Description: hyd_logo

Highways Department                  路政署

Major Works Project Management office        主要工程管理處

 

Agreement No. CE44/2011 (HY)

Proposed Road Improvement Works in West Kowloon Reclamation Development – Phase 1 – Investigation, Design and Construction

 

Description: Picture for report cover

 

Environmental Impact Assessment Report

Volume 1 of 4 – Text

(September 2013)

 

Description: PB%20logo_blue


 

Environmental Impact Assessment REPORT (september 2013)

 

CONTENTS

                                                                                                                                              Page

1.                INTRODUCTION                                                                                                               1

1.1               Background                                                                                                                     1

1.2               This Assignment                                                                                                               2

 

2.                GENERAL                                                                                                                        4

2.1               Needs for the Project                                                                                                        4

2.2               Consideration of Alternative Alignment, Alternative Construction Method and Selection of Preferred Scenario                                                                                                                                       5

2.3               Concurrent Projects                                                                                                          7

2.4               Designated Project                                                                                                           7

2.5               EIA Study Brief                                                                                                                8

2.6               Objectives of the EIA Study                                                                                              8

2.7               Structure of EIA Report                                                                                                     9

 

3.                AIR QUALITY IMPACT                                                                                                   10

3.1               Introduction                                                                                                                    10

3.2               Environmental Legislation, Standards and Guidelines                                                       10

3.3               Description of Environment                                                                                             11

3.4               Air Sensitive Receivers                                                                                                    11

3.5               Potential Sources of Impact                                                                                            14

3.6               Identification of Representative Air Pollutants                                                                   15

3.7               Assessment Methodology                                                                                               16

3.8               Prediction and Evaluation of Environmental Impacts                                                         26

3.9               Mitigation of Adverse Environmental Impacts                                                                   33

3.10             Environmental Monitoring and Audit Requirements                                                           34

3.11             Conclusion                                                                                                                     34

 

4.                NOISE IMPACT                                                                                                              35

4.1               Introduction                                                                                                                    35

4.2               Environmental Legislation, Standards and Guidelines                                                       35

4.3               Description of Environment                                                                                             37

4.4               Project Road Sections Identification                                                                                37

4.5               Noise Sensitive Receivers                                                                                               39

4.6               Assessment Methodology                                                                                               41

4.7               Identification of Environmental Impacts                                                                            44

4.8               Prediction and Evaluation of Environmental Impacts                                                         44

4.9               Noise Mitigation Measures                                                                                              46

4.10             Evaluation of Residual Impacts                                                                                       49

4.11             Environmental Monitoring and Audit Requirements                                                           50

4.12             Conclusion                                                                                                                     50

 

5.                WATER QUALITY IMPACT                                                                                             52

5.1               Introduction                                                                                                                    52

5.2               Environmental Legislation, Standards and Guidelines                                                       52

5.3               Proposed Assessment Area                                                                                            54

5.4               Identification of Water Sensitive Receivers                                                                       55

5.5               Assessment Methodology                                                                                               55

5.6               Existing Conditions                                                                                                         56


 

5.7               Identification of Potential Impact                                                                                     58

5.8               Recommended Water Quality Mitigation Measures                                                            61

5.9               Conclusion                                                                                                                     64

 

6.                WASTE MANAGEMENT                                                                                                 65

6.1               Introduction                                                                                                                    65

6.2               Environmental Legislation                                                                                                65

6.3               Environmental Guidelines                                                                                                66

6.4               Assessment Approach and Methodology                                                                         67

6.5               Mitigation of Adverse Environmental Impact                                                                     75

6.6               Conclusion                                                                                                                     88

 

7.                LANDSCAPE AND VISUAL IMPACT                                                                               89

7.1               Introduction                                                                                                                    89

7.2               Relevant Environmental Legislation, Standards and Guidelines                                          89

7.3               Proposed Assessment Area                                                                                            89

7.4               Proposed Assessment Methodology                                                                               90

7.5               General Approaches to Mitigate Predicted Landscape and Visual Impact                           93

7.6               Review of Planning and Development Framework Guideline                                              94

7.7               Cumulative Impact                                                                                                          94

7.8               Existing Baseline Conditions                                                                                           95

7.9               Landscape Assessment                                                                                                101

7.10             Visual Assessment                                                                                                        117

7.11             Conclusion                                                                                                                   137

 

8.                SUMMARY OF ENVIRONMENTAL OUTCOMES                                                             139

8.1               Introduction                                                                                                                  139

8.2               Approaches Adopted to Minimize Environmental Impact                                                 139

8.3               Approaches Adopted to Mitigate Environmental Impacts                                                140

8.4               Air Quality Impact                                                                                                          140

8.5               Noise Impact                                                                                                                141

8.6               Water Quality Impact                                                                                                     142

8.7               Waste Management                                                                                                       143

8.8               Landscape and Visual Impact                                                                                        143

 

9.                ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS                                    145

9.1               Introduction                                                                                                                  145

9.2               Air Quality                                                                                                                     145

9.3               Noise                                                                                                                           145

9.4               Water Quality                                                                                                                145

9.5               Waste Management                                                                                                       146

9.6               Landscape and Visual                                                                                                   146

 

10.                    CONCLUSION                                                                                                                                                   147

10.1             General                                                                                                                         147

10.2             Air Quality Impact                                                                                                          147

10.3             Noise Impact                                                                                                                147

10.4             Water Quality Impact                                                                                                     148

10.5             Waste Management                                                                                                       148

10.6             Landscape and Visual Impact                                                                                        148

10.7             Environmental Monitoring and Audit Requirements                                                          148

10.8             Overall                                                                                                                          149


 

TABLES

 

Table 2.1         Concurrent Projects Anticipated During Construction Phase

Table 3.1         Hong Kong Air Quality Objectives

Table 3.2         Representative Air Sensitive Receivers

Table 3.3         Emission Factors for Dusty Construction Activities

Table 3.4         Air Quality Monitoring Results for XRL Project

Table 3.5         16 Vehicle Classes Considered in the EMFAC-HK Model

Table 3.6         Different Road Types for EMFAC-HK Model

Table 3.7         Summary of 2010 Hong Kong Emission Inventory for the PATH model

Table 3.8         Summary of 2015 Hong Kong Emission Inventory for the PATH model

Table 3.9         Summary of 2020 Hong Kong Emission Inventory for the PATH model

Table 3.10       Summary of Wind Standard Deviation Adopted in the Model

Table 3.11       Predicted Cumulative Maximum Hourly, Daily and Annual Construction Dust Concentrations at Various Heights above ASRs for Year 2014

Table 3.12       Predicted Cumulative Maximum Hourly, Daily and Annual Construction Dust Concentrations at Various Heights above ASRs for Year 2015

Table 3.13       Predicted Cumulative Maximum Hourly, Daily and Annual Average Air Pollutants Concentrations at Representative ASRs for Worst-case Scenario (Year 2016)

Table 3.14       Summary Breakdown of Predicted Cumulative NO2 Concentrations for ASRs with Potential Exceedance

Table 4.1         Construction Noise Standards During Non-Restricted Hours

Table 4.2         Construction Noise Standards During Restricted Hours

Table 4.3        Area Sensitivity Ratings (ASRs)

Table 4.4         Road Types of the Project Roads

Table 4.5         Representative Noise Sensitive Receivers

Table 4.6         Concurrent Projects Considered During the Construction Phase

Table 4.7         Unmitigated Construction Noise Impact, dB(A)

Table 4.8         Unmitigated Road Traffic Noise Level (DP Roads), dB(A)

Table 4.11       Mitigated Cumulative Construction Noise Level

Table 4.12       Adverse Residual Noise Impacts During Examination Period for Year 2014 and Year 2015

Table 5.1         Summary of Water Quality Objectives for Victoria Harbour (Phase 2) WCZ

Table 5.2         Summary of Water Quality criteria for WSD intake

Table 5.3         Baseline Marine Water Quality Condition for Victoria Harbour WCZ

Table 5.4         Marine Water Quality Condition for Yau Ma Tei Salt Water Pumping Station

Table 5.5         Comparison of Monitored Salt Water Quality Data against WSD Criteria

Table 6.1         Identification of Waste Types and sources during Construction Phase of the Project

Table 6.2         Annual Generation of C&D Materials

Table 6.3         Summary of Waste Handling Methods and Disposal Routes

Table 7.1        Significance Thresholds

Table 7.2        Summary of Magnitude of Change of Landscape Resources and Landscape Character Areas

Table 7.3        Summary of Sensitivity of Landscape Resources and Landscape Character Areas

Table 7.4        Summary of the Assessment of Landscape Resources and Landscape Character Areas

Table 7.5        Description of VSRs around Scheme H, I, and J

Table 7.6        Magnitude of Change for the identified VSRs for Scheme H, I, and J

Table 7.7        Summary of the Deciding Factors of Sensitivity for Scheme H, I, and J

Table 7.8        Description of VSRs around Interim Scheme Q and Road Junction Improvement Works

Table 7.9        Magnitude of Change for the identified VSRs for Interim Scheme Q and Road Junction Improvement Works

Table 7.10      Summary of the Deciding Factors of Sensitivity for Interim Scheme Q and Road Junction Improvement Works

Table 7.11      Summary of Visual Impact Assessment for Scheme H, I and J

Table 7.12      Summary of Visual Impact Assessment for Interim Scheme Q and Road Junction Improvement Works

 

 


 

FIGURES

 

Figure No.          Title

1.1                        Proposed Road Improvement Works in West Kowloon Reclamation Development Phase 1

1.1A                     Concurrent Projects by others

1.2                        Scheme H(A) General Layout Plan

1.3                        Scheme H(B) & I General Layout Plan

1.4                        Scheme J General Layout Plan

1.5                        Interim Scheme Q General Layout Plan

2.1                        Traffic Routes With and Without Scheme H(A) and H(B)

2.2                        Traffic Routes With and Without Scheme I

2.3                        Traffic Routes With and Without Scheme J

3.1                        Work Boundary and 500m Study Area for Air Quality Assessment

3.2                        Location of Air Sensitive Receivers (Page 1 of 2)

3.3                        Location of Air Sensitive Receivers (Page 2 of 2)

3.4                        Location of Marine Emissions

3.5                        Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 1 of 2)

3.6                        Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 2 of 2)

3.7                        Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 1 of 2)

3.8                        Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 2 of 2)

3.9                        Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 1 of 2)

3.10                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2014 (Unmitigated) (Page 2 of 2)

3.11                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 1 of 2)

3.12                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 2 of 2)

3.13                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 1 of 2)

3.14                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 2 of 2)

3.15                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 1 of 2)

3.16                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2015 (Unmitigated) (Page 2 of 2)

3.17                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 1 of 2)

3.18                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 2 of 2)

3.19                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 1 of 2)

3.20                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 2 of 2)

3.21                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 1 of 2)

3.22                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2014 (Mitigated) (Page 2 of 2)

3.23                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 1 of 2)

3.24                      Contour of 1 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 2 of 2)

3.25                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 1 of 2)

3.26                      Contour of 24 hour TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 2 of 2)

3.27                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 1 of 2)

3.28                      Contour of Annual TSP Concentration (with background) at 1.5m above ground of Year 2015 (Mitigated) (Page 2 of 2)

3.29                      Contour of Maximum 1hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.30                      Contour of Maximum 1hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.31                      Contour of Maximum 24hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.32                      Contour of Maximum 24hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.33                      Contour of Annual NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.34                      Contour of Annual NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.35                      Contour of Maximum 24hour RSP Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.36                      Contour of Maximum 24hour RSP Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.37                      Contour of Annual RSP Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.38                      Contour of Annual RSP Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.39                      Contour of Fourth Maximum 1hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.40                      Contour of Fourth Maximum 1hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.41                      Contour of Second Maximum 24hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 1 of 2)

3.42                      Contour of Second Maximum 24hour NO2 Concentration (with background) at 1.5m above ground of Year 2016 (Page 2 of 2)

3.43                      Contour of Second Maximum 24hour NO2 Concentration (with background) at 4m above ground of Year 2016 (Page 1 of 2)

3.44                      Contour of Second Maximum 24hour NO2 Concentration (with background) at 4m above ground of Year 2016 (Page 2 of 2)

3.45                      Contour of Annual NO2 Concentration (with background) at 4m above ground of Year 2016 (Page 1 of 2)

3.46                      Contour of Annual NO2 Concentration (with background) at 4m above ground of Year 2016 (Page 2 of 2)

4.1                        Work Boundary and 300m Study Area for Noise Impact Assessment

4.2                        Location of Noise Sensitive Receivers (Page 1 of 2)

4.3                        Location of Noise Sensitive Receivers (Page 2 of 2)

4.4                        Location of Construction Sites (Page 1 of 2)

4.5                        Location of Construction Sites (Page 2 of 2)

4.6                        Extent of Low Noise Road Surface on the Existing and Planned Roads

5.1                        Environment Impact Assessment Location of Water Quality Sensitive Receivers

5.2                        Location Plan for the EPD Monitoring Station

7.1                        Planning Development Framework of Scheme H, I, J and Q

7.2                        Landscape Resources at Scheme H, I, J and Q

7.3                        Landscape Character Areas at Scheme H, I, J and Q

7.4                        Location of Representative Visual Sensitive Receivers

7.51                      Broad Brush Tree Survey Plan (Sheet 1 of 5)

7.52                      Broad Brush Tree Survey Plan (Sheet 2 of 5)

7.53                      Broad Brush Tree Survey Plan (Sheet 3 of 5)

7.54                      Broad Brush Tree Survey Plan (Sheet 4 of 5)

7.55                      Broad Brush Tree Survey Plan (Sheet 5 of 5)

7.5a                      Scheme H(A) Existing Tree Survey Plan (Sheet 1 of 3)

7.5b                      Scheme H(A) Existing Tree Survey Plan (Sheet 2 of 3)

7.5c                     Scheme H(A) Existing Tree Survey Plan (Sheet 3 of 3)

7.5d                    Scheme H(B) & I Existing Tree Survey Plan

7.5e                     Scheme J Existing Tree Survey Plan

7.5f                     Interim Scheme Q Existing Tree Survey Plan (Sheet 1 of 2)

7.5g                     Interim Scheme Q Existing Tree Survey Plan (Sheet 2 of 2)

7.6a                     Tree Compensation Plan (Sheet 1 of 9)

7.6b                     Tree Compensation Plan (Sheet 2 of 9)

7.6c                     Tree Compensation Plan (Sheet 3 of 9)

7.6d                    Tree Compensation Plan (Sheet 4 of 9)

7.6e                     Tree Compensation Plan (Sheet 5 of 9)

7.6f                     Tree Compensation Plan (Sheet 6 of 9)

7.6g                     Tree Compensation Plan (Sheet 7 of 9)

7.6h                     Tree Compensation Plan (Sheet 8 of 9)

7.6i                      Tree Compensation Plan (Sheet 9 of 9)

7.71                      Tree and Landscape Plan (Sheet 1 of 8)

7.72                      Tree and Landscape Plan (Sheet 2 of 8)

7.73                      Tree and Landscape Plan (Sheet 3 of 8)

7.74                      Tree and Landscape Plan (Sheet 4 of 8)

7.75                      Tree and Landscape Plan (Sheet 5 of 8)

7.76                      Tree and Landscape Plan (Sheet 6 of 8)

7.77                      Tree and Landscape Plan (Sheet 7 of 8)

7.78                      Tree and Landscape Plan (Sheet 8 of 8)

7.7a                     Photographic Record of Landscape Resources

7.7b                     Photographic Record of Landscape Character Areas

7.7c                     Photographic Record of Key Visually Sensitive Receivers

7.7d                    Photographic Record of Key Visually Sensitive Receivers

7.9a                     Illustration of Scheme H(A) and J

7.9b                     Illustration of Scheme H(B) and I

7.9c                     Illustration of Interim Scheme Q and Road Junction Improvement Works

7.10a                   Photomontage of Scheme H(A)

7.10b                   Photomontage of Scheme H(B) and I

 



APPENDICES

 

Appendix 3.1            Traffic Data of the Study Area

Appendix 3.2            Sensitivity Test

Appendix 3.3            Assumption and Input Parameters for EMFAC-HK

Appendix 3.4            Calculation of Vehicular Emission Factors for Different Roads

Appendix 3.5            Detailed Calculation of Chimney, Portal, Top Opening and Ventilation Building Emission

Appendix 3.6            Marine Emissions

Appendix 3.7            Results of the Pollutant Concentrations for Discrete ASRs

Appendix 3.8            Calculation of Emission Factor for Construction Dust Assessment

Appendix 3.9            Results of Construction Dust Assessment for Year 2014 and Year 2015

Appendix 4.1A         Photos of Existing NSRs

Appendix 4.1B         Correspondence from Planning Department

Appendix 4.2A         Unmitigated Powered Mechanical Equipment

Appendix 4.2B         Unmitigated Sound Power Level of the Project

Appendix 4.2C         Notional Distance from Construction Sites of the Project

Appendix 4.2D         Detailed Calculation of Unmitigated Construction Noise Level of the Project

Appendix 4.2E          Summary of Unmitigated Construction Noise Level of the Project

Appendix 4.3A         Traffic Flow Data for Traffic Noise Assessment at Design Year (Year 2030)

Appendix 4.3B         Traffic Flow Data for Prevailing Traffic Noise Assessment (Year 2013)

Appendix 4.3C         Endorsement Letter from Transport Department

Appendix 4.3D         Traffic Data of Internal Roads of WKCD

Appendix 4.4A         Sensitivity Test for Canton Road

Appendix 4.4B         Detailed Calculations of Traffic Noise Levels for NSRs along Canton Road

Appendix 4.4C         Traffic Flow Data for Traffic Noise Assessment of Interim Access in Austin Road West

Appendix 4.5            Detailed Calculations of Traffic Noise Levels

Appendix 4.6            Sample Calculation of the Traffic Noise Model

Appendix 4.7            Road-plots for Road Traffic Noise Model

Appendix 4.8A         Mitigated Powered Mechanical Equipment

Appendix 4.8B         Mitigated Sound Power Level of the Project

Appendix 4.8C         Notional Distance from Construction Sites of the Project

Appendix 4.8D         Detailed Calculation of Mitigated Construction Noise Level of the Project

Appendix 4.8E          Summary of Mitigated Construction Noise Level of the Project

Appendix 4.9A         Plant List of the Concurrent Projects

Appendix 4.9B         Sound Power Level of the Concurrent Projects

Appendix 4.9C         Notional Distance from Construction Sites of the Concurrent Projects

Appendix 4.9D         Detailed Calculation of Construction Noise Level of the Concurrent Projects

Appendix 4.9E          Summary of Construction Noise Level of the Concurrent Projects

Appendix 4.9F          Summary of Mitigated Cumulative Construction Noise Level

Appendix 6.4A         Sediment Sampling and Testing Plan (Issue 2)

Appendix 6.4B        Existing Ground Investigation Records (Extracts)

Appendix 6.4C         Availability of Marine Disposal Sites for Proposed Sediment Removal

Appendix 6.4D         Designated Disposal Ground to Receive Construction Waste (excluding contaminated materials)

Appendix 7.1            Tree Survey Schedule

Appendix 8.1            Implementation Schedule of Recommended Mitigation Measures