Chapter 1 – Introduction
CONTENTS
1.3 Purpose and Objectives of this EIA
List of Figures
Figure 1-1 Site
Layout Plan
1.1.1
This Project is to
construct and operate a new offices-cum-vehicle depot building (the Depot) to accommodate the existing facilities in
Sai Yee Street Vehicle Depot. The Project Proponent
is the Food and Environmental Hygiene Department (FEHD), which is responsible
for the operation of the Project after completion of construction works. P&T Architect and Engineers Limited was
awarded as the lead consultant, for the design and construction supervision of
the Project. URS Hong Kong Limited was
appointed as the environmental sub-consultant to undertake the Environmental
Impact Assessment (EIA) study for this Project.
1.2.1
As mentioned in Section 1.1.1, this Project is to construct and operate a new offices-cum-vehicle
depot building to accommodate the existing
facilities in Sai Yee Street Vehicle Depot.
The Site is located on an urbanized area at Yen Ming Road. It is an area zoned as “Government, Institution or Community” use,
whilst commercial, residential and institutional uses are located nearby. The site location of this Project is shown in Figure 1-1. The Site constitutes an area of previously
developed reclaimed land which was occupied by Civil Engineering and Development Department (CEDD) as site offices and associated storage (just returned).
1.2.2
The proposed
offices-cum-vehicle depot building will be a five-storey building comprising
various facilities for vehicle washing and repair operation, parking of
vehicles as well as offices. It will
occupy a site area of about 8,278m2. A detailed description
of the Project is provided in Chapter 3.
1.2.3
In accordance with Item A.6, Part I, Schedule 2 of Environmental Impact Assessment (EIA) Ordinance, this Project is a
designated project under the category of “A transport depot located less than 200m from the nearest boundary of
an existing or planned residential area / educational institution. An EIA is required and an Environmental Permit
(EP) is to be obtained prior to construction commencement. An application for the EIA Study Brief under Section 5(1) of the
EIA Ordinance (EIAO) was submitted by the FEHD on 17 April 2012 with a Project
Profile (No. PP-463/2012). The EIA Study
Brief (No. ESB-245/2012) was issued by the Environmental Protection Department (EPD) on 25 May
2012 to proceed with an EIA study for the Project.
1.3
Purpose and Objectives of this EIA
1.3.1
This EIA Report was
prepared in accordance with the abovementioned EIA Study Brief (No. ESB-245/2012), the purpose of
this EIA study is to provide information on the nature and extent of the potential
environmental impacts arising from construction and
operation of the Project and associated works that will take place concurrently.
This information will contribute to the decisions by the EPD on:
·
The overall acceptability of any adverse
environmental consequences that are likely to arise as a result of the Project;
·
The conditions and requirements for the detailed
design, construction and operation of the Project to mitigate against adverse
environmental consequences wherever practicable; and
· The
acceptability of residual impacts after the proposed mitigation measures is
implemented.
1.3.2
According to the EIA Study Brief (No. ESB-245/2012),
the specific objectives of this EIA study are as follows:
·
To describe the Project and associated works
together with the requirements and environmental benefits for carrying out the
Project and the types of designated projects to be covered by the Project;
·
To identify and describe elements of community and
environment likely to be affected by the Project and/or likely to cause adverse
impacts to the Project, including natural and man-made environment and the
associated environmental constraints;
·
To provide information on the consideration of
alternative options of the Project including scale/size, extent, layout,
configuration/orientation, design and construction methods with a view to avoid
and minimise potential environmental impacts to the environmentally sensitive
areas and sensitive uses; to compare the
environmental benefits and dis-benefits of different options; to provide
reasons for selecting the preferred option(s) and to describe the part
environmental factors played in the selection of preferred option(s);
·
To identify and quantify emission sources,
including air and gaseous emission, noise emission, sewage and wastewater
emission, waste generation and land contamination, and determine the
significance of impacts on sensitive receivers and potential affected uses;
·
To identify any potential landscape and visual
impacts and to propose measures to mitigate these impacts;
·
To propose the provision of infrastructure or
mitigation measures so as to minimize pollution, environmental disturbance and
nuisance during construction and operation of Project;
·
To investigate the feasibility, practicability,
effectiveness and implications of the proposed mitigation measures;
·
To identify, predict and evaluate the residual
environmental impacts (i.e. after practicable mitigation) and the cumulative
effects expected to arise during the construction and operation phases of the
Project in relation to the sensitive receivers and potential affected uses;
·
To identify, assess and specify methods, measures
and standards, to be included in the detailed design, construction and
operation of the Project which are necessary to mitigate these environmental
impacts and cumulative effects and reduce them to acceptable levels;
·
To investigate the extent of the secondary
environmental impacts that may arise from the proposed mitigation measures and
to identify constraints associated with the mitigation measures recommended in
the EIA study, as well as the provision of any necessary modification; and
·
To design and specify environmental monitoring and
audit requirements to ensure the effective implementation of the recommended
environmental protection and pollution control measures.
1.4.1
The following
general principles and approaches for evaluating the potential environmental
impacts were adopted in this EIA study:-
Description of the Environment
1.4.2 The characteristics of the existing environment were described for the
identification and prediction of potential impacts which are likely to arise
from implementing the Project. Baseline
environmental surveys were conducted where
necessary and relevant reports / documents were reviewed to determine the
existing environmental conditions on the Project site and in all surrounding
areas likely to be affected by the Project.
Impact Prediction
1.4.3
Individual aspect
assessments were undertaken in accordance with the relevant guidelines on
assessment methodologies given in the Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM).
1.4.4
Similar methodologies
applied in the assessments have previously been adopted in other EIA studies in
Hong Kong, which have been generally accepted for use
in predicting environmental impacts and for the comparison of assessment
results with the EIAO-TM requirements. Limitations are however envisaged of these methodologies and the
accuracy of the prediction will be affected by the degree of uncertainty in
input data for quantitative assessments.
For example, base data for future conditions such as weather conditions,
which have to be considered during the formulation of assessment conclusions. These have been addressed by the adoption of
realistic but worst case assumptions have been made in order to provide a conservative assessment of environmental impacts. Where worst case assumptions have been used,
it would be stated in the assessment methodologies.
Impact Evaluation
1.4.5
The predicted changes and
effects resulting from the Project were evaluated with
respect to the criteria given in the EIAO-TM and were in
quantitative assessments as far as practicable.
Impact Mitigation
1.4.6
Mitigation measures have
been identified and evaluated to avoid, reduce and remedy the impacts. Priority was given to avoidance of impacts as
a primary means of mitigation. The
effectiveness of the proposed mitigation was assessed and the residual
environmental impacts were identified and considered for their acceptability.
1.4.7
An implementation schedule
for the mitigation measures was prepared to identify when and where each
mitigation measure is required, and to identify which parties are responsible
for its implementation and where necessary, for its maintenance.
1.5.1
The environmental issues
covered in this EIA study, as addressed in the EIA Study Brief (No.
ESB-245/2012), are as follows:
·
Potential air quality impact from the construction
and operation of the Project; potential air quality impact on the sensitive
receivers near the Project site from air pollutant emission sources (such as
vehicular emission, industrial emission from chimneys and odour emission
sources);
·
Potential noise impact on sensitive receivers
caused by the Project, including impact from construction equipment during
construction, operational noise impact from fixed noise sources, and
arrangement of traffic route;
·
Potential water quality and sewerage impacts from
the construction and operation of the Project;
·
Potential waste management implications and land
contamination issues arising from the construction and operation of the
Project;
·
Potential landscape and visual impacts during the
construction and operation of the Project; and
·
Potential cumulative environmental impacts of the
Project and associated works, through interaction or in combination with other
existing, committed and planned projects in their vicinity, and that those
impacts may have a bearing on the environmental acceptability of the Project.
1.6.1
This EIA Report comprises 12 chapters
including this introductory section, which described the background, purpose,
scope and approach of the EIA study. The
other sections are outlined below:
· Chapter
2 describes the consideration
of alternative schemes of the Project and the reasons for selecting the
preferred scheme and construction
methods. It also summarises the Project’s anticipated
environmental benefits;
· Chapter
3 presents the
Project site and its surrounding environment,
preliminary design of the Depot and the major activities in the Project;
· Chapter
4 identifies and
assesses the potential air quality impacts arising during the construction and
operation of the Project;
· Chapter
5 identifies and
assesses the potential construction and operational noise impacts arising from
the Project;
· Chapter
6 identifies and
assesses the potential water quality and sewerage impacts during the
construction and operation of the Project;
· Chapter
7 identifies and
assesses the potential waste management implications and land contamination
issues during the construction and operation of the Project;
· Chapter
8 identifies and
assesses the potential landscape and visual impacts arising during the
construction and operation of the Project;
· Chapter
9 summaries the
environmental outcomes arising from this Project;
· Chapter
10 defines the scope
of the EM&A requirements for the Project;
· Chapter
11 presents the
overall conclusion for this EIA Report; and
· Chapter
12 provides information on the implementation
of the mitigation measures.