Chapter 2 – Consideration of Alternatives
CONTENTS
2. Consideration of Alternatives
2.4 “Without Project” Alternative
List of Figures
Figure 2-1 Location
Plan of Alternative Site
Figure 2-2 Location
Plan of Alternative Routings
2.1.1
Options and
alternatives have been considered in this Project for refinement and selection
of the preferred option for the Depot to be taken forward
for the EIA and detailed design. Details of the options considered and constraints
assessed in adopting the preferred scheme have been reviewed, including
alternative site, designs and construction methodologies. The review has also taken into account
engineering feasibility, site conditions, programme
aspects and environmental considerations with a view to identifying the optimum
arrangement.
2.1.2
This Section is prepared in
accordance with Section 3.3.1 of the EIA Study Brief (No. ESB-245/2012).
2.2.1
The existing Sai Yee Street
Vehicle Depot in Mong Kok has
to be demolished as the land
of the Site is scheduled to be returned to Lands Department by
March 2017. FEHD therefore requires a land piece for housing the
existing facilities in Sai Yee Street Vehicle Depot.
2.2.2
The proposed offices-cum-vehicle depot building at Yen
Ming Road aims to replace these facilities and to carry out vehicle washing and
repairing services for the FEHD fleet in the district and their parking
when they are not in operation.
2.3.1
As discussed in Section 1.2.1, the Project is located on an urbanised area at Yen Ming Road, which is a land piece zoned as “Government, Institution or Community” use,
whilst commercial, residential and institutional uses are located in the proximity. The Site constitutes an area of previously
developed reclaimed land which was recently occupied by CEDD as site offices
and associated storage (being returned). The site location of
this Project is shown in Figure 1-1.
2.3.2
In the early planning stage
of the Project, site searching process was carried out and 2 potential sites in
the district were identified by FEHD and shortlisted for evaluation, which are:
Site A – land piece
at Yen Ming Road; and
Site B – land piece
at Ngong Shung Road
and are indicated in Figure 2-1.
2.3.3
Compare to Site B, Site A
is more accessible by the public and convenient to continue timely
environmental hygiene services to the local districts, and thus preferred in
view of providing public services.
Also, Site B was occupied by Drainage Services Department for a sewage
pumping station and therefore the site is now not available.
2.3.4
Furthermore, re-provision at the original Sai
Yee Street site (eg. in form of basement) is screened
out because of technical feasibility / preferences and lack of site for
temporary reprovisioning to maintain the required
services.
2.4
“Without Project”
Alternative
2.4.1
A fundamental Project alternative is the option not to
construct the new offices-cum-vehicle depot building at Yen Ming Road, which is
referred to as the “Do-nothing” option in environmental terms. As spelt out in Section 2.2, the Site is scheduled to be
returned to Lands Department by March 2017 whilst continuation of the
vehicle repairing and maintenance services of the existing Sai
Yee Street Vehicle Depot as well as the washing service of the new depot is
crucial to ensure the vehicles are clean, hygienic and under normal and safe
operation in the FEHD fleet of West Kowloon region including Sham Shui Po, Mongkok, Yau Ma Tei and Tsim Sha Tsui
districts.
2.4.2
The existing depot in Sai
Yee Street is the only depot currently for repairing and maintenance of the
FEHD vehicle fleet in the region. In the absence of this proposed depot, the
vehicle fleet of the said region would have to depend upon the services
provided by other depot(s) in the surrounding region, which in turn demands longer travelling distance and
time and, hence, lead to other off-site environmental impacts on the existing
road networks, including traffic congestion, noise and vehicular emissions.
2.4.3
Taking the above reasons into accounts, the “Do-nothing”
option is not preferred and not considered to be an environmentally preferred
solution to cope with the current demand of the washing, repairing and
maintenance of the FEHD vehicles fleet of the region.
2.5.1
The following design options were considered and reviewed in order to optimise
the operational and environmental benefits of the facility:
Form
2.5.2
The Project aims to reprovision of the existing facilities, including all
offices, stores, workshop, etc, in Sai Yee Street Vehicle Depot at the new
site. The form of Project was
reviewed to examine whether separating offices from other facilities would be a
preferred options.
2.5.3
Considering
and taking a balance between various factors, including objectives, availability,
convenience to the public, operability, etc, it is
preferred for a combined option (ie.
offices-cum-vehicle depot) rather than a separation form (ie.
a site for offices whilst depot is at another location).
Building Design
2.5.4
To minimise the potential environmental
impacts, in particular on noise and air quality perspectives, different forms
of building have been considered and eventually non-open form was preferred for
vehicle repairing and washing activities, which are now to be located at ground
floor and refined and covered by the above floors.
Facilities Layout
2.5.5 Layout design was
investigated in details in order to strike the balance between operational
needs, as well as catering environmental considerations. Activities with potential environmental
implication / nuisance were located in a confined manner as possible.
2.5.6 Vehicle repairing
bays and workshop is proposed to be covered at ground floor, surrounded by
storerooms for noise screening and buffering purpose as possible. In addition, solid partition wall is
proposed to the manual vehicle washing bays to entirely isolate the pedestrian
from potential nuisance.
2.5.7 Moreover, to enhance
the visual quality of the Depot, substantial greenery features were considered,
including vertical green walls and green roofing.
Ventilation
and Local Exhaust Design
2.5.8 A vast amount of openings are proposed at the building façade to optimise the use of natural
ventilation at the car parking
area at lower floors. Mechanical ventilation is only designed for standby forced ventilation
system. As a result of rare usage
of the associated substantial mechanical ventilation system, potential noise
nuisance from this fixed plant system could be minimised.
2.5.9 On the other hand,
for those activities with potential environmental nuisance including vehicle
repairing activities at the workshop and vehicle washing, controlled mechanical
ventilation with sufficient forced air changes is desired, rather than merely
relying on natural ventilation. In
addition, ventilated exhaust is to be treated prior to discharging to the
atmosphere. Various gas treatments
were evaluated and the most appropriate technology with proven removal
efficiency (eg. activated carbon filter, bio-oxygen
generator, chemical scrubber) will be applied. Location and orientation of the local
exhaust were carefully examined to ensure sufficient dispersion and to avoid
direct impact to the nearby receivers.
Construction Method
2.5.10
Construction
of the Depot would involve various typical work stages and conventional
building services works. As such, consideration of alternative
construction method is focused on the design of
the foundation works. According to the ground condition of the Site,
two foundation types, namely driven steel-H piling (percussive) and bored
piling (non-percussive) are considered to be technically viable for the Project.
Steel-H
Driven Piling
2.5.11
Steel-H driven piling is a percussive piling method
and with the following advantages for the construction of the Project in term
of engineering / economic features:
·
Construction time required is relatively short;
·
The system has been proof tested to work well;
·
This technology is easily available;
·
Driven H-pile has the supporting capacity more suitable
for this kind of low rise buildings, higher flexibility in the pile
arrangement, enabling higher load/capacity; and
·
It is relatively the most cost effective pile
system.
2.5.12
In terms of environmental issues, driven steel
H-piling is anticipated to bring the following potential environmental
benefits:
·
Minimal waste is generated and fewer plants (e.g.
sedimentation tank, grouting machines) are required; and
·
With a shorter construction time, the potential
environmental impacts during the construction phase, e.g. construction dust,
noise, site effluent, C&D waste, etc would hence
be reduced.
Bored Piling
2.5.13
Bored piling is a non-percussive piling
method and with the following advantages for the construction of the Project in
term of engineering features:
·
Pile capacity is high. Suitable for medium to high rise
buildings;
·
Quality of pile can be controlled effectively; and
·
Common pile type in Hong Kong and most specialist
piling contractors are capable to install this pile type.
2.5.14
However, bored piling has the following disadvantages:
·
Commonly end-bearing piles founded in rock. Hence, it needs to reach deep bedrock
and with long pile length;
·
Relatively more expensive compared to driven-H
piling; and
·
Construction time is long (especially in rock) in
comparison to other pile types.
2.5.15
In terms of environmental issues, bored piling is anticipated to bring lower noise and vibration would be generated during
construction.
2.5.16
Although less noise and vibration
would be generated by bored piling during construction, as compared to steel-H
driven piling, the pile borehole diameter is normally large in size. The excavation would hence be
comparatively substantial and not cost effective
when compared to driven steel H-pile with smaller diameter pile. In view of the above, driven steel
H-pile would be considered to be more cost-effectiveness for the proposed
development.
2.5.17
On the other hand, as the Project site is currently
separated from noise sensitive receivers (including Sir Ellis Kadoorie Secondary School and Tai Kok
Tsui Catholic Primary School located across Hoi Fan
Road) by the existing CLP Tai Kok Tsui
Substation, noise impact of percussive piling system is considered to be
acceptable and it is anticipated that the noise criteria stipulated under the
current noise regulation would be fulfilled even for the closest school, which
is located over 80m away from the noise sources. With the implementation of the
appropriate noise mitigation measures during piling operation, the noise level
would further be reduced.
Traffic Routings
2.5.18
At the early stage of the Project, incoming and outbouding traffic routings were developed based on ease
and need of operation. During
project development and public engagement, local concerns on the proposed
traffic routings were received and thus modification to the routings were
considered necessary requiring substantial changes in order to address the
concerns.
2.5.19
As a
result of traffic assessment, alternative traffic routes as shown in Figure 2-2 were examined and proposed
in order to avoid utilizing those concerned junctions and roads, as possible.
2.6.1
Based on the above considerations of alternatives, a preferred
option has been selected in the Scheme and Preliminary Design phases of this
Project as summarised below, based on which the detailed design of this Project
will be proceeded and this EIA study was carried out:
·
Optimum design for building design, facilities
layout, ventilation and local exhaust design; and
·
Optimum construction method using steel-H driven
piling.
2.6.2
This preferred option is determined upon the
comparison of the feasibility in line with the environmental benefits and
dis-benefits of the various options and alternatives. It was also selected on the principal of
minimising the environmental impacts and optimizing
overall environmental benefits and acceptability over the other options.