Chapter 11 – CONCLUSIONS
CONTENTS
11.5 Waste Management Implication and Land
Contamination
11.6 Landscape and Visual Impacts
11.1.1
This EIA Report has provided an assessment of the potential
environmental impacts associated with the construction and operation of a new
offices-cum-vehicle depot building to accommodate the existing facilities in
Sai Yee Street FEHD Vehicle Depot (the Depot), based on the design information
available. The EIA has been
conducted, in accordance with the EIA Study Brief No: ESB-245/2012 issued under
the EIAO for this Project. The
findings of this EIA study have determined the likely nature and extent of
environmental impacts predicted to arise from the construction and operation of
the Project. During the EIA
process, environmental control measures were identified and incorporated into
the planning and design of the Project to achieve the compliance with
environmental legislation and standards during both the construction and
operation phases. The Environmental
Mitigation Implementation Schedules are presented in Chapter 12 of this EIA Report.
Details of individual environmental aspects are summarised below.
11.2.1
There would be no major earthworks carried out for the site formation
works for the Project site during construction phase. With the implementation of sufficient
dust suppression measures as stipulated under the Air Pollution Control
(Construction Dust) Regulation, adverse construction dust impact would not be
anticipated.
11.2.2
For the operation of the Depot, no adverse air quality impacts would be
anticipated as there would be limited vehicular emissions from the repairing
and parking activities of the Project, considered with cumulative effect of emissions from open roads
networks within the Study Area (500m from Project boundary). Results show that the predicted maximum
1-hour, daily and annual average NO2 and maximum daily and annual
average RSP concentrations at the representative ASRs and within the Study Area
would comply with the AQOs. No
mitigation measures are required.
11.2.3
Considering the fact that potential odour emission and minimal spread in
the Depot to be localised only in the washing bays, together with the provision
of mechanical ventilation adopting with proper installation and maintenance of deodourisation system, potential odour nuisance associated
with the operation of the Depot is anticipated to be negligible.
11.3.1
With the implementation of the recommended mitigation measures such as
the use of QPME employed in the works, temporary noise barriers, noise jackets,
mufflers, and limiting the number of plants operated concurrently, adverse
construction noise impact is not anticipated. Despite
any description or assessment made in this EIA report on construction noise
aspects, the Noise Control Authority will take into account of contemporary
conditions / situations of adjoining land uses and at the site before making
his decision in granting a CNP for construction works within restricted hours
as guided by the relevant Technical Memoranda issued under the NCO.
11.3.2
Concerning fixed plant noise during operation of the Project, with the
implementation of the mitigation measures for both workshop vehicle repair
activities and MVAC installation such as workshop vehicle repair activities to
be carried out under the covered area to be operated during daytime and evening
periods only and acoustic treatments, such as acoustic silencers, acoustic louvres to be applied to the MVAC installations in order to
achieve the specified maximum allowable SWL, adverse impact to the NSRs due to
the fixed plant noise would not be anticipated during operation phase.
11.3.3
For off-site traffic noise, based on the insignificant off-site traffic
generation and routings for the Project development, the assessment results
demonstrate that the operation of the FEHD Depot would introduce insignificant
traffic noise impact on all representative NSRs for short-term and in the long
run.
11.4.1
Potential water pollution sources have been identified as construction
site run-off, sewage from workforce, and potential risk of chemical
spillage. Mitigation measures
including the implementation of the construction site practices in accordance
with the EPD’s ProPECC PN 1/94 Construction Site
Drainage, provision and management of portable toilets on-site, and preventive
measures to avoid accidental chemical spillages are recommended to mitigate any
adverse water quality impacts, based on which adverse residual impacts would
not be anticipated. Furthermore, there
would be insignificant sewerage and sewage treatment implications during the
operation of this Project, and adverse water quality impact would not be
anticipated with the implementation of the recommended mitigation measures
based on the findings of this EIA study.
11.5 Waste Management Implication and Land Contamination
11.5.1
Waste to be generated during construction phase has been examined in
terms of quantity, type and nature etc.
Opportunities for minimising waste generation via on-site sorting and
reusing excavated fill materials are identified. Preventive measures have been
recommended to implement during the construction phase to address any potential
environmental impacts.
11.5.2
The waste streams that would be generated during the operation phase of
the Project were also identified and evaluated. Measures to ensure proper treatment and
disposal of these wastes have been made.
11.5.3
With regard to the historical land uses and current site condition,
there was no sign of land contamination due to the past and current activities
at the Site. For the future operation,
as the Site will be paved and good practice for storage and handling of limited
DGs, chemicals and chemical wastes will be followed, leakage of contaminants
causing quantifiable adverse land contamination impacts would therefore not be
anticipated.
11.5.4
Provided that the recommendations set out above are implemented,
unacceptable environmental impacts would not be expected to arise from the
handling, storage, transportation and disposal of wastes and chemicals during
both the construction and operation of the Project.
11.6 Landscape and Visual Impacts
11.6.1
With the implementation of mitigation measures such as control of
construction activities and temporary landscape treatment during construction
phase, the proposed Depot will inevitably result in some landscape impact but
no adverse visual impact during the construction phase. On the contrary, ground floor planting,
vertical greening and roof gardens will be provided for the proposed Depot
during operation phase. Both landscape and visual impact would become negligible
in Year 10 when the mitigation measures are already established.
11.6.2
Comparing with the original setting of the Site before the proposed
Project where undesirable and weedy species are located at the Site, the
overall landscape character and visual quality of the Site would be improved,
with the provision of landscape design including ground floor planting at
pedestrian zone, vertical greening and roof gardens for the proposed
Depot. The landscape and visual
character of the Site have been complemented and therefore landscape and visual
impact arising from the proposed Depot is considered as beneficial.