Development of
Organic Waste Treatment Facilities, Phase 2
Environmental Impact Assessment Report
Chapter Title
Tables
Table 6.1___ Water Quality
Objective for the Deep Bay WCZ
Table 6.2:__ Summary of River Water Quality
Monitoring Data at River Indus (2011)
Table 6.3:__ Summary
of Water Sampling on 15 April 2013
Table
6.4: _ Estimated
Wastewater Volumes by Source at OWTF2_
Figures
Figure
6.1 Preliminary Layout of
Proposed Sewer Connection
Figure
6.2 Water Quality Impact
Assessment Study Area and Water Sensitive Receivers
Figure
6.3 Water Quality Sampling
Locations
This section presents an assessment of the potential water quality impacts associated with the construction and operation phases of the Project. Recommendations for mitigation measures have been made, where necessary, to reduce the identified water quality impacts to an acceptable level.
The Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM) is issued by the Environmental
Protection Department under Section 16 of the EIAO. It specifies the assessment
method and criteria that needs to be followed in EIA studies. Reference
sections in the EIAO-TM provide the details of the assessment criteria and
guidelines that are relevant to the water quality impact assessment, including:
¡ Annex 6 Criteria for Evaluating Water
Pollution
¡ Annex 14 Guidelines for Assessment of Water
Pollution
The Water Pollution Control Ordinance (WPCO)
(Cap.358) provides the major statutory framework for the protection and control
of water quality in Hong Kong. According to the Ordinance and its subsidiary
legislation, the whole Hong Kong waters are divided into ten Water Control
Zones (WCZs). Water Quality Objectives (WQOs) were established based on
different water regimes (marine waters, inland waters, bathing beaches
subzones, secondary contact recreation subzones and fish culture subzones) to
protect the beneficial uses of water quality in WCZs. Specific WQOs are applied
to each WCZ. The Project is located within the Deep Bay WCZ and its
corresponding WQOs are listed in Table 6.1.
Table 6.1 Water Quality Objective for the Deep Bay WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive Odour, Tints |
Not to be present |
Whole zone |
Colour |
Not to exceed 30 Hazen units |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
Not to exceed 50 Hazen units |
Yuen Long & Kam Tin (Lower) Subzone and other inland waters |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E.
coli |
Not to exceed 610 per 100 mL, calculated as the geometric mean of the all samples taken in 1 calendar year |
Secondary Contact Recreation Subzone and Maricultural Subzone |
|
Should be zero per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals between 7 and 21 days |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
Not to exceed 1000 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals between 7 and 21 days |
Yuen Long & Kam Tin (Lower) Subzone and other inland waters |
|
Not to exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days |
Yung Long Bathing Beach Subzone |
Depth-averaged Dissolved Oxygen (DO) |
Not less than 4.0 mg L-1 for 90% of samples |
Outer Marine Subzone excepting Mariculture Subzone |
Dissolved Oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg L-1 for 90% of samples |
Outer Marine Subzone excepting Mariculture Subzone |
Dissolved Oxygen (DO) |
Not less than 4.0 mg L-1 for 90%of the sampling occasions during the year, values taken at 1m below surface |
Inner Marine Subzone excepting Mariculture Subzone |
|
Not less than 5.0 mg L-1 for 90%of the sampling occasions during the year, values taken at 1m below surface |
Mariculture Subzone |
|
Not less than 4.0 mg L-1 |
Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground Subzones and other inland waters of the Zone |
pH |
To be in the range of 6.5 - 8.5, change due to waste discharge not to exceed 0.2 |
Marine waters excepting Yung Long Bathing Beach Subzone |
|
Not to exceed the range of 6.5 – 8.5 due to waste discharge |
Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
To be in the range of 6.0 - 9.0 |
Other inland waters |
|
To be in the range of 6.0 – 9.0 for 95% of samples. Waste discharge shall not cause the natural pH range to be extended by more than 0.5 units |
Yung Long Bathing Beach Subzone |
Salinity |
Change due to waste discharge not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to waste discharge not to exceed 2 oC |
Whole zone |
Suspended solids |
Waste discharge not to raise the natural ambient level by 30% nor cause the accumulation of suspended solids which may adversely affect aquatic communities |
Marine waters |
|
Annual median not to exceed 20 mg L-1 due to waste discharges |
Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Ganges Subzone, Indus Subzone, Water Gathering Ground Subzones and other inland waters |
Unionized Ammonia |
Annual mean not to exceed 0.021 mg L-1 as unionised form |
Whole zone |
Nutrients |
Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants. |
Inner and Outer Marine
Subzone |
|
Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.7 milligram per litre, expressed as annual mean. |
Inner Marine Subzone |
|
Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 milligram per litre, expressed as annual water column average (arithmetic mean of at least 2 measurements at 1 metre below surface and 1 metre above seabed). |
Outer Marine Subzone |
5-Day Biochemical Oxygen Demand (BOD5) |
Not to exceed 3 mg L-1 |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
Not to exceed 5 mg L-1 |
Yuen Long & Kam Tin (Lower) Subzone and other inland waters |
Chemical Oxygen Demand |
Not to exceed 15 mg L-1 |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
Not to exceed 30 mg L-1 |
Yuen Long & Kam Tin (Lower) Subzone and other inland waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
|
Waste Discharge should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Phenol |
Not to be present to produce a specific odour, or in concentration greater than 0.05 mg L-1 as C6H5OH |
Yung Long Bathing Beach Subzone |
Turbidity |
Not to reduce light transmission substantially from normal level due to waste discharges |
Yung Long Bathing Beach Subzone |
Source: Statement of Water Quality Objectives (Deep Bay Water Control Zone).
Discharges of effluents are subject to control under the WPCO. The Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) sets limits for effluent discharges. Specific limits apply for different areas and are different between surface waters and sewers. The limits vary with the rate of effluent flow. Sewage from the proposed construction activities would be discharged into inland waters and therefore should comply with the standards for effluent discharged into inland waters, as shown in Table 6 of the TM-DSS. Sewage from the proposed operation activities would be discharged to the public sewerage network leading to Shek Wu Hui Sewage Treatment Works and therefore should comply with the ‘Standards for effluents discharged into foul sewers leading to Government sewage treatment plants’, and the ‘Standards for effluents discharged into foul sewers leading to Government sewage treatment plants with microbial treatment’, as shown in Table 1 and 2 of the TM-DSS.
Effluent treatment is required prior to discharge into the water courses in the Deep Bay Area, in order to meet the criteria of “no net increase in pollution load requirement”. The underlying principle is to protect the important habitats and wildlife of the Deep Bay region.
A practice note for professional persons was issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The Practice Note for Professional Persons on Construction Site Drainage (ProPECC Note PN 1/94) provides good practice guidelines for dealing with various types of discharge from a construction site. Practices outlined in ProPECC Note PN 1/94 should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.
The
OWTF 2 is designed to
treat 300 tons/day of organic waste generated by the Commercial and Industrial
(C&I) Sectors. The organic waste to be received at the site will be
collected from various sources in the New Territories.
The processing of organic waste includes pre-treatment, anaerobic digestion,
and post-treatment (such as dewatering and composting). It is predicted that approximately
213 m3 of effluent per day will be generated during processing that
will require treatment and disposal. (A detailed breakdown
of the wastewater generation is presented in Table 6.4).
The Project site area
and alignment of a new sewer to connect the site to the sewerage network is
shown in Figure 6.1.
The scope of the works within Project comprises the following:
¡ Demolition and removal of the existing above
ground structures of the Livestock Waste Composting Facility;
¡ Construction of superstructure for an office
and enclosed waste reception area;
¡ Installation and operation of organic waste
treatment facilities;
¡ Installation and operation of biogas holding
tanks;
¡ Installation and operation of air treatment,
auxiliary facilities for biogas processing, utilisation and transmission;
Though not part of the Project at Sha Ling the following activities are identified and
assessed as a cumulative impact:
¡ Road widening of carriageway at
Kong Nga Po Road;
¡ Connection for OWTF2 to Sha Ling LPS and the existing NENT sewage network to discharge at SWHSTW.
According to Clause 3.4.6.2 of the EIA Study Brief, water quality impact assessment has been carried out in all areas within 500m from the Project site boundary and other areas such as water courses and the associated water systems in the vicinity that might be impacted by the Project.
The Project site is located at Sha Ling in the North District, within the Frontier Closed
Area (See Figure 6.2).
There are no areas of conservation value, ecological importance or mariculture activities identified in the vicinity of the
Project site. Four fish ponds and two
watercourses are identified as the nearby inland water sensitive
receivers. The closest water sensitive receiver identified in this assessment are the water ponds
and a small stream located on the northeast side of the Project site.
There are no EPD marine and river water quality monitoring stations in vicinity of the Project site. The nearest EPD marine water quality monitoring station DM1 in the Inner Deep Bay is located more than 1.5 km from the Project site boundary. The nearest inland water monitoring stations are identified about 1 km at the upstream end of Shenzhen River, River Indus and its tributaries. The nearest river water quality monitoring stations (IN1 and IN2) in the River Indus are located at about 1.5 km south-west and 1.2 km south of the Project site boundary. EPD monitoring data collected at these two monitoring stations in 2011 is summarised in Table 6.2.
According to the River Water Quality in Hong Kong in 2011, which is the latest available information from EPD, the upstream section of River Indus has a relatively high WQO compliance rate of 75% and rated with “Excellent” in the Water Quality Index (WQI). The compliance rate decreases downstream, with the midstream and downstream stations rated with “Good” and “Bad” WQI. The compliance rates of the midstream station (IN2) and the downstream station (IN1) were 85% and 42% for River Indus. The report suggested that the downstream of River Indus is affected by backflow from Shenzhen River [1].
Table 6.2: Summary of River Water Quality Monitoring Data at River Indus (2011)
Parameter |
River WQOs |
River Indus |
|
IN1 |
IN2 |
||
Dissolved Oxygen (mg/L) |
≥ 4 |
3.7 (2.4
– 7.8) |
5.8 (3.6
– 10.3) |
pH |
6.5 – 8.5 |
7.3 (7.1
– 7.4) |
7.4 (7.1
– 8.3) |
Suspended solids (mg/L) |
≤ 20 |
36 (21
– 460) |
11 (7
- 40) |
5-day Biochemical Oxygen Demand (mg/L) |
≤ 3 |
7 (3
– 28) |
3 (2
– 10) |
Chemical Oxygen Demand (mg/L) |
≤ 15 |
15 (8
- 28) |
9 (6
– 16) |
Oil & grease (mg/L) |
NA |
<0.5 (<0.5
– 0.8) |
<0.5 (<0.5
– 0.9) |
Faecal coliforms (cfu/100mL) |
NA |
420,000 (29,000
– 4,500,000) |
39,000 (9,000
– 350,000) |
E. coli (cfu/100mL) |
NA |
180,000 (7,000
– 2,500,000) |
4,100 (280
– 66,000) |
Ammonia-nitrogen (mg/L) |
NA |
4.75 (0.95
– 12.00) |
0.77 (0.25
– 2.70) |
Nitrate-nitrogen (mg/L) |
NA |
2.85 (0.04
– 4.90) |
1.20 (0.81
– 1.80) |
Total Kjeldahl nitrogen (mg/L) |
NA |
6.05 (1.80
– 15.00) |
1.55 (0.79
– 3.40) |
Ortho-phosphate (mg/L) |
NA |
0.24 (0.04
– 0.41) |
0.11 (0.03
– 0.16) |
Total phosphate (mg/L) |
NA |
0.66 (0.36
– 3.40) |
0.21 (0.14
– 0.32) |
Total Sulphide (mg/L) |
NA |
<0.02 (<0.02
– 0.34) |
<0.02 (<0.02
– <0.02) |
Aluminium (µg/L) |
NA |
295 (190
– 3,200) |
140 (<50
– 490) |
Cadmium (µg/L) |
NA |
<0.1 (<0.1
– 0.5) |
<0.1 (<0.1
– <0.1) |
Chromium (µg/L) |
NA |
5 (1
– 67) |
<1 (<1
– <1) |
Copper (µg/L) |
NA |
7 (3
– 12) |
2 (1
– 3) |
Lead (µg/L) |
NA |
3 (2
– 19) |
2 (1
– 5) |
Zinc (µg/L) |
NA |
40 (20
– 280) |
20 (10
– 30) |
Flow (L/s) |
NA |
NM |
NM |
Source: River Water Quality in Hong Kong in 2011
Remarks:
1. Data presented are in annual medians of monthly samples; except those for faecal coliforms and E. coli which are in annual geometric means.
2. Figures in brackets are annual ranges
3. NM – no measurement taken
4. cfu – colony forming unit
5. Values at or below laboratory reporting limits are presented as laboratory reporting limits
6. Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits
Water sampling at the nearby sensitive receivers was conducted on 15 April 2013. Two locations were chosen as the upstream (W3) and downstream (W1) of the same water course and sampling was also conducted at a fish pond (W2) west of the Project area. The locations of the sampling points are identified in Figure 6.3.
The sampling results show compliance with WQO for the tested parameters at W1 and W3, but exceedances of BOD at W2. The monitoring results are summarised in Table 6.3.
Table 6.3: Summary of Water Sampling on 15 April 2013
|
|
|
|
Monitoring Locations |
|||||
Parameters |
Unit |
LOR |
|
W1 |
W2 |
W3 |
|||
pH |
|
0.1 |
Mean |
6.8 |
8.2 |
6.8 |
|||
Range |
6.7 |
6.8 |
8.1 |
8.2 |
6.8 |
6.8 |
|||
Turbidity |
NTU |
1 |
Mean |
2 |
23 |
19 |
|||
Range |
2 |
3 |
22 |
23 |
19 |
19 |
|||
D.O. Content |
mg/L |
0.1 |
Mean |
4.3 |
12.8 |
5.9 |
|||
Range |
4.3 |
4.3 |
12.7 |
12.8 |
5.9 |
5.9 |
|||
D.O. Percentage |
% |
1 |
Mean |
50 |
154 |
72 |
|||
Range |
50 |
50 |
154 |
155 |
72 |
72 |
|||
Suspended Solids |
mg/L |
2 |
Mean |
<2 |
16 |
4 |
|||
Range |
<2 |
<2 |
15 |
16 |
4 |
4 |
|||
5-day Biochemical Oxygen Demand |
mg/L |
2 |
Mean |
<2 |
10 |
<2 |
|||
Range |
<2 |
<2 |
9 |
11 |
<2 |
<2 |
In accordance with Clause 3.4.6 and Appendix D of the EIA Study Brief, the assessment has been carried out in accordance with Annexes 6 and 14 of the EIAO-TM.
Potential pollutants from point discharges and non-point sources discharging as surface water runoff, sewage or polluted discharge generated from the Project that could affect the quality of surface water runoff and nearby waters have been considered. The potential water quality impacts and their impact significance have been determined. Mitigation measures to reduce any identified adverse impacts on water quality to acceptable levels have been also determined.
Potential sources of water quality impact associated with
construction activities for the Project include:
¡ Construction site runoff;
¡ General construction activities;
¡ Excavation works;
¡ Accidental spillage; and,
¡ Sewage effluent from the construction workforce.
The surface runoff from construction works areas may contain
suspended solids (SS), contaminants and increased loads of sediments. Potential
sources of pollution from site drainage include:
¡ Runoff and erosion from site surfaces, drainage channels, earth working areas and stockpiles;
¡ Release of any bentonite slurries, concrete washings and other grouting materials with construction runoff and storm water;
¡ Wash water from dust suppression sprays and wheel wash facilities; and,
¡ Fuel, oil, solvents and lubricants from maintenance of construction vehicles and mechanical equipment.
Sediment laden runoff particularly from works areas subjected to excavation or earth works, if uncontrolled, may carry pollutants (adsorbed onto the particle surfaces) into any nearby stormwater drains. Mitigation measures and good site practices should be implemented to control construction site runoff and drainage from the works area, to avoid runoff and drainage water with high levels of SS entering the nearby stormwater system.
On-site construction activities may result in water pollution from the following:
¡ Uncontrolled discharge of debris and rubbish such as packaging, construction materials and refuse
¡ Spillages of liquids stored on-site, such as oil, diesel and solvents etc.
Good construction and site management practices should be observed to ensure that litter, fuels and solvents do not enter the drainage system and existing streams and rivers.
Construction of the OWTF2 involves excavation to form the foundation. Excavated material may have to be stored on-site before being sorted, reused or transported off-site. On-site storage of loose soil in stockpiles may generate site runoff during rainfall, if the stockpile is not properly covered. Site runoff of this kind contains high levels of suspended solid and may lead to increased SS levels and oxygen demand in the water environment if washed into nearby streams or storm drains.
A variety of chemicals could be stored on-site during the construction phase of the Project. These chemicals may include petroleum products, spent lubricants, oil and grease, mineral oil, solvent and other chemicals. Accidental spillages of these chemicals may contaminate the top soil at the construction site. The contaminated soil particles in the works area may then be washed away as construction site runoff and cause water pollution.
Domestic sewage would be generated from the workforce during the construction phase. However, portable chemical toilets will be provided within the construction site. The Contractor would have the responsibility to ensure that chemical toilets are used and properly maintained, and that licensed Contractors are employed to collect and dispose of the waste off-site at approved locations. Therefore no water quality impacts are anticipated from this activity.
Potential areas of concern on operation phase water quality impacts include:
¡ Sewage effluents and sewerage impact;
¡ Wastewater generation from the organic waste treatment processes; and
¡ Contaminated stormwater runoff and accidental spillages.
Sewage and wastewater effluents generated from the operation staff and visitors at the proposed facility can contain high levels of nutrients. Direct discharge of domestic sewage into the water environment would cause excessive algal growth and reduce dissolved oxygen in the water body. Connection to the existing NENT sewerage network is required, which will be planned during the design stage.
The proposed OWTF 2 will convert source-separated organic waste into compost and biogas. The plant will process around 300 tonnes of organic waste per day when in operation. Details of possible wastewater sources are shown in Table 6.4:
Table 6.4: Estimated Wastewater Volumes by Source at OWTF2
Element |
m3 / year |
m3 / day |
Peak |
From separator to WWTP |
83,651 |
229.18 |
5.31 |
From other sources to WWTP (i.e. domestic wastewater, wash water other than vehicle washing water, and leachate) |
14,381 |
39.40 |
0.91 |
Total to WWTP |
98,032 |
268.58 |
6.22 |
Sludge (disposal) |
3,657 |
10.02 |
0.23 |
Filtrate recycled to compost |
919 |
2.52 |
0.06 |
Treated effluent total |
93,457 |
256.05 |
5.93 |
Treated effluent recycled to pulper |
15,695 |
43.00 |
1.00 |
Treated effluent to public sewer |
77,762 |
213.05 |
4.93 |
Leachate
from the waste reception and composting process
Organic waste would be collected and transported to OWTF 2 by dedicated organic waste collection vehicles. On arrival at OWTF 2, the source-separated organic waste would be tipped from the dedicated organic waste collection vehicles into an enclosed receiving pit. Due to the wet nature of organic waste, some leachate generation is anticipated in the reception area.
Dewatering
of digestate
The outgoing material from the digester will be conveyed to a centrifuge (separator) to separate liquid and solid fractions, resulting in a wastewater flow of 229.18 m3/day and a peak flow of 5.31L/s. The wastewater generated would cause adverse water quality impact if discharged uncontrolled.
Condensate
from biogas drying, odour treatment and ventilation system
Biogas from the digester contains moisture. Removal of water from biogas by condensation, or other means, is required before conveying gas to a gas holder. A small amount of wastewater would be generated from condensate removal.
In addition a small amount of wastewater would be generated during the odour treatment process.
Washing
of waste delivery trucks
Vehicle washing facilities will be provided
for washing outgoing waste delivery vehicles. The system would be automatic
with high pressure jets washing down wheels and under body. Wash water would require disposal and this
could cause adverse water quality impact if uncontrolled.
Untreated
wastewater from wastewater treatment plant
Wastewater generated on-site would be
treated at wastewater treatment plant before discharge into the public sewerage
network. The treatment plant will
consist of biological treatment to treat nutrient rich wastewater. Prolonged breakdown of the plant might cause
higher loading to the existing sewerage network, as the wastewater is not
treated before discharge. In addition, if the plant and pipes are not
maintained, leaking of untreated wastewater may occur from damaged pipes or
storage tanks and this might cause adverse water quality impact.
Leakage
of materials from wastewater treatment
Sludge will generate from the wastewater
treatment process. Sludge will be
recycled to the composting process and/or disposed of to an appropriate sludge
treatment facility off site. If the
plant is not maintained, leaking of sludge and wastewater might take place
which could lead to adverse water quality impacts.
General construction works would be carried out in both wet and dry seasons. Heavy rainfall during wet seasons may generate silty runoff from the site where vegetation has been removed. If the site runoff is not managed properly, runoff may enter the nearby stream/drains causing elevated level of SS (and oil/grease if accidental spillage of chemicals occurred at the site).
Water from composting plant, on-site water treatment facilities and digesters contain high levels of nutrients, E. coli, microorganisms and SS. Accidental spillage from these facilities, if not contained properly, may enter the nearby streams/drains causing elevated level of BOD, COD and SS.
The site practices outlined in ProPECC Note PN 1/94 should be followed as far as
practicable in order to minimise surface runoff and erosion, which can cause
increase level of SS and DO depletion if entering nearby storm water drains.
The following measures are recommended to protect water quality of the inland
areas, and when properly implemented should be sufficient to adequately control
site discharges so as to avoid water quality impacts:
¡ At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels, earth bunds
or sand bag barriers should be provided on site to direct storm water to silt
removal facilities. The design of the temporary on-site drainage system should
be undertaken by the Contractors prior to the commencement of construction;
¡ Sand/silt
removal facilities such as sand/silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements of
the TM standards under the WPCO. The
design of efficient silt removal facilities should be based on the guidelines
in Appendix A1 of ProPECC Note PN 1/94. Sizes may vary depending upon the flow rate.
The detailed design of the sand/silt traps should be undertaken by the
Contractors prior to the commencement of construction;
¡ All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation at
all times and particularly during rainstorms. Deposited silt and grit should be
regularly removed, at the onset of and after each rainstorm to ensure that
these facilities are functioning properly at all times;
¡ Measures
should be taken to minimise the ingress of site drainage into excavations. If
excavation of trenches in wet periods is necessary, they should be dug and
backfilled in short sections wherever practicable. Water pumped out from
foundation excavations should be discharged into storm drains via silt removal
facilities;
¡ All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An
adequately designed and sited wheel washing facility should be provided at
construction site exit where practicable. Wash-water should have sand and silt
settled out and removed regularly to ensure the continued efficiency of the
process. The section of access road leading to, and exiting from, the wheel-wash
bay to the public road should be paved with sufficient backfall
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains;
¡ Open
stockpiles of construction materials or construction wastes on-site should be
covered with tarpaulin or similar fabric during rainstorms. Measures should be
taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system;
¡ Manholes
(including newly constructed ones) should be adequately covered and temporarily
sealed so as to prevent silt, construction materials or debris being washed
into the drainage system and stormwater runoff being
directed into foul sewers;
¡ Precautions
should be taken at any time of the year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecasted and actions to be
taken during or after rainstorms are summarised in Appendix A2 of ProPECC Note PN 1/94.
Particular attention should be paid to the control of silty surface runoff during storm events, especially for
areas located near steep slopes; and,
¡ Bentonite slurries used on site should be
reconditioned and reused wherever practicable. Temporary enclosed storage
locations should be provided on site for any unused bentonite
that needs to be transported away after all the related construction activities
are completed. The requirements in ProPECC Note PN
1/94 should be adhered to in the handling and disposal of bentonite
slurries.
The construction phase discharge would
be collected by the temporary drainage system installed by the Contractor and
then treated or desilted on-site before discharge to
storm water drains. The Contractor would be required to obtain a license from
EPD under the WPCO for discharge to the public drainage system.
Implementation of good construction and proper site management should be performed. Collection of construction solid waste, debris and refuse generated on-site, then handled and disposed of properly to avoid entering any nearby stormwater drain; stockpiles of cement and other construction materials should be kept covered when not being used. This can prevent water pollution arising from the wastewater generated from the on-site construction activities. It is anticipated that water quality impacts caused by general construction activities would be insignificant with proper implementation of recommended mitigation measures.
Excavated material and on-site
storage of loose soil can generate site runoff during rainfall causing increase
of SS concentration in the nearby watercourses.
The construction programme should be properly planned to minimise
excavation works during the wet season (April to September), temporarily exposed
slope/soil surfaces should be covered by a tarpaulin or other means, as far as
practicable. Interception
channels should be provided (e.g. along the crest/edge of the excavation) to
prevent storm runoff from washing across exposed soil
surfaces. Arrangements should be in place to ensure that adequate surface
protection measures can be safely carried out well before the arrival of a
rainstorm. Other measures
that need to be implemented before, during and after rainstorms are summarized
in ProPECC PN 1/94.
With the implementation of good construction practices and
mitigation measures, no adverse water quality impact is anticipated.
The Contractor should register as a chemical waste producer if chemical wastes are produced from construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes. This will prevent contamination of top soil and water pollution due to construction site runoff.
Maintenance of vehicles and equipment, involving activities with potential for leakage and spillage, should only be undertaken within areas appropriately equipped to control these discharges.
Oils and fuels should only be stored
in designated areas which have pollution prevention facilities. To prevent
spillage of fuels and solvents to any nearby storm water drain, all fuel tanks
and storage areas should be provided with locks and be sited on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the largest
tank. The bund should be drained of rainwater after a rain event.
Disposal of chemical wastes should be carried out in compliance
with the Waste Disposal Ordinance. The Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes published under the Waste
Disposal Ordinance details the requirements to deal with chemical wastes. General
requirements are given as follows:
¡ Suitable containers should be used to hold
the chemical wastes to avoid leakage or spillage during storage, handling and
transport.
¡ Chemical waste containers should be suitably
labelled, to notify and warn the personnel who are handling the wastes, to
avoid accidents.
¡ Storage area should be selected at a safe location
on site and adequate space should be allocated to the storage area.
With the implementation of good construction practices and mitigation measures, no adverse water quality impact is anticipated.
Domestic sewage would be generated
from the workforce during construction phase. However, temporary sanitary
facilities, such as portable chemical toilets should be installed within the
construction site to handle sewage from the workforce. The Contractor have the
responsibility to ensure that chemical toilets are used and properly
maintained, and that licensed Contractors are employed to collect and dispose
of the waste off-site at approved locations. Therefore, adverse water quality
impact is not anticipated.
During
operation of OWTF 2, sewage effluent would be generated from operation staff
and visitors. Generated
sewage should be discharged to the Shek Wu Hui Sewage
Treatment Works (SWHSTW) via a new sewer connection between OWTF2 to the Sha Ling Pumping Station, part of the existing NENT
sewerage network.
In order to minimise the risk of exceeding
flow capacity of the sewerage system, on-site underground storage of effluent
is recommended for the OWTF 2, with a capacity of 6 hours of peak flow. Using
the values presented in the preliminary design, the on-site storage required to
buffer excess capacity would be equivalent to 30 m3. A belowground
effluent retention tank would function to store effluent produced during peak
periods when usage of the Sha Ling pumping station is
high. Effluent stored during such periods could then be pumped out of the
retention tank and discharged into the public sewer during off-peak times when
capacity is sufficient.
With the implementation of the above
recommended design measure, no adverse water quality impact is anticipated and
no further mitigation measure is considered necessary.
Wastewater will be generated from the OWTF 2
including leachate from the waste reception and composting process, dewatering
of the digestate from the digesters, condensate from
biogas drying, odour treatment and ventilation system and washing of waste
delivery trucks. Wastewater must be collected and diverted to the wastewater
treatment plant.
An adequately sized WWTP with technologies
such as membrane bioreactor, reverse osmosis or multi-phase separation process
or system should be provided for the OWTF 2. Polluting parameters in the
effluent should be in compliance with the requirements as specified in the
TM-DSS.
Effluent from on-site wastewater treatment
will be discharged to the SWHSTW via a new sewer connection between OWTF2 and
the Sha Ling LPS, part of the existing NENT sewerage
network. No further mitigation measure is considered necessary.
Leachate
from the waste reception and composting process
Due to the high water content of organic
waste, occasional formation of leachate would be expected. A drainage system
will be provided at the reception area connecting to the proposed
onsite WWTP. The
leachate would be treated in the WWTP and there would be no
direct discharge of leachate, hence, adverse water quality impact would not be
anticipated.
Dewatering
of the digestate from the separators
The wastewater generated from the dewatering of digestate from the digesters is expected to be around 229.18 m3/day and a peak flow of 5.31L/s. The on-site WWTP will deploy suitable treatment process in order to reduce the pollution level to an acceptable standard. The effluent shall be treated according to the TM-DSS standard before discharging to foul sewers. Therefore, adverse water quality impact is not anticipated.
Condensate
from biogas drying, odour treatment and ventilation system
Condensate from biogas handling and wastewater from the odour treatment process would be collected and transferred to the WWTP. There is no direct discharge of wastewater to the sewer and therefore adverse water quality impact would not be anticipated.
Washing
of waste delivery trucks
Surplus wastewater generated from the vehicle washing facilities would be collected and transferred to the WWTP for further treatment before discharging to the foul sewer. Hence, no adverse water quality impact is anticipated.
Untreated
wastewater from wastewater treatment plant
Maintenance of the WWTP and its connection
pipe work would be conducted regularly to confirm the condition of the holding
tank and pipes. This will ensure early detection of any damage for repair or
replacement. Hence, no adverse water quality impact is anticipated.
Leakage
of materials from WWTP
Regular scheduled maintenance of the WWTP
will be carried out to confirm the condition of the facility and detect any
damages at an early stage for repair or replacement. Hence, no adverse water
quality impact is anticipated.
Most
of the activities of OWTF 2 will be located in enclosed buildings. Therefore,
contaminated materials will not enter stormwater
runoff during rainfall. Outside the building, good site practice will be
adopted to prevent and contain accidental spillage, if any. All surface runoff
and spillage generated inside the facility areas would be collected and
transferred to the on-site wastewater treatment plant. Hence, adverse water
quality impact is not anticipated.
Regular
maintenance of plant facilities, as recommended in Section 6.8.2.2, will
be performed to confirm the condition of plant facilities and detect any damage
for repair or replacement. Training should be provided to the employees on handling
accidental spillage, so that in such cases, actions can be carried out quickly
to avoid runoff to nearby streams/drains.
No
adverse water quality impacts are anticipated with implementation of the
recommended mitigation measures.
All
potential concurrent projects identified in Chapter 2 are in the planning or
feasibility study stage. The closest
project is the Kong Nga Po CDA Development, which is tentatively scheduled for
implementation in 2020. As the water
quality impact of the Project is relatively minor, the cumulative impacts
arising in conjunction with other project will not be significant, and water
quality impacts for other projects, implemented after OWTF2, will be assessed
separately.
With the
implementation of the recommended mitigation measures for the construction and
operation phases of the proposed Project, no significant residual water quality
impact is anticipated.
Adverse
water quality impact was not predicted during the construction and operation
phase of the Project. Nevertheless, appropriate mitigation measures are
recommended to minimise potential water quality impacts. Water quality
monitoring is not considered necessary. However, regular audit of
the implementation of the recommended mitigation measures during construction
phase at the work areas should be undertaken during construction phase to ensure
the recommended mitigation measures are properly implemented.
During
the construction phase, potential water quality impact would be generated from
site run-off, sewage from workforce, and discharge of wastewater from various
construction activities. With the implementation of the recommended mitigation
measures, no adverse water quality impact from the construction works for OWTF
2 is anticipated.
Sewage effluent from operation of the OWTF 2
would be discharged to the SWH STW via a new sewer connection (OWTF2 to Sha Ling LPS) and the existing NENT sewerage network. Adverse water quality impact is not expected.
Wastewater generated from the operation of the OWTF 2 would be adequately treated in the on-site wastewater treatment plant prior to discharge to the public sewerage system. Therefore, no adverse water quality impact is anticipated.
[1] River Water Quality in Hong Kong in 2011