Table of Contents

 

1.    Introduction

1.1    Project Background

2.    Project Description

2.1    Project Location and Brief Description

2.2    Purpose and Objectives of the Project

2.3    Project Implementation Programme

3.    Key Findings of the Environmental Impact Assessment

3.1    Air Quality

3.2    Noise

3.3    Water Quality

3.4    Waste Management

3.5    Land Contamination

3.6    Ecology

3.7    Fisheries

3.8    Cultural Heritage

3.9    Landscape and Visual

3.10  Environmental Monitoring and Audit

4.    Key environmental outcomes of the project

4.1    Environmental Benefits of the Project and the Environmental Protection Measures Recommended

4.2    Population and Environmentally Sensitive Area Protected

4.3    Environmentally Friendly Designs Recommended

4.4    Key Environmental Problems Avoided

5.    Conclusion

 

 

List of Figure

 

Figure 2.1        Proposed Works in Cheung Chau

 

 

List of Table

 

Table 2.1         Tentative Implementation Schedule for Different Works Packages

 

 

 

 


1.               Introduction

1.1             Project Background

1.1.1         In 2002, the Environmental Protection Department (EPD) carried out the Outlying Islands Sewerage Master Plan Stage 2 Review, and completed the Preliminary Project Feasibility Study for Outlying Islands Sewerage Stage 2 (hereinafter referred to as “PPFS”).

1.1.2         In February 2008, Drainage Services Department (DSD) commenced the Investigation Stage of “Upgrading of Cheung Chau and Tai O Sewage Collection, Treatment and Disposal Facilities” under Agreement No. CE 31/2007 (DS) by commissioning a consultant to carry out review on the conclusions and recommendations of the PPFS report, surveys, investigations, impact assessments, preliminary environmental review and preliminary design of the recommended works (hereinafter referred to as “Investigation Consultancy”).

1.1.3         In December 2010, DSD commissioned Atkins China Limited (ACL) to undertake Design and Construction of “Upgrading of Cheung Chau and Tai O Sewage Collection, Treatment and Disposal Facilities” under Agreement No. CE 15/2010 (DS).

1.1.4         An Environmental Impact Assessment (EIA) Study Brief No. ESB-212/2009 was issued to cover the Upgrading of Cheung Chau Sewage Collection, Treatment and Disposal Facilities (hereinafter refers to as “the Project”).  The EIA Study covers the following main works elements:

Ÿ  Expansion of the sewage treatment capacity and upgrading of the treatment level of the existing Cheung Chau Sewage Treatment Works (STW);

Ÿ  Expansion of the pumping capacity of the existing Pak She Sewage Pumping Station (SPS) and construction of a new SPS at Kwun Yam Wan;

Ÿ  Upgrading of some existing sewers and construction of some new sewers in various necessary locations in Cheung Chau; and

Ÿ  Construction of effluent reuse facilities within the Cheung Chau STW.

1.1.5         The purpose of this EIA study is to assess the environmental issues arising from the construction and operational phases of the Project, and to recommend appropriate mitigation measures for all identified adverse environmental impacts. 

2.               Project Description

2.1             Project Location and Brief Description

2.1.1         The Cheung Chau STW is located at the western side of the Cheung Kwai Estate.  It is currently a primary treatment works with design capacity of 4,000 m3/day.  Upon completion of the Project, it will be increased to a capacity of 9,800 m3/day with secondary treatment level.  A Membrane-bioreactor (MBR) type sewage treatment plant will be adopted.  Effluent reuse would be proposed for non-potable use within the Cheung Chau STW including toilet flushing and process cleansing.

2.1.2         Existing Pak She SPS was commissioned in 1984 and is located at the junction of Pak She Praya Road and Ping Chong Road, opposite to the Cheung Chau Fire Station.  The current pumping capacity of Pak She SPS is 29,376 m3/day (340 L/s).  Upon completion of the Project, it will be increased to a capacity of 42,336 m3/day (490 L/s).

2.1.3         The original Kwun Yam Wan SPS scheme proposed under the Investigation Consultancy is not recommended due to potential adverse environmental impacts arising from close proximity of the proposed SPS to the adjacent Kwun Yam Wan Beach.  The land resumption required and the operation and maintenance difficulties of the Kwun Yam Wan SPS also made it not preferable.  Therefore, the proposed Kwun Yam Wan SPS has been eliminated under the Project.  A Deep Sewer Option has been proposed to replace the SPS scheme by constructing a 700 m long underground gravity sewer to collect sewage from Kwun Yam Wan to the existing sewerage along Cheung Chau Praya Street.

2.1.4         Sewers works in Cheung Chau includes:

Ÿ  Upgrading of approximately 120 m long existing sewer of size 150 mm to 400 mm diameter;

Ÿ  Rehabilitation of approximately 160 m long existing sewer of size 525 mm diameter;

Ÿ  Construction of approximately 7,500 m long of new sewer with size 150 mm to 400 mm diameter in village areas by open cut method; and

Ÿ  Construction of approximately 300 m long of new deep sewer with size Twin 400 mm to Twin 500 mm diameter along Cheung Chau Sports Road and Tung Wan Road by trenchless method.

2.1.5         Under Part I, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO), the Project consists of the following Designated Projects (DP):

(a)  Upgrading of the existing Cheung Chau STW – under Item F.2 which is Sewage Treatment Works with an installed capacity of more than 5,000 m3/day and a boundary less than 200 m from the boundary of a residential area;

(b)  Upgrading of the existing Pak She SPS – under Item F.3 which is Sewage Pumping Station with an installed capacity of more than 2,000 m3/day and a boundary less than 150 m from the boundary of a residential area; and

(c)  Upgrading of the existing Cheung Chau STW – under Item F.4 which includes an activity for the reuse of treated sewage effluent from a treatment plant.

2.1.6         The works for this Project in Cheung Chau are shown in Layout Plan of Figure 2.1.

2.2             Purpose and Objectives of the Project

2.2.1         Currently there are areas in Cheung Chau not provided with public sewerage system.  Sewage and greywater generated from most of these village houses are disposed of at septic tanks that regular maintenance is required, and in some occasions they are even discharged directly into surface drainage system.  In addition, the existing Cheung Chau STW is a primary treatment facility which would be inadequate to cope with the population growth and future development.  In this regard, there is a need to improve this situation.

2.2.2         The Project is to improve the coastal water quality to the northwest of Cheung Chau by upgrading of existing sewers and provision of new sewers where practicable within the catchment, upgrading of the existing primary treatment plant to a secondary STW and expand the STW to cope with the population growth and future developments to improve the hygiene conditions at Cheung Chau.

2.3             Project Implementation Programme

2.3.1         The tentative implementation schedule for different works packages is presented in Table 2.1 below.

                Table 2.1 : Tentative Implementation Schedule for Different Works Packages

 

Package 1

Cheung Chau STW and Pak She SPS Upgrading

Package 2 

Cheung Chau Sewers Works

EIA Endorsed

Nov 2013

Scheme Gazette under WPC(S)R

-

May 2014

Scheme Authorization

-

Aug 2014

Tender Gazette

May 2014

Apr 2015

Contract Commencement

Sep 2014

Aug 2015

Contract Completion

Mar 2019

Mar 2019

 

3.               Key Findings of the Environmental Impact Assessment

3.1             Air Quality

3.1.1         Construction dust generating activities were identified and evaluated.  Mitigation measures including proper watering of on-site construction area and good practices on dust control measures are recommended.  Model simulation results show that the fugitive dust emissions are minimized and the dust levels are limited to acceptable levels by implementing the recommended mitigation measures.

3.1.2         The operation of Cheung Chau STW and Pak She SPS are the main potential odour emission sources.  The upgrading works will include the installation of better odour control for these facilities to avoid or minimize potential odour nuisance.  Upon completion of the upgrading works, all potential odour generating components of the facilities will be enclosed, and odourous gas will be ventilated to the deodorization units for further treatment before discharge.  During sludge transportation, it is recommended that the sludge should be carried by closed container to avoid or minimise odour nuisance.

3.1.3         With the above measures, odour impact should be insignificant.  An Environmental Monitoring and Audit (EM&A) programme will be implemented to ensure the continuing effectiveness of the odour control installations.

3.2             Noise

3.2.1         Concurrent construction noise impacts from the Project, including the Cheung Chau STW and Pak She SPS upgrading works and sewers works have been assessed.  A theoretical worst case in construction noise assessment has been undertaken with consideration of cumulative impacts arising from other projects proposed in the vicinity of the study area. 

3.2.2         Construction noise control measures such as adopting quiet plant, use of temporary barriers along site boundary of the Cheung Chau STW and Pak She SPS, employing movable barrier close to construction plants and good scheduling of works, etc., have been recommended to minimise construction noise.

3.2.3         With the above measures, noise impact is not anticipated during the Cheung Chau STW and Pak She SPS upgrading works.  However, for the sewers works, predicted noise level would exceed the noise criteria at some isolated occasions for certain NSRs that are in close proximity to the proposed sewers works.  This residual impact is expected to be localised, temporary, reversible, and the actual impact can be minimized through proper phasing of works and properly managed construction schedule.  A systematic EM&A programme will be carried out to ensure proper implementation of both construction phase mitigation measures and the construction schedule of the sewers works.

3.2.4         Noise impacts due to the upgraded Cheung Chau STW and Pak She SPS during the operational phase are not anticipated as proper acoustic treatment, including silencer and acoustic louvre would be provided.  Basic building design such as avoiding opening or louvres facing the nearest NSR would also be adopted.  Noise commissioning test for all major fixed noise sources is recommended and the requirements would be included in the contract documents.

3.3             Water Quality

3.3.1         Potential water quality impacts during construction phase will be mainly associated with land-based construction that may result from site runoff and sewage from the construction workforce.  Effluent will be controlled to comply with the WPCO standards by implementing the mitigation measures recommended on the basis of ProPECC Note (PN1/94) for Construction Site Drainage.  Adverse water quality impact is not expected.

3.3.2         Improvement in water quality of surrounding water body due to the operation of the Project is anticipated.  Assessment of water quality impact was made using the Delft3D model.  Generally, the proposed Cheung Chau STW upgrading would result in a reduction in concentration of TIN, UIA, SS, BOD5 and E. coli. under normal operation of the Cheung Chau STW.  This is mainly attributable to the improved treatment efficiency of upgraded facility and better quality of the upgraded Cheung Chau STW effluent, resulting in a reduction in pollutant loads into the marine water. 

3.3.3         Upon upgrading of the Pak She SPS, emergency overflow of raw sewage from the Pak She SPS will be diverted to Cheung Chau STW.  Therefore, the potential water quality impact on Cheung Chau receiving water body due to emergency overflow of Pak She SPS will be eliminated.  

3.3.4         The assessment of potential impacts associated with the emergency discharge from the Cheung Chau STW was conducted although emergency discharge is rare.  The prediction results show that the impact of emergency discharge would be limited only to local areas.  The potential impact would disappear rapidly and sharp concentration of water quality variables such as E. coli would return to their normal levels in less than 12 hours after the emergency discharge of 9,800 m3/day flow for 6 hours.  Impact to more distant WSRs would be extremely small and insignificant.

3.4             Waste Management

3.4.1         Waste types generated by the construction activities include C&D materials, general refuse from the workforce, and chemical wastes from the replacement of construction plants and equipments.  Wastes generated during the operation activities include screenings, silt and debris, grits and dewatered sludge and chemical waste.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are followed, adverse environmental impacts are not anticipated during the construction and operation phases.

3.5             Land Contamination

3.5.1         The land contamination assessment was undertaken by reviewing historical and current land uses and site reconnaissance.  Based on the findings of the site appraisal, there were potential contaminated sites at the shipyard and the machinery repairing and recycling workshops for ship along Ping Chong Road and Pak She Praya Road.  However, as there are no excavation works within the contaminated site, no potential contaminated soils would be disturbed.  The impacts of land contamination are not expected during the construction phase of the Project. 

3.5.2         The operation of the Project will not cause potential land contamination.  No operational contamination impacts are anticipated.

3.6             Ecology

3.6.1         No important habitat or optimal habitats of fauna species of conservation importance will be lost due to the Project as all works will be located within developed land.  The overall ecological impact is ranked as minimal and the residual impact is considered acceptable with respect to EIAO-TM.

3.6.2         Besides good site practices, no other major mitigation measure for ecology is required.  With the regular site inspection performed under the Environmental Monitoring and Audit Programme, no specific ecological monitoring programme is needed.

3.7             Fisheries

3.7.1         The fisheries baseline condition has been established within the assessment area and assessment of potential impacts has been conducted in accordance with the EIAO-TM requirements.  All construction works would be land-based and no works would be carried out in the marine or intertidal environment.  No significant adverse fisheries impacts are anticipated and no specific fisheries EM&A programme would be required.  Upon completion of this Project, the water quality and hence the habitat quality for fisheries resources is expected to be improved.

3.8             Cultural Heritage

3.8.1         No impacts on archaeology or built heritage will occur due to the Cheung Chau STW and Pak She SPS upgrading works.  Thus, no specific mitigation measures are required.

3.8.2         An Archaeological Watching Brief programme during construction phase was recommended for the sewers works within Tung Wan Site of Archaeological Interest.  In order to better protect the Cheung Chau Rock Carving which is a Declared Monument, a buffer zone is required to ensure that the Declared Monument and its environs are not infringed upon during the construction works.

3.8.3         There are graded and non-graded historical buildings identified near the proposed sewers works.  None of the buildings will be infringed upon during the construction works.  Protective measures include condition survey, vibration monitoring, provision of buffer zone, protective covering, and safe public access.

3.9             Landscape and Visual

3.9.1         Landscape and visual impact assessment has been carried out for the proposed upgrading of the Cheung Chau STW to be constructed within the boundary of the existing Cheung Chau STW.

3.9.2         Landscape Resources (LRs), Landscape Character Areas (LCAs) and Visually Sensitive Receivers (VSRs) have been identified within the study area to assess the landscape and visual impacts arising from the proposed expansion and upgrading of the Cheung Chau STW.  After mitigation, residual landscape and visual impacts are considered to be “Slight” and “Insubstantial”.  With reference to the criteria defined in EIAO-TM, landscape and visual impacts in the construction and operation phases arising from the proposed works is considered as acceptable.

3.9.3         All the upgrading works of Pak She SPS will be constructed within the existing superstructure of the SPS.  Landscape and visual impact during construction and operation stage is therefore considered to be negligible.

3.9.4         For the sewers works, the proposed new and upgrading of sewers will mainly be laid underground along the existing carriageway, footpaths and paved tracks.  The construction works will be carried out section by section in a local area with a short period of time, in order to reduce the disturbance to the surrounding areas and nearby residents.  The works area will be reinstated to its original conditions.  Residual landscape and visual impact is considered to be negligible.

3.10          Environmental Monitoring and Audit

3.10.1      An Environmental Monitoring and Audit (EM&A) Manual and an Environmental Mitigation Implementation Schedule (EMIS) have been prepared to monitor and audit the relevant air quality, noise, water quality, waste management, cultural heritage impacts, and landscape and visual impacts.  Event and action plan for the potential environmental impacts has been formulated and stated in the EM&A Manual. 

4.               Key environmental outcomes of the project

4.1             Environmental Benefits of the Project and the Environmental Protection Measures Recommended

4.1.1         The sewage treatment level of the Cheung Chau STW will be upgraded from primary to secondary and the capacity will be expanded to cope with the population growth and future developments.  Discharge of low quality effluent to the receiving water body will be reduced and hence will improve the coastal water quality of Cheung Chau.  Furthermore, hygiene problems within the catchment areas arising from the use of septic tanks will be largely relieved with provision of public sewers to currently unsewered villages, where practicable. 

4.2             Population and Environmentally Sensitive Area Protected

4.2.1         The marine waters near Cheung Chau are protected by the improved treatment standard and treatment capacity of the Cheung Chau STW and the elimination of overflow from Pak She SPS.  The residential areas and village houses which are currently unsewered are also protected by provision of new sewers under this Project.

4.3             Environmentally Friendly Designs Recommended

4.3.1         The Deep Sewer Option instead of Kwun Yam Wan SPS would eliminate any potential environmental impacts arising from the construction of a new SPS adjacent to Kwun Yam Wan Beach and the need of private land resumption. 

4.3.2         For Cheung Chau STW and Pak She SPS, the provision of standby parts and standby power sources improve the reliability of the sewage treatment and disposal system, while the provision of deodorizing units could reduce the possible odour impact to adjacent sensitive receivers.  In the design of Cheung Chau STW, non-potable reuse of treated effluent within the STW site will be proposed to reduce the consumption of potable water.  The facilities of the upgraded Cheung Chau STW are so arranged as to minimize disturbance to the existing trees within the STW and more trees will be planted within the upgraded STW to enhance greenings and improve the visual appearances.

4.4             Key Environmental Problems Avoided

4.4.1         Potential deterioration of effluent quality of the existing Cheung Chau STW due to ageing problem of the facilities will be avoided by the proposed upgrading of the sewage treatment level and increasing the existing capacity of the STW.  The hygiene problems arising from the use of septic tanks will also be largely relieved by the provision of public sewers to currently unsewered village, where practicable.  Furthermore, potential sewage overflow to Cheung Chau receiving water body will be eliminated by the proposed upgrading works for Pak She SPS.

5.               Conclusion

5.1.1         Upon completion of the proposed upgrading works, there will be improvement in water quality of the water body around Cheung Chau.  The EIA study concludes that with incorporation of the recommended mitigation measures and proper implementation of the EM&A programme, the Project will not impose adverse impacts on the neighbouring environment during construction and operational phases.