Chapter 9 – Summary of Environmental Outcomes
CONTENTS
9. Summary of Environmental Outcomes
9.2 Summary of Measures Adopted to Minimize
Environmental Impacts
List of Tables
Table 9‑1 Summary
of Key Environmental Outcomes
Table 9‑2 Summary
of Measures Adopted to Minimize Environmental Impacts
9.1.1
This EIA study predicted that, with the implementation of the
recommended mitigation measures, the Project would be environmentally
acceptable with no adverse residual impacts on the population and
environmentally sensitive resources.
Table 9‑1 summarises
the environmental outcomes and benefits that accrued from the environmental
considerations and analysis during the EIA process and the implementation of
environmental control measures of the Project. The requirements for the EM&A
programme have been recommended, where necessary, to check for the compliance
with environmental legislation and standards.
Table 9‑1 Summary
of Key Environmental Outcomes
Area / Issue |
Environmental
Outcomes and Mitigation Measures |
The Project |
Based on
the preferred option of the facilities, the proposed offices-cum-vehicle
depot will be constructed in the form of a five-storey building occupying a
site area of approximately 8,278m2. The lowest three floors will provide
vehicle maintenance facilities, vehicle washing facilities for carrying out
general vehicle repair and washing activities as well as providing parking
spaces for the FEHD vehicle fleet.
Offices and stores will be mainly located on the higher floors, with
green roof design providing substantial landscape features. The
offices-cum-depot would mainly include the following: ·
Parking
spaces (about 140 nos.); ·
Covered
vehicle maintenance workshop including 3 vehicle repair bays; ·
Covered
vehicle washing facilities including an automatic vehicle washing bay and 2
manual vehicle washing bays; ·
Storage
rooms; ·
Offices; ·
Special
ancillary facilities, including underground waste lubrication oil tank; underground
oil interceptor; scrap metal yard; dangerous goods (DGs) store; ·
Associated
plant rooms; and ·
Toilets
and shower rooms. |
Environmentally Friendly
Design Recommended |
Building Design To minimise the potential environmental
impacts, in particular on noise and air quality perspectives, non-open
building form was recommended for vehicle repairing and washing activities,
which are now to be located at ground floor and refined and covered by the
above floors. Facilities Layout Layout design was investigated in details in
order to strike the balance between operational needs, as well as catering
environmental considerations.
Activities with potential environmental implication / nuisance were located
in a confined manner as possible. Vehicle repairing bays and workshop is
recommended to be covered at ground floor, surrounded by storerooms for noise
screening and buffering purpose as possible. In addition, solid partition wall is
proposed to the manual vehicle washing bays to entirely isolate from the
pedestrian from potential nuisance. Moreover, to enhance the visual quality of
the Depot, substantial greenery features were considered, including vertical
green walls and green roofing. Ventilation and Local Exhaust Design A vast amount of openings are proposed at
the building façade to optimise the use of natural ventilation at the car
parking area at lower floors.
Mechanical ventilation is only designed for standby forced ventilation
system. As a result of rare usage
of the associated substantial mechanical ventilation system, potential noise
nuisance from this fixed plant system could be minimised. On the other hand, for those activities with
potential environmental nuisance including vehicle repairing activities at the
workshop and vehicle washing, controlled mechanical ventilation with
sufficient forced air changes is desired, rather than merely relying on
natural ventilation. In addition,
ventilated exhaust is to be treated prior to discharging to the
atmosphere. Various gas
treatments were evaluated and the most appropriate technology with proven
removal efficiency (eg. activated carbon filter, bio-oxygen generator,
chemical scrubber) will be applied.
Location and orientation of the local exhaust were carefully examined
to ensure sufficient dispersion and to avoid direct impact to the nearby
receivers. Construction Method Construction of the depot would involve
various typical work stages and conventional building services works. As such, consideration of beneficial
construction method is focused on the design of the foundation works. According to the ground condition of
the Site, two foundation types, namely driven steel-H piling (percussive) and
bored piling (non-percussive) are considered to be technically viable for the
Project. With various factors
including environmental benefits, programming, engineering feasibility,
cost-effectiveness, etc, driven steel H-pile is thus recommended. Traffic Routings At the early stage of the Project, incoming
and outbounding traffic routings were developed based
on ease and need of operation.
During project development and public engagement, local concerns on
the proposed traffic routings were received and thus modification to the
routings were considered necessary requiring substantial changes in order to
address the concerns. |
Population and
Environmentally Sensitive Areas Protected |
With the adoption of the environmentally
friendly design in the preferred option, the major environmental sensitive
receivers will be protected. This preferred option is determined
based on the comparison of the environmental benefits and dis-benefits of the
various options and alternatives and has been selected on the basis that it
minimises environmental impacts and presents overall environmental benefits
over the other options and is considered the optimum scheme from an
environmental perspective. |
Air Quality |
Air quality impact and odour analysis have
been conducted for the construction and operation of the Depot. For the construction aspect, there would be
no major earthworks carried out for the site formation works for the Project
site. With the implementation of
sufficient dust suppression measures as stipulated under the Air Pollution
Control (Construction Dust) Regulation, adverse construction dust impact
would not be anticipated. For the operation of the Depot, no adverse
air quality impact would be anticipated as there would be limited vehicular
emissions from the repairing and parking activities of the Project, considered with cumulative
effect of emissions from open roads networks within the Study Area (500m from
Project boundary). Results show
that the predicted maximum 1-hour, daily and annual average NO2
and maximum daily and annual average RSP concentrations at the representative
ASRs and within the Study Area would comply with the AQOs. No mitigation measures are required.
Lastly, taking into account the fact that
potential odour emission and minimal spread in the Depot to be localised only
in the washing bay, together with the provision of mechanical ventilation
adopting with proper installation and maintenance of deodourisation system,
as well as the dilution along considerable buffer distance between the Depot
to the adjacent ASRs, potential odour nuisance associated with the operation
of the Depot is anticipated to be negligible. |
Noise |
Noise impact assessment has
been conducted for the construction and operation of the Depot. Regarding construction phase, with the
implementation of the recommended mitigation measures such as the use of QPME
employed in the works, temporary noise barriers, noise jackets, mufflers, and
limiting the number of plants operated concurrently, adverse construction
noise impact is not anticipated. Concerning fixed plant noise during
operation, with the implementation of the mitigation measures for both
workshop vehicle repair activities and MVAC installation to be carried out
under the covered area to be operated during daytime and evening periods only
and acoustic treatments, such as acoustic silencers, acoustic louvres to be
applied to the MVAC installations in order to achieve the specified maximum
allowable SWL, adverse impact to the NSRs due to the fixed plant noise would
not be anticipated during operation phase. For off-site traffic noise, based on the
insignificant off-site traffic generation and routings for the Project
development, the assessment results demonstrate that the operation of the
FEHD Depot would introduce insignificant traffic noise impact less than 1.0
dB(A) on all representative NSRs for short-term and in the long run. |
Water Quality |
Potential water pollution sources have been
identified as construction site run-off, sewage from workforce, and potential
risk of chemical spillage.
Mitigation measures including the implementation of the construction
site practices in accordance with the EPD’s ProPECC PN 1/94 Construction Site
Drainage, provision and management of portable toilets on-site, and
preventive measures to avoid accidental chemical spillages are recommended to
mitigate any adverse water quality impacts, based on which adverse residual
impacts would not be anticipated.
Furthermore, there would be insignificant sewerage and sewage
treatment implications during the operation of this Project, and adverse
water quality impact would not be anticipated with the implementation of the
recommended mitigation measures based on the findings of this EIA study. |
Waste Management Implication and Land Contamination |
The waste streams that would be generated
during the construction phase of the Project were identified and evaluated in
terms of their quantity, type and nature etc. Opportunities for minimising
waste generation via on-site sorting and reusing excavated fill materials are
identified. Preventive measures have been recommended for the Contractor to
implement during the construction phase to address any potential
environmental impacts. The waste streams that would be generated
during the operation phase of the Project were also identified and
evaluated. Measures to ensure
proper treatment and disposal of these wastes have been made. With regard to the historical land uses and
current site condition, there was no sign of land contamination due to the
past and current activities at the Site.
For the future operation, as the Site will be paved and good practice
for storage and handling of limited DGs, chemicals and chemical wastes will
be followed, leakage of contaminants causing quantifiable adverse land
contamination impacts would therefore not be anticipated. Provided that the recommendations set out
are implemented, unacceptable environmental impacts would not be expected to
arise from the handling, storage, transportation and disposal of wastes and
chemicals during both the construction and operation of the Project. |
Landscape and Visual |
With the implementation of mitigation measures
such as control of construction activities and temporary landscape treatment
during construction phase, the proposed Depot will inevitably result in some
landscape impact but no adverse visual impact during the
construction phase. On the
contrary, ground floor planting, vertical greening and roof gardens will be
provided for the proposed Depot during operation phase. Both landscape and
visual impact would become negligible in Year 10 when the mitigation measures
are already established. Comparing with the original setting of the Site
before the proposed Project where undesirable and weedy species are located
at the Site, the overall landscape character and visual quality of the Site
would be improved, with the provision of landscape design including ground
floor planting at pedestrian zone, vertical greening and roof gardens for the
proposed Depot. According to
Annex 10 of EIAO-TM, the landscape and visual character of the Site have been
complemented and therefore landscape and visual impact arising from the
proposed Depot is considered as beneficial. |
9.2
Summary of Measures Adopted to
Minimize Environmental Impacts
9.2.1
The various chapters and appendices of this EIA Report have presented
the measures to minimize pollution in the planning, design, construction and
operation stages. The key measures
to minimize pollution are summarized below in Table 9‑2 for easy reference and they are
not exhaustive. For details, please refer to the relevant chapters and
appendices as appropriate.
Table 9‑2 Summary
of Measures Adopted to Minimize Environmental Impacts
Area / Issue |
Measures
Adopted to Minimize Environmental Impacts |
Alternatives Adopted and Environmentally Friendly Design Recommended |
·
Siting
– The proposed Site locates adjacent to the CLP Tai Kok Tsui Substation,
which provides screening acoustic effect to the nearby noise sensitive
receivers of schools. ·
Building
Design – Non-open form is adopted to minimize potential noise and air quality
nuisance. ·
Layout
– Repairing activities are to be located at ground floor surrounded by
storerooms for noise screening and buffering purpose and solid partition wall
is proposed to manual washing bays to entirely isolate the pedestrian from
potential nuisance. Substantial
greenery features are proposed to roof area to enhance visual quality. ·
Ventilation
– Mechanical ventilation is only designed for standby forced ventilation,
such that potential noise nuisance from fixed plant is minimized. Adequate ventilation equipped with
odour removal treatment for areas of repairing workshops and vehicle washing
is to be provided to minimize potential odour nuisance. ·
Exhaust
Location – Location and orientation of local exhaust were carefully examined
to ensure sufficient dispersion and to avoid direct impact to nearby
receivers. ·
Traffic
Routing of Vehicle Fleets – Alternative traffic routes were examined and
adopted to avoid utilizing those public concerned junctions and roads to
minimize potential air quality and noise impacts. |
Air Quality |
·
Construction
– Sufficient dust suppression measures and good site practices are to be
adopted to minimize potential dust impact by construction activities. ·
Operation
– Adequately designed ventilation system equipped with odour removal
facilities are to be provided for repairing and vehicle washing bays to
minimize potential odour nuisance to the environ. |
Noise |
·
Construction
– A number of available construction noise mitigation measures are to be
adopted to minimize construction noise, including: ·
selection
and optimization of construction programmes, avoidance of parallel operation
of noisy PME, and/or reduction in the proportion of usage of PME during noise
sensitive periods such as school examination period; ·
use
of “quiet” PME and working methods; ·
use
of temporary at-source noise mitigation measures such as noise barriers,
noise enclosures, noise jacket and mufflers; and ·
use
of good site practice to limit noise emission from construction site. ·
Operation
– Acoustic treatment such as acoustic louvres, scilencers and enclosures
would be applied to various noisy plants. Furthermore, major noisy repairing
activities are to be carried out in covered workshops and limited in
nighttime period to minimize fixed plant noise during operation. |
Water Quality |
·
Construction
– General good site practice, such as perimeter drains, silt removal
facilities, construction programming, dusty stockpiling covering, is to be
implemented to minimize potential water quality impact during construction
phase. ·
Operation
– Proper sewer connections are to be provided to collect and divert sewage
generated from Depot operation. Adequately designed petrol interceptors and
sedimentation tanks will be provided to oily and silty wastewater polluting
water system. |
Waste Management Implication and Land Contamination |
·
Construction
– Typical good site practices are to be adopted to minimize generation of
C&D waste and chemical spillage. ·
Operation
– The Depot covering vehicle washing bays, maintenance workshop and storage
areas for DGs, chemicals and wastes are to be impervious and properly paved
by concrete. Adequate drainage management system including oil interceptor is
to be provided. Emergency procedures
for accidental spillage of chemicals are to be formulated and regularly
reviewed and trials, to minimize chance of contaminating land / soil. |
Landscape and Visual |
·
Construction
– Control of construction activities and temporary landscape treatment, such
as applying hoardings, are to be implemented to minimize impact by
construction activities. ·
Operation
– In order to enhance the landscape and visual quality, substantial greenery features
are to be provided for the building, including green roof garden, vertical
greening and various hard landscape features. |
Environmental Monitoring and Auditing
9.2.2
In addition to the mitigation measures as described above (see more
details in the Implementation Schedule in Chapter
12), environmental monitoring and auditing programme would be implemented
to cover various aspects of concern. An Independent Environmental Checker would
also be employed to ensure that all the necessary mitigation measures are
implemented in a timely and orderly manner.
Overall
9.2.3
Mitigation measures and good site practices to minimize the
environmental impacts were recommended throughout the impact assessments of air
quality, noise, water quality, waste management, land contamination and
landscape and visual. These
measures were consolidated in Chapter 12
Implementation Schedule which specifies the responsibility, methodology and
timing of implementation, such that effective and appropriate implementation of
the measures can be assured.