1................ Introduction
1.1......... Project Background
1.2......... Project Description
1.3......... Project Programme
1.4......... Purpose of this Environmental Monitoring and Audit (EM&A) Manual
1.5......... Project Organisation
2.2......... Air Quality Parameters
2.3......... Monitoring Requirements and Equipment
2.4......... Air Quality Monitoring Locations
2.5......... Baseline Air Quality Monitoring
2.6......... Impact Air Quality Monitoring
2.7......... Environmental Quality Performance Limits
2.8......... Event and Action Plan
2.9......... Mitigation Measures
3.2......... Monitoring Requirements and Equipment
3.3......... Noise Monitoring Methodology
3.4......... Noise Monitoring Locations
3.5......... Baseline Noise Monitoring
3.6......... Impact Noise Monitoring
3.7......... Event and Action Plan
3.8......... Mitigation Measures
4................ Water
Quality
4.2......... Water Quality Monitoring Equipment
4.3......... Construction Phase Water Quality Monitoring
4.4......... Operational Phase Water Quality Monitoring
4.5......... Event and Action Plan
4.6......... Mitigation Measures
5................ Waste
Management
5.2......... Construction Phase EM&A Requirements
5.3......... Operational Phase EM&A Requirements
6................ CultuRal
HeritaGe
6.2......... Construction Phase Protective Measures
6.3......... Operational Phase Protective Measures
6.4......... Construction Phase EM&A Requirements
6.5......... Operational Phase EM&A Requirements
7................ Landscape
and Visual
7.2......... Construction Phase EM&A Requirements
7.3......... Operational Phase EM&A Requirements
7.4......... Mitigation Measures
8................ Site
Inspection / Audit
8.1......... Site Inspection Requirements
8.2......... Compliance with Legal and Contractual Requirements
8.3......... Environmental Complaints
9.1......... Baseline Monitoring Report
9.2......... Monthly EM&A Reports
9.3......... Final Summary EM&A Report
9.5......... Interim Notifications of Environmental Quality Limit Exceedances
List of Appendices
Line of
Communication |
|
Sample of
Monitoring Data Record Sheet |
|
Implementation
Schedule of Mitigation Measures |
|
Methodology for
Archaeological Watching Brief (AWB) |
List of Tables
Table 1.1 Tentative
Implementation Schedule for Different Works Packages
Table 2.1 Proposed
Dust Monitoring Stations
Table 2.2 Proposed
Odour Monitoring Stations
Table 2.3
Action / Limit Levels for Air Quality
Table 2.4 Event
and Action Plan for Air Quality (Construction Dust)
Table 2.5 Event
and Action Plan for Air Quality (Operational Phase)
Table 3.1 Noise
Monitoring Locations
Table 3.2 Action
and Limit Levels for Construction Noise
Table 3.3 Event
/ Action Plan for Construction Noise
Table 4.1 Analytical
Methods and Detection Limits for Marine Water Samples
Table 4.2 Marine
Water Monitoring Locations
Table 4.3 Thresholds
for Marine Water Quality Parameters
Table 4.4 Event
and Action Plan for Protection of Marine Water Quality
Table 6.1 Proposed
Further Archaeological Works during Construction Phase
Table 6.2 Mitigation
Recommendations for Graded Historical Buildings in Cheung Chau
Table 6.3 Mitigation
Recommendations for Non-Graded Historical Structures in Cheung Chau
Table 7.1 Proposed
Mitigation Measures during Construction Phase
Table 7.2 Proposed
Mitigation Measures during Operational Phase
List of Figures
Proposed Works in Cheung Chau |
|
Proposed General Layout of Cheung Chau STW |
|
Air Quality Monitoring Locations (Sheet 1 of 2) |
|
Air Quality Monitoring Locations (Sheet 2 of 2) |
|
Noise Monitoring Locations (Sheet 1 of 8) |
|
Noise Monitoring Locations (Sheet 2 of 8) |
|
Noise Monitoring Locations (Sheet 3 of 8) |
|
Noise Monitoring Locations (Sheet 4 of 8) |
|
Noise Monitoring Locations (Sheet 5 of 8) |
|
Noise Monitoring Locations (Sheet 6 of 8) |
|
Noise Monitoring Locations (Sheet 7 of 8) |
|
Noise Monitoring Locations (Sheet 8 of 8) |
|
EM&A Monitoring Stations |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 1 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 2 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 3 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 4 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 5 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 6 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 7 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 8 of 15) |
|
Assessment of Archaeological Potential within Project in Cheung
Chau (Sheet 9 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 10 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 11 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 12 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 13 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 14 of 15) |
|
Assessment of Archaeological Potential within Project in
Cheung Chau (Sheet 15 of 15) |
|
Location of Built Heritage Resources (Sheet 1 of 15) |
|
Location of Built Heritage Resources (Sheet 2 of 15) |
|
Location of Built Heritage Resources (Sheet 3 of 15) |
|
Location of Built Heritage Resources (Sheet 4 of 15) |
|
Location of Built Heritage Resources (Sheet 5 of 15) |
|
Location of Built Heritage Resources (Sheet 6 of 15) |
|
Location of Built Heritage Resources (Sheet 7 of 15) |
|
Location of Built Heritage Resources (Sheet 8 of 15) |
|
Location of Built Heritage Resources (Sheet 9 of 15) |
|
Location of Built Heritage Resources (Sheet 10 of 15) |
|
Location of Built Heritage Resources (Sheet 11 of 15) |
|
Location of Built Heritage Resources (Sheet 12 of 15) |
|
Location of Built Heritage Resources (Sheet 13 of 15) |
|
Location of Built Heritage Resources (Sheet 14 of 15) |
|
Location of Built Heritage Resources (Sheet 15 of 15) |
1.1.1 In 2002, the Environmental Protection Department (EPD) carried out the Sewerage Master Plan Stage 2 Review (SMP Stage 2 Review), and completed the Preliminary Project Feasibility Study for Islands Sewerage Stage (hereinafter referred to as ¡§PPFS¡¨).
1.1.2 In February 2008, Drainage Services Department (DSD) commenced the Investigation Stage of ¡§Upgrading of Cheung Chau and Tai O Sewage Collection, Treatment and Disposal Facilities¡¨ under Agreement No. CE 31/2007 (DS) by commissioning a consultant to carry out review on the conclusions and recommendations of the PPFS report, surveys, investigations, impact assessments, preliminary environmental review and preliminary design of the recommended works (hereinafter referred to as ¡§Investigation Consultancy¡¨).
1.1.3 During the implementation of Investigation Consultancy, DSD conducted various consultations activities, including attending the Islands District Council, meetings with Legislative Council member, Green Lantau Association and the Association for Tai O Environment and Development. DSD committed that extensive and in-depth consultation would be conducted during the design and construction stage of this Project.
1.1.4 In December 2010, Drainage Services Department (DSD) commissioned Atkins China Limited (ACL) to undertake Design and Construction of Upgrading of Cheung Chau and Tai O Sewage Collection, Treatment and Disposal Facilities under Agreement No. CE 15/2010 (DS).
1.1.5 The works for the Project as recommended in the Investigation Consultancy mainly comprises the upgrading for the sewage collection, treatment and disposal facilities in two outlying islands, Cheung Chau and Tai O in Lantau. In December 2009, DSD applied for two separate Environmental Impact Assessment (EIA) Study Briefs under Section 5(1) the Environmental Impact Assessment Ordinance (EIAO) for the works in Cheung Chau and Tai O, respectively.
1.1.6 An Environmental Impact Assessment (EIA) Study Brief No. ESB-212/2009 was issued to cover the upgrading of Cheung Chau Sewage Collection, Treatment and Disposal Facilities (hereinafter referred as the ¡§Project¡¨).
1.2.1 The works for this Project in Cheung Chau mainly comprises the following items and as shown in Layout Plan of Figure 1.1:
(a) Upgrading of the existing
Cheung Chau Sewage Treatment Works (STW);
(b) Upgrading of the existing
Pak She Sewage Pumping Station (SPS) by increasing the pumping capacity; and
(c) Sewers works in Cheung Chau
including upgrading/rehabilitation of the existing sewers at Cheung Chau and
provision of new sewers to unsewered areas/villages including Tai Kwai Wan San
Tsuen, Pak She San Tsuen, Nam She Tong, Fa Peng, Chi Ma Hang, Round Table
Villages, Tai Shek Hau and Sin Yan Tseng, Tai Tsoi Yuen Kui, Ko Shan Tsuen and
Lung Tsai Tsuen.
1.2.2 Upgrading of the existing Cheung Chau STW to include upgrading of the sewage treatment level of Cheung Chau STW to provide secondary treatment with design capacity of 9,800 m3/day. Proposed general layout of the Cheung Chau STW is shown in Figure 1.2.
1.2.3 Under Part I, Schedule 2 of the EIAO, the Project consists of the following designated projects (DP):
(a) Upgrading of the existing
Cheung Chau STW ¡V under Item F.2 which is Sewage
Treatment Works with an installed capacity of more than 5,000 m3/d
and a boundary less than 200 m from the boundary of a residential area;
(b) Upgrading of the existing
Pak She SPS - under Item F.3 which is Sewage
Pumping Station with an installed capacity of more than 2,000 m3/d
and a boundary less than 150 m from the boundary of a residential area; and
(c) Upgrading of the existing
Cheung Chau STW ¡V under Item F.4 which includes an activity for the reuse of treated sewage effluent from a treatment
plant.
1.3.1 The Project is divided into four phases, namely Review, Design, Tender and Construction. The Construction of the first works contract is tentatively scheduled to commence in late 2014 with a view to completing the works in 2019.
1.3.2 The tentative implementation schedule for different works packages is presented in Table 1.1.
Table 1.1 Tentative Implementation Schedule for
Different Works Packages
|
Package 1 |
Package 2 |
EIA Endorsed |
Oct 2013 |
|
Scheme Gazette under WPC(S)R |
- |
May 2014 |
Scheme Authorization |
- |
Aug 2014 |
Tender
Gazette |
May 2014 |
Jun 2015 |
Contract
Commencement |
Sep 2014 |
Oct 2015 |
Contract
Completion |
Mar 2019 |
Mar 2019 |
1.4.1 The purpose of this EM&A Manual (hereinafter refer to as the ¡§Manual¡¨) is to guide the set up of an EM&A programme to ensure compliance with the recommendations in the EIA study covering the upgrading of Cheung Chau Sewage Collection, Treatment and Disposal Facilities, to assess the effectiveness of the recommended mitigation measures and to identify any further need for additional mitigation measures or remedial action. This Manual outlines the monitoring and audit programme for both the construction and operational phase of both the DP component (upgrading of Cheung Chau STW and Pak She SPS) and non-DP component (sewers works) of the Project. It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with the construction and operational phases.
1.4.2 This Manual provides specific information, guidance and instruction to personnel in charged with environmental responsibilities and undertaking environmental monitoring and auditing works for the upgrading of Cheung Chau STW and Pak She SPS (DP component of the Project). It also provides systematic procedures for monitoring, auditing, and minimising environmental impacts associated with the construction activities.
1.4.3 The EM&A programme contain the following information:
¡P
project organization for the Project;
¡P
responsibilities of the Contractor, the Engineer or Engineer¡¦s
Representative (ER) and Environmental Team (ET) with respect to the
environmental monitoring and audit requirements during the course of the
Project;
¡P
the basis for, and description of the broad approach underlying the
EM&A programme;
¡P
requirements with respect to the construction programme schedule and the
necessary environmental monitoring and audit programme to track the varying
environmental impact;
¡P
details of the methodologies to be adopted, including all field
laboratories and analytical procedures, and details on quality assurance and
quality control programme;
¡P
definition of Action and Limit levels;
¡P
establishment of Event and Action plans;
¡P
requirements for reviewing pollution sources and working procedures
required in the event of non-compliance with the environmental criteria and
complaints;
¡P
requirements for presentation of environmental monitoring and audit data
and appropriate reporting procedures; and
¡P
requirements for review of EIA predictions and the effectiveness of the
mitigation measures / environmental management systems and the EM&A
programme.
1.5.1 Involvement of relevant parties in a collaborative and interactive manner is essential for the implementation of the recommended EM&A programme. The following sections outline the primary responsibilities and duties of the key EM&A programme participants. The lines of communication with respect to EM&A works are shown in Appendix A.
1.5.2 Drainage Services Department (DSD) is the project proponent and works department and hence will assume overall responsibility for the project.
1.5.3 Environmental Protection Department (EPD) is the statutory enforcement body for environmental protection matters in Hong Kong
1.5.4 The Engineer¡¦s Representative (ER) shall appoint an appropriate member of the resident site staff, who shall:
(i)
Monitor the Contractor¡¦s compliance with the
contract specifications, including the EM&A programme, and the effective
implementation and operation of environmental mitigation measures in a timely
manner;
(ii)
Ensure that impact monitoring is conducted at
the correct locations at the correct frequency as identified in the EM&A
programme;
(iii)
Instruct the Contractor to follow the agreed
protocols or those In the Contract Specifications in the event of exceedances
or complaints;
(iv)
Review the programme of works with a view to
identifying any potential environmental impacts before they arise;
(v)
Check that mitigation measures that have been
recommended in the EIA Report, this document and contract documents, or as
required, are correctly implemented in a timely manner, when necessary;
(vi)
Report the findings of site audits and other
environmental performance reviews to DSD;
(vii)
Verify the environmental acceptability of
permanent and temporary works, relevant design plans and submissions, and
(viii)
Comply with the agreed Event Contingency Plan
in the event of any exceedance.
1.5.5 The Independent Environmental Checker (IEC) shall advise the ER on environmental issues related to the project. The IEC shall not be in any way an associated body of the ER, the Contractor or the ET for the project. The IEC shall be empowered to audit from an independent viewpoint the environmental performance during the construction of the Project. The IEC shall be a person who has relevant professional qualifications in environmental control and at least 7 years experience in EM&A and environmental management.
1.5.6 The IEC shall be responsible for the duties defined in this Manual, and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in this Manual, as well as any other relevant submissions required under the Environmental Permit. The IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under the EP. The IEC shall verify the logbook prepared and kept by the ET Leader. The IEC shall notify EPD by fax, within 24 hours of receipt of notification from the ET Leader of any such instance or circumstance or change of circumstances or non-compliance with the EIA Report or the EP, which might affect the monitoring or control of adverse environmental impact.
1.5.7 The main duties of the IEC are to carry out independent environmental audit of the project. This shall include, inter alias, the following:
(i)
Review and audit in an independent, objective and professional manner in all
aspects of the EM&A programme;
(ii) Validate and confirm the accuracy of monitoring results, appropriateness
of monitoring equipment, monitoring locations with reference to the locations
of the nearby sensitive receivers, and monitoring procedures;
(iii) Carry out random sample check and audit on monitoring data and sampling
procedures, etc;
(iv) Conduct random site inspection (at least once a month);
(v) Audit the EIA recommendations and EP requirements against the status of
implementation of environmental protection measures on site;
(vi) Review the effectiveness of environmental mitigation measures and
Project environmental performance;
(vii) On an as needed basis, verify and certify the environmental
acceptability of the construction methodology (both temporary and permanent
works), relevant design plans and submissions under the environmental
permit. Where necessary, the IEC
shall agree in consultation with the ET Leader and the Contractor the least
impact alternative;
(viii) Verify investigation results of complaint cases and the effectiveness of
corrective measures;
(ix) Verify EM&A reports submitted and certified by the ET Leader; and
(x) Feedback audit results to ER/ ET by signing according to the Event/
Action Plans specified in this Manual.
1.5.8 An Environmental Team (ET) headed by an ET Leader shall preferably be appointed by the Contractor to carry out the recommended EM&A programme for the Project. Neither ET Leader nor ET shall be in any way an associated body of ER, IEC or the Contractor. The ET Leader shall plan, organise and manage the implementation of the EM&A programme, and ensure that the EM&A works are undertaken to the required standards. The ET Leader shall have relevant professional qualifications in environmental control and possess at least 7 years experience in EM&A and/or environmental management subject to the approval of their employer.
1.5.9 The ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements specified in this Manual and the EP. The ET Leader shall keep a contemporaneous logbook for recording each and every instance or circumstance or change of circumstances that may affect the compliance with the recommendations of the EIA report. This logbook shall be kept readily available for inspection by the IEC, and Director of Environmental Protection (DEP) or his authorised officers.
1.5.11 The broad categories of works of the ET comprise the following:
(i)
To monitor the various environmental
parameters as required by the EM&A programme;
(ii)
To follow up and close out of the
non-compliance actions;
(iii)
To investigate and audit the Contractor¡¦s
equipment and work methodologies with respect to pollution control and
environmental mitigation, and to anticipate environmental issues that may
require mitigation before the problem arises;
(iv)
To audit and prepare audit reports on the
environmental monitoring data and the site environmental conditions;
(v)
To review the EM&A programme after the
collection and analysis of the baseline data,
(vi)
To modify the EM&A programme in terms of
parameters, sites, sample sizes, frequency etc. if appropriate in consultation
with the ER and EPD, and
(vii)
To report the environmental monitoring and
audit results to the IEC, Contractor and the ER.
1.5.13 The broad categories of works of the Contractor comprise the following:
(i)
Work within the scope of the construction
contract and other tender conditions with respect to environmental
requirements;
(ii) Operate
and strictly adhere to the guidelines and requirements in this EM&A
programme and contract specifications;
(iii) Provide
assistance to ET in carrying our monitoring;
(iv) Participate
in the site inspections undertaken by the ET as required, and undertake
correction actions;
(v) Provide
information / advice to the ET regarding works activities which may contribute,
or be continuing to the generation of adverse environmental conditions;
(vi) Submit
proposals on mitigation measures in case of exceedances of Action and Limit
levels in accordance with the Event / Action Plans;
(vii) Implement
measures to reduce impact where Action and Limit levels are exceeded; and
(viii) Adhere
to the procedures for carrying out complaint investigation.
1.5.14 The Contractor should also participate in the environmental performance review undertaken by the ER and undertake any corrective actions as instructed by the ER.
2.1.1 In this section, the requirements, methodology, equipment, monitoring location, criteria and protocols for the monitoring and audit of air quality impacts during the construction and operation of upgrading of Cheung Chau STW and Pak She SPS (DP component) and sewers works (non-DP component) under the Project are presented.
2.1.2 With the implementation of dust suppression and control measures stipulated in the Air Pollution Control (Construction Dust) Regulation, the potential dust impacts due to the construction of sewers works would be minimal. Therefore, construction dust monitoring is only recommended for the construction works of upgrading of Cheung Chau STW.
2.1.3 During the operational phase of the Project, all the potential odour generating facilities would be enclosed by air-tight covers. Odourous gas generated from the Cheung Chau STW would be ventilated to the deodourisation facility for treatment before discharge. The deodourisation facility would be designed to achieve an odour removal efficiency of 99% for Cheung Chau STW and 99% for Pak She SPS. During sludge transportation, the sludge should be carried by enclosed container to avoid unacceptable odour nuisance. With the above mitigation measures incorporated into the design, no unacceptable odour impacts are anticipated. Odour monitoring and audit is proposed during the operation phase to ensure the continuing effectiveness of the odour control measures.
2.2.1 The air quality parameters to be monitored includes:
¡P 24-hour
TSP;
¡P 1-hour TSP; and
¡P odour units or equivalent Hydrogen Sulphide (H2S)
concentration.
Construction Phase
(i)
0.6 ¡V 1.7 m3 per minute adjustable
flow range;
(ii)
equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
(iii)
installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
(iv)
capable of providing a minimum exposed area
of 406 cm2;
(v)
flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
(vi)
equipped with a shelter to protect the filter
and sampler;
(vii)
incorporated with an electronic mass flow
rate controller or other equivalent devices;
(viii)
equipped with a flow recorder for continuous
monitoring;
(ix)
provided with a peaked roof inlet;
(x)
incorporated with a manometer;
(xi)
able to hold and seal the filter paper to the
sampler housing at horizontal position;
(xii)
easily changeable filter; and
(xiii)
capable of operating continuously for a
24-hour period.
2.3.5 Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The concerned parties such as ER shall properly document the calibration data for future reference. All the data shall be converted into standard temperature and pressure condition.
2.3.6 The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded in the data sheet as mentioned in Appendix B.
2.3.7 If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, he shall submit sufficient information to the ER to prove that the instrument is capable of achieving a comparable result to the HVS. The instrument shall also be calibrated regularly, and the 1-hour sampling shall be determined periodically by the HVS to check the validity and accuracy of the results measured by direct reading method.
2.3.8 Wind data monitoring equipment shall also be provided by the ET and set up at conspicuous locations for logging wind speed and wind direction near to the dust monitoring locations. The equipment installation location shall be proposed by the ET and agreed with the ER in consultation with the IEC. For installation and operation of wind data monitoring equipment, the following points shall be observed:
(i)
The wind sensors shall be installed 10m above
ground so that they are clear of obstructions or turbulence caused by the
buildings;
(ii)
The wind data shall be captured by a data
logger. The data shall be
downloaded for analysis at least once a month;
(iii)
The wind data monitoring equipment shall be
re-calibrated at least once every six months; and
(iv)
Wind direction should be divided into 16
sectors of 22.5 degrees each.
2.3.9 In exceptional situations, the ET may propose alternative methods to obtain representative wind data upon approval from the ER and agreement from the IEC.
Laboratory
Measurement / Analysis
2.3.11 If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER and the measurement procedures shall be witnessed by the ER. Any measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER. The ER shall regularly audit the measurement performed by the laboratory to ensure the accuracy of measurement results. The ET Leader shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), (Appendix B) for his reference.
2.3.12 Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.
2.3.13 After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity-controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.
2.3.14 All the collected samples shall be kept in a good condition for 6 months before disposal.
Operation Phase
General
2.3.16 The following items should be recorded during odour sampling
and H2S concentration measurement:
¡P
the
prevailing weather condition;
¡P
wind
direction;
¡P
any odour detected during sampling and the flavours
of odour with detailed description of characteristics (e.g. sewage or
rotten-egg smell, decayed vegetables, ammonical, dischargeable odour,
putrefaction, sharp, pungent, fish, irritating, fruit, vinegar, etc);
¡P
downwind or
upwind direction from the odour source;
¡P
duration of
odour (intermittent or continuous) during sampling; and
¡P
photo
showing the sampling locations relative to existing land features. The relevant meteorological data (e.g. ambient temperature, wind speed and
direction, relative humidity, etc.) from the nearest Hong Kong Observatory
station during the sampling period should also be recorded for reference.
¡P
Measurement at each location shall be carried out
at least three (3) times for each sampling event.
Odour Sampling
2.3.19 The odour concentration of the collected air samples should be
determined by a forced-choice dynamic olfactometer with a panel of human
assessors being the sensor in accordance with the European Standard
Method: Air Quality ¡V Determination of Odour Concentration by Dynamic
Olfactometry (EN13725) within 24 hours after collection.
H2S Measurement
2.3.20 H2S concentrations shall be measured by portable H2S
analyser, type Jerome 631-X H2S, or equivalent which utilises a gold
film sensor for the detection of hydrogen sulphide. The instrument is controlled by
microprocessor, ensuring rapid accurate analyses, and should be fitted with the
following accessories:
¡P
Data logger (to allow the instrument to
operate unattended);
¡P
Interface cable and interface software; and
¡P
Data download and graphics services.
2.3.21 The instrument is capable of measuring H2S concentration in the range 1ppb to 50ppm, to an accuracy of ¡Ó6%.
Odour Complaint
Registration
2.3.22 A complaint registration system should be in place to handle the odour complaint case. The operator of the Cheung Chau STW and Pak She SPS (i.e. DSD) in future can have their complaint registration system and would not be limited to the below proposed complaint registration system.
2.3.23 In the event when an odour complaint is received, the operator shall liaise with the complainant and a Complaint Registration Form shall be completed. The Complaint Registration Form is to record detailed information regarding the odour complaint and hence, facilitates efficient investigation work. The registration form shall contain, but not be limited to the following information:
(i)
Location of where the odour nuisance
occurred, including whether the odour was experienced indoors or outdoors;
(ii) Date
and time of the complaint and the nuisance event;
(iii) Description
of the complaint, i.e. the type and characteristics of the odour; and an
indication of the odour strength (highly offensive / offensive / slightly
offensive / just continuously detectable /intermittently detectable); and
(iv) Name
and contact information of the complainant.
2.3.24 This information shall be obtained by the plant engineer or his representative(s) of the Cheung Chau STW and Pak She SPS when the complaint is received. The Odour Complaint Register is recommended to be kept at the Cheung Chau STW. The Complaint Registration Form is shown in Appendix B for reference.
2.3.25 In addition, it is recommended to obtain the following information:
(i)
Meteorological conditions from the Hong Kong
Observatory¡¦s Cheung Chau Weather Station (including temperature, wind speed,
relative humidity) at the time of the complaint; and
(ii) Whether
any abnormal operations are being carried out at the Cheung Chau STW and Pak
She SPS at the time the nuisance occurred.
Construction Dust
2.4.1 The status and location of the air quality sensitive receivers may change after issuing this Manual. The ET shall propose updated monitoring locations and seek approval from EPD, and agreement from the ER and the IEC before the baseline monitoring commences.
2.4.2 Should alternative monitoring locations be proposed, the proposed sites shall, as far as practicable:
(i)
be at the site boundary or such locations
close to the major dust emission source;
(ii)
be close to the sensitive receptors; and
(iii)
take into account the prevailing
meteorological conditions.
2.4.3 The ET shall agree with the ER and the IEC on the position of the HVS for the installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:
(i)
a horizontal platform with appropriate support to secure
the samplers against gusty wind shall be provided;
(ii)
no two samplers shall be placed less than 2 meters apart;
(iii)
the distance between the sampler and an obstacle, such as
buildings, must be at least twice the height that the obstacle protrudes above
the sampler;
(iv)
a minimum of 2 meters of separation from walls, parapets
and penthouses is required for rooftop samplers;
(v)
a minimum of 2 meters separation from any supporting
structure, measured horizontally is required;
(vi)
no furnace or incinerator flue is nearby;
(vii)
airflow around the sampler is unrestricted;
(viii)
the sampler is more than 20 meters from the dripline;
(ix)
any wire fence and gate, to protect the sampler, shall
not cause any obstruction during monitoring;
(x) permission must be
obtained to set up the samplers and to obtain access to the monitoring
stations; and
(xi) a secured supply of
electricity is needed to operate the samplers.
2.4.4 The proposed dust monitoring station is presented in Table 2.1 and the respective locations are shown in Figure 2.1.
Table 2.1 Proposed Dust Monitoring Stations
ID No. |
Location |
Nature of Use |
A1 |
Cheung King
House, Cheung Kwai Estate |
Residential |
A2 |
Cheung Chau
Slaughter House |
Slaughter house |
2.4.5 Four existing Air Sensitive Receivers (ASRs) have been identified for odour monitoring as shown in Table 2.2 and illustrated in Figure 2.1 and Figure 2.2. Monitoring shall be conducted at 1.5m above the ground surface.
Table 2.2 Proposed
Odour Monitoring Stations
ID No. |
Location |
Nature of Use |
A1 |
Cheung King House, Cheung Kwai Estate |
Residential |
A2 |
Cheung Chau Slaughter House |
Slaughter house |
A3 |
Cheung Chau Commercial Centre |
Office |
A4 |
Cheung Chau Fire Station |
Government Quarter |
Construction Dust
2.5.1 Baseline dust monitoring shall be carried out at the designated monitoring location shown in Table 2.1 for at least 14 consecutive days prior to the commissioning of the construction works to obtain daily 24-hour TSP samples. One-hour TSP sampling shall also be done at least 3 times per day while the highest dust impact is expected.
2.5.2 During the baseline monitoring, there shall not be any construction or dust generation activities in the vicinity of the monitoring station. Before commencing baseline monitoring, the ET shall inform the ER and IEC of the baseline monitoring programme.
2.5.3 In case the baseline monitoring cannot be carried out at the designated monitoring location during the baseline monitoring period, the ET Leader shall carry out the monitoring at an alternative location that can effectively represent the baseline conditions at the impact monitoring location. The alternative baseline monitoring location shall be approved by the ER and IEC.
2.5.4 In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the ER and IEC to agree on an appropriate set of data to be used as a baseline reference and submit to ER and IEC for approval.
2.5.5 Ambient conditions may vary seasonally and shall be reviewed once every three months. When the ambient conditions have changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring shall be conducted at times when the Contractor's activities are not generating dust, at least in the proximity of the monitoring stations. Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, shall be revised. The revised baseline levels and air quality criteria shall be agreed with the ER and IEC.
Odour
2.5.6 Prior to the demolition of the existing major odour emission sources in Cheung Chau STW or commissioning of the upgraded treatment facility of Cheung Chau STW, and prior to commissioning of the upgraded Pak She SPS, a programme to odour sampling with olfactometry analysis and H2S concentration measurement at the selected ASRs as shown in Table 2.2, A1 to A4, shall be undertaken by the ET to establish the prevailing odour condition for one year at a three months interval. The ET shall submit the baseline monitoring programme to the IEC for agreement prior to conducting the monitoring works. In case insufficient baseline monitoring results are obtained, the ET shall liaise with the ER and IEC to agree on an appropriate set of data to be used as a baseline reference and submit to ER and IEC for agreement.
Construction Phase
2.6.1 The ET shall carry out impact monitoring during construction phase of the Project. For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days shall be undertaken when the highest dust impact occurs. Before commencing the impact monitoring, the ET Leader shall inform the IEC of the impact monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the impact monitoring results.
2.6.2 In case of non-compliance with the air quality criteria, additional monitoring as specified in the Action Plan in Table 2.4 shall be conducted within 24 hours after the result is obtained. This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified.
Operation Phase
Odour Monitoring during
Commissioning Stage
2.6.3 The odour removal efficiency of deodorization units shall be audited at a monthly interval during the first year of commissioning stage. Odour sampling with olfactometry analysis and H2S measurements shall be conducted at the exhaust vent and inlet of the each deodorization unit. Correlation between odour level (in odour units) and H2S concentration will be established. Once such correlation is established, only H2S monitoring shall be carried out after the commissioning period, which serves as a surrogate indicator for odour. The H2S concentrations measured can be converted to equivalent odour units. Air flow rate at the exhaust vent shall also be recorded.
2.6.4 In addition, odour sampling with
olfactometry analysis and H2S measurements are to be conducted at a monthly interval during the first
year of commissioning stage at the selected ASRs as
shown in Table 2.2.
2.6.5
Upon completion of the first commissioning year monitoring, the ET shall
summarise all the monitored results including analysis of the results to
establish the correlation between H2S concentration and the odour
units due to the operation of the upgraded Cheung Chau STW and Pak She SPS, and
the trend of odour removal efficiency of the deodorization
units, for the IEC agreement. The trend of the odour removal
efficiency of the deodorization units will be used for reviewing their
maintenance frequency.
Subsequent Monitoring
2.6.6
Based on the
monitoring results obtained from the first year commissioning period the ET
shall propose detailed monitoring requirements and programme for the Operation
and Maintenance (O&M) period thereafter the first commissioning year for
agreement by the IEC. As a basic
approach, odour monitoring shall be
conducted in the first five years of the Operation and Maintenance (O&M) period after the first commissioning
year. The odour
removal efficiency of deodorization units shall be monitored. H2S measurement shall be conducted at the exhaust vent and inlet of the each deodorization unit at a three month interval for the
upgraded Cheung Chau STW and Pak She SPS.
The measured H2S concentration shall be converted to the
equivalent odour units based on the correlation established during the first
year commissioning period. The odour removal efficiency of the deodorization units shall be calculated and
reported. With reference to the
monitoring results, the frequency of monitoring could be revised to fit the
situation, subject to EPD¡¦s approval.
2.7.1 The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP. Table 2.3 shows the air quality criteria, namely Action and Limit levels to be used.
Table 2.3 Action
/ Limit Levels for Air Quality
Parameters |
Action Level |
Limit Level |
1-hour TSP Level
|
For baseline level ≤ 200 µg/m3 For baseline level > 200 µg/m3 |
260 µg/m3 |
24-hour TSP
Level in µg/m3 |
For baseline level ≤ 384 µg/m3 For baseline level > 384 µg/m3 |
500 µg/m3 |
Odour Nuisance |
Averaged baseline H2S concentration measured at ASRs (commissioning period only); or any incidence of odour complaint received through the Odour Complaint Register |
Averaged baseline H2S
concentration or the 5 OU equivalent, whichever is greater at ASRs
(commissioning period only); or two or more complaints through the Odour
Complaint Register within a three month period; or odour removal efficiency
of deodorization units drops below 99%. |
Note: AL = Action level, LL
= Limit level, BL = Baseline level |
2.8.1 Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Table 2.4 and Table 2.5 shall be carried out.
Table 2.4 Event and Action Plan for Air Quality
(Construction Dust)
ACTION Plan for
Construction Dust |
||||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
Exceedance for
one sample |
1.
Identify source, investigate the causes of
exceedance and propose remedial measures; 2.
Inform IEC and ER; 3.
Repeat measurement to confirm finding; and 4.
Increase monitoring frequency to daily. |
1. Check monitoring
data submitted by ET; and
2. Check
Contractor¡¦s working method. |
1.
Notify Contractor. |
1.
Rectify any unacceptable practice; and 2.
Amend working methods if appropriate. |
Exceedance for
two or more consecutive samples |
1.
Identify source; 2.
Inform IEC and ER; 3.
Advise the ER on the effectiveness of the
proposed remedial measures; 4.
Repeat measurements to confirm findings; 5.
Increase monitoring frequency to daily; 6.
Discuss with IEC and Contractor on remedial
actions required; 7.
If exceedance continues, arrange meeting
with IEC and ER; and 8.
If exceedance stops, cease additional
monitoring. |
1. Check monitoring
data submitted by ET;
2. Check
Contractor¡¦s working method;
3. Discuss with ET
and Contractor on possible remedial measures;
4. Advise the ET on
the effectiveness of the proposed remedial measures; and
5. Supervise
implementation of remedial measures |
1.
Confirm receipt of notification of failure
in writing; 2.
Notify Contractor; and 3.
Ensure remedial measures properly
implemented. |
1.
Submit proposals for remedial to IEC within
3 working days of notification; 2.
Implement the agreed proposals; and 3.
Amend proposal if appropriate. |
EVENT |
ACTION
Plan for Construction Dust |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
LIMIT LEVEL |
||||
Exceedance for
one sample |
1. Identify source,
investigate the causes of exceedance and propose remedial measures; 2. Inform IEC, ER,
and EPD; 3. Repeat measurement
to confirm finding; 4. Increase
monitoring frequency to daily; and 5. Assess
effectiveness of Contractor¡¦s remedial actions and keep EPD and ER informed
of the results. |
1. Check monitoring
data submitted by ET;
2. Check
Contractor¡¦s working method;
3. Discuss with ER
and Contractor on possible remedial measures;
4. Advise the ER on
the effectiveness of the proposed remedial measures; and
5. Supervise
implementation of remedial measures.
|
1. Confirm receipt
of notification of failure in writing; 2. Notify Contractor;
and 3. Ensure remedial
measures properly implemented. |
1. Take immediate
action to avoid further exceedance; 2. Submit proposals
for remedial actions to IEC within 3 working days of notification; 3. Implement the
agreed proposals; and 4. Amend proposal if
appropriate. |
Exceedance for
two or more consecutive samples |
1. Notify ER,
Contractor and EPD; 2. Identify source; 3. Repeat
measurement to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry out analysis
of Contractor¡¦s working procedures to determine possible mitigation to be
implemented; 6. Arrange meeting
with IEC and ER to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER informed
of the results; and 8. If exceedance
stops, cease additional monitoring. |
1. Discuss amongst
ER, ET and Contractor on potential remedial actions; 2. Review
Contractor¡¦s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; and 3. .Supervise the
implementation of remedial measures.
|
1.
Confirm receipt of notification of failure
in writing; 2.
Notify Contractor; 3.
In consolidation with the IEC, agree with
the Contractor on the remedial measures to be implemented; 4.
Ensure remedial measures properly
implemented; and 5.
If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1. Take immediate
action to avoid further exceedance; 2. Submit proposals
for remedial actions to IEC within 3 working days of notification; 3. Implement the
agreed proposals; 4. Resubmit
proposals if problem still not under control; and 5. Stop the
relevant portion of works as determined by the ER until the exceedance is
abated. |
Table
2.5 Event and Action Plan for Air Quality
(Operational Phase)
EVENT |
ACTION Plan for ODOUR |
|
Person in charge of Odour Monitoring |
DSD |
|
ACTION LEVEL |
||
Exceedance of
Action level (odour measurement) |
1.
Identify source/ reason of exceedance; 2.
Repeat
measurement to confirm findings. |
1.
Carry out investigation to identify the
source/reason of exceedance.
Investigation shall be completed within 2 weeks; 2.
Implement more mitigation measures if
necessary; 3.
Inform EPD if the cause of exceedance is
considered to be caused by the STW / SPS; 4.
Undertake maintenance of the deodourization
facility if necessary. |
Exceedance of
Action level (odour
complaint) |
1.
Identify source/ reason of complaint; 2.
Carry out measurement to determine odour
emissions from STW / SPS. |
1.
Carry
out investigation and verify the complaint whether it is related to potential
odour emissions from the STW / SPS.
Investigation
should be completed within 2 weeks; 2.
Implement more mitigation measures if
necessary; 3.
Inform EPD if the complaint is considered
to be related to the STW / SPS; 4.
Undertake maintenance of the deodourization
facility if necessary. |
LIMIT LEVEL |
||
Exceedance of
Limit level |
1.
Identify source/ reason of exceedance /
complaint; 2. Carry
out measurement to determine odour emissions from STW / SPS; 3. Carry out analysis of the
operation and implementation of odour mitigation measures to determine if
possible mitigation to be implemented; 4. Carry
out measurement to determine odour emissions from STW / SPS after
implementation of abatement measures to confirm their effectiveness. |
1.
Carry out investigation to identify the source/reason
of exceedance. Investigation
shall be completed within 2 weeks;
2.
Inform EPD if the cause of exceedance /
complaint is considered to be caused by the STW / SPS; 3.
Formulate abatement measures; 4.
Ensure abatement measures are properly implemented; 5.
If exceedance continues, consider what more / enhanced mitigation measures should be implemented, until the exceedance is abated; 6.
Undertake maintenance of the deodourization
facility if necessary. |
Construction Phase
2.9.1 Mitigation measures for dust control have been recommended in the EIA report. The contractor shall be responsible for the design and implementation of these measures.
2.9.2 For the construction activities under the Project, the suitable requirements stipulated in the Air Pollution Control (Construction Dust) Regulation shall be implemented during the construction activities to minimise the dust impact. It is recommended that typical dust control methods including the following good site practices should also be incorporated during construction phase:
¡P
Watering
eight times a day on active works areas and paved haul roads to reduce dust
emissions by 90.9% (e.g. watering intensity at 0.5 litres/m2. Actual application shall depend on the
site condition and weather conditions).
¡P
Watering
every hour on unpaved areas and stockpiles of dusty materials (if no tarpaulin
is provided) to reduce dust emissions by 90% (e.g. watering intensity at 1.5
litre/m2 during the first hour, subsequent application at 0.2
litre/m2. Actual
application shall depend on the site condition and weather conditions).
¡P
Use
of regular watering, with complete coverage, to reduce dust emissions from
exposed site surfaces and unpaved roads, particularly during dry weather.
¡P
Use
of frequent watering for particularly dusty construction areas and areas close
to ASRs.
¡P
Vehicle
washing facilities should be provided at every vehicle exit point.
¡P
Where
a site boundary adjoins a road, streets or other areas accessible to the
public, hoarding of not less than 2.4 m high from ground level should be provided
along the entire length except for a site entrance or exit.
¡P
Stockpiles
of imported material kept on site shall be contained within hoarding, dampened
and/or covered during dry and windy weather.
¡P
Material
stockpiled alongside trenches should be covered with tarpaulins.
¡P
Open
stockpiles shall be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs.
¡P
Any
excavated or stockpile of dusty material should be covered entirely by
impervious sheeting or spayed with water to maintain the entire surface wet
during the non-working hours.
¡P
All
dusty materials shall be sprayed with water prior to any loading, unloading or
transfer operation so as to keep the dusty materials wet.
¡P
Water
sprays shall be used during the delivery and handling of sands aggregates and
the like.
¡P
All
demolished items that may emit dust particles should be covered entirely by
impervious sheeting or placed in an area sheltered on the top and the 3 sides
within a day of demolition.
¡P
Good
site practices for concrete batching
plant:
-
Every
stock of more than 20 bags of cement or dry pulverized fuel ash (PFA) should be
cover entirely by impervious sheeting or placed in an area sheltered on the top
and the sides.
-
Cement
or dry PFA delivered in bulk should stored in a closed silo fitted with an
audible high level alarm which is interlocked with the material filling line
and no overfilling is allowed.
-
Loading,
unloading, transfer, handling or storage of bulk cement or dry PFA should be
carried out in a totally enclosed system or facility, and any vent or exhaust
should be fitted with effective fabric filter or equivalent air pollution
control system (maximum TSP emission factor of silos and mixing tower: 50 mg/m3)
Operation Phase
2.9.3 The design of enclosing the odour sources of the upgraded Cheung Chau STW and Pak She SPS and the installation of deodorization units would readily reduce the potential odour impacts. Adverse odour impact from the upgraded Cheung Chau STW and Pak She SPS is not anticipated.
2.9.4 In addition, good housekeeping practices listed below should be followed to control odour emissions from the plant and these standard practices should be included in the plant operator manual:
¡P
Screens
should be cleaned regularly to remove accumulated organic debris;
¡P
Grit
and screening transfer systems should be flushed regularly with water to remove
organic debris and grit;
¡P
Grit
and screened materials should be transferred to closed containers to minimize
odour escape;
¡P
Sludge
should be frequently withdrawn from tanks to prevent the production of gases;
¡P
Sludge
should be transferred to closed containers; and
¡P
Sludge
containers should be flushed with water regularly.
3.1.1 In this section, the requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of noise impacts during the construction of upgrading of Cheung Chau STW and Pak She SPS (DP component) and sewers works (non-DP component) under the Project are presented.
3.1.2 No adverse operational noise impacts are expected if appropriate design and noise mitigation are adopted. Therefore, no EM&A programme is recommended for the operational phase of the Project.
Noise Parameters
3.2.1 The construction noise level shall be measured in terms of equivalent A-weighted sound pressure level (Leq). Leq (30min) shall be used as the monitoring parameter for the time period between 07:00-19:00 hours on normal weekdays. For all other time period, Leq (5min) shall be employed for comparison with the Noise Control Ordinance criteria. The two statistical sound levels L10 and L90, the level exceeded for 10% and 90% of the time respectively, shall also be recorded during monitoring. The L90 may be considered as the ambient level into which the L10 as an average peak level intrudes. A sample data record sheet is shown in Appendix B.
Noise Monitoring Equipment /
Calibration
3.2.2 Sound level meters and calibrators shall comply with the International Electrotechnical Commission (IEC) Publication 651:1979 (Type 1) and 804:1985 (Type 1) specification as referred to in the Technical Memorandum (TM) issued under the Noise Control Ordinance. The sound level meters shall be supplied and used with the manufacturer recommended weather shield as appropriate.
3.2.3 Sound level meters shall be calibrated using a portable calibrator prior to and following each noise measurement. The calibration levels shall be noted with the measurement results and where the difference between the calibration levels is greater than 1.0 dB(A), the measurement shall be repeated. Calibrated hand-held anemometers shall also be supplied for the measurement of wind speeds during noise monitoring periods.
3.2.4 The equipment shall be kept in a good state of repair in accordance with the manufacturer¡¦s recommendations and maintained in proper working order with sufficient spare equipment available in the event of breakdown to maintain the planned monitoring programme.
3.2.5 Noise measurements will not be made in the presence of fog, rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed shall be checked with the hand-held anemometers capable of measuring the wind speed in m/s.
3.2.6 The ET is responsible for provision of the monitoring equipment. He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. All the equipment and associated instrumentation shall be clearly labelled.
3.3.1 Weatherproof logging sound level meters shall be installed at the monitoring locations during baseline monitoring. Continuous baseline noise for the A-weighted levels Leq, L10 and L90 shall be measured over a two week period, and sampling period of 5 minutes will be used throughout the monitoring. Average, by sound power, of six consecutive Leq (5 min) reading is used to provide Leq (30 min) for the non-restricted period and three consecutive Leq (5 min) reading is used to provide Leq (15 min) for the restricted period during the impact stage.
3.3.2 Regular visits, for a period of at least once every three to four days, shall be conducted by the ET to ensure the continuous operations of the sound level meter. Impact monitoring shall be conducted once a week. Information such as date of monitoring, weather condition, equipment used, measurement results and major noise sources will be recorded on the data record sheet. Examples of the record sheets are presented in Appendix B.
3.4.1 Ten monitoring locations as presented in Table 3.1 have been identified for noise monitoring within the Study Area. Their locations are shown in Figure 3.1 ¡V 3.8. The status and locations of noise sensitive receivers may change after the approval of the EIA Report. If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from ER.
Table 3.1 Noise Monitoring Locations
ID No. |
Location |
Nature of Uses |
Construction Works (1) |
N1 |
No.4 Tai Kwai
Wan San Tsuen |
Residential |
Non-DP |
N2 |
Cheung King
House, Cheung Kwai Estate |
Residential |
DP |
N3 |
No. 1A Pak She
Second Lane |
Residential |
DP |
N4 |
3A Golden Lake
Garden |
Residential |
Non-DP |
N5 |
No.24 Tai Hing
Tai Road |
Residential |
Non-DP |
N6 |
Cheng Chau
Fisheries Joint Association Public School |
Educational |
Non-DP |
N7 |
No. 34 Praya
Street |
Residential |
Non-DP |
N8 |
No.41A Peak Road |
Residential |
Non-DP |
N9 |
Block G-H Fu
Yuen |
Residential |
Non-DP |
N10 |
Caritas Ka Fai
House |
Residential |
Non-DP |
Note: (1)
DP refers to the works of upgrading of Cheung Chau STW and Pak She SPS;
Non-DP refers to the works of sewers works |
3.4.2 When alternative monitoring locations are proposed, the monitoring locations shall be chosen based on the following criteria:
(i)
The locations shall be close to the site activities
which are likely to have significant noise impacts;
(ii)
The locations shall be close to the noise
sensitive receivers (NSRs) (NB. For the purpose of this section, any domestic
premises, hotel, hostel, temporary housing accommodation, hospital, medical
clinic, educational institution, place of public worship, library, court of
law, performing art centre shall be considered as NSR); and
(iii)
Care shall be taken to cause minimal
disturbance to the occupants of sensitive receivers.
3.4.3 The monitoring location shall normally be at a position from the exterior of the sensitive receivers building façade and 1.2m above the ground. If there is a problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurement made. For reference, a correction of +3dB(A) shall be made to free field measurements. The ET Leader shall agree with the IEC on the monitoring position and the corrections adopted. Once the positions for the monitoring stations are chosen, the baseline and impact monitoring shall be carried out at the same position.
3.5.1 To obtain fully satisfactory baseline results, weatherproof logging sound level meter shall be used. Continuous baseline noise for the A-weighted levels Leq, L10 and L90 shall be measured over a period of two consecutive weeks and sampling period of 5 minutes will be used throughout the monitoring. Average, by sound power, of six consecutive Leq (5 min) reading is used to provide Leq (30 min) for the non-restricted period and three consecutive Leq (5 min) reading is used to provide Leq (15 min) for the restricted period. The monitoring period shall be selected prior to the commencement of any construction activities and so as to avoid other typical noise sources. Measurements shall be recorded to the nearest 0.1 dB. Major noise sources observed, both on-site and off-site, at each location will be recorded. A schedule on the baseline monitoring shall be submitted to the IEC for approval before the monitoring.
3.5.2 In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader and Contractor shall liaise with the IEC to agree on an appropriate set of data to be used as a baseline reference and submit to the IEC for approval.
3.6.1 Noise monitoring shall be undertaken at all designated monitoring stations when there are construction works nearby. The following is an initial guide on the regular monitoring frequency for each station on a per week basis when construction activities are undertaken:
(i)
one set of Leq (30 min) noise
level as six consecutive Leq (5 min) between 07:00-19:00 hours on
normal weekdays;
(ii)
one set of Leq (15 min) noise
level as three consecutive Leq (5 min) for the restricted hours.
3.6.2 Major noise sources observed, both on-site and off-site, at each location shall be recorded.
3.6.3 Where the designated noise monitoring station is a school, noise monitoring shall be scheduled during the school examination period. The ET Leader shall liaise with the school¡¦s personnel and the Examination Authority to ascertain the exact dates and times of all examination periods during the course of the contract.
3.6.4 In the case of non-compliance with the construction noise criteria, more frequent monitoring as specified in the Event and Action Plan in Table 3.3 shall be carried out. This additional monitoring shall be continued until the exceedance is rectified or proved to be from a source other than the construction activities.
3.7.1 The Action and Limit levels for construction noise are shown in Table 3.2. All NSRs identified in the Project are classified with an Area Sensitivity Rating (ASR) A in accordance with the Technical Memorandum on Noise from Construction Work Other Than Percussive Piling. Should non-compliance of the noise criteria occurs, action in accordance with the Event / Action Plans in Table 3.3 shall be carried out.
Table 3.2 Action and Limit Levels
for Construction Noise
Time Period |
Action |
Limit |
07:00-19:00
hours on normal weekdays; |
When one or more
documented complaints are received |
75dB(A)* |
07:00-23:00
hours on holidays; |
45(1)
dB(A) |
|
23:00-07:00
hours of the next day |
30(1) dB(A) |
Note: • Between 07:00-19:00 hours, construction noise
limit for school during normal term time is 70dB(A) and 65dB(A) during
examination period.
ASR = ¡§A¡¨ which is a rural area that are not affected by
the IF.
(1) - As stipulated In the Technical Memorandum on Noise
from Construction Work in Designated Areas.
(2) - As stipulated in the Technical Memorandum on Noise
from Construction Work other than Percussive Piling
Table 3.3
Event / Action Plan for Construction Noise
Event |
ET |
IEC |
ER |
CONTRACTOR |
Action Level |
1.
Notify ER, IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the
IEC, ER and Contractor; 4.
Discuss with the IEC and contractor and
formulate remedial measures; and 5.
Increase monitoring frequency to check the
effectiveness of mitigation measures. |
1. Review the
investigation results submitted by the ET;
2. Review the
proposed remedial measures by the Contractor and advise the ER accordingly;
and
3. Advise the ER on
the effectiveness of the proposed remedial measures. |
1. Confirm receipt
of notification of failure in writing;
2. Notify
Contractor;
3. In consolidation
with the IEC, agree with the Contractor on the remedial measures to be
implemented; and
4. Supervise the
implementation of remedial measures.
|
1. Submit noise
mitigation proposals to IEC and ER; and
2. Implement noise
mitigation proposals. |
Limit Level |
1. Notify IEC, ER,
EPD & Contractor;
2. Identify source
and investigate the cause of exceedance;
3. Repeat
measurement to confirm findings;
4. Increase
monitoring frequency;
5. Carry out
analysis of Contractor¡¦s working procedures to determine possible mitigation
to be implemented;
6. Discuss with the
IEC, Contractor and ER on remedial measures required;
7. Assess the
effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER
informed of the results; and
8. If exceedance
stops, cease additional monitoring. |
1. Discuss amongst
ER, ER and Contractor on the potential remedial actions; and
2. Review
Contractor¡¦s remedial actions whenever necessary to assure their effectiveness
and advise the ER accordingly. |
1. Confirm receipt
of notification of failure in writing;
2. Notify
Contractor;
3. In consolidation
with the EIC, agree with the Contractor on the remedial measures to be
implemented;
4. Supervise the
implementation of remedial measures; and
5. If exceedance
continues, consider stopping the Contractor to continue working on that
portion of work which causes the exceedance until the exceedance is abated. |
1. Take immediate
action to avoid further exceedance;
2. Submit proposals
for remedial actions to IEC and ER within 3 working days of notification;
3. Implement the
agreed proposals;
4. Submit further
proposal if problem still not under control; and
5. Stop the
relevant portion of works as determined by ER, until the exceedance is
abated. |
3.8.1 The Contractor shall be responsible for the design and implementation of the measures recommended in Appendix C, Table C2.
4.2 Water Quality Monitoring Equipment
Dissolved Oxygen (DO) and Temperature Measuring Equipment
Turbidity Measurement Instrument
Water Sampling Equipment
Water Depth Detector
Salinity
pH
Monitoring Positioning Equipment
4.3 Construction Phase Water Quality Monitoring
Construction Site Audit
Site Inspection
¡P
Record the problems and investigate the cause;
¡P
Issue action notes to the Contractor who is responsible for the works;
¡P
Implement remedial and corrective actions immediately;
¡P
Re-inspect the site condition upon completion of the remedial and
corrective actions; and
¡P
Record the event and discuss with the Contractor for preventive actions.
Compliance Audit
¡P
Notify the Contractor, IEC and ER on the non-compliance;
¡P
Identify the sources of pollution;
¡P
Check the implementation status of recommended mitigation measures;
¡P
Investigate the operating conditions of on-site treatment systems;
¡P
Implement corrective and remedial actions to improve the effluent
quality;
¡P
Increase the monitoring frequency until the effluent quality is in
compliance with the discharge licence requirements; and
¡P
Record the non-compliance events and propose preventive measures.
4.4 Operational Phase Water Quality Monitoring
Water Quality Parameters
Laboratory Analysis
Table 4.1 Analytical
Methods and Detection Limits for Marine Water Samples
Parameters |
Standard Method |
Detection Limit |
Suspended Solid
(SS) |
APHA 20ed.2540
D |
0.5 mg /L |
5-day
Biochemical Oxygen Demand (BOD5) |
APHA 18ed.
5210B |
0.1 mg /L |
Ammonia
Nitrogen (NH3-N) |
ASTM D3590-89 B
(FIA) |
0.005 mg /L |
Unionised
Ammonia (NH4-N) |
By Calculation |
0.001 mg/L |
Total Kjeldahl
Nitrogen (TKN) |
ASTM D3590-89 B
(FIA) and APHA 20ed 4500-N A&D (FIA) |
0.05 mg/L |
Total Inorganic
Nitrogen (TIN) |
By Calculation |
0.01 mg/L |
Nitrite-nitrogen
(NO2) |
APHA 20ed.
4500-NO2- B (FIA) |
0.002 mg/L |
Nitrate-nitrogen
(NO3) |
APHA 20ed.
4500-NO3- F & I (FIA) |
0.002 mg/L |
Orthophosphorus
(PO4) |
ASTM D515-88 A
(FIA) |
0.002 mg/L |
Total
Phosphorus (TP) |
ASTM D515-88 B
(FIA) and APHA 20ed 4500-P G (FIA) |
0.02 mg/L |
E.coli |
membrane
filtration with CHROMagar Liquid E. coli ¡Vcoliform culture (1) |
1 cfu/100mL |
Note:
(2)
(a) DoE, DHSS & PHLS (1983); The
Bacteriological Examination of Drinking Water Supplies 1982, Sec.7.8 & 7.9;
and (b) B.S.W. Ho and T.Y. Tam (1997), Enumeration of E. coli in environmental
waters and wastewater using a chromogenic medium. Wat. Sci. Tech.Vol.35,
No.11-12, pp.409-413; method adopted in 1997.
Monitoring Locations
Table 4.2 Marine Water Monitoring Locations
Locations |
Station |
Easting |
Northing |
Cheung Chau STW |
W1 |
820151.20 |
808236.90 |
Cheung Chau Wan |
W2 |
820579.40 |
807761.65 |
Tung Wan |
W3 |
821221.73 |
808130.84 |
Kwun Yam Wan |
W4 |
821469.22 |
807804.01 |
Tai Kwai Wan |
W5 |
820493.00 |
808822.31 |
Chi Ma Wan |
W6 |
817649.00
|
811487.00 |
Baseline Water Quality Monitoring
Operational Phase Marine Water Monitoring
Operational Phase STW Effluent Quality Monitoring
Table 4.3 Thresholds
for Marine Water Quality Parameters
Parameters |
Action Threshold |
Limit Threshold |
DO in mg/ L (Surface, Middle & Bottom) |
Surface & Middle : 5 percentile of baseline data for surface and middle layer Bottom: 5 percentile of baseline data for bottom layer. |
Surface & Middle: 4 mg/L or 1 percentile of baseline data for surface and middle
layer. Bottom: 2 mg/L or 1 percentile of baseline data for bottom layer. |
SS in mg/ L (depth-averaged) |
95 percentile of baseline data or 120% of upstream control station's
SS at the same tide of the same day. |
99 percentile of baseline data or 130% of upstream control station's
SS at the same tide of the same day. |
Unionised Ammonia in mg /L (depth-averaged) |
95 percentile of baseline data. |
99 percentile of baseline data or 0.021 mg /L. |
E.coli (depth-averaged) |
95 percentile of baseline data. |
(i)
99 percentile of baseline or
610 cfu/100mL as geometric mean for secondary contact, recreation subzones
and fish culture zones. (ii) 99 percentile of baseline or 180 cfu/100mL as geometric mean for bathing
beach subzones. |
Turbidity in NTU (depth-averaged) |
95 percentile of baseline data or 120% of upstream control station's
turbidity at the same tide of the same day. |
99 percentile of baseline or 130% of upstream control station's turbidity
at the same tide of the same day. |
TIN in mg/ L (depth-averaged) |
95 percentile of baseline data. |
99 percentile of baseline data. |
Notes: 1. ¡§Depth-averaged¡¨ value is calculated by taking the arithmetic
means of reading of all three depths.
2. For DO, non-compliance of the water quality limits occurs when
monitoring result is lower than the threshold.
3. For turbidity, SS and TIN, non-compliance occurs when monitoring
result is higher than the threshold.
4. All the figures given in the table are used for reference only and
could be amended by EPD.
Table 4.4 Event and Action Plan for Protection of
Marine Water Quality
Event |
Actions to be Taken |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action threshold
exceeded by one sampling day |
1. Repeat in-situ
measurement on next day of exceedance to confirm findings; 2. Identify source(s)
of impact; 3. Inform IEC,
Contractor and ER; and 4. Check monitoring
data, all plant, equipment and Contractor¡¦s working methods. |
1. Check monitoring
data submitted by ET and Contractor¡¦s working methods. |
1. Confirm receipt
of notification of noncompliance in writing; and 2. Notify
Contractor. |
1. Inform the ER and
confirm notification of the noncompliance in writing; 2. Rectify
unacceptable practice; and 3. Amend working
methods if appropriate. |
Action threshold exceeded
by two or more consecutive sampling days |
1. Repeat
measurement on next day of exceedance to confirm findings; 2. Identify
source(s) of impact; 3. Inform IEC,
Contractor, ER, EPD, and AFCD; 4. Check monitoring
data, all plant, equipment and Contractor¡¦s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure mitigation
measures are implemented; and 7. Increase the
monitoring frequency to daily until no exceedance of Action level. |
1. Check monitoring
data submitted by ET and Contractor¡¦s working method; 2. Discuss with ET
and Contractor on possible remedial actions; 3. Review the
proposed mitigation measures submitted by Contractor and advise the ER
accordingly; and 4. Supervise the
implementation of mitigation measures. |
1. Discuss with IEC
on the proposed mitigation measures; 2. Ensure mitigation
measures are properly implemented; and 3. Assess the
effectiveness of the implemented mitigation measures. |
1. Inform the
Engineer and confirm notification of the noncompliance in writing; 2. Rectify
unacceptable practice; 3. Check all plant
and equipment and consider changes of working methods; 4. Submit proposal
of additional mitigation measures to ER within 3 working days of notification
and discuss with ET, IEC and ER; and 5. Implement the
agreed mitigation measures. |
Limit threshold
exceeded by one sampling day |
1. Repeat
measurement on next day of exceedance to confirm findings; 2. Identify
source(s) of impact; 3. Inform IEC, Contractor,
ER, EPD, and AFCD; 4. Check monitoring
data, all plant, equipment and Contractor¡¦s working methods; and 5. Discuss
mitigation measures with IEC, ER and Contractor. |
1. Check monitoring
data submitted by ET and Contractor¡¦s working method; 2. Discuss with ET
and Contractor on possible remedial actions; and 3. Review the
proposed mitigation measures submitted by Contractor and advise the ER
accordingly. |
1. Confirm receipt
of notification of failure in writing; 2. Discuss with IEC,
ET and Contractor on the proposed mitigation measures; and 3. Request
Contractor to review the working methods. |
1. Inform the ER and
confirm notification of the noncompliance in writing; 2. Rectify
unacceptable practice; 3. Check all plant
and equipment and consider changes of working methods; and 4. Submit proposal
of mitigation measures to ER within 3 working days of notification and
discuss with ET, IEC and ER. |
Limit threshold
exceeded by two or more consecutive sampling days |
1. Repeat measurement
on next day of exceedance to confirm findings; 2. Identify
source(s) of impact; 3. Inform IEC,
Contractor, ER, EPD, AFCD; 4. Check monitoring
data, all plant, equipment and Contractor¡¦s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure mitigation
measures are implemented; and 7. Increase the
monitoring frequency to daily until no exceedance of Limit level for two
consecutive days. |
1. Check monitoring
data submitted by ET and Contractor¡¦s working method; 2. Discuss with ET
and Contractor on possible remedial actions; 3. Review the
Contractor¡¦s mitigation measures whenever necessary to assure their
effectiveness and advise the ER accordingly; and 4. Supervise the
implementation of mitigation measures. |
1. Discuss with IEC,
ET and Contractor on the proposed mitigation measures; 2. Request
Contractor to critically review the working methods; 3. Make agreement on
the mitigation measures to be implemented; 4. Ensure mitigation
measures are properly implemented; and 5. Consider and
instruct, if necessary, the Contractor to slow down or to stop all or part of
the construction activities until no exceedance of Limit level. |
1. Take immediate
action to avoid further exceedance; 2. Submit proposal
of mitigation measures to ER within 3 working days of notification and
discuss with ET, IEC and ER; 3. Implement the
agreed mitigation measures; 4. Resubmit
proposals of mitigation measures if problem still not under control; and 5. As directed by
the Engineer, to slow down or to stop all or part of the construction
activities until no exceedance of Limit level. |
Site Audit / Inspection
Waste Management Practices
Mitigation Measures
¡P
To minimize the production of construction waste through careful design,
planning, good site management, and control of ordering procedures, segregation
and reuse of materials; To arrange for private contractors to collect used
formwork materials for reuse;
¡P
To dispose of any chemical wastes such as lubricating oil or solvent in
strict accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. Only licensed chemical
waste collectors shall be employed to collect any chemical waste generated at
site. The handling, storage, transportation
and disposal of chemical wastes shall be conducted in accordance with the Code
of Practice on the Packaging, Labelling and Storage of Chemical Wastes and A
Guide to the Chemical Waste Control Scheme both published by EPD;
¡P
All chemical toilets, if any, shall be regularly cleaned and the
night-soil collected and transported by a licensed contractor to a Government
Sewage Treatment Works facility for disposal;
¡P
To assign a reliable waste collector to collect general refuse generated
from the construction site on a daily basis to minimise the potential odour,
pest and litter impacts;
¡P
To identify requirements on proper waste management for implementation
during the operation of the project; and
¡P
Toolbox talks shall be provided to workers about the concepts of site
cleanliness and appropriate waste management procedures, including waste
reduction, reuse and recycling.
Good Site Practices
¡P
The Contractor shall be responsible for identifying what materials can
be recycled/ reused, whether on-site or off-site. In the event of the latter,
the Contractor shall make arrangements for the collection of the recyclable
materials. Any remaining non-inert
waste shall be collected and disposed of to the Public Filling Areas whilst any
inert C&D materials shall be re-used on site as far as possible. Alternatively, if no use of the inert
material can be found on-site, the materials can be delivered to a Public Fill
Area or Public Fill Bank after obtaining the appropriate licence;
¡P
In order to monitor the disposal of C&D material and solid wastes at
public filling facilities and landfills, and control fly-tipping, a trip-ticket
system shall be implemented by the Contractor, in accordance with the contract
and the requirements of Development Bureau Technical Circular (Works) (TC(W))
No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition
Materials;
¡P
Under the Waste Disposal (Chemical Waste) (General) Regulation, the
Contractor shall register with EPD as a Chemical Waste Producer if there is any
use of chemicals on site including lubricants, paints, diesel fuel, etc. Only licensed chemical waste collectors
shall be employed to collect any chemical waste generated at site. The handling, storage, transportation
and disposal of chemical wastes shall be conducted in accordance with the Code
of Practice on the Packaging, Labelling and Storage of Chemical Wastes and A
Guide to the Chemical Waste Control Scheme both published by EPD;
¡P
A sufficient number of covered bins shall be provided on site for the
containment of general refuse to prevent visual impacts and nuisance to the
sensitive surroundings. These bins
shall be cleared daily and the collected waste disposed of to the refuse
transfer station. Further to the issue of ETWB TCW No. 6/2002A, Enhanced
Specification for Site Cleanliness and Tidiness, the Contractor is required to
maintain a clean and hygienic site throughout the project works;
¡P
All chemical toilets, if any, shall be regularly cleaned and the
night-soil collected and transported by a licensed contractor to a Government
Sewage Treatment Works facility for disposal; and
¡P
The Contractor shall comply with all relevant statutory requirements and
guidelines and their updated versions that may be issued during the course of
project construction.
6.2 Construction Phase Protective Measures
Table 6.1 Proposed Further Archaeological Works
during Construction Phase
Tai San Street , Tai San Back
Street, Chung Hing Street and Chung Hing Back Street |
Archaeological Watching Brief
(within boundary of Tung Wan Site of Archaeological Interest) |
Archaeological Watching Brief area covers
all marked alignments within Figures 6.6, 6.8, 6.9, 6.10. 100% monitoring is required for the
proposed sewer at Chung Hing Street (Figure 6.6) due to its known high
archaeological potential. 100% monitoring is proposed for the
proposed sewer near the Cheung Chau Fisheries Joint Association Public School
(Figure 6.8). Due to the moderate archaeological
potential which is based on previous findings and level of existing impacts,
one visit per four sections monitoring frequency is proposed (Figures 6.6, 6.8, 6.9, 6.10). |
|
|
Archaeological Watching Brief area is
marked on Figure 6.11. Due to its
proximity to a Declared Monument, one visit per four sections
monitoring frequency is proposed (Figure 6.11). |
||
|
A buffer zone
including the rock carving and its immediate environs and Hak Pai Road and the
nearby open space (see Figure 6.11). Within
the buffer zone, construction works as well as storage of construction
materials are not allowed.
Erection of temporary fencing/barriers to demarcate the buffer zone is
not required. The rock carving
should be maintained and directional signage should be erected or installed
at appropriate location(s) near the rock carving to facilitate visitors to
access the rock carving during the construction phase. It has to be noted
however that the access to the rock carving
will not be blocked as the works area does not encroach upon the access or
immediate environs of the rock carving. The directional signage can only be
erected on the fencing at the edge of construction works area which is locate
more than 10m from the entrance to the rock carving. |
||
Archaeological Watching Brief area at
Manhole nos. 24-28 is marked on Figure 6.8. Despite the moderate potential of
the area a 100% monitoring of the manholes until sterile soils are reached is
recommended. The manhole areas are relatively small and will be excavated by
hand. |
Provision of Buffer Zones
(BZ)
Provision of Protective
Covering (PC)
Table 6.2 Mitigation Recommendations for Graded
Historical Buildings in Cheung Chau
PC
¡V Provision of Protective Covering
Table 6.3 Mitigation Recommendations for Non-Graded
Historical Structures in Cheung Chau
PC ¡V Provision of Protective Covering
6.3 Operational Phase Protective Measures
6.4 Construction Phase EM&A Requirements
6.5 Operational Phase EM&A Requirements
Table 7.1 Proposed Mitigation Measures during Construction Phase
Landscape and Visual Impact Mitigation Measures |
Implementation Agent |
Management/ Maintenance Agent |
|
CM-1 |
Visual
Screen/Hoarding Decorative hoarding or boundary fence for
construction sites shall be considered, and designed to be compatible to the
surroundings. |
Contractor |
Contractor |
CM-2 |
Protection
to Existing Trees within Works Areas All
existing trees which are not in direct conflict with the proposed works will
be retained. The existing trees proposed to be retained shall be properly
maintained and protected by means of fencing to prevent vehicular or
pedestrian intrusion that may potentially damage tree canopies, trunks and
root zones. Detailed tree protection specifications shall be allowed and
included in the Contract Specification, which specifying the tree protection
requirement, submission and approval system, and tree monitoring system. For
trees with high preservation value, individual tree assessments and
continuous tree monitoring reports shall be provided by a certified Arborist,
Landscape Architect or related professional during construction. All retained
trees shall be recorded photographically at the commencement of contract. Root
pruning to the retained trees should be prohibited. Retained trees should be
well-preserved by setting up a tree protection zone throughout the
construction period for protecting the retained trees from damages. To maximize protection to existing trees
and ground vegetation, construction contracts may designate ¡§No-intrusion
Zone¡¨ to various areas within the site boundary with rigid and durable
fencing for each individual no-intrusion zone. The contractor should close
monitor and restrict the site working staff not to enter the ¡§no-intrusion
zone¡¨, even for non-direct construction activities and storage of equipment. |
DSD
and Contractors |
DSD
and Contractors |
CM-3 |
Tree
Transplanting Existing
trees to be affected shall be directly transplanted to the proposed tree
receiving sites, or to temporary tree nurseries alternatively. Temporary tree
nurseries may be set up for the transplanted tree and proposed trees at an
early stage to allow small trees to grow during the construction stage. By
the time when planting area becomes available, trees have been mature and
required minimal pruning and suffer much less damage during transplanting.
The construction programme should also allow sufficient time for root pruning
and root ball preparation prior to transplanting, if necessary, and
transplanting operations to be carried out in planting season. Tree pruning such as topping, lion tailing
would be prohibited as far as possible. Also, frequent keep watering would be
necessary for transplanting trees. The proposed tree preservation measures
during construction would be carried out and approved by the competent
persons. |
Contractors |
Contractors |
CM-4 |
Construction
Light Security floodlight for construction areas
shall be controlled, such as equipped with adjustable shield, frosted
diffusers and reflective covers, at night to avoid excessive glare to the
nearby areas and residents. Other security measures shall also be considered
to minimize the visual impacts by construction light. |
Contractor |
Contractor |
CM-5 |
Dust
and Erosion Control for Exposed Soil Excavation works and demolition of existing
building blocks shall be well planned with precautions to suppress dust.
Exposed soil shall be covered or watered often. Areas that are expected to be
left with bare soul for a long period of time after excavation shall be
properly covered with suitable protective fabric. Suitable drainage shall be
provided around construction sites to avoid discharge of contaminants and
sediments into sensitive water-based habitats. |
Contractor |
Contractor |
CM-6 |
Reinstatement
of Works Areas The affected works areas shall be properly
reinstated to the satisfaction of relevant government departments. |
Contractor |
Contractor |
Table 7.2 Proposed Mitigation Measures during Operational Phase
Landscape and Visual Impact Mitigation Measures |
Implementation Agent |
Management / Maintenance Agent |
|
OM-1 |
Architectural and Landscape Design The
appearance of the proposed structures shall be properly designed, including
a careful selection of material, colour and texture, so as to fit into the existing
suburban, natural to semi-natural surroundings. The aesthetic design of the
proposed structures will follow the requirements in the Guidelines on
Aesthetic Design of Pumping Station Buildings and submitted to Vetting
Committee on Aesthetic Design of Pumping Station Buildings (VCAB) for
approval in accordance with DSD TC No. 9/2006, and circulated to ASD for
comment in accordance with ETWB TCW No. 8/2005. Sufficient planting shall be
considered and provided around the boundary fence of the proposed buildings
for screening. Buffer planting will also be considered during the detailed
design. |
DSD |
DSD |
OM-2 |
Establishment Period A
12-month establishment period for the soft landscape works shall be allowed
in the main contract for contractor to carry out routine horticultural
operations, including watering, pruning, weeding, pest control, replacement
of dead plants etc. to ensure healthy establishment of new planting during a
12 month establishment period. This period can also serves as a kind of warranty/guarantee
on the quality of the plants supplied and installed by the contractor.
Monthly monitoring during the first year of establishment period is
recommended. |
DSD and Contractor |
DSD and Contractor |
(i)
The EIA
recommendations on environmental protection and pollution control
mitigation measures;
(ii)
Works progress and programme;
(iii)
Individual works methodology proposals (which
shall include proposal on associated pollution control measures);
(iv)
The contract specifications on environmental
protection;
(v)
The relevant environmental protection and
pollution control laws; and
(vi)
Previous site inspection/audit results.
(i)
log complaint and date of receipt and inform
the ER immediately;
(ii)
investigate the complaint to determine its
validity, and to assess whether the source of the problem is due to works
activities;
(iii)
if a complaint is valid and due to works,
identify mitigation measures;
(iv)
if mitigation measures are required, advise
the Contractor accordingly;
(v)
review the Contractor¡¦s response on the
identified mitigation measures, and the updated situation;
(vi)
if the complaint is transferred from EPD, submit
interim report to EPD after endorsement by ER on status of the complaint
investigation and follow-up action within the time frame assigned by EPD;
(vii)
undertake additional monitoring and audit to
verify the situation if necessary, and review that any valid reason for
complaint does not recur,
(viii)
report the investigation results and the
subsequent actions to the source of complaint for responding to complainant (If
the source of complaint is FM), the results should be reported within the time
frame assigned by EPD); and
(ix)
record the complaint, Investigation, the
subsequent actions and the results in the monthly EM&A reports.
(i)
Executive Summary;
(ii)
Project background information;
(iii)
Drawings showing the locations of the
baseline monitoring stations;
(iv)
Monitoring methodology, equipment used and
calibration details, parameters monitored, locations, dates and times, etc.;
(v)
Monitoring results (in both hard and diskette
copies) including graphical plots;
(vi)
Interpretation of the significance of
monitoring results and explanation of influencing factors;
(vii)
Determination of the Action and Limit levels
for each monitoring parameter and statistical analysis of the baseline data;
(viii)
Revisions for inclusion in the EM&A
programme; and
(ix)
Comments and conclusions.
(i)
1-2 pages executive summary;
(ii)
Basic project information including a
synopsis of the project organisation programme and management structure, and
the work undertaken during the month;
(iii)
Brief summary of EM&A requirement:
(iv)
All monitoring parameters;
(v)
Environmental quality performance limits
(Action and Limit Levels);
(vi)
Event/Action Plan
(vii)
Environmental mitigation measures;
(viii)
Environmental requirements in contract
documents;
(ix)
Advice on the implementation status of
environmental protection and pollution control/mitigation measures;
(x)
Drawing showing the project area, any
environmental sensitive receivers and the monitoring location;
(xi)
Monitoring results together the following
information:
(xii)
Monitoring Methodology;
(xiii)
Equipment used and calibration details;
(xiv)
Parameter monitored;
(xv)
Monitoring location (and depth);and
(xvi)
Monitoring date, time, frequency and
duration.
(xvii)
Graphical plots of monitored trends over the
past four reporting periods and the following information:
¡P
Major
activities being carried out on site during the period;
¡P
Weather
condition during the period; and
¡P
Other
factor which might affect the monitoring results.
(xviii) Summary
of non-compliance (exceedance) of the environmental quality performance limits
(Action and Limit Levels);
(xix)
Review of the reasons for and the
implications of non-compliance including review of pollution sources and
working procedures;
(xx)
Description of recommendations and/or actions
taken, or outstanding, in the event of non-compliances or deficiencies,
including site inspections and audits;
(xxi)
A summary record of all complaints received
and follow-up actions;
(xxii)
Summary record of notification of summons,
successful prosecutions for breaches of environmental protection/pollution
control legislation, and actions taken to rectify such breaches; and
(xxiii) Future
key issues as reviewed from the work programme and work method statements
(i)
Title page;
¡P
1-2
pages executive summary
¡P
Breaches
of Action / Limit Levels;
¡P
Complaint
Log;
¡P
Reporting
Changes; and
¡P
Future
key issues.
(ii)
Content Page
(iii)
Environmental Status
¡P
Drawing
showing the project area, any environmental sensitive receivers and monitoring
locations;
¡P
Monitoring
results;
¡P
Summary
of non-compliance with the AL Levels; and
¡P
Summary
of complaints.
(iv)
Environmental Issues and Actions
¡P
Review
issues carried forward and/or follow-up procedures related to earlier
non-compliance (complaints and deficiencies);
¡P
Description
of the action taken in the event of non-compliance and deficiency reporting;
¡P
Recommendations
and advice on the implementation status of the environmental mitigation
measures and the corresponding effectiveness of the measurement; and
¡P
Summary
of the updated implementation schedules.
(v)
Future Key Issues; and
(vi)
Appendix.
¡P
Action
/ Limit Levels
¡P
Graphical
plot of monitored parameters over the past four reporting period and the
following information:
(a)
major activities being carried out on site during the period;
(b)
Weather condition during the period; and
(c)
Other factor which might affect the monitoring results.
¡P
Monitoring
schedule for the next reporting month;
¡P
Cumulative
complaints statistics; and
¡P
Details
of complaints, outstanding issues and deficiencies.
(i)
Executive Summary (1-2 pages);
(ii)
Drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations;
(iii)
basic project information including a
synopsis of the project organization contacts of key management, and a synopsis
of work undertaken during the course of the project or past twelve months;
(iv)
A brief summary of EM&A requirements
including:
¡P
environmental
mitigation measures, as recommended in the EIA Report;
¡P
environmental
impact hypotheses tested;
¡P
Action
/ Limit Levels;
¡P
all
monitoring parameters; and
¡P
Event
Action Plans.
(v)
A summary of the implementation status of
environmental protection and pollution control/mitigation measures as
recommended in the EIA report summarized in the updated implementation
schedule;
(vi)
Graphical plots and the statistical analysis
of the trends of monitored parameters over the course of the project, including
the post project monitoring (for the past twelve months for annual report) for
all monitoring stations against;
¡P
the
major activities being carried out on site during the period;
¡P
weather
conditions during the period; and
¡P
any
other factors which might affect the monitoring results
(vii)
A summary of non-compliance (exceedances) of
the environmental quality performance limits (Action / Limit Levels);
(viii)
A review of the reasons for and the
implications of non-compliance including review of pollution sources and
working procedures as appropriate;
(ix)
A description of the actions taken in the
event of non-compliance;
(x)
A summary record of all complaints received
(written or verbal) for each media liaison and consultation undertaken, action
and follow-up procedures taken;
(xi)
A summary record of notifications of summons
and successful prosecutions for breathes of the current environmental
protection/pollution control legislations including locations and nature of the
breaches, investigation, follow-up actions taken and results;
(xii)
A review of the validity of EIA Report
predictions and identification of shortcomings in EIA Report recommendations;
(xiii)
A review of the effectiveness and efficiency
of the mitigation measures; and
(xiv)
A review of success of the EM&A programme
to cost effectively identify deterioration and to initiate prompt effective
mitigation action when necessary.