Development
of Organic Waste Treatment Facilities, Phase 2
Environmental
Impact Assessment Report
Chapter Title
|
Table
14.1:_ Implementation Schedule of
Mitigation Measures |
This chapter presents the implementation schedule of the proposed mitigation measures for the Project. Table 14.1 summarises the details of the mitigation measures for all works areas. For each recommended mitigation measure, both the location and timing for the measure have been clearly identified. As well, the parties responsible for implementing the measure and for maintenance (where applicable) have also been clearly identified.
Table 14.1: Implementation Schedule of
Mitigation Measures
|
|
|
|
|
Implementation
Stage1 |
|
|||
EIA Ref. |
EM&A
Ref. |
Environmental
Protection Measures |
Location
/ Duration of measures / Timing of completion of measures |
Implementation
Agent |
Des |
Con |
Op |
Dec |
Relevant
Legislation & Guidelines |
Air Quality Impact (Construction) |
|||||||||
3.8.1.1 |
2.4 |
General
Dust Control Measures Dust emissions could be
suppressed by regular water spraying on site. In general, water spraying
twice a day could reduce dust emission from active construction area by 50%.
However, for the Project more frequent water spraying is proposed. Watering
eight times per day, or once every 1.5 hours, is suggested at all active
works areas in order to achieve a higher dust suppression efficiency of
87.5%. |
Within
construction site / Duration of the construction phase |
Contractor
|
|
P |
|
|
EIA
Recommendation and Air Pollution Control (Construction Dust) Regulation |
3.8.1.2 |
2.4 |
Best Practice For Dust Control The
relevant best practices for dust control as stipulated in the Air Pollution Control (construction Dust)
Regulation should be adopted to further reduce the construction dust
impacts of the Project. These best practices include: Good
Site Management ¡ Good site management is important to help
reducing potential air quality impact down to an acceptable level. As a
general guide, the Contractor should maintain a high standard of housekeeping
to prevent emissions of fugitive dust. Loading, unloading, handling and
storage of raw materials, wastes or by-products should be carried out in a
manner so as to minimise the release of visible dust emission. Any piles of
materials accumulated on or around the work areas should be cleaned up
regularly. Cleaning, repair and maintenance of all plant facilities within
the work areas should be carried out in a manner minimising generation of
fugitive dust emissions. The material should be handled properly to prevent
fugitive dust emission before cleaning. Disturbed
Parts of the Roads ¡ Each
and every main temporary access should be paved with concrete, bituminous hardcore materials or metal plates and kept clear of
dusty materials; or ¡ Unpaved
parts of the road should be sprayed with water or a dust suppression chemical
so as to keep the entire road surface wet. Exposed
Earth ¡ Exposed
earth should be properly treated by compaction, hydroseeding,
vegetation planting or seating with latex, vinyl, bitumen within six months
after the last construction activity on the site or part of the site where
the exposed earth lies. Loading,
Unloading or Transfer of Dusty Materials ¡ All
dusty materials should be sprayed with water immediately prior to any loading
or transfer operation so as to keep the dusty material wet. Debris
Handling ¡ Any
debris should be covered entirely by impervious sheeting or stored in a
debris collection area sheltered on the top and the three sides. ¡ Before
debris is dumped into a chute, water should be sprayed so that it remains wet
when it is dumped. Transport
of Dusty Materials ¡ Vehicle
used for transporting dusty materials/spoils should be covered with tarpaulin
or similar material. The cover should extend over the edges of the sides and
tailboards. Wheel
washing ¡ Vehicle
wheel washing facilities should be provided at each construction site exit.
Immediately before leaving the construction site, every vehicle should be
washed to remove any dusty materials from its body and wheels. Use
of vehicles ¡ The
speed of the trucks within the site should be controlled to about 10km/hour
in order to reduce adverse dust impacts and secure the safe movement around
the site. ¡ Immediately
before leaving the construction site, every vehicle should be washed to
remove any dusty materials from its body and wheels. ¡ Where
a vehicle leaving the construction site is carrying a load of dusty
materials, the load should be covered entirely by clean impervious sheeting
to ensure that the dusty materials do not leak from the vehicle. Site
hoarding ¡ Where
a site boundary adjoins a road, street, service lane or other area accessible
to the public, hoarding of not less than 2.4m high from ground level should
be provided along the entire length of that portion of the site boundary
except for a site entrance or exit. |
Within
construction site / Duration of the construction phase |
Contractor
|
|
P |
|
|
EIA
Recommendation and Air Pollution Control (Construction Dust) Regulation |
Air Quality Impact (Operation) |
|||||||||
3.8.2 |
2.3 |
Odour
patrol at site boundary of the Project |
Site
boundary / During operation stage ( the need to continue the odour patrol
after the end of the 2-year monitoring period would depend on the monitoring
results and should be agreed with EPD) |
OWTF
Operator |
P |
|
P |
|
EIAO-TM |
3.8.2 |
2.4 |
Install
gas cleaning equipment and stack on the CHP and odour treatment unit ¡ The
preliminary design suggests the use of a two stage process involving either a
biofilter or Ultraviolet Light (UV-C) together with
ozone treatment as the first stage, and an activated carbon filter as the
second stage for the odour treatment unit. It is recommended to install the
UV-C and ozone treatment system with second stage active carbon filters as
this has a lower footprint requirement than the biofilter
option. However, the actual unit installed depends on the final design by the
contractor in the design phase. ¡ The
preliminary design incorporates a combination of thermal and catalytic
treatment processes to remove pollutants from the exhaust gasses from the
CHP. ¡ Both
the odour treatment unit and the CHP emissions are suggested to be directed
to a flue to aid the dispersion and minimise effects on ASRs. |
CHP
and odour treatment unit |
Design
Consultant / OWTF Operator |
P |
|
P |
|
EIA
Recommendation |
Hazard Risk Assessment (Operation) |
|||||||||
4.9 |
3.2 |
The
HA has assumed that the following “Good Practices” and “recommended design
measures” for the safe operation of OWTF 2 shall be carried out as far as
reasonably practicable: ¡ The
process plant building will be provided with adequate number of gas detectors
distributed over the various areas of potential leak sources to provide
adequate coverage. ¡ All
electrical equipment inside the building will be classified in accordance
with the electrical area classification requirements. No unclassified
electrical equipment will be used during operations or maintenance. ¡ Reference
can be made to Codes of Practice and guidance issued in Europe that applies
to places where explosive atmospheres may occur (called ‘ATEX’ requirements).
These are covered as part of the European Directive: the Explosive
Atmospheres Directive (99/92/EC) and the UK regulations, Dangerous Substances
and Explosive Atmospheres Regulations 2002 (DSEAR). Where potentially
explosive atmospheres may occur in the workplace, the requirements include,
identifying and classifying (zoning) areas where potentially explosive
atmospheres may occur; avoiding ignition sources in zoned areas, in
particular those from electrical and mechanical equipment; where necessary,
identifying the entrances to zoned areas; providing appropriate anti-static
clothing for employees; and before they come into operation, verifying the
overall explosion protection safety of areas where explosive atmospheres may
occur. ¡ All
safety valves design shall take into account discharging any released fluid
to a safe location, or stopping misdirection of fluid flows in order to avoid
hazardous outcome. ¡ Safety
markings and crash barriers will be provided to the aboveground piping,
digesters and the gas holder near the entrance. ¡ Lightning
protection installations will be installed following IEC 62305, BS EN 62305,
AS/NZS 1768, NFPA 780 or equivalent standards. ¡ A
10m high boundary wall with fire resistance will be provided in the vicinity
of the digester tanks, gasholders and gas purification equipment to protect
the equipment against external fires, and to provide some protection to
external areas from the effects of fire/explosion. ¡ Suitable
fire extinguishers will be provided within the site. An External Water Spray System (EWSS) will
be installed in appropriate areas, such as around the gasholders, gas
purification, desulphurisation units, and digester areas. The facilities will
also be equipped with fire and gas detection system and fire suppression
system. Stringent procedures are implemented to prohibit smoking or naked
flames to be used on-site. ¡ Fixed
crash barriers will be provided in areas where process equipment is adjacent
to the internal roadway to protect against vehicle collision. Adequate warning signage and lighting will
also be provided and maximum speed limit will also be in place. |
During
design and operation phases |
Design
Consultant / OWTF Operator |
P |
|
P |
|
EIAO
& EIAO TM Annex 4 |
Noise Impact (Construction) |
|||||||||
5.9.1 |
4.2.7 |
Good Site Practice Good site practice and noise management can
significantly reduce the impact of construction site activities on nearby
NSRs. The following package of measures should be followed during each phase
of construction: ¡ only
well-maintained plant to be operated on-site and plant should be serviced
regularly during the construction works; ¡ machines
and plant that may be in intermittent use to be shut down between work
periods or should be throttled down to a minimum; ¡ plant
known to emit noise strongly in one direction, should, where possible, be
orientated to direct noise away from the NSRs; ¡ mobile
plant should be sited as far away from NSRs as possible; and ¡ material
stockpiles and other structures to be effectively utilised, where
practicable, to screen noise from on-site construction activities. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
EIAO,
EIAO-TM and Noise Control Ordinance |
5.9.1 |
4.2.7 |
Selection of Quieter PME The recommended
quieter PME adopted in the assessment were taken from the EPD’s QPME
Inventory and British Standard, namely Noise
Control on Construction and Open Sites, BS 5228: Part 1: 2009 . It should be
noted that the silenced PME selected for assessment can be found in Hong
Kong. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
EIAO,
EIAO-TM and Noise Control Ordinance |
5.9.1 |
4.2.7 |
Use of Movable Noise Barriers Movable noise barriers can be very effective
in screening noise from particular items of plant when constructing the
Project. Noise barriers located along the active works area close to the
noise generating component of a PME could produce at least 10 dB(A) screening
for stationary plant and 5 dB(A) for mobile plant provided the direct line of
sight between the PME and the NSRs is blocked. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
EIAO,
EIAO-TM and Noise Control Ordinance |
5.9.1 |
4.2.7 |
Use of Noise Enclosure/ Acoustic Shed The use of noise enclosure or acoustic shed
is to cover stationary PME such as air compressor and generator. With the
adoption of the noise enclosure, the PME could be completely screened, and
noise reduction of 15 dB(A) can be achieved
according to the EIAO Guidance Note No.9/2010. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
EIAO,
EIAO-TM and Noise Control Ordinance |
5.9.1 |
4.2.7 |
Use of Noise Insulating Fabric Noise insulating fabric can also be adopted
for certain PME (e.g. pilling machine etc). The fabric
should be lapped such that there are no openings or gaps on the joints.
According to the approved Tsim Sha
Tsui Station Northern Subway EIA report
(AEIAR-127/2008), a noise reduction of 10 dB(A) can
be achieved for the PME lapped with the noise insulating fabric. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
EIAO,
EIAO-TM and Noise Control Ordinance |
Noise Impact (Operation) |
|||||||||
5.9.2 |
4.2.7 |
Fixed Plant Noise Specification of the maximum allowable sound
power levels of the proposed fixed plants should be followed. The following
noise reduction measures should be considered as far as practicable during
operation: ¡ Choose
quieter plant such as those which have been effectively silenced; ¡ Include
noise levels specification when ordering new plant (including chillier and
E/M equipment); ¡ Locate
fixed plant/louver away from any NSRs as far as practicable; ¡ Locate
fixed plant in walled plant rooms or in specially designed enclosures; ¡ Locate
noisy machines in a completely separate building; ¡ Install
direct noise mitigation measures including silencers, acoustic louvers and
acoustic enclosure where necessary; and ¡ Develop
and implement a regularly scheduled plant maintenance programme so that
equipment is properly operated and serviced in order to maintain a controlled
level of noise. |
Within
construction site / During operation phase / Throughout operation phase |
Design
Consultant /
Contractor |
P |
|
P |
|
EIAO,
EIAO-TM and Noise Control Ordinance |
Water Quality Impact (Construction) |
|||||||||
6.8.1.1 |
5.3 |
Construction site runoff The
site practices outlined in ProPECC Note PN 1/94
should be followed as far as practicable in order to minimise surface runoff
and the chance of erosion. The following measures are recommended to protect
water quality and sensitive uses of the coastal area, and when properly
implemented should be sufficient to adequately control site discharges so as
to avoid water quality impacts: ¡ At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels, earth
bunds or sand bag barriers should be provided on site to direct storm water
to silt removal facilities. The design of the temporary on-site drainage
system should be undertaken by the Contractor prior to the commencement of
construction; ¡ Sand/silt
removal facilities such as sand/silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements
of the TM standards under the WPCO.
The design of efficient silt removal facilities should be based on the
guidelines in Appendix A1 of ProPECC Note PN
1/94. Sizes may vary depending upon
the flow rate. The detailed design of the sand/silt traps should be
undertaken by the Contractors prior to the commencement of construction. ¡ All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation
at all times and particularly during rainstorms. Deposited silt and grit
should be regularly removed, at the onset of and after each rainstorm to
ensure that these facilities are functioning properly at all times. ¡ Measures
should be taken to minimize the ingress of site drainage into excavations. If
excavation of trenches in wet periods is necessary, they should be dug and
backfilled in short sections wherever practicable. Water pumped out from
foundation excavations should be discharged into storm drains via silt
removal facilities. ¡ All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An
adequately designed and sited wheel washing facility should be provided at
construction site exit where practicable. Wash-water should have sand and
silt settled out and removed regularly to ensure the continued efficiency of the
process. The section of access road leading to, and exiting from, the
wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle
tracking of soil and silty water to public roads
and drains. ¡ Open
stockpiles of construction materials or construction wastes on-site should be
covered with tarpaulin or similar fabric during rainstorms. Measures should
be taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system. ¡ Manholes
(including newly constructed ones) should be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris
being washed into the drainage system and stormwater
runoff being directed into foul sewers. ¡ Precautions
should be taken at any time of the year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecasted and actions to be
taken during or after rainstorms are summarized in Appendix A2 of ProPECC Note PN 1/94.
Particular attention should be paid to the control of silty surface runoff during storm events, especially for
areas located near steep slopes. ¡ Bentonite
slurries used in piling or slurry walling should be reconditioned and reused
wherever practicable. Temporary enclosed storage locations should be provided
on-site for any unused bentonite that needs to be
transported away after all the related construction activities are completed.
The requirements in ProPECC Note PN 1/94 should be
adhered to in the handling and disposal of bentonite
slurries. |
Within
construction site / Duration of the construction phase |
Contractor
|
|
P |
|
|
ProPECC Note PN 1/94 |
6.8.1.2 |
5.3 |
General
construction activities Construction solid waste, debris and refuse generated
on-site should be collected, handled and disposed of properly to avoid
entering any nearby storm water drain. Stockpiles of cement and other
construction materials should be kept covered when not being used. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
ProPECC Note PN 1/94 |
6.8.1.3 |
5.3 |
Excavation
works The construction programme
should be properly planned to minimise excavation works during the wet season
(April to September), temporarily exposed slope/soil surfaces should be
covered by a tarpaulin or other means, as far as practicable. Interception channels should be
provided (e.g. along the crest/edge of the excavation) to prevent storm
runoff from washing across exposed soil surfaces. Arrangements should be
in place to ensure that adequate surface protection measures can be safely
carried out well before the arrival of a rainstorm. Other measures that need to be
implemented before, during and after rainstorms are summarized in ProPECC PN 1/94. |
Within construction site / During
construction phase |
Contractor |
|
P |
|
|
ProPECC Note PN 1/94 |
6.8.1.4 |
5.3 |
Accidental
spillage ¡ The Contractor should register as a
chemical waste producer if chemical wastes are produced from construction
activities. The
Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in
particular the Waste Disposal (Chemical Waste) (General) Regulation should be
observed and complied with for control of chemical wastes. ¡ Maintenance of vehicles and equipment,
involving activities with potential for leakage and spillage, should only be
undertaken within areas appropriately equipped to control these discharges. ¡ Oils and fuels should only be stored in
designated areas which have pollution prevention facilities. To prevent
spillage of fuels and solvents to any nearby storm water drain, all fuel
tanks and storage areas should be provided with locks and be sited on sealed
areas, within bunds of a capacity equal to 110% of the storage capacity of
the largest tank. The bund should be drained of rainwater after a rain event. ¡ Disposal of chemical wastes should be
carried out in compliance with the Waste Disposal Ordinance. The
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes
published under the Waste Disposal Ordinance details the requirements to deal
with chemical wastes. General requirements are given
as follows: -
Suitable
containers should be used to hold the chemical wastes to avoid leakage or
spillage during storage, handling and transport. -
Chemical
waste containers should be suitably labelled, to notify and warn the
personnel who are handling the wastes, to avoid accidents. - Storage area should be selected at a safe
location on site and adequate space should be allocated to the storage area. |
Within construction site / During
construction phase |
Contractor |
|
P |
|
|
ProPECC Note PN 1/94 and Waste Disposal Ordinance |
6.8.1.5 |
5.3 |
Sewage
effluent from construction workforce Temporary sanitary facilities, such as
portable chemical toilets, should be employed on-site where necessary to
handle sewage from the workforce. A licensed contractor should be employed to
provide appropriate and adequate portable toilets and be responsible for
appropriate disposal and maintenance. |
Within
construction site / During construction phase |
Contractor
|
|
P |
|
|
ProPECC Note PN 1/94 |
Water Quality Impact (Operation) |
|||||||||
6.8.2.1 |
5.3 |
Sewage effluent and sewerage impact In order to
minimise the risk of exceeding capacity of the sewerage system, on-site
underground storage of effluent is recommended for the OWTF 2, with a
capacity of 6 hours of peak flow. Using the values presented in the
preliminary design, the on-site storage required to buffer excess capacity
would be equivalent to 30 m3. A below ground effluent retention
tank would function to store effluent produced during peak periods when usage
of the Sha Ling pumping station is high. Effluent
stored during such periods could then be pumped out of the retention tank and
discharged into the public sewer during off-peak times when capacity is
sufficient. |
Within
construction site / During design and operation phase |
Design
Consultant / OWTF Operator |
P |
|
P |
|
EIA
recommendations |
6.8.2.2 |
5.3 |
Wastewater generation from organic waste
treatment processes Wastewater
must be collected and diverted to the wastewater treatment plant (WWTP). An adequately
sized WWTP with technologies such as membrane bioreactor, reverse osmosis or
multi-phase separation process or system should be provided for the OWTF 2.
Polluting parameters in the effluent should be in compliance with the
requirements as specified in the TM-DSS. Leachate from the waste reception and composting
process § A drainage system will be provided at the reception area connecting to the
proposed onsite WWTP. The leachate would be treated in the WWTP and there would
be no direct discharge of leachate. Dewatering of the digestate
from the separators § The wastewater generated from the
dewatering of digestate from the digesters is
expected to be around 229.18 m3/day and a peak flow of
5.31L/s. The on-site WWTP will deploy
suitable treatment process in order to reduce the pollution level to an
acceptable standard. The effluent shall be treated according to the TM-DSS
standard before discharging to foul sewers. Condensate from biogas drying, odour treatment
and ventilation system § Condensate from biogas handling and
wastewater from the odour treatment process would be collected and
transferred to the WWTP. There is no direct discharge of wastewater to the
sewer. Washing of waste delivery trucks § Surplus wastewater generated from the
vehicle washing facilities would be collected and transferred to the WWTP for
further treatment before discharging to the foul sewer. Untreated wastewater from wastewater treatment plant § Maintenance of
the WWTP and its connection pipe work would be conducted regularly to confirm
the condition of
the holding tank and pipes. This will ensure early detection of any damage
for repair or replacement. Leakage of materials from WWTP § Regular
scheduled maintenance of the WWTP will be carried out to confirm the
condition of the facility and detect any damages at an early stage for repair
or replacement. |
Within construction site / During design
and operation phase |
Design
Consultant / OWTF Operator |
P |
|
P |
|
TM-DSS, Water
Pollution Control Ordinance |
6.8.2.3 |
5.3 |
Contaminated stormwater
runoff and accidental spillages Regular maintenance of plant facilities, as recommended in Section 6.8.2.2 of the EIA report, will be performed to confirm the condition
of plant facilities and detect any damage for repair or replacement. Training should be provided to the employees on handling
accidental spillage, so that in such cases, actions can be carried out
quickly to avoid runoff to nearby streams/drains. |
Within
construction site / During operation phase / Throughout operation phase |
OWTF
Operator |
|
|
P |
|
TM-DSS;
Water Pollution Control Ordinance |
Waste Management Implications
(Construction) |
|||||||||
7.6.1.1 |
6.3 |
Good
Site Practices Recommendations
for good site practices during the construction activities include: ¡ Obtain the relevant waste disposal
permits from appropriate authorities, in accordance with the Waste Disposal
Ordinance (Cap. 354) and subsidiary Regulations and the Land (Miscellaneous
Provisions) Ordinance (Cap. 28); ¡ Provide staff training for proper waste
management and chemical handling procedures; ¡ Provide sufficient waste disposal points
and regular waste collection; ¡ Provide appropriate measures to minimise
windblown litter and dust during transportation of waste by either covering
trucks or by transporting wastes in enclosed containers; ¡ Carry out regular cleaning and
maintenance programme for drainage systems, sumps and oil interceptors; ¡ Separate chemical wastes for special
handling and disposal to licensed facilities for treatment; and ¡ Employ licensed waste collectors to
collect waste. |
Project
construction site / Throughout construction stage / Until completion of all
construction activities |
Contractor
|
|
P |
|
|
Waste Disposal Ordinance; Regulation and the Land (Miscellaneous
Provisions) Ordinance; Waste Disposal (Chemical Wastes) (General)
Regulation; Technical Circular (Works) No. 19/2005
Environmental Management on Construction Site |
7.6.1.2 |
6.3 |
Waste
Reduction Measures Recommendations
to achieve waste reduction include: ¡ Design foundation
works to minimise the amount of excavated material to be generated; ¡ Provide training on
the importance of site cleanliness and appropriate waste management
procedures, including waste reduction, reuse and recycling; ¡ Sort demolition debris and
excavated materials from demolition works to recover reusable/recyclable
portions ¡ Segregation and storage of
different types of waste in different containers
or skips to enhance reuse or recycling of materials and their proper
disposal ¡ Encourage collection of
recyclable waste such as waste paper and aluminium cans by providing separate
labelled bins to enable such waste to be segregated from other general refuse
generated by the work force ¡ Plan the use of construction
materials carefully to minimise amount of waste generated and avoid
unnecessary generation of waste |
Project
construction site / Throughout construction stage / Until completion of all
construction activities |
Contractor
|
P |
P |
|
|
Waste Disposal Ordinance |
7.6.1.3 |
6.3 |
Excavated
and C&D Materials In
order to minimise impacts resulting from collection and transportation of
C&D material for off-site disposal, the excavated materials should be
reused on-site as fill material as backfilling material and for landscaping
works far as practicable. Other mitigation requirements are: ¡ A Waste Management
Plan (WMP), which becomes part of the Environmental Management Plan (EMP),
should be prepared in accordance with ETWB TC(W) No.19/2005; ¡ A recording system
for the amount of wastes generated, recycled and disposed of (including the
disposal sites) should be adopted for easy tracking; and ¡ In order to monitor
the disposal of excavated and non-inert C&D material at public filling
facilities and landfills and to control fly-tipping, a trip-ticket system
should be adopted (refer to DEVB TC(W) No. 6/2010). |
Project
construction site / Throughout construction stage / Until completion of all
construction activities |
Contractor
|
P |
P |
|
|
Waste Disposal Ordinance ; DEVB Technical Circular (Works) No.6/2010
for Trip Ticket System for Disposal of Construction & Demolition
Materials; Technical Circular (Works) No. 19/2005
Environmental Management on Construction Site |
7.6.1.4 |
6.3 |
Chemical
Waste Should
chemical wastes be produced at the construction site, the Contractor would be
required to register with EPD as a Chemical Waste Producer and to follow the
guidelines stated in the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes. Good quality containers compatible with the chemical
wastes should be used, and incompatible chemicals should be stored
separately. Appropriate labels should be securely attached on each chemical
waste container indicating the corresponding chemical characteristics of the
chemical waste (such as explosive, flammable, oxidizing, irritant, toxic,
harmful, or corrosive). The Contractor should employ a licensed collector to
transport and dispose of the chemical wastes, to either the CWTC in Tsing Yi, or any other licensed facilities, in accordance
with the Waste Disposal (Chemical Waste) (General) Regulation. |
Project
construction site / Throughout construction stage / Until completion of all
construction activities |
Contractor
|
|
P |
|
|
Code of Practice
on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General)
Regulation |
7.6.1.5 |
6.3 |
General
Refuse General refuse should be stored in enclosed
bins or compaction units separated from excavated and non-inert C&D
materials. A reputable waste collector should be employed by the Contractor to remove general refuse from the
site, separately from inert C&D materials. Preferably an enclosed and
covered area should be provided to reduce the occurrence of 'wind blown' light material. |
Project
construction site / Throughout construction stage / Until completion of all
construction activities |
Contractor
|
|
P |
|
|
Waste
Disposal Ordinance and Public Health and Municipal Services Ordinance -
Public Cleansing and Prevention of Nuisances Regulation |
Waste Management Implications (Operation) |
|||||||||
7.6.2.1 |
6.3 |
Good site practices Adoption of
the following good operational practices should be recommended to minimise
waste management impacts: ¡ Obtain the necessary
waste disposal permits from the appropriate authorities, in accordance with
the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Chemical Waste)
(General) Regulation and the Land (Miscellaneous Provision) Ordinance (Cap.
28); ¡ Nomination of an
approved person to be responsible for good site practice, arrangements for
collection and effective disposal to an appropriate facility of all wastes
generated at the site; ¡ Use of a waste
haulier licensed to collect specific category of waste; ¡ A trip-ticket system
should be included as one of the contractual requirements and implemented by
the Environmental Team to monitor the disposal of solid wastes at public
filling facilities and landfills, and to control fly tipping. Reference
should be made to DEVB TC(W) No. 6/2010. ¡ Training of site
personnel in proper waste management and chemical waste handling procedures; ¡ Separation of
chemical wastes for special handling and appropriate treatment at a licensed
facility; ¡ Routine cleaning and
maintenance programme for drainage systems, sumps and oil interceptors; ¡ Provision of
sufficient waste disposal points and regular collection for disposal; ¡ Adoption of
appropriate measures to minimise windblown litter and dust during
transportation of waste, such as covering trucks or transporting wastes in
enclosed containers; and, ¡ Implementation of a
recording system for the amount of wastes generated, recycled and disposed of
(including the disposal sites). |
Construction
site / On a regular basis / Throughout operation stage |
OWTF
Operator |
|
|
P |
|
Waste Disposal Ordinance; Waste Disposal (Chemical Waste) (General); Regulation and the Land (Miscellaneous
Provision) Ordinance; DEVB Technical Circular (Works) No. 6/2010. |
7.6.2.2 |
6.3 |
Waste reduction measures Adoption of the following good operational
practices should be recommended to ensure waste reduction: ¡ Segregation and
storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of materials and their proper
disposal; ¡ Encourage collection
of aluminium cans, plastic bottles and packaging material (e.g. carton boxes)
and office paper by individual collectors.
Separate labelled bins should be provided to help segregate this waste
from other general refuse generated by the work force; and ¡ Any unused chemicals
or those with remaining functional capacity should be reused as far as
practicable. |
Construction
site / On a regular basis / Throughout operation stage |
OWTF
Operator |
|
|
P |
|
Waste Disposal Ordinance; Waste Disposal (Chemical Waste) (General); Regulation and the Land (Miscellaneous
Provision) Ordinance |
7.6.2.3 |
6.3 |
Waste generated from pre-treatment
process Wastes
generated from pre-treatment process should be recycled as far as
possible. Wastes generated from
pre-treatment process should also be separated from any chemical waste and
stored in covered skips. The recyclables
should be collected by licensed collectors, while the rest of the waste
should be removed from the site on a daily basis to minimise odour, pest and
litter impacts. Open burning must be
strictly prohibited. |
Pre-treatment
process / Throughout operation stage |
OWTF
Operator |
|
|
P |
|
Waste Disposal (Chemical Waste) (General) |
7.6.2.4 |
6.3 |
Chemical Waste ¡ Chemical waste
generated from machinery maintenance and servicing should be managed in
accordance with the Code of Practice on the Packaging, Labelling and storage
of Chemical Wastes under the provisions of Waste Disposal (Chemical Waste)
(General) Regulation. The chemical waste should be collected by drum-type
containers and, when transported off-site, removed by licensed chemical waste
contractors. Alternatively, some of the chemical waste may be retained
on-site for re-use by the Project in the manufacture of biogas or other
products, subject to their composition being confirmed as suitable for such
application. ¡ Plant /
equipment maintenance schedules should be planned in order to minimise the
generation of chemical waste. ¡ Non-recyclable
chemical wastes and lubricants should be disposed of at appropriate
facilities, such as CWTC. Copies or
counterfoils from collection receipts issued by the licensed waste collector
should be kept for recording purpose. ¡ Recyclable
chemical waste will be transported off-site for treatment by a licensed
collector. The Contractor will need to
register with EPD as a chemical waste producer. |
Construction
site Throughout operation stage |
OWTF
Operator |
|
|
P |
|
Code of Practice
on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General)
Regulation |
7.6.2.5 |
6.3 |
General Refuse ¡ Waste
generated in site offices should be reduced through segregation and
collection of recyclables. To promote
the recycling of wastes such as used paper, aluminium cans and plastic
bottles, it is recommended that recycling bins should be clearly labelled and
placed at locations with easy access.
For the collection of recyclable materials, they should be collected
by licensed collectors. ¡ General
refuse, other than segregated recyclable wastes, should be separated from any
chemical waste and stored in covered skips.
The general refuse should be removed from the site on a daily basis to
minimise odour, pest and litter impacts.
Also, open burning of refuse must be strictly prohibited. |
Construction
site / On a regular basis / Throughout operation stage |
OWTF
Operator |
|
|
P |
|
Waste
Disposal Ordinance |
Ecological Impact (Construction) |
|||||||||
8.7 |
7.3 |
For precautionary purposes and to further
ensure that no wild flora species of conservation interest will be affected, prior
to commencement of any construction works, it is recommended to conduct a detailed
vegetation survey as baseline monitoring to update the exact locations,
number and condition of individuals of Aquilaria sinensis and any other floral species
of conservation interest within the Project Area. A Vegetation Survey Report
summarizing the findings and recommendations of the detailed vegetation
survey should be prepared and submitted to AFCD for approval no later than
one month prior to commencement of construction works. |
Before
Project commencement |
OWTF
Operator |
P |
|
|
|
EIAO-TM |
8.7 |
7.3 |
During
construction phase, erection of a temporary protective fence along the
plantation area where trees and vegetation, including
those of conservation concern identified under the detailed vegetation
survey, would be retained within the Project Area is recommended for precautionary
purposes to avoid any potential impact from construction activities such as
vehicle movement and materials storage. Establishment of the protective fence
could also raise the awareness of personnel to be present and protection of
the plants. While the protective fence should be properly maintained,
monitoring of individuals of Aquilaria sinensis and any other floral species of conservation
interest identified in the detailed vegetation survey during construction
phase on a monthly basis should be conducted to make sure that they are not
affected by the construction works of the Project. |
Throughout
construction stage |
OWTF
Operator |
|
P |
|
|
EIAO-TM |
Ecological Impact (Operation) |
|||||||||
|
|
No
mitigation measure is required. |
|
|
|
|
|
|
|
Landscape and Visual Impact (Construction) |
|||||||||
Table 10.7 (CP1) |
Table
8.1 (CP1) |
Preservation of Existing Vegetation The
development proposals would avoid disturbance to the existing trees as far as
practicable within the confines of the development site. A preliminary tree survey has been
undertaken to establish the existing resources. A tree survey review with formal tree
removal application will be submitted to the relevant government departments
for approval in accordance with ETWB TC(W) 03/2006
Tree Preservation, during the detailed design phase of the Project. Based on
the preliminary findings it would be possible to retain 441 of the existing
trees. If possible, all trees which are not in conflict with the proposals
would be retained and shall be protected through the means of fencing, where
appropriate, to prevent potential damage to tree canopies and root zones from
vehicles and materials storage.
Specifications for the protection of existing trees will be circulated
to the relevant government authorities for approval together with the formal
tree removal application. |
Construction
site / Throughout construction stage / Until completion of all construction
activities |
Contractor |
P |
P |
|
|
Technical Circular (Works) No. 3/2006 |
Table 10.7 (CP2) |
Table 8.1 (CP2) |
Control of site construction activities ¡ Storage of materials should be carefully
arranged to minimise potential landscape and visual impact. ¡ The location and appearance of site
accommodation should be carefully designed to minimise potential landscape
and visual impact. ¡ Site lighting should be carefully
designed to prevent light spillage, ¡ Extent of the works area and construction
period should be minimised as far as practicable. ¡ Screen hoarding with compatible design to
blend into the surrounding natural environmental should be considered. ¡ Temporary works areas should be
reinstated at the earliest possible opportunity. |
Construction
site / Throughout construction stage / Until completion of all construction
activities |
Contractor |
P |
P |
|
|
EIAO-TM |
Table 10.7
(CP3) |
Table
8.1 (CP3) |
Transplantation of existing trees Under
current proposal, no tree is recommended to be transplanted since the trees
in conflict with the proposed works are not suitable to be transplanted.
However, should transplantation be proposed in the detailed design stage
after an update tree survey, the recommended final recipient sites should be
adjacent to their current locations. Enough time
should be reserved for tree transplantation works to increase the survival
rate of the transplanting trees. To
ensure the survival of transplanted trees, protection work should be
considered. The tree transplantation
proposal will be submitted to relevant authorities for approval together with
the formal tree removal application. |
Construction
site / Throughout construction stage / Until completion of all construction
activities |
Contractor |
P |
P |
|
|
Technical
Circular (Works) No. 3/2006 |
Landscape and Visual Impact (Operation) |
|||||||||
Table 10.8 (OP1) |
Table
8.2 (OP1) |
Design of the Proposed OWTF OWTF
will incorporate design features as part of design mitigation measures
including ·
Integrated
design approach - the location of OWTF should be within the existing
Livestock Waste Composting Plant, as far as technically feasible. The location and orientation of the OWTF
should be away from landscape and visually sensitive areas such as ponds and
woodlands. ·
Building
massing – the proposed use of simple responsive design includes having
specific height profile requirement such as, single-storey, lower than the
adjacent building structures, and avoiding large built structure for
supporting facilities to reduce the intrusion of mass in the rural areas. ·
Treatment
of built structures – the structural design should seek to reduce the
apparent visual mass of the facilities further through the use of natural
materials such as wooden frames or other sustainable materials such as
recycled plastics. ·
Responsive
building finishes – Natural tones should be considered for the colour
palette for proposed structures.
Non-reflective finishes are recommended on the outward facing building
facades to reduce glare effect. ·
Responsive
lighting design – Aesthetic design of architectural and lighting with
following glare design measures: -
Directional and full cut off lighting is
recommended within the boundaries of OWTF to minimise light spillage to the
surroundings; -
Minimise geographical spread of lighting, only
applying for safety at the key access points and staircases; and Limited
lighting intensity to meet the minimum safety and operation requirement. |
Construction
site / During design stage |
Design
Consultant / OWTF Operator |
P |
|
|
|
EIAO-TM |
Table 10.8 (OP2) |
Table 8.2 (OP2) |
Amenity / Compensatory Planting Tree
retention within the works area is considered to be important. New tree plantings will be concentrated in
the proposed amenity areas along the boundaries of the site and along the
exterior of OWTF buildings. Although a
preliminary planting proposal is not yet available at the moment of producing
this EIA Report, anticipated new tree planting within the Project site should
be able to fully compensate for the loss of 14 trees proposed to be felled in
terms of both quantity and quality. 441
existing trees will be retained through preserving them at their current
locations. Establishment of newly
planted trees is expected. Trees with
high amenity value will be placed along the access routes to provide shade
and soften the hard structures of OWFT buildings. Amenity plantings will utilise native tree
species found on existing neighbouring slopes or woodland areas to improve
the ecological connectivity between existing habitats and create a coherent
landscape network. Tree species with
aggressive roots should be avoided to prevent damage to OWTF buildings and
structures. Trees with high or
moderate amenity value and low to medium maintenance should be considered as
part of landscape resource enhancement.
Recommended tree species include Celtis sinensis and Liquidambar formosana. These proposals
will be subjected to review at detail design stage of the Project. |
Construction
site / during design and operation stage |
Design
Consultant / OWTF Operator |
P |
|
P |
|
Technical Circular (Works) Nos. 7/2002 and 3/2006 |
Table 10.8 (OP3) |
Table 8.2 (OP3) |
Treatment of Slopes In
accordance with GEO Publication No. 1/2011 “Technical Guidelines on
Landscape Treatment for
Slopes”, these engineering structures will be aesthetically enhanced
through the use of soft landscape works including tree and shrub planting to
give man-made slopes a natural appearance, blending into the natural
landscape. Whip-sized plantings are preferred on the face of soil cut slopes,
at the crest and toe of the slope and within berm planters. These smaller, younger plants can adapt to
their new growing conditions quicker than larger sized stock and establish a
naturalistic effect rapidly. Recommended tree species include Mallotus paniculatus, Broussonetia papyrifera and
Alangium chinense. |
Construction
site / during design and operation stage |
Design
Consultant / OWTF Operator |
P |
|
P |
|
GEO
Publication No. 1/2011
“Technical Guidelines on Landscape Treatment for Slopes |
Table 10.8 (OP4) |
Table 8.2 (OP4) |
Amenity enhancement Rooftop
greening and vertical greening to mitigate the visual impact of taller
structures can soften the façade of OWTF structures. Frameworks utilised for vertical greening
should appear naturalistic. |
Construction
site / during design and operation stage |
Design
Consultant / OWTF Operator |
P |
|
P |
|
Technical Circular (Works) No. 7/2002 |
Remarks:
1. Des – Design Stage,
C – Construction Stage, O – Operation, Dec - Decommissioning