2.               Project Description

2.1             Location and Description of the Project

2.1.1         The works for this Project in Cheung Chau mainly comprises the following items and as shown in Layout Plan of Figure 2.1:

(a)       Upgrading of the existing Cheung Chau STW;

(b)       Upgrading of the existing Pak She SPS by increasing the pumping capacity; and

(c)       Sewers works in Cheung Chau including upgrading/rehabilitation of the existing sewers at Cheung Chau and provision of new sewers to unsewered areas/villages including Tai Kwai Wan San Tsuen, Pak She San Tsuen, Nam She Tong, Fa Peng, Chi Ma Hang, Round Table Villages, Tai Shek Hau and Sin Yan Tseng, Tai Tsoi Yuen Kui, Ko Shan Tsuen and Lung Tsai Tsuen.

Sewage Treatment Works

2.1.2         Existing Cheung Chau STW is located at the western side of the Cheung Kwai Estate.  It is currently a primary treatment works with design capacity of 4,000 m3/d. Upon completion of the Project, it will be increased to a capacity of 9,800 m3/d with secondary treatment level.  A Membrane-bioreactor (MBR) type sewage treatment plant will be adopted.

2.1.3         Conventional secondary sewage treatment generally involves the biological degradation of organic content in the influent followed by secondary sedimentation to settle out the sludge from the aqueous activated sludge solution.  Rather than employing sedimentation, an MBR system passes the aqueous activated sludge solution through membrane filtration to separate water from the sludge.  The MBR systems can operate at a considerably higher mixed liquor suspended solids concentration and provide an effective and reliable barrier, therefore MBR system has smaller footprint, superior effluent quality and less sludge production over the conventional process.  All the MBR modules will be placed in MBR tanks, which are covered and installed indoor.

2.1.4         The STW upgrading works will include construction of new treatment facilities and also effluent reuse facilities to reuse portion of the treated effluent for non-potable uses within STW.  All the upgrading works will be constructed within the existing site boundary of Cheung Chau STW.  Proposed general layout of the Cheung Chau STW and the Schematic Flow Diagram are shown in Figure 2.2 and Figure 2.4, respectively.

Sewage Pumping Station

2.1.5         Existing Pak She SPS was commissioned in 1984 and is located at the junction of Pak She Praya Road and Ping Chong Road, opposite to the Cheung Chau Fire Station.  It is currently equipped with three screw pumps (two duty and one standby) with existing pumping capacity of 29,376 m3/d (340 L/s).  Upon completion of the Project, it will be increased to a capacity of 42,336 m3/d (490 L/s).

2.1.6         The upgrading works of Pak She SPS mainly include replacement of pumps with higher pumping capacity and other Electrical and Mechanical (E&M) equipments, minor modification of existing pump troughs. Dual power supply or standby power sources, and deodourizing units will be provided to the upgraded Pak She SPS. 

2.1.7         There is an existing 750mm dia. emergency bypass at the Pak She SPS currently connected to the Cheung Chau typhoon shelter.  Under this Project, the emergency bypass from Pak She SPS will be diverted away from the typhoon shelter by constructing a 750mm dia. bypass pipe connecting from the existing overflow pipe of the SPS to downstream sewerage system as presented in Figure 2.5.  No sewage emergency discharge from Pak She SPS into the Cheung Chau typhoon shelter would be anticipated after the upgrading works.

Sewers works

2.1.8         The proposed sewers works in Cheung Chau include:

(a)       Upgrading of approximately 120 m long existing sewer of size 150 mm to 400 mm diameter;

(b)       Rehabilitation of approximately 160 m long existing sewer of size 525 mm diameter;

(c)       Construction of approximately 7,500 m long of new sewers with size 150 mm to 400 mm diameter in village areas by open cut method; and

(d)       Construction of approximately 300 m long of new deep sewers with size Twin 400 mm to Twin 500 mm diameter along Cheung Chau Sports Road and Tung Wan Road by trenchless method.

2.1.9         Under Part I, Schedule 2 of the EIAO, the Project consists of the following designated projects:

(a)      Upgrading of the existing Cheung Chau STW – under Item F.2 which is Sewage Treatment Works with an installed capacity of more than 5,000 m3/d and a boundary less than 200 m from the boundary of a residential area;

(b)      Upgrading of the existing Pak She SPS - under Item F.3 which is Sewage Pumping Station with an installed capacity of more than 2,000 m3/d and a boundary less than 150 m from the boundary of a residential area; and

(c)      Upgrading of the existing Cheung Chau STW – under Item F.4 which includes an activity for the reuse of treated sewage effluent from a treatment plant.

2.2             Need of the Project

Existing Conditions

2.2.1         There is no public sewerage system for some of the village houses currently in Cheung Chau.  Sewage and greywater generated from most of these village houses are disposed of at septic tanks adjacent, where regular maintenance is needed.  Sewage and greywater generated from some of the village houses is even directly discharged into surface drainage system.

2.2.2         Besides, the existing sewage treatment plant at Cheung Chau is a primary treatment facility and inadequate to cope with the population growth and future development within the catchments.

Purpose and Objectives of the Project

2.2.3         The Project is to improve the coastal water quality to the northwest of Cheung Chau by upgrading of existing sewers and provision of new sewers where practicable within the catchment, upgrading of the existing primary treatment plant to a secondary STW and expand the STW to cope with the population growth and future developments to improve the hygiene conditions at Cheung Chau.

2.3             Scenarios With and Without the Project

Without Project

2.3.1         Most of the village houses will remain unsewered.  Sewage will be disposed of at septic tanks and required to be cleared manually from time to time.  Hygiene problems will continue to arise such as odour impacts.  Improper maintenance of septic tanks will also cause problems such as overflow from septic tanks or soakaway pit, which would cause pollution to nearby areas and/or streams. Moreover, the sewage treatment plant will remain as primary treatment level and suffer from insufficient capacity to cope with increased sewage flows and loads in the future, and consequently deteriorate the coastal water quality.

With Project

2.3.2         Public sewers will be provided to unsewered village houses as far as practicable.  Hygiene problems arising from the use of septic tanks will be largely relieved. Moreover, the sewage treatment level will be upgraded from primary to secondary and the capacity of the STW will be expanded to cope with the population growth and future developments.  Discharge of low quality effluent to the receiving water body will be reduced and hence will improve the coastal water quality of Cheung Chau.

2.4             Consideration of Alternative Design and Layout

2.4.1         Under the Investigation Stage, the proposed works for SPS in Cheung Chau include construction of a new Kwun Yam Wan SPS and upgrading of the existing Pak She SPS.

2.4.2         Kwun Yam Wan SPS was proposed under the conforming design for conveying sewage from Fa Peng and Chi Ma Hang, through the low spot area near Kwun Yam Wan, to the existing sewerage system at Cheung Chau Sports Road.

2.4.3         Due to the close proximity of the Kwun Yam Wan SPS and Kwun Yam Wan Beach, which is a Gazetted Beach, the proposed SPS will likely create adverse environmental impacts to beach visitors and swimmers during both construction and operation if impacts are not properly controlled.  Moreover, the catchment of the SPS consists of village houses, squatter huts and a camp site, which contribute to a major population of the catchment, the design flow is relatively small and will fluctuate with peak flows only occurring at weekends from the camp sites.  These flow conditions will create potential septicity problems, maintenance and operational difficulties to the Kwun Yam Wan SPS and its associated rising mains.  In addition, the proposed SPS site will require land resumption, which adds to the uncertainties associated with this pumping scheme.

2.4.4         Alternatives to the construction of the Kwun Yam Wan SPS have been investigated:

(a)      Reduced Sewerage Provision Option: sewerage works not provided to catchments upstream of the Kwun Yam Wan SPS;

(b)      Exposed and Deep Sewers Option: construction of a section of 220 m long exposed gravity sewers along hillside and a section of 60 m long deep sewers with depth between 6 m to 15 m connecting to the existing sewerage at Cheung Chau Sports Road; and

(c)      Deep Sewers Option: Construction of a section of 700 m long gravity sewers from the Kwun Yam Wan, of which 300 m long are at a depth of 4 m to 8 m (ground to invert level) along Cheung Chau Sports Road and Tung Wan Road, connecting to the existing sewerage at Praya Road.  It is proposed that the 300 m long sewers along Cheung Chau Sports Road and Tung Wan Road to be constructed by trenchless technique.

2.4.5         Preliminary assessment on sewerage impact and construction methodology had been studied.  Among the three alternatives mentioned above, Option (c) - Deep Sewer Option is recommended as an alternative to the Kwun Yam Wan SPS construction based on the extent of sewerage catchment, technical feasibility and ease of maintenance.  The proposed layout of the Deep Sewer Option is shown in Figure 2.3.

2.4.6         The Deep Sewer Option will eliminate the Kwun Yam Wan SPS and serve the same catchment as that of the SPS scheme.  The diversion of upstream sewage flows to the deep sewers will eliminate the need to upgrade the existing sewers along Cheung Chau Sports Road and Tung Wan Road (proposed under the Kwun Yam Wan SPS Option).  With the introduction of trenchless construction method under the Deep Sewer Option, the extent of road opening works along the Cheung Chau Sports Road and Tung Wan Road could be reduced.

2.4.7         The major drawback of the Deep Sewer Option is the difficulty in maintenance due to the deeper sewer alignment beneath Cheung Chau Sports Road and Tung Wan Road.  The gradient of the deep sewer is constrained by the existing invert level of the downstream connecting sewerage, and results in a slack gradient.  However, by introducing the use of HDPE pipes and diversion of sewage flow from existing Nam She Tong SPS, a minimum velocity of 0.75 m/s could be reached along the sewers from Kwun Yam Wan to Cheung Chau town centre.  Twin sewers would be provided to facilitate future maintenance.  Rehabilitation of the trunk sewers along Praya Street is also proposed to enhance the hydraulic performance of the pipes.

2.4.8         Table 2.1 provides the environmental benefits and dis-benefits of the proposed Kwun Yam Wan SPS Option and the Deep Sewer Option.

Table 2.1 : Environmental Benefits and Dis-Benefits of Alternative Options

Options

Environmental Benefits

Environmental Dis-Benefits

Other Considerations

Kwun Yam Wan SPS Option

Ÿ  Relatively shallower sewers and rising mains will be constructed along Tung Wan Road, which can be completed within a shorter duration.  Hence nuisance to the sensitive receivers would be of shorter period.

Ÿ  The proposed SPS may have potential adverse environmental impacts such as dust during construction; and emergency discharge, visual impacts and odour to the swimmers nearby during operation.

Ÿ  Approximately 15% of the population served by the proposed SPS is contributed by two camp sites in Fa Peng (population is categorised as institution). This would contribute to about 32% sewage inflow to proposed sewage pumping station.  As this flow from the camp sites would fluctuate significantly, potentially between zero flow during weekdays, to a high flow during holidays, this will create operation and maintenance problems to the proposed SPS and rising mains.  Sewage would remain stored in the pumping station wet well and rising main until subsequent inflows reach the SPS before triggering the pump to operate, which may cause septicity issue.

Ÿ  Open-trench excavation is required for proposed rising main and existing sewer upgrading works.  Noise nuisance will affect all sensitive receivers along the entire works alignment.

Ÿ  Construction difficulties will be encountered for the construction works at Kwun Yam Wan Beach area with limited space.

Ÿ  The proposed Kwun Yam Wan SPS is located on private lot where land resumption and site clearance is required.

Deep Sewer Option

Ÿ  Potential adverse environmental impacts (such as water quality of emergency discharge, visual and odour) to the swimmers in Kwun Yam Wan Beach can be eliminated.

Ÿ  No operation and additional maintenance for the SPS is required.

Ÿ  Excavation is only required at the working pit locations, hence localised construction nuisance to the sensitive receivers near the working pits only.

Ÿ  Comparatively less excavated materials will be generated.

Ÿ  Noise impacts at the pit locations during construction.

Ÿ  Relatively more difficult in maintenance of the deep sewer.

Ÿ  Diversion of upstream flow to the deep sewers so that no upgrading of existing sewers along Tung Wan Road and Praya Road is required.

 

2.5             Consideration of Alternative Construction Methods and Sequences of Work

2.5.1         Trenchless construction techniques are proposed for the construction of pipes beneath Cheung Chau Sports Road and Tung Wan Road.  Both trenchless techniques by Tunnel Boring Machine (TBM) and Hand-Shield Excavation – Segmental Method are feasible in Cheung Chau but as discussed below, the Segmental Method is more suitable for Cheung Chau.

2.5.2         TBM method for the construction of a single small diameter sewer is considered technically feasible in Cheung Chau.  The major concern for TBM method is the heavy TBM equipment which creates transport logistical difficulties within Cheung Chau.  Furthermore, the large equipment will also occupy large working space to house the slurry tank and electricity generator, which would be a nuisance to the public, in particular along Cheung Chau Sports Road and Tung Wan Road, which are busy.  Construction of twin pipes is also considered impractical with TBM technique because separation distances between the pipe construction is necessary and results with the need to have larger corridor widths and larger construction areas, which is limited on Cheung Chau.

2.5.3         Segmental Method is a manual excavation method which involves a shield head to be launched into the ground.  The erection of the pre-fabricated segmental rings is done within the shield head.  The rock/spoil is excavated manually from the tunnel face and transferred to ground level to be disposed of offsite.  Wastewater generated shall be properly treated by desilting tanks before discharged (similar to all other excavation works).  Relatively smaller working space and smaller machines would be required for Segmental Method.  It also enables twin gravity pipes to be laid within trenches.  The major drawback for Segmental Method is the slow progress with excavation in rock, but it is expected that through multiple workfronts and proper sequencing of works, this programme implication would be resolved to not affect the overall Project completion.

2.5.4         Table 2.2 provides the environmental benefits and dis-benefits of the Hand-Shield (Segmental Method) and the TBM construction Method.

Table 2.2 : Environmental Benefits and Dis-Benefits of Alternative Construction Methods

Options

Environmental Benefits

Environmental Dis-Benefits

Hand Shield Excavation (Segmental Method)

Ÿ  Less environmental nuisance to the public during construction as it requires much less working space when compared with TBM method.

Ÿ  Launching pit size is about
2.5 m x 3 m.

Ÿ  No slurry tank and electricity generator is required.

Ÿ  Longer period of environmental disturbance at the workfronts due to slow construction progress: 1m per day in soil and 1m per 6 days in rock.

Ÿ  Multiple workfronts and proper sequencing of works are required, which may give rise to more nuisance.

TBM Method

Ÿ  Jacking head returns back to launching pit.  Construction works can be speeded up and hence reducing the period of environmental disturbance.

Ÿ  Nuisance to the public as large working space is required for placing the machine, the slurry tank and the electricity generator.  The space required for launching pit is large. (Approx. 4-6m)

 

2.6             Selected of Preferred Scenario

2.6.1         The Deep Sewer Option is recommended mainly because it eliminates the need of a new SPS which will have the potential to cause adverse environmental impacts to the nearby Kwun Yam Wan Beach.

2.6.2         The Hand Shield Excavation (Segmental Method) is recommended due to its smaller machine and less space required.  To compensate for the slow progress, multiple workfronts and proper sequencing of works are required.

2.7             Effluent Reuse

2.7.1         The following non-potable effluent reuse elements are proposed for MBR treated effluent:

(a)      Process cleaning water for: screens, grit classifier, membrane filter press, storm tanks, channels and tanks, floor wash down, etc.; and

(b)      On-site toilet flushing.

2.7.2         200m3/d of the treated effluent would be undergoing chlorination in the disinfection tank before being conveyed to the treated water storage tank for further distribution to the effluent reuse units within the STW.  The quality of chlorinated effluent for effluent reuse in this Project is summarized in Table 2.3.  This is the effluent reuse standards recommended in the proposed expansion of Shek Wu Hui STW for off-site toilet flushing and other non-potable uses.  The recommended standards are more strengthened when compared with the treated effluent standard recommended for Ngong Ping STW, where the effluent is reused for off-site toilet flushing and other potential non-potable reuses (such as irrigation, water features, cooling towers, etc.).

Table 2.3 : Effluent Reuse Standards

Water Quality Parameter

Unit

Ngong Ping STW Effluent Reuse Quality

Shek Wu Hui STW Effluent Reuse Quality

Recommended Effluent Reuse Quality for Cheung Chau STW

pH

-

Not specified

6-9

6-9

Residual Chlorine

mg/L

³ 0.5

³ 1

³ 1

E.Coli

counts/100 ml

< 100

Not detectable

Not detectable

Turbidity

NTU

£ 10

£ 5

£ 5

Biochemical Oxygen Demand (BOD5)

mg/L

£ 10

£ 10

£ 10

Dissolved Oxygen

mg/L

³ 2

³ 2

³ 2

Total Suspended Solid (TSS)

mg/L

£ 10

£ 5

£ 5

Ammonia Nitrogen (NH3N)

mg/L

£ 1

£ 1

£ 1

Colour

Hazen Unit

£ 20

£ 20

£ 20

Synthetic Detergents

mg/L

£ 5

£ 5

£ 5

Threshold Odour Number (TON)

-

Not specified

£ 100

£ 100

 

2.7.3         The schematic diagram of effluent reuse is presented in Figure 2.4. A chlorine dosing system in the form of sodium hypochlorite with contact time of about 30 minutes will be installed.  The remaining portion of treated effluent without chlorination will be discharged via outfall. The chlorination process will cease when its quantity is monitored to reach a pre-set level to avoid over generation of chlorinated treated effluent.  In-house monitoring would be performed by STW Operators at the discharge point to ensure the residual chlorine level in discharged effluent is less than 1mg/L as stated in the Technical Memorandum on Standards for Effluent Discharged into Drainage and Sewerage Systems, Inland and Coastal Water (TM) for Marine Waters of the Southern Water Control Zone.

2.7.4         Small amount of sodium hypochlorite solution (<250L) will be stored on-site.  Such amount could be exempted from licensing requirements under the Dangerous Goods Ordinance (Cap 295) and is far less than that planned to be stored in the Stonecutters Island STW (1.8 million L of sodium hypochlorite) for the operation of the disinfection facilities in the Harbour Area Treatment Scheme (HATS), storage of which has been concluded to present an “acceptable” risk in the quantitative risk assessment of the approved EIA study for HATS.

2.7.5         Sodium hypochlorite is classified as a Category 4 poisonous substance under the Dangerous Goods Ordinance (Cap 295). They are not acutely toxic, flammable, or explosive substances, but hazardous gas would be generated if they were accidentally mixed with incompatible chemicals.  Also, the use of these chemicals in the treated effluent reuse system would not constitute a potentially hazardous installation in accordance with EPD’s ProPECC PN 2/94 Potentially Hazardous Installation.

2.8             Human Health Impacts due to Effluent Reuse

2.8.1         The effluent reuse is expected to reduce the amount of potable water demand required for the on-site STW operation, thereby providing an environmental benefit.  Since there is no off-site effluent reuse, no potential health impacts to general public on effluent reuse is anticipated.

2.8.2         The treated effluent is to undergo a chlorination treatment process before being conveyed to the point of storage and usage.  Chlorination is to minimize bacterial growth and contamination during the water transmission.  The recommended residual chlorine level in Shek Wu Hui STW is 1 mg/L for reducing odour and bacterial growth.

2.8.3         The process for the generation of chlorinated treated effluent will cease when its quantity is monitored to reach a pre-set level.  In-house monitoring would be performed by STW Operators at the discharge point to ensure the residual chlorine level in discharged effluent is in compliance with the discharge requirements.  No adverse water quality impacts are therefore anticipated from the normal operation of the effluent reuse system.

2.8.4         To avoid the potential health and hygiene problems associated with possible incorrect pipe connections, pipes for the treated effluent would be specially arranged to differentiate them from potable water pipes.  For example, pipes for the treated effluent are colour-coded, clearly labelled with warning signs and notices, and/or sized differently, so that physical connection of the treated effluent pipes with potable water fittings would be unlikely.  The effluent reuse system will also be provided with safe guard system to avoid arbitrarily contact from human.   Appropriate provisions would also be incorporated into the operation and maintenance manual to prevent possible incorrect pipe connections.  With proper preventative measures in place, health and hygiene impacts are not anticipated to occur during the normal operation of the effluent reuse system. 

2.9             Project Implementation Programme

2.9.1         The tentative implementation schedule for different works packages is presented in Table 2.4 below.

Table 2.4 : Tentative Implementation Schedule for Different Works Packages

 

Package 1
Cheung Chau STW and Pak She SPS upgrading

Package 2
Cheung Chau Sewers Works

EIA Endorsed

Nov 2013

Scheme Gazette under WPC(S)R

-

May 2014

Scheme Authorization

-

Aug 2014

Tender Gazette

May 2014

Apr 2015

Contract Commencement

Sep 2014

Aug 2015

Contract Completion

Mar 2019

Mar 2019

 

2.10          Public Consultations

2.10.1      Project Profile had been prepared in December 2009 for application of Environmental Impact Assessment Study Brief under EIAO.  No adverse comments had been received from the public.

2.10.2      Consultations had been conducted with Cheung Chau Rural Committee and Islands District Councilor regarding the proposed works under this Project. Three consultation meetings had been arranged in June 2011 and general supports on the Cheung Chau Sewerage Works were gained from the forum.

2.11          Project Interface / Concurrent Projects

2.11.1      Based on our review of the Investigation Stage and the latest information gathered during the Review Phase, the following interface projects in Cheung Chau have been identified:

(a)        “Improvement of Fresh Water Supply to Cheung Chau - Design and Construction” undertaken by WSD Design Division;

(b)        “Replacement and Rehabilitation of Water Mains Stage 3, Mains On Hong Kong and Islands – Investigation, Design and Construction” untaken by WSD CM Division;

(c)        “Replacement and Rehabilitation of Water Mains Stage 4, Mains On Hong Kong and Islands – Investigation, Design and Construction” untaken by WSD CM Division; and

(d)        “Improvement to Existing Roads and Drains in Cheung Chau Old Town, Remaining Engineering Works, Stage 3, Cheung Chau” undertaken by CEDD/HK&I.

2.11.2      The following discusses the potential interface issues between this Project’s components and the projects mentioned in Section 2.11.1.

Improvement of Fresh Water Supply to Cheung Chau - Design and Construction

2.11.3      Based on the information provided by WSD, the captioned Agreement is currently under detailed design stage.  Construction will commence in mid 2013 and complete in end 2015.  There is potential interface with the sewers works proposed under this Project at Cheung Chau Tai Kwai Wan.

2.11.4      A short section of the land-based watermains at Tai Kwai Wan will be laid and connected to the existing trunk mains.  Close liaison will be undertaken with the project proponent of the interfacing project to avoid concurrent works as far as possible.  By avoiding concurrent works and given the short section of the land-based watermains and the small scale works involved, adverse cumulative environmental impact is not expected.

Replacement and Rehabilitation of Water Mains Stage 3 and Stage 4, Mains on Hong Kong and Islands - Investigation, Design and Construction

2.11.5      Based on the information provided by WSD, Stage 3 works have been completed by end 2012.  No direct interface will be expected from the two projects.

2.11.6      The construction of Stage 4 works commenced in October 2012 and is anticipated for completion in end 2015.  The potential interface with the sewers works under this Project is at Cheung Chau – Tai Shek Hau, Tung Koon San Tsuen, Round Table 2nd Village and Round Table 3rd Village.

2.11.7      Close liaison will be undertaken with the project proponent of the interfacing project to avoid concurrent works as far as possible.  By avoiding concurrent works and given the short section of the land-based water main and the small scale works involved, adverse cumulative environmental impact is not expected.

Improvement to Existing Roads and Drains in Cheung Chau Old Town, Remaining Engineering Works Stage 3, Cheung Chau

2.11.8      Potential interface between the proposed sewerage, road and drainage works under CEDD project with this Project were identified mainly in Cheung Chau Town Centre, Hill Side Road, Kwun Yam Wan Road, Tai Shek Hau, Lung Tsai Tsuen, Ko Shan Tsuen and Pak She San Tsuen.

2.11.9      Based on the information provided by CEDD, Stage 3 is currently under detailed design stage and the construction programme could not be ascertained at time of this EIA Study.  However, it has been agreed in principle with CEDD that any construction works under the two projects within a local area would be undertaken by only one party as far as practicable.  By avoiding concurrent works involved, adverse cumulative environmental impact is not expected.

Summary - Potential Interfacing Projects During Construction

2.11.10   The interfacing projects that may have potential to cause cumulative construction impacts are summarized in Table 2.5.

Table 2.5 : Interfacing Projects

Interfacing Project

Scheduled Construction Period

Overlapping Months

Potential Cumulative Impacts

Start

Complete

Improvement of Fresh Water Supply to Cheung Chau

Mid 2013

End 2015

5

Yes

Replacement and Rehabilitation of Water Mains Stage 3, Mains on Hong Kong and Islands

--

End 2012

--

No

Replacement and Rehabilitation of Water Mains Stage 4, Mains on Hong Kong and Islands

Oct 2012

End 2015

5

Yes

Improvement to Existing Roads and Drains in Cheung Chau Old Town, Remaining Engineering Works, Stage 3, Cheung Chau

Construction programme not yet confirmed

--

--

 

2.11.11   Notwithstandingly, continuous liaison will be conducted with all works department and utilities companies to ensure adequate phasing with each concurrent project is taken into consideration, if interfacing does eventually occurs.  Cumulative environmental impact will therefore be eliminated by proper scheduling of works to avoid concurrent works.