Impact Assessment
is an understanding of the existing visual qualities within an area that could
be affected by the Project. This area refers to the Visual Envelope. The Visual
Envelope of the Project is illustrated in Figure 15.10.8.
It is defined by the area in proximity and
visually affected by the Project. It includes the first row of street blocks or
buildings facing towards the Project site, such as the residential and
commercial buildings located to the east and the northeast of the flyover
structure, and the area where the flyover structure located (i.e. West Harbour
Crossing Toll Plaza), and New Yau Ma Tei Typhoon Shelter.
Since
the scale of the Project is small, the primary zone of the visual influence is
considered as the Visual Envelope of the Project, covering the area in
proximity to the site. Different from the Visual Envelope of the WKCD
development, the Visual Envelope of the Project does not extend to the northern
side of
Visual Resources
Natural Ridgelines
Located to the north of West Kowloon, the
ridgeline of Lion Rock is a natural visual resource, providing a natural backdrop to the
high-rise urban areas of
Victoria Harbour is a unique natural asset of
Hong Kong, providing an open sea view to the areas along the northern coast of
Hong
Key Views
Key views include the magnificent views to
Existing
Site and Visual Character of the Project Site and Its Surroundings
The landscape character and the existing
state of the project site and its surroundings described in Section 15.10.4.1 to 15.10.4.4
contributes to the overall visual character of the project site.
According to the Landscape Character Map of Hong Kong published by Planning
Department in September 2003, the landscape character type of the project site
is Transport Corridor Landscape.
Where two or more major highways are
constructed parallel to each other and in close proximity, they form what can
be termed a Transportation Corridor Landscape. Situated on coastal
reclamations, these are linear landscapes, whose major features are the
highways and railways that define them, but which also include flyovers, noise
barriers, signage gantries, clover-leaf interchanges, traffic islands,
footbridges and toll plazas as well as associated miscellaneous roadside land
uses. Between the roads and railways are landscaped embankments and islands,
generally with a semi-mature amenity vegetation of trees and shrubs. The
outcome is a particularly linear landscape of rather diverse features.
Accordingly, the existing landscape character
of the project site comprises of transport corridor (i.e.
The site for the Project is located outside
the WKCD site as shown in Figure 15.10.1. It is currently occupied by
the Western Harbour Crossing (WHC) toll plaza.
Visually Sensitive
Receivers (VSRs)
Eight
existing VSRs and one planned VSR
located within the Primary Zone of Visual Influence
have been identified and shown in Figures 15.10.8.
The selected VSRs located within the
Primary Zone of Visual Influence are considered
to be visually most affected by the Project. Photos of the existing VSRs
within the study area are illustrated shown in Figure 15.10.9 and 15.10.10.
The baseline assessment of the sensitivity of the existing and planned VSRs within the study area is shown in Table 15.10.7. The sensitivity of the VSRs depends on the location of VSRs, the distance from the project area, the degree of visibility, and the type of VSR which determines the duration and frequency of views.
The sensitivity of residential VSRs (e.g. VSR 3) located in close proximity to the site is considered to be high, since they will have direct and frequent views towards the project area.
The sensitivity of VSR 1 International Commerce Centre (ICC) is considered to be medium to high, whilst the sensitivity of VSR 2 (the Elements) is considered to medium. It is because the DP is generally fully visible to VSR 1, but it is partly visible to VSR 2. Residential/commercial VSR, the Cullinun (VSR 7) is considered to have high sensitivity because it has long and frequent of view.
Transient VSRs including travellers on the sea transportation at Yau Ma Tei Typhoon Shelter (VSR 7), and travellers arriving West Harbour Crossing Toll Plaza (VSR 5) and at the footbridge crossing the WHC Toll Plaza (VSR 6), and travelling on the roads in the periphery of the WKCD such as Austin Road West (VSR 8) have low sensitivity, because their views are transient in nature.
The sensitivity of the planned VSR, M+
Museum (Phase 2) (VSR 9) is considered to be medium as it will have partial
views towards the project area.
Most of the VSRs are located at elevated levels, including VSR 1, VSR 2, VSR 3 and VSR 4. All the transient VSRs have views to the site at ground level.
This VIA also assesses committed
developments located immediately adjacent to the site. These committed
developments are the concurrent projects mentioned in Section 15.10.7 Concurrent Projects. The cumulative visual impacts
to the selected VSRs will be assessed.
Brief descriptions of the eight existing VSRs identified within the Visual Envelope are provided in Table 15.10.6.
Table 15.10.6: Brief descriptions of the VSRs and the existing views
Key VSR |
Brief
descriptions of the VSR and
the existing views |
|
Residential/Commercial VSRs Located
Immediately to the East and Northeast of the site |
||
VSR 1 |
International
Commerce Centre (ICC) |
¡ Standing above Kowloon Station and the Elements
shopping mall, ICC rises to 490 metres above sea level and is the tallest
building in ¡ Located to the east of the site. ¡ Elevated view
of the site can be seen. ¡ Due to the orientation of the building block,
only the views from the western facing offices would be affected. ¡ The workers at lower levels have partial views to
the site, whilst the workers at higher levels have an open view to the site. |
VSR 2 |
The Elements |
¡ At the base of the ICC tower and 5 high rise
residential developments (i.e. the Harbourside, the Arch, the Waterfront,
Sorrento Towers and the Cullinan), the Elements shopping mall comprises of 4
floors of retail shops, including ground, first, second and roof floors (i.e.
podium level). ¡ Views to the site are largely blocked by the
existing footbridge and flyover located to the east of VSR 2. However, a close view of the site can be seen at podium level. ¡ On the ground floor level, most of the areas are
occupied by the transportation facilities, including public transport
interchange, concourse of Kowloon Station, Airport Express in Town check in hall,
coach terminus and parking etc. Most of these areas are enclosed. ¡ Due to the orientation of the building block,
only the views from the south
western and western facing areas of
the mall and its podium would be affected. |
VSR 3 |
The Cullinun |
¡ Located next to ICC and above Kowloon Station and
the Elements shopping mall, the Cullinun is comprised of a towering twin
edifice. VSR 3 has a partial view of the site that is blocked by the existing
footbridge. ¡ W Hotel occupies the first to the 38th
floors of the Cullinan. ¡ Due to the orientation of the building block,
only the view from the western and south western facing units of the hotel
and residential development would be affected. |
Transport related
VSRs located to the southeast of the Project Site |
||
VSR 4 |
|
¡ Located to the southeast of the site,
administration building at Western Harbour
Crossing is a three storey
building. ¡ Close and partial view to the Project site can be
seen. ¡ Due to the orientation of the building block,
only the view from the northern facing workers would be affected. |
Transient VSRs |
||
VSR 5 |
Travellers
arriving Western Harbour
Crossing (WHC) |
¡ The Western
Harbour Crossing is a dual 3-lane immersed tube tunnel in Hong Kong, linking
the newly reclaimed land in West Kowloon with Sai Ying Pun on ¡ Varying views depending on locations at ¡ Views to the ¡ The travellers arriving at |
VSR 6 |
Travellers at the
footbridge crossing the |
¡ Varying views depending on locations at the
footbridge. ¡ It is viewed at elevated view. ¡ Views to the site will be blocked by the
footbridge structure itself and the advertisement board at the footbridge. |
VSR 7 |
Travellers at Yau Ma Tei Shelter |
¡ Varying views depending on locations at Yau Ma Tei Typhoon Shelter. ¡ Views to the site will be partially blocked by
the footbridge structures located to the north of the site and the vegetation
located along the waterfront. |
VSR 8 |
Travellers along |
¡ Varying views depending on locations along ¡ Close and partial view to the site when approaching the western end of ¡ It is viewed at the ground level. |
Planned VSR |
||
VSR 9 |
M+ Museum (Phase
2) |
¡ Immediately located to the east of the Park and
the entrance of the Western Harbour Tunnel, M+ will be the ¡ It will have a partial view of the flyover
structure when viewed to the north. |
Table 15.10.7: Sensitivity of the VSRs
Type of
VSR |
VSRs |
Name of VSRs |
Viewing Distance (m) approx. |
Estimated Number of Individuals/ receiver population (Many/ medium/ few) |
Type of
VSR |
Value and Quality of Existing View |
Availability and amenity of alternative views |
Degree of Visibility |
Duration (Long/ Medium/ Short) and Frequency of View (Frequent/Occasional/Rare) |
Sensitivity (Low/ Medium/ High) |
CDA |
VSR 1 |
International Commerce
Centre (ICC) |
60m |
Many |
View from commercial development (i.e. offices and hotel) (workers/ hotel guests) |
Good |
Limited availability /Good amenity of alternative
view |
Partly to fully visible |
Long/ Occasional |
Medium to High |
CDA |
VSR 2 |
The Elements |
45m |
Many |
View from commercial development (i.e. shopping mall) (workers/ visitors) |
Medium |
Medium availability/ Medium amenity of
alternative view |
Partly visible |
Long/Occasional |
Medium |
R |
VSR 3 |
The Cullinun |
270m |
Many |
View from residential development
and hotel (residents and hotel guests) |
Good |
Good availability /Good amenity of alternative
views |
Partly visible |
Long/Frequent |
High |
C |
VSR 4 |
|
45m |
Few |
View from the administration building (Workers) |
Medium |
Medium availability /Medium amenity of alternative
views |
Fully visible |
Long/Occasional |
Low |
T |
VSR 5 |
Travellers arriving |
Varies |
Many |
Travellers arriving the |
Fair |
Limited availability |
Glimpse view |
Short/Frequent |
Low |
T |
VSR 6 |
Travellers at the
Footbridge Crossing the |
Varies |
Few |
Travellers Crossing the |
Fair |
Medium availability |
Glimpse view |
Short/Occasional |
Low |
T |
VSR 7 |
Travellers at Yau Ma Tei Typhoon Shelter |
Varies |
Medium |
Travellers on sea transportation |
Good |
Good availability/ Good amenity of
alternative views |
Glimpse view |
Short/Occasional |
Low |
T |
VSR 8 |
Travellers along |
Varies |
Medium |
Passengers/ pedestrians and other road users |
Medium |
Medium availability/ Fair amenity of
alternative view |
Glimpse view |
Short/Occasional |
Low |
OU |
VSR 9 |
M+ Musuem (Phase 2) |
40m |
Medium |
View from M+ Building (Workers and Visitors) |
Fair |
Medium availability/ Medium amenity of
alternative view |
Partly visible |
Long/Occasional |
Medium |
Notes: Type of VSR: Comprehensive Development Area (CDA); Residential (R); Commercial (C); Other Specified (OU) and Transient (T).
15.10.5 Evaluation and Assessment of Landscape and Visual Impacts
15.10.5.1 Landscape Impact Assessment
Source of Landscape Impacts
Landscape impacts arise due to the
construction of the
Potential sources of impacts on LRs and LCAs during construction and operation phases are summarized in Table 15.10.8:
Table 15.10.8: Source of impacts during construction and operation phase
Landscape Impacts |
|
Construction Phase
(Direct Impacts) |
|
LC1-1 |
Construction of the flyover and associated
works |
LC1-2 |
Removal and
disturbance of existing trees |
Construction
Phase (Indirect Impacts) |
|
LC1-3 |
The laying
down of utilities, including water, drainage and power, |
LC1-4 |
Temporary site
access areas, site cabins, material storage and heavy machinery, |
Operation Phase
Impacts |
|
LO1-1 |
Operation of the new flyover |
Magnitude of Change of LRs and LCAs
The magnitude of change, before implementation of mitigation
measures, on landscape resources and
landscape character area that would occur in the construction and operation phase are summarized
in Table 15.10.9 and Table 15.10.10 respectively. It is
assumed that the construction of
Note that only the landscape resources (Open
Space: LR1.7; Amenity Planting: LR2.29 and LR2.31 and LR2.36) and landscape
characters area (LCA01, LCA03, LCA08 and LCA09) which are affected by Austin
Road flyover will be assessed with magnitude of change. Some landscape
resources (Open Space: LR1.15; Amenity Planting: LR2.26 to LR2.28; LR2.30;
LR2.32 to LR2.35; Water Body: LR3.1) and landscape character area (LCA02, LCA04
to LCA07 and LCA10), which are not affected by Austin Road Flyover, are omitted
in the assessment since they are insubstantially impacted and have no source of
impact.
Table 15.10.9: Impacts on landscape resources during construction and operation phase
LR No. |
Landscape Resources |
Compatibil-ity of
the project with the surrounding landscape (High / Medium / Low) |
Reversibility (High / Medium / Low) |
Scale of Develop-ment (Large / Medium /
Small) |
Source of Impact |
Description of
Impacts |
Duration of Impact
under construction and operation phases (Long/Short) |
Magnitude of
changes (Large/ Intermediate/ Small / Negligible) |
||
Construct-ion Phase |
Operation Phase |
Construct-ion Phase |
Operation Phase |
|||||||
LR1:
Open Space |
||||||||||
LR 1.7 |
Temporary open space along the waterfront promenade within the site boundary |
Medium |
Medium |
Small |
LC1-1,
LC1-3, LC1-4 |
|
Due to the
construction works, excavation works and interim works of the underpass road,
there will be loss of approximately 0.002ha temporary open space to the public in the construction stage. Affected area consists of parts of the road
and cycling track with associated street planting leading towards the
temporary waterfront promenade. In the
operation phase, affected area of the landscape resource will be reinstated
as part of the Park with the provision of
open space for public enjoyment. |
Short |
Small |
Small |
LR2: Amenity Planting |
||||||||||
LR2.29 |
Roadside |
Medium |
Medium |
Small |
LC1-1 to LC1-4 |
LO1-1 |
Although there are 96 roadside trees in LR2.29,
only 36 roadside trees in raised planter (~0.2 ha) near WKCD area will be
affected by the construction of Austin Road Flyover (LC1-1), and indirectly
affected by associated temporary works (LC1-2 to LC1-4) during construction
period. 20 trees, with poor form/heath will be proposed to be felled. As the
amenity and health condition of these tress are medium, 16 trees are proposed
to be transplanted and 60 trees without affected by the works will be
proposed to be retain in situ with adequate tree protection measures during
the construction stage. In the operation phase, this LR will become part of
the WKCD pedestrian walkway. |
Long |
Intermed-iate |
Intermed-iate |
LR2.31 |
Trees Buffering |
Low |
Low |
Medium |
LC1 -1 to, LC1-4 |
LO1-1 |
Although there are 250 trees in LR2.31, only 50 trees n the tree
buffer area (~0.16ha) within WKCD area will be affected by construction of
Austin Road Flyover (LC1-1) and
indirectly affected by associated temporary works (LC1-2 to LC1-4) during
construction period. 30 trees are proposed to be felled as they are
mainly ubiquitous species easily replaceable by new planting with better
quality, while others (20 trees) with medium amenity value,
will be proposed to be transplanted. 200 trees, with no direct conflicts with
the construction of Austin Road Flyover, are proposed to be retained in situ
with adequate tree protection works. Part of this LR (~0.02ha) will become
Austin Road Flyover during operation phase. |
Long |
Intermed-iate |
Intermed-iate |
LR2.36* |
Tree Cluster in the Eastern Part within the Boundary Area |
Low |
Low |
Medium |
LC1-1 to LC1-4 |
|
Although there are 372 trees in LR 2.36, only 10 trees with grassland (~0.0027 ha) will be affected.10 trees with
fair health and tree form and medium amenity value will be transplanted
within site and 362 trees in this LR with no direct conflict with the
construction of Austin Road Flyover, will be retained in situ. During operation phase, this LR will become part of the Park and
Avenue. |
Long |
Small |
Small |
* Note that some trees located in LR2.36 are currently being relocated to areas around LR2.31 by LCSD, hence the actual tree numbers are subject to further changes.
Table 15.10.10: Impacts on landscape character areas during construction and operation phase
LCA. No. |
Landscape Resources |
Compatibility of
the project with the surrounding landscape (High/Medium/ Low) |
Reversibility (High/ Medium/ Low) |
Scale of Develop-ment (Large/Medium/Small) |
Source of Impact |
Description of
Impacts |
Duration of Impact
under construction and operation phases
(Long/Short) |
Magnitude of
changes (Large/ Intermediate/ Small / Negligible) |
||
Construction Phase |
Operation Phase |
Construct-ion Phase |
Operation Phase |
|||||||
LCA01 |
|
Medium |
Medium |
Small |
LC1-1 to LC1-4 |
LO1-1 |
Approximately
0.35ha of this LCA will be affected permanently by construction of Austin
Road Flyover(LC1-1), which will result in lost a
portion of the LCA01.Part of
this LCA will changed into part of the Flyover and will result to existing
tree will be felled and incompatibility of construction works to the LCA. There are
total 522 trees (150 trees in LR2.31 and 372 trees in LR2.36) in this LCA, of
which 30 trees and tree buffer area (~0.16ha) in LR2.31 will be felled, 30
trees will be transplanted (20 trees in LR2.31 and 10 trees in LR2.36) and
462 trees will be retained in situ (100 trees in LR2.31 and 362 tree sin
LR2.36). Also, this LCA may be indirectly affected by the associated excavation
works and temporary works (LC1-2 to
LC1-4) of the construction of Austin Road Flyover
(LC1-1). |
Long |
Intermed-iate |
Intermed-iate |
LCA03 |
|
Medium |
Medium |
Small |
LC1-1, LC1-4 |
LO1-1 |
Relatively small area (approximately 0.02ha) of this LCA will be affected permanently by construction of Austin Road Flyover (LC1-1). Part of this LCA will changed into part of the Flyover, which will result to the incompatibility of construction works to this LCA. Also, this LCA will be indirectly affected by the associated excavation works and temporary works of the flyover and may cause convenience to the entrance of the WKCD temporary waterfront during construction period.. |
Long |
Small |
Small |
LCA08 |
|
Low |
Low |
Large |
LC1-1, LC1-3 and LC1-4 |
LO1-1 |
Approximately 0.3ha of this LCA will be permanently affected by the
construction of Austin Road Flyover
(LC1-1), which will result to the incompatibility of construction works to
this LCA. 100 trees in LR2.31 with no direct conflicts with the construction
of Austin Road Flyover will be retained in situ. Also, this LCA may be
directly affected by associated temporary construction works (LC1-3 and LC1-4). |
Long |
Intermed-iate |
Intermed-iate |
LCA09 |
Tsim Sha Tsui Late 20C / Early 21C Commercial / Residential Complex Landscape |
Medium |
Medium |
Medium |
LC1-1 to LC1-4 |
LO1-1 |
Approximately 0.32ha of this LCA will be affected by the construction of Austin Road Flyover (LC1-1), which will result in existing trees to be felled and and incompatibility of construction works to the LCA. There are total 96 trees in LR2.29, which 20 trees in raised planter (~0.2ha)will be felled, 16 trees will be transplanted and 60 trees, with no direct conflicts with the construction of Austin Road Flyover, will be retained in situ. Also, this LCA will be indirectly affected by the associated excavation works and temporary works of the flyover |
Long |
Small |
Small |
* Note that some trees located in LR 2.36 are
currently being relocated to areas around LR 2.31 by LCSD, hence the actual
tree numbers are subject to further changes.
Landscape Impacts to LRs during Construction and Operation Phase (Before Mitigation)
The significance of landscape impact is a function of the sensitivity of the affected landscape receptors and the magnitude of change that they will experience. The major landscape impact that will arise from the proposed development is the existing trees would be felled within site boundary during construction phase.
In summary, it is anticipated that affected
Landscape Resources during construction and operation phase are LR1.7, LR2.29, LR2.31
and LR2.36. Those LRs with insubstantial impact are not elaborated in details.
The significant of landscape impacts, before
implementation of mitigation measures, to Landscape Resources, in the
construction and operation phase are assessed and presented in Table 15.10.17.
The significance of unmitigated impacts on landscape resources would vary from slight
adverse to moderate adverse.
Impact on LR1
Open Space
LR 1.7 – Temporary open space along the
waterfront promenade within the site boundary
It is a temporary open space with medium sensitivity. During construction
phase, construction of Austin Road Flyover will result the temporary loss of public
open space (~0.002ha). Affected
area consists of parts of the road and cycling track with associated street
planting leading towards the temporary waterfront promenade. However,
as the affected area is relatively small (~0.002ha), which magnitude of change
due to construction of Austin Road Flover is considered as small and the
resultant unmitigated impact during construction and operation phase is slight
adverse.
Impact on LR2
Amenity Planting
LR2.29 – Roadside
96 roadside trees will be affected by the
construction of Austin Road Flyover and indirectly affected by associated
temporary works during construction period. Trees affected are common species
with medium amenity value and poor to fair condition and of young to semi
mature size. Their sensitivity is considered medium. Existing trees in
raised planters (~0.2ha) will be felled, which 20 trees with poor form/health
will be felled, 16 trees with medium amenity and health condition will be
transplanted. Magnitude of change due to the construction activities is
considered intermediate. The unmitigated landscape impact on this LR during
construction and operation phase is moderate adverse.
LR2.31 – Tree
Buffering
250 existing trees in the tree buffer area
(~-0.16ha) within the WKCD area will be affected by the construction of Austin
Road Flyover and indirectly affected by associated temporary works. Trees found
are common species with low to medium amenity value and poor to fair condition
and of young to semi mature size. Their sensitivity is considered medium.
Existing trees in tree buffer area within the works area will be felled from
the site, of which 30 trees with tree buffer area (~0.16ha) will be felled and
20 trees with amenity value will be transplanted during the construction phase.
200 trees in this LR with no direct conflicts with the construction of Austin
Road Flyover will be retained in situ. Magnitude of change to this LR is
considered intermediate. It is noted that some trees in LR2.36 will be
relocated to areas around LR 2.31 by LCSD, hence actual tree numbers are
subject to further changes. The
unmitigated landscape impact on this LR during construction and operation phase
is moderate adverse.
LR2.36 – Tree Cluster in the Eastern Part
within the Boundary Area
This LR will be affected by the construction
of Arena and the surrounding plaza and landscape area. Tree cluster, with
medium amenity value and poor to fair condition, and grassland are found
scattered in the eastern part within the boundary area. Their sensitivity is
considered as medium. Although there
are 372 trees in this LR, approximate 10 trees with fair health and tree form
and medium amenity will be transplanted within site and grassland (~0.0027ha)
will be removed from site. Other 362 trees in LR 2.36 with no direct conflicts
with the construction of Austin Road Flyover will be retained in situ. The magnitude
of change is considered as small. It is noted
that some trees in LR2.36 will be relocated to areas around LR 2.31 by LCSD, hence
actual tree numbers are subject to further changes. The unmitigated landscape
impact during construction and operation phases on this LR is slight adverse.
Impact on
Existing Trees
For LR, approximately 718 trees (96 trees in
LR2.29, 250 trees in LR2.31 and 372 trees in LR2.36) will be affected by the
construction of Austin Road Flyover, of which 50 trees (20 trees in LR2.29 and
30 trees in LR2.31) with self-seed species and/or poor health and tree form
will be felled, 46 rees (16 trees in
LR2.29, 20 trees in LR2.31 and 10 trees
in LR2.36) with fair health condition and tree form and medium amenity value
will be transplanted and 622 trees (60 trees in LR 2.29, 200 trees in LR 2.31
and 362 trees in LR2.36), with no direct conflicts with the construction of
Austin Road Flyover, will be retained in situ.
Affected tree species include Acacia auriculiformis, Acacia confusa, Bauhinia
x blakeana, Casuarina equisetifolia, Celtis sinensis,
Cinnamomum camphora, Crateva unilocularis, Ficus benjamina, Ficus microcarpa,
Ficus virens, Grevillea robusta, Hibiscus tiliaceus, Lagerstroemia speciosa,
Peltophorum pterocarpum, Senna siamea, Senna surattensis, Syzygium cumini
and Terminalia mantaly. The majority
of tree species affected is self-seeded weed Leucaena leucocephala. The condition of the tree
range from poor to fair. Amenity value range from low
to medium.
Landscape Impacts to LCAs during Construction and Operation Phase (Before Mitigation)
For LCAs, approximately 0.99 ha of the LCAs
will be affected. Affected Landscape Character Area during construction phase are LCA01, LCA03, LCA08 and LCA09. Major landscape impacts
to affected LCAs (LCA01, LCA03, LCA08 and LCA09) are the loss of existing
trees, permanent loss of portion of LCA and the incompatibility of construction
works to the LCAs.
The significant of landscape impacts, before
implementation of mitigation measures, to Landscape Character Area, in the
construction and operation phases are assessed and presented in Table 15.10.18.
The significance of unmitigated impacts on landscape character area would vary
from slight to moderate. They are described as below:
LCA01
This LCA is still a vacant land reserved for
WKCD development, which has no direct or regional significance. The sensitivity
of this LCA is low during construction phase. Part of this LCA (~0.35ha)
will be permanently affected by the construction of Austin Road Flyer and
associated excavation works and temporary works. Part of this LCA will change
into part of the Flyover and will result to the existing trees will be felled and
incompatibility of construction works to this LCA There are total
522 trees (150 trees in LR2.31 and 372 trees in LR2.36) in this LCA, of which
30 trees and tree buffer area (~0.16ha) in LR2.31 will be felled, 30 trees will
be transplanted (20 trees in LR2.31 and 10 trees in LR2.36) and 462 trees will
be retained in situ (100 trees in LR2.31 and 362 tree sin LR2.36). Magnitude of change to this LCA is
considered as intermediate. The unmitigated landscape impact during
construction and operation phase is moderate adverse.
LCA03
This area is currently a temporary open
space opened to the public and allow activities along the waterfront, as this
LCA is temporary, which has no district or regional significance, the
sensitivity of the LCA is
considered as low. Part of this LCA (~-0.02ha) of this LCA
will permanently affected by the construction of Austin Road Flyer and form
part of it, which will result to the incompatibility of construction works to
this LCA during construction phase. As the affected area (~0.02ha) is
relatively small, magnitude of change to this LCA is considered as small.
. The unmitigated landscape impact during construction and operation phase is slight
adverse.
LCA08
This cross harbour tunnel with buffering
tree is characterised with heavy traffic, which has no district or regional significance,
the sensitivity of this LCA is considered as medium. Part of this LCA
(~0.3ha) will be affected by the construction of Austin Road Flyover, which
will result incompatibility of construction works to this LCA. 100 trees in LR2.31 with no direct
conflicts with the construction of Austin Road Flyover will be retained in situ. Magnitude of changes is considered as intermediate.
The unmitigated landscape impact during construction and operation phase is moderate
adverse.
LCA09 Tsim Sha Tsui Late 20C/Early 21C
Commercial/ Residential Complex Landscape
This LCA is dominated with mixed residential
and commercial use and characterized as an enclosed and colourful urban landscape, the sensitivity of this LCA is medium.
Part of this LCA (0.32ha) will be affected by the construction of Austin Road
Flyover, which will result to the existing trees to be felled and and incompatibility of construction
works to the LCA. There are
total 96 trees in LR2.29, which 20 trees in raised planter (~0.2ha)will be
felled, 16 trees will be transplanted and 60 trees, with no direct conflicts
with the construction of Austin Road Flyover, will be retained in situ. Magnitude of change to this LCA is
considered as small. The significance of unmitigated landscape impact
during construction and operation is considered as slight adverse.
15.10.5.2
Visual Impact Assessment
The
assessment of the significance of visual impacts is based on a combination of
factors, including the sensitivity of
the selected VSRs, their
magnitude of change and whether impacts are beneficial or adverse, short term or long term, reversible or
irreversible and direct or indirect. Visual compatibility of the associated structures of the Project with the surroundings, and
its obstruction and interference with key views of the VSRs are important
considerations for the visual
impact assessment.
Sources of Visual Impacts during
Construction and Operation Phases
Major
direct visual impacts,
including degrading of visual quality of existing views, and visual incompatibility
of the works with the visual context of
the surrounding areas,
will be resulted from the following construction activities during construction
phase. In addition to the construction
activities mentioned above, night time lighting provided for the construction
activities could be one of the sources of visual impacts during construction
phase. However, the visual impacts derived by these construction activities are temporary.
The
impacts during operation phase depend on visual compatibility of the associated
structures to the surrounding landscape.
The sources of direct and indirect visual
impacts during construction and operation phases are listed in Table 15.10.11.
Table 15.10.11: Sources of direct and indirect visual impacts during construction and operation phases
Sources
of Direct Visual Impacts during Construction Phase |
|
DVIC
1 |
Construction of flyover and associated
works |
DVIC
2 |
Rearrangement of existing facilities on top
of the |
DVIC
3 |
Night time lighting provided for the construction activities |
Sources of Indirect
Visual Impacts during Construction Phase |
|
IVIC
1 |
Construction traffic |
IVIC
2 |
Various construction activities including operation
of PME, utilities at the piers
and diversion of abutments of the flyover |
IVIC
3 |
Temporary site access |
IVIC
4 |
Heavy machinery |
IVIC
5 |
Dust during dry weather |
Source
of Direct
Visual
Impacts
during Operation
Phase |
|
DVIO
1 |
Erection of flyover |
Magnitude of Change of the VSRs
The factors determining the magnitude of impacts include scale of development, compatibility of the project with the surrounding landscape, reversibility of change, viewing distance, potential blocking of view, duration of impacts under construction and operation phases.
Given
that the scale of the development is small, high reversibility of impact/change
and short duration of impact during construction phase, the magnitude of change
of the VSRs mainly depends on the viewing distance, and potential blocking of
view by the Project. The magnitude of change of the VSR 4 (
Except VSR 4 (Administration Building at Western Harbour Crossing) has an intermediate magnitude of change, the magnitude of change of all VSRs ranges from negligible to small during operation phase, due to the high compatibility of the proposed development with the surrounding landscape,.
The magnitude of change of the VSRs during construction and operation phases is shown in Table 15.10.12.
Table 15.10.12: Magnitude of Change of VSRs
VSRs |
|
Viewing Distance (m) approx. |
Potential Blocking of View (Full/Partial/ Slight/None) |
Reversibility of Impact (Yes/No) |
Compatibility of
the Proposed
development with the Surrounding Landscape (High/Medium/Low) |
Scale of Proposed Development (large/small) |
Duration of Impacts during Construction/ Operation Phases |
Magnitude
of Change |
|
During Construction
Phase |
During Operation
Phase |
||||||||
VSR 1 |
International Commerce Centre (ICC) |
60m |
Slight |
Yes |
High |
Small |
Short/ Permanent |
Small |
Small |
VSR 2 |
The Elements |
45m |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Small |
Small |
VSR 3 |
The Cullinun |
270m |
None |
Yes |
High |
Small |
Short/ Permanent |
Negligible |
Negligible |
VSR 4 |
|
45m |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Intermediate |
Intermediate |
VSR 5 |
Travellers arriving |
Varies |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Intermediate |
Small |
VSR 6 |
Travellers at the |
Varies |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Intermediate |
Small |
VSR 7 |
Travellers at Yau Ma Tei Typhoon Shelter |
Varies |
None to Slight |
Yes |
High |
Small |
Short/ Permanent |
Negligible to
small |
Negligible |
VSR 8 |
Travellers along |
Varies |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Small |
Small |
VSR 9 |
M+ Museum |
40m |
Partial |
Yes |
High |
Small |
Short/ Permanent |
Small |
Small |
Visual Impacts during
Construction Phase (Before Mitigation)
During construction phase, the unmitigated
visual impacts are adverse in nature. The visual impacts are resulted from
blockage of views to the visual resources, visual incompatibility of the construction
works with the surroundings and degrading of visual quality of existing views.
Due to the small
scale of the DP, most of the VSRs will experience slight to moderate visual
impacts before mitigation. However,
the visual impacts during
construction phase are
temporary. The assessment of visual impacts during construction phase is
summarised in Table
15.10.13.
Visual Impacts
during Operation Phase (Before Mitigation)
During operation phase, the major unmitigated visual impacts are resulted from blockage of views. Since the scale of the Project is localized, VSRs to be affected will be confined to those located in close proximity to the Project. Since the visual context in the proximity is dominated by road network structures, the proposed flyover is considered compatible with the surroundings. The visual impacts derived by the Project during operation phase are generally small.
The assessment of visual impacts during
construction phase is summarised in Table 15.10.13. The photomontages showing the flyover structures are provided at Figures 15.10.11a to 15.10.13b.
Night
Time Visual Impacts due to the Project
Since the scale of the Project is
comparatively small and there are a number of light sources in the surrounding
areas of the project site, it is considered that it is compatible with the
existing urban setting, and hence the night time visual impacts arising from the
Project during construction and operation phases are not significant to most
VSRs. It is also acceptable to residential VSRs nearby (ie. VSR 3 The Cullinun), which is the most sensitive VSR to the night
time visual impacts. It is because VSR 3 is located to the north of the project
site, and the night time illumination arising from the project will be as
strong as other road side night time lighting. Whilst some night time lighting
will be blocked by the existing footbridge crossing
Table 15.10.13: Assessment of Visual Impacts during Construction Phases
VSRs |
|
Location of VSRs |
Type & Approximate Number of VSRs |
Description of Existing View & Degree
of Visibility of DP |
Receiver’s Sensitivity |
Source of Impact |
Minimum Viewing Distance of VSRs |
Magnitude of Change |
Significance Threshold of Potential Visual Impact (Before Mitigation) |
Mitigation Measures |
Significance Threshold of Residual
Impact |
|
|
|
|||||||||
VSR 1 |
International Commerce Centre (ICC) |
Located immediately to the east of the site and the |
Type of VSR View from commercial
development (i.e. offices and hotel)
(workers/ hotel guest) Number of VSR Many |
Existing View n
Elevated view of the site can be seen. n
Visual composition comprises a footbridge and the
WHC toll plaza in the foreground, with Yau Ma Tei Typhoon Shelter in the
background. Degree of
Visibility of DP n
The DP will be largely blocked by the existing
footbridge when viewed from lower floors. n
The top view of the DP will be seen from upper
floors. |
Medium to
High |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4 |
60m |
Small |
Slight (upper floors) Moderate (lower
floors) |
MMCP1 |
Slight (upper floors) Slight to Moderate (lower floors) |
VSR 2 |
The Elements |
Located immediately to the east of the site and the |
Type of VSR View from commercial
development (i.e. shopping mall) (workers/ visitors) Number of VSR Many |
Existing View n
Visual composition comprises footbridges, and
existing flyover in the foreground, and Degree of
Visibility of DP n
Views to the site are largely blocked by the existing footbridges and flyover. n
Partial view of the DP can be seen at podium
level.
|
Medium |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4 |
45m |
Small |
Moderate |
MMCP1 |
Slight to Moderate |
VSR 3 |
The Cullinun |
Located immediately to the northeast of the site and to the east of |
Type of VSR View from residential
development and hotel (residents and hotel guests) Number of VSR Many |
Existing View n
Visual composition comprises Degree of
Visibility of DP n
VSR 3
has a partial view of the DP
that is largely blocked by the
existing footbridge. |
High |
DVIC 1, DVIC
2, DVIC 3 IVIC 1, IVIC
2, IVIC 3, IVIC
4, |
270m |
Negligible |
Slight |
MMCP1, MMCP2 |
Negligible |
VSR 4 |
|
Located immediately to the south of the site and in front of the
entrance of the WHC |
Type of VSR View from the administration building (Workers) Number of VSR Few |
Existing View n
Existing view comprises a footbridge, the n
Close and open view of the site and Degree of
Visibility of DP n
Visual composition comprises the DP in the
foreground. |
Low |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4, IVIC 5 |
45m |
Intermediate |
Moderate |
MMCP1 |
Slight to Moderate |
VSR 5 |
Travellers arriving |
Located to the north of the site |
Type of VSR Travellers arriving the Number of VSR Many |
Existing View n
Varying
views depending on locations at Degree of
Visibility of DP n
Partial view of the DP can be seen due to the
footbridge blocks the view to the DP when viewed from the north of the DP. |
Low |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4, IVIC 5, IVIC
6 |
Varies |
Small (viewed from the north of
the site) Intermediate (viewed from the south of
the site) |
Slight |
MMCP1 |
Slight |
VSR 6 |
Travellers at the |
Located immediately to the
north of the site |
Type of VSR Travellers Crossing the Number of VSR Few |
Existing View n
Varying
views depending on locations at the footbridge. n
Elevated view of the entrance of the WHC and the Degree of Visibility
of DP n
Partial view of the DP can be viewed. |
Low |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4, IVIC 5, IVIC
6 |
Varies |
Intermediate |
Slight |
MMCP1 |
Slight |
VSR 7 |
Travellers at Yau Ma Tei Typhoon Shelter |
Located to the west of the site and the |
Type of VSR Travellers on sea transportation Number of VSR Medium |
Existing View n
Varying
views depending on locations at Yau Ma Tei Typhoon Shelter. n
Existing views to the WHC Toll Plaza are largely
blocked by the vegetation along the waterfront and footbridge structures in
the foreground. Degree of
Visibility of DP n
View to the DP is largely blocked by the
vegetation along the waterfront and the footbridge in the foreground. n
Only partial view of the DP can be seen. |
Low |
DVIC 1 &
DVIC 2 |
Varies |
Negligible to
Small |
Slight |
MMCP1 |
Negligible |
VSR 8 |
Travellers along |
Located immediately to the east
of the site and to the south of VSR 1and VSR 2 |
Type of VSR Passengers/ pedestrians and other road users Number of VSR Medium |
Existing View n
Varying
views depending on locations at n
Visual composition comprises carriageways and
roadside planting on both sides of the roads. Degree of
Visibility of DP n
Close view of the site can be seen when
approaching to the western end of |
Low |
DVIC 1, DVIC
2, IVIC 1, IVIC
2, IVIC 3, IVIC
4, IVIC 5, IVIC
6 |
Varies |
Small |
Slight |
MMCP1 |
Slight |
VSR 9 |
M+ Museum |
Located to the east of the site |
Type of VSR View from an arts
andcultural facility (Workers and
Visitors) Number of VSR Medium |
Existing View n
Existing view comprises a footbridge, the n
Close and partial view of the site. Degree of
Visibility of DP n
Only partial view of the DP can be seen. Part of
the views is blocked by the administration building at WHC. |
Medium |
DVIC 1, DVIC 2, IVIC 1, IVIC 2, IVIC 4, IVIC
5. |
40m |
Small |
Moderate |
MMCP1 |
Slight to Moderate |
Table 15.10.14: Assessment of Visual Impacts during Operation Phase
VSRs |
|
Location
of VSRs |
Type
& Approximate Number of VSRs |
Description
of Existing View & Degree of Visibility of DP |
Receiver’s
Sensitivity |
Source
of Impact |
Minimum
Viewing Distance of VSRs |
Magnitude
of Change |
Significance
Threshold of Potential Visual Impact (Before
Mitigation) |
Mitigation
Measures |
Significance
Threshold of Residual Impact |
|
|
|
|
Operation (Day
1) |
Operation (Year
10) |
||||||||
VSR 1 |
International
Commerce Centre (ICC) |
Located immediately to the east of the site and the
|
Type of VSR View from commercial development (i.e. offices and
hotel) (workers/ hotel
guest) Number of VSR Many |
Existing View n
Elevated view of the site can be seen. n
Visual composition comprises a footbridge and the
WHC toll plaza in the foreground, with Yau Ma Tei Typhoon Shelter in the
background. Degree of Visibility of DP n
The DP will be largely blocked by the existing
footbridge when viewed from lower floors. n
The top view of the DP will be seen from upper
floors. |
Medium to High |
DVIO 1 |
60m |
Small |
Insubstantial (upper floors) Slight (lower floors) |
MMOP1, MMOP2, MMOP3, |
Insubstantial (upper floors) Slight (lower floors) |
Insubstantial (upper floors) Slight (lower floors) |
VSR 2 |
The Elements |
Located immediately to the east of the site and the
|
Type of VSR View from commercial development (i.e. shopping mall) (workers/ visitors) Number of VSR Many |
Existing View n
Visual composition comprises footbridges, and
existing flyover in the foreground, and Degree of Visibility of DP n
Views to the site are largely blocked by the footbridges and flyover. n
Partial view of the DP can be seen at podium
level.
|
Medium |
DVIO 1 |
45m |
Small |
Slight to Intermediate |
MMOP1, MMOP2, MMOP3. |
Slight |
Slight |
VSR 3 |
The Cullinun |
Located immediately to the northeast of site and to
the east of |
Type of VSR View from residential development and hotel (residents and hotel guests) Number of VSR Many |
Existing View n
Visual composition comprises Degree of Visibility of DP n
VSR 3
has a partial view of the DP
that is largely blocked by the
existing footbridge. |
High |
DVIO 1 DVIO 2 |
270m |
Negligible |
Slight |
MMOP1, MMOP2, MMOP3, MMOP4.
|
Insubstantial |
Insubstantial |
VSR 4 |
|
Located immediately to the south of site and in
front of the entrance of the WHC |
Type of VSR View from the administration building (Workers) Number of VSR Few |
Existing View n
Existing view comprises a footbridge and the n
Close and open view of the site. . Degree of Visibility of DP n
Visual composition comprises the DP in the
foreground. |
Low |
DVIO 1 |
45m |
Intermediate |
Slight to Moderate |
MMOP1, MMOP2, MMOP3. |
Slight |
Slight |
VSR 5 |
Travellers
arriving |
Located to the north of the site |
Type of VSR Travellers arriving the Number of VSR Many |
Existing View n
Varying
views depending on locations at Degree of Visibility of DP n
Partial view of the DP due to blockage of the
view to the DP by the existing footbridge when viewed from the north of the
D. |
Low |
DVIO 1 |
Varies |
Small |
Small (viewed from the north of the site) Small to Moderate (viewed from the south of the site) |
MMOP1, MMOP2, MMOP3. |
Insubstantial (viewed from the north of the site) Small (viewed from the south of the site) |
Insubstantial viewed from the
north of the site) Small (viewed from the south of the site) |
VSR 6 |
Travellers at the
|
Located immediately
to the north of the site |
Type of VSR Travellers Crossing the Number of VSR Few |
Existing View n
Varying
views depending on locations at the footbridge. n
Elevated view of the entrance of the WHC and the Degree of Visibility of DP n
Partial view of the DP can be viewed. |
Low |
DVIO 1 |
Varies |
Small |
Small |
MMOP1, MMOP2, MMOP3. |
Insubstantial |
Insubstantial |
VSR 7 |
Travellers at Yau Ma Tei Typhoon Shelter |
Located to the west of the site and the |
Type of VSR Travellers on sea transportation Number of VSR Medium |
Existing View n
Varying
views depending on locations at Yau Ma Tei Typhoon Shelter. n
Existing views to the WHC Toll Plaza are largely
blocked by the vegetation along the waterfront and footbridge structures in
the foreground. Degree of Visibility of DP n
View to the DP is largely blocked by the
vegetation along the waterfront and the footbridge in the foreground. n
Only partial view of the DP can be seen. |
Low |
DVIO 1 |
Varies |
Negligible |
Insubstantial |
MMOP1, MMOP2, MMOP3. |
Insubstantial |
Insubstantial |
VSR 8 |
Travellers along |
Located immediately
to the east of the site and to the south of VSR 1and VSR 2 |
Type of VSR Passengers/ pedestrians and other road users Number of VSR Medium |
Existing View n
Varying
views depending on locations at n
Visual composition comprises carriageways and
roadside planting on both sides of the roads. Degree of Visibility of DP n
Close view of the site can be seen when
approaching to the western end of |
Low |
DVIO 1 |
Varies |
Small |
Slight |
MMOP1, MMOP2, MMOP3. |
Insubstantial |
Insubstantial |
VSR 9 |
M+ Museum |
Located to the east of the site |
Type of VSR View from an arts
and cultural facility (Workers and
Visitors) Number of VSR Medium |
Existing View n
Existing view comprises a footbridge, the n
Close and partial view of the site. Degree of Visibility
of DP n
Only partial view of the DP can be seen. Part of
the views is blocked by the |
Medium |
DVIO 1 |
40m |
Small |
Slight to Intermediate |
MMOP1, MMOP2, MMOP3. |
Slight |
Slight |
Considerations of Alternative
Options
Alternative options have been considered to
compare the advantages and disadvantage of different options. It is considered
that at-grade and underground options are not technically viable due to direct
conflict with the existing WHC operation, and insufficient space and
obstruction by existing piled foundations below the WHC toll plaza
respectively.
Given the site constraints and site
conditions, the proposed flyover is virtually the only alignment option for the
provision of the essential alternative vehicular access to Mega Performance
Venue (MPV) and Exhibition Centre (EC) at the WKCD.
During the planning process, design measures
have been incorporated in the development layout so as to minimize any
potential adverse visual impact on the VSRs at the WKCD. For instance, the eastern
end of the proposed flyover will be connected to the existing elevated road
junction of
The details of Consideration of
Alternative Development Options are provided at Section 15.2.4.
15.10.6 Mitigation Measures
15.10.6.1 Landscape Mitigation Measures
The construction works would inevitably create undesired adverse impacts to the landscape resources and landscape character areas.
Design Measures as Mitigation
Measures during Detail Design Stage
Design measures will be developed as mitigation measures during detail design stages.
- Transplanting of mature tree in good health and amenity value where appropriate and reinstatement of areas disturbed during construction by compensatory hydro-seeding and planting;
- Protection measures for the trees to be retained during construction activities;
- Maximize coverage of greenery with tree, shrub and other vegetation planting to compensate the loss of existing tree and amenity planting area;
- Providing salt tolerant tree species along the planter strips at the waterfront promenade;
- Temporary greening measures, e.g. roadside ornamental planting in removable planters around peripheral of site works area as temporary screening and carry out removal green roof panel/vertical green panel on the roof/facade of site offices during construction works;
- Maximize the opportunity of soft landscape treatments, such as vertical green wall/ climber/ roof greening, etc, to soften the hard architectural and engineering structures and facilities;
- Landscape design shall be incorporated to architectural and engineering structures in order to provide aesthetically pleasing designs.
Mitigation Measures to be applied during Construction and Operation Phase
To reduce the impact towards the existing landscape resources, mitigation measures during construction and operation phase are proposed and summarized in Table 15.10.15 and Table 15.10.16. Generally, mitigation measures shall be implemented as early as possible and many of these measures perform multiple functions.
Table 15.10.15: Landscape mitigation measures during construction phase
Ref. No. |
Mitigation Measures during Construction Phase |
Funding Agency |
Implementation Agency |
Management/ Maintenance
Agency |
CM1 |
Trees should be retained in situ on site as far as possible. Should tree removal be unavoidable due to construction impacts, trees will be transplanted or felled with reference to the stated criteria in the Tree Removal Applications to be submitted to relevant government departments for approval in accordance to ETWB TCW No. 29/2004 and 3/2006. |
WKCDA – for work area within
WKCD site CEDD- for work areas of
external connections Private Developer – for works areas within private land sale lots |
Contractor |
WKCDA or appointed landscape contractor |
CM2 |
Compensatory tree planting shall be incorporated to the
proposed project and maximize the
new tree, shrubs and other vegetation planting to compensate tree felled and
vegetation removed. Also, implementation of compensatory planting
should be of a ratio not less than 1:1 in terms of quality and quantity
within the site. |
Same as
above |
Contractor |
WKCDA or appointed landscape
contractor |
CM3 |
Buffer trees for screening purposes to soften the hard
architectural and engineering structures and facilities. |
WKCDA |
Contractor |
WKCDA or appointed landscape
contractor |
CM4 |
Softscape treatments such as vertical green wall panel /planting of climbing and/or weeping plants, etc, to maximize the green coverage and soften the hard architectural and engineering structures and facilities. |
WKCDA |
Detailed Design Consultant/ Contractor |
WKCDA or appointed landscape
contractor |
CM7 |
Structure, ornamental planting shall be provided along amenity strips to enhance the landscape quality. |
WKCDA |
Contractor |
WKCDA or appointed landscape contractor |
CM8 |
Landscape design shall be incorporated to architectural and engineering structures in order to provide aesthetically pleasing designs. |
WKCDA |
Detailed Design Consultant / Contractor |
WKCDA or appointed landscape
contractor |
Table 15.10.16: Landscape mitigation measures during operation phase
Ref. No. |
Mitigation Measures during Operation Phase |
Funding Agency |
Implementation Agency |
Management/ Maintenance Agency |
OM1 |
Provide
proper planting establishment works, including watering, pruning, weeding,
pest control, replacement of dead plant, etc, on the new planting areas to
enhance the aesthetic design degree |
WKCDA – for work area within
WKCD site CEDD- for work areas of
external connections Private Developer – for works areas within private land sale lots |
Contractor |
LCSD – for public roadside and
pedestrian footbridge planting1 Private Developers – for all
landscaping within the private land sale lots WKCDA – for all other areas
within WKCD |
OM2 |
Provision of
open space in various forms and at different levels on or above ground,
including park, waterfront promenade, piazzas and terrace garden and
assoociated green connections for public enjoyment. |
WKCDA |
Detailed Design Consultant / Contractor |
WKCDA or appointed landscape
contractor |
1 in accordance with ETWB No.
2/2004
The Landscape Master Plan and general
landscape arrangement for the WKCD development is shown in Figure 15.10.15. The plan is
preliminary and for illustrative purpose only and subject to further amendment
in detailed design stage. List of Landscape and Visual Mitigation Measures for
Austin Road Flyover are shown in Figure 15.10.14. Details of landscape
mitigation measures are shown in Figure 15.10.15 to 15.10.17.
15.10.6.2 Significance Threshold of Residual Impact (Before and After Mitigation Measures)
The significance threshold of each LR and
LCA has been derived through the assessment of sensitivity abnd magnitude of
change associated with the proposed works. Table 15.10.1
shows the relationship between sensitivity and magnitude of change. The
efficiency and success of proposed mitigation measures are taken in
consideration when analyzing the significance of the threshold of residual
impact after mitigation. The residual
impact of each LR and LCA regarding the significance threshold before and after
mitigation measures are summarized in the Table 15.10.17 and
Table 15.10.18.
Table 15.10.17: Significance of impacts on landscape resources during construction and operation phases
LR No. |
Landscape Resources |
Sensitivity (Low, Medium, High) |
Magnitude of Change (Negligible, Small, Intermediate, Large) |
Significance Threshold of impacts before Mitigation
(Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Significance Threshold of Residual Impact after Mitigation
(Insubstantial, Slight, Moderate, Substantial) |
||||||||
Construction Phase |
Operation |
|||||||||||||
Construction Phase |
Operation Phase |
Construction Phase |
Operation Phase |
Construction Phase |
Operation Phase |
Day 1 |
YR 10 |
|||||||
Existing Landscape Resources LR1: Open Space |
||||||||||||||
LR1.7 |
Temporary
Open Space along the Waterfront Promenade within the Site Boundary |
Medium |
Medium |
Small |
Small |
Slight (adverse) |
Slight (adverse) |
CM4, CM7 and CM8; OM1, OM2 |
Insubstantial |
Insubstantial |
Slight
(beneficial) |
|||
LR1.15 |
Public
Open Space at the podium of Kowloon Station |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2: Roadside Amenity |
||||||||||||||
LR2.26 |
Trees
along |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.27 |
Amenity
Planting within the private development at the Kowloon Station |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.28 |
Roadside
|
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.29 |
Roadside
|
Medium |
Medium |
Intermediate |
Intermediate |
Moderate (adverse) |
Moderate (adverse) |
CM1 to
CM3, CM4, CM7 and CM8; OM1 |
Slight (adverse) |
Slight (adverse) |
Insubstantial |
|||
LR2.30 |
Roadside
|
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.31 |
Trees
Buffering |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate (adverse) |
Moderate (adverse) |
CM1 to
CM3, CM4, CM7 and CM8; OM1 |
Slight (adverse) |
Slight (adverse) |
Insubstantial |
|||
LR2.32 |
Roadside
|
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.33 |
Trees
along New Yau Ma Tei Typhoon Shelter Pier |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.34 |
Amenity
Planting within Salt Water Pumping Station |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.35 |
Tree
Cluster in the Western Part within the Boundary Area |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
LR2.36 |
Tree
Cluster in the Eastern Part within the Boundary Area |
Medium |
Medium |
Small |
Small |
Slight (adverse) |
Slight (adverse) |
CM1 to
CM3, CM4, CM7 and CM8; OM1 |
Insubstantial |
Insubstantial |
Slight
(beneficial) |
|||
LR3: Water Body |
||||||||||||||
LR3.1 |
|
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|||
*Notes: All significance thresholds are adverse unless otherwise stated.
Table 15.10.18: Significance of impacts on landscape character area during construction and operation phases (all impacts are adverse unless otherwise stated)
ID. No. |
Landscape Character Areas |
Sensitivity (Low, Medium, High) |
Magnitude of Change (Negligible, Small, Intermediate, Large) |
Significance Threshold of Impact before Mitigation
(Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Significance Threshold of Residual Impact after Mitigation
(Insubstantial, Slight, Moderate, Substantial) |
||||||
Construction |
Operation |
|||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Day 1 |
Year 10 |
|||||
Existing Landscape Character Areas |
||||||||||||
LCA01 |
|
Low |
High |
Intermediate |
Intermediate |
Moderate (adverse) |
Moderate (adverse) |
CM1 to CM3; OM1 |
Slight (adverse) |
Insubstantial |
||
LCA02 |
|
Low |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
LCA03 |
|
Low |
High |
Small |
Small |
Slight (adverse) |
Moderate (adverse) |
CM3,
CM7 and CM8; OM1 and OM2 |
Insubstantial |
Insubstantial |
Slight (Beneficial) |
|
LCA04 |
New Yau
Ma Tei Typhoon Shelter Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
LCA05 |
|
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
LCA06 |
|
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
LCA07 |
New Yau
Ma Tei Container Terminal Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
LCA08 |
|
Medium |
Medium |
Intermediate |
Intermediate |
Moderate (adverse) |
Moderate (adverse) |
CM1 to
CM3; OM1 |
Slight (adverse) |
Insubstantial |
Slight (Beneficial) |
|
LCA09 |
Tsim Sha
Tsui Late 20C / early 21C Commercial / Residential Complex Landscape |
Medium |
Medium |
Small |
Small |
Moderate (adverse) |
Moderate (adverse) |
CM1 to
CM3; OM1 |
Slight (adverse) |
Insubstantial |
Slight (Beneficial) |
|
LCA10 |
Guangzhou-Shenzhen-Hong
Kong Express Rail Link (XRL) Terminus Construction Site and Austin Station |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
|
15.10.6.3 Visual Mitigation Measures
Representative
views from the key VSRs have been selected to illustrate the effectiveness of
the proposed mitigation measures. Photomontages of the viewpoints viewed by the
selective key VSRs are shown in Figure 15.10.11a to 15.10.13b.
Visual Mitigation Measures
during Construction Phase
Mitigation
measures will be used to lessen any visual impacts of the construction works
such as the use of decorative screen hoarding/boards and control of night time
lighting. Screens
or hoardings around the site limit should be in visually unobtrusive colour to
screen the proposed works. These
construction phase measures should be adopted from the commencement of construction
and should be in place throughout the entire construction period. In addition to visual mitigation measures mentioned above, control of
night time lighting such as avoidance of lighting from spilling onto nearby
developments will be adopted to minimise the night time visual impacts during
construction phase.
A summary of the
visual mitigation measures to be implementation during construction phase is
shown in Table
15.10.19.
Table
15.10.19: Visual Mitigation Measures during
Construction Phase
Mitigation Measures |
Target VSRs |
Funding Agency |
Implementation Agency |
Management/ Maintenance Agency |
|
MMCP1 |
Use of decorative screen hoarding/ boards |
All of the VSRs |
WKCDA – for work area within WKCD site CEDD – for works areas of external connections |
Contractor |
Contractor |
MMCP2 |
Control of night time lighting such as avoidance of lighting from spilling onto nearby developments |
Residential VSR (i.e. VSR 3) |
WKCDA – for work area within WKCD site |
Contractor |
Contractor |
Visual Mitigation Measures during Operation Phase
The Project will incorporate design measures aiming to avoid unacceptable visual impacts. An aesthetically pleasing, integrated design in terms of form, textures and colour of the proposed project components and associated structures will be compatible with the existing surroundings. Control of night time lighting is one of the mitigation measures for the potential night time visual impacts. It can be controlled by careful considerations for the locations and the angle of the lighting to avoid lighting from spilling onto nearby developments.
The operation phase mitigation measures should be adopted as part of the construction works so that they are in place at the date of commissioning of the Project.
It is noted that despite of infeasibility and inadequate space for planting at the flyover, softscape treatments such as climbers are proposed to mitigate the visual impacts derived by the hard engineering structures of the flyover. Full effect of the soft landscape mitigation measures at the WKCD, in particular the trees planted at the entrance of the WHC and the Park would reach a level maturity after several years. This may contribute to greening of the visual composition when viewed to the Project.
A
summary of the visual mitigation measures to be implemented during operation
phase is shown in Table
15.10.20.
Table
15.10.20: Visual Mitigation Measures during Operation
Phase
|
Mitigation Measures |
Target VSRs |
Funding Agency |
Implementation Agency |
Management/Maintenance Agency |
MMOP1 |
Integrated design of the flyover with the existing flyover located to the west of the Elements |
All VSRs |
WKCDA – for work areas within WKCD site CEDD – for works areas of external connections |
Contractor |
n/a |
MMOP2 |
Softscape treatments such as climbers shall be incorporated to soften the hard engineering structures. |
All VSRs |
Same as above |
Contractor |
LCSD – for public roadside and
pedestrian footbridge planting1 WKCDA – for all other areas
within WKCD |
MMOP3 |
Compensatory planting in close proximity of the flyover structure |
All VSRs |
Same as above |
Contractor |
LCSD – for public roadside and
pedestrian footbridge planting1 WKCDA – for all other areas
within WKCD |
MMOP4 |
Control of night time lighting such as careful considerations for the locations and the angle of the lighting |
Residential VSR (i.e. VSR 3) |
WKCDA – for work areas within WKCD site |
Contractor |
WKCDA / Contractor |
1 in accordance with ETWB No.
2/2004
15.10.6.4 Programme
of Implementation of Landscape and Visual Mitigation Measures
The
construction phase measures listed in Table 15.10.15 and Table 15.10.19 should be adopted from commencement of
construction, and shall be in place throughout the entire construction period.
The operation phase measure listed in Table 15.10.16 and Table 15.10.20
should be adopted during the detailed design stage, and be built as part of the
construction, so that they are in place at the dated of commissioning of the
Project. It should be noted that the soft landscape mitigation measures would
not be appreciated for several years.
The WKCD
development will be constructed in many phase. It is assumed that the
construction of
15.10.7 Evaluation of Cumulative and Residual Impacts
15.10.7.1
Cumulative impacts
An assessment of the cumulative landscape
and visual impacts of the
The sources of impact from concurrent
projects during construction and operation phases are summarised as Table 15.10.21.
Table 15.10.21: Potential cumulative
landscape and visual impacts from concurrent projects
Proposed Development |
Construction Phase |
Operation Phase |
Express Rail
Link (and WKT) |
Construction of diaphragm wall and foundations, excavation concreting and backfill works as well as the operation of concrete batching plant and barging points, etc. |
Above-ground structures including WKT and ventilation
shafts in |
Road
Improvement Works in |
Excavation, roads/ underpasses construction and construction of noise screening structures, etc |
Structures such as noise barriers |
Central |
Construction of a trunk road and tunnel, with administration and ventilation buildings; and associated works. |
Structures such as ventilation buildings |
Table 15.10.22 shows the summary of the affected LRs and LCAs and VSRs and potential
cumulative impacts generated by the concurrent designated projects in the
adjacent areas and the proposed WKCD development.
Table 15.10.22: Summary of LRs, LCAs and
VSRs affected by concurrent projects
Concurrent
Designated Projects |
Affected LRs/LCAs |
Affected VSRs |
Express Rail Link (and WKT) |
As construction is in progress, accumulative
impacts are minimal. |
Construction and Operation Phases VSR 1, VSR 2, VSR 8, VSR 9 |
Road works at |
||
Road Improvement Works in |
Construction Phase VSR 2, VSR 3, VSR 4, VSR 5 ,VSR 7 and VSR 8 Operation Phase All of the above except VSR 7 |
|
Central |
N/A |
Affected LRs/LCAs
Cumulative
Impacts on Landscape Resources during Construction and Operation Phase
The concurrent projects in the surrounding
area are concentrated at the northern site boundary. As the construction of the
concurrent projects is in progress, accumulative landscape impacts to
affected landscape resources are minimal. Only those LRs near the northern site boundary, e.g. LR2.29 will be
affected by the construction of Austin Road Flyover and concurrent projects.
The cumulative impacts on landscape resources are the loss of existing roadside
planting area and existing trees (36 trees in LR2.29) would be felled. Some of
the road side planting LR2.29 (~0.65ha) will be transformed to the future road
works at
With the implementation of proposed mitigation
landscape measures (including compensatory tree planting) during construction
phase, it is considered that there would not have any additional insurmountable
landscape impact during construction phase. Tree loss due to the construction
of Austin Road Flyover and concurrent project will be compensated in a ratio of
1:1 or more in construction phase. Compensatory tree will be located within the
site boundary. It is expected to have a
net gain of trees. The residual cumulative impacts on existing
trees during operation phase will be slight adverse in Day 1 and insubstantial
in Year 10.
Construction activities might cause
disturbances to the landscape resources in the surrounding area. For instance,
dust and construction noise may deteriorate the value and usage of the
surrounding open space. Dust and pollutant emissions due to traffic congestion
during construction phase may affect the health of existing trees. The
foundation works of the piers may affect the existing street trees. Given the
number of trees located immediately within the construction area of the flyover
is relatively small, these indirect impacts are considered to be low.
Cumulative Impacts
on Landscape Character Area during Construction and
Operation Phases
It is expected that construction of Austin
Road Flyover and other concurrent projects, i.e. XRL Terminus, Residential/CDA development
above Austin Station and Road Works at
As a
whole, cumulative impacts on LCAs will not create additional insurmountable
adverse impact with the implementation of mitigation measures.
Affected
VSRs during Construction Phase
Road
Works at
As the road works at
The cumulative visual impacts imposed on the
relevant VSRs after the implementation of mitigation measures such as screens
and hoardings are considered to be slight/ moderate.
Road
Improvement Works in
VSR 2, VSR 3, VSR 5, VSR 7, VSR 8 and VSR 9 are
the affected VSRs for the road improvement works in West Kowloon Reclamation
Development (Phase I and Phase II).
Construction of road bridge linking
to WKH and construction of road
bridge and carriageway connecting WKH and NCR are anticipated to pose moderate to substantial cumulative impacts on
VSR 2, VSR 3, VSR 4, VSR 5 and VSR 9, whilst junction improvement works
at Junctions of Canton Road/ Austin Road
are considered to pose moderate cumulative impacts on VSR 7 and VSR 8 during
construction phase due to its transient nature.
Since the type of VSR 3 is residential, its
sensitivity is considered to be high due to long and frequent duration of view.
Therefore, the cumulative impacts on VSR 3 are substantial even after the
implementation of the mitigation. However, the cumulative impacts during
construction phase are temporary only.
Affected
VSRs during Operation Phase
Road
Works at
Given the
magnitude of change of the affected VSRs (i.e. VSR 1, VSR 2, VSR 8 and VSR 9)
is small, the cumulative visual impacts posed on the affected VSRs are mostly
slight/ insubstantial during operation phase.
Road
Improvement Works in
It is anticipated the road improvement works
will be highly compatible with the visual amenity of the transport corridor
type of landscape. Give the magnitude of change is small,
the cumulative impacts on the affected VSRs are generally slight and even
negligible.
15.10.7.2
Residual impacts
Residual Landscape Impact
Despite the mitigation measures mentioned in
Section 15.10.6, it is inevitable
that certain residual impacts would still be placed on the site, both in
construction and operation phases. The residual impacts on landscape resources
and landscape character areas are generally insubstantial to slight beneficial.
Residual Impact on
Landscape Resources during Construction and Operation Phase
Impact on LR1 Open Space
None of these landscape resources will be affected during construction and operation phase.
LR 1.7 – Temporary open space along the
waterfront promenade within the site boundary
Relatively small area (~0.002ha) of
temporary open space to the public will be affected. Affected area consists of
parts of the road and cycling track with associated street planting. However,
as the construction of underpass road may be at the same time with the
construction of the Park and waterfront promenade, There
will be slight adverse residual impact on this LR during construction
phase due to the construction of Austin Road Flyover. During operation phase,
affected area of LR will become part of the Park for public enjoyment, with minimum 23ha of open
space for public use will be provided within the site boundary . With the
re-provided vegetation grows and established, enhancement of landscape quality
with the provision of the open space and better connection of WKCD and
neighbour area facilitate the public enjoyment during operation phase of Austin
Road Flyover, residual impact on this LR will become insubstantial in Day 1 and slight beneficial in Year 10.
Impact on LR2 Amenity Planting
LR2.29 – Roadside
36 roadside trees in raised planter (~0.2 ha) near WKCD area will be affected by the construction of Austin Road Flyover (LC1-1), and indirectly affected by associated temporary works (LC1-2 to LC1-4) during construction period. 20 trees, with poor form/heath will be proposed to be felled. As the amenity and health condition of these tress are medium, 16 trees are proposed to be transplanted and 60 trees without affected by the works will be proposed to be retain in situ with adequate tree protection measures during the construction stage. In the operation phase, this LR will become part of the WKCD pedestrian walkway. 16 transplanted trees and new compensatory trees will be planted to the reinstated new landscaped area during construction phase, there will be slight adverse residual impact on this LR. During operation phase, part of the LR will permanently become part of the road works. With the re-provided vegetation grows and established, enhancement of landscape quality, it is considered the residual impact will be slight adverse in Day 1 and insubstantial in Year 10 during operation phase with the implementation of mitigation measures.
LR2.31 – Tree Buffering
30 trees with tree buffer area (~0.16ha) will be felled and 20 trees will be transplanted during construction of Austin Road Flyover. However, 20 transplanted trees and new compensatory buffer trees will be planted in landscaped area of this LR with the sensitive streetscape design during construction, there will be slight adverse residual impact on this LR. During operation phase, part of this LR will become Austin Flyover. With the re-provided vegetation grows and established, enhancement of landscape quality, it is considered that residual impact will be slight adverse in Day 1 and insubstantial in Year 10 during operation with the implementation of mitigation measures.
Impact on LR3 Waterbody
Total 5 trees will be transplanted and
grassland (~0.0027ha) will be felled during the construction of Austin Road
Flyover. However, 5 transplanted trees and new compensatory buffer trees with
vertical green will be provided in the site during construction phase. This
relatively small affected area will be further developed into part of the Park
and Avenue within this LR. Aesthetic landscape design, with new compensatory
trees, will be incorporated to architectural/engineering structures to enhance
the landscape quality of this LR during construction phase,
it is considered there will be insubstantial
residual impact on this LR. With the
re-provided vegetation grows and established and enhancement of landscape
quality during operation phase in this LR,, residual impact on this LR will
become insubstantial in Day 1 and
slight beneficial in Year 10 with the implementation of mitigation measures..
Impact on Existing Trees
Based on the broad brush tree survey,
approximately 1194 trees are surveyed within the study boundary. There are 718
trees (96 trees in LR2.29, 250 trees in LR2.31 and 372 trees in LR2.36) will be affected by
construction of
Approximately 50 trees (20 trees in LR2.29
and 30 trees in LR2.31) with self-seed species and/or poor health and tree form
will be felled and 46 trees (16 trees in
LR2.29, 20 trees in LR2.31 and 10 trees in LR2.36) with fair health condition
and tree form and medium amenity value will be transplanted and 622 trees ( 60
trees in LR2.29, 200 trees in LR2.31 and 362 trees in LR2.36) with no direct
conflicts with the construction of Austin Road Flyover, will be retained in situ
during construction period. It is considered that transplanted trees will recover
after Year 10.
With the implementation of new compensatory
tree and transplanted trees to be provided within the site during construction
phase, the residual impact is considered
slight beneficial. Many of the trees are not recommended to be transplanted
as they are either in poor form and health or are weed species. None of the
affected trees are LCSD Champion Trees or Registered Old and Valuable Trees.
There are no rare species or endangered species but common species. All trees
with medium to high amenity value, which are unavoidably affected by the works will be transplanted where possible. Detailed tree
felling application and compensatory planting proposal will be submitted in
accordance with ETWB TC 3/2006 during the detailed design stage. Implementation
of compensatory planting should be of a ratio not less than 1:1 in terms of
quality and quantity within the site.
The quality of compensatory trees should be at least of “heavy standard”
(Section 3 of the General Specification for Civil Engineering Works refers).
Proposals which deviate from this principle will be supported with
justification, in order to ensure the greening opportunity within the site is
optimised where feasible. Also, sufficient space will be provided for the
planting of compensatory trees with the consideration of minimum space required
to cater for the establishment and healthy growth of the trees.
Affected tree species include Acacia auriculiformis, Acacia confusa, Bauhinia
x blakeana, Casuarina equisetifolia, Celtis sinensis,
Cinnamomum camphora, Crateva unilocularis, Ficus benjamina, Ficus microcarpa,
Ficus virens, Grevillea robusta, Hibiscus tiliaceus, Lagerstroemia speciosa,
Peltophorum pterocarpum, Senna siamea, Senna surattensis, Syzygium cumini
and Terminalia mantaly. The majority
of tree species affected is self-seeded weed Leucaena leucocephala. The condition of the tree
range from poor to fair. Amenity value range from low
to medium.
The actual figure of trees to be
transplanted/ felled should depend on the result of a more detailed tree survey
on the affected tree. The quantities of trees affected are summarized in Table 15.10.23.
Table 15.10.23: Residual impacts on existing trees during construction phase
Ref. No. |
Landscape Resources |
Source of Impact |
|
Residual Impacts during Construction Phase |
||
|
|
|
Total no. of tree in LRs |
No of trees to be felled |
No
of trees to be transplanted |
No
of trees to be retained |
LR2.29 |
Roadside |
LC1-1 to
LC1-4 |
96 |
20 |
16 |
60 |
LR2.31* |
Trees
Buffering |
LC1-1 to
LC1-4 |
250 |
30 |
20 |
200 |
LR2.36* |
Tree Cluster
in the Eastern Part within the Boundary Area |
LC1-1 to
LC1-4 |
372 |
0 |
10 |
362 |
|
|
Total: 718 no.
affected tree |
718 |
50 |
46 |
622 |
* Note that some trees
located in LR2.36 are currently being relocated to areas around LR2.31 by LCSD,
hence the actual tree numbers are subject to further changes.
Detail tree felling application and compensatory
planting proposal will be submitted in accordance with ETWB TC 3/2006 during
the detailed design stage. Implementation of compensatory planting
should be of a ratio not less than 1:1 in terms of quality and quantity within
the site. The quality of compensatory
trees should be at least of “heavy standard” (Section 3 of the General
Specification for Civil Engineering Works refers). Proposals which deviate from
this principle will be supported with justification, in order to ensure the
greening opportunity within the site is optimised where feasible. Also,
sufficient space will be provided for the planting of compensatory trees with
the consideration of minimum space required to cater for the establishment and healthy
growth of the trees. The compensatory tree planting and new landscape works as
mitigation measures to the loss of greenery are proposed for the Austin Road
Flyover. As the landscape quality of the existing trees is low, the proposed
substantial number of new tree plantings as a mitigation measures are
sufficient to compensate the loss of existing trees. The overall cumulative
residual impacts on existing trees are considered to be beneficial in the
longer term after development. The beneficial impact would substantially
increase with time after trees reach maturity.
Residual Impact on Landscape Character
Areas during Construction and Operation Phase
The residual impacts on landscape character
areas are generally insubstantial to slight adverse during construction
phase and insubstantial to slight beneficial in operation phase The residual impact on landscape character areas during
operation phase are mostly considered to be beneficial in the long term. Details
are summarised in Table
15.10.24.
Table 15.10.24: Residual impacts on landscape character areas during operation phase
Ref. No. |
Landscape Character Areas |
Residual Impact on Landscape Character Areas |
LCA01 |
|
31 and 372 trees in LR2.36) in this LCA, of which 30 trees and tree
buffer area (~0.16ha) in LR2.31 will be felled, 30 trees will be transplanted
(20 trees in LR2.31 and 10 trees in LR2.36) and 462 trees will be retained in
situ (100 trees in LR2.31 and 362 tree sin LR2.36). With the new compensatory tree to be
provided within the site, there will be slight adverse residual impact on this LCA during
construction phase. As LCA01 will be
under construction and largely become Park area and part of the M+ extension
are, MPV, Hotel and the Arena Plaza during operation phase, the quality of
the greenery space will be greatly improved. With the
re-provided vegetation grows and established, enhancement of landscape quality
and better connection between WKCD and neighbourhood area during operation
phase, residual impact on this LCA is considered as insubstantial in Day 1 and slightly beneficial in Year 10 of operation phase. |
LCA03 |
|
Relatively small area (~0.02ha) of this LCA will be affected by the construction
of Austin Road Flyover , which will result to the
loss of temporary open space (~0.02ha) in LR1.7 and incompatibility to the
LCA. With the new
compensatory tree to be provided within the site, there will be insubstantail residual impact on
this LCA during construction phase. However, as LCA03 will be under construction and substituted by a newly designed waterfront promenade providing better facilitates and open space quality. Also, the operation phase of Austin Road Flyover facilitates the public enjoyment and provide better connection between WKCD and neighbourhood area. With the re-provided vegetation grows and established and provision of open space during operation phase, the residual impact in Day 1 of operation phase is considered to be insubstantial and become slightly beneficial in Year 10. |
LCA08 |
|
Approximately 0.3 ha of this LCA will be
affected by the construction of Austin Road Fl.over and will result to the
incompatibility of the construction works to this LCA. 100 trees in LR2.31 with no direct
conflicts with the construction of Austin Road Flyover will be retained in
situ. With the provision of ornamental roadside
planting to further enhance the landscape quality during construction phase,
there will be slight adverse residual impact on
this LCA. During operation phase, Austin Road Flyover will provide better
connection in LCA08. LCA08
comprising |
LCA09 |
Tsim Sha Tsui Late 20C / Early 21C Commercial Residential Complex Landscape |
Approximate 0.32ha of this LCA will become part of the Austin Road
Flyer, which will result existing
trees to be felled and and incompatibility of construction works to the LCA. There are total 96 trees in LR2.29, which
20 trees in raised planter (~0.2ha)will be felled, 16 trees will be
transplanted and 60 trees, with no direct conflicts with the construction of
Austin Road Flyover, will be retained in situ. With the provision of new compensatory planting during construction
phase, there will be slight adverse residual impact on
this LCA. During operation phase, Austin Road Flyover will provide better connection in LCA09 and improve the accessibility brought by operation of Austin Road Flyover. New compensatory tree with planting area will be provided with sensitive streetscape design and further enhance the landscape quality. With the re-provided vegetation grows and established and further enhancement of the landscape quality to this LCA, the residual impact is considered to be insubstantial in Day 1 and slight beneficial in Year 10 with implementation of mitigation measures during operation phase . |
Residual Visual Impact
Residual Visual Impacts
during Construction Phase
As the scale of the Project is small, it is considered that the residual visual impact on most of the VSRs is slight to moderate during construction phase with the implementation of mitigation measures such as erection of screen hoarding, except VSR 3 The Cullinun and VSR 7 Travellers at Yau Ma Tei Typhoon Shelter. However, the mitigation measures proposed at ground level would not be able to mitigate the visual impacts for views from the higher level of some of the VSRs, in particular VSR 1 International Commerce Centre (ICC).
Residual Visual Impacts
during Operation Phase
The flyover structure is compatible with the “transport
corridor” landscape setting of the West Harbour Crossing, the residual
adverse impact on most of the
VSRs, therefore, is considered
to be slight or even insubstantial. A transport corridor is a generally linear tract
of land that contains lines of transportation such as highways,
or railroads.
The
VSRs located in close proximity to the flyover such as VSR 1 International Commerce Centre (ICC), VSR 4
Administration Building at Western Harbour Crossing will have direct and full/partial views to the flyover structures.
Despite of the short distance, the
residual visual impacts on VSR 1 are considered to be slight and insubstantial
for workers at the lower and upper floors respectively.
Despite the structures of the flyover can be
seen from the south of the site, VSR 5 (Travellers arriving Western harbour
VSRs
located further away have partial views to the flyover structures and it is
considered that the residual visual impacts on these VSRs are insubstantial. Transient
VSRs such as VSR 5 Travellers Arriving
Western Harbour Crossing Toll Plaza, VSR
6 Travellers at the Footbridge Crossing the WHC Toll Plaza, VSR 7 Travellers at Yau Ma Tei Typhoon Shelter, and VSR 8 Travellers along Austin Road West only have glimpse views of the
flyover structures and therefore the residual visual impacts during operation
phase is insubstantial.
The Photomontages showing the flyover
structures are provided at Figure 15.10.11a to Figure 15.10.13b.
15.10.8 Environmental Monitoring and Audit
In addition to
ensure the effective implementation of mitigation measure recommended in Section 15.10.6 and compliance with
relevant environment standards; systematic procedures for monitoring, auditing
and minimizing the environmental impacts associated with construction and
operation phase is required.
During construction and operation phases,
monitoring programme are required to ensure that the Contractors and the
Operators could properly carry out mitigation measures and evaluate the actual
impact on landscape and visual amenity. This should be undertaken by a
Registered Landscape Architect (RLA), or capable person, as landscape auditor.
Corrective actions should be undertaken if there are unacceptable adverse
impacts.
15.10.9 Conclusion
The
WKCD is to be developed into a world-class integrated arts and cultural
district to enrich the arts and cultural life for the people in
It is considered that potential impacts on both landscape and visual amenity are unavoidable. The major sources of impacts include various construction activities and removal of existing trees during construction phase. Potential impacts have been considered during the preliminary design stage to avoid direct impacts on significant landscape resources and VSRs.
There
are 13 LRs, 10 LCAs, and 9 representative VSRs identified within the assessment
area that may be affected by the
construction of
In
addition to situating in an urban setting, the transport corridor type of
landscape character of the project site comprising the
Due to the scale of Austin Road flyover is small, the overall residual landscape and visual impacts associated with the construction and operation phases of the Austin Road flyover are anticipated to be acceptable with the implementation of appropriate mitigation measures and in the long term, the Project will be beneficial to the accessibility requirement of the planning context for the WKCD development.
15.11 Environmental and Monitoring Audit
15.11.1 Air Quality Impact
15.11.1.1 Construction Phase
Regular dust monitoring is considered necessary during the construction phase of the Project and regular site audits are also required to ensure the dust control measures are properly implemented. Details of the environmental monitoring and audit (EM&A) programme will be presented in the stand-alone EM&A Manual.
15.11.1.2 Operation Phase
Since it has been assessed that all the ASRs would be in compliance with all the relevant AQOs for SO2, NO2 and RSP, no residual air quality impacts due to vehicular or marine traffic emissions are anticipated. Therefore, no monitoring is considered necessary for vehicular or marine traffic emissions.
15.11.2 Noise Impact
15.11.2.1 Construction Phase
Though no residual noise impact is predicted during the construction of the flyover, an Environmental Monitoring and Audit (EM&A) programme is recommended to ensure that nearby NSRs will not be subjected to unacceptable construction noise impact. Details of the noise monitoring requirements, methodology and action plans would be described in a separate EM&A Manual.
15.11.2.2 Operation Phase
No monitoring is considered necessary.
15.11.3 Water Quality
Adverse
water quality impact was not predicted during the construction and operation
phases of the proposed flyover.
Nevertheless, appropriate mitigation measures are recommended to minimize
potential water quality impacts.
Water
quality monitoring is recommended to obtain a robust, defensible database of
baseline
Regular
audit of the implementation of the recommended mitigation measures during the
construction phase at the work areas should also be undertaken to ensure the
recommended mitigation measures are properly implemented.
Details of the water quality monitoring and audit programme and the Event and Action Plan are provided in the stand-alone EM&A Manual.
15.11.4 Sewerage and Sewage Treatment Implication
There are no sewerage and sewage treatment implications associated with the flyover.
15.11.5 Waste Management Implication
It will be the Contractor’s responsibilities to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and the relevant regulations and requirements. The recommended mitigation measures shall form the basis of the Waste Management Plan to be developed by the Contractor in the construction phase.
During construction phase, regular site inspection as part of the EM&A procedures should be carried out to determine if various types of waste are being managed in accordance with approved procedures and the Waste Management Plan. It should cover different aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal.
15.11.6 Land Contamination
There is no potential land contamination issues associated with the flyover.
15.11.7 Ecology Impact
The implementation of good site practices would
avoid and minimize any ecological impacts to an acceptable level. No specific
ecological monitoring programme is thus required for the flyover.
15.11.8 Landscape and Visual Impact
In addition to
ensure the effective implementation of mitigation measure recommended in Section 15.10.6 and compliance with
relevant environment standards; systematic procedures for monitoring, auditing
and minimizing the environmental impacts associated with construction and
operation phase is required.
During construction and operation phases,
monitoring programme are required to ensure that the Contractors and the
Operators could properly carry out mitigation measures and evaluate the actual
impact on landscape and visual amenity. This should be undertaken by a
Registered Landscape Architect (RLA), or capable person, as landscape auditor.
Corrective actions should be undertaken if there are unacceptable adverse
impacts.
15.12.1 Air Quality Impact
15.12.1.1 Construction Phase
With
implementation of the recommended mitigation measures as well as the relevant
control requirements as stipulated in the Air
Pollution Control (Construction Dust) Regulation and EPD’s Guidance Note on the Best Practicable Means
for Cement Works (Concrete Batching Plant) BPM 3/2(93), it has been
assessed that there would neither be exceedance of the hourly TSP limit under the Tier 2 mitigated
scenario nor exceedance of the AQO for daily TSP under the Tier 1 mitigated scenario at any of the ASRs throughout
the entire construction period. For
annual TSP results, no exceedance of the corresponding AQO was predicted at any
of the ASRs during the construction phase provided the recommended mitigation
measures are in place.
15.12.1.2 Operation Phase
Majority of the vehicular emission sources
and all marine emission sources are due to respectively the nearby current/planned
road networks serving the
According to the
modelling results, all the identified ASRs would be in compliance with the
corresponding AQO for hourly, daily and annual SO2; for hourly,
daily and annual NO2 as well as for daily and annual RSP. However, during the worst case year of 2015,
two existing ASRs, namely, SRT-1 and SRT-2, would be subject to exceedance of
the AQO for hourly NO2 (i.e., 300 μg/m3) by about 3.7-14.9 μg/m3 (or about 1.2%-5.0%
of the relevant AQO) for once a year, and one planned ASR, namely, P37-1, would be subject to
marginal exceedance of the AQO for daily NO2 (i.e., 150 μg/m3) by about 0.2 μg/m3 (or about 0.1% of
the relevant AQO) for once a year. Since
the numbers of such hourly and daily NO2 exceedances are within the respective
allowable numbers of exceedances (3 times per year for hourly NO2
and once per year for daily NO2), the AQO for hourly and daily NO2
would still be complied with at the three ASRs.
In conclusion,
no adverse air quality impacts due to vehicular or marine traffic emissions are
anticipated during the operation phase of the WKCD Project.
15.12.2 Noise Impact
15.12.2.1 Construction Phase
The construction phase noise impact
assessment has been made based on the best available information. The
construction noise levels at all representative NSRs are predicted to comply
with the noise standards stipulated in the
15.12.2.2 Operation Phase
The
potential road traffic noise impacts have been assessed based on the peak
traffic flows in 2032. The noise levels predicted at the representative NSRs
would range from 69 to 72 dB(A). Road traffic noise is
predicted to be dominant by the existing and committed Road Works at
15.12.3 Water Quality Impact
15.12.3.1 Construction Phase
The key issue in terms of water quality during the construction phase of the flyover would be the potential for release of wastewater into coastal waters from construction site runoff and drainage.
Deterioration in water quality could be minimised to acceptable levels through implementing adequate mitigation measures such as control measures on suspended solids release, on-site runoff and drainage from the works areas to minimise suspended solids spillage and construction runoff prior to discharge. Proper site management and good housekeeping practices would also be required to ensure that construction wastes and other construction-related materials would not enter the public drainage system and coastal waters. Sewage effluent arising from the construction workforce would also be handled through provision of portable toilets.
With the implementation of these recommended mitigation measures, no unacceptable impacts on water quality from the construction works for the flyover are anticipated. Water quality monitoring and site inspections during construction phase should be undertaken routinely to inspect the construction activities and works areas to ensure the recommended mitigation measures are properly implemented.
15.12.3.2 Operation Phase
Surface runoff from the proposed
flyover may be contaminated by oils leaked from passing vehicles. It is
considered that impacts upon water quality will be acceptable provided that the
proposed flyover is designed with adequate drainage systems and appropriate oil
interceptors, as required in accordance with Highways Department Guidance Notes RD/GN/035 – Road Pavement Drainage
Design.
15.12.4 Sewage and Sewage Treatment Implication
There are no sewerage and sewage treatment implications associated with the flyover.
15.12.5 Waste Management Implication
15.12.5.1
Construction Phase
The major waste types generated by the construction activities will include inert C&D materials from minor excavation at piers and abutments as well as from construction of superstructures and substructures; C&D materials from general site clearance; chemical waste from maintenance and servicing of construction plant and equipment; and general refuse from the workforce. Provided that all these identified wastes are handled, transported and disposed of in strict accordance with the relevant legislative and recommended requirements and that the recommended good site practices and mitigation measures are properly implemented, no adverse environmental impact is expected during the construction phase.
15.12.5.2 Operation Phase
During
operation phase, the
15.12.6 Land Contamination
There is no potential land contamination issues associated with the flyover.
15.12.7 Ecology Impact
The findings from the field survey and
desktop review indicated that the major terrestrial habitats in the Study Area
are developed area, open field and plantation, with small amount of sloping
seawall along the coastline. All these habitats are with low vegetation cover,
short planting history and of low to very low ecological value. Therefore,
direct ecological impact on loss of habitat is considered to be of
insignificant. The indirect disturbance impact to offsite habitat is considered
to be of insignificant in both construction and operation phases, since the proposed
flyover is surrounded by urbanized area. The plantation and landscape planting
included in the development plan would have potential positive contribution to
the local ecology.
15.12.8 Landscape and Visual Impact
The
WKCD is to be developed into a world-class integrated arts and cultural
district to enrich the arts and cultural life for the people in
It is considered that potential impacts on both landscape and visual amenity are unavoidable. The major sources of impacts include various construction activities and removal of existing trees during construction phase. Potential impacts have been considered during the preliminary design stage to avoid direct impacts on significant landscape resources and VSRs.
There
are 13 LRs, 10 LCAs and 9 representative VSRs identified within the assessment
area that may be affected by the
construction of
In
addition to situating in an urban setting, the transport corridor type of
landscape character of the project site comprising the
Due to the scale of Austin Road flyover is small, the overall residual landscape and visual impacts associated with the construction and operation phases of the Austin Road flyover are anticipated to be acceptable with the implementation of appropriate mitigation measures and in the long term, the Project will be beneficial to the accessibility requirement of the planning context for the WKCD development.
The implementation schedule for the mitigation measures to be implemented under this Project is presented in Table 15.11.1.
Table 15.11.1: Implementation Schedule
|
|
|
|
|
Implementation Stage1 |
|
|||||||||
EIA Ref. |
EM&A Ref. |
Environmental Protection Measures |
Location / Duration of measures / Timing of completion of measures |
Implementation Agent |
Des |
Con |
Op |
Dec |
Relevant Legislation & Guidelines |
||||||
Air
Quality Impact (Construction) |
|||||||||||||||
15.3.6.1 |
|
General
Dust Control Measures Frequent water spraying for active construction areas (12 times a day or once every one hour), including Heavy construction activities such as construction of buildings or roads, drilling, ground excavation, cut and fill operations (i.e., earth moving) |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA Recommendation and Air Pollution Control (Construction Dust) Regulation |
||||||
15.3.6.1 |
|
Best
Practice For Dust Control The relevant best practices for dust
control as stipulated in the Air Pollution Control (construction Dust)
Regulation should be adopted to further reduce the construction dust impacts
from the Project. These best practices include: Good Site Management ¡ Good
site management is important to help reducing potential air quality impact
down to an acceptable level. As a general guide, the Contractor should
maintain high standard of housekeeping to prevent emission of fugitive dust.
Loading, unloading, handling and storage of raw materials, wastes or
by-products should be carried out in a manner so as to minimise the release
of visible dust emission. Any piles of materials accumulated on or around the
work areas should be cleaned up regularly. Cleaning, repair and maintenance
of all plant facilities within the work areas should be carried out in a
manner minimising generation of fugitive dust emissions. The material should
be handled properly to prevent fugitive dust emission before cleaning. Disturbed Parts of the Roads ¡ Each
and every main temporary access should be paved with concrete, bituminous
hardcore materials or metal plates and kept clear of dusty materials; or ¡ Unpaved
parts of the road should be sprayed with water or a dust suppression chemical
so as to keep the entire road surface wet. Exposed Earth ¡ Exposed
earth should be properly treated by compaction, hydroseeding, vegetation
planting or seating with latex, vinyl, bitumen within six months after the
last construction activity on the site or part of the site where the exposed
earth lies. Loading, Unloading or Transfer of Dusty
Materials ¡ All
dusty materials should be sprayed with water immediately prior to any loading
or transfer operation so as to keep the dusty material wet. Debris Handling ¡ Any
debris should be covered entirely by impervious sheeting or stored in a
debris collection area sheltered on the top and the three sides. ¡ Before
debris is dumped into a chute, water should be sprayed so that it remains wet
when it is dumped. Transport of Dusty Materials ¡ Vehicle
used for transporting dusty materials/spoils should be covered with tarpaulin
or similar material. The cover should extend over the edges of the sides and
tailboards. Wheel washing ¡ Vehicle
wheel washing facilities should be provided at each construction site exit.
Immediately before leaving the construction site, every vehicle should be
washed to remove any dusty materials from its body and wheels. Use of vehicles ¡ The
speed of the trucks within the site should be controlled to about ¡ Immediately
before leaving the construction site, every vehicle should be washed to
remove any dusty materials from its body and wheels. ¡ Where
a vehicle leaving the construction site is carrying a load of dusty
materials, the load should be covered entirely by clean impervious sheeting
to ensure that the dusty materials do not leak from the vehicle. Site hoarding ¡ Where a site boundary adjoins a road, street, service lane or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length of that portion of the site boundary except for a site entrance or exit. |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA Recommendation and Air Pollution Control (Construction Dust) Regulation |
||||||
15.3.6.1 |
|
Best Practicable Means for Cement Works
(Concrete Batching Plant) The relevant best practices for dust control as stipulated in the Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) should be followed and implemented to further reduce the construction dust impacts of the Project. These best practices include: Exhaust from Dust Arrestment Plant ¡
Wherever possible the final discharge point from particulate matter
arrestment plant, where is not necessary to achieve dispersion from residual
pollutants, should be at low level to minimise the effect on the local
community in the case of abnormal emissions and to facilitate maintenance and
inspection Emission Limits ¡
All emissions to air, other than steam or water vapour, shall be
colourless and free from persistent mist or smoke Engineering Design/Technical Requirements ¡ As
a general guidance, the loading, unloading, handling and storage of fuel, raw
materials, products, wastes or by-products should be carried out in a manner
so as to prevent the release of visible dust and/or other noxious or
offensive emissions |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIA recommendation; Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) |
||||||
Air
Quality Impact (Operation) |
|||||||||||||||
|
|
No
mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Noise
Impact (Construction) |
|||||||||||||||
15.4.6 |
|
Good Site
Practice Good
site practice and noise management can significantly reduce the impact of
construction site activities on nearby NSRs. The following package of
measures should be followed during each phase of construction: ¡ only
well-maintained plant to be operated on-site and plant should be serviced
regularly during the construction works; ¡ machines
and plant that may be in intermittent use to be shut down between work
periods or should be throttled down to a minimum; ¡ plant
known to emit noise strongly in one direction, should, where possible, be
orientated to direct noise away from the NSRs; ¡ mobile
plant should be sited as far away from NSRs as possible; and ¡ material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||
15.4.6 |
|
Adoption of
Quieter PME The
recommended quieter PME adopted in the assessment were taken from EPD’s QPME Inventory and “Sound Power Levels of Other Commonly Used PME”.
It should be noted that the silenced PME selected for assessment can be found
in |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||
15.4.6 |
|
Use of Movable
Noise Barriers Movable
noise barriers can be very effective in screening noise from particular items
of plant when constructing the Project. Noise barriers located along the
active works area close to the noise generating component of a PME could
produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile
plant provided the direct line of sight between the PME and the NSRs is
blocked. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||
15.4.6 |
|
Use of Noise
Enclosure/ Acoustic Shed The
use of noise enclosure or acoustic shed is to cover stationary PME such as
air compressor and concrete pump. With the adoption of the noise enclosure,
the PME could be completely screened, and noise reduction of 15 dB(A) can be achieved according to the EIAO Guidance Note
No.9/2010. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||
15.4.6 |
|
Use of Noise
Insulating Fabric Noise
insulating fabric can also be adopted for certain PME (e.g. drill rig,
pilling machine etc). The fabric should be lapped such that there are no
openings or gaps on the joints. According to the approved Tsim Sha Tsui
Station Northern Subway EIA report (AEIAR-127/2008), a noise reduction of 10 dB(A) can be achieved for the PME lapped with the noise
insulating fabric. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO and Noise Control Ordinance |
||||||
Noise
Impact (Operation) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Water
Quality Impact (Construction) |
|||||||||||||||
15.5.5.1 |
|
Construction
site runoff and drainage The site practices outlined in ProPECC Note PN 1/94 should be followed as far as practicable in order to minimise surface runoff and the chance of erosion. The following measures are recommended to protect water quality and sensitive uses of the coastal area, and when properly implemented should be sufficient to adequately control site discharges so as to avoid water quality impacts: ¡ At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels, earth
bunds or sand bag barriers should be provided on site to direct storm water
to silt removal facilities. The design of the temporary on-site drainage
system should be undertaken by the WKCDA’s Contractor prior to the
commencement of construction; ¡ Sand/silt
removal facilities such as sand/silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements
of the TM standards under the WPCO.
The design of efficient silt removal facilities should be based on the
guidelines in Appendix A1 of ProPECC Note PN 1/94. Sizes may vary depending upon the flow
rate. The detailed design of the sand/silt traps should be undertaken by the
WKCDA’s Contractor prior to the commencement of construction. ¡ All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation
at all times and particularly during rainstorms. Deposited silt and grit
should be regularly removed, at the onset of and after each rainstorm to
ensure that these facilities are functioning properly at all times. ¡ Measures
should be taken to minimize the ingress of site drainage into excavations. If
excavation of trenches in wet periods is necessary, they should be dug and
backfilled in short sections wherever practicable. Water pumped out from
foundation excavations should be discharged into storm drains via silt
removal facilities. ¡ All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An
adequately designed and sited wheel washing facility should be provided at
construction site exit where practicable. Wash-water should have sand and
silt settled out and removed regularly to ensure the continued efficiency of
the process. The section of access road leading to, and exiting from, the
wheel-wash bay to the public road should be paved with sufficient backfall
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains. ¡ Open
stockpiles of construction materials or construction wastes on-site should be
covered with tarpaulin or similar fabric during rainstorms. Measures should
be taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system. ¡ Manholes
(including newly constructed ones) should be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris
being washed into the drainage system and stormwater runoff being directed
into foul sewers. ¡ Precautions
should be taken at any time of the year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecasted and actions to be
taken during or after rainstorms are summarized in Appendix A2 of ProPECC
Note PN 1/94. Particular attention
should be paid to the control of silty surface runoff during storm events,
especially for areas located near steep slopes. ¡ Bentonite
slurries used in piling or slurry walling should be reconditioned and reused
wherever practicable. Temporary enclosed storage locations should be provided
on-site for any unused bentonite that needs to be transported away after all
the related construction activities are completed. The requirements in
ProPECC Note PN 1/94 should be adhered to in the handling and disposal of
bentonite slurries. |
Within WKCD site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||
15.5.5.1 |
|
Sewage effluent from construction workforce Temporary
sanitary facilities, such as portable chemical toilets, should be employed
on-site where necessary to handle sewage from the workforce. A licensed
contractor should be employed to provide appropriate and adequate portable toilets
and be responsible for appropriate disposal and maintenance. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||
15.5.5.1 |
|
General construction activities Construction solid
waste, debris and refuse generated on-site should be collected, handled and
disposed of properly to avoid entering any nearby storm water drain.
Stockpiles of cement and other construction materials should be kept covered
when not being used. Oils
and fuels should only be stored in designated areas which have pollution
prevention facilities. To prevent spillage of fuels and solvents to any
nearby storm water drain, all fuel tanks and storage areas should be provided
with locks and be sited on sealed areas, within bunds of a capacity equal to
110% of the storage capacity of the largest tank. The bund should be drained
of rainwater after a rain event. |
Within WKCD site / During construction phase / Prior to commencement of operation |
Contractor appointed by WKCDA |
|
P |
|
|
ProPECC Note PN 1/94 |
||||||
Water
Quality Impact (Operation) |
|||||||||||||||
15.5.5.2 |
|
Road
and surface runoff For operation of the proposed WKCD development and associated local road network, a surface water drainage system would be provided to collect road and surface runoff. It is recommended that the road drainage should be provided with adequately designed silt trap and oil interceptors, as necessary. The design of the operation stage mitigation measures for the proposed WKCD development and associated local road network should take into account the guidelines published in the Practice Note for Professional Persons on Drainage Plans Subject to Comment by the Environmental Protection Department (ProPECC Note PN 5/93) and Highways Department Guidance Notes RD/GN/035 – Road Pavement Drainage Design. |
Within WKCD site / During operation phase / Throughout operation phase |
HyD (for exclusive road drains) |
|
|
P |
|
ProPECC Note PN 5/93, Highways Department Guidance Notes RD/GN/035 |
||||||
Sewerage
and Sewage Treatment Implications (Design) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Sewerage
and Sewage Treatment Implications (Operation) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Waste
Management Implications (Construction) |
|||||||||||||||
15.7.4.1 |
|
Good Site Practices Recommendations for good site practices during the
construction activities include: ¡
Nomination of an
approved person, such as a site manager, to be responsible for good site
practices, arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site ¡
Training of site
personnel in proper waste management and chemical handling procedures ¡
Provision of
sufficient waste disposal points and regular collection of waste ¡
Appropriate
measures to minimise windblown litter and dust/odour during
transportation of waste by either covering trucks or by transporting wastes
in enclosed containers ¡
Provision of wheel
washing facilities before the trucks leaving the works area so as to minimise
dust introduction to public roads ¡
Well planned delivery
programme for offsite disposal such that adverse
environmental impact from transporting the inert or non-inert C&D
materials is not anticipated |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance; Waste Disposal (Chemical Wastes) (General) Regulation; and Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site |
||||||
15.7.4.1 |
|
Waste Reduction Measures Recommendations to achieve waste reduction include: ¡
Sort inert C&D
materials to recover any recyclable portions such as metals ¡
Segregation and
storage of different types of waste in different containers or skips to enhance
reuse or recycling of materials and their proper disposal ¡
Encourage
collection of recyclable waste such as waste paper and aluminium cans by
providing separate labelled bins to enable such waste to be segregated from
other general refuse generated by the work force ¡
Proper site
practices to minimise the potential for damage or contamination of inert C&D
materials ¡
Plan the use of
construction materials carefully to minimise amount of waste generated and
avoid unnecessary generation of waste |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance |
||||||
15.7.4.1 |
|
Inert and
Non-inert C&D Materials In order to minimise impacts resulting from
collection and transportation of inert C&D materials for off-site disposal,
the excavated materials should be reused on-site as fill material as far as practicable. In addition, inert C&D
materials generated from excavation works could be reused as fill materials in local projects that require public fill for
reclamation. ¡
The surplus inert C&D
materials, if any, will be disposed of at the Government’s PFRFs for
beneficial use by other projects in ¡
Liaison with the
CEDD Public Fill Committee (PFC) on the allocation of space for disposal of
the inert C&D materials at PFRF will be initiated. No construction work
is allowed to proceed until all issues on management of inert C&D
materials have been resolved and all relevant arrangements have been endorsed
by the relevant authorities including PFC and EPD. ¡
The C&D materials
generated from general site clearance should be sorted on site to segregate
any inert materials for reuse or disposal of at PFRFs whereas the non-inert
materials will be disposed of at the designated landfill site. ¡
In order to monitor
the disposal of inert and non-inert C&D materials at respectively PFRFs
and the designated landfill site, and to control fly-tipping, it is
recommended that the Contractor should follow the Technical Circular (Works)
No.6/2010 for Trip Ticket System for Disposal of Construction &
Demolition Materials issued by Development Bureau. In addition, it is also recommended that
the Contractor should prepare and implement a Waste Management Plan detailing
their various waste arising and waste management practices in accordance with
the relevant requirements of the Technical Circular (Works) No. 19/2005
Environmental Management on Construction Site. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance ; Technical Circular (Works) No.6/2010 for Trip Ticket System for Disposal of Construction & Demolition Materials; and Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site |
||||||
15.7.4.1 |
|
Chemical Waste If chemical wastes are produced at the construction
site, the Contractor will be required
to register with the EPD as a chemical waste producer and to follow the
guidelines stated in the “Code of Practice on the Packaging Labelling and Storage of Chemical
Wastes”. Good
quality containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. Appropriate labels should
be securely attached on each chemical waste container indicating the
corresponding chemical characteristics of the chemical waste, such as
explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc.
The Contractor should use a licensed collector to transport and dispose of
the chemical wastes at the approved Chemical Waste Treatment Centre or other
licensed recycling facilities, in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation. Potential environmental impacts arising
from the handling activities (including
storage, collection, transportation and disposal of chemical waste) are
expected to be minimal with the implementation of appropriate mitigation measures as
recommended. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Code of Practice on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General) Regulation |
||||||
15.7.4.1 |
|
General Refuse General
refuse should be stored in enclosed bins or compaction units separated from inert
C&D materials. A reputable waste collector should be employed by the Contractor to remove general refuse from the
site, separately from inert C&D materials. Preferably an enclosed and
covered area should be provided to reduce the occurrence of 'wind blown'
light material. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
|
P |
|
|
Waste Disposal Ordinance and Public Health and Municipal Services Ordinance - Public Cleansing and Prevention of Nuisances Regulation |
||||||
Waste
Management Implications (Operation) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Land
Contamination (Construction) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Land
Contamination (Operation) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Ecological
Impact (Construction) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Ecological
Impact (Operation) |
|||||||||||||||
|
|
No mitigation measure is required. |
|
|
|
|
|
|
|
||||||
Landscape
and Visual Impact (Construction) |
|||||||||||||||
(CM1) |
|
Trees should be retained in situ on site as far as possible. Should tree removal be unavoidable due to construction impacts, trees will be transplanted or felled with reference to the stated criteria in the Tree Removal Applications to be submitted to relevant government departments for approval in accordance to ETWB TCW No. 29/2004 and 3/2006. |
WKCD construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by WKCDA |
P |
P |
|
|
ETWB TCW No. 29/2004 and 3/2006 |
||||||
(CM2) |
|
Compensatory tree planting shall be incorporated to the proposed project and maximize the new tree, shrubs and other vegetation planting to compensate tree felled and vegetation removed. Also, implementation of compensatory planting should be of a ratio not less than 1:1 in terms of quality and quantity within the site. |
|
Contractor appointed by WKCDA |
P |
P |
|
|
ETWB TCW No. 3/2006 |
||||||
Table 15.10.15 (CM3) |
|
Buffer trees for screening purposes to soften the hard architectural and engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||
(CM4) |
|
Softscape treatments such as vertical green wall panel /planting of climbing and/or weeping plants, etc, to maximize the green coverage and soften the hard architectural and engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Contractor
appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||
(CM7) |
|
Structure, ornamental planting shall be provided along amenity strips to enhance the landscape quality. |
Alongside superstructures within WKCD / After completion of superstructure construction / Prior to operation stage |
Contractor
appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||
15.10.15 (CM8) |
|
Landscape design shall be incorporated to engineering structures in order to provide aesthetically pleasing designs. |
WKCD structures / After completion of structure construction / Prior to operation stage |
Detailed
Design Consultant / Contractor appointed by WKCDA |
P |
P |
|
|
EIAO-TM |
||||||
(MMCP1) |
|
Use of decorative screen hoarding/boards |
WKCD construction sites / Throughout construction stage / Prior to operation stage |
Contractor appointed by WKCDA |
|
P |
|
|
ETWB TCW No. 3/2006 |
||||||
(MMCP2) |
|
Control of night time lighting. |
WKCD construction sites / During night time / Throughout construction stage |
Contractor appointed by WKCDA |
|
P |
|
|
EIAO-TM |
||||||
Landscape
and Visual Impact (Operation) |
|||||||||||||||
Table 15.10.16 (OM1) |
|
Provide proper planting establishment works, including watering, pruning, weeding, pest control, replacement of dead plant, etc, on the new planting areas to enhance the aesthetic design degree |
WKCD open areas / Throughout operation phase / As-needed basis |
Landscape Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||
(OM2) |
|
Provision of open
space in various forms and at different levels on or above ground, including
park, waterfront promenade, piazzas and terrace garden and associated green
connection for public enjoyment. |
WKCD open areas / Throughout operation
phase / As-needed basis |
Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||
(MMOP1) |
|
Integrated design of the flyover with the existing flyover located to the west of the Elements |
Project site of flyover/ During detailed design stage / Throughout operation phase |
Detailed Design Consultant appointed by WKCDA |
P |
|
P |
|
EIAO-TM |
||||||
(MMOP2) |
|
Softscape treatments such as climbers are proposed to be incorporated to soften the hard engineering structures and facilities. |
Alongside superstructures within WKCD / After completion of superstructure construction / Throughout operation stage |
Landscape Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||
(MMOP3) |
|
Compensatory planting in close proximity of the flyover structure |
In
close proximity of the project site/ After completion of
superstructure construction / Throughout operation stage |
Landscape Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||
(MMOP4) |
|
Lighting control measures such as careful considerations for the locations and the angle of the lighting. |
WKCD building exterior and open areas / During night time / Throughout operation stage |
Contractor appointed by WKCDA |
|
|
P |
|
EIAO-TM |
||||||
1 Des = Design; Con = Construction; Op = Operation; Dec
= Decommission
[1] http://www.epd.gov.hk/epd/english/environmentinhk/air/data/files/2011HKEIReport.pdf
[2] http://www.epd-asg.gov.hk/english/report/files/AQR2011e_final.pdf
[3] http://www.epd-asg.gov.hk/english/report/files/AQR2012_prelim_en.pdf
[4] Good Practice Guide for Atmospheric Dispersion
Modelling. Ministry
for the Environment,
[5] Starcrest Consulting Group, LLC, 2009. Rubber Tired Gantry (RTG) Crane Load Factor Study. Poulsbo: Starcrest Consulting Group, LLC.