12.             Environmental Monitoring and Audit Requirements

12.1          Introduction

12.1.1      This section provides a summary of the requirements of the environmental monitoring and audit (EM&A) for the upgrading of the Cheung Chau STW and Pak She SPS (DP component) and the sewers works (non-DP component) based on the findings of this EIA study. 

12.1.2      The objectives of conducting the EM&A programme for the Project are as follows:

Ÿ  To provide a database against which any short or long-term environmental impacts of the Project can be determined;

Ÿ  To provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

Ÿ  To monitor the performance of the Project and the effectiveness of mitigation measures;

Ÿ  To verify the environmental impacts predicted in this EIA;

Ÿ  To determine project compliance with regulatory requirements, standards and government policies;

Ÿ  To take remedial action if unexpected problems or unacceptable impacts arise; and

Ÿ  To provide data to enable an environmental audit.

12.1.3      The following section summarizes the recommended EM&A requirements for the Project.  Details of the specific requirements for the upgrading of the Cheung Chau STW and Pak She SPS (DP component of the Project) and the sewers works (non-DP component of the Project) are provided in the EM&A Manual prepared in accordance with Annex 21 of the EIAO-TM. 

12.2          Air Quality

Construction Phase

12.2.1     The predicted TSP results show that exceedance of recommended TSP levels would occur if no mitigation measures are undertaken.  Mitigation Measures are therefore needed to reduce the dust impact to an acceptable level.  With the implementation of the dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices, no adverse construction dust impacts would be expected.  Nevertheless, it is recommended that environmental monitoring and audit (EM&A) for air quality be carried out during the construction period to ensure proper implementation of construction phase mitigation measures with consideration of practicability in local level.

12.2.2      Further details of the specific EM&A requirements of the Project are detailed in the EM&A Manual, together with event action plans and procedures for complaints.

Operational Phase

12.2.3      All the odorous gas arising from the sewage would be collected and properly treated by deodorization unit with 99% odour removal efficiency for Cheung Chau STW and Pak She SPS. The predicted odour levels at the ASRs would comply with the EIAO-TM criterion.  Odour monitoring and audit should be carried out during the commissioning stage to ensure the continuing effectiveness of the odour control measures.  Details of monitoring and audit programme of odour due to the operation of Cheung Chau STW and Pak She SPS are presented in the EM&A Manual.  Commissioning test of the deodorization unit is also a mandatory requirement to confirm the effectiveness of the odour removal efficiency is in compliance with the design criteria.

12.3          Noise

Construction Phase

12.3.1      With the adoption of appropriate noise mitigation measures, construction noise levels caused by construction works of the upgraded Cheung Chau STW and Pak She SPS at all representative NSRs would comply with the EIAO-TM daytime noise criteria of 75 dB(A). It was envisaged that there would be no adverse residual impact at the NSRs. Nonetheless, it is recommended that environmental monitoring and audit (EM&A) for construction noise be carried out throughout the construction period of the upgrading of Cheung Chau STW and Pak She SPS to ensure proper implementation of construction phase mitigation measures with consideration of practicability in local levels.

12.3.2      Residual impacts during the construction of the sewers works were predicted. As such, it is recommended that construction phase EM&A is also undertaken for the sewers works to minimize the impacts as far as practicable. It is noted that during the construction process, episodes of high noise levels may occur and it will be the function of the EM&A process to identify these events and take the necessary action such as, for example, temporarily adjustment of the number of plant to be used or an equivalent measure as necessary. Further details of the specific EM&A requirements are detailed in the EM&A Manual.   

Operational Phase

12.3.3      Operational noise impacts from fixed plant of the Cheung Chau STW and Pak She SPS can be effectively mitigated by implementing noise control treatment at source. Adverse operation noise impacts are not anticipated. EM&A during operational phase is not required. In order to ensure compliance of the operational airborne noise impacts with the relevant noise standards, the requirement for carrying out a noise commissioning test for all major fixed noise sources should be included in the tender document.

12.4          Water Quality

Construction Phase

12.4.1      With effective controls through good operation and management practices, no adverse water quality impact is anticipated to occur during the construction phase of both the upgrading works for the Cheung Chau STW and Pak She SPS and the sewers works of the Project.

Operational Phase

12.4.2      For the operational phase, water quality in the study area is expected to be in compliance with the WQOs under the normal operation of the upgraded Cheung Chau STW (Scenario 2) with the exception for TIN, based on the modelling and analysis results. Given that the background TIN level in the Southern WCZ is already higher the WQO for TIN, the upgraded Cheung Chau STW was not predicted to impose additional adverse impacts to water quality conditions of the receiving marine environment.

12.5          Waste Management

Construction Phase

12.5.1      The assessment has concluded that proper handling, storage, collection, transportation and disposal of waste materials generated during construction and operation of the Project will not give rise to any significant impacts to nearby sensitive receivers.

12.5.2      It is recommended that during the construction phase, site inspections and supervisions of waste management procedures and auditing of the effectiveness of implemented mitigation measures should be undertaken on a regular basis (e.g. weekly as a minimum). These tasks shall be scheduled in the WMP to be prepared by the Contractor, and a summary of the site audit findings shall be presented in the EM&A reports.   

Operational Phase

12.5.3      No EM&A requirement is considered necessary during the operational phase.

12.6          Land Contamination

Construction Phase

12.6.1      The land contamination assessment was undertaken by reviewing historical and current land uses and site reconnaissance.  Based on the findings of the site appraisal, there were potential contaminated sites in the vicinity of the proposed upgrading works at the Pak She SPS.  However, as there are no excavation works in the potential contaminated sites, no potential contaminated soils would be disturbed.  The impacts of land contamination are not expected during the construction phase of the Project.  There are no EM&A requirements for land contamination.

Operational Phase

12.6.2      The operation of the Project is not potential contaminated land use. No operational contamination impacts are anticipated.  There are no EM&A requirements for land contamination.

12.7          Ecology

Construction Phase

12.7.1      Given the limited sizes of the works areas, the ecological value of the habitats affected by the works areas is limited, no specific ecological monitoring is required during construction phase.

Operational Phase

12.7.2      No adverse ecological impacts would be expected as a result of the implementation of the Project during operational phase.  Thus, no specific EM&A programme during the operational phase is required.

12.8          Fisheries

Construction Phase

12.8.1      Since no unacceptable impact on fishing resources is identified, no specific fisheries EM&A programme would be required during the construction phase of the Project.

Operational Phase

12.8.2      No adverse fisheries impacts would be expected as a result of the implementation of the Project during operational phase.  Thus, no specific EM&A programme with respect to fisheries during the operational phase is required.

12.9          Cultural Heritage

Built Heritage

12.9.1      No adverse impacts on any built heritage resources would be expected from the works of upgrading of Cheung Chau STW and Pak She SPS.  No specific EM&A programme for the upgrading of Cheung Chau STW and Pak She SPS is required.

12.9.2      The construction of sewers works may have potential indirect impacts to the built heritage resources. Monitoring and preventive measures for the sewers works will be recommended as detailed in the EM&A Manual.  The recommended measures are described as follow:

Condition Survey

12.9.3      The requirements for condition survey have been highlighted in Sections 10.4.32 and 10.4.33. A condition survey will be required for all highlighted Graded Historic Buildings and Non-Graded heritage structures as shown in Table 10.3 and Table 10.4 respectively.

Vibration Monitoring

12.9.4      The requirements for vibration monitoring have been highlighted in Section 10.4.34.  The condition survey report will confirm the Graded Historic Buildings and Non-Graded heritage structures that will require vibration monitoring during the construction works.

Provision of Buffer Zone

12.9.5      The requirements for provision of buffer zone have been highlighted in Section 10.4.35.  Resources requiring buffer zone are shown in Table 10.3 and Table 10.4.

Protective Covering

12.9.6      The requirements for protective covering have been highlighted in Section 10.4.36. Resources requiring protective covering are shown in Table 10.3 and Table 10.4.

Safe Public Access

12.9.7      The requirements for safe public access have been highlighted in Section 10.4.37. Resources requiring safe public access are shown in Table 10.3 and Table 10.4.

Archaeology

12.9.8      No archaeological potential will be affected by the upgrading of Cheung Chau STW and Pak She SPS. 

12.9.9      For the construction of sewers works, Archaeological Watching Brief programme and provision of buffer zone will be recommended as detailed in the EM&A Manual.

Archaeological Watching Brief Programme

12.9.10   Archaeological Watching Brief programme at Tai San Street, Tai San Back Street, Chung Hing Street and Chung Hing Back Street, Ko Shan Tsuen and Tung Wan Road.  Archaeological Watching Brief should be undertaken by a qualified archaeologist, who must apply for a licence under the Antiquities and Monuments Ordinance (Cap. 53) from the Antiquity Authority before the commencement of archaeological fieldwork.

12.9.11   Should significant findings be identified, additional archaeological resources should be provided in the form of additional or extended visits to ensure that appropriate recording and retrieval is accomplished prior to the continuation of engineering groundworks.  Upon discovery of any artefact or archaeological feature in the course of other excavation works during the construction stage, the AMO will be notified immediately for site inspection, on site discussion with the AMO will be arranged to agree on further actions required.

Provision of Buffer Zone

12.9.12   A buffer zone should be provided to ensure that the declared monument and its environs are not infringed upon during the construction works. In order to better protect the Rock Carving and its environs a buffer zone is required which includes Hak Pai Road and the nearby open space. Within the buffer zone, construction works as well as storage of construction materials are not allowed. Erection of temporary fencing/barriers to demarcate the buffer zone is not required. In addition, access to the rock carving should be maintained and directional signage should be erected or installed at appropriate location(s) near the rock carving to facilitate visitors to access the rock carving during the construction phase.

12.9.13   In addition, periodic monitoring of the declared monument is recommended.  It is recommended to conduct inspection of the site every 3 months during the construction phase.  Inspection record supplemented with the site photos showing the condition of the overall declared monument should be submitted to AMO for record purposes.

Operational Phase

12.9.14   No adverse impacts on any cultural heritage resources would be expected as a result of the implementation of the Project during operational phase.  Thus, no specific EM&A programme with respect to cultural heritage during the operational phase is required.

12.10       Landscape and Visual

Construction Phase

12.10.1   During the construction phase of the Project, some of the existing trees and vegetation would be disturbed.  A number of on-site landscape mitigation measures are recommended to minimise the potential landscape and visual impacts. With the implementation of the recommended mitigation measures, the landscape and visual impacts are considered to be negligible.

12.10.2   Regular audits should be carried out to ensure all the recommended landscape and visual mitigation measures would be effectively implemented and audited by the Environment Team during construction phases of the Project.   The EM&A will comprise audit of the tree transplanting, compensatory planting and planting establishment through site audit programme.

Operational Phase

12.10.3   Operational stage EM&A during the operational phase will comprise audit of the implementation of the landscape plan in the form of site inspection.