Chapter 10 – Environmental Monitoring and Audit
Requirements
CONTENTS
10. Environmental Monitoring and Audit
Requirements
10.6 Waste Management and Land Contamination
List of Tables
Table 10-1 Summary of EM&A Requirements
10.1.1
Based on the assessment in previous chapters on various environmental
parameters, programme and methodologies for Environmental Monitoring and Audit
(EM&A) are recommended for evaluating the environmental performance and
compliance or implementing the Project.
This chapter summarises the requirements for EM&A. Details of the
EM&A programme are presented as part of this EIA report in a stand-alone
EM&A Manual which is formulated in accordance with Annex 21 of the EIAO-TM
and EPD’s EM&A Guidelines for Development Projects in Hong Kong.
10.1.2
The EM&A programme provides systematic procedures for monitoring,
auditing and minimising of the environmental impacts associated with the
construction and operation of the Project. Major objectives of the EM&A
includes:-
·
To ensure
compliance with the EIA study recommendations and regulatory requirements,
standards and government policies;
·
To enhance the
effectiveness of recommended on-site mitigation measures through monitoring and auditing;
·
To allow early
warning for impact prevention or minimisation;
·
To identify
any further need for additional mitigation measures or remedial action to redress unacceptable or unanticipated
environmental impacts;
·
To determine
the scope and extent of remedial action if any exceedance
of environmental compliance.
10.1.3
All EM&A data, assessment and recommendations would be reported in a
series of regular EM&A reports during the next phases of this Project.
10.2.1
All recommended mitigation measures in the EIA study will be
incorporated in an EM&A programme during implementation. This will enable
the Contractor to have early warning and provide necessary action to reduce
impacts at specific areas if the critical assessment criteria are
approached. Table 10-1 summaries the EM&A
requirements of each environmental parameters.
Table 10-1 Summary of
EM&A Requirements
Parameters |
Construction
Phase |
Operational
Phase |
||
Monitoring |
Audit |
Monitoring |
Audit |
|
Air Quality |
- |
ü |
ü |
- |
Noise |
ü |
ü |
- |
- |
Water Quality |
- |
ü |
- |
- |
Waste and Land Contamination |
- |
ü |
- |
- |
Landscape and Visual |
- |
ü |
- |
- |
10.2.2
Details of the recommended mitigation measures, monitoring procedures
and locations are presented in a stand-alone Environmental Monitoring and Audit
(EM&A) Manual.
Construction Phase
10.3.1
No adverse dust impact would be anticipated at the ASRs with the
implementation of sufficient dust suppression measures as stipulated under the
Air Pollution Control (Construction Dust) Regulation and good site
practices. Regular site
environmental audits during the construction phase of the Project as specified
in the EM&A Manual should be conducted to ensure the recommended dust
suppression measures are implemented.
Operational phase
10.3.2
The results of the operational air quality impact assessment related to
vehicular emissions indicate that no adverse impact would be expected from the
operation of the Project. Therefore, the EM&A works related to traffic air
quality for the operational phase is not considered as
necessary.
10.3.3
In order to ensure the odour removal efficiency (at least 85%) of the proposed odour removal
unit, commissioning test requirement should be incorporated in the
specification during commissioning period.
10.3.4
Upon commissioning, odour removal efficiency of the proposed odour
removal unit should be tested quarterly for the first year of operation, in
order to ensure adequate maintenance and operation of the unit. If all results fulfil the above minimum requirement,
the monitoring programme would be ceased. If failure, the programme shall be
increased to monthly monitoring and extended until in consecutive 3 times
fulfilling the requirement. Most
importantly, it is critical and necessary to carry out investigation to examine
rationale(s) (eg. airduct
blockage) for failure, suggest and implement effective rectifying action(s) (eg. increasing frequency of media replacement). Since the design is subject to later
modification, it is recommended the Project Proponent to develop a monitoring
and investigation plan, as well as work procedure, prior to operation of the
unit.
Construction Phase
10.4.1 The assessment has concluded that, with the
implementation of mitigation measures in form of utilising quieter plant,
limiting the number of construction plants operating concurrently, temporary
noise barrier, noise jackets and mufflers, no adverse residual construction
impact would be anticipated.
10.4.2 However, environmental monitoring and audit measures
are recommended during the construction phase of the Project to ensure adverse
impacts do not occur. An appropriate path for noise complaints handling
procedures is a key element of the EM&A programme. Detailed implementation schedules of all
mitigation measures are also provided in the EM&A Manual.
Operation
Phase
10.4.3 Noise monitoring during the operation phase is
considered not necessary as the proposed Depot would not be expected to result
in significant noise impact to adjacent
identified NSRs with the implementation of the recommended mitigation measures.
10.5.1
The implementation of good construction works practices as well as the
various specific mitigation measures recommended above will be important to
prevent the pollution of marine water during the construction phase. It is, therefore, recommended that
construction activities should be subject to a routine audit programme
throughout the construction period.
Further details on the scope of this audit are provided in the EM&A
Manual. No operational phase
EM&A for water quality is considered required.
10.6
Waste Management and Land Contamination
10.6.1
It is recommended that regular auditing by an Environmental Team should
be carried out during the construction phase of the Project to ensure waste are
being managed with the appropriate procedures or practices in accordance to
relevant legislation and waste management guidelines as well as those
recommended in this EIA Report. The
audits will examine all aspects of waste management including waste generation,
storage, recycling, transport and disposal.
10.6.2
A Waste Management Plan (WMP), as part of Environmental Management Plan
(EMP), should be prepared in accordance with ETWB TC(W)
No.19/2005 and submitted to the Project/ Site Engineer for approval. The recommended mitigation measures
should form the basis of the WMP.
The monitoring and auditing requirement stated in ETWB TC(W) No.19/2005 should be followed with regard to the
management of C&D Materials.
10.6.3
As the land contamination at the Site was identified to be insignificant
during construction and operation phases with the implementation of good site
practice and design, no EM&A for contaminated land is recommended.
Construction Phase
10.7.1
Given the limited footprint of the proposed Depot, no significant
impacts on the identified LRs and LCAs will be anticipated except for impacts
on LR 5-3 Vacant Land Vegetation and LCA 4 Open Space/Vacant Land due to
felling of 15 common trees of the Site.
Construction site hoardings should be erected to surround the site to
minimise the landscape and visual impacts on viewers from road level. No monitoring is recommended during the
construction phase.
Operation Phase
10.7.2
The Project will result in the felling of 15 trees within the Site. The landscape design as mentioned in Sections 8 are adopted as mitigation measures to compensate for the trees lost,
which is proposed to plant 27
nos. compensatory trees of heavy standard
size (100mm DBH) on-grade and on 3/F,
exceeding minimum compensatory
requirements as per the Circular in accordance with ETWB TC(W)
No. 3/2006 i.e. in a compensatory ratio not less than 1:1 in terms of both
quality and
quantity. Planting of these trees would be
completed before the completion of construction work of the Project. Approval on tree felling would be
obtained from the relevant government departments including Lands
Department. The compensatory
plantings would be implemented and any necessary monitoring of the compensatory
planting after establishment would be conducted (if required) according to the
tree felling approval conditions as required by the approval authorities.