Table 15.1: Implementation Schedule
|
|
|
|
|
Implementation Stage1 |
|
|||
EIA Ref. |
EM&A Log Ref. |
Environmental Protection Measures |
Location / Duration of measures / Timing of completion of measures |
Implementation Agent |
Des |
Con |
Op |
Dec |
Relevant Legislation & Guidelines |
Cat.1 Key/specific proposed mitigation
measure |
|||||||||
Noise Impact (Construction) |
|||||||||
5.7 |
3.2 |
Selecting Quiet Plant
The actual SWL of
quiet plant is less than the value specified in GW-TM for the same piece of equipment.
It should be noted that the silenced PME taken from EPD’s Quality Powered
Mechanical Equipment (QPME) Inventory. |
Within Project area / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by OPC |
|
✓ |
|
|
EIAO and Noise Control Ordinance |
5.7 |
3.2 |
Use of Movable Barriers
Movable noise
barriers can be very effective in screening noise from particular items of
plant when constructing the Project. Noise barriers located along the active works
area close to the noise generating component of a PME could produce at least
10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided
that the direct line of sight between the PME and the NSRs is blocked. |
Within Project area / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by OPC |
|
✓ |
|
|
EIAO and Noise Control Ordinance |
Ecological Impact |
|||||||||
10.7 |
8.3 |
Inspection
of Active Ardeid Nest Prior to site clearance works at the
planting area abandoned for ardeid breeding, the
area around the boundary of the ardeids roosting
site as indicatively shown in Figures 10.3a and 10.3b should be inspected to
confirm no active ardeid nest is present. If any
active ardeid nest is observed, suitably sized
buffer area should be established to avoid human or machinery disturbance
until the nest is abandoned. |
Indicative boundary of the ardeids roosting site within Project construction site (location indicated in Figure 10.3b in EIA Report) / For once / Before site clearance |
Qualified ecologist appointed by OPC |
P |
|
|
|
EIAO-TM; HK Ordinance Cap. 170 |
10.7 |
8.3 |
Inspection
of Short-nosed Fruit Bat As precautionary measure, prior to any
proposed arboricultural works of the trees
(particularly the Chinese Fan-palms), daytime inspection should be carried
out to confirm no Short-nosed Fruit Bat is present. If any Short-nosed Fruit
Bat is observed roosting, suitably sized buffer area should be established
around the tree to minimise human or machinery disturbance until the bat has
left. |
Project construction site / For once / Before arboricultural works of the trees |
ET appointed by OPC |
P |
P |
|
|
EIAO-TM; HK Ordinance Cap. 170 |
10.7 |
8.3 |
In-situ
Preservation of Plant Species of Conservation Interest During construction phase, protective fence
for the identified flora species of conservation concern shall be erected and
maintained. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
10.7 |
8.3 |
Inspection
of Ardeid Nest during breeding season After commencement of construction phase, the
Site should be monitored monthly in breeding season (April to July) to check
for any potential breeding and nesting activities. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Qualified ecologist appointed by OPC |
|
P |
|
|
EIAO-TM |
10.7 |
8.2 |
Timing
of site clearance and tree felling works Site clearance and tree felling works at
the existing ardeid night roost location as shown
in Figures 10.3a and 10.3b should be avoided during the peak wintering season
of ardeids, i.e. between November and March. |
Indicative boundary of the ardeids roosting site within Project construction site (location indicated in Figure 10.3b in EIA Report) / Throughout construction stage / Until completion of site clearance and tree felling works within the boundary |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
10.7 |
8.3 |
Compensation
for Ardeid Roosting Site An enhancement area with following features
should be provided as an alternative roosting site for ardeids.
§ The location is at southern part of the Project area (location indicated in Figure 10.4 in EIA Report) § The enhancement area shall include a Flamingo
Pond § Native tree species Macaranga tanarius and Celtis sinensis and tree species which was
used by ardeids for roosting Mallotus paniculatus, Ficus hispida and Cratoxylum cochinchinense shall be considered in the plan. § Heavy standard sized trees shall be considered
for planting to allow early establishment of the trees around the Flamingo
Pond. |
Southern part of Project construction site (location indicated in Figure 10.4 in EIA Report) / Before and throughout construction stage / Until completion of Flamingo Pond construction and tree planting activities at that area |
Qualified ecologist and Contractor appointed by OPC |
P |
P |
P |
|
EIAO-TM |
10.7 |
8.3 |
Compensation
for Woodland Habitat § Provision
of a Woodland Area of about 1.62 ha, which includes 0.84 ha woodland
compensation on-site and 0.78 ha on-site woodland reinstatement, to mitigate
for permanent loss of woodland habitat. § In
the woodland compensation area, whips should be planted with predominately
native tree species similar to the affected woodland, such as Celtis sinensis, Cratoxylum cochinchinense,
Polyspora axillaris
and Sterculia lanceolata. |
Location of Woodland Compensation Area indicated in Figure 10.5 of EIA report / Before and throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
P |
|
EIAO-TM |
Landscape and Visual Impact (Construction) |
|||||||||
Table 12.13 (CP07) |
Table 9.1 (CP07) |
Temporary Tree Nurseries Temporary tree nurseries may be set up
within the Project area at an early stage to allow small trees to grow during
the construction period. By the time
these trees are needed for landscape planting at the end of the construction
phase, they will have grown larger, require minimal pruning and suffer much
less damage during transplanting, as the moving distance from an on-site
rather than off-site nursery will be much smaller. The temporary tree nurseries can also temporarily
hold the existing trees to be transplanted if direct transplantation from
their original locations to the final recipient location is
impracticable. The locations of the
temporary tree nurseries should be carefully selected so that the trees can
also act as screen planting to block the views of the Project area from the
VSRs during the construction phase, if practicable. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP08) |
Table 9.1 (CP08) |
Advance Planting Advance planting
should be undertaken at the earliest possible stage of the construction phase
of the project. Plant species,
preferably native ones, should be carefully selected to blend in with the
existing preserved vegetation.
Landscape planting in movable planters should also be considered as a
temporary greening measure for the Project area. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Landscape and Visual Impact (Operation) |
|||||||||
Table 12.14 (OP04) |
Table 9.2 (OP04) |
Green
Roofs and Vertical Greening
Green Roofs and Vertical Greening should be
provided where feasible and appropriate to screen and soften the hard edges
of building structures. |
Project building rooftops / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Table 12.14 (OP05) |
Table 9.2 (OP05) |
Reprovision of Flamingo Pond A pond is recommended to replace the
demolished Flamingo Pond as compensation for the loss of semi-natural ponds, where
wildlife, such as birds, can utilise. |
Project area / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Table 12.14 (OP07) |
Table 9.2 (OP07) |
Woodland
Compensation 1.53ha of affected woodland is recommended
to be reinstated / compensated by 1.62ha of whip tree planting adjacent to
the existing unaffected woodland and tall shrubland. Native species should be proposed as far as
practicable to re-create a native landscape, restore the ecological habitats
and blend in with the existing native vegetation. |
Project area / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Cat. 2 Submission required post EIA stage |
|||||||||
7.7 |
5.2 |
Detailed
Sewerage Design Report In
order to prevent septicity problems during operation phase, a detailed
sewerage design report should be submitted to DSD for approval prior to
installation of the rising mains. |
Rising mains site
/ During design stage |
Design Engineer |
P |
|
|
|
Sewerage Manual Part 1 |
Ecological Impact (Construction) |
|||||||||
10.7 |
8.3 |
Vegetation
Survey for Plant Species of Conservation
Interest For precautionary purposes and to further
ensure no flora species of conservation interest to be affected, a detailed
vegetation survey need to conduct to the exact locations, number and condition
of individuals of Platycodon grandiflorus.
|
Project
construction site / For once / Before site clearance |
Qualified botanist/ecologist of the ET appointed by OPC |
P |
|
|
|
EIAO-TM; Hong Kong Ordinance Cap. 96 |
10.7 |
8.3 |
Woodland
Compensation Plan A Woodland Compensation Plan shall be
prepared and submitted to AFCD for approval no later than one month prior to
commencement of site
clearance. The plan shall include but not limited to
the following: § Timing of planting works § Planting location § Species, size and number of trees § Monitoring
methodology § Action
Plan |
Location of Woodland Compensation Area indicated in Figure 10.5 in EIA Report / Before construction stage / No later than one month prior to commencement of site clearance |
Qualified botanist/ecologist of the ET appointed by OPC |
P |
|
|
|
EIAO-TM |
Landscape and Visual Impact (Construction) |
|||||||||
Table 12.13 (CP05) |
Table 9.1 (CP05) |
Transplantation of Existing Trees Trees which are in
direct conflict with the development proposals and suitable for
transplantation should be transplanted as far as practicable. A tree transplantation proposal should be
submitted together with the tree removal application. Trees proposed to be transplanted should
preferably be transplanted from their original locations directly to their
final recipient locations in one go.
If this is infeasible, the trees should be held in a temporary tree
nursery, preferably within the Project area, where the trees will be properly
maintained. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM; LAO PN No. 07/2007 |
Landscape and Visual Impact (Operation) |
|||||||||
Table 12.14 (OP02) |
Table 9.2 (OP02) |
Compensatory
Tree Planting Existing trees to be felled should be
compensated as far as practicable.
Native species should be proposed as far as practicable to re-create a
native landscape, restore the ecological habitats and blend in with the
existing native vegetation. A
compensatory tree planting proposal should be submitted together with the
tree removal application for approval by relevant authorities in accordance with LAO Practice Note No.
7/2007. It is recommended that approximately 608 heavy standard trees and
approximately 18,202 whip trees could be planted on-site. The availability of
off-site compensatory tree planting area is still subject to further
investigation and agreement with relevant authorities. |
Project area / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM; LAO PN No. 07/2007 |
Cat. 3 Good site practice/housekeeping
measures under EM&A mechanism |
|||||||||
Air Quality Impact (Construction) |
|||||||||
3.9.1 |
2.2 |
Dust Control Measures
To achieve compliance with the FSP, RSP and TSP
criteria during the construction phase, good practices for dust control
should be implemented to reduce dust impacts. The dust control measures are
detailed as follows: § Use of regular water
spraying (once every 2.5 hours or 4 times per day) to reduce dust emissions
from heavy construction activities (including ground excavation, earth moving,
etc.) at all active works area exposed site surfaces and unpaved roads,
particularly during dry weather. § Covering 80% of stockpiling area by
impervious sheets and spraying all dusty material with water immediately prior to any loading transfer
operations to keep the dusty materials wet during material handling at the
stockpile areas Relevant dust control
practices as stipulated in the Air Pollution Control (Construction Dust)
Regulation should be adopted: Good Site Management §
Good site management is important to help reduce potential air quality
impact down to an acceptable level. As a general guide, the Contractor should
maintain high standards of housekeeping to prevent emissions of fugitive
dust. Loading, unloading, handling and storage of raw materials, wastes or
by-products should be carried out in a manner so as to minimise the release
of visible dust emission. Any piles of materials accumulated on or around the
work areas should be cleaned up regularly. Cleaning, repair and maintenance
of all plant facilities within the work areas should be carried out in a
manner minimising generation of fugitive dust emissions. The material should
be handled properly to prevent fugitive dust emission before cleaning. Disturbed Parts of the
Roads §
Main temporary access points should be paved with concrete, bituminous
hardcore materials or metal plates and be kept
clear of dusty materials; or §
Unpaved parts of the road should be sprayed with water or a dust
suppression chemical so as to keep the entire road surface wet. Exposed Earth §
Exposed earth should be properly treated by compaction, hydroseeding, vegetation planting or seating with latex,
vinyl, bitumen within six months after the last construction activity on the
site or part of the site where the exposed earth lies. Loading, Unloading or
Transfer of Dusty Materials §
All dusty materials should be sprayed with water immediately prior to
any loading or transfer operation so as to keep the dusty material wet. Debris Handling §
Any debris should be covered entirely by impervious sheeting or stored
in a debris collection area sheltered on the top and the three sides. §
Before debris is dumped into a chute, water should be sprayed onto the
debris so that it remains wet when it is dumped. Transport of Dusty
Materials §
Vehicles used for transporting dusty materials/spoils should be
covered with tarpaulin or similar material. The cover should extend over the
edges of the sides and tailboards. Wheel washing §
Vehicle wheel washing facilities should be provided at each
construction site exit. Immediately before leaving the construction site,
every vehicle should be washed to remove any dusty materials from its body
and wheels. Use of vehicles §
The speed of the trucks within the site should be controlled to about
10 km/hour in order to reduce adverse dust impacts and secure the safe
movement around the site. §
Immediately before leaving the construction site, every vehicle should
be washed to remove any dusty materials from its body and wheels. §
Where a vehicle leaving the construction site is carrying a load of
dusty materials, the load should be covered entirely by clean impervious
sheeting to ensure that the dusty materials do not leak from the vehicle. Site hoarding § Where a site boundary
adjoins a road, street, service lane or other area accessible to the public,
hoarding of not less than 2.4 m high from ground level should be provided
along the entire length of that portion of the site boundary except for a
site entrance or exit |
Project construction site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by OPC |
|
✓ |
|
|
EIA Recommendation and Air Pollution Control (Construction Dust) Regulation |
Noise Impact (Construction) |
|||||||||
5.7 |
3.2 |
Good
Site Practice
Good site practice and noise management can
significantly reduce the impact of construction site activities on nearby
NSRs. § only well-maintained plant
to be operated on-site and plant should be serviced regularly during the
construction works; § machines and plant that
may be in intermittent use to be shut down between work periods or should be
throttled down to a minimum; § plant known to emit noise
strongly in one direction, should, where possible, be orientated to direct
noise away from the NSRs; § mobile plant should be
sited as far away from NSRs as possible; and § material stockpiles and other
structures to be effectively utilised, where practicable, to screen noise
from on-site construction activities. |
Project construction site / Duration of the construction phase / Prior to commencement of operation |
Contractor appointed by OPC |
|
✓ |
|
|
EIAO and Noise Control Ordinance |
Noise Impact (Operation) |
|||||||||
5.7 |
3.3.2 |
Fixed
Plant Noise
With the adoption of the
proposed maximum allowable SWLs, all representative NSRs is expected to
comply with the relevant noise criteria for the daytime and evening time periods.
No adverse fixed plant noise impact is anticipated.
It is also recommended
that the following noise reduction measures should be considered as far as
practicable during design stage: § choose quiet plant such as
those which have been effectively silenced; § include noise levels
specification when ordering new plant (including chiller and E&M
equipment); § locate fixed plant / louvre away from any NSRs as far as practicable; § locate fixed plant in
walled plant rooms or in specially designed enclosures; § locate noisy machine in a
basement or a completely separate building; § install direct noise
mitigation measures including silencers, acoustic louvres
and acoustic enclosure where necessary; and § develop and implement a regularly
scheduled plant maintenance programme so that equipment is properly operated
and serviced in order to maintain a controlled level of noise. Prior to the operation of the Project, noise commissioning tests for
all major fixed noise sources should be conducted. |
Within Project area / Prior to operation phase / Duration of the operation phase / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
✓ |
✓ |
✓ |
|
EIAO and Noise Control Ordinance |
5.7 |
3.3.2 |
Open
Air Entertainment Noise
With the adoption of the
proposed maximum allowable SWLs, all representative NSRs is expected to
comply with the relevant noise criteria for the daytime and evening periods,
the following measures should be considered as far as practicable during
stage:
§ use small clusters of
small power loudspeakers rather than a few large power loudspeakers; and § loudspeakers should
be pointed away from nearby NSRs. |
Within Project area / Duration of the operation phase / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
✓ |
✓ |
|
|
EIAO and Noise Control Ordinance |
Water Quality Impact (Construction) |
|||||||||
6.7 |
4.2 |
Construction Site Runoff The site practices outlined in ProPECC Note PN 1/94 should be followed as far as practicable in order to minimise surface runoff and erosion. The following measures are recommended to protect water quality of the inland areas: § At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works and erosion and sedimentation control facilities implemented. Channels, earth bunds or sand bag barriers should be provided on site to direct storm water to silt removal facilities. The design of the temporary on-site drainage system should be undertaken by the Contractors prior to the commencement of construction; § Sand/ silt removal facilities such as sand/silt traps and sediment basins should be provided to remove sand/silt particles from runoff to meet the requirements of the TM standards under the WPCO. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC Note PN 1/94. Sizes may vary depending upon the flow rate. The detailed design of the sand/silt traps should be undertaken by the Contractors prior to the commencement of construction; § All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit should be regularly removed, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times; § Measures should be taken to minimise the ingress of site drainage into excavations. If excavation of trenches in wet periods is necessary, they should be dug and backfilled in short sections wherever practicable. Water pumped out from site formation excavations should be discharged into storm drains via silt removal facilities; § All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and sited wheel washing facility should be provided at construction site exit where practicable. Wash-water should have sand and silt settled out and removed regularly to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains; § Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system; § Manholes (including newly constructed ones) should be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and stormwater runoff being directed into foul sewers; § Precautions should be taken at any time of the year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC Note PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events, especially for areas located near steep slopes; and, § Bentonite slurries used on site should be reconditioned and reused wherever practicable. Temporary enclosed storage locations should be provided on site for any unused bentonite that needs to be transported away after all the related construction activities are completed. The requirements in ProPECC Note PN 1/94 should be adhered to in the handling and disposal of bentonite slurries. The Contractor would be required to obtain a license from EPD under the WPCO for discharge to the public drainage system or the marine environment. Construction site discharge should be collected by the temporary drainage system installed by the Contractor and treated or desilted on-site to fulfil the WPCO discharge license requirements before discharge. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM; ProPECC Note PN 1/94; WPCO; TM-DSS |
6.7 |
4.2 |
General Construction Activities Best
Management Practices (BMPs) should be implemented at the construction site,
including proper handling, sorting and storage of construction solid waste,
debris and refuse generated on-site prior to disposal. Stockpiles of cement
and other construction materials should be kept covered when not being
used. The Contractor should also
follow the guidelines set in the “Pesticides Used for Outdoor Mosquito
Control”, published by AFCD in 2010, for mosquito control on site. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM; ProPECC Note PN 1/94 |
6.7 |
4.2 |
Expansion of Existing Storm U-Channel Guidelines
and measures summarised in ProPECC PN 1/94 for trenching
activities should be implemented. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94 |
6.7 |
4.2 |
Interception of Natural Streams Guidelines
and measures summarised in ProPECC PN 1/94 for
excavation and stockpiling activities should be implemented. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94 |
6.7 |
4.2 |
Site Formation Works The construction programme should be properly planned to minimise excavation works during the wet season (April to September), temporarily exposed slope/soil surfaces should be covered by a tarpaulin or other means, as far as practicable. Interception channels should be provided (e.g. along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces. Arrangements should be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm. Measures will be taken to minimise water ingress into the excavation. Diverting any water from the excavated areas to on-site wastewater treatment facilities for treatment prior to discharge should also be performed. Other measures that need to be implemented before, during and after rainstorms are summarised in ProPECC PN 1/94. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94 |
6.7 |
4.2 |
Construction of Sewage Sump Pit and
Rising Mains Measures for excavation works summarised for site formation works should also be implemented during construction of the sewage sump pit. During
the laying of rising mains, guidelines and measures summarised in ProPECC PN 1/94 for trenching activities should be
performed. Concrete water generated
from the construction of the concrete support should be collected and treated
with the wastewater treatment facilities prior to discharge. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94 |
6.7 |
4.2 |
Accidental Spillage The Contractor should register as a chemical waste producer if chemical wastes are produced from construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes. This will prevent contamination of top soil and water pollution due to construction site runoff. Maintenance of vehicles and equipment, involving activities with potential for leakage and spillage, should only be undertaken within areas appropriately equipped to control these discharges. Oils and fuels should only be stored in designated areas which have pollution prevention facilities. To prevent spillage of fuels and solvents to any nearby storm water drain, all fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank. The bund should be drained of rainwater after a rain event. Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows: § Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport. § Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents. § Storage
area should be selected at a safe location on site and adequate space should
be allocated to the storage area. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94; Waste Disposal Ordinance (Cap 354); Waste Disposal (Chemical Waste) (General) Regulation |
6.7 |
4.2 |
Sewage Effluent from the Construction
Workforce The
Contractor should provide temporary sanitary facilities, such as portable
chemical toilets within the construction site to handle sewage from the
workforce. The Contractor has the responsibility to ensure that chemical
toilets are used and properly maintained, and that licensed Contractors are
employed to collect and dispose of the waste off-site at approved locations. |
Project construction site / Duration of the construction phase |
Contractor appointed by OPC |
|
P |
|
|
ProPECC Note PN 1/94 |
Water Quality Impact (Operation) |
|||||||||
6.7 |
4.2 |
Runoff from Road Surfaces Road
drainage system design has already included silt traps in the gully inlets to
remove silt and grit before the runoff enters the public storm water drainage
system. Silt traps should be regularly checked and maintained to ensure
efficient operation. |
Within Project area / During operation phase |
OPC/Operator appointed by OPC |
|
|
P |
|
EIAO-TM; WPCO |
6.7 |
4.2 |
Runoff from On-site Planting Area Watering
of plants on site should always be performed before application of
pesticides, herbicides and fertilizers.
Regular training should also be provided to frontline staff on the
appropriate treatment and disposal of pesticides, herbicides and fertilizers. |
Within Project area / During operation phase |
OPC/Operator appointed by OPC |
|
|
P |
|
EIAO-TM; WPCO; TM-DSS |
Waste Management Implications (Construction) |
|||||||||
8.5.1.1 |
6.2 |
Good
Site Practice
Recommendations for good site practices
during the construction activities include: §
Nomination of an
approved person, such as a site manager, to be responsible for good site
practices, arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site §
Training of site
personnel in proper waste management and chemical handling procedures §
Provision of
sufficient waste disposal points and regular collection of waste §
Appropriate
measures to minimise windblown litter and dust/ odour during transportation
of waste by either covering trucks or by transporting wastes in enclosed
containers §
Stockpiles of
C&D materials should be kept covered by impervious sheets to avoid
wind-blown dust §
All dusty
materials including C&D materials should be sprayed with water immediately
prior to any loading transfer operation so as to keep the dusty material wet
during material handling at the stockpile areas §
Provision of
wheel washing facilities before the trucks leaving the works area so as to minimise
dust introduction to public roads §
Well planned
delivery programme for offsite disposal such that adverse environmental
impact from transporting the inert or non-inert C&D materials is not anticipated |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal Ordinance; Waste Disposal (Chemical Wastes) (General) Regulation; and ETWB Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site |
8.5.1.2 |
6.2 |
Waste
Reduction Measures
Good management and control can prevent the generation of
a significant amount of waste. Waste reduction is best achieved at the planning
and design stage, as well as by ensuring the implementation of good site
practices. Recommendations to achieve waste reduction include:
§
Sort inert
C&D materials to recover any recyclable portions such as metals §
Segregation and
storage of different types of waste in different containers or skips to
enhance reuse or recycling of materials and their proper disposal §
Encourage
collection of recyclable waste such as waste paper and aluminium cans by
providing separate labelled bins to enable such waste to be segregated from
other general refuse generated by the work force §
Proper site
practices to minimise the potential for damage or contamination of inert
C&D materials §
Plan the use of
construction materials carefully to minimise amount of waste generated and
avoid unnecessary generation of waste |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal Ordinance |
8.5.1.3 |
6.2 |
Inert
and Non-inert C&D materials
In
order to minimise impacts resulting from collection and transportation of
inert C&D materials for off-site disposal, the inert C&D materials
should be reused on-site as fill
material as far as practicable. In addition, inert C&D materials
generated from excavation works could
be reused as fill materials in local projects that
require public fill for reclamation.
The
surplus inert C&D materials will be disposed of at the Government’s PFRFs
for beneficial use by other projects in Hong Kong.
The
C&D materials generated from general site
clearance should be sorted on site to segregate any inert materials for reuse
or disposal of at PFRFs whereas the non-inert materials will be disposed of
at the
designated landfill site. In
order to monitor the disposal of inert and non-inert C&D materials at
respectively PFRFs and the designated landfill site, and to control
fly-tipping, it is recommended that the Contractor should follow the DEVB
Technical Circular (Works) No.6/2010 for Trip Ticket System for Disposal of
Construction & Demolition Materials issued by Development Bureau. In
addition, it is also recommended that the Contractor should prepare and
implement a Waste Management Plan detailing their various waste arising and
waste management practices in accordance with the relevant requirements of
the ETWB Technical Circular (Works) No. 19/2005 Environmental Management on
Construction Site.
|
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal Ordinance ; DEVB Technical
Circular (Works) No.6/2010 for Trip Ticket System for Disposal of
Construction & Demolition Materials; and ETWB Technical Circular (Works) No.
19/2005 Environmental Management on Construction Site |
8.5.1.4 |
6.2 |
Chemical
Waste
If
chemical wastes are produced at the construction site, the Contractor will be
required to register with the EPD as a chemical waste producer and to follow
the guidelines stated in the “Code of Practice on the Packaging Labelling and
Storage of Chemical Wastes”. Good quality containers compatible with the
chemical wastes should be used, and incompatible chemicals should be stored
separately. Appropriate labels should be securely attached on each chemical
waste container indicating the corresponding chemical characteristics of the
chemical waste, such as explosive, flammable, oxidising, irritant, toxic,
harmful, corrosive, etc. The Contractor should use a licensed collector to
transport and dispose of the chemical wastes at the approved Chemical Waste
Treatment Centre or other licensed recycling facilities, in accordance with
the Waste Disposal (Chemical Waste) (General) Regulation.
Potential environmental impacts arising from the handling
activities (including storage, collection, transportation and disposal of
chemical waste) are expected to be minimal with the implementation of
appropriate mitigation measures as recommended.
|
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Code of Practice
on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General)
Regulation |
8.5.1.5 |
6.2 |
General
Refuse
General
refuse should be stored in enclosed bins or compaction units separated from
inert C&D materials. A reputable waste collector should be employed by
the Contractor to remove general refuse from the site, separately from inert
C&D materials. Preferably an enclosed and covered area should be provided
to reduce the occurrence of 'wind blown' light
material.
|
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal
Ordinance and Public Health and Municipal Services Ordinance - Public
Cleansing and Prevention of Nuisances Regulation |
8.5.1.6 |
6.2 |
Floating
Refuse
Provide general refuse collection points on site can minimise the
refuse contaminate the marine environment. The construction contractors will
be required to regularly check and clean any refuse trapped or accumulated
along the artificial seawall. Such
refuse will then be stored and disposed of together with the general refuse.
|
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal Ordinance |
Waste Management Implications (Operation) |
|||||||||
8.5.2.1 |
6.2 |
General
Refuse
General refuse should be collected on daily basis and delivered to
the refuse collection point accordingly. A reputable waste collector should be
employed to remove general refuse regularly to avoid odour nuisance or
pest/vermin problem. Sufficient recycling containers are recommended to be
provided at suitable locations of the Project to encourage recycling of such
waste as aluminium cans, plastics and waste paper.
|
Project area / On a regular basis / Throughout operation stage |
Contractor appointed by OPC |
|
|
P |
|
Waste Disposal Ordinance |
8.5.2.2 |
6.2 |
Chemical
Waste
If
chemical wastes are expected to be produced during the operation phase, the
Project Proponent should register with the EPD as a chemical waste producer
and follow the guidelines stated in the “Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes”. Good quality containers compatible
with the chemical wastes should be used, and incompatible chemicals should be
stored separately. Appropriate labels
should be securely attached on each chemical waste container indicating the
corresponding chemical characteristics of the chemical waste, such as
explosive, flammable, oxidising, irritant, toxic, harmful, corrosive, etc.
Licensed collector should be deployed to transport and dispose of the
chemical wastes at the approved Chemical Waste Treatment Centre or other
licensed recycling facilities, in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation.
|
Project area / On a regular basis / Throughout operation stage |
Contractor appointed by OPC |
|
|
P |
|
Code of Practice on the Packaging Labelling and Storage of Chemical Wastes; Waste Disposal (Chemical Waste) (General) Regulation |
8.5.2.3 |
6.2 |
Floating
Refuse
Regular
inspection should be carried out along the artificial seawall of the Project boundary
for any entrapment or accumulation of floating refuse. Where an appreciable
amount of floating refuse is found on the artificial seawall during the
inspection, the locations of such refuse will be recorded and arrangements
with the project proponent will immediately be made to collect and clear the
refuse from the seawall.
|
Project area / On a regular basis / Throughout operation stage |
Contractor appointed by OPC |
|
|
P |
|
Waste Disposal Ordinance |
Land Contamination (Construction) |
|||||||||
9.6 |
7.2 |
In any case where contaminated soil is identified after the commencement of works, a Contamination Assessment Plan (CAP) is required to be prepared for EPD's endorsement prior to the site investigation. The Contamination Assessment Report (CAR) and/ or Remediation Action Plan (RAP) should be prepared for EPD's approval after the site investigation. If land contamination is confirmed, remediation works should be carried out according to the approved RAP. A Remediation Report (RR) should also be prepared for EPD's endorsement to demonstrate that the clean-up of the contaminated land is completed. No construction work or development of site should be carried out before the approval of the RR. |
Project construction site / Before construction stage |
Contractor appointed by OPC |
P |
|
|
|
Guidance Note for
Contaminated Land Assessment and Remediation Guidance Manual for Use
of Risk-based Remediation Goals for Contaminated Land Management Practice Guide for Investigation and Remediation of Contaminated Land |
9.6 |
7.2 |
If contaminated soil is identified, the following mitigation measures are for the excavation and transportation of contaminated materials (if any): § To minimise the incidents of construction workers coming in
contact with any contaminated materials, bulk earth-moving
excavation equipment should be employed; § Contact with
contaminated materials can be minimised by wearing appropriate clothing and
personal protective equipment such as gloves and masks (especially when
working directly with contaminated material), provision of washing facilities
and prohibition of smoking and eating on site; § Stockpiling of
contaminated excavated materials on site should be avoided as far as
possible; § The use of any
contaminated soil for landscaping purpose should be avoided unless
pre-treatment was carried out; § Vehicles
containing any excavated materials should be suitably covered to reduce dust
emissions and/or release of contaminated wastewater; § Truck bodies and
tailgates should be sealed to prevent any discharge; § Only licensed
waste haulers should be used to collect and transport contaminated material
to treatment/disposal site and should be equipped
with tracking system to avoid fly tipping; § Speed control for
trucks carrying contaminated materials should be exercised. § Observe all
relevant regulations in relation to waste handling, such as Waste Disposal
Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation
(Cap 354) and obtain all necessary permits where required; and §
Maintain records of waste generation and disposal
quantities and disposal arrangements. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
Waste Disposal
Ordinance (Cap 354) Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) |
Landscape and Visual Impact (Construction) |
|||||||||
Table 12.13 (CP01) |
Table 9.1 (CP01) |
Minimisation of Construction Period The construction programme should be
carefully designed to minimise the length of the construction period. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP02) |
Table 9.1 (CP02) |
Minimisation of Works Areas The footprint of the proposed hard
structures as well as the extent of temporary works areas should be minimised
as far as practicable. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP03) |
Table 9.1 (CP03) |
Construction Site Controls Construction site
controls should be enforced, where possible, to ensure that the landscape and
visual impacts arising from the construction phase activities, such as the
storage of materials, the location and appearance of site accommodation, etc.
are minimised. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP04) |
Table 9.1 (CP04) |
Preservation of Existing Vegetation The development
proposal should avoid disturbance to existing vegetation as far as
practicable. A formal tree removal
application should be submitted for approval by relevant authorities in
accordance with LAO PN No. 07/2007 “Tree Preservation and Tree Removal
Application for Building Development in Private Projects” during the detailed
design phase of the Project. Where possible, all trees which are not in
direct conflict with the development proposals should be retained in situ. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM; LAO PN No. 07/2007 |
Table 12.13 (CP06) |
Table 9.1 (CP06) |
No Intrusion Zones Where practicable,
“no intrusion zones” should be designated within the Project area for
protection of existing vegetation.
Durable boundary fences should be erected to clearly demarcate these
“no intrusion zones”. No construction
activities, storage of materials and vehicular access will be allowed within
the “no intrusion zones” to prevent potential damage to canopies and root
zones of vegetation. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP09) |
Table 9.1 (CP09) |
Construction Site Hoardings Two types of
hoardings should be considered. One is
used for areas in close contact with visitors and for areas where visual intrusion
is a key concern. It should be
graphical and thematic, and visually ‘impermeable’ to block the views of
construction activities from the VSRs.
The other is used for areas to be viewed at a distance. It should be
subtle and camouflaged so that it blends in with the surrounding landscape. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
P |
P |
|
|
EIAO-TM |
Table 12.13 (CP10) |
Table 9.1 (CP10) |
Dust and Erosion Control for Exposed Soil Exposed soil shall
be covered or “camouflaged” and watered frequently. Areas that are expected to be left with
bare soil for a long period of time should be hydroseeded
and / or covered with suitable protective fabrics. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
Table 12.13 (CP11) |
Table 9.1 (CP11) |
Appearance of Construction Plant / Machinery To minimise the
visual intrusion of construction activities to visitors and other VSRs, a
suitable colour scheme of construction machines and plants should be adopted
where possible. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
Table 12.13 (CP12) |
Table 9.1 (CP12) |
Construction Lighting Control All security floodlights
for construction sites should be equipped with adjustable shield, frosted
diffusers and reflective covers, and be carefully controlled to minimise
light pollution and night-time glare to the VSRs. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
Table 12.13 (CP13) |
Table 9.1 (CP13) |
Appearance of Construction Workers To protect Ocean Park’s
image, construction workers should be required to enter the park areas with
their helmets and safety vests properly stored or carried in non-transparent
bags. They should also dress properly
and cleanly. |
Project construction site / Throughout construction stage / Until completion of all construction activities |
Contractor appointed by OPC |
|
P |
|
|
EIAO-TM |
Landscape and Visual Impact (Operation) |
|||||||||
Table 12.14 (OP01) |
Table 9.2 (OP01) |
Sensitive
Design and Disposition All proposed hard structures should be
sensitively designed in a manner that responds to the existing and planned
landscape context, and minimises potential adverse landscape and visual
impacts. The structural design should
seek to reduce the apparent visual mass through the use of natural materials
such as wooden frame and semi-transparent panels. Subdued tones should be considered for the
colour palette with non-reflective finishes to reduce glare effect. Site specific
measures, such as the disposition of the key structures closer to the
northern slopes, the design of building forms as extension along the existing
slope topography, the use of concave roof form and the location of ride
platforms on or near the slopes to minimise structural support, should also
be considered for better integration with the surroundings and minimisation
of potential visual impacts. |
Project buildings / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Table 12.14 (OP03) |
Table 9.2 (OP03) |
Enhancement
Planting Other than compensatory tree planting,
additional trees, shrubs, groundcovers and lawn should also be considered to
maximise greening within the redevelopment area. |
Project area / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Table 12.14 (OP06) |
Table 9.2 (OP06) |
Responsive
Lighting Design Overall lighting design would carefully consider
a reasonable level of functional and thematic lighting with due consideration
of possible light pollution and night-time glare to the surroundings. Consideration shall be made by the lighting
designers to the following measures: § Lighting shall be
designed with due consideration of mounting height and direction of light
fixtures so as not to point directly towards any sensitive receiver. § Lighting shall be
arranged with due consideration of reflectance so as to avoid glare effect. § Lighting shall be regularly
monitored during operation. § Lights located
adjacent or in proximity to neighbours shall be carefully designed to prevent
possible light intrusion. § Lighting operation
schedule shall specify only lights necessary for security to be left on after
business hours. § Paving materials
should be selected as necessary to reduce potential glare from surface
reflectance. § Particular attention
should be paid to the use of lighting having a high intensity or harsher tone
(e.g. metal halide lamps). § Lights shall generally
be models having precise cut-off range (such as full cut-off optics where
available and practicable) and if necessary be fitted with adjustable
anti-glare shields. |
Project area / During design stage / Throughout operation phase |
Design Architect / Contractor appointed by OPC |
P |
|
P |
|
EIAO-TM |
Remarks:
1. Des – Design Stage, Con – Construction Stage,
Op – Operation, Dec - Decommissioning