|
|||||
|
|||||
|
This report takes into account the particular It is not intended for and should
not be relied Job number |
|
|
|
||
Ove Arup & Partners
Hong Kong Ltd 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong |
|
|||||||||||||
|
|
|
|||||||||||
Agreement No.
CE 18/2012 (CE) Development of Anderson Road Quarry - Investigation |
|
||||||||||||
|
|
||||||||||||
|
|
|
|
||||||||||
|
|
||||||||||||
5.22 |
|
||||||||||||
|
|
|
|||||||||||
227724-REP-042-03 |
|
||||||||||||
|
|
|
|
|
|||||||||
|
|||||||||||||
|
|
|
|
||||||||||
Draft
1 |
18 October 2013 |
|
|||||||||||
|
|
||||||||||||
Various |
S Y Chan |
Fergal Whyte |
|
||||||||||
|
|
|
|
||||||||||
|
|
|
|
||||||||||
Final |
11 April 2014 |
Final EIA Executive Summary |
|
||||||||||
Final |
|
||||||||||||
|
|
||||||||||||
S Y Chan |
Fergal Whyte |
|
|||||||||||
|
|
|
|
||||||||||
|
|
|
|
||||||||||
Final 2 |
26 May 2014 |
Revised Final EIA Executive Summary |
|
||||||||||
Final 2 |
|
||||||||||||
|
|
||||||||||||
S Y Chan |
Fergal Whyte |
|
|||||||||||
|
|
|
|
||||||||||
|
|
|
|
||||||||||
Final 3 |
11 Jun 2014 |
Revised Final EIA Executive Summary |
|
||||||||||
|
|||||||||||||
|
|
||||||||||||
S Y Chan |
Fergal Whyte |
|
|||||||||||
|
|
|
|
||||||||||
|
|
|
|||||||||||
|
|
|
ü |
|
|
||||||||
|
|
|
|||||||||||
2.1 General Description of the Project
2.3 Recommended Outline Development Plan and
Consideration of Alternatives
2.4 Nature, Benefit, Scope and Implementation
Programme of the Project
3 SUMMARY OF KEY FINDINGS OF THE ENVIRONMENTAL
IMPACT ASSESSMENT
3.4 Sewerage and Sewage Treatment
3.9 Environmental Monitoring and Audit
227724/E/0001 Location of Project
227724/E/0002 Locations of Designated Projects
227724/E/0003 Recommended Outline Development Plan
1.1.1 The Anderson Road Quarries have been in operation since 1956. In 1998, the Central and East Kowloon Development Statement proposed new housing developments at a platform site covering about 40 ha of Anderson Road Quarries (the upper quarry site, now called the Anderson Road Quarry site, ARQ) and at an area west of Anderson Road covering about 20 ha (the lower quarry site, now called the Development at Anderson Road, DAR).
1.1.2 The site formation works of the lower quarry site are now in progress under Contract No. CV/2007/03 ‘Development at Anderson Road – Site Formation and Associated Infrastructure Works’.
1.1.3 PlanD commissioned Arup on 27 January 2011 under Agreement No. CE 4/2010 (TP) to undertake a Planning Study on Future Land Use at Anderson Road Quarry (the Planning Study) to examine the future land use and explore the development potential of the upper quarry area. The recommendations and the Recommended Outline Development Plan (RODP) proposed under the Planning Study provided the basis for the development at the ARQ.
1.1.4 CEDD commissioned Arup on 26 October 2012 under Agreement No. CE 18/2012 (CE) ‘Development of Anderson Road Quarry – Investigation’ to undertake the engineering feasibility study of the development proposals at the Anderson Road Quarry site recommended in the Planning Study and the associated road improvement works and pedestrian connectivity to Kwun Tong Town Centre and nearby MTR stations.
1.2.1
The Study Area, as delineated in Figure 227724/E/0001, is located on the
south-western slopes of Tai Sheung Tok at the far north-eastern edge of urban East Kowloon,
and lies close to the major population centre of Kwun
Tong, Lam Tin and Sau Mau Ping. Specifically, the Study Area covers an area of
approximately 86 hectares, which includes a platform area of approximately 40
hectares.
1.3.1
In accordance with the requirements of
Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO), a project
profile (No. PP-465/2012) for the Development of Anderson Road Quarry (the
Project) was submitted to the Director of Environmental Protection (the “DEP”)
for application for an EIA Study Brief on 8 May 2012. Pursuant to Section 5(7)(a) of the EIAO, the DEP has issued a Study Brief (No.:
ESB-247/2012 dated 19 June 2012) for the EIA study.
1.3.2
The purpose of this EIA study is to
provide information on the nature and extent of environmental impacts arising
from the construction and operation of the Project and associated works that
will take place concurrently. This information will contribute to decisions by
the Director on:
(1) the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
(2) the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
(3) the acceptability of residual impacts after the proposed mitigation measures are implemented.
1.4.1
The engineering feasibility study of the Project
is a designated project (DP) under item 1 of Schedule 3 of the Environmental
Impact Assessment Ordinance (EIAO), which specifies that “Engineering
feasibility study of urban development projects with a study area covering more
than 20 ha or involving a total population of more than 100,000”.
1.4.2
On the other hand, the Project also
includes the proposed cavern development in the Study Area and the road improvement works at junction of (J/O) Lin Tak Road and Sau Mau Ping Road, at J/O Clear Water Bay Road and
Road L1 of DAR, as well as at the merging lane
at New Clear Water Bay Road near Shun Lee Tsuen Road. These have been identified as DPs as per
Schedule 2, Part I of the EIAO:
(1) Proposed cavern development: Item Q.2 – Underground rock caverns;
(2) Road improvement works: Item A.1 – A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing road.
1.4.3
The locations of these two Schedule 2 DPs
are shown in Figure 227724/E/0002. The
potential environmental impacts of these two Schedule 2 DPs have been reviewed,
and concluded that no insurmountable environmental impacts arise from these two
Schedule 2 DPs. Nevertheless, the detailed environmental implications of these
two Schedule 2 DPs will be further investigated in separate EIAs under EIAO.
2.1
General Description of the Project
2.1.1
The Project comprises the development of
ARQ and associated supporting infrastructure. Through the Planning Study, a
Recommended Outline Development Plan (RODP) for the development of the ARQ has
been developed with residential as the leading land use. The development plan,
the associated infrastructure provisions and the major activities in the
project scope are outlined below.
2.2.1
In the Policy Address 2010/11, the Chief
Executive expressed Government’s intention to make land available for an
average of 20,000 new private units per year in the next 10 years and 15,000 Public
Rental Housing (PRH) units per year, together with a total of 5,000 “My Home
Purchase Plan (MHPP)” units and 5,000 Home Ownership Scheme flats per year. In
previous consultation with Kwun Tong and Sai Kung District Councils during the Planning Study,
members agreed that residential developments should be provided at the Study
Area to meet the need on housing. Since the Study Area consists of a
development platform of approximately 40 ha in area and in close proximity to
urban area in Kwun Tong, it has a high potential to
fulfil the territorial housing demand and can also act as a solution space for
accommodating district-wide Government, Institution or Community (G/IC)
provision.
Predicted Future Environment without Project
2.2.2
Due to its use as a quarry site, ARQ is a
highly disturbed environment where ecological value is considered to be
minimal. Under the rehabilitation contract (No. GE/96/10), the landscape of the
quarry will be rehabilitated through extensive tree and shrub planting on exposed
rock face.
2.2.3
Without the proposed development, the
planting established under the rehabilitation contract will, though gradually, begin
to mature. Some habitats may be expected to increase in ecological value in
future as a result of ecological succession, such as the maturation of shrubland into woodland.
2.2.4
However, without the proposed development,
the Study Area will be left as an extensive vacant government land. The
opportunity to fulfil the social needs of the local community and to enhance
local economy through the creation of recreational space, tourist development
and G/IC facilities in the Study Area will be lost. It will also be difficult
to meet the housing demand within the urban area for which alternative sites with
similar development potential is unlikely to be available in the vicinity.
2.3
Recommended Outline Development Plan and Consideration of Alternatives
2.3.1
Taking into account the comments received
from community engagements under the Planning Study with careful and
comprehensive consideration, and the findings of the engineering feasibility
study under this Assignment, the RODP have been refined and finalized.
2.3.2
Figure
227724/E/0003 presents the final RODP. A summary of the major
planning parameters proposed in the final RODP is given in Table 2.1 below:
Table
2.1: Major planning parameters of the
final RODP
Planning Parameters |
|
Total Population |
25,000 |
Private Housing Population (no. of flat) |
7,530 |
Subsidised Housing Population (no. of flat) |
1,880 |
Residential Mix (Private : Subsidised Housing) (based on target population or number of units) |
80:20 |
Average Plot Ratio – Private Housing |
4.2 |
Average Plot Ratio – Subsidised Housing |
6.3 |
2.3.3
During the course of the engineering
feasibility study, the following considerations have been given such that the
Project will be implemented in a more environmentally friendly manner:
(a)
Alignment
of Road L4 has been revised to
substantially reduce the amount of rock cutting required;
(b)
Tunneling
method will be used as an alternative construction method for the access road
leading to Po Lam Road to reduce excavation required, reduce area of woodland
affected and to preserve the surrounding natural habitats;
(c)
Discussion had been made with the
Geotechnical Engineering Office (GEO) and quarry operator on the additional
rock excavation to be carried out under the current Contract of “Rehabilitation
of Anderson Road Quarry”. With this arrangement, the bulk rock excavation
activities will be completed before the population intake of DAR and thus the
inherent construction nuisances to population in DAR could be kept at the
minimum.
(d)
The two proposed drainage retention tanks
will be combined into one. With this arrangement, the piece of land being
reserved for one of the drainage retention
tanks will be released and quantity of excavated
spoil materials require
offsite disposal will also be reduced; and
(e)
The sewer pipe from ARQ site will be connected
to the terminal manhole at Po Lam Road with a refined alignment. The proposal
has been discussed with DAR project office and agreed that part of the proposed
works, which falls within DAR’s project boundary, will be undertaken by DAR to
minimise the traffic disturbance in future.
2.4
Nature, Benefit, Scope and Implementation
Programme of the Project
Nature of the Project
2.4.1
The Project comprises housing and infrastructure developments at ARQ
with a Study Area of about 86 hectares (including a platform site of approximately
40 hectares). The planning of the developments within ARQ are broadly divided
into four areas, namely the Civic Core, Northern Community, Southern Community,
and Recreation Network, and will provide a mix of housing types as well as
basic infrastructure and community facilities for a target population of
25,000.
Benefits of the Project
2.4.2
The benefits of the Project, including environmental benefits, are
broadly described below:
Land Use Planning
(1) Provide around 40 ha platform as a solution space to meet housing demand in the urban area.
(2) Provide an opportunity to create a green and sustainable environment that complements the land uses and urban environment of the surrounding area.
Socio-economic Aspect
(1) Provide an opportunity to increase housing choices to accommodate younger population and different income level in order to introduce a more balanced demographic mix, enable socio-economic development and thereby build a harmonious community.
(2) With its unique location, land form, land area and visual resources, the quarry may potentially serves as a new recreational/ leisure/ tourism destination for both local residents and visitors.
(3) Tourism development will contribute to the development of local economy and provide employment opportunities and, at the same time, improves the amenities and environmental quality of the area.
Engineering
(1) Provide an opportunity to utilising spaces within rock caverns and drop-cuts to release land resources in other areas, and using the rock face for recreational purposes.
Environmental Benefits
(1) The Project will provide the opportunity to remove the existing quarry (i.e. a bare site) from the urban area and to enhance the existing landform of the Study Area through greening to create a green and liveable community.
(2) The Project will greatly enhance the landscape and visual resources/amenity of the existing barren quarry by creation of new open space, green promenade, Quarry Park, and pedestrian corridors which are well connected within the ARQ development and to the adjacent districts.
(3) The Project will adopt appropriate building and urban design control to create pleasant micro-climate conditions in the Study Area.
(4) The urban design scheme of the Project encourages the use of public transportation to access the Study Area in order to reduce traffic burden and air/ noise pollution.
(5) The existing rock crushing plant, concrete batching plant and asphalt plant in the existing quarry site can be removed through the Project and there will be opportunity to clean up these potentially contaminated lands.
(6) As the Project makes use of existing land, rather than carrying out reclamation works, it reduces the need to explore reclamation options which will alter natural waterfront and seawater resources.
Scope
and Implementation Programme of the Project
2.4.3
The scope and tentative implementation
programme of the Project are summarised in Table
3.1 below. The construction of the ARQ development is anticipated to
commence in 2016 for completion in 2026. It is anticipated that the development
will be commissioned in phases, with half of the population intake expected in
2022 and the final population intake in 2026.
Table 3.1: Scope of project
Works Package |
Works
Components |
Works
Arrangement/ Time Line |
Works Package 1 |
Site formation at the southern portion of the Study Area |
These works components are included in the EIA/ mid 2016 – end 2018 |
Internal roads at the southern portion of the Study Area |
||
Access road for main external access via. Po Lam Road |
||
Access road for supplementary external access via. DAR local road with
associated bus bays and semi-enclosure noise barrier |
||
Supporting infrastructure works, including two-way escalators and
subways, for pedestrian connectivity between development of ARQ and DAR |
||
Stormwater drainage
systems at the southern portion of the Study Area |
||
Sewerage systems at the southern portion of the Study Area |
||
Water supply systems at the southern portion of the Study Area |
||
Landscaping at the southern portion of the Study Area |
||
Works Package 2 |
Site formation at the northern portion of the Study Area |
These works components are included in the EIA/ early 2018 –
end 2020 |
Internal roads with associated public transport terminus at the
northern portion of the Study Area |
||
Stormwater drainage
systems at the northern portion of the Study Area |
||
Sewerage systems at the northern portion of the Study Area |
||
Water supply systems at the northern portion of the Study Area |
||
Landscaping at the northern
portion of the Study Area |
||
Works Package 3 |
Drainage retention tank in the Study Area |
This works component is included in the EIA/ mid 2016 – mid 2019 |
Works Package 4 |
Viewing platforms |
This work component is included in the EIA/ early 2018 – end 2020 |
Works Package 5 |
Salt and fresh water pumping stations in the Study Area |
These works components are included in the EIA/ mid 2018 – end 2020 |
Service reservoirs in the Study Area |
||
Works Package 6 |
Road improvement works at J/O Lin Tak Road and Sau Mau Ping Road,
including road widening works at Lin Tak Road and a new vehicular bridge from
Lin Tak Road to Sau Mau Ping Road |
The
environmental acceptability of these works components is addressed in this
EIA whilst the detailed environmental implications of these works components
will be further investigated in a separate EIA under the EIAO/ early 2017 –
early 2022 |
Bus-bus interchange (BBI) at TKO Tunnel Toll Plaza Area |
||
Associated site formation works |
||
Works Package 7 |
Road improvement works at J/O Clear Water Bay Road and Road L1
constructed under DAR, including provision of u-turn
facility. |
The
environmental acceptability of these works components is addressed in this
EIA whilst the detailed environmental implications of these works components
will be further investigated in a separate EIA under the EIAO/ early 2017 –
early 2021 |
Road improvement works at merging lane at New Clear Water Bay Road
near Shun Lee Tsuen Road, including increase of
merging length |
||
Associated site formation works |
||
Works Package 8 |
Rock cavern development |
The
environmental acceptability of this
works component is addressed in this EIA whilst the detailed environmental
implications of these works components will be further investigated in a separate
EIA under the EIAO/ early 2018 – end 2020 |
2.5.1
The preferred construction methods are presented below:
Site Formation Works
2.5.2
The Study Area will be a net fill intake
site that will not generate net inert C&D material disposal to the public
fill bank. Fill would be imported to the Study Area to fill the area to the
site formation level. Appropriate sources of fill material would be identified
in consultation with the Public Fill Committee and Environmental Protection
Department. Public fill from the fill bank will be adopted as far as available.
The trucks logistic route for public fill import will utilize the existing Anderson
Road and/or DAR local roads.
2.5.3
In order to avoid secondary environmental
impact, external disposal of the spoil material will be minimized as far as
technically practicable and subject to works programme. The phasing programme
of the site formation has been determined to cope with the population intake
programme.
Road Networks of the Study Area
2.5.4
The construction of
road networks (including internal
roads and access roads) and the associated drainage
systems, sewerage networks, water supply networks and utility construction will
include earthwork, utilities laying and paving.
Landscaping Works of
the Study Area
2.5.5
Landscaping works will be
conducted after site formation works. As it will mainly involve planting and
minor pedestrian facilities, environmental impact is not anticipated.
Drainage Retention Tank
2.5.6
The area of drainage retention tank will
be about 6,600 m2. The major construction works will include
earthwork and concrete works for the tank and construction of associated facilities
including air ventilation ducts, intake fan room and deodorization room and
control room, maintenance access road etc.
Service Reservoirs
2.5.7
The area of fresh and salt water service
reservoirs will be about 600 m2 and 108 m2 respectively.
The major construction works will include earthwork, slopework, concrete works for service reservoir structure
and construction of associated pipeworks and
maintenance access road.
Viewing Platforms
2.5.8
The major construction activities for the
viewing platforms will be platform erection works on existing rock slope.
Rock Cavern Development and Road Improvement Works
2.5.9
Construction methods for the two
associated infrastructures i.e. the cavern development and the road improvement
works are also given below. As mentioned in Section 1.4, the detailed environmental implications of these two
Schedule 2 DPs will be further investigated in separate EIAs under EIAO.
Rock
Cavern Development
2.5.10
The major construction activities for the
rock cavern development will be excavation works on existing rock slope.
Road
Improvement Works
2.5.11
The major construction activities for the
road improvement measures, e.g. road widening works and provision of u-turn facility, will include slope works and paving.
For the construction of vehicular bridge from Lin Tak Road to
Sau Mau Ping Road, in order to maintain the traffic flow and minimize
disturbance to the existing traffic on TKO Road and the existing vehicular
bridge over TKO Road during the construction of the flyover, balanced
cantilever construction method with in-situ adjustable form-travellers might be
adopted.
Construction Phase
3.1.1
Construction dust is the key pollutant during the construction phase of
the Project which would be generated from various construction works, including
site clearance, soil excavation, backfilling, temporary storage, handling and
transportation of materials, and wind erosion of open sites.
3.1.2
Quantitative fugitive dust
assessments have been conducted, taking into account the cumulative impact
caused by nearby concurrent projects. Effective dust control following the requirements given in the Air
Pollution Control (Construction Dust) Regulation and in accordance with the
EM&A programme during construction are recommended. Assessment results
suggested that watering at site once per hour would be required to control the
fugitive dust impact to acceptable levels.
Operational Phase
3.1.3
The major sources of air
quality impacts during the operational phase of the Project include vehicular
emissions from proposed road network (i.e. proposed internal road within the
Study Area and the DAR development, and the road improvement works) and the
existing road network as well as chimney
emissions from the United Christian Hospital and nearby restaurants.
3.1.4
Quantitative
assessment on cumulative air quality impact has been conducted
and based on the assessment results, all the predicted cumulative 1-hour and annual Nitrogen Dioxide (NO2),
24-hour and annual Respirable Suspended Particulates
(RSP), 24-hour and annual Fine Suspended Particulates (FSP) concentrations
would comply with the relevant Air Quality Objectives (AQOs), except a marginal
exceedance
of annual NO2 (i.e. 41 µg/m3)
is found at 1.5m
of ASMP-34 (Sau Fai House). The
ground level of this single aspect building was intentionally designed not for
residential purpose, but only for non-sensitive uses such as machinery and
transformers plant rooms etc. The assessment result at 1.5m of this ASR is
therefore for reference only. The floors occupied by residences are at least 5m
above the ground level, and all assessment results at 5m and other higher
levels of this ASR comply with the AQOs. Therefore, adverse cumulative air
quality impact within 500m assessment area during the operational phase is not
anticipated.
Construction Phase
3.2.1
Assessment of construction noise, including cumulative impact from the
proposed pedestrian connectivity and the rock cavern development, has been
conducted. With the implementation of all the practicable mitigation measures including
good site practice, use of site hoarding, use of movable noise barrier &
enclosure, use of “quiet” plant and working methods, the potential construction
noise impacts to the nearby Noise Sensitive Receivers (NSRs) would be minimised.
3.2.2
However, due to the close proximity of some NSRs to the construction
sites, residual construction noise impacts are anticipated at several planned
NSRs including two planned residential NSRs and three planned educational
institutions where exceedances have been identified
during the normal and examination period. To further reduce the noise impacts,
it is recommended that the Contractor should closely liaise with the schools to
avoid scheduling the noisy construction works during examination period.
3.2.3
With the implementation of all the practicable mitigation measures, the
residual noise impacts have been minimised. Given the transient nature of the
impact, the residual noise impacts are considered acceptable.
Operational Phase
3.2.4
Operational noise impacts associated with road traffic noise and fixed
noise sources have been assessed. With the recommendation of
noise mitigation measures in form of setback, building orientation, use of
non-noise sensitive use and non-openable windows/ maintenance window that
are not opened for ventilation, compliance of road traffic noise criteria
is achieved in the ARQ. However, the road traffic noise assessment revealed that exceedance of noise criteria are found at several planned
residential and educational institutions NSRs at DAR along Road
L4. Direct
mitigation measure in the form of a semi-enclosure is recommended along Road
L4.
3.2.5
The sound power level for the fixed noise source (proposed pumping
station for saltwater and freshwater and the proposed rock caver devleopment) has been specified. Noise control measures have
also been recommended for this fixed noise source in order to comply with the
statutory criteria. The public transport terminus is recommended to be designed
to no direct line-of-sight of the noise sources at the noise sensitive uses.
3.2.6
With the implementation of the recommended mitigation measures, no
adverse noise impacts are anticipated during the construction and operational
phase.
3.3.1
The potential water quality impacts
arising from the construction and operation of the ARQ development have been
assessed in accordance with the requirements of Annexes 6 and 14 of the
TM-EIAO.
3.3.2
Water sensitive receivers (WSRs) have been
identified for the Project, including Tseng Lan Shue Stream and Ma Yau
Tong Stream. There will be no dredging, reclamation and stream/river
alternation works such that in general the works will have no direct contact
with water bodies.
3.3.3
During construction phase, potential water
quality impacts would arise from construction runoff, sewage from workforce.
Control measures such as silt traps and oil interceptors will be implemented on
site to control the potential surface runoff. Best management practice as
stipulated in the Practice for Professional Persons on Construction Site
Drainage, Environmental Protection Department, 1994 (ProPECC
PN 1/94) should be followed.
3.3.4
During operational phase, change of
hydrological regime is not anticipated. Non-point sources pollution due to
additional runoff will be intercepted by silt traps. Regular cleaning of
drainage system should be provided. Point source pollution due to sewage will
be diverted to existing sewage system. It is understood
that EPD’s “Upgrading of Kwun Tong Preliminary
Treatment Works – Feasibility Study, Agreement No. CE5/2008(DS)” recommended to
upgrade the peak capacity of the Kwun Tong
Preliminary Treatment Works and should be adequate
to cater for the additional flow from the ARQ development. No additional
mitigation measure is required.
3.3.5
With full implementation of the mitigation
measures, no adverse residual and cumulative impacts are
anticipated during both the construction and operational phase of the Project.
3.4
Sewerage and Sewage Treatment
3.4.1 Sewage generated from the Project will be collected at the Kwun Tong Preliminary Treatment Works (KTPTW) for further treatment and disposal. Since the capacity of the KTPTW will be upgraded and the upgraded capacity will be adequate to cater for the increased flow due to the Project, no additional pumping stations and sewerage treatment facilities are required. The KTPTW upgrading works is anticipated to be completed in June 2021 under Agreement No. CE47/2013(DS) “Upgrading of Kwun Tong Preliminary Treatment Works – Investigation, Design and Construction”. Since the first population intake is planned in 2022, no programme gap between the KTPTW upgrading works and the ARQ development is anticipated.
3.4.2
However to cater for the increased sewage due to the Project, two routes
of sewerage system will be built in the ARQ and upgrade of the downstream
sewers at Po Lam Road is also recommended in order to handle the sewerage
generated from ARQ.
Construction
Phase
3.5.1
During the construction phase, typical wastes include top soil,
construction and demolition (C&D) materials, rock, chemical wastes, general
refuse and sewage would be generated. All generated top soil and inert C&D
material would be reused on-site and off-site disposal is not required. For
other wastes types such as chemical waste and general refuse, mitigation
measures including good site practices, on-site sorting and reuse, proper
storage, collection and transportation of waste, etc. are recommended. A
summary of the construction waste arising from the works area with
recommendation for outlets during construction phase is presented in Table 3.1.
Operational Phase
3.5.2 During the operational phase of the proposed development, municipal solid waste would be the major waste type. Recommendations are given to ensure proper handling and disposal of the waste. No adverse impacts on the environment would be anticipated with the implementation of the recommended mitigation measures. A summary of the waste arising from the operational phase is presented in Table 3.2.
Table 3.1: Summary of waste arising from the works
area with recommendation for outlets during construction phase (Phase I and
Phase II)
Activities |
Waste type |
Total amount generated (m3) |
Total amount reused (m3) |
Total amount disposed (m3) |
Recommended outlets |
|||
|
|
Phase I |
Phase II |
Phase I |
Phase II |
Phase I |
Phase II |
|
Site clearance |
Top soil |
2,300 |
2,300 |
2,300 |
2,300 |
0 |
0 |
Reuse within the site |
Vegetation |
2,000 |
2,000 |
200 |
200 |
1,800 |
1,800 |
Reuse within the site; Disposal to landfill |
|
Contaminated soil |
TBC [5] |
N/A |
N/A |
|||||
Site formation |
Inert soft C&D materials [1] |
78,000 |
312,000 |
78,000 |
312,000 |
0 |
0 |
Reuse within the site |
Rock [2] |
102,000 |
120,000 |
102,000 |
120,000 |
0 |
0 |
Reuse within the site |
|
Construction of new buildings and structures |
AHM [3] |
23,112 |
25,800 |
23,112 |
25,800 |
0 |
0 |
Reuse within the site as much as possible |
Non-inert C&D materials [4] |
5,778 |
6,450 |
0 |
0 |
5,778 |
6,450 |
Reuse and recycle as much as possible before disposal to landfill |
|
General construction activities |
General refuse |
308 tonne |
410 tonne |
0 |
0 |
308 tonne |
410 tonne |
General refuse: Disposal to landfill |
Paper, metals, plastics etc. |
Paper, metals and plastics etc.: Collected by recycler |
|||||||
Chemical waste |
A few hundred litres per month |
A few hundred litres per month |
Recycled by licensed facility as far as possible, the remaining was disposal of at CWTC |
|||||
Sewage |
37.5 m3/day |
0 |
37.5 m3/day |
Chemical toilets to be collected and disposed by licensed collector |
Notes:
[1]
“Inert
soft C&D material” includes, but not limited to, excavated soil.
[2]
“Rock”
includes all grade rock.
[3]
“Artificial
hard material” includes, but not limited to, broken concrete, asphalt, bitumen
and granular materials, etc.
[4]
“Non-inert
C&D material” includes, but not limited to, bamboo, timber, paper and
plastic, etc.
[5]
TBC:
To be confirmed. As the Study Area is managed by private operator and still in
operation, therefore undertaking the environmental SI at this EIA stage is not
feasible. The proposed environmental SI should be carried out once the
operation is terminated and the land is resumed to determine the extent of land
contamination.
Table 3.2: Summary of waste arising from the operational phase
Major activities |
Waste type |
Total amount generated |
Handling procedures |
Recommended disposal outlets |
General activities within Study Area |
Municipal Solid Waste |
32.2tpd |
Provide on-site refuse collection points with recycle bins |
Disposal to landfill |
Paper, metal, plastic and glass etc. |
35.0tpd |
Recycler |
||
Laboratory from secondary school |
Chemical waste |
Insignificant |
Store on-site in designated area before being collected and disposed of by licensed collector |
Recycle by licensed facility as much as possible, the remaining was disposal to CWTC |
3.6.1
The potential contaminative land use within the Study Area and their
potential impacts to the future development has been assessed which involved
desktop review, site surveys and proposed environmental site investigation (SI).
3.6.2
Based on the assessment results, a total of five potentially
contaminated areas within the Study Area were proposed for environmental SI.
However, as all the five potentially contaminated areas are managed by private
operator and still in operation, undertaking the environmental SI works at this
EIA stage is not feasible. The proposed environmental SI works for these areas
should commence once the operation is terminated and the land is resumed.
3.6.3
Following the completion of the environmental SI, a Contamination
Assessment Report (CAR) will be prepared to present the findings and evaluate
the level and extent of the potential contamination. If land contamination is
identified and remediation is required, a Remediation Action Plan (RAP) will be
prepared to recommend specific remediation measures. Upon completion of the
remediation works, if any, a Remediation Report (RR) to demonstrate the
clean-up works are adequate would also be prepared. The CAR, RAP and RR would
be submitted to EPD for approval prior to commencement of any construction /
development works.
3.7.1
The proposed development will be concentrated at the existing quarry
site and the surrounding developed areas which are of low ecological value. The
majority of the plantation and secondary woodland habitats will be preserved
and remain contiguous with the terrestrial hillside habitats at Tai Sheung Tok Hill. Hence, no major
ecological impacts are expected of the Project.
3.7.2
The proposed road and underpass works at the southeast part of the Study
Area will cause the loss of three scattered small-sized young secondary
woodlands (with a total area of about 1.13 ha). These affected woodland are
either isolated patches or at the woodland fringe, and the proposed underpass will
go underneath the woodland and emerge at Po Lam Road. Hence, the overall
integrity of the major woodland patch at the southeast part of the Study Area
will be kept.
3.7.3
A Wooded Area of about 1.2 ha will be provided at the proposed Quarry
Park to compensate for the loss of these small secondary woodland patches. An
updated vegetation survey identifying any potential presence of floral of
conservation importance within the inaccessible secondary woodland and habitats
to be directly impacted by the proposed development, as well as transplantation
of the affected individuals will be conducted prior to the construction phase. Relocation of Hong Kong Newts (or other species of
conservation significance) found in the water channels or streams within the
proposed development area will also be carried out as a precautionary measure.
3.7.4
Other mitigation measures recommended include good site practices to
prevent construction site run-off from entering the nearby watercourses and to
minimise the potential indirect light disturbance impact on the wildlife groups
inhabiting the terrestrial habitats surrounding the Study Area. Overall,
with the implementation of the proposed mitigation measures, all ecological
impacts of the Project will be fully mitigated. Only low or insignificant
residual impacts are predicted after the implementation of the mitigation
measures. On the other hand, there will be a positive enhancement on the
existing habitat with the compensatory planting in the future Quarry Park.
3.8
Landscape and Visual
3.8.1 The scale of ARQ Development, particularly ex-quarry barren land, will inevitably result in some landscape and visual impacts; which have been minimized through careful consideration of the layout plans for the development incorporate design mitigation measures such as, creation of new Quarry Park, creation of new open space and green spines, creation of, pedestrian corridors and breezeways, retention of views to ridgelines at strategic level, preservation of the Tai Sheung Tok Hill Rock Face as landmark for Kowloon East, aesthetic design of roads and streetscapes and provision of compensatory planting proposals, in the development. It is considered that the urban planning scheme on ARQ Development will have enhancement to both landscape and visual perspective.
3.8.2 Based on a very broad brush estimate, approximately 1,100 existing trees will be impacted by ARQ Development, of which approximately 1,021 no. of trees will be felled and 79 no. of trees will be transplanted. Approximately 5,000 nos. of trees will be planted within new open spaces and approximately 1,000 nos. of trees will be planted for new roadside amenity to compensate for the loss of existing trees. The overall residual impact on trees is considered acceptable with mitigation measures and in the longer term beneficial.
3.8.3 A Wooded Area of about 1.2 ha will be provided to compensate the loss of semi-natural hillside vegetation due to the proposed road and underpass. The loss of landscape resource will be compensated by the newly created landscape resources, such as buffer planting along new road when the trees in the new landscape resources matured. The permanent loss would be compensated by new trees planting, new recreational space, quarry park, green promenade, civic spine, streetscape and gateway at ARQ development. It is considered that the residual impact on this resource will be reduced to slight with implementation of compensation measures.
3.8.4
A series of open space
system that create landscape and visual connector with landscape elements to
accommodate a number of leisure, recreation and civic activities are proposed
in the development layout. These combine
different types and character of spaces, comprising Quarry Park, Green Spines,
Summit Outlook, Gateway features, Children Playground,
Viewing Platform, Civic Square, Viewing Deck, Rock Face, Rock Cavern, Hiking
Trail and Green Promenade. Key
major open space provided at the close vicinity includes, Jordan Valley Park, Shun Lee Tsuen Sports Centre and Park, Sau
Ngau Road Playground, Hong Ning
Road Park and Sau Ming Road Park. A total of approximately 25 ha of open space
and 37 ha of green belts (mainly on rock face) will be provided within the ARQ
development. These open spaces are well
connected within the development and to the adjacent surrounding districts.
These new open spaces network are provided within ARQ at the close vicinity of
the adjacent districts.
Therefore the residual impact on LR9 and LR9.1 will be substantially beneficial
in the future when all mitigation measures become mature.
3.8.5
Quarry Landscape Character Area LCA6 and LCA7 will be significantly enhanced by the proposed ARQ Development after 10 years of operation. As compared with
the barren quarry, with little landscape resources/interests, the proposed ARQ
Development with new open spaces interconnected with green corridors in a new
urban setting. It is considered that the
residual impact on LCA6 and LCA7 will be substantially beneficial
in the future when all landscape becomes mature.
3.8.6
The scale and the extent of ARQ development is extensive and
significantly alters the visual context of area, particularly due to partially
or fully loss of open view, enclosure and blocking or reduction of depth of
current view. There will unavoidably be moderate residual impact on the VSRs in
Sau Mau Ping local area (R1.1,
R1.2, R1.3, R1.4, R1.5, R1.6, R1.7, R1.8, R1.12, R1.15, O1.4, and P1.1). However, the impact will be
slight after 10 years of operation. With implementation of mitigation measures,
there will be new open spaces and visual resources. These visual resources will
bring insubstantial visual impact to the VSRs in district and strategic levels.
3.8.7
Overall, the landscape and
visual impacts due to the ARQ Development
are considered to be acceptable with the implementation of the appropriate
mitigation measures, there will be insubstantial impact for visual and in the
long term be beneficial in respect of landscape.
3.9
Environmental Monitoring and Audit
3.9.1
The Environmental Monitoring and Audit
(EM&A) requirements and the mitigation measures to be implemented during
construction and operational phases of the ARQ development have been specified
in the EM&A Manual.
The EM&A Manual contains full details of the proposed baseline and
impact monitoring programmes, as well as performance specifications, audit
requirements and monitoring procedures. The EM&A programme will be
implemented throughout the entire construction period and operation period
(i.e. noise commissioning test for fixed noise sources) to regularly monitor
the environmental impacts on the neighbouring sensitive receivers.
4.1.1
The findings of the EIA provided
information on the nature and extent of the environmental impacts likely to
arise from the construction and operation of the ARQ development. The EIA has,
where appropriate, identified mitigation measures to ensure compliance with
environmental legislation and standards.
4.1.2
Overall, the EIA concluded that the ARQ
development would comply with the requirements of the EIAO and TM-EIAO with the
implementation of the proposed mitigation measures during the construction and
operational phases. The schedule of implementation of the proposed mitigation
measures has been provided in the EIA report. An EM&A programme has also been recommended to check the effectiveness of the proposed
mitigation measures.