Chapter 5 – Noise ImpAct Assessment

 

CONTENTS

5.     Noise Impact Assessment

5.1            Introduction

5.2            Environmental Legislation and Guidelines

5.3            Noise Sensitive Receivers

5.4            Identification of Potential Noise Impacts

5.5            Assessment Methodology

5.6            Prediction and Evaluation of Noise Impacts

5.7            Proposed Noise Mitigation Measures

5.8            Assessment of Noise Impacts with the Application of Mitigation Measures

5.9            Residual Impact

5.10         Environmental Monitoring and Audit

5.11         Conclusions

 

 

List of Tables

Table 5‑1             Area Sensitivity Rating Criteria Specified in the GW-TM

Table 5‑2             Basic Noise Levels (in Leq,30min, dB(A))

Table 5‑3             Acceptable Noise Levels for Percussive Piling Specified in the PP-TM

Table 5‑4             Acceptable Noise Level during Operational Phase

Table 5‑5             Road Traffic Noise Assessment Criteria Specified in the EIAO-TM

Table 5‑6             Summary of the Identified Existing and Planned NSRs near the Project

Table 5‑7             Identified Area Sensitivity Ratings of NSRs

Table 5‑8             Measured Prevailing Background Noise Levels for NSRs and Recommended Fixed Plant Noise Assessment Criteria

Table 5‑9             Summary of Selected Noise Assessment Points at Each Representative NSR

Table 5‑10           PME identified as Major Noise Sources

Table 5‑11           Summary of Workshop Equipment and Repair Activity

Table 5‑12           Estimated Quantity of Identified Fixed Plant Noise Sources

Table 5‑13           Summary of Anticipated Works of XRL

Table 5‑14           Predicted Cumulative Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Unmitigated Scenario

Table 5‑15           Predicted Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Unmitigated Scenario due to the Project ONLY

Table 5‑16           Summary of Predicted Operational Levels at NSRs

Table 5‑17           Year 2017 Traffic Forecast

Table 5‑18           Year 2032 Traffic Forecast

Table 5‑19           Predicted Noise Levels for “with project” and “without project” Scenarios during AM Peak Off-site Traffic of FEHD Depot (0700 – 0800) in Year 2017, L10,(1-hr)

Table 5‑20           Predicted Noise Levels for “with project” and “without project” Scenarios during PM Peak Off-site Traffic of FEHD Depot (1500 – 1600) in Year 2017, L10,(1-hr)

Table 5‑21           Predicted Noise Levels for “with project” and “without project” Scenarios during AM Peak Off-site Traffic of FEHD Depot (0700 – 0800) in Year 2032, L10,(1-hr)

Table 5‑22           Predicted Noise Levels for “with project” and “without project” Scenarios during PM Peak Off-site Traffic of FEHD Depot (1500 – 1600) in Year 2032, L10,(1-hr)

Table 5‑23           Maximum SWLs for Selected “Quiet” and Alternative Plants

Table 5‑24           Predicted Cumulative Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Mitigated Scenario

Table 5‑25           Predicted Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Mitigated Scenario due to the Project ONLY

                           

 

List of Figures

Figure 5-1            Locations of Project Boundary and Identified Noise Sensitive Receivers (NSRs)

Figure 5-2            Locations of Background Noise Measurements

Figure 5-3            Locations of Assessment Points of Each NSRs

Figure 5-4            Locations of Works Front, NSRs and Corresponding Notional Points for NSRs

 

 

List of Appendices

Appendix 5-1       Corresponding MLP of Planned Development at Nam Cheong Station and Correspondence with MTRC

Appendix 5-2       Photographs of the Identified existing NSRs

Appendix 5-3       Split Type A/C Observed at NSR1 and NSR2

Appendix 5-4       Construction Programme

Appendix 5-5       Latest Layout and Elevation Plan

Appendix 5-6       Photos of Identified Workshop Vehicle Repair Activities

Appendix 5-7       Summary of Estimated Off-site Traffic Generation (Inbound and Outbound) from FEHD Depot and Summary of Traffic Forecast

Appendix 5-8       Detailed Calculation of Construction Noise Impact Assessment and Complete PME Inventory (Unmitigated Scenario)

Appendix 5-9       Construction Noise Levels due to XRL project according to AEIAR-143/2009

Appendix 5-10     Detailed Calculation of Fixed Plant Noise Impact Assessment

Appendix 5-11     Detailed Calculations of Construction Noise Impact Assessment and Complete PME Inventory (Mitigated Scenario)

 

 

 


5.           Noise Impact Assessment

5.1         Introduction

5.1.1     Potential noise impact arising from the Project would be contributed by both construction and operation phases.  This Chapter summarises the identified potential sources of noise impact during both phases, details of noise impact assessment and, where necessary, the recommended noise mitigation measures to reduce the identified noise impacts to the acceptable levels.

5.2         Environmental Legislation and Guidelines

Construction Phase

5.2.1     In Hong Kong, control of construction noise is carried out under the Noise Control Ordinance (NCO) and the two subsidiary Technical Memoranda on Noise from Percussive Piling (PP-TM) and Noise from Construction Work Other Than Percussive Piling (GW-TM).  Construction Noise Permit (CNP) is required for carrying out percussive piling at daytime on a day not being a general holiday and general construction works during restricted hours (i.e. 1900 to 0700 hours on a day not being a general holiday and at any time on a general holiday). In addition, there are provisions under the Environmental Impact Assessment Ordinance (EIAO) and the associated Technical Memorandum (EIAO-TM) for assessing the impacts from construction activities during 0700 to 1900 hours on a day not being a general holiday.

5.2.2     The Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) deals with the control of noise generated by Specified Powered Mechanical Equipment (SPME) and Prescribed Construction Works (PCWs) in identified designated areas. SPME includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held poker vibrator; PCWs include erection/dismantling of formwork/scaffolding, loading/unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material, and hammering.  Since the Yen Ming Road Site Boundary is within the designated area, CNP would be required for this section of the Project for carrying out PCWs and construction works involving the use of SPME during restricted hours (i.e. 1900 to 0700 hours and anytime on a general holiday).

5.2.3     The NCO criteria for the control of noise from Powered Mechanical Equipment (PME) are dependent on the Area Sensitivity Ratings for the Noise Sensitive Receivers (NSRs).  Area Sensitivity Rating is a function of the type of area within which the NSRs are located and the degree of the effect on the NSRs of particular Influencing Factors (IFs).  Categorization of Area Sensitivity Ratings is shown in Table 5-1.  In this EIA report, the Area Sensitivity Rating for the NSRs is determined to be “C” in general due to influencing factor of heavily trafficked West Kowloon Corridor. Despite any description or assessment made in this EIA report on construction noise aspects, there is no guarantee that a CNP will be issued for the construction of the Project. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the NCO.  The Noise Control Authority will take account of contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in this EIA report shall bind the Noise Control Authority in making his decision.  If a CNP is to be issued, the Noise Control Authority shall include in it any condition he thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

Table 51        Area Sensitivity Rating Criteria Specified in the GW-TM

Type of area containing the NSR

Degree to which NSR is affected by IF

Not Affected [1]

Indirectly

Affected [2]

Directly

Affected [3]

Rural area, including country parks or village type developments

A

B

B

Low density residential area consisting of low-rise or isolated high-rise developments

A

B

C

Urban area

B

C

C

Area other than those above

B

B

C

Notes:

1.     “Not Affected” means that the NSR is at such a location that the noise generated by the influencing factors [4] (IFs) is not noticeable at the NSR.

2.     “Indirectly Affected” means that the NSR is at such a location that the noise generated by the IF, whilst noticeable at the NSR, is not a dominant feature of the noise climate of the NSR.

3.     “Directly Affected” means that the NSR is in such a location that the noise generated by the IF is readily noticeable at the NSR and is a dominant feature of the noise climate of the NSR.

4.     “IF” is defined as any industrial area, major road or the area within the boundary of Hong Kong International Airport. The term “major road” means a road which has a heavy and generally continuous flow of vehicular traffic and, in normal circumstances, means a road with an annual average daily traffic flow in excess of 30,000.

 

5.2.4     Construction activities of proposed developments will be planned and controlled in accordance with the NCO, GW-TM, DA-TM and PP-TM.  Works requiring the use of PME during restricted hours and particularly at night will be carried out under the provision of a CNP and planned to achieve the required Acceptable Noise Levels (ANLs). The basis of the ANLs, i.e. the Basic Noise Levels (BNLs) are shown in Table 5-2.

Table 52        Basic Noise Levels (in Leq,30min, dB(A))

Time Period

Area Sensitivity Rating

A

B

C

All days during the evening (1900 to 2300 hours) and general holidays (including Sundays) during the day and evening (0700 to 2300 hours)

60 (45)

65 (50)

70 (55)

All days during the night-time (2300 to 0700 hours)

45 (30)

50 (35)

55 (40)

Notes:

·         BNLs in brackets apply to SPME and PCW specified in the DA-TM.

·         The BNLs should be corrected to obtain the ANLs according to the relevant TM

 

5.2.5     For constructions carried out on a day not being a general holiday, daytime period (i.e. 0700 to 1900 hours), noise standard of 75 dB(A) Leq,30 min, as stipulated in Table 1B, Annex 5 of the EIAO-TM, is adopted for this assessment for all domestic premises including temporary housing accommodations and hostels. For schools, a daytime noise standard of 70 dB(A) Leq,30 min, lowered to 65 dB(A) Leq,30 min during examination periods, is adopted. These standards apply to uses which rely on opened windows for ventilation.

5.2.6     Subsidiary regulations of the NCO include the Noise Control (Hand Held Percussive Breakers) and Noise Control (Air Compressors) Regulations, which require compliance with relevant noise emission standards and the fixing of noise emission labels to specified plants and equipment.  While these requirements are not directly relevant to the construction noise impact assessment, contractors must meet them during the construction phase of the Project.

5.2.7     Percussive piling is prohibited between 1900 and 0700 hours on a day not being a general holiday and at any time on a general holiday.  A CNP is required for carrying out of percussive piling between 0700 and 1900 hours on a day not being a general holiday. The PP-TM sets out the requirements for working and determination of the permitted hours of operations. ANLs criteria for percussive piling are shown in Table 5-3.

Table 53        Acceptable Noise Levels for Percussive Piling Specified in the PP-TM

Architectural Characteristics of NSR

ANL, Leq,30min dB(A)

No windows or other openings

100

With central air conditioning system

95

With windows or other openings but without central air conditioning system

85

Note:    10 dB(A) should be subtracted from the ANLs shown above for NSRs which are hospitals, medical clinics, educational institutes, courts of laws or other NSRs which are considered by the Authority to be particularly sensitive to noise.

 

Operation Phase

Fixed Plant Noise

5.2.8     The NCO and Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM) control operational noise from places or premises other than domestic premises, public places or construction sites. For the assessment of impacts from these noise sources, the Area Sensitivity Ratings (ASR) of the NSRs should be determined in accordance with the IND-TM, and thus to figure out  the appropriate ANL according to the ASR. There are four types of areas described in the IND-TM which are summarised in Table 5-1 in above Section 5.2.3.

5.2.9     The ANL based upon the different ASRs are shown in Table 5-4 below.

 

Table 54        Acceptable Noise Level during Operational Phase

Time Period

ASR of “A”

ASR of  “B”

ASR of  “C”

Daytime and Evening (0700-2300 hours)

60

65

70

Night-time (2300-0700 hrs)

50

55

60

 

5.2.10   According to the EIAO-TM, noise standards for planning purposes for fixed noise sources are determined with the following criteria:

(a)       5dB(A) below the appropriate Acceptable Noise Levels (ANL) shown in Table 3 of the IND-TM (i.e. Table 5-4), or

(b)       The prevailing background noise levels (for quiet areas with level 5 dB(A) below the ANL)

5.2.11   In order to obtain prevailing background noise levels, surveys have been conducted on 4 and 17 July 2012. The measured background noise levels and determined assessment criteria for each NSR will be detailed in Section 5.3.

Traffic Noise

5.2.12   Road traffic noise criteria are listed in Table 1A, Annex 5 of the EIAO-TM, which provides guidance on acceptable road traffic noise levels at various types of noise sensitive buildings.  The relevant criteria are shown in Table 5-5.  These standards apply to uses which rely on opened windows for ventilation.

Table 55        Road Traffic Noise Assessment Criteria Specified in the EIAO-TM

Uses

Road Traffic Noise Assessment Criteria – Peak Hour Traffic

(L10,(1-hour)) / dB(A)

Domestic Premises

70

Hotels and Hostels

70

Offices

70

Educational Institutions

65

Places of public worship and courts of law

65

Hospitals, clinics, convalescences and homes for the aged, diagnostic rooms, wards

55

Note: The above standards apply to uses which rely on opened windows for ventilation.

5.2.13   To ascertain the off-site traffic noise impact caused by the operation of the depot, a comparison of traffic noise levels during AM peak and PM peak of FEHD depot off-site traffic for the “with project” and “without project” scenarios is required. Noise contribution from the FEHD depot is considered as insignificant when the difference is less than 1.0dB(A).

 

5.3         Noise Sensitive Receivers

5.3.1     NSRs have been identified in accordance with Annexes 5 and 13 of the EIAO-TM which can include domestic premises, temporary housing accommodation, educational institutions, nurseries, hospitals, medical clinics, homes for the aged, convalescent homes, places of public worship, libraries, courts of law, performing arts centres, having direct line-of-sight and substantial angle of view to the Project Area. Sensitive receivers present within the 300m study area boundary have been identified.

5.3.2     Besides, a planned residential development on Nam Cheong Station has been identified at the commencement of the assessment. Details of the planned development including floor plan and number of floors have been referenced to the latest approved Master Layout Plan (MLP approved in Town Planning Application A/K20/119).  In accordance with information provided by the MTRC, construction of the development has been commenced and the anticipated completion of the whole Development would be no later than Year 2019.  Corresponding MLP of Planned Development at Nam Cheong Station and correspondence with MTRC are enclosed in Appendix 5-1.

5.3.3     Figure 5-1 illustrates the Project boundary together with identified Noise Sensitive Receivers. Details of the identified existing and planned NSRs are summarized in Table 5-6. Photographs of the identified existing NSRs are shown in Appendix 5-2.

Table 56        Summary of the Identified Existing and Planned NSRs near the Project

NSR

Name of Building

 

Use

No. of Floor

Approximate Distance from the Project Site

Remarks

1

Sir Ellis Kadoorie Secondary School (West Kowloon)

 

Education Institute

8

100m

Split type A/C were noted on site

2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

 

Education Institute

8

180m

Split type A/C were noted on site

3

Hampton Place

Residential

48

290m

/

4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

15

260m

/

5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

15

250m

/

6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

15

290m

/

7

Fu Cheong Estate Fu Yun House

 

Education / Homes for the Aged

5

270m

/

8

Planned Residential Development on Nam Cheong Station

 

Residential

9

110m

Anticipated Completion no later than Year 2019

40

160m

5.3.4     In addition, according to the site visit observation dated 4 July and 17 July 2012, spilt-type air-conditioners (A/C) have been installed at Sir Ellis Kadoorie Secondary School (West Kowloon) and Tai Kok Tsui Catholic Primary School (Hoi Fan Road).  Appendix 5-3 shows the existing split type A/C of NSR 1 and NSR 2.

5.3.5     Notwithstanding the provision of spilt-type air-conditioners, since it is also possible for the schools abovementioned to rely on opened window ventilation, all schools within the Noise Assessment Area are still considered as NSRs for noise impact assessment.

Area Sensitivity Rating of Noise Sensitive Receivers

5.3.6     According to the latest Outline Zoning Plan (OZP) in the Nam Cheong, there is an existing industrial zoning area at south-west to the Project. By site observation, the industrial area was an open storage for cargo transfer station which operates 24-hour as advised by the staff.  Therefore, the open storage is considered to be an influencing factor (IF).

5.3.7     As per the Annual Traffic Census (ATC) of 2011 by Transport Department, the Annual Average Daily Traffic (AADT) of West Kowloon Highway (WKH) is about 74,000 vehicles, as such WKH is considered as an IF in accordance with Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM).

5.3.8     NSRs 1 and 2 are located at “Area other than those above” mentioned in Table 5-1 which are directly affected by the IFs (OZP Industrial Zone and WKH). Therefore, an ASR of C would be allocated.

5.3.9     NSRs 3 to 8 are located within the urban area of Nam Cheong which are indirectly / directly affected by the IF (WKH).  Therefore, an ASR of C would be allocated.

5.3.10   The identified Area Sensitivity Ratings of NSRs are tabulated in Table 5-7.

Table 57       Identified Area Sensitivity Ratings of NSRs

NSR

Name of Building

 

Influencing Factor (IF)

Directly / Indirectly Affected

Identified ASR

1

Sir Ellis Kadoorie Secondary School (West Kowloon)

OZP Industrial Zone & West Kowloon Highway

Directly

C

2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

West Kowloon Highway

Directly

C

3

Hampton Place

West Kowloon Highway

Indirectly

C

4

Nam Cheong Estate Block 6 Cheong Chit House

West Kowloon Highway

Indirectly

C

5

Nam Cheong Estate Block 5 Cheong Yat House

West Kowloon Highway

Indirectly

C

6

Nam Cheong Estate Block 4 Cheong Shun House

West Kowloon Highway

Indirectly

C

7

Fu Cheong Estate Fu Yun House

West Kowloon Highway

Indirectly

C

8

Planned Residential Development on Nam Cheong Station

West Kowloon Highway

Directly

C

 

5.3.11   Besides the identification of ASR in IND-TM, more stringent criteria for assessing fixed plant noise are stipulated in the EIAO-TM for planning purpose.  The stipulated assessment criteria:-

·      Criteria 1: 5 dB(A) below the appropriate ANL shown in Table 3 of IND-TM; or

·      Criteria 2: the prevailing background noise levels (for quiet areas with level 5 dB(A) below the ANL)

5.3.12   In order to determine the appropriate assessment criteria, prevailing background noise survey at the NSRs have been conducted on 4 and 17 of July 2012.  The measured background noise levels and the recommended fixed plant noise assessment criteria are shown in Table 5-8 and the geographical locations are shown in Figure 5-2.

Table 58        Measured Prevailing Background Noise Levels for NSRs and Recommended Fixed Plant Noise Assessment Criteria

NSR

Representative Background Noise Measurement Locations

Measured Background Noise Levels (Leq,30mins) / dB(A)

ANL – 5 / dB(A)

Recommended Fixed Plant Noise Assessment Criteria (Leq,30mins) / dB(A)

Daytime

Nighttime

Daytime

Nighttime

Daytime

Nighttime

1

NML 1

64.7

NA

65

NA

65

NA

2

NML 2

62.1

NA

65

NA

62

NA

3

NML 3

65.6

56.7

65

55

65

55

4

NML 4

66.3

58.9

65

55

65

55

5

NML 4

66.3

58.9

65

55

65

55

6

NML 5

66.1

63.4

65

55

65

55

7

NML 6

68.1

63.4

65

55

65

55

8

NA[1]

NA

NA

65

55

65

55

Remark:

[1] Planned Residential Development on Nam Cheong Station (NSR 8) shall be constructed above the non-domestic podium of 27mPD or 20m above ground, which will be equivalent to the elevation of the existing roof level of Nam Cheong Station. Due to the safety concern, request to conduct background noise survey at that elevated position was rejected.  On the other hand, it was considered not appropriate to conduct background noise survey at the ground level fronting Nam Cheong Station, as ground level does not have direct line-of-sight to the West Kowloon Highway, which is identified to be the dominant prevailing noise source of the concerned development due to its heavy on-road traffic. Therefore, background noise level measurement is not available.

 

5.3.13   Noise assessment points are selected at each identified NSR in the Project.  Details of the selected noise assessment points are summarised in Table 5-9. And the locations are illustrated in Figure 5-3 for operational noise impact assessments and in Figure 5-4 for construction noise impact assessments.

Table 59        Summary of Selected Noise Assessment Points at Each Representative NSR

NSR ID

Description

Land Use

No. of Noise Sensitive Storeys above Podium/Site Level

Podium (P)/Site Level (S) (mPD)

No. of Noise Assessment Points at Each Floor

1

Sir Ellis Kadoorie Secondary School (West Kowloon)

Education Institute

8

5.6 (S)

3

2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

Education Institute

8

5.5 (S)

3

3

Hampton Place

Residential

48

14.8 (P)

1

4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

15

5.2 (S)

1

5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

15

5.2 (S)

1

6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

15

5.2 (S)

1

7

Fu Cheong Estate Fu Yun House

Education / Homes for the Aged

5

16.2 (P)

1

8

Planned Residential Development on Nam Cheong Station

Residential

9

26.4 (P)

2[1]

 

40

3[1]

Remark:

[1] Noise assessment points of N801 to N805 in Figure 5-3 are selected for operational noise impact assessments. Noise assessment points of N811 to N815 in Figure 5-4 are selected for construction noise impact assessment.

 

5.4         Identification of Potential Noise Impacts

Construction Phase

5.4.1     The potential sources of noise impact during the construction phase of the Project would be the use of Powered Mechanical Equipment (PME) for various construction activities.  As broadly indicated in construction programme in Appendix 5-4, the construction of the project would be tentatively starts from end 2014 and lasts for about 25 months.  Location of notional noise sources are provided in Figure 5-4.  The key construction noise activities include:

-                Site mobilisation and hoarding

-                Foundation

-                Superstructure

-                Finishes

5.4.2     Foundation construction will adopt driven H-pile, which is kind of percussive piling as controlled under “Technical memorandum on Noise from Percussive Piling” under Noise Control Ordinance, would be adopted for foundation construction. Since the issuance of a CNP by the Noise Control Authority would depend on the submission of an application by the contractor, and on the contractor’s compliance with the percussive piling noise limits set out within the PP-TM, the assessment of this type of noise are thus not to be included in this EIA Report, and it is upon the authority to make final judgment in granting of CNP and this report make no binding effect to the authority in executing of NCO. However, other auxiliary PME for the piling works, other than the hydraulic hammer driving rig for steel pile, including mobile crane, generator for welder and generator will be included in construction noise impact assessment to reflect construction noise from these PMEs.

5.4.3     The key PME to be used for the construction works activities are shown in Table 5-10. In order to provide a realistic assessment of the works activities, the percentages of time that PME will be operating on site have also been considered when calculating the cumulative Sound Power Levels (SWL) for the construction activities. The noise levels at the NSRs have been assessed on a monthly basis in respect to the individual noise levels induced by the construction works activities, assuming they are operating cumulatively.

Table 510      PME identified as Major Noise Sources

PME [1]

TM or other ref.

No. of PME

SWL in dB(A)

On time %

Total SWL [2]

1-1         Site Mobilisation and Hoarding

Loader, wheeled (Back-hoe) (All)

CNP 081

1

112

50

115.3

Excavator, Tracked (All)

CNP 081

1

112

50

Lorry, with crane, 5.5 tonne <GVH <= 38 tonne (All)

Other ref. [3]

1

105

50

Generator (All)

CNP 103

1

95

100

Breaker, mini-robot mounted (Act 1)

Other ref. [3]

1

115

50

Air Compressor, air flow < 10m3/min (Act 1)

CNP 001

1

100

50

Concrete Lorry Mixer (Act 2)

CNP 044

1

109

100

Poker, Vibratory, hand-held, electric (Act 2)

Other ref. [3]

2

102

100

2-1         Piling (Driven H Pile)

Mobile Crane (All)

CNP 048

3

112

100

116.8

Generator, portable (All)

Other ref. [3]

1

100

50

Generator (All)

CNP 103

1

95

100

Driven H-Pile Rig 

(Controlled under PP-TM)

3-1         Superstructure (Pile Cap Construction)

Excavator, Tracked (Act 1)

CNP 081

2

112

50

114.3

Lorry, with crane, 5.5 tonne <GVH <= 38 tonne (Act 1)

Other ref. [3]

2

105

50

Mobile Crane (Act 1)

CNP 048

1

112

50

Concrete Lorry Mixer (Act 2)

CNP 044

1

109

50

Poker, Vibratory, hand-held, electric (Act 2)

Other ref. [3]

2

102

100

Bar Bender and cutter, electric (All)

CNP 021

1

90

70

3-2 Superstructure (Superstructure and Concreting)

Lorry, with crane, 5.5 tonne <GVH <= 38 tonne (All)

Other ref. [3]

2

105

50

111.7

Concrete Lorry Mixer (All)

CNP 044

1

109

50

Concrete Pump (All)

CNP 047

1

109

50

Poker, Vibratory, hand-held, electric (All)

Other ref. [3]

2

102

100

Tower Crane, electric (All)

CNP 049

1

95

100

Bar bender and cutter, electric (All)

CNP 021

3

90

50

3-3 Finishes

Drill, hand-held, battery (All)

Other ref. [3]

3

89

50

106.9

Jig-saw, hand-held, wood, electric (All)

Other ref. [3]

1

99

50

Saw, wire (All)

Other ref. [3]

2

101

50

Lorry, with crane, 5.5 tonne <GVH <= 38 tonne (All)

Other ref. [3]

2

105

50

Notes:

[1] The grouping of PMEs in sub-construction task is reflected in brackets. “(ALL)” denotes that the PME would be adopted for all sub-construction tasks in that construction activity. “(Act 1)”, (Act 2)”, etc. denotes that the PME would be adopted for particular sub-construction task of a construction activity only.

[2] Total SWL reflects the predicted total SWL in consideration of the number of PMEs, their on-time percentage and accounts for the inventory grouping (sub-construction tasks) contributing to the highest noise level.

[3] PME referenced to the document “Sound power levels of other commonly used PME”.

 

5.4.4     The proposed plant inventory involves the use of Specified Powered Mechanical Equipment (SPME), as detailed in Section 5.2.2, including hand-held breaker, concrete lorry mixer and hand-held poker vibrator. As such, should construction works extended into restricted hours, the DA-TM will become effective and further restriction on the acceptable noise will be imposed.

Operation Phase

5.4.5     Identified potential operational noise from the development includes the following:

(1)    Fixed Plant Noise

                          i.    Workshop Vehicle Repair Activities

                         ii.    Mechanical Ventilation and Air Conditioning System (MVAC) and other Building Services Equipment

(2)    Off-site Traffic Noise

 

Fixed Plant Noise - Workshop Vehicle Repair Activities

5.4.6     During the operational phase, noise sources could arise from the repair activities for the vehicles and engine noise emission from the vehicles during commissioning tests. All of the planned vehicle repair activities are limited to 0700 to 1900 hours only and all of them would be carried out within “indoor” covered area on ground floor of the development, as shown in Appendix 5-5.

5.4.7     The workshop vehicle repair activities for the development have been validated to include:

·           Sand Blasting;

·           Grinding;

·           Hammering;

·           Roller Brake Tester;

·           Vehicle Washing;

·           Vehicle Welding;

·           Parts Welding;

·           Screw Driver; and

·           Tyre Changer.

5.4.8     Photos of the current workshop vehicle repair activities are shown in Appendix 5-6.

5.4.9     Noise surveys were conducted on 26 June 2012 and 6 July 2012 at the existing FEHD Kwai Chung Depot and Sai Yee Street Depot respectively to measure the operational noise level of the equipment.

5.4.10   Noise measurements were conducted by using a calibrated Bruel & Kjaer Type 2260 Sound Level Meter. SWL of the noisy activity was determined taking consideration of standard acoustic principles, as well as the methodology presented in the International Standard ISO 3746: Acoustics – Determination of sound power levels of noise sources using sound pressure – survey method using an enveloping measurement surface over a reflecting plane, and Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM). Several noise measurements were carried out for each activity and the averaged levels were adopted for the calculation.

5.4.11   Noise data associated with operation of vehicle washing, roller brake testing and tyre changer were obtained by making reference to the approved EIA Reports for New World First Bus Permanent Depot at Chai Wan (AEIAR-029/2000) and Proposed Headquarters and Bus Maintenance Depot in Chai Wan (AEIAR-045/2001).

5.4.12   According to the “Technical Memorandum for the Assessment of Noise from Place Other Than Domestic Premises, Public Places or Construction Sites”, correction for tonality of each workshop equipment and repair activity have also been considered.

5.4.13   The quantity, measured noise levels, referenced SWL, tonality, operation duration, operation frequency of workshop equipment and repair activity in the development are shown in Table 5-11.

Table 511      Summary of Workshop Equipment and Repair Activity

Item

Activities

Qty

Averaged Measured Sound Pressure Level / dB(A)

SWL, dB(A)

Correction for Tonality / dB(A)

Operation Duration (mins)

Operation Frequency (per 30 mins)

1

Sand Blasting

1

108 at 1m

116

/

1

2

2

Grinding

1

100 at 1m

108

/

1

2

3

Hammering (12lb Hammer)

1

102 at 1m

113[3]

/

1

1

4

Roller Break Tester

1

/

98.6[1]

/

1

5

5

Vehicle Washing

(Manual)

1

/

88.4[2]

/

30

1

6

Vehicle Welding

1

70 at 1m

78

3

20

1

7

Parts Welding

1

80 at 1m

88

/

5

4

8

Screw Driver

1

92 at 1m

100

/

1

5

9

Tyre Changer

1

/

97.6[2]

/

5

4

Remarks:

[1] SWL values based on the approved EIA report for New World First Bus Permanent Depot at Chai Wan (AEIAR-029/2000), with similar works and project nature.

[2] SWL values based on the approved EIA report for Proposed Headquarters and Bus Maintenance Depot in Chai Wan (AEIAR-045/2001) with similar works and project nature.

[3] 3 dB(A) correction for impulsiveness has been taken into account in the measured SWL (110 + 3 = 113 dB(A)).

 

5.4.14   Vehicles entering the workshop would require engine warm-up during maintenance. The operational noise assessment has been undertaken based on the daily operations of the workshop. The estimated number and type of FEHD vehicles under repairing per day in the proposed depot would be 9 based the following vehicles categories:-

·           Refuse Collection Vehicle: 4

·           Street Washing Vehicle / Mechanical Gully Emptier: 3

·           Van / Light Bus / Light Truck: 2

5.4.15   As the estimated number would be only 9 vehicles per day (0700 to 1900hrs) that would require engine warm-up during maintenance. It is anticipated that the operational noise due to the idling vehicle engines of the maintenance vehicles would be minimal. Therefore, the key potential noise source during maintenance would be limited to the identified repair activities and workshop equipment.

Fixed Plant Noise - Mechanical Ventilation and Air Conditioning System (MVAC) and other Building Services Equipment

5.4.16   Potential sources of noise impacts are identified as the mechanical equipment associated with the operation of the FEHD Vehicle Depot.  All mechanical equipment will be fully enclosed within plant rooms except the fan discharge of cooling towers on the 4/F.  A total of 2 cooling towers will be operated during the daytime and evening time periods (0700 to 2300hrs); while only 1 cooling tower with low speed will be operated during the nighttime period (2300 to 0700hrs next day).

5.4.17   The identified key noise sources of MVAC installations are based on the preliminary design layout plans (Appendix 5-5).  The proposed locations of plant rooms and the estimated quantity of identified noise sources to be operated during daytime and evening time periods and nighttime period are shown in Table 5-12.

Table 512      Estimated Quantity of Identified Fixed Plant Noise Sources

Location of Plant Rooms

Estimated Quantity of Identified Noise Sources

Floor

Rooms

Operation during Daytime and Evening Time Period

(0700hr – 2300hr)

Operation during Nighttime Period (2300hr – 0700hr next day)

G/F

Transfer Tank Pump Room

2 nos. Transferred Water Pumps

1 no. Exhaust Fan

2 nos. Transferred Water Pumps

1 no. Exhaust Fan

Chiller Pump Room

2 nos. Water Pumps

1 no. Exhaust Fan

1 no. Water Pump

1 no. Exhaust Fan

Transformer Room

2 nos. Transformers

1 no. Exhaust Fan

2 nos. Transformers

1 no. Exhaust Fan

UG/F

Chiller Plant Room

2 nos. Chillers

1 no. Exhaust Fan

1 no. Chiller

1 no. Exhaust Fan

AHU Room

1 no. AHU

Nil

Water Vehicle Filing and Automatic Washing System Water Tank and Water Pump Room

5 nos. Water Pumps

1 no. Exhaust Fan

5 nos. Water Pumps

1 no. Exhaust Fan

Potable Flushing and make up water and water pump Room

3 nos. Water Pumps

1 no. Exhaust Fan

3 nos. Water Pumps

1 no. Exhaust Fan

Exhaust Fan Room

 

4 nos. General Exhaust Fans

2 nos. Welding Exhaust Fans

3 nos. Vehicle Exhaust Fans

Nil

TBE Room

 

1 no. Exhaust Fan

1 no. Exhaust Fan

3/F

PAU Rooms

5 nos. PAU

5 nos. PAU

Generator Room

 

1 no. Generator

(operates during power failure / maintenance)

1 no. Generator

(operates during power failure)

4/F

 

 

Cooling Tower Plant Room

2 nos. Cooling Towers 

1 no. Cooling Tower

PAU Room

2 nos. PAU

1 no. PAU

LR/F

Generator Room

 

1 no. Generator

(operates during power failure / maintenance)

1 no. Generator

(operates during power failure)

Heat Pump Plant Room

 

1 no. Heat Pump

1 no. Heat Water Circulation Pump

1 no. Exhaust Fan

1 no. Heat Pump

1 no. Heat Water Circulation Pump

1 no. Exhaust Fan

 

Off-site Traffic Noise

5.4.18   The vehicles entering and exiting the proposed FEHD Vehicle Depot may potentially increase the traffic noise levels at the NSRs.

5.4.19   As per the estimated off-site traffic from the Depot, the AM peak off-site traffic of the Depot would be 37 vehicles at 0700 to 0800hour and the PM peak off-site traffic of the Depot would be 34 vehicles at 1500 to 1600hour.  It is expected that the highest noise contribution generated by the Depot would be during AM peak and PM peak off-site traffic of the Depot.

5.4.20   Summary of estimated off-site traffic generation (inbound and outbound) from FEHD Depot and summary of traffic forecast, taken into account of surrounding planned developments including the one in Cheung Sha Wan Wholesale Food Market Phase 2 site, are shown in Appendix 5-7.

5.5         Assessment Methodology

Construction Phase

5.5.1     Methodology for assessing noise from the construction activities associated with the proposed works is developed based on the GW-TM and is summarized as follows:

·           location of appropriate NSRs with respect to the work sites;

·           determination of distance attenuation and screening effects to NSRs from notional noise source of relevant work site;

·           prediction of construction noise levels at NSRs in the absence of any mitigation measures;

·           proposal of mitigation measures and determine their effectiveness; and 

·           determination of the residual impacts.

5.5.2     The construction noise impacts have been assessed against the noise standards given in the EIAO-TM as follows:

·           75 dB(A) Leq,30min for residential dwellings;

·           70 dB(A) Leq,30min for schools; and

·           65 dB(A) Leq,30min for schools during examination period. 

Operation Phase

Fixed Plant Noise

5.5.3     As discussed in Section 5.4 above, major operational noise source from proposed development would be (a) workshop vehicle repair activities; and (b) MVAC and other building services equipment.

5.5.4     The identified key noise sources of the workshop activities and MVAC installations and other building services equipment are based on the preliminary design layout plans.

5.5.5     The assessment approach for the operational noise impacts from workshop vehicle repair activities, has been conducted based on consideration of standard acoustic principles presented in IND-TM which are summarised as follow:

a.         Sound Power Level (SWL) associated with operation of workshop equipment and vehicle repair activities were obtained from the previous approved EIA Reports and via on-site noise surveys discussed in Sections 5.4.10 and 5.4.11.

b.         Sound Pressure Level (SPL) at representative NSRs calculated based on consideration on distance attenuation, tonality correction, impulsiveness correction, noise shielding effect, façade correction.

5.5.6     Since the detailed design of the equipment to be installed within the plant rooms is not available during course of study, the maximum allowable sound power levels (SWLs) emitted from the plant rooms would be calculated to be compliant to noise criteria set out, taking into account also concurrent operation of noise from workshop equipment and repair activities.

Off-site Traffic Noise

5.5.7     The prediction of traffic noise impact is evaluated according to the “Calculation of Road Traffic Noise” by Department of Transport UK. 

5.5.8     The off-site traffic noise impacts generated from vehicles leaving and returning the proposed vehicle depot to the NSRs in the vicinity is evaluated in Section 5.6.

5.6         Prediction and Evaluation of Noise Impacts

Construction Phase

5.6.1     Construction activities for the proposed upgrading works in the Project include the following:

·           Site mobilisation and hoarding;

·           Foundation; and

·           Superstructure.

·           Finishes

5.6.2     The extent of construction noise impacts depends on the type and number of Power Mechanical Equipment (PME) to be used in different construction activities and varies during different construction phases. As shown in Appendix 5-4, the proposed construction programme is expected to last for 25 months, from end 2014 to 2017.  The construction activities are expected to be conducted only during normal daytime working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday).  The corresponding predicted construction noise levels of the construction activities listed in Section 5.4 at the selected NSRs between Year 2014 and 2016 are shown in Table 5-10. Detailed calculations of the construction noise impact assessment and complete PME inventory are provided in Appendix 5-8.

5.6.3     Planned NSRs have also been taken into account in this construction noise assessment. Correspondence showing anticipated completion dates of planned residential developments at Nam Cheong Station are shown in Appendix 5-1.  The period during which respective planned NSRs would be exposed to the construction noise impact from the Project are as follows:

·           Development at Nam Cheong Station from 2013

5.6.4     Express Rail Link (XRL) is being carried out along Sham Mong Road, the nearby works area of XRL. The Highways Department has been consulted and construction programme of the XRL project was updated. Correspondence showing anticipated completion dates of XRL are provided in Appendix 5-9. The anticipated works during FEHD construction are shown in Table 5-13.

Table 513      Summary of Anticipated Works of XRL

Works Area

Location

Anticipated Concurrent Works

Anticipated Construction Period

Q

Name Cheong Station

Reprovisioning of bored-piles and pile caps

Mid 2013 to End 2014

R

Sham Mong Road

Nil (Reinstatement of Sham Mong Road scheduled to be completed in early 2014)

N/A

S

Nam Cheong Park

Site office maintained

Till early 2015

T

Nam Cheong Park

Site office maintained

Till early 2016

5.6.5     The approved EIA report of the XRL project with EPD Register No. AEIAR-143/2009 has been referenced. The following NSRs are in the vicinity of both XRL and proposed FEHD project:

·           Cheong Chit House, Nam Cheong Estate

·           Cheong Yat House, Nam Cheong Estate

·           Fu Yun House, Fu Cheong Estate

5.6.6     According to the predicted construction noise levels in Appendix 5-8 of AERIA-143/2009, construction noise impact due to the XRL project at the above corresponding NSRs during different works stages are updated with XRL construction schedule provided in Table 5-13 above. Corresponding section of Appendix 5-8 of AEIAR-143/2009, the location of noise sensitive receivers in the AEIAR-143/2009, correspondence showing updated construction schedule of XRL project, and the corresponding potential construction noise impact due to XRL project to relevant NSRs considered in this assessment are provided in Appendix 5-9.

5.6.7     For the uncertainty in detailed construction noise impact from Nam Cheong Station development, construction plant inventory of Nam Cheong Station development was assumed, with construction schedule assumed lasting from before 2012 towards end 2019 to represent the worst case scenario. The assumed plant inventory is also provided in Appendix 5-8. Predicted construction noise levels of cumulative construction noise impact from the proposed FEHD depot development together with XRL construction and the Nam Cheong Station development, as well as construction noise impact from the proposed FEHD development alone are provided.

5.6.8     The predicted construction noise levels shown in Tables 5-14 and 5-15 indicate that construction activities of the Project, if unmitigated, would result in exceedance of the daytime construction noise criteria during normal working hours at Sir Ellis kadoorie Secondary School (West Kowloon), Tai Kok Tsui Catholic Primary School (Hoi Fan Road) and Fu Cheong Estate Fu Yun House (NSR N1, N2 and N7 respectively). Mitigation measures are therefore considered to reduce the construction noise impact to acceptable levels.

Table 514      Predicted Cumulative Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Unmitigated Scenario

NSR ID

Descriptions

Land Use

ANL, dB(A)

Predicted Construction Noise Levels at each Assessment Year

(Leq, dB(A))

2014

2015

2016

N1

Sir Ellis Kadoorie Secondary School (West Kowloon)

Education Institute

65 [1]

69

72

66

N2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

Education Institute

65 [1]

65

68

61

N3

Hampton Place

Residential

75

61

64

58

N4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

75

63

66

60

N5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

75

63

66

60

N6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

75

62

65

60

N7

Fu Cheong Estate Fu Yun House

Education / Homes for the Aged

65 [1]

66

67

65

N8

Planned Residential Development on Nam Cheong Station

Residential

75

68

71

64

Notes:

1.             Construction noise standard for schools is 70 dB(A) at normal school days and is reduced to 65 dB(A) during examination period. The more conservative 65 dB(A) standard is applied in this construction noise impact assessment.

2.             Noise levels exceeding the construction noise standards are bold.

 

 

Table 515      Predicted Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Unmitigated Scenario due to the Project ONLY

NSR ID

Descriptions

Land Use

ANL, dB(A)

Predicted Construction Noise Levels at each Assessment Year

(Leq, dB(A))

2014

2015

2016

N1

Sir Ellis Kadoorie Secondary School (West Kowloon)

Education Institute

65 [1]

69

72

65

N2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

Education Institute

65 [1]

65

68

61

N3

Hampton Place

Residential

75

60

64

57

N4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

75

61

65

58

N5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

75

62

65

58

N6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

75

60

64

57

N7

Fu Cheong Estate Fu Yun House

Education / Homes for the Aged

65 [1]

61

64

57

N8

Planned Residential Development on Nam Cheong Station

Residential

75

68

71

64

Notes:

1.       Construction noise standard for schools is 70 dB(A) at normal school days and is reduced to 65 dB(A) during examination period. The more conservative 65 dB(A) standard is applied in this construction noise impact assessment.

2.       Noise levels exceeding the construction noise standards are bold.

 

Operation Phase

Fixed Plant Noise

5.6.9     During the operational phase, noise impact due to the identified fixed plant noise sources including (a) workshop vehicle repair activities and (b) MVAC installation has been assessed.  Based upon the assumptions discussed in Sections 5.5.3 to 5.5.6, the predicted operational noise levels at the representative NSRs are shown in Table 5-16.  Detailed calculations of fixed plant noise impact assessment are in Appendix 5-10.

Table 516      Summary of Predicted Operational Levels at NSRs

NSR ID

Name

Daytime & Evening Time (D) / Nighttime (N)

Predicted Maximum Noise Level  /Leq, 30mins dB(A)

EIAO-TM Noise Criteria / Leq,30mins /dB(A)

1

Sir Ellis Kadoorie Secondary School (West Kowloon)

D

54.4

65

N

N/A

N/A

2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

D

48.4

62

N

N/A

N/A

3

Hampton Place

D

46.6

65

N

43.7

55

4

Nam Cheong Estate Block 6 Cheong Chit House

D

53.7

65

N

49.4

55

5

Nam Cheong Estate Block 5 Cheong Yat House

D

53.4

65

N

49.8

55

6

Nam Cheong Estate Block 4 Cheong Shun House

D

51.8

65

N

47.1

55

7

Fu Cheong Estate Fu Yun House

D

52.0

65

N

48.8

55

8

Planned Residential Development on Nam Cheong Station

D

58.2

65

N

54.9

55

 

5.6.10   The maximum allowable Sound Power Level (SWL) of each of the equipment in the plant rooms would be 90 dB(A), which should not be exceeded in order to achieve the noise criteria.

5.6.11   Results in Table 5-16 show that the predicted maximum noise levels at the identified NSRs due to workshop vehicle repair activities and the MVAC installations would comply with both daytime and nighttime EIAO–TM noise criteria.

Off-site Traffic Noise

5.6.12   The inbound and outbound routings of the off-site traffic of the proposed depot have been agreed with the Government in the Traffic Impact Assessment (TIA) report (endorsed by Transport Department). The agreed inbound and outbound vehicle routing plans are shown in Appendix 5-7.

5.6.13   The peak flows of the off-site traffic from the Depot would be at 0700 to 0800hour and 1500 to 1600hour during AM and PM respectively.  By comparing of the noise levels between “with project” and “without project” during AM and PM peaks off-site traffic of the Depot, the highest noise contribution generated by the Depot could be assessed.

5.6.14   In order to assess the off-site traffic noise short-term and long-term contribution generated by the Depot, the assessment years for the off-site traffic noise are 2017 and 2032, which are the tentative commencement of occupation year and 15 years after operation respectively.

5.6.15   The traffic forecast at AM peak (0700 – 0800) and PM peak (1500 – 1600) for two scenarios including “with project” and “without project” were provided by the Project Traffic Consultant and endorsed by TD. The traffic forecasts for year 2017 and year 2032 are shown in Table 5-17 and Table 5-18 respectively.  Relevant correspondence showing the endorsement of the traffic forecast data by the Authority is presented in Appendix 5-7.  Alignment of the road carriageways is shown in Appendix 5-7.


Table 517      Year 2017 Traffic Forecast

Label

AM Peak FEHD Depot Traffic

(0700 - 0800)

PM Peak FEHD Depot Traffic

(1500 - 1600)

With Project

Without Project

With Project

Without Project

veh/hr

HV %

veh/hr

HV %

veh/hr

HV %

veh/hr

HV %

A1

95

94%

58

90%

134

92%

118

91%

A2

128

91%

128

91%

57

93%

39

90%

A3

14

93%

14

93%

49

94%

31

90%

A4

50

98%

13

92%

42

93%

26

88%

A5

105

90%

105

90%

32

91%

32

91%

A6

19

95%

19

95%

41

90%

41

90%

B1

188

93%

151

91%

61

93%

45

91%

B2

128

91%

128

91%

57

93%

39

90%

B3

188

98%

188

98%

66

98%

66

98%

C1

199

44%

199

44%

372

42%

372

42%

C2

180

41%

180

41%

332

38%

332

38%

C3

1,041

31%

1,034

31%

1,980

30%

1,963

30%

C4

1,216

41%

1,216

41%

2,336

40%

2,318

40%

C5

1,242

42%

1,205

40%

2,296

40%

2,280

39%

D1

388

48%

358

43%

666

42%

656

41%

D2

295

41%

295

41%

564

41%

553

40%

D3

227

48%

223

47%

408

44%

406

44%

E3

150

59%

120

48%

205

53%

194

50%

E4

246

46%

246

46%

444

42%

444

42%

F1

186

49%

179

47%

332

45%

330

45%

F2

216

50%

216

50%

396

48%

393

47%

F3

134

54%

111

45%

178

47%

166

43%

F4

158

39%

158

39%

287

34%

287

34%

H3

293

27%

293

27%

578

29%

564

27%

H4

389

34%

389

34%

755

35%

755

35%

I1

339

29%

332

28%

618

26%

612

25%

I2

217

40%

217

40%

396

37%

390

36%

I3

173

38%

173

38%

334

37%

334

37%

I4

343

29%

343

29%

676

30%

662

29%

J5

67

24%

67

24%

134

25%

134

25%

J6

73

26%

73

26%

138

24%

138

24%

K1

195

47%

188

45%

371

46%

369

45%

K2

219

49%

219

49%

424

49%

421

49%

L1

206

49%

199

47%

384

46%

382

46%

L2

216

48%

216

48%

432

49%

429

49%

M3

1,188

36%

1,188

36%

2,785

33%

2,785

33%

M4

668

36%

668

36%

1,569

33%

1,569

33%


Table 518      Year 2032 Traffic Forecast

 

Label

AM Peak FEHD Depot Traffic

(0700 - 0800)

PM Peak FEHD Depot Traffic

(1500 - 1600)

With Project

Without Project

With Project

Without Project

veh/hr

HV %

veh/hr

HV %

veh/hr

HV %

veh/hr

HV %

A1

106

93%

69

90%

153

92%

137

91%

A2

148

91%

148

91%

63

92%

45

89%

A3

17

94%

17

94%

53

94%

35

91%

A4

52

98%

15

93%

45

93%

29

90%

A5

122

91%

122

91%

37

92%

37

92%

A6

22

95%

22

95%

49

90%

49

90%

B1

214

92%

177

90%

69

93%

53

91%

B2

148

91%

148

91%

63

92%

45

89%

B3

219

98%

219

98%

77

99%

77

99%

C1

230

43%

230

43%

432

42%

432

42%

C2

207

40%

207

40%

385

37%

385

37%

C3

1,207

31%

1,200

31%

2,296

30%

2,279

30%

C4

1,410

41%

1,410

41%

2,710

40%

2,692

40%

C5

1,434

42%

1,397

40%

2,665

40%

2,649

39%

D1

444

47%

414

43%

772

42%

762

41%

D2

341

41%

341

41%

654

41%

643

40%

D3

261

47%

257

46%

475

44%

473

44%

E3

166

58%

136

49%

237

53%

226

50%

E4

283

46%

283

46%

511

42%

511

42%

F1

213

48%

206

47%

383

45%

381

44%

F2

248

50%

248

50%

459

48%

456

48%

F3

148

54%

125

46%

204

47%

192

44%

F4

184

39%

184

39%

333

34%

333

34%

H3

342

28%

342

28%

671

29%

657

27%

H4

450

34%

450

34%

877

35%

877

35%

I1

394

30%

387

28%

718

26%

712

25%

I2

253

40%

253

40%

459

37%

453

36%

I3

204

39%

204

39%

386

37%

386

37%

I4

397

29%

397

29%

784

30%

770

29%

J5

76

22%

76

22%

157

25%

157

25%

J6

83

25%

83

25%

162

25%

162

25%

K1

225

46%

218

44%

430

46%

428

45%

K2

253

49%

253

49%

491

49%

488

49%

L1

238

48%

231

47%

448

46%

446

46%

L2

249

48%

249

48%

498

50%

495

49%

M3

1,378

36%

1,378

36%

3,232

33%

3,232

33%

M4

774

36%

774

36%

1,824

33%

1,824

33%


5.6.16   Noise models for the off-site traffic noise impact assessment have been established using computer simulation software RoadNoise 2000.

5.6.17   Table 5-19 and Table 5-20 summarise the predicted traffic noise levels at NSRs for the “with project” and “without project” scenarios during both AM peak and PM peak off-site traffic of the Depot in year 2017.  As advised by MTRC, the anticipated completion of the whole development on Nam Cheong Station (NSR 8) would be no later than year of 2019.  Therefore, the planned residential development on Nam Cheong station shall not be taken into account for the off-site traffic noise prediction in year 2017.

Table 519      Predicted Noise Levels for “with project” and “without project” Scenarios during AM Peak Off-site Traffic of FEHD Depot (0700 – 0800) in Year 2017, L10,(1-hr)

NSR ID and Name

Noise Assessment Points

Floors

AM Peak Off-site Traffic of

FEHD Depot

Year 2017

Traffic Noise Contribution by FEHD Depot / dB(A)[1]

With Project

Without Project

NSR 1

Sir Ellis Kadoorie Secondary School (West Kowloon)

N101

1/F – 8/F

64.4 - 68.6

65.5 - 70.2

-1.6 ~ -0.8

N102

1/F – 8/F

60.4 - 64.7

60.7 - 64.9

-0.3 ~ -0.1

N103

1/F – 8/F

68.9 - 71.8

69.0 - 72.0

-0.2 ~ -0.1

NSR 2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

N201

1/F – 8/F

62.4 - 67.3

62.4 - 68.0

-0.7 ~ 0.0

N202

1/F – 8/F

54.4 - 58.5

54.4 - 58.5

0.0 ~ 0.0

N203

1/F – 8/F

69.9 - 72.1

70.0 - 72.2

-0.1 ~ 0.0

NSR 3

Hampton Place

N301

1/F – 48/F

64.0 - 71.1

64.6 - 71.2

-0.7 ~ -0.1

NSR 4

Nam Cheong Estate Block 6 Cheong Chit House

N401

1/F – 15/F

61.7 - 69.6

61.5 - 69.5

0.0 ~ 0.2

NSR 5

Nam Cheong Estate Block 5 Cheong Yat House

N501

1/F – 15/F

61.8 - 69.8

61.6 - 69.7

0.1 ~ 0.2

NSR 6

Nam Cheong Estate Block 4 Cheong Shun House

N601

1/F – 15/F

58.0 - 66.6

57.8 - 66.4

0.2 ~ 0.3

NSR 7

Fu Cheong Estate Fu Yun House

N701

1/F – 5/F

62.9 - 69.4

62.7 - 69.1

0.2 ~ 0.3

Note:

[1] This is the difference between the predicted traffic noise levels “with” and “without” the FEHD Depot project

 


Table 520      Predicted Noise Levels for “with project” and “without project” Scenarios during PM Peak Off-site Traffic of FEHD Depot (1500 – 1600) in Year 2017, L10,(1-hr)

NSR ID  and Name

Noise Assessment Points

Floors

PM Peak Off-site Traffic of

FEHD Depot

Year 2017

Traffic Noise Contribution by FEHD Depot / dB(A)[1]

With Project

Without Project

NSR 1

Sir Ellis Kadoorie Secondary School (West Kowloon)

N101

1/F – 8/F

67.3 - 71.5

68.3 - 73.0

-1.5 ~ -0.7

N102

1/F – 8/F

62.9 - 67.3

63.2 - 67.4

-0.3 ~ -0.1

N103

1/F – 8/F

71.9 - 74.8

71.9 - 75.0

-0.2 ~ 0.0

NSR 2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

N201

1/F – 8/F

65.4 - 70.2

65.4 - 71.0

-0.8 ~ 0.0

N202

1/F – 8/F

57.3 - 61.3

57.2 - 61.3

0.0 ~ 0.1

N203

1/F – 8/F

72.9 - 75.1

72.9 - 75.2

-0.1 ~ 0.0

NSR 3

Hampton Place

N301

1/F – 48/F

66.9 - 74.3

67.4 - 74.4

-0.6 ~ -0.1

NSR 4

Nam Cheong Estate Block 6 Cheong Chit House

N401

1/F – 15/F

64.4 - 72.2

64.3 - 72.1

0.0 ~ 0.1

NSR 5

Nam Cheong Estate Block 5 Cheong Yat House

N501

1/F – 15/F

64.5 - 72.4

64.4 - 72.3

0.0 ~ 0.1

NSR 6

Nam Cheong Estate Block 4 Cheong Shun House

N601

1/F – 15/F

60.6 - 69.1

60.5 - 69.0

0.0 ~ 0.1

NSR 7

Fu Cheong Estate Fu Yun House

N701

1/F – 5/F

65.6 - 71.7

65.5 - 71.6

0.1 ~ 0.1

Note:

[1] This is the difference between the predicted traffic noise levels “with” and “without” the FEHD Depot project

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


5.6.18   Table 5-21 and Table 5-22 summarise the predicted traffic noise levels at NSRs for the “with project” and “without project” scenarios during AM peak and PM off-site traffic of the Depot in year 2032. Noted that the planned NSR8 (Nam Cheong Station) has been included.

Table 521      Predicted Noise Levels for “with project” and “without project” Scenarios during AM Peak Off-site Traffic of FEHD Depot (0700 – 0800) in Year 2032, L10,(1-hr)

NSR ID and Name

Noise Assessment Points

Floors

AM Peak Off-site Traffic of

FEHD Depot

Year 2032

Traffic Noise Contribution by FEHD Depot / dB(A)[1]

With Project

Without Project

NSR 1

Sir Ellis Kadoorie Secondary School (West Kowloon)

N101

1/F – 8/F

65.0 - 69.2

66.1 - 70.9

-1.7 ~ -0.9

N102

1/F – 8/F

60.8 - 65.1

61.1 - 65.3

-0.3 ~ -0.2

N103

1/F – 8/F

69.6 - 72.4

69.7 - 72.7

-0.3 ~ -0.1

NSR 2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

N201

1/F – 8/F

63.1 - 67.9

63.1 - 68.7

-0.8 ~ 0.0

N202

1/F – 8/F

54.8 - 58.9

54.8 - 58.9

0.0 ~ 0.0

N203

1/F – 8/F

70.6 - 72.8

70.7 - 72.9

-0.1 ~ 0.0

NSR 3

Hampton Place

N301

1/F – 48/F

64.6 - 71.7

65.2 - 71.9

-0.7 ~ -0.1

NSR 4

Nam Cheong Estate Block 6 Cheong Chit House

N401

1/F – 15/F

62.3 - 70.0

62.1 - 69.9

0.0 ~ 0.2

NSR 5

Nam Cheong Estate Block 5 Cheong Yat House

N501

1/F – 15/F

62.2 - 70.2

62.0 - 70.1

0.1 ~ 0.2

NSR 6

Nam Cheong Estate Block 4 Cheong Shun House

N601

1/F – 15/F

60.5 - 67.2

60.4 - 67.1

0.1 ~ 0.3

NSR 7

Fu Cheong Estate Fu Yun House

N701

1/F – 5/F

62.3 - 69.9

62.2 - 69.6

0.1 ~ 0.3

NSR 8

Planned Residential Development on Nam Cheong Station

N801

1/F – 9/F

77.3 - 81.9

77.2 - 81.9

0.0 ~ 0.1

N802

1/F – 9/F

69.6 - 78.3

69.5 - 78.2

0.0 ~ 0.1

N803

1/F – 40/F

67.3 - 72.6

67.3 - 72.6

0.0 ~ 0.1

N804

1/F – 40/F

68.2 - 71.9

68 - 71.7

0.1 ~ 0.3

N805

1/F – 40/F

65.4 - 69.9

64.9 - 69.4

0.4 ~ 0.7

Note:

[1] This is the difference between the predicted traffic noise levels “with” and “without” the FEHD Depot project

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Table 522      Predicted Noise Levels for “with project” and “without project” Scenarios during PM Peak Off-site Traffic of FEHD Depot (1500 – 1600) in Year 2032, L10,(1-hr)

 

NSR ID  and Name

Noise Assessment Points

Floors

PM Peak Off-site Traffic of

FEHD Depot 

Year 2032

Traffic Noise Contribution by FEHD Depot / dB(A)[1]

With Project

Without Project

NSR 1

Sir Ellis Kadoorie Secondary School (West Kowloon)

N101

1/F – 8/F

68.0 - 72.1

68.9 - 73.6

-1.5 ~ -0.7

N102

1/F – 8/F

63.6 - 68.0

63.9 - 68.2

-0.3 ~ -0.1

N103

1/F – 8/F

72.5 - 75.4

72.5 - 75.6

-0.2 ~ 0.0

NSR 2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

N201

1/F – 8/F

66.0 - 70.9

66.0 - 71.6

-0.7 ~ 0.0

N202

1/F – 8/F

58.0 - 62.1

58.0 - 62.1

0.0 ~ 0.1

N203

1/F – 8/F

73.5 - 75.7

73.5 - 75.8

-0.1 ~ 0.0

NSR 3

Hampton Place

N301

1/F – 48/F

67.6 - 74.9

68.1 - 75.0

-0.6 ~ -0.1

NSR 4

Nam Cheong Estate Block 6 Cheong Chit House

N401

1/F – 15/F

64.9 - 72.5

64.8 - 72.5

0.0 ~ 0.1

NSR 5

Nam Cheong Estate Block 5 Cheong Yat House

N501

1/F – 15/F

64.8 - 72.7

64.8 - 72.7

0.0 ~ 0.1

NSR 6

Nam Cheong Estate Block 4 Cheong Shun House

N601

1/F – 15/F

63.3 - 69.7

63.3 - 69.7

0.0 ~ 0.1

NSR 7

Fu Cheong Estate Fu Yun House

N701

1/F – 5/F

64.9 - 72.2

64.9 - 72.1

0.0 ~ 0.1

NSR 8

Planned Residential Development on Nam Cheong Station

N801

1/F – 9/F

80.5 - 85.3

80.5 - 85.3

0.0 ~ 0.1

N802

1/F – 9/F

72.7 - 81.5

72.6 - 81.5

0.0 ~ 0.1

N803

1/F – 40/F

70.2 - 75.6

70.2 - 75.6

0.0 ~ 0.1

N804

1/F – 40/F

70.8 - 74.5

70.7 - 74.5

0.0 ~ 0.1

N805

1/F – 40/F

67.4 - 71.9

67.3 - 71.8

0.1 ~ 0.2

Note:

[1] This is the difference between the predicted traffic noise levels “with” and “without” the FEHD Depot project

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.6.19   As read from the predicted results in the year of 2017 as shown in Table 5-19 and Table 5-20, there is insignificant increase in noise contribution caused by the off-site traffic of FEHD Depot in the range of 0 – 0.3 dB(A) and 0 – 0.1 dB(A) during AM peak and PM peak respectively at Cheong Chit House (NSR 4), Cheong Yat House (NSR5), Cheong Shun House (NSR 6) and Fu Yun House (NSR 7).  On the other hand, it is suggested that the Depot could act as a substantial barrier benefits to noise reductions for the traffic noise in the range of -0.1 to -1.6 dB(A) and -0.1 to -1.5 dB(A)  during AM peak and PM peak respectively for Sir Ellis Kadoorie Secondary School (West Kowloon) (NSR1), Tai Kok Tsui Catholic Primary School (Hoi Fan Road) (NSR2) and Hampton Place (NSR3).

5.6.20   For the predicted results in the year of 2032 as shown in Table 5-21 and Table 5-22, insignificant increase in noise contribution could be concluded also caused by the off-site traffic of FEHD in the range of 0 – 0.7 dB(A) and 0 – 0.2 dB(A) during AM peak and PM peak respectively at Cheong Chit House (NSR 4), Cheong Yat House (NSR5), Cheong Shun House (NSR 6), Fu Yun House (NSR 7) and planned residential development on Nam Cheong station (NSR 8).  Similar to the case in year 2017, the Depot has brought environmental benefits in terms of useful noise reductions for the traffic noise in the range of -0.1 to -1.7 dB(A) and -0.1 to -1.5 dB(A)  during AM peak and PM peak for Sir Ellis Kadoorie Secondary School (West Kowloon) (NSR1), Tai Kok Tsui Catholic Primary School (Hoi Fan Road) (NSR2) and Hampton Place (NSR3).

5.6.21   The assessment results demonstrate that only insignificant off-site traffic noise level would be generated from the Depot, which are less than 1.0 dB(A) at all representative NSRs in both short-term period and in the long run.  Moreover, environmental benefits by the development of the Depot as a noise tolerate building fronting some of the NSRs could also contribute traffic noise reduction by up to 1.7dB(A).

 

5.7         Proposed Noise Mitigation Measures

Construction Phase

5.7.1     Mitigation measures are required for the NSRs at which unmitigated construction noise levels are predicted to exceed the corresponding construction noise criteria as shown in Section 5.2.5.

Available Construction Noise Mitigation Measures

5.7.2     A number of available construction noise mitigation measures have been considered in this assessment, including:

·           selection and optimization of construction programmes, avoidance of parallel operation of noisy PME, and/or reduction in the proportion of usage of PME during noise sensitive periods such as school examination period;

·           use of “quiet” PME and working methods;

·           use of temporary at-source noise mitigation measures such as noise barriers, noise enclosures, noise jacket and mufflers; and

·           use of good site practice to limit noise emission from construction site.

Selection and Programming of Construction Processes

5.7.3     The timing and sequencing of the various construction activities shall be carefully arranged according to the actual site work situation, in order to limit the amount of concurrent activities and where applicable, to avoid parallel operation of noisy PME in order to minimise the total noise generated during construction periods.  Limiting the quantity of PME to be operated concurrently and also their proportion of usage were recommended in the Project and incorporated in this assessment. The proposed quantity of PMEs and their proportion of usage have been confirmed feasible by the Project Engineer. In the case during school examination while more stringent construction noise criteria should be imposed, the potentially most disruptive construction activities should be avoided, and arranged to be conducted during school holidays as far as practicable.

Use of “Quiet” Alternative Plant and Working Methods

5.7.4     The use of particular plant with equipment noise levels quieter than those specified in the GW-TM can result in reduction of noise levels generated by the plant.  The level of noise reduction achieved is dependent on the contractor’s chosen methods of working.  It is possible for the contractor to achieve noise reductions from the adopted working methodologies by specifying maximum limits of sound power level for specific plant equipment.

5.7.5     “Quiet” plant is defined as a PME having actual Sound Power Levels (SWLs) lower than the values specified for PME in the GW-TM.  SWLs for typical PME provided in the GW-TM and that for equivalent “quiet” plants are presented in Table 5-23. 

5.7.6     The type of quiet PME adopted in this assessment is for reference only and to be confirmed by the contractors, in view of the actually construction conditions and programmes. The contractors are allowed to use other type of quiet PME, which have the equivalent total SWLs, to meet their needs.

Table 523      Maximum SWLs for Selected “Quiet” and Alternative Plants

Identification Code in GW-TM

Descriptions of PME

SWL in GW-TM, dB(A)

“quiet” PME example in QPME list [1]

SWL of “quiet” PME, dB(A)

CNP 081

Loader, wheeled (Back-hoe)

112

EPD-00946

104

CNP 081

Excavator, Tracked

112

EPD-01652

99

CNP 103

Generator

95

EPD-01593

89

CNP 048

Mobile Crane

112

EPD-01516

101

Note:

1.     QPME list available on the EPD website

 

Temporary Noise Barriers

5.7.7     Temporary noise barriers provide noise attenuation by screening NSRs from stationary and mobile plants from direct line-of-sight in shadow zone. The use of 3m high moveable barriers with skid footing and a small cantilevered upper portion can be located within 6m from stationary plants and about 5m from mobile plants such as back-hoe loader, tracked excavator. Whilst screening effects can be achieved at upper floors of NSRs, greater benefits result at lower floors where screening is the most effective. These temporary noise barriers will become more effective when located immediately adjacent to working area, and can reduce the noise level by up to 5 dB(A) and 10 dB(A) for mobile and stationary plants, respectively.  The temporary noise barriers could also be located along the working area in order to make sure that all construction plants could be screened during all kinds of construction activities.  Besides, there would be use of hand-held drill, jig saw, wire saws for finishes construction. Since the works would be within internal of concrete building envelope, noise reduction of 5 dB(A) is also considered to reflect the reality.

5.7.8     Depending on site situation, when temporary noise barriers are not practicable or noise reduction achieved is insufficient, noise jacket/muffler can be applied to cover the noisy part of the engine or at the engine exhaust of particular mobile plants respectively.  Applicable PME with temporary noise barrier include excavator, wheeled loader, mini-robot mounted breaker, concrete lorry mixer and concrete pump. It is assumed that temporary noise barriers of this type can provide partial screening effect of 5 dB(A) in the assessment.

5.7.9     The noise attenuation of 5dB(A) are considered achievable by careful selection of insulation material for temporary noise barrier, and, if necessary, acoustic mats at noisy mechanical parts of the equipment. Barrier material of surface density of at least 10 kg/m2 is recommended in order to achieve the necessary screening effect.

Good Site Practice

5.7.10   The use of good site practice/techniques can provide considerable reductions in noise emissions.  Examples of these site practice include:

·           use of well-maintained and regularly-serviced plant during the works;

·           plant operating on intermittent basis should be turned off or throttled down when not in active use;

·           plant that is known to emit noise strongly in one direction should be orientated to face away from the NSRs;

·           silencers, mufflers and enclosures for plant should be used where possible and maintained adequately throughout the works;

·           where possible fixed plants should be sited away from NSRs; and

·           stockpiles of excavated materials and other structures such as site buildings should be used effectively to screen noise from the works.

Operation Phase

Fixed Plant Noise - Workshop Vehicle Repair Activities

5.7.11   The future operator should ensure that the workshop vehicle repair activities should be carried out under the covered area of the Transport Workshop Section on the G/F (Appendix 5-5) as the building of FEHD Depot itself provide screening effect to the NSRs.

5.7.12   As the noise limit during nighttime period (2300 – 0700hrs next day) is more stringent than the daytime and evening time periods (0700 – 2300), the future operator should ensure that the workshop vehicle repair activities should not be carried out during nighttime period.

Fixed Plant Noise - MVAC and other Building Services Equipment

5.7.13   With reference to “Good practices on Ventilation System Noise Control (GP-VS)”, acoustic treatments, such as acoustic louvres, silencers, enclosures could be applied to achieve noise attenuation so that the SWL of the equipment shall not exceed the specified “maximum allowable SWL” in various plant rooms of the latest layout plan in Appendix 5-5.

Off-site Traffic Noise

5.7.14   In view of the results of noise predictions mentioned in Sections 5.6.19 to 5.6.21, the potential off-site noise impact due to on-site vehicular traffic and vehicular traffic would be insignificant. No mitigation measure is recommended for the off-site traffic noise.

 

5.8         Assessment of Noise Impacts with the Application of Mitigation Measures

Construction Phase

5.8.1     Construction noise calculations have been carried out with the incorporation of different noise mitigation measures as discussed in Section 5.7, as far as practicable according to the actual construction condition and limitation.  Mitigation measures adopted in this assessment include:

·           the use of quiet plants for PME (QPME);

·           temporary noise barriers for PME, as well as noise jacket and mufflers to cover the noisy part of PME and at the engine exhaust of mobile plants respectively;

·           limiting of number of plants operated concurrently.

5.8.2     Construction noise levels at the selected NSRs (which are predicted to be the worst affected by the associated construction works) under the mitigated scenario are summarized in Tables 5-24 and 5-25.  Detailed calculations of the construction noise impact assessment and complete PME inventory are provided in Appendix 5-11.

Table 524      Predicted Cumulative Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Mitigated Scenario

NSR ID

Descriptions

Land Use

Limit

Predicted Construction Noise Levels at each Assessment Year

(Leq, dB(A))

2014

2015

2016

N1

Sir Ellis Kadoorie Secondary School (West Kowloon)

Education Institute

65 [1]

63

64

64

N2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

Education Institute

65 [1]

59

60

60

N3

Hampton Place

Residential

75

55

56

56

N4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

75

60

60

59

N5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

75

59

59

59

N6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

75

58

59

59

N7

Fu Cheong Estate Fu Yun House

Education / Homes for the Aged

65 [1]

65

64

64

N8

Planned Residential Development on Nam Cheong Station

Residential

75

61

62

62

Note:

1.             Construction noise standard for schools is70 dB(A) at normal school days and is reduced to 65 dB(A) during examination period. The more conservative 65dB(A) standard is applied in this construction noise impact assessment.

 

 

 

Table 525      Predicted Construction Noise Levels at Selected NSRs during Normal Daytime Working Hours under the Mitigated Scenario due to the Project ONLY

NSR ID

Descriptions

Land Use

Limit

Predicted Construction Noise Levels at each Assessment Year

(Leq, dB(A))

2014

2015

2016

N1

Sir Ellis Kadoorie Secondary School (West Kowloon)

Education Institute

65 [1]

63

63

63

N2

Tai Kok Tsui Catholic Primary School (Hoi Fan Road)

Education Institute

65 [1]

58

59

59

N3

Hampton Place

Residential

75

54

55

55

N4

Nam Cheong Estate Block 6 Cheong Chit House

Residential

75

55

56

56

N5

Nam Cheong Estate Block 5 Cheong Yat House

Residential

75

55

56

56

N6

Nam Cheong Estate Block 4 Cheong Shun House

Residential

75

54

55

55

N7

Fu Cheong Estate Fu Yun House

Education / Homes for the Aged

65 [1]

54

55

55

N8

Planned Residential Development on Nam Cheong Station

Residential

75

61

62

62

Note:

1.             Construction noise standard for schools is 70dB(A) at normal school days and is reduced to 65 dB(A) during examination period. The more conservative 65dB(A) standard is applied in this construction noise impact assessment.

 

5.8.3     In view of the results listed on Tables 5-24 and 5-25, it can be noted that the predicted construction noise levels with noise mitigation measures at the NSRs shall comply with the corresponding construction noise limits.

5.8.4     It is noted that predicted construction noise levels at nearby educational institutions, such as Fu Cheong Estate Fu Yun House and Sir Ellis Kadoorie Secondary School complies with corresponding assessment criteria during normal school days, i.e. 70dB(A), but only marginally comply with the assessment criteria of examination period, i.e. 65dB(A). Although this predicted overall construction noise level has taken into account concurrent construction works in the vicinity and the contribution due to the Project itself is minimal with the implementation of mitigation measures, it is recommended that more detailed construction work programme should be considered before actual construction work is undertaken by the contractor, and applicable noise mitigation measures should be implemented according to the actual site condition and constraints, in order to minimise the potential cumulative construction noise impact with concurrent projects. In particular, the Contractor shall keep close liaison with the nearby educational institutions, and special arrangement on PME operations should be determined during school examination periods.

Operation Phase

Fixed Plant Noise

5.8.5     With the implementation of the mitigation measures for both workshop vehicle repair activities and MVAC installation discussed in Sections 5.7.11 to 5.7.13. The predicted maximum noise levels at the identified NSRs due to workshop vehicle repair activities and the MVAC installations are shown in Table 5-16 which would comply with both daytime and nighttime EIAO–TM noise criteria.

Off-site Traffic Noise

5.8.6     As noise mitigation measure is not necessary for the off-site traffic noise, there is no off-site traffic noise assessment result under mitigation measures.

 

5.9         Residual Impact

Construction Phase

5.9.1     With the implementation of the mitigation measures in form of utilising quieter plant and temporary noise barrier, predicted construction noise level at majority of the selected NSRs shall comply with the corresponding construction noise limits. Thus, there would be no adverse residual impact anticipated at nearby NSRs.

Operation Phase

5.9.2     With the implementation of the mitigation measures for both workshop vehicle repair activities and MVAC installation discussed in Sections 5.7.11 to 5.7.13. The predicted maximum noise levels at the identified NSRs due to workshop vehicle repair activities and the MVAC installations would comply with both daytime and nighttime EIAO–TM noise criteria.  Therefore, there would be no residual impact at the NSRs due to the fixed plant noise sources.

5.9.3     As discussed in Sections 5.6.19 to 5.6.21, potential traffic noise impact generated by the future operation of the Depot is predicted to be insignificant.  There would be no adverse residual impact anticipated at nearby NSRs due to the off-site traffic noise.

 

5.10      Environmental Monitoring and Audit

Construction Phase

5.10.1   The assessment has concluded that, with the implementation of mitigation measures in form of utilising quieter plant, limiting the number of construction plants operating concurrently, temporary noise barrier, noise jackets and mufflers, no adverse residual construction impact would be anticipated.

5.10.2   Environmental monitoring and audit measures are recommended during the construction phase of the Project to ensure adverse impacts do not occur. An appropriate path for noise complaints handling procedures is a key element of the EM&A programme.  Detailed implementation schedules of all mitigation measures are also provided in the EM&A Manual.

Operation Phase

5.10.3   Noise monitoring during the operation phase of this is considered not necessary as the proposed Depot would not be expected to impose significant noise impact to adjacent identified NSRs with the implementation of the recommended mitigation measures.

 

5.11      Conclusions

Construction Phase

5.11.1   With the implementation of the recommended mitigation measures such as the use of QPME employed in the works, temporary noise barriers, noise jackets, mufflers, and limiting the number of plants operated concurrently, adverse construction noise impact is not anticipated. It is recommended that more detailed construction work programme should be considered before actual construction work is undertaken by the contractor, and applicable noise mitigation measures should be implemented according to the actual site condition and constraints, in order to minimise the potential cumulative construction noise impact with concurrent projects. In particular, the Contractor shall keep close liaison with the nearby educational institutions, and special arrangement on PME operations should be determined during school examination periods.

5.11.2   Environmental monitoring and auditing procedures are also recommended in EM&A manual to ensure the implementation of construction noise mitigation measures as well as to establish an appropriate path for noise complaints handling. Regardless of the results of construction noise impact assessment for restricted hours, the Noise Control Authority will process Construction Noise Permit (CNP) application, if necessary, based on the NCO, the relevant technical memoranda issued under NCO, and the contemporary conditions/situations.

Operation Phase

Fixed Plant Noise

5.11.3   With the implementation of the mitigation measures for both workshop vehicle repair activities and MVAC installation such as workshop vehicle repair activities to be carried out under the covered area to be operated during daytime and evening periods only and acoustic treatments, such as acoustic silencers, acoustic louvres to be applied to the MVAC installations in order to achieve the specified maximum allowable SWL. Adverse impact to the NSRs due to the fixed plant noise would not be anticipated during operation phase.

Off-site Traffic Noise

5.11.4   Based on the insignificant off-site traffic generation and routings for the Project development, the assessment results demonstrate that the operation of the FEHD Depot would introduce insignificant traffic noise impact less than 1.0 dB(A) to all representative NSRs for short-term period and in the long run.

5.11.5   Moreover, environmental benefits by the development of Depot as a noise tolerate building fronting some of the NSRs could also contribute traffic noise reduction by up to 1.7 dB(A).