Highways Department 路政署 Major Works
Project Management office 主要工程管理處 |
Agreement No. CE44/2011 (HY)
Proposed Road Improvement Works in
West Kowloon Reclamation Development – Phase 1 – Investigation, Design and
Construction
EM&A Manual (September 2013)
EM&A
MANUAL (september 2013)
CONTENTS
1.3 Purpose of the
EM&A Manual
2.4 Engineer’s
Representatives (ER)
2.5 Independent
Environmental Checker (IEC)
3.8 Air Quality
Performance Limit
8.3 Compliance with
Legal and Contractual Requirements
9.2 Baseline
Monitoring Report
9.6 Interim
Notification of Environmental Quality Limit Exceedances
DRAWINGS
Drawing No. CE44/T/ST/EM01 Site Location
Plan
Drawing No.
CE44/T/ST/EM02 Project Organisation for
Environmental Works
Drawing No. CE44/T/ST/EM03-04 Locations
of Environmental Monitoring Stations
APPENDICES
Appendix A Environmental Mitigation
Implementation Schedule
Appendix B Sample Data Sheet for Monitoring
Appendix C Event and Action Plan
Appendix D Sample Template for Interim
Notification
TABLES
Table 3.1 ..... Proposed Construction Dust Monitoring
Locations
Table 3.2..... Action / Limit Levels for Air
Quality
Table 4.1..... Proposed Construction Noise
Monitoring Locations
Table 4.2..... Action / Limit Levels for Noise
There will be substantial developments in West
Kowloon Reclamation Development (WKRD). With the completion of one of the
developments and the commissioning of the new transport facilities, their
traffic impacts to the road network of WKRD and its vicinity will be
significant.
Apart from the additional traffic impacts arising
from the major developments and transport
facilities in WKRD,
several major junctions
in the area
are currently operating with
insufficient capacity causing
serious congestion to
some existing major road
corridors such as Jordan
Road (JRD), Ferry
Street (FST) and Canton Road
(CRD).
To enhance the road network of the area, Transport
Department commissioned the “West Kowloon Reclamation Development Traffic
Study” which identified and recommended Core and Additional Schemes together
with the improvement works at the junction of CRD/FST/JRD. Implementation of
these schemes would enable most of the key road junctions in the study area to
operate with spare capacity, and the traffic queue length would also be reduced
avoiding blockage to the upstream junctions.
1.2
The
Assignment
On 7 March 2012, the Government of Hong Kong
Administration Region awarded Agreement No. CE44/2011 (HY) Proposed Road
Improvement Works in West Kowloon Reclamation Development – Phase 1 –
Investigation, Design and Construction to Parsons Brinckerhoff
(Asia) Ltd.
The assignment involved construction and modification
of road bridge and carriageway, road improvement and associated works for the proposed schemes and junction improvement
works. An Environmental Impact
Assessment (EIA) was conducted to identify and evaluate the environmental
impacts due to the project and to recommend practical mitigation measures. The
site location plan can be found in DRAWING NO. CE44/T/ST/EM01.
1.3
Purpose
of the EM&A Manual
This
EM&A Manual is prepared based on the findings and recommendations in the
EIA and with reference to the requirements stipulated in Annex 21 Technical Memorandum
under the Environmental Impact Assessment Ordinance (EIAO-TM):
(a) To propose EM&A programme to monitor
the environmental performance of the project
(b) To check the implementation status of
mitigation measures to minimize construction and operational impacts on the
environment
(c) To identify the need for additional
mitigation measures
(d) To advise the responsibilities of different
parties involved in the project and communication flow among them
(e) To detail monitoring requirements
(locations, environmental parameters, frequency, duration) before and during
the construction period and in the operational period
(f) To propose monitoring equipment required
and quality assurance
(g) To determine action and limit levels of
each environmental parameter based on the legislative criteria and standards for
compliance checking
(h) To set up event and action plans for
remedial actions if exceedance of compliance is identified
(i) To devise procedures for handling
complaint/consultation
(j) To detail reporting requirement
The
expected construction period for this project is from the early of 2014 to the end of 2015.
The
implementation schedule of environmental mitigation proposed in the EIA report
can be found in Appendix A.
Parties involved in
the environmental protection works are the Contractor, Engineer’s
Representative (ER), Environmental Team (ET) and the Independent Environmental
Checker (IEC)). Their respective
roles and duties/responsibilities are shown in the following sub-sections. The
proposed line of communication can be found in DRAWING NO. CE44/T/ST/EM02.
The Project Proponent (Highways Department) shall appoint
Independent Environmental Checker (IEC) to audit and verify the EM&A works
of the Environmental Team (ET).
The Contractor
implies all construction contractors and sub-contractors working on the project
site. He should:
(i)
Engage the ET to carry out EM&A work
(ii)
Notify the ET construction activities that may have
environmental concern
(iii)
Participate in the site inspection carried out by
the ET and to rectify any environmental deficiency identified
(iv)
Propose and implement necessary measures to mitigate
any exceedance in Action/Limit Level recorded in accordance to the Event/Action
Plans
(v)
Investigate complaints according to the agreed
procedures
2.4
Engineer’s
Representatives (ER)
The ER shall be responsible to oversee the
construction work of all contractors to ensure that the contract specification
can be met. He should:
(i)
Supervise the Contractor’s activities to ensure
that they comply with the requirement in the EIA, EM&A Manual,
Environmental Permit (EP) and the contract specifications
(ii)
Follow the agreed procedures in the Event/Action
Plan in case of any exceedance and instruct the Contractor to carry out
remedial actions
(iii)
Investigate complaints according to the agreed
procedures and instruct the Contractor to follow up
(iv)
Assist the ET in implementation of EM&A
programme when required
2.5
Independent
Environmental Checker (IEC)
The IEC shall be
appointed by Highways Department to audit and verify the EM&A works of the
ET and to oversee the environmental performance of the project site. He shall
not have any association with the Contractor, ER or ET.
(i)
Review and verify EM&A Reports and submissions
for EP prepared by the ET and advise for improvement
(ii)
Audit and confirm the validity and accuracy of
monitoring activities and results. He may carry out random sample
check and audit on monitoring data and sampling procedures, etc
(iii)
Review the implementation status and effectiveness
of mitigation measures onsite and ensure that they are carried out properly
(iv)
Conduct monthly and random site inspection.
(v)
Investigate complaints according to the agreed
procedures
(vi)
Review the proposal of mitigation measures by the
Contractor in an event of exceedance according to the Event/Action Plan
The ET shall be
lead by the ET Leader to carry out EM&A programme and to check the
Contractor’s compliance with the environmental protection requirements in the EIA,
EM&A Manual and EP. He should:
(i)
Set up monitoring station to carry out monitoring,
statistical analysis and compliance checking against legislative standard and
guidelines
(ii)
Repeat field measurement in case of exceedance and
propose mitigation measures for improvement
(iii)
Conduct weekly site inspection to audit the
Contractor’s site practice on pollution prevention and the effectiveness and adequacy
of mitigation measures
(iv)
Advise the Contractor rectification work required
when environmental deficiency is identified
(v)
Prepare monthly and quarterly EM&A report to
summarise environmental performance and to anticipate future key issues
(vi)
Review and comment on work schedule and methodology
as necessary
(vii)
Support the Contractor for submissions required
under the EP
(viii)
Investigate complaints and propose corrective
measures according to the agreed procedures
(ix)
Liaise with the IEC on environmental performance
With implementation of dust suppression measures, no unacceptable
construction air quality impact is anticipated. Regular air quality monitoring should
be carried out at representative ASRs and to ensure that relevant air quality
standard can be met.
Based on the modeling results, the results are complied with the air
quality objectives for all modeled parameters at ASRs in the operational phase.
No operational phase monitoring or audit is proposed.
This section outlines the monitoring requirement for air quality during
the construction phase.
The ET shall evaluate
the construction air quality impact by conducting 1-hour and 24-hour Total
Suspended Particulates (TSP) measurements.
1-hour and 24-hour TSP levels will be
measured in accordance to the standard high volume sampling method as set out
in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix
A.
Other than using high volume sampler, 1-hour
TSP levels can be measured alternatively by direct reading from portable dust
meters upon approval from ER. The meters should be capable of producing
comparable results as that by the high volume sampling method, to indicate
short event impacts.
3.4.1 High Volume Sampler
The ET shall provide sufficient number of high
volume samplers (HVSs) for measurement at different ASRs during each
monitoring. The HVSs shall comply with the following specifications for
carrying out the 1-hour and 24-hour TSP monitoring:
(a)
0.6 -
1.7 m3 per minute adjustable flow range;
(b)
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
(c)
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
(d)
capable
of providing a minimum exposed area of 406 cm2;
(e)
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
(f)
equipped
with a shelter to protect the filter and sampler;
(g)
incorporated
with an electronic mass flow rate controller or other equivalent devices;
(h)
equipped
with a flow recorder for continuous monitoring;
(i)
provided
with a peaked roof inlet;
(j)
incorporated
with a manometer;
(k)
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
(l)
equipped
with easily changeable filter; and
(m) capable of operating continuously for a
24-hour period.
Clearly labelled
calibration kit and filter papers shall also be provided. The HVSs should be
equipped with an electronic mass flow controller and be calibrated against a
traceable standard at regular intervals.
Calibration
should first be conducted after installing the HVSs and repeated on bi-monthly
basis. The transfer standard shall be traceable to the internationally
recognised primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
The flow-rate of the sampler before and after the sampling exercise with
the filter in position shall be verified to be constant and be recorded in the
data sheet in Appendix B.
3.4.2 Direct Reading Meter
If the ET prefers to adopt direct reading method for 1-hour TSP, he
should provide adequate support to the IEC for verifying the capacity of the
meter as with the HVSs in obtaining comparable measurements. The meter shall be
calibrated at regular intervals in accordance to the specification in the
manufacturer’s manual. The calibration certificates shall be available to the
IEC for checking upon request. The validity and accuracy of the meter shall
also be tested against the results by the HVS periodically.
3.4.3 Collection of Wind Data
For recording wind speed and wind direction, the ET shall install wind
data monitoring equipment near the dust monitoring locations. The installation location shall be proposed
by the ET and agreed with the IEC. The
installation and operation of the equipment shall meet the following criteria:
(a)
The
wind sensors should be installed 10 m above ground so that they are clear of
obstructions or turbulence caused by buildings.
(b)
The
wind data should be captured by a data logger.
The data shall be downloaded for analysis at least once a month.
(c)
The
wind data monitoring equipment should be re-calibrated at least once every six
months.
(d)
Wind
direction should be divided into 16 sectors of 22.5 degrees each.
If agreed by the
ER and the IEC, the ET may obtain wind data using alternative method.
3.4.4 Laboratory Testing
Filter paper to
be placed in the HVSs should have a size of 8" x 10"
and be labelled before sampling. It should be clean without pinholes, and be
conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
After air is
passed through the HVSs, the filter paper inside will be loaded with dust. It
shall be collected inside a clean and tightly sealed plastic bag for
transporting to a laboratory. It shall be reconditioned in the
humidity-controlled chamber followed by accurate weighing by an electronic
balance with accuracy up to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
All samples
should be kept in good condition for 6 months before disposal.
The testing
laboratory should be HOKLAS accredited. It should be clean and can maintain a
stable temperature and humidity. Measuring and conditioning instruments should
be available for handling the dust samples. It should be able to carry out
result analysis, equipment calibration and maintenance.
If a site or
non-HOKLAS laboratory will be responsible for conducting the testing, the
laboratory equipment shall be approved by the ER and the measurement procedures
shall be witnessed by the IEC. Any
measurement performed by the laboratory shall be demonstrated to the
satisfaction of the ER and the IEC. The
IEC shall regularly audit the measurement performed by the laboratory to ensure
the accuracy of measurement results. The ET Leader shall provide the ER with
one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix A for his reference.
3.5.1 Monitoring Location
Four
representative Air Quality Monitoring stations (AMSs) are proposed as follows:
Table
3.1 Proposed Construction
Dust Monitoring Locations
Monitoring
Stations |
Location |
AM1 |
Marine Department New Yau Ma Tei Public Cargo
Working Area Administrative Building (YMT) |
AM2 |
Garden Building (GB) |
AM3 |
The Cullinan I (CLS) |
AM4 |
Lai Chack Middle School (LCMS) |
The location of
the stations can be found in Drawing No. CE44/T/ST/EM03-04.
The status and
locations of dust sensitive receivers may change after issuing this manual. In
this case, the ET Leader shall propose alternative monitoring locations taken
into account the following considerations and seek approval from the ER and the
IEC:
(a)
locate
at the site boundary or such locations close to the major dust emission source;
(b)
locate
close to the sensitive receptors; and
(c)
take
into account the prevailing meteorological conditions.
3.5.2 Placement of Equipment
The ET shall
agree with the ER in consultation with the IEC on the position of the HVS for
the installation of the monitoring equipment.
When positioning the samplers, the following points shall be noted:
(a)
a
horizontal platform with appropriate support to secure the samplers against
gusty wind should be provided;
(b)
no two
samplers should be placed less than 2 meters apart;
(c)
the
distance between the sampler and an obstacle, such as buildings, must be at
least twice the height that the obstacle protrudes above the sampler;
(d)
a
minimum of 2 meters of separation from walls, parapets and penthouses is
required for rooftop samplers;
(e)
a
minimum of 2 meters separation from any supporting structure, measured
horizontally is required;
(f)
no
furnace or incinerator flue is nearby;
(g)
airflow
around the sampler is unrestricted;
(h)
the
sampler is more than 20 meters from the dripline;
(i)
any
wire fence and gate, to protect the sampler, should not cause any obstruction
during monitoring;
(j)
permission
must be obtained to set up the samplers and to obtain access to the monitoring
stations; and
(k)
a
secured supply of electricity is needed to operate the samplers.
Baseline
monitoring shall be conducted to determine the existing air quality in terms of
1-hour and 24-hour TSP levels before commencement of construction work. A
consecutive measurement for 14 days shall be done for 24-hour TSP at all
monitoring stations. At least 3 sets of 1-hour TSP data shall also be collected
every day during this period, at the predicted time in which greatest impact is
expected.
During the
baseline monitoring, there should be no major construction or dust generating
activities near the monitoring stations. As there are a number of concurrent
projects in the West Kowloon Reclamation Development, the ET shall propose a
monitoring schedule to the IEC so that he can conduct onsite audit to ensure
the accuracy of the measurement where necessary.
Alternative
baseline AMS that can give representative baseline result may be proposed for
ER and IEC’s approval with justifications.
In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET shall liaise with the IEC and EPD to
agree on an appropriate set of data to be used as a baseline reference and
submit to ER for approval.
The baseline monitoring data shall be reviewed once every three months.
When there is seasonal change to ambient conditions, the baseline condition may
need to be updated. Repeated measurement shall be conducted during which no
dust generating activity is being carried out near the AMS. If a change in
ambient condition is recorded, the baseline levels and therefore air quality
criteria should be revised accordingly and agreed with the IEC and EPD.
Impact
monitoring shall be carried out throughout the construction period at all AMSs.
24-hour TSP sampling shall be conducted at a frequency of at least once in
every 6 days, while that for 1-hour TSP shall be at least 3 times in every 6
days when the highest dust impact takes place. Similar to baseline monitoring,
the ET shall submit a monitoring schedule to the IEC for onsite audit of the
accuracy of the monitoring result where necessary.
The ET shall
clearly define and strictly follow the starting and ending time for 24-hour TSP
monitoring for each AMS.
If exceedance of
air quality criteria is recorded, more frequent measurement shall be done
within the specified timeframe in accordance to the Action Plan. The additional
monitoring shall be continued until the excessive dust emission or the
deterioration in air quality is rectified, and upon agreement with the IEC.
3.8
Air
Quality Performance Limit
The Air Quality
Objective sets the statutory limit for 1-hour and 24-hour TSP levels while the
baseline monitoring results shall be interpreted to derive the action levels.
Table 3.2 Action / Limit Levels for Air
Quality
Parameters |
Action |
Limit |
24-hour
TSP Level in µg m-3 |
For
baseline level £ 200 µg m-3, Action level =
(baseline level * 1.3 + Limit level)/2; For
baseline level > 200 µg m-3 Action level = Limit level |
260
µg/m3 |
1-hour
TSP Level in µg m-3 |
For
baseline level £ 384 µg m-3, Action level =
(baseline level * 1.3 + Limit level)/2; For
baseline level > 384 µg m-3, Action level = Limit level |
500µg/m3 |
Should
non-compliance of the air quality criteria occur, actions in accordance with
the Action Plan in Appendix C shall be carried out.
The EIA proposed a number of construction phase mitigation measures,
examples as follows:
(a)
Good
housekeeping to minimize dust generation, e.g. by properly handling and storing
dusty materials
(b)
Adopt
dust control measures, such as dust suppression using water spray on exposed
soil, in areas with dusty construction activities and during material handling
(c)
Limit
vehicle speed within site
(d)
Minimize
exposed earth after completion of work in a certain area by hydroseeding,
vegetating, soil compacting or covering with bitumen
(e)
Provide
wheel washing at site exit to prevent carrying dust outside of the site
(f)
Hard
pave the area at site exit
with concrete, bitumen or hardcores
(g)
Cover
materials on trucks before leaving the site
Detailed mitigation measures are listed out
in the EMIS in Appendix A.
Implementation status and the effectiveness of these measures shall be audited
through regular site inspection.
Based on the modeling results, cumulative construction
noise exceedance at NSRs is anticipated for the noise criteria during
examination period even if mitigation measures are properly implemented. Regular
noise monitoring should be carried out at representative NSRs to ensure that
relevant noise standard can be met.
In the operational phase, the traffic noise impact arising
from the Project is considered insignificant. Moreover, the traffic noise
emanating from the Project roads would also comply with the relevant standard. No operational phase monitoring or audit is
proposed.
This
section outlines the monitoring requirement for noise during the construction
phase.
Construction
noise level shall be measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq
30min shall be used as the monitoring parameter for the time period
between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq 5 min shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
As
supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
Sound level meters shall be employed to measure the construction noise
level. It should comply with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications in
accordance to the Technical Memorandum (TM) issued under the NCO.
An acoustic calibrator shall be used to validate the accuracy of the
sound level meter before and after each noise measurement. The calibrator can
generate a known sound pressure level at a known frequency. The noise record
will only be accepted if the calibration level from before and after the noise
measurement agrees to within 1.0 dB.
Sufficient number of the above equipment shall be provided by the ET,
who will also be responsible for installation, operation, maintenance and
dismantlement. All equipment and instrumentation shall be clearly labelled.
Noise measurement shall normally be at a point 1 m from the exterior of
the sensitive receiver building façade and be at a position 1.2 m above the
ground. If the normal monitoring
position cannot be accessed, an alternative position may be chosen, and a
correction to the measurements shall be made.
For reference, a correction of +3 dB(A) shall be made to the free field
measurements. The ET shall agree with
the IEC on the monitoring position and the corrections adopted. The agreed
position shall be chosen in subsequent baseline and impact monitoring.
Noise measurements should be made in
accordance with standard acoustical principles and practices in relation to
weather conditions.
Noise exceedance is expected at the following SRT, CLS, LCMS, YTB and schools
LKPC and YCS during examination period. As such, five representative Noise
Monitoring Stations (NMSs) are proposed as follows:
Table
4.1 Proposed Construction Noise Monitoring
Locations
Monitoring Stations |
Location |
NM1 |
Sorrento - Tower 1 (SRT) |
NM2 |
Yau Ma Ti Catholic Primary
School (Hoi Wang Road) (YCS) |
NM3 |
The Cullinan I (CLS) |
NM4 |
Lai
Chack Middle School (LCMS) |
NM5 |
Yue Tak Building (YTB) |
The location of the stations can be found in Drawing No.
CE44/T/ST/EM03-04.
The status and locations of noise sensitive receivers may change after
issuing this manual. In this case, the ET Leader shall propose alternative
monitoring locations taken into account the following considerations and seek approval
from the ER and the IEC:
(a) locate
close to the major site activities which are likely to have noise impacts;
(b) locate close to the most affected existing
NSRs; and
(c)
take
into account the possibility of minimizing disturbance to occupants at the NSRs
during monitoring.
Baseline noise measurement shall be conducted to determine the background
noise before commencement of work. Daily measurement of A-weighted levels Leq,
L10 and L90 shall be conducted for at least two weeks. The sample period shall be 30
minutes between 0700 and 1900.
During the baseline monitoring, there should be no major construction
activities near the monitoring stations. As there are a number of concurrent
projects in the West Kowloon Reclamation Development, the ET shall propose a
monitoring schedule to the IEC prior to the monitoring so that he can conduct
onsite audit to ensure the accuracy of the measurement where necessary.
Alternative baseline NMS that can give representative baseline result
may be proposed for ER and IEC’s approval with justifications.
In exceptional cases, when insufficient
baseline monitoring data or questionable results are obtained, the ET shall
liaise with the IEC to agree on an appropriate set of data to be used as a
baseline reference and submit to ER for approval.
For daytime construction work on normal weekdays (0700-1900 Monday to
Saturday), one set of 30-min measurement shall be carried out at each NMS every
week based on the measurement procedures under the Noise Control Ordinance-TM.
Similar to baseline monitoring, the ET shall submit a monitoring schedule to
the IEC beforehand.
Should there be any education institute near the construction site,
noise measurement should be carried out during the examination period. The ET
shall ask for examination time during the contract period from school personnel
and the Examination Authority.
If noise exceedance is being recorded, additional noise monitoring shall
be conducted in accordance to the Event Action Plan. The monitoring shall
consider complete if the exceedance is being rectified or proved to be from
source other than the project construction work.
The EIAO-TM sets the statutory limit for noise level produced during
construction work.
Table
4.2 Action
/ Limit Levels for Noise
Time
Period |
Action
Level |
Limit
Level |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75*dB(A) |
(*) Reduce to 70dB(A) for schools and 65dB(A) during school examination periods.
Should non-compliance of the noise criteria occur, actions in accordance
with the Action Plan in Appendix C
shall be carried out.
The EIA proposed a number of construction
phase mitigation measures, examples as follows:
(a) Adopt good site practice, such as regular
maintenance of plant equipment, throttle down unused machines
(b) Use Quality Powered Mechanical Equipment (QPME)
(e.g. Excavator/Loader
(EPD-01431), Asphalt Paver (EPD-01226), Road Roller (EPD-00244) and Mobile
Crane (EPD-01477))
(c) Erect movable noise barrier of 3m height to
shed large plant equipment (e.g. concrete pump, concrete lorry mixer,
excavator/loader, road sweeper, asphalt paver, road roller and lorry) or hand-held items (e.g. Breaker and Poker) near low-rise NSR, with special design
where necessary, e.g. with noise absorbing material or bend top. Its length
should be at least five times greater than its height. The minimum surface density
of the movable noise barrier is 7 kg/m2.
Detailed mitigation measures are listed out in the
EMIS in Appendix A. Implementation status and the effectiveness
of these measures shall be audited through regular site inspection.
Potential water quality impact may arise from
surface runoff carrying high level of suspended solids, discharge of sewage
effluent and accidental chemical spillage into the storm drain. No adverse
construction water quality impact is expected if the mitigation measures are
implemented properly.
In the operational phase, surface runoff will be
collected and screened by road drainage system before entering the storm water
drains. As limited water quality impact is anticipated, no monitoring or audit
is proposed.
Weekly site audit is recommended to monitor the
implementation of the proposed water quality mitigation measures and check the Contractor’s
work practice on water pollution prevention during construction phase.
Should water pollution is observed (e.g. discharge
of silty water into storm drains), the ET should record the environmental
deficiency for investigation. The Contractor should be notified and responsible
for carrying out rectification work immediately. The ET shall re-inspect the
site and review the effectiveness of the remedial measure performed until
satisfaction. The Contractor shall implement preventive measure to avoid
causing the same problem.
Effluent testing should be carried out at interval
stipulated in the discharge license issued by the EPD and should comply with
the requirement.
Should non-compliance be recorded, the Contractor
should notify the site management and carry out investigation to identify the
source. Check if all mitigation measures are carried out. The Contractor shall
employ remedial measures to improve effluent quality, e.g. further treatment if
needed. No effluent should be discharged until the effluent quality meets the
required standard. The Contractor shall implement preventive measure to avoid
causing the same problem.
The EIA proposed a number of construction phase
mitigation measures, examples as follows:
(a) Well manage construction materials,
chemicals, sewage for proper storage and usage and to prevent accumulation
onsite
(b) Immediately clean up contaminated soil upon
chemical and oil leakage
(c) Label chemical waste containers as
reminder. Store fuels, chemicals and waste at designated area with locks and
bunds
(d) Register as chemical waste producer
(e) Settle surface runoff in sedimentation tank
prior to discharge
(f) Provide sufficient number of chemical
toilets and employ licensed contractor for regular clean-up and maintenance
(g) Provide wheel washing bay at site exit and
maintain regularly to prevent dust and silty water from leaving the site
(h) Cover slope and loose materials with
tarpaulin before rainstorm and inspect the area afterwards
(i) Cover manhole to prevent silty runoff from
entering the foul sewer
Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of
these measures shall be audited through regular site inspection.
Waste includes Construction and Demolition
(C&D) materials from excavation, site formation and demolition, chemicals
from plant maintenance, general refuse and marine sediment. No adverse waste impact is expected if the
mitigation measures are implemented properly.
During operational phase, limited amount of waste
will be generated in the form of silt or grit from road gullies and litter.
Therefore, the operational phase waste impact is negligible.
The Contractor should apply for relevant
licences/permits for waste disposal under different regulations and ordinances
as follows:
(a) Chemical Waste Permits/licenses under the
Waste Disposal Ordinance (Cap 354);
(b) Public Dumping Licence under the Land
(Miscellaneous Provisions) Ordinance (Cap 28); and
(c) Effluent Discharge Licence under the Water
Pollution Control Ordinance.
Reference should be made to EPD’s booklets on
licences/permits. The Contractor shall also document recycling receipts/
disposal record to keep track of waste movement. The ET shall check with the
Contractor that these licences/permits have been obtained. He should also
review the above documentations regularly to ensure compliance with
legislations and specifications. Testing should be carried out to verify the
sediment quantity and quality as recommended in EIA report.
The contractor should formulate waste management
measures on waste minimization, storage, handling and disposal in a Waste
Management Plan as part of Environmental Management Plan in accordance to ETWB
TC (W) No.19/2005 for construction phase. The Environmental Management Plan
should be submitted to the Engineer for approval. Mitigation measures proposed
in the EIA Report and the EM&A Manual should be adopted.
The EIA proposed a number of construction phase mitigation
measures, examples as follows:
(a) Reuse inert C&D materials onsite and
dispose excess uncontaminated ones to public fill
(b) Provide sufficient waste collection points
for general refuse and regularly maintained to avoid accumulation. Dispose the
waste at waste transfer or disposal facilities
(c) Minimize wastage through careful planning
and avoiding over-purchase of construction materials
(d) Provide training to workers on site
cleanliness, waste management (waste reduction, reuse and recycle) and chemical
handling procedures
(e) Hire licensed waste disposal contractors
for waste collection and removal. Dispose waste at licensed waste disposal
facilities
Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of
these measures shall be audited through regular site inspection.
During the construction phase, construction activities, temporary
stockpiling, storage of construction plant and materials, work area, traffic
and road diversions and dust emission may lead to landscape and visual impacts.
Mitigation measures are proposed to minimize the degree of impact.
During the operational phase, the newly built roads will be a source of
landscape and visual impact. Mitigation measures are proposed to minimize the
degree of impact.
A Registered Landscape Architect should be employed by the Contractor as
part of the ET. He should ensure that the mitigation measures are carried out
in accordance to the recommendations in the EIA and any specification in the
contract or agreement with relevant departments. He will inspect the site and
audit the implementation of mitigation measures once every two weeks during construction
phase and on monthly basis in the operational phase.
He will monitor adequacy of tree preservation, status of tree planting
and removal during construction phase. He will also check maintenance of the
transplanted and newly planted trees during the establishment period in the
operational phase. Furthermore, he will review the compliance of the landscape work
with the proposed design.
The EIA proposed a number of mitigation measures to
be implemented by HyD’s contractor, examples as follows:
Construction Phase
(a) Shorten the construction period whenever
possible
(b) Limit work within site area without
encroaching into the landscape resources offsite.
(c) Protect retained trees from damage during
construction work
(d) Maintain transplanted trees to ensure
healthy development during the establishment period
(e) Match the design and materials of road
structure with the surrounding environment and with the future West Kowloon
Reclamation Development and the Advisory Committee on the Appearance of Bridges
and Associated Structures
Operational Phase
(a) Carry out compensatory planting to mitigate
the loss greenery
(b) Provide vertical greening and shrub
planting for hiding hard landscape
Detailed mitigation measures are listed out in the
EMIS in Appendix A. Implementation status and the effectiveness of
these measures shall be audited through regular site inspection.
While a number of mitigation measures are proposed
in the EIA report, regular site inspection is recommended for direct observation
of the implementation progress to ensure they are properly implemented. Through
a well-established action and reporting system, additional pollution control
measures to identified environmental deficiency can be proposed and carried out
at early stage. Site inspection is a useful way to enforce the environmental
protection requirements onsite during construction.
The ET Leader will be responsible for the site
environmental audit. He will design the environmental site inspection,
deficiency and action reporting system and conduct regular site inspection. He
should prepare a proposal on the site inspection and reporting methodology to
the Contractor for agreement and to the ER for approval.
Weekly site inspection shall be performed by the ET
within the site where environmental protection measures will be implemented and
also offsite where the construction activities may directly or indirectly be
impacted upon. The following shall be noted during the inspection:
(a) environmental protection and pollution
control mitigation measures proposed in the EIA, contract specification, EP and
this Manual
(b) works progress and programme
(c) ongoing results of the EM&A programme
(d) individual works methodology proposals
(including associated pollution control measures)
(e) relevant environmental protection and
pollution control laws
(f) previous site inspection results
The Contractor shall inform the ET on any update of
all relevant information on the construction contract necessary for him to
carry out the site inspection. After each site inspection, the ET shall submit
an inspection report to the Contractor and the ER within 24 hours. It should
include inspection result on any identification of environmental deficiency and
corresponding mitigation recommendations for taking immediate rectification
action. Follow up of identified problem from the previous inspection shall also
be included. The Contractor shall report on any rectification actions after the
site inspection in accordance to the procedures and timeframe proposed by the
ET in the environmental site inspection, deficiency and action reporting
system.
If significant environmental issue is identified,
additional site inspection shall be performed. This may also be required upon
receipt or during investigation of environmental complaint in accordance to the
Action Plan for environmental monitoring and audit.
8.3
Compliance
with Legal and Contractual Requirements
The environmental protection and pollution control
laws in Hong Kong and project contract stipulate environmental protection and
pollution control requirement for construction activities.
As such, the Contractor should submit all work
method statements for ER’s approval and ET Leader’s review on environmental
compliance with the contractual requirements. Sufficient environmental
protection and pollution control measures shall be demonstrated in the method
statement.
The ET Leader should also check that the work
progress and programme can comply with legal requirement on environmental terms
and to prevent violation in the future.
The Contractor shall regularly copy relevant
documents to the ET for checking, including but not limited to updated Work
Progress Reports, updated Works Programme, application letters for different
licence/permits under the environmental protection laws, and all valid licences/permits.
The site diary shall also be available for inspection upon ET Leader’s request.
Should any non-compliance with the contractual and
legislative requirements is identified after reviewing the documents, the ET
should notify the ER and Contractor so that follow-up actions can be taken. He
should also inform the ER and Contractor if the current status on
licence/permit application and any environmental protection and pollution
control preparation works may not meet the works programme or the construction
work may lead to potential violation of environmental protection and pollution
control requirements in due course.
The Contractor shall carry out remedial actions
immediately upon receipt of ET’s advice. The ER shall check with the Contractor
to ensure that appropriate actions has been taken accordingly and can satisfy
the environmental protection and pollution control requirement.
Upon receipt of complaint, the following procedures
shall be followed:
(a) The Contractor to log complaint and
date of receipt onto the complaint database and inform the ER, ET and IEC
immediately;
(b) The Contractor to
investigate, with the ER and ET, the complaint to determine its validity, and
assess whether the source of the problem is due to construction works of the
Project
with the support of additional monitoring frequency and stations, if necessary;
(c) The Contractor to
identify remedial measures in consultation with the IEC, ET and ER if a
complaint is valid and due to the construction works of the Project;
(d) The Contractor to implement the
remedial measures as required by the ER and to agree with the ET and IEC any
additional monitoring frequency and stations, where necessary, for checking the
effectiveness of the remedial measures;
(e) The ER, ET and IEC to review
the effectiveness of the Contractor's remedial measures and the updated
situation;
(f) The ET/Contractor to undertake
additional monitoring and audit to verify the situation if necessary, and oversee that circumstances
leading to the complaint do not recur;
(g) If the complaint is
referred by the EPD, the Contractor to prepare interim report on the status of
the complaint investigation and follow-up action stipulated above, including
the details of the remedial measures and additional monitoring identified or
already taken, for submission to EPD within the time frame assigned by the EPD; and
(h) The ET to record
the details
of the complaint, results of the investigation,
subsequent actions taken to address the complaint and updated situation
including the effectiveness of the remedial measures, supported by regular and
additional monitoring results in the monthly EM&A reports.”
The ET shall prepare baseline monitoring report,
monthly EM&A reports, quarterly EM&A report and final EM&A report.
They shall be submitted to the EPD in paper and electronic formats in timely
order.
9.2
Baseline
Monitoring Report
Baseline monitoring of air quality and noise are
proposed. The baseline monitoring report shall be submitted within 10 workings
days after completion of the monitoring work. The recipients include the IEC,
Contractor and ER. It should first be verified by the IEC before formal
submission to the EPD. The ET shall liaise with the relevant parties on the
number of copies required. The report format and monitoring data format shall
be agreed with the EPD prior to submission. The baseline monitoring report
generally includes but not limited to the following:
(a) up to half a page executive summary;
(b) brief project background information;
(c) drawings showing locations of the baseline
monitoring stations;
(d) monitoring results (in both hard and soft
copies) together with the following information:
a. monitoring methodology;
b. equipment used and calibration details;
c. parameters monitored;
d. monitoring locations (and depth);
e. monitoring date, time, frequency and
duration;
f. quality assurance (QA) / quality control
(QC) results and detection limits;
(e) details of influencing factors, including:
a. major activities, if any, being carried out
on the site during the period;
b. weather conditions during the period; and
c. other factors which might affect results;
(f) determination of the Action and Limit
Levels for each monitoring parameter and statistical analysis of the baseline
data;
(g) revisions for inclusion in the EM&A
Manual; and
(h) comments, recommendations and conclusions.
The ET Leader shall prepare monthly EM&A
reports which summarize the result and findings in all EM&A work conducted
in accordance to the Manual, such as monitoring and site inspection. It shall
be submitted within 10 workings days of the end of each reporting month, with
the first report due in the month after construction commences. The recipients
include the IEC, Contractor, ER and the EPD. It should first be verified by the
IEC before formal submission. The ET shall liaise with the relevant parties on
the exact number of copies required and the report format for both paper and
electronic format prior to submission of the first EM&A report.
As there may be changes in surrounding environment
and nature of work in progress, the ET Leader shall review and update the
number and location of monitoring stations and parameters to be monitored every
6 months or on as needed basis.
9.3.1 First EM&A Report
The first EM&A report generally includes but
not limited to the following:
(a) Executive summary (1-2 pages):
a. breaches of Action and Limit levels;
b. complaint log;
c. notifications of any summons and successful
prosecutions;
d. reporting changes; and
e. future key issues.
(b) Basic project information:
a. project organisation including key
personnel contact names and telephone numbers;
b. construction programme;
c. management structure, and
d. works undertaken during the month
(c) Environmental status:
a. works undertaken during the month with
illustrations (such as location of works); and
b. drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations (with co-ordinates of the monitoring locations)
(d) A brief summary of EM&A requirements
including:
a. all monitoring parameters;
b. environmental quality performance limits
(Action and Limit levels);
c. Event and Action Plans;
d. environmental mitigation measures, as
recommended in the project EIA Report; and
e. environmental requirements in contract
documents;
(e) Implementation status:
a. advice on the implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the project EIA Report;
(f) Monitoring results (in both hard and
diskette copies) together with the following information:
a. monitoring methodology;
b. equipment used and calibration details;
c. parameters monitored;
d. monitoring locations;
e. monitoring date, time, frequency, and
duration;
f. weather conditions during the period;
g. major activities being carried out on site
during the period;
h. any other factors which might affect the
monitoring results; and
i.
QA/QC
results and detection limits;
(g) Report on non-compliance, complaints, and
notifications of summons and successful prosecutions:
a. record of all non-compliance (exceedances)
of the environmental quality performance limits (Action and Limit levels);
b. record of all complaints received (written
or verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
c. record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislation, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
d. review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
e. description of the actions taken in the
event of non-compliance and deficiency reporting and any follow-up procedures
related to earlier non-compliance;
(h) Others
a. an account of the future key issues as
reviewed from the works programme and work method statements;
b. advice on the solid and liquid waste
management status; and
c. comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
9.3.2 Subsequent EM&A Reports
Subsequent EM&A report generally includes but
not limited to the following:
(a) Executive summary (1 - 2 pages):
a. breaches of Action and Limit levels;
b. complaints log;
c. notifications of any summons and successful
prosecutions;
d. reporting changes; and
e. future key issues.
(b) Basic project Information:
a. project organization including key personnel
contact names and telephone numbers;
b. programme;
c. management structure; and
d. works undertaken during the month.
(c) Environmental status:
a. works undertaken during the month with
illustrations (such as location of works etc.); and
b. drawing showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations.
(d) Implementation status:
a. advice on the implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the project EIA;
(e) Monitoring results (in both hard and
diskette copies) together with the following information:
a. monitoring methodology;
b. equipment used and calibration details;
c. parameters monitored;
d. monitoring locations;
e. monitoring date, time, frequency, and
duration;
f. weather conditions during the period;
g. major activities being carried out on site
during the period;
h. any other factors which might affect the
monitoring results; and
i.
QA /
QC results and detection limits.
(f) Report on non-compliance, complaints, and
notifications of summons and successful prosecutions:
a. record of all non-compliance (exceedances)
of the environmental quality performance limits (Action and Limit levels);
b. record of all complaints received (written
or verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
c. record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislation, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
d. review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
e. description of the actions taken in the
event of non-compliance and deficiency reporting and any follow-up procedures
related to earlier non-compliance.
(g) Others
a. an account of the future key issues as
reviewed from the works programme and work method statements;
b. advice on the solid and liquid waste
management status; and
c. comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
(h) Appendix
a. Action and Limit levels;
b. graphical plots of trends of monitored
parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following:
i.
major
activities being carried out on site during the period;
ii.
weather
conditions during the period; and
iii.
any
other factors that might affect the monitoring results.
c. monitoring schedule for the present and
next reporting period;
d. cumulative statistics on complaints, notifications
of summons and successful prosecutions; and
e. outstanding issues and deficiencies.
9.3.3 Quarterly EM&A Summary Reports
The quarterly EM&A summary report shall consist
of around 5 pages (3 pages of text and tables and 2 pages of figures). It
generally includes but not limited to the following:
(a) up to half a page executive summary;
(b) basic project information:
a. a
synopsis of the project organisation, programme;
b. contacts of key management;
c. proponents' contacts and any hotline
telephone number for the public to make enquiries; and
d. a synopsis of works undertaken during the
quarter.
(c) a brief summary of EM&A requirements:
a.
monitoring
parameters;
b.
environmental
quality performance limits (Action and Limit Levels); and
c.
environmental
mitigation measures, as recommended in the EIA Report;
(d) environmental status:
a. a synopsis of work undertaken during the
quarter;
b. drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations;
(e) implementation status:
a.
advice
on the implementation status of environmental protection and pollution
control/mitigation measures, as recommended in the EIA report, summarised in
the updated implementation schedule;
(f) graphical plots of the trends of monitored
parameters over the past 4 months (the last month of the previous quarter and
the present quarter) for representative monitoring stations annotated against;
a.
the
major activities being carried out on site during the period;
b.
weather
conditions during the period; and
c.
any
other factors which might affect the monitoring results;
(g) advice on the solid and liquid waste
management status;
(h) summary of non-compliance
a.
a
summary of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit Levels);
b.
a
brief review of the reasons for and the implications of non-compliance
including review of pollution sources and working procedures;
c.
a
summary description of the actions taken in the event of non-compliance and any
follow-up procedures related to earlier non-compliance;
d.
a
summary record of all complaints received (written or verbal) for each media,
liaison and consultation undertaken, actions and follow-up procedures taken;
(i) comments (e.g. effectiveness and efficiency
of the mitigation measures), recommendations (e.g. any improvement in the
EM&A programme) and conclusions for the quarter; and
9.3.4 Final EM&A Report
The
termination of EM&A programme shall be determined on the following basis:
(a)
completion
of construction activities and insignificant environmental impacts of the remaining
outstanding construction works;
(b) trends analysis to demonstrate the narrow down of
monitoring exceedance due to construction activities and the return of ambient
environmental conditions in comparison with baseline data; and
(c)
no
environmental complaint and prosecution involved.
The proposed termination may be required to consult
related local community such as village representative/committee and/or
District Board and the proposal should be endorsed by the IEC, ER and the
project proponent prior to final approval from the Director of Environmental
Protection.
A Final EM&A report shall be prepared
summarizing the results and findings of the EM&A works throughout the
construction period. It should be submitted within 14 working days after
project completion. It generally includes but not limited to the following:
(a) An
executive summary;
(b) Drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations;
(c) Basic project information:
a. a synopsis of the project organisation;
b. contacts of key management; and
c. a synopsis of work undertaken during the
entire construction period.
(d) A brief summary of EM&A requirements:
a. monitoring parameters;
b. environmental quality performance limits
(Action and Limit levels); and
c. environmental mitigation measures, as
recommended in the project EIA Report;
d. Event and Action Plans.
(e) A summary of the implementation status of
environmental protection and pollution control/mitigation measures, as
recommended in the project EIA Report, summarised in the updated implementation
schedule;
(f) Graphical plots of the trends of monitored
parameters over the construction period for representative monitoring stations,
including the post-project monitoring annotated against:
a. the major activities being carried out on
site during the period;
b. weather conditions during the period; and
c. any other factors which might affect the
monitoring results.
(g) Summary of non-compliance:
a. a summary of non-compliance (exceedances)
of the environmental quality performance limits (Action and Limit levels);
b. a brief review of the reasons for and the
implications of non-compliance including review of pollution sources and
working procedures as appropriate;
c. a summary description of the actions taken
in the event of non-compliance;
d. a summary record of notifications of
summons and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, locations and nature of the
breaches, investigation, follow-up actions taken and results;
(h) A review of the validity of EIA predictions
through comparison with the monitoring data and identification of shortcomings
in EIA recommendations;
(i) A review of the effectiveness and
cost-effectiveness of the monitoring methodology
(j) A review of the effectiveness and
efficiency of the mitigation measures and of the performance of the overall
EM&A programme;
(k) Recommendations for improvement;
(l) Evaluation on the return of environmental
condition the baseline or predicted conditions in the EIA Report; and
(m) Conclusion on the environmental
acceptability of the project.
The ET shall keep the site documents (such as
monitoring field records, site inspection forms etc.) in order and make
available for inspection upon request. These documents do not form part of the
EM&A report. The monitoring data should also be input into electronic
format for checking upon request. All documents and data shall be kept for at
least one year after completion of the construction contract.
A dedicated internet web-site will be set up for
reporting the EM&A data for public inspection in
real-time. Real-time reporting in this context refers to the posting
of monitoring data after it has been through the appropriate processing, QA/QC
checking by the ET and validation by the IEC.
9.6
Interim
Notification of Environmental Quality Limit Exceedances
Should any exceedance in environmental quality
performance limit be recorded, the ET Leader should immediately inform the IEC,
ER, Contractor and EPD as appropriate in accordance to the Event and Action
Plan. He should advise to the IEC, ER, Contractor and EPD the investigation
result, remediation actions performed, effectiveness of the measures and
proposal of further actions required. A sample interim notification template
can be found in Appendix D.
This Manual lists out the EM&A requirements for
environmental parameters air quality, noise, water quality, waste management
and landscape and visual. Environmental monitoring on air quality and noise are
proposed and regular site inspection is recommended for all other parameters.
Any non-compliance identified should be notified to all parties according to
the Event and Action Plan and remediation measures should be carried out.
Complaints received should be investigated and problems related to construction
works should be solved till satisfaction. Baseline, monthly, quarterly and
final EM&A reports shall be prepared to report on the continual monitoring
results and evaluate the EM&A works.