Content |
Chapter Title
1.2 Designated
Projects under the EIA Ordinance 1.3 Objectives
of the EIA Study 1.6 Structure
of the EIA Report |
Appendices
Appendix
1.1 Responses
to Public Comments on Project Profile
In the virtue of Category
O.8 in Part I Schedule 2 of the Environmental Impact Assessment Ordinance
(EIAO), a theme park or amusement park with a site area of more than 20 ha in size
is a Designated Project (DP). The Ocean Park is an exempted DP as it was
already in operation before the enactment of the EIAO. In the project entitled
“Repositioning and Long Term Operation Plan of Ocean Park” (the Repositioning
project), it involved construction/modification of existing facilities and
expansion of the Ocean Park, which constituted a material change to the
exempted DP, and therefore an environmental impact assessment (EIA) was carried
out for obtaining an environmental permit (EP) for construction and operation
of the Repositioning project under the EIAO. The EP was issued by Environmental
Protection Department (EPD) on 28 July 2006, which was subsequently varied in
October 2006, November 2010 and December 2013.
Ocean Park
Corporation (OPC) plans to establish and operate a proposed development at Tai
Shue Wan (TSW) and a Technical Feasibility Study (TFS) for the proposed
development including a conceptual design was completed in June 2012. A project
information outline was also prepared in March 2013. A portion of this Project
area is within the boundary of the Repositioning project while the remaining
part of the Project falls within the exempted DP area of Ocean Park. Therefore the current Project constitutes: (a) a material change to the
environmental impact of the Repositioning project; and (b) a material change to
the exempted DP area of Ocean Park. Both (a) and (b) require an EIA to be
conducted under EIAO in order for OPC to apply for an EP for the Project and to
surrender the TSW area covered in the EP of Repositioning project.
In August 2013,
OPC commissioned Mott MacDonald Hong Kong Limited (MMHK) to carry out the EIA
study for the proposed Project at Ocean Park (hereafter referred as “the
Project”) for the construction and operation.
The Project Profile for the
Project was submitted to EPD on 10 May 2013, and was exhibited for public
consultation between 11 May 2013 and 24 May 2013. Public comments on the
Project Profile were received and these comments have been addressed in relevant
sections of this EIA report as shown in Appendix 1.1. On 13 June 2013, EPD
issued an EIA Study Brief for the Project (ESB-261/2013).
The issued EIA Study Brief
sets out the purposes and objectives of the EIA study, the scope of
environmental issues to be addressed, the requirements that the EIA study needs
to fulfil, and the necessary procedural and reporting requirements. The
designated projects covered and the EIA study requirements are described below.
As stated in the Project
Profile and the EIA Study Brief, the Ocean Park is considered as a DP based on
item O.8 in Part I of Schedule 2 to
the EIAO and exempted under section 9(2) of the EIAO as it was already in operation
before the enactment this ordinance. Since the Project involves physical
addition and alternation resulting in adverse environmental impacts that
constitutes a material change to an exempted DP. A full EIA study to go through
the statutory EIA process is therefore required.
In accordance with Clause
2.1 of the EIA Study Brief, the objectives of the EIA study are:
§ to
describe the Project and associated works together with the requirements and
environmental benefits for carrying out the Project;
§ to
identify and describe the elements of the community and environment likely to
be affected by the Project, and/or likely to cause adverse impacts to the
Project, including both the natural and man-made environment and the associated
environmental constraints;
§ to
identify and quantify emission sources and determine the significance of
impacts on sensitive receivers and potentially affected uses;
§ to
identify and quantify any potential losses or damage to flora, fauna and
natural habitats;
§ to
propose the provision of infrastructure or mitigation measures to minimise
pollution, environmental disturbance and nuisance during construction and
operation of the Project;
§ to
investigate the feasibility, effectiveness and implications of the proposed
mitigation measures;
§ to
identify, predict and evaluate the residual (i.e. after practicable mitigation)
environmental impacts and the cumulative effects expected to arise during the
construction and operation phases of the Project in relation to the sensitive
receivers and potential affected uses;
§ to
identify, assess and specify methods, measures and standards, to be included in
the detailed design, construction and operation of the Project which are
necessary to mitigate these residual environmental impacts and cumulative
effects and reduce them to acceptable levels;
§ to
design and specify the environmental monitoring and audit requirements; and
§ to
identify any additional studies necessary to implement the mitigation measures
or monitoring and proposals recommended in the EIA report.
This EIA report addresses
all key potential environmental issues associated with the construction and
operational phases of the Project, which are as specified under Clause 3.2 of
the Study Brief:
§ Potential
air quality impacts on sensitive receivers due to the construction activities
and operation of the Project, if
there are any gaseous emissions from the water sterilisation system, as well as
induced traffic;
§ Potential
noise impacts on sensitive receivers due to the construction and operation of
the Project, as well as induced traffic;
§ Potential
water quality impacts and sewerage infrastructure impacts due to the
construction and operation of the Project, including the discharges of surface
runoff during construction stage; sewage generated from visitor attraction
facilities, discharges, if any, containing disinfectants/residue chemicals from
the Project pools, surface runoff from landscape areas potentially containing
pesticides of fertilizer residues, backwash water produced from water
filtration systems, thermal and chemical discharge, if any, from cooling
systems, possible sewage overflow and/or emergency bypass, if any, from sewage
treatment and disposal within the Project during the operation stage;
§ Potential
waste management and land contamination implications arising from the Project;
§ Potential
terrestrial and marine/aquatic ecological impacts due to the construction and
operation of the Project, including the loss of habitats, removal of vegetation
and disturbance to wildlife, in particular the site clearance for providing
land for new developments and construction of EVA road;
§ Potential
landscape and visual impacts caused by the removal of trees and vegetation, the
form and appearance of the Project, as well as night time visual impacts during
the night time operation and due to lighting of the Project; and
§ Potential
cumulative environmental impacts of the Project and associated works, through
interaction or in combination with other existing, committed and planned
projects in the vicinity of the Project, and that the impacts of these projects
may have a bearing on the environmental acceptability of the Project.
The general approach to
this EIA study will be conducted in accordance
with the requirements of the EIA Study Brief issued by EPD (ESB-261/2013) and
the guidelines on assessment methodologies provided in Annexes 12 to 19 of the
Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). The
approaches and methodologies adopted for assessment will follow the general
description in the relevant technical sections including description of the
environment, impact prediction, impact evaluation and impact mitigation.
This EIA report has been
structured as follows:
§ Chapter
1 – Introduction presents the purpose and scope of the EIA study.
§ Chapter
2 – Project Description presents a description of the Project, the need
and benefits of the Project, and
consideration of alternatives.
§ Chapter
3 – Air Quality Impact presents the approach, findings and recommendations from
the air quality impact assessment.
§ Chapter
4 – Hazard to Life presents the approach, findings and recommendations from the
hazard to life impact assessment.
§ Chapter
5 – Noise Impact presents the approach, findings and recommendations from the
noise impact assessment.
§ Chapter
6 – Water Quality Impact presents the approach, findings and recommendations
from the water quality impact assessment.
§ Chapter
7 – Sewerage and Sewage Treatment Implication presents the approach, findings
and recommendations from the sewerage and sewage assessment.
§ Chapter
8 – Waste Management Implication presents the approach, findings and
recommendations from the waste assessment.
§ Chapter
9 – Land Contamination presents the approach, findings and recommendations from
the land contamination assessment.
§ Chapter
10 – Ecological (Terrestrial and Marine/Aquatic) Impact presents the approach,
findings and recommendations from the terrestrial and marine/aquatic ecology
impact assessment.
§ Chapter
11 – Fisheries Impact presents the approach, findings and recommendations from
the fisheries impact assessment.
§ Chapter
12 – Landscape and Visual Impact presents the approach, findings and
recommendations from the landscape and visual impact assessment.
§ Chapter
13 – Environmental Monitoring
and Audit Requirements identify and justify the need for EM&A activities
during the construction and operation phases.
§ Chapter
14 – Conclusions summarises the findings and recommendations from the EIA.
§ Chapter 15 - Implementation
Schedule of Mitigation Measures summarises the schedule for implementation of
mitigation measures specified in chapters 3 to 12.