|
|||||
|
|||||
|
This report takes into account the particular It is not intended for and should
not be relied Job number |
|
|
|
||
Ove Arup & Partners
Hong Kong Ltd 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong |
General
5.1.1 The relevant legislation and associated guidance applicable to present the study for the assessment of noise impacts include:
(1) Noise Control Ordinance (NCO) (Cap.400);
(2) Technical Memorandum (TM) on Noise from Construction Work other than Percussive Piling (TM-GW);
(3) TM on Noise from Percussive Piling (TM-PP);
(4) TM on Noise on Construction Work in Designated Areas (TM-DA);
(5) TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (TM-Places);
(6) EIAO (Cap. 499) and TM-EIAO;
(7) Hong Kong Planning Standards Guidelines (HKPSG); and
(8)
Noise Control Guidelines for
Holding Open Air Entertainment Activities.
Construction Noise
5.1.2 The NCO provides the
statutory framework for noise control in Hong Kong. Assessment procedures and
standards are set out in the respective TM promulgated under NCO.
5.1.3 To ensure a better
environment, the TM-EIAO promulgated under the EIAO has imposed more stringent
criteria. For construction, there is no statutory limit on daytime construction
noise under the NCO and related TMs. Nevertheless, the TM-EIAO stipulates
criteria of 65 – 75 dB(A) for daytime construction activities, as shown in
the Table 5.1.
Table 5.1: Noise standards for construction activities
Uses |
Noise Standards[1], Leq (30mins)
dB(A) |
0700 to 1900 hours on any day not being a Sunday or general holiday |
|
All domestic premises including temporary housing accommodation |
75 |
Hotels and hostels |
75 |
Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required |
70 65 (During examinations) |
Note:
[1] The above standards apply to uses that rely on opened windows for
ventilation.
Construction Noise During Restricted Hours
5.1.4 The NCO also provides statutory control on general construction works during restricted hours (i.e. 1900 to 0700 hours (of the next day) from Monday to Saturday and at any time on Sundays or public holidays). The use of Powered Mechanical Equipment (PME) for construction works during restricted hours would require a Construction Noise Permit (CNP). The TM-GW details the procedures adopted by EPD for assessing such application. The granting of a CNP is subject to conditions stated in the CNP and it may be revoked at any time for failure to comply with the permit conditions.
5.1.5 In addition to the general controls on the use of PME during restricted hours, the use of Specified Powered Mechanical Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW) during the restricted hours in a designated area are controlled by the TM-DA. Construction plant or equipment classified as SPME under the TM-DA includes hand-held breakers, bulldozers, concrete mixer lorries, dump trucks and poker vibrators. The PCW includes the erection or dismantling of formwork or scaffolding, hammering, handling of rubble, wooden boards, steel bars, or scaffolding material, and the disposal of rubble through plastic chutes.
5.1.6 The TM-DA details the procedures that should generally be adopted by the Authority for assessing the use of SPME during restricted hours and for determining whether a CNP would be issued.
5.1.7 Maximum noise levels from construction activities during restricted
hours at affected Noise Sensitive Receivers (NSRs) are controlled under the TMs
and shall not exceed the specified Acceptable Noise Levels (ANLs). These ANLs are stipulated in accordance with
the Area Sensitivity Ratings established for the NSRs. The ANLs for construction works in Designated
Areas are more stringent than those given in the GW-TM and are summarised in Table 5.2.
Table
5.2: ANLs for construction during restricted hours
Time Period |
ANLs for Area Sensitive Ratings[1], dB(A) |
||
A |
B |
C |
|
All weekdays during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day and evening (0700 to 2300 hours) |
60 (45) |
65 (50) |
70 (55) |
All days during the night-time (2300 to 0700 hours) |
45 (30) |
50 (35) |
55 (40) |
Note:
[1] Figures in brackets are ANLs for SPME construction work in designated areas.
5.1.8 As defined in the Noise Control Designated Area Plan No. EPD/AN/K &
NT-02, Kowloon East areas such as Shun Lee Estate, Shun Tin Estate, Shun On
Estate, Sau Mau Ping Estate, Sau Mau Ping South Estate, Po Tat Estate etc are
within the Designated Area.
5.1.9 Despite any description made in this report, there is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into account contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making a decision in granting a CNP. Nothing in the report shall bind the Noise Control Authority in making a decision. If a CNP is to be issued, the Noise Control Authority shall include in it any conditions it may demand. Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO.
Percussive Piling
5.1.10 Under the TM-PP,
CNPs are also required for percussive piling works, involving the use of
diesel, pneumatic and / or steam hammer. This TM specifies the permitted hours
and other conditions for percussive piling. Table 5.3 lists the acceptable percussive piling noise levels for
various types of NSR.
Table 5.3: ANLs for
percussive piling
NSR Window Type or
Means of Ventilation |
ANL, dB(A) |
(i) NSR (or part of NSR) with no window or other opening |
100 |
(ii) NSR with central air conditioning system. |
90 |
(iii) NSR with windows or other openings but without central air conditioning system |
85 |
5.1.11 Depending on the number and type of piling machines and the separation distance from NSRs, percussive piling may be restricted to 12, 5 or 3 hours per day. For NSRs that are particularly sensitive to noise, such as hospitals, medical clinics, educational institutions and courts of law, a further reduction of 10dB(A) shall be applied to the above ANLs.
5.1.12 To minimize the construction noise impact, alternative construction methods to replace percussive piling and blasting shall be proposed as far as practicable.
Construction Groundborne Noise
5.1.13 Noise arising from general construction works that may generate
groundborne noise during normal working hours is governed by the TM-EIAO under
the EIAO as shown in Table 5.1. The Technical Memorandum for the Assessment
of Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-Places) under the NCO stipulates that noise transmitted
primarily through the structural elements of building, or buildings, shall be
10 dB(A) less than the relevant ANLs.
5.1.14 Based on the same principle for the groundborne noise criteria (i.e.
ANL-10 dB(A) under the TM-Places), the construction groundborne noise levels
inside domestic premises and schools shall be limited to 65 dB(A) and 60 dB(A)
respectively when compared to the TM-EIAO.
5.1.15 For construction works conducted on general holidays, Sundays and
weekdays during evening (i.e. 1900-2300 hrs) and night time (i.e. 2300-0700
hrs) the following day, the construction groundborne noise level shall be
limited to 10 dB(A) below the respective ANLs for the Area Sensitive Rating
appropriate to those NSRs affected by the Project. A summary of these criteria
is given in the Table 5.4 below.
Table 5.4: Construction
groundborne noise criteria
NSR type |
Noise
Criteria, dB(A) |
||
[1] |
[2] |
[3] |
|
All domestic premises including
temporary housing accommodation |
65 |
50/55/60[4,5] |
35/40/45[4,5] |
Hotels and hostel |
|||
Educational institutions
including kindergarten, nurseries and all others where unaided voice
communication is required |
60 55 (for during examination) |
N/A[6] |
N/A[6] |
Notes:
[1] Daytime (0700 – 1900) except general holidays and Sunday
[2] Daytime (0700 – 1900) during general holidays and Sundays and all days during Evening (1900 –2300 hrs)
[3] Night-time (2300 – 0700 hrs)
[4] Based on the Basic Noise Level for NSRs with Area Sensitivity Ratings of A, B, and C detailed in the Technical Memorandum on Noise From Construction Work Other Than Percussive Piling.
[5] Construction Noise Permit is required for works during this period.
[6] No sensitive use in educational institutions during evening and night-time period is assumed except specified.
Operational Noise
5.1.16 The TM-EIAO (Annex 5 of TM) stipulates the noise standards for various noise sources as shown in Table 5.5. It should, however, be noted that the following noise criteria are only applicable to uses that rely on opened windows for ventilation.
Table 5.5: Noise standards for operational phase
Common Uses |
Noise Standards[1] |
|
Road Traffic Noise L10 (1hour) dB(A) |
Fixed Noise Sources |
|
All domestic premises including temporary housing accommodation |
70 |
a) 5dB(A) below the appropriate ANLs shown
in Table 3 of the Technical Memorandum for the Assessment of Noise from
Places Other than Domestic Premises, Public Places or Construction Sites, or b) the prevailing background noise levels
(For quiet areas with level 5 dB(A) below the ANL) |
Hotels and hostels |
70 |
|
Offices |
70 |
|
Educational institutions including kindergartens, nurseries & all
others where unaided voice communication is required |
65 |
|
Places of public worship and courts of law |
65 |
|
Hospitals, clinics, convalescences and homes for the aged (diagnostic
rooms and wards only) |
55 |
Note:
[1] The above standards apply to uses that rely on opened windows for ventilation.
Road Traffic Noise
5.1.17 The criteria for assessing road traffic noise is given in the TM-EIAO
and tabulated in Table 5.5. For
domestic premises, hotels, hostels and offices, the criterion is 70dB(A). For
educational institutes and places of worship, the criterion is 65dB(A). For
hospitals, clinics etc, a more stringent criterion of 55dB(A) is
stipulated. It should be noted that all
these criteria only apply to NSRs that rely on open-windows for ventilation.
Fixed Noise Sources
5.1.18 Operational noise from fixed noise sources is controlled under the NCO’s
TM on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-Places). To plan for a better environment, the TM-EIAO
has specified the following requirements, whichever is more stringent.
(1) 5dB(A) below the appropriate ANLs in the TM-Places; or
(2) the prevailing background noise levels.
The ANLs for different Area Sensitivity Ratings
during different periods are summarised in Table
5.6.
Table 5.6: ANLs for fixed
noise sources
Time Period |
ANL, dB(A) |
||
Area
Sensitivity Rating A |
Area
Sensitivity Rating B |
Area
Sensitivity Rating C |
|
Day (0700 to 1900 hours) |
60 |
65 |
70 |
Evening (1900 to 2300 hours) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
50 |
55 |
60 |
5.1.19 For assessing fixed noise sources, the Area Sensitivity Ratings at the NSRs are defined in accordance with the relevant TMs. Clear Water Bay Road and Sau Mau Ping Road have an Annual Average Daily Traffic (AADT) of 27,470 and 22,640 respectively in Year 2012 and hence it is not considered as an Influencing Factor (IF) due to the daily traffic flow of lower than 30,000 vehicles. An Area Sensitivity Rating of “B” is therefore assigned for the NSRs indirectly influenced by the IF and “C” for NSRs directly influenced by the IF according to the TM. The Assessment Area of ARQ consists of high-rise building blocks at south and low density residential area at north. As ARQ is located in between these two areas, the NSRs of ARQ are considered as “Type (iv) Others Area” according to the TM. An Area Sensitivity Rating of the NSRs of ARQ is considered as “B”.
Noise from Bus
Terminus
5.1.20 There are no noise level standards stipulated for the noise from the operation of bus terminus. Chapter 9 of Hong Kong Planning Standards and Guidelines (HKPSG) provides considerations for the Project Proponent to determine the location and layout of the bus terminus during planning stage.
5.2
Description of Existing Environment
5.2.1 The major land use in the
vicinity of the Study Area is residential, with high-rise developments. The
existing noise climate is dominated by the road traffic noise from New Clear
Water Bay Road, Clear Water Bay Road, Anderson Road, Sau Mau Ping Road, Shun On
Road, Lee On Road, Po Lam Road, etc. The
Study Area is far away (~1500m) from the existing industrial areas in Kwun Tong
and Kowloon Bay. Noise impacts
attributed by existing industrial premises on the Study Area would be
insignificant.
5.3
Study Area & Noise Sensitive Receivers
Study
Area
5.3.1 The Study Area, as delineated in Figure
227724/E/0001, is located on the south-western slopes of the Tai Shueng Tok
Hill at the far north-eastern edge of urban East Kowloon, and is close to the
major population centres of Kwun Tong, Lam Tin and Sau Mau Ping. Specifically,
the Study Area covers an area of
about 86 ha, which includes a platform area of about 40 ha.
Sensitive
Receivers
5.3.2 With reference to Annex 13 of the TM-EIAO, NSRs include residential uses (all domestic premises including temporary housing), institutional uses (educational institutions including kindergarten and nurseries), hospitals, medical clinics, homes for the aged, convalescent homes, places of worship, libraries, court of law, performing arts centres, auditoria and amphitheatres, country park and others.
5.3.3 Representative NSRs within the assessment area have been identified with the first layer of NSRs selected for assessment. These NSRs cover all existing sensitive developments and planned NSRs during construction and operational phases.
5.3.4 The existing NSRs are identified by means of topographic maps, aerial photos, land status plans, S.16 / S.12a Town Planning Ordinance and site inspections. Planned / committed NSRs are identified by making reference to relevant Outline Zoning Plans (OZP), Outline Development Plans (ODP), Layout Plans and other published plans in relation to the Town Planning Board.
5.3.5 Referring to Section 1.1, prior to this Investigation Study, a Planning Study on Future Land Use at Anderson Road Quarry to examine the future land use and explore the development potential of the upper quarry area has been carried out. A Recommended Outline Development Plan (RODP) under the Planning Study is shown in Figure 227724/E/0002. The recommendations for noise mitigation measures under the Planning Study including the setback distance and/ or non-openable windows/ maintenance window that are not opened for ventilation facing the road networks, use of non-sensitive structure and building orientation have been adopted and summarized in Table 5.7 below. Figure 227724/E/2000 illustrates the recommendations and the assumed building layout plans within ARQ are for assessment purpose.
Table 5.7: Recommended noise mitigation
measures in RODP
Zone |
Recommendations |
R2-1,
R2-2, R2-3, R2-5 |
5m building setback |
R2-6 |
8m building setback |
R2-7
(facing north) |
8m building setback |
R2-7
(facing east) |
8m building setback; Proper building layout; Use of architectural fins; and Non-openable windows/ maintenance window that are not opened for ventilation |
R2-8
(facing north) |
8m building setback; Proper building layout; Use of architectural fins; Non-openable windows/ maintenance window that are not opened for ventilation; and Absorptive type balcony |
R2-8 (facing
east) |
8m building setback |
R2-9&10 |
8m building setback; Proper building layout; Use of architectural fins; Non-openable windows/ maintenance window that are not opened for ventilation; and Absorptive type balcony |
RS-1 |
10m building setback |
E-1 |
Proper orientation of L-shaped standard design school layout; Use of non-sensitive structure for noise screening; and Provision
of non-openable windows/ maintenance window that are not opened for
ventilation (no specific location of non-openable windows/
maintenance window that are not opened for ventilation
in Planning Study) |
E-2 |
Proper orientation of L-shaped standard design school layout; Use of non-sensitive structure for noise screening; and Non-openable windows/ maintenance window that are not opened for ventilation |
Note:
[1] All the building setback is measured from the nearest site boundary.
5.3.6 The existing and planned
NSRs in the vicinity, which may be affected within the Study Area of ARQ are
identified and summarized in Table 5.8 and
illustrated in Figures 227724/E/2010-2040. Photos showing the
existing NSRs are given in Appendix 5.1.
Table 5.8: Existing and planned NSRs
Location |
NSR ID. |
Land Use[1] |
Potential
Impact[2] |
Intake Year |
ARQ – Planned |
||||
Development of Anderson Road Quarry |
R2-1 – R001 ~
R005 |
R |
R |
2026 |
R2-1 – R006 |
R |
F |
2026 |
|
R2-2 – R002 ~
R012 |
R |
R |
2026 |
|
R2-2 – R013 |
R |
F |
2026 |
|
R2-3 – R001 ~ R009 |
R |
R |
2026 |
|
R2-4 – R001 ~ R009 |
R |
R |
2026 |
|
R2-5 – R001 ~ R009 |
R |
R |
2026 |
|
R2-6 – R001 ~ R010 |
R |
R |
2026 |
|
R2-6 –
R010 |
R |
F |
2026 |
|
R2-7 – R001 ~ R004, R007 ~ R011 |
R |
R |
2026 |
|
R2-7 –
R009 ~ R010 |
R |
F |
2026 |
|
R2-8 – R003 ~ R010, R013 ~ R014, R016 ~ R019, R022 |
R |
R |
2022 |
|
R2-8 –
R010 |
R |
C, R |
2022 |
|
R2-8 –
R009, R016 |
R |
F |
2022 |
|
R2-9&10 – R001 ~ R003, R005 ~ R006, R008, R011 ~ R019 |
R |
R |
2022 |
|
R2-9&10
– R001 |
R |
C |
2022 |
|
RS-1 – R001 ~ R010 |
R |
R |
2022 |
|
RS-1 –
R001 |
R |
F |
2022 |
|
RS-1 –
R008 |
R |
C, R |
2022 |
|
E-1 – R002 ~ R003 |
E |
R |
2026 |
|
E-2 – R001 ~
R002 |
E |
R |
2022 |
|
E-2 –
R003 |
E |
C |
2022 |
|
E-3 – R001 ~ R002 |
E |
R |
2026 |
|
DAR – Under Construction |
||||
Development
at Anderson Road |
Site A&B – R102 ~ R906 |
R |
R |
2016 |
Site
A&B – R203 |
R |
C, F |
2016 |
|
Site
A&B – R803 |
R |
C |
2016 |
|
Site
A&B – R903 |
R |
C |
2016 |
|
Site A&B –
School 01 |
E |
C, R, F |
Unknown at this stage [4] |
|
Site A&B – School 02 |
E |
R |
Unknown at this stage |
|
Site C1 – R1001 ~ R1105 |
R |
R |
Unknown at this stage |
|
Site C2 – R101 ~ R103 |
R [3] |
R |
Unknown at this stage |
|
Site C2 – R102 |
R [3] |
C |
Unknown at this stage |
|
Site C2 –
School 02 ~ 04 |
E |
R |
Unknown at this stage |
|
Site C2 –
School 05 |
E |
C, R |
Unknown at this stage [4] |
|
Site E – R501 ~ R1004 |
R |
R |
2015 |
|
Site E –
R502, R604, R803, R904, R1003 |
R |
C |
2015 |
|
Site E – School |
E |
C, R |
2015 |
|
Existing |
||||
Lung Wo Tsuen |
CYCS – 01 |
W |
R |
- |
Lung Wo Tsuen 01
~ 02 |
R |
R |
- |
|
Tan Shan Tsuen |
TSV-01 |
R |
R |
- |
Anderson Road |
Leighton
Pavilion 01 ~ 02 |
R |
R |
- |
Ma Yau Tong Village |
Fat Yuen Temple |
W |
R |
- |
Haven of Hope Sunnyside School |
E |
R |
- |
|
Ma Yau Tong Village |
R |
C, R |
- |
|
Ma Yau Tong Village No.1 |
R |
C, R |
- |
|
Missionary Society of St. Columban |
W |
R |
- |
|
Sau Mau Ping Estate |
Holm Glad
Primary School 01 ~ 02 |
E |
R |
- |
Sau Ching House 01 ~ 02 |
R |
R |
- |
|
Sau Fai House |
R |
R |
- |
|
Sau Hong House |
R |
R |
- |
|
Sau Lok House |
R |
R |
- |
|
Sau Nga House 01 ~ 02 |
R |
R |
- |
|
Sau Yee House 01 ~ 02 |
R |
R |
- |
|
Sau Yin House 01 ~ 02 |
R |
R |
- |
|
Sau Ming
Primary School 01 ~ 02 |
E |
R |
- |
|
Shun Lee Estate |
Lee Foo House 01 ~ 02 |
R |
R |
- |
Shun Lee General Out-patient Clinic |
C |
R |
- |
|
Shun Tin Estate |
Ning Po No.2 College |
E |
R |
- |
Tin Wan House 01 ~ 02 |
R |
R |
- |
|
Po Tat Estate |
Kwun Yam Temple |
W |
R |
- |
Planned City God Temple |
W |
R |
- |
|
Planned Monkey King Temple |
W |
R |
- |
|
Sau Mau Ping
Catholic Primary School 01 ~ 02 |
E |
C, R |
- |
|
Tat Cheung House 01 |
R |
R |
- |
|
Tat Cheung House 02 |
R |
C |
- |
|
Tat Chui House |
R |
R |
- |
|
Tat Fung House |
R |
R |
- |
|
Tat Hong House 01 ~ 02 |
R |
R |
- |
|
Tat Yan House |
R |
C, R |
- |
|
Tat Yi House |
R |
R |
- |
|
Tin Hau Temple |
W |
R |
- |
Notes:
[1] R – Residential Premises, E – Educational Institutions, W – Places of Public Worship, C – Clinic
[2] C – Construction Airborne Noise, R – Operational Road Traffic Noise, F – Operational Fixed Noise
[3] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
[4] As there is no confirmed intake programme of the schools, worst-case scenario of assuming the schools will be occupied during the construction period is therefore adopted for assessment purpose.
5.4
Potential Concurrent Projects
5.4.1 In order to assess the cumulative impacts, it is critical to identify
the implementation programme and details of concurrent projects in the vicinity
that would have an environmental bearing on the noise sensitive receivers for
the Project.
5.4.2 After collating the information available in the public domain (e.g.
approved EIA reports, LegCo paper etc.), the project proponents of these
concurrent projects has been approached to verify the best available
information for incorporation into the report. Referring to Section 3.8, there are four major
concurrent projects including the Development at Anderson Road (DAR); Road
improvement works at J/O Lin Tak Road and Sau Mau Ping Road, at J/O New Clear
Water Bay Road and Anderson Road, as well as at the merging lane at Clear Water
Bay Road near Shun Lee Tsuen Road; proposed rock cavern development within ARQ
and pedestrian connection. Locations of
the concurrent projects are shown in Figure
227724/E/0008. Each concurrent
project is discussed in the following.
5.4.3 DAR is located in the East Kowloon District. It is bounded by Anderson
Road to the north, the realigned Sau Mau Ping Road to the south, Po Lam Road to
the east, and Lee On Road and Shun On Road to the west. The scope of works of
DAR includes construction of site formation, roads, drains and upgrading of
existing infrastructure to provide usable land of about 20 hectares for housing
and associated government, institution or community uses at the site between
existing Anderson Road Quarry and Sau Mau Ping Road in Kwun Tong District. The construction works of DAR has commenced
in early-2008 and is scheduled for completion in early 2017 according to the
latest programme advised by Housing Department. As mentioned in Section 3.8, the tentative major construction work of ARQ is
envisaged to commence in mid 2016. Although there may have half year
overlapping period from late 2016 to early 2017, the major construction works
of DAR including site formation and building foundation would be completed in
2016, and the remaining works would be minor building works which construction noise is minimal. The cumulative construction noise impact
arising from the minor building works of DAR should be minimal.
5.4.4 Road improvement works at J/O Lin Tak Road and Sau Mau Ping Road, at J/O
New Clear Water Bay Road and Anderson Road, as well as at the merging lane at
Clear Water Bay Road near Shun Lee Tsuen Road are located outside the 300m
assessment area of Study Area and would also blocked by the high-rising
buildings in the vicinity. Hence, these
improvement works are considered insignificant.
5.4.5 The proposed rock cavern with the ARQ and proposed vertical transfer
system are located within the 300m assessment area and hence has been assessed
in the cumulative impact.
5.4.6 The cumulative impacts have been considered during the operational phase
of the project. The impacts from the
committed roads and the impacts to the committed NSRs have been addressed in this
report.
Construction
Phase - Construction Noise
5.5.1 The construction noise impact assessment during daytime, on weekdays
other than general holidays have been assessed in accordance with the
methodology in paragraphs 5.3 and 5.4 of Annex 13 of the TM.
5.5.2 Construction noise assessment has been conducted based on the following procedures:
(1) Determine the assessment area, and identify representative NSRs that may be affected by the works;
(2) Obtain the construction method and work sequence for the construction period;
(3) Obtain the plant items for each corresponding construction work sequence;
(4) Determine the sound power levels of the plant items according to the information stated in the TM-GW or other recognised sources of reference, where appropriate;
(5) Calculate the correction factors based on the distance between the NSRs and the notional noise source positions of the work sites;
(6) Apply corrections for façade, distance, barrier attenuation, acoustic reflection where applicable;
(7) Quantify the level of impact at the NSRs, in accordance with TM-GW;
(8) Predict the cumulative noise impacts by any concurrent construction works in the vicinity; and
(9)
For any exceedance of noise
criteria, all practical mitigation measures such as alternative construction
methodology, quiet plant, silencer, enclosure, etc, shall be examined to
alleviate the predicted noise impacts as much as practicable.
5.5.3 Consideration of noise mitigation measures follows Annex 13 of TM-EIAO
and EIAO Guidance Note “Preparation of Construction Noise Impact Assessment
under the Environmental Impact Assessment Ordinance” [GN 9/2010].
5.5.4 As there is no construction activities related to the use of tunnel
boring machine, construction groundborne noise impacts are not anticipated.
Scenarios
5.5.5 The construction noise assessment would include the following scenarios:
(1) Unmitigated scenario (Construction noise impacts without any mitigation measures); and
(2) Mitigated scenario (Construction noise impacts after implementing practicable mitigation measures such as movable barrier, enclosure, etc).
5.5.6 Both the unmitigated and mitigated scenarios would consider the implementation
strategy.
Prediction of Noise
Impact
5.5.7 The predicted construction noise levels in Leq (30 min) dB(A)
at the selected assessment points have been presented in tables and plans of
suitable scale.
Mitigation of
Construction Noise Impact
5.5.8 Where the predicted construction noise impact exceeds the criteria set
in Table 1B of Annex 5, TM, direct mitigation measures including noise
barriers, enclosures, quieter alternative methods, re-scheduling, restricting
hours of operation of noisy tasks, etc. have been adopted. The feasibility,
practicability, programming and effectiveness of the recommended mitigation
measures have been confirmed by Civil Engineer and stated in this report.
Construction Noise Assessment
Tool
5.5.9 An in-house program has been used for construction noise calculations. Initially, the program runs were conducted without any mitigation measures (i.e. the “Unmitigated Scenario”). Where noise level exceedance was identified, further runs would be made assuming different combinations of mitigation measures to be incorporated (i.e. the “Mitigated Scenario”).
Operational Phase – Road Traffic Noise
5.5.10 The calculation method stated in the UK Department of the Transport
"Calculation of road Traffic Noise" (CRTN) would be adopted. The
predicted noise levels at the building facades include 2.5dB(A) facade
reflection and correction factors for effects due to gradient, distance, view
angle, road surface and barriers.
5.5.11 In the preparation for noise prediction, the project road scheme and
surrounding road networks within the Study Area have been included in the model
with parameters of road width, surface type, and traffic condition.
5.5.12 The future road traffic noise has been calculated based on the peak hour
traffic flow in respect of maximum traffic projection within the next 15 years
upon commencement of operation of the Project.
Scenarios
5.5.13 The road traffic noise impact assessment of the Project has been
conducted with respect to the criteria set in Annex 5 of the TM (i.e. refer to Section 5.1 for details).
5.5.14 The road traffic noise model adopted in the EIA include following
scenarios:
(1) Unmitigated scenario at assessment year;
(2) Mitigated scenario at assessment year; and
(3) Prevailing scenario for indirect mitigated measures eligibility assessment.
5.5.15 The assessment year of unmitigated and mitigated scenarios which is the
future road traffic noise shall be calculated based on peak hour traffic flow
in respect of maximum traffic projection within the next 15 years upon
commencement of operation of the Project, i.e. 2026 + 15 = 2041. The noise assessment for prevailing year
would adopt the year before the commencement of road construction works, i.e. 2016
– 1 = 2015. The traffic data adopted in
the EIA study has been endorsed by Transport Department on 25 September 2013
and given in Appendix 5.2.
Prediction of Noise Impact
5.5.16 The predicted noise levels in L10 (1 hour) dB(A) at the
selected assessment points at various representative floor levels (in mPD) have
been presented on tables and plans of suitable scale.
5.5.17 The assessment covers the cumulative road traffic noise impact resulting
from road traffic noise due to the Project and existing road network on
existing, committed and planned NSRs within the assessment area.
5.5.18 The total number of dwellings, classrooms and other noise sensitive
receivers that would be exposed to noise impact exceeding the criteria set in
Annex 5 in the TM have been quantified.
Consideration of Noise
Mitigation Measures
Direct Mitigation Measures
5.5.19 Consideration of noise mitigation measures follows Annex 13 of TM-EIAO
and EIAO Guidance Note “Road Traffic Noise Impact Assessment under the
Environmental Impact Assessment Ordinance” [GN 12/2010].
5.5.20 Where the predicted noise impact exceeds the noise criteria, direct
mitigation measures shall be considered on the project road to reduce the noise
from the project road to a level that it
(1) Is not higher than the standard; and
(2) Has no significant contribution to the overall noise from other existing roads, if the cumulative noise level, i.e. noise from the new road together with other existing roads exceeds the standard (i.e. not more than 1.0 dB(A))
5.5.21 Where the predicted road traffic noise impact exceeds the criteria set
in Table 1B of Annex 5, TM, direct mitigation measures including screening by
noise tolerant buildings, etc. have been adopted. The feasibility,
practicability, programming and effectiveness of the recommended mitigation
measures have been confirmed by Civil Engineer and stated in this report.
5.5.22 Where necessary, noise mitigation measures such as building setback and
building orientation for planned NSRs have been proposed to minimise noise
impact during the operation of the Project.
For the planned residential premises, mitigation measures have been
proposed such that the noise criterion is achieved.
5.5.23 The total numbers of NSRs that would be benefited from and be protected by
direct mitigation measures have been provided. The total numbers of other noise
sensitive receivers that would still be exposed to noise above the criteria
with the implementation of all recommended direct mitigation measures have been
quantified.
5.5.24 The environmental requirements / constraints identified in the EIA study
to assess the development potential of concerned sites would be made known to
the relevant parties.
Indirect Mitigation
Measures
5.5.25 According to EPD’s Guidance Note 12/2010, in the case where NSRs are
still exposed to noise levels exceeding the relevant noise criteria after the
implementation of all direct mitigation measures, the total number of existing
dwellings, classrooms and other noise sensitive elements which may qualify for
indirect technical remedies, the associated costs and any implications for such
implementation should be identified and estimated. The eligibility of the affected premises for
indirect technical remedies is determined with reference to the following three
criteria:
(1) the predicted overall noise level must be above a specified noise level (e.g. 70 dB(A) for domestic premises and 65 dB(A) for education institutions, all in L10,1hr);
(2) the predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level, i.e. the total traffic noise level existing before the works to construct the road were commenced; and
(3) the contribution to the increase in the predicted overall noise level from the road project must be at least 1.0dB(A).
5.5.26 For planned noise sensitive uses which are also subject to potential road traffic noise impacts, the overall noise levels for maximum projected traffic within 15 years has been predicted. In the case where the planned NSRs are exposed to excessive noise levels, direct mitigation measures shall be proposed to ensure compliance of the relevant noise criteria.
Operational
Phase – Fixed Plant Noise
5.5.27 The following general procedures in accordance with methodology in
paragraph 5.2 of Annex 13 of the TM have been adopted for the operation noise
assessment.
(1) Identify and locate representative NSRs that may be affected by the noise sources;
(2) Determine the noise criteria for both daytime and night-time;
(3) Use standard acoustic principle for attenuation and directivity;
(4)
Determine the maximum sound power levels (SWLs) of the fixed noise
sources identified during EIA
study; and
(5) Cumulative impacts will be included, if any.
5.5.28 The assessment has been based on the best available information during
the preparation of EIA process. However, given the nature of the study, some of
the detailed information may not be available by the time of EIA preparation.
In such case, maximum sound power levels (SWLs) of the fixed noise sources has
been predicted.
Prevailing Background
Noise Levels
5.5.29 The proposed noise criterion depends on the prevailing noise level. The locations of prevailing noise measurement
are illustrated in Figure 227724/E/2050. Consideration of its transient and impulsive
characteristics has been taken into account.
5.5.30 The DAR is under construction, which construction noise would be the
dominated noise source in ARQ. In order to determine the future noise climate
of ARQ, prevailing background noise levels have been measured in the vicinity
of the Study Area in January 2013. The environment of the selected monitoring
locations are considered similar to future ARQ, the measured noise level was
then be used to determine noise criteria.
A summary of the noise measurement results are given in the Table 5.9.
Table 5.9:
Prevailing background noise measurements
Monitoring Location [3] |
Prevailing Background
Noise Levels[1], dB(A) |
||
Day[2] |
Evening[2] |
Night[2] |
|
Shun
Lee Estate (PNM-1) |
58 - 59 |
56 - 57 |
49 - 50 |
Shun
Tin Estate (PNM-2) |
59 |
53 - 54 |
50 |
Sau
Mau Ping Estate (PNM-3) |
65 - 66 |
63 - 65 |
60 - 61 |
Po
Tat Estate (PNM-4) |
59 - 61 |
58 - 60 |
54 - 55 |
Notes:
[1] Measurements conducted in January 2013.
[2] Day: 0700 – 1900 hours, Evening: 1900 – 2300 hours, Night: 2300 – 0700 hours.
[3] PNM represents prevailing background noise measurement location.
5.5.31 The proposed noise criteria at representative NSRs due to general fixed
plant noise sources are summarized in Table
5.10.
Table
5.10:
Proposed noise criteria at
representative NSRs due to fixed plant sources
No. |
NSR |
ANL – 5, dB(A)[1] |
Background Noise Level,
dB(A) |
Criteria, LAeq (30
min) dB(A) |
Reference Location |
|||
Day & Evening |
Night |
Day & Evening [2] |
Night |
Day & Evening |
Night |
|||
R2-1 ~
R2-7 |
Planned Residential Buildings at ARQ |
60 |
50 |
56 |
49 |
56 |
49 |
PNM-1 |
R2-8 ~
R2-10 |
Planned Residential Buildings at ARQ |
60 |
50 |
58 |
54 |
58 |
50 |
PNM-4 |
E-1 |
Planned Schools at ARQ |
60 |
50 |
56 |
49 |
56 |
49 |
PNM-1 |
E-2, E-3 |
Planned Schools at ARQ |
60 |
50 |
58 |
54 |
58 |
50 |
PNM-4 |
Site A,
B, C1 |
Planned Public Housing at DAR |
60 |
50 |
53 |
50 |
53 |
50 |
PNM-2 |
Site E |
Planned Public Housing at DAR |
60 |
50 |
63 |
60 |
60 |
50 |
PNM-3 |
Notes:
[1] An Area Sensitivity Rating of “B” is assumed for NSRs at “Others Area” which do not have any IF in the vicinity.
[2] Lowest background noise among day and evening time is adopted.
5.6
Construction Noise Assessment
Inventory of Noise Sources
5.6.1 Despite the construction methodologies are yet to be established, it is anticipated that the major construction works would include the following activities:
(1) Site clearance and formation activities;
(2) Internal roads;
(3) Installation of utilities; and
(4) Superstructure.
Phases of Construction
5.6.2 Given the scale of development, it is anticipated that the Project has
been implemented in phases. This phasing strategy would depend on a number of
considerations. This landuse option and its implementation strategy would form
the implementation assumption for the construction noise assessment. The
construction workfronts showing the construction of ARQ and new access roads
are shown in Appendix 5.3.
5.6.3 These construction activities would be carried out with the use of Powered
Mechanical Equipment (PME) including breakers, pipe pile rigs, excavators,
lorries, mobile cranes, concrete pumps, concrete mixers, pokers, rollers, etc. The
types of PME adopted are listed in Appendix
5.3.
5.6.4 The utilization rates, which have been reviewed by the Project Engineer, are also presented in Appendix 5.3. In practice, the PME would not be operating at all times within a work site. However, the following construction noise assessment would demonstrate a worst case scenario. The construction plant inventory used in the assessment has been confirmed to be representative of the works by the project proponent.
Assessment Results - Unmitigated Scenario
5.6.5 According to the latest
engineering design, the construction works would mainly comprise of the
activities as described in Section 3.6. The corresponding Sound Power Levels (SWLs)
of these activities have been estimated according to the PME’s SWLs and the
assessment methodology in the GW-TM. Appendix 5.4 presents the PME inventory adopted in construction works area of ARQ. Appendix 5.5A presents the detailed PME inventory for each works area of ARQ. Appendix 5.5B presents the distance between the notional sources and the NSRs. Appendix 5.5C presents the monthly unmitigated
noise contribution during the construction period. Appendix 5.5D also
presents the unmitigated
construction noise impacts at selected representative NSRs
and the duration of exceedance could be referred to Appendix 5.5D. The predicted construction noise impacts on
the NSRs are summarized in Table
5.11 below.
Table 5.11: Predicted maximum unmitigated
construction
noise
levels
at NSRs
Location |
NSR ID. |
Uses |
Criterion, dB(A)
[1] |
Unmitigated Noise Level, dB(A)
[2] |
Exceedance, dB(A) |
DAR |
Site A&B – R203 |
R |
75 |
71 |
- |
Site A&B – School 01 |
E |
70 (65) |
74 |
4 (9) |
|
Site A&B – R803 |
R |
75 |
75 |
- |
|
Site A&B – R903 |
R |
75 |
79 |
4 |
|
Site C2 – R102 |
R [3] |
75 |
94 |
19 |
|
Site C2 – School 05 |
E |
70 (65) |
91 |
21 (26) |
|
Site E – R502 |
R |
75 |
92 |
17 |
|
Site E – R604 |
R |
75 |
79 |
4 |
|
Site E – R803 |
R |
75 |
79 |
4 |
|
Site E – R904 |
R |
75 |
80 |
5 |
|
Site E – R1003 |
R |
75 |
80 |
5 |
|
Site E – School |
E |
70 (65) |
83 |
13 (18) |
|
Po Tat Estate |
Tat Cheung House |
R |
75 |
85 |
10 |
Sau Mau Ping Catholic Primary School 02 |
E |
70 (65) |
80 |
10(15) |
|
Tat Yan House |
R |
75 |
74 |
- |
|
Ma Yau Tong Village |
Ma Yau Tong Village |
R |
75 |
83 |
8 |
Ma Yau Tong Village No. 1 |
R |
75 |
86 |
11 |
|
ARQ |
R2-9&10 – R001 |
R |
75 |
80 |
5 |
E2-R003 |
E |
70 (65) |
87 |
17 (22) |
|
RS-1 – R008 |
R |
75 |
80 |
5 |
|
R2-8 – R010 |
R |
75 |
79 |
4 |
Notes:
[1] Values in parentheses indicate the noise criterion during examination period of educational institution.
[2] Bolded values mean exceedance of the relevant noise criteria.
[3] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
Mitigation Measures
5.6.6 The predicted construction noise levels show that the unmitigated construction noise impacts would exceed the daytime noise criteria. Mitigation measures are therefore required. The following mitigation measures have been considered:
(1)
Good site
practices to limit noise emissions at the source;
(2)
Use of
quiet plant and working methods;
(3)
Use of
site hoarding as noise barrier to screen noise at ground level of NSRs;
(4)
Use of
shrouds / temporary noise barriers to screen noise from relatively static PMEs;
(5)
Use of
large full enclosure to screen all the plant, wherever practicable;
(6)
Scheduling
of construction works outside school examination periods in critical area; and
(7)
Alternative
use of plant items within one worksite, wherever practicable.
5.6.7 The above mitigation measures would need to be implemented in all work sites as good practices. It should be noted that whilst “Good Practice” mitigation measures would help to alleviate the noise impacts, some of these measures have not be included in the quantitative assessment as discussed in the following sections. This would ensure a more conservative assessment.
5.6.8 Detailed descriptions of
these mitigation measures are given in the following sections.
Good Site Practices and Noise Management Techniques
5.6.9 Good site practice and noise management techniques could considerably reduce the noise impact from construction site activities on nearby NSRs. The following measures should be followed during each phase of construction:
(1)
only well-maintained
plant should be operated on-site and plant should be serviced regularly during
the construction programme;
(2)
machines
and plant (such as trucks, cranes) that may be in intermittent use should be
shut down between work periods or should be throttled down to a minimum;
(3)
plant
known to emit noise strongly in one direction, where possible, be orientated so
that the noise is directed away from nearby NSRs;
(4)
silencers
or mufflers on construction equipment should be properly fitted and maintained
during the construction works;
(5)
mobile
plant should be sited as far away from NSRs as possible and practicable; and
(6) material stockpiles, site office and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
5.6.10 The benefits of these techniques can vary according to specific site conditions and operations. The environmental noise climate would certainly be improved through these control practices, although the improvement can only be quantified during implementation when specific site parameters are known. The assessment has therefore not taken into account the effectiveness of “Good Site Practices and Noise Management Techniques”.
Use of “Quiet” Plant and Working Methods
5.6.11 The use of quiet plant is a feasible solution to tackle noise impacts associated with construction works. It is generally known (supported by field measurement) that particular models of construction equipment are quieter than standard types given in the TM-GW. Whilst it is generally considered too restrictive to specify that the Contractor has to use specific models or items of plant, it is reasonable and practicable to set plant noise performance specifications for specific PME so that some flexibility in selection of plant is allowed. A pragmatic approach would be to request that the Contractor independently verifies the noise level of the plant proposed to be used and demonstrates through furnishing of these results, that the plant proposed to be used on the site meets the requirements.
5.6.12 An inventory of SWLs of quiet plant associated with the construction works is given in EPD’s Quality Powered Mechanical Equipment (QPME) and additional reference is made to typical SWLs for international manufacturer. It should be also noted that while various types of silenced equipment could be found in Hong Kong, EPD when processing a CNP application for evening or night time works may apply the noise levels specified in the TM-GW and TM-DA. CNP applications which contain sufficient details of any particularly quiet items of PME or any special noise control measures which the CNP applicant proposes to employ on the site may be given special consideration by the Noise Control Authority.
5.6.13 A summary of the “Quiet” PMEs adopted and the associated SWLs is given in Appendix 5.4.
Use of Site Hoarding
5.6.14 Purpose built temporary noise barriers (approximately 2.5m high) located on the site boundaries between noisy construction activities and NSRs could generally reduce noise levels at low-level zone of NSRs through partial screening. In general, this would provide minimum 5 dB(A) attenuation for the low level receivers. It would be possible for the Contractor to provide these in the form of site hoardings to achieve this attenuation effect, provided that the barriers have no openings or gaps. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period. For conservative assessments, however, the site hoarding has not been taken into consideration in the construction noise assessments.
Use of Temporary Noise Barrier & Enclosure (with
Sufficient Ventilation)
5.6.15 Movable temporary noise barriers that can be located close to noisy plant and be moved concurrently with the plant along a worksite can be very effective for screening noise from NSRs. A typical design which has been used locally is a wooden framed barrier with a small-cantilevered on a skid footing with 25mm thick internal sound absorptive lining. This measure is particularly effective for low level zone of NSRs. A cantilevered top cover would be required to achieve screening benefits at upper floors of NSRs.
5.6.16 Movable barriers would be used for some PME (e.g. asphalt paver, excavator etc). It is anticipated that suitably designed barriers could achieve at least 5 - 10dB(A) reduction. For a conservative assessment, only a reduction of 5dB(A) is assumed. Acoustic mat would be used for other plant items such as trench cutter, piling, oscillator and drilling rig and a 10 dB(A) noise reduction is anticipated. Barrier material with surface mass at least 7kg/m2 is recommended to achieve the predicted screening effect. This assumption has been adopted in other approved EIA Reports.
5.6.17 The use of enclosure (with sufficient ventilation and surface mass at least 10 kg/m2) has been considered in this assessment to shelter relatively static plant including air compressor, generator. The enclosures barriers can provide about 10dB(A) noise reduction.
5.6.18 A summary of the temporary movable barriers and enclosures adopted for various PMEs, and the associated noise reduction is given in Appendix 5.4 and summarised in Table 5.12 below. Appendix 5.6 shows the sketch of typical temporary noise barrier / enclosure.
Table 5.12:
Summary of barrier and noise enclosure adopted for PMEs
PME |
Enclosure / Shed / Silencer / Barriers
/ Acoustic Mat |
Attenuation, dB(A) |
Air compressor |
Enclosure / Shed |
-10 |
Asphalt paver |
Movable Barriers |
-5 |
Bar bender, cutter |
Movable Barriers |
-5 |
Breaker, handheld |
Movable Barriers |
-5 |
Breaker |
Movable Barriers |
-5 |
Breaker, excavator mounted (pneumatic) |
Movable Barriers |
-5 |
Breaker, excavator mounted (Hydraulic) |
Movable Barriers |
-5 |
Bulldozer |
Movable Barriers |
-5 |
Concrete lorry mixer |
Movable Barriers |
-5 |
Water truck |
Movable Barriers |
-5 |
Concrete pump |
Movable Barriers |
-5 |
Mobile crane |
Movable Barriers |
-5 |
Tower crane |
Movable Barriers |
-5 |
Truck |
Movable Barriers |
-5 |
Dump truck |
Movable Barriers |
-5 |
Backhoe |
Movable Barriers |
-5 |
Excavator |
Movable Barriers |
-5 |
Generator |
Enclosure / Shed |
-10 |
Piling, large bored pile |
Acoustic Mat |
-10 |
Piling machine |
Acoustic Mat |
-10 |
Vibratory poker |
Movable Barriers |
-5 |
Rock drill, crawler mounted (hydraulic) |
Movable Barriers |
-5 |
Roller |
Movable Barriers |
-5 |
Roller, vibratory |
Movable Barriers |
-5 |
Saw, circular, wood |
Movable Barriers |
-5 |
Ventilation fan |
Enclosure with silencer system |
-15 |
Water pump |
Enclosure / Shed |
-10 |
Sequencing Operation of Construction Plant Equipment
5.6.19 In practice, some plant
items would operate sequentially
within the same work site, and certain reduction of the predicted noise impacts
could be achieved. However, any
additional control on the sequencing of plant would impose a restrictive constraint to the Contractor on the operation
and planning of plant items, and the implementation of the requirement would be
difficult to be monitored. Hence,
sequencing operation of PME has not been taken into consideration in the construction
noise assessments.
Assessment Results - Mitigated Scenario
5.6.20 With the implementation of
the abovementioned mitigation measures, the construction noise levels at the
affected NSRs are predicted. The
predicted noise levels at most of the NSRs would comply with the corresponding
noise criteria, except some NSRs near the works area at Road
L4 of ARQ.
Non-compliance at these NSRs is due to the shorter separation distance
between the worksites. Appendices 5.5E present the
mitigated noise contribution on a monthly basis during the construction
period. Appendices 5.5F present the predicted mitigated construction noise levels at
selected representative NSRs. The predicted construction noise impacts on the
NSRs are summarized in Table
5.13 below.
Table 5.13: Predicted maximum mitigated construction noise levels at NSRs
Location |
NSR ID. |
Uses |
Criterion, dB(A)
[1] |
Mitigated Noise
Level, dB(A) [2] |
Exceedance, dB(A) |
DAR |
Site A&B – R203 |
R |
75 |
59 |
- |
Site A&B – School 01 |
E |
70 (65) |
61 |
- |
|
Site A&B – R803 |
R |
75 |
61 |
- |
|
Site A&B – R903 |
R |
75 |
63 |
- |
|
Site C2 – R102 |
R [3] |
75 |
77 |
2 |
|
Site C2 – School 05 |
E [4] |
70 (65) |
74 |
4 (9) |
|
Site E – R502 |
R |
75 |
77 |
2 |
|
Site E – R604 |
R |
75 |
67 |
- |
|
Site E – R803 |
R |
75 |
67 |
- |
|
Site E – R904 |
R |
75 |
69 |
- |
|
Site E – R1003 |
R |
75 |
67 |
- |
|
Site E – School |
E |
70 (65) |
68 |
0 (3) |
|
Po Tat Estate |
Tat Cheung House |
R |
75 |
70 |
- |
Sau Mau Ping Catholic Primary School 02 |
E |
70 (65) |
65 |
- |
|
Tat Yan House |
R |
75 |
61 |
- |
|
Ma Yau Tong Village |
Ma Yau Tong Village |
R |
75 |
66 |
- |
Ma Yau Tong Village No. 1 |
R |
75 |
68 |
- |
|
ARQ |
R2-9&10 – R001 |
R |
75 |
66 |
- |
E2-R003 |
E |
70 (65) |
73 |
3 (8) [5] |
|
RS-1 – R008 |
R |
75 |
66 |
- |
|
R2-8 – R010 |
R |
75 |
68 |
- |
Notes:
[1] Values in parentheses indicate the noise criterion during examination period of educational institution.
[2] Bolded values mean exceedance of the relevant noise criteria.
[3] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
[4] As there is no confirmed intake programme of the school, worst-case scenario of assuming the school will be occupied during the construction period is therefore adopted for assessment purpose.
[5] Refer to Table 5.14 and Table 5.15 for details.
Residual Noise Impact from the Project Exceeding the Construction Noise Criterion
5.6.21 As discussed above, even with all practicable construction noise mitigation measures adopted, such as the use of quiet PME, temporary movable noise barrier and enclosure, residual impacts exceeding the construction noise criterion are still expected at some NSRs, as summarized in Table 5.14 below. Only those NSRs with residual construction noise impact from the Project exceeding the construction noise criterion are shown.
Table 5.14: Residual impacts at noise sensitive receivers
NSR ID |
Uses |
Criterion, dB(A)
[1] |
Maximum Mitigated Noise Level, dB(A) |
Exceedance, dB(A) |
Site C2 – R102 |
R [3] |
75 |
77 |
2 |
Site C2 – School 05 |
E [4] |
70 (65) |
74 |
4 (9) |
Site E – R502 |
R |
75 |
77 |
2 |
Site E – School |
E |
70 (65) |
68 |
0 (3) |
E2 – R003 |
E |
70 (65) |
73 |
3 (8) [5] |
Notes:
[1] Values in parentheses indicate the noise criterion during examination period (typical examination period in May, June, November and December) of educational institution.
[2] Values in parentheses indicate the duration of residual impact in consideration of the noise criterion during examination period.
[3] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
[4] As there is no confirmed intake programme of the school, worst-case scenario of assuming the school will be occupied during the construction period is therefore adopted for assessment purpose.
[5] Please refer to Table 5.16 and Table 5.17 for the total impact duration for noise exceedance.
5.6.22 The above table indicates that the maximum residual impacts and the associated duration despite of the implementation of all practicable noise mitigation measures.
5.6.23 Extensive mitigation measures have been considered and implemented exhaustively to abate construction noise impacts on neighbouring NSRs. These mitigation measures include but not limited to the use of quiet construction plant, movable noise barrier, noise enclosure, acoustic mat etc. With all the mitigation measures implemented, assessment results indicate that the majority of the NSRs would comply with the noise criteria in TM-EIAO.
5.6.24 Two planned NSRs (residential) would exceed the noise criteria, one NSR (Site C2 – R102) is located close to the Road L4 of ARQ and the other NSR (Site E – R502) is located close to the proposed vertical transfer system A would have residual construction noise impact. It should be noted that all of these receivers would only exceed the relevant noise criteria by less than 5dB(A) as shown in Table 5.15 below. However, it should be noted that the impact duration for noise exceedance for these two residential uses would be 9-10 months out of the whole construction period of mid 2016 to 2026, i.e. around 125 months. The duration of exceedance could be referred to Appendix 5.5F.
Table 5.15: Residual noise impacts (residential premises)
NSR-ID |
Impact
Duration (Month) for Noise Exceedance |
|
1 dB(A) |
2 dB(A) |
|
Site C2 – R102 |
8 |
2 |
Site E – R502 |
- |
9 |
5.6.25 Three planned NSRs (educational institution) closer would exceed the noise criteria, one NSR (Site C2 – School 05) is located close to the Road L4 of ARQ, the one NSR (Site E – School) is located close to the proposed vertical transfer system B would have residual construction noise impact and one NSR (E-2 – R003) is located close to the construction site of ARQ E-2. It should be noted that only Site C2 – School 05 would exceed the relevant noise criteria by only 1dB(A) during normal period as shown in Table 5.16 below. However, it should be noted that the impact duration for noise exceedance during normal period for these two educational institutions would be 6-13 months out of the whole construction period of mid 2016 to 2026, i.e. around 125 months. The duration of exceedance could be referred to Appendix 5.5F.
Table 5.16: Residual
noise
impacts
(educational
institution
during
normal
period)
NSR-ID |
Impact
Duration (Month) for Noise Exceedance |
||
1dB(A) |
2dB(A) |
3dB(A) |
|
Site C2 – School 05 [1] |
- |
- |
6 |
Site E – School |
- |
- |
- |
E-2 – R003 |
8 |
4 |
1 |
Note:
[1] As there is no confirmed intake programme of the school, worst-case scenario of assuming the school will be occupied during the construction period is therefore adopted for assessment purpose.
5.6.26 Further analysis has also been conducted to evaluate the potential noise impacts by adopting the noise criterion for examination period. It can be seen that a number of the schools along the alignment would be affected by construction noise during their examination periods. For assessment purpose, it is assumed that examination periods would be in May, June, November and December. The duration for construction noise impacts with exceedance during the school examination periods is shown in Table 5.17 below. However, it should be noted that the impact duration for noise exceedance during examination period for these three educational institutions would be 6-8 months out of the whole construction period of mid 2016 to 2026, i.e. around 125 months. The duration of exceedance could be referred to Appendix 5.5F.
Table 5.17: Residual noise impacts (educational institution during examination period) [1]
NSR-ID |
Impact
Duration (Month) for Noise Exceedance |
||||||||
1dB(A) |
2dB(A) |
3dB(A) |
4dB(A) |
5dB(A) |
6dB(A) |
7dB(A) |
8dB(A) |
9dB(A) |
|
Site C2 – School 05 [2] |
- |
2 |
- |
- |
- |
- |
- |
2 |
2 |
Site E – School |
6 |
- |
2 |
- |
- |
- |
- |
- |
- |
E-2 – R003 |
- |
- |
- |
- |
- |
2 |
2 |
2 |
- |
Notes:
[1] Typical examination period in May, June, November and December.
[2] As there is no confirmed intake programme of the school, worst-case scenario of assuming the school will be occupied during the construction period is therefore adopted for assessment purpose.
Evaluation of Residual Impact
Road L4 of ARQ
5.6.27 The noise impacts on Site C2 – R102 would only exceed the relevant noise criteria up to 2dB(A). The number of months of noise impact with exceeding the relevant noise criteria by less than or equal to 2dB(A) would be 10 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months. It should be noted that the separation distance of Site C2 – R102 is about 10m from the construction site which make it experiencing the residual construction noise impact despite all practical mitigation measures have been implemented.
5.6.28 The noise impacts on Site C2 – School 05 would only exceed the relevant noise criteria during normal period of 3dB(A). The number of months that would be exposed to 3dB(A) above the relevant criteria would be 6 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months. The number of months of noise impact with exceeding the relevant noise criteria during examination by less than or equal to 9dB(A) would be 6 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months. It should be noted that the separation distance of Site C2 – School 05 is about 15m from the construction site which make it experiencing the residual construction noise impact despite all practical mitigation measures have been implemented.
Proposed Vertical Transfer System A
5.6.29 The noise impacts on Site E – R502 would only exceed the relevant noise criteria up to 2dB(A). The number of months of noise impact with exceeding the relevant noise criteria by 2dB(A) would be 9 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months. It should be noted that the separation distance of Site E – R502 is about 20m from the construction site which make it experiencing the residual construction noise impact despite all practical mitigation measures have been implemented.
Proposed Vertical Transfer System B
5.6.30 The noise impacts on Site E – School would not exceed the relevant noise criteria during normal period. However, the number of months of noise impact with exceeding the relevant noise criteria during examination by 1dB(A) and 3dB(A) would be 6 and 2 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months respectively. It should be noticed that construction activity contributing noise impact with exceeding the relevant noise criterion is the piling and superstructure of the proposed vertical transfer system B where located next to this sensitive receiver. The number of PME used has been reviewed as practicable for the construction programme, the dominate noise source would be concrete lorry mixer, dump truck and rock drill for the construction works, mitigation measures including use of quiet plant and movable noise barrier have already been applied on this construction activity.
Development of Anderson Road Quarry
5.6.31 The noise impacts on E-2 – R003 would only exceed the relevant noise criteria during normal period of less than or equal to 3dB(A). The number of months that would be exposed to 1dB(A), 2dB(A) and 3dB(A) above the relevant criteria would be 8, 4 and 1 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months respectively. The number of months of noise impact with exceeding the relevant noise criteria during examination by less than or equal to 8dB(A) would be 6 months out of whole construction period of mid 2016 to 2026, i.e. around 125 months. It should be noted that the separation distance of E-2 – R003 is about 25m from the construction site which make it experiencing the residual construction noise impact despite all practical mitigation measures have been implemented.
Summary of Residual Impact
5.6.32 All the practicable mitigation measures including use of quiet plant, acoustic mat, insulation fabric, movable noise barrier and scheduling of works have already been applied and exhausted on these construction activity. Hence, the residual noise impacts have been minimized. In general practice, examination period should only last for 2 weeks. By scheduling the construction works to avoid the examination period, the residual impact should be minimised.
5.6.33 To further reduce the noise impacts, it is proposed the Contractor should closely liaise with the school to avoid noisy construction works during examination period. The construction works should be carried out at summer holiday as far as possible.
5.6.34 Moreover, to further mitigate the construction noise impact along the Road L4, it is proposed to implement a temporary noise barrier during the construction stage. In order to maximize the possibility of enhancing its performance in noise screening, it is suggested to have the top section cantilevered towards the construction site, and the material to be used for the noise barrier should achieve a minimum surface density of 7kg/m2. The exact extent of the temporary noise barriers would be adjusted to suit the need for construction activities and should be implemented as far as practicable. Figure 227724/E/2100 illustrates the indicative extent of temporary noise barrier.
5.6.35 Furthermore, the construction noise level at designated monitoring locations after implementation of the proposed mitigation measures shall be monitored as stipulated in the EM&A Manual.
5.7
Road Traffic Noise Assessment
Inventory of Noise Sources
5.7.1 During the operational phase, road traffic could cause traffic noise
impact on the NSRs within and in the vicinity of the Study Area, such as Sau
Mau Ping Road, Po Lam Road, etc. Road sections for the purpose of road traffic
noise impact assessment have been presented and confirmed with EPD prior to the
commencement of the assessment. For the purpose of the assessment, roads have
been classified as the following categories in Table 5.18.
Figure 227724/E/2200 illustrates
the extent of project roads in ARQ.
Table 5.18: Road category
Category |
Road |
Project roads (by ARQ) |
Road network in ARQ |
Committed roads (by DAR) |
Road network in DAR |
Existing roads |
Anderson Road,
New Clear Water Bay Road, Clear Water Bay Road, Sau Mau Ping Road, Lee On
Road, Shun On Road, Po Lam Road, etc. |
Noise Model Setup
5.7.2 The road networks within the Study Area and the traffic flow within 300m assessment area have been summarised in Appendix 5.7. The extent of road sections paved with friction course materials have been provided by Highways Department and are shown in Appendix 5.8. The use of noise absorptive paving materials on project roads can theoretically reduce the traffic noise impact. As per the values specified in CRTN, the use of pervious road surface can reduce the basic noise level by 3.5 dB(A), as compared to that of 1.0 dB(A) for common impervious paving. This information has been included in the road traffic noise model accordingly. The noise mitigation measures recommended during the Planning Study including setback from road, non-openable windows/ maintenance window that are not opened for ventilation facing the road networks, use of non-sensitive structure and building orientation have been adopted in the unmitigated scenario.
Evaluation
of Unmitigated Road Traffic Noise Impact
5.7.3 The predicted road traffic
noise levels at the representative NSRs for ARQ are summarized in Table 5.19
below. Appendix 5.9 shows the detailed breakdown of road traffic noise impacts on ARQ.
Table 5.19: Unmitigated road traffic noise impact in Year 2041
NSR ID |
Uses [1] |
Noise Criteria, L10(1
hr) dB(A) |
Predicted Project Road Noise Level, L10 (1hr) dB(A) [2] |
Predicted Overall Noise Level, L10 (1hr) dB(A) [3] |
Contribution from
Project Roads, L10 (1hr) dB(A) |
Affected Floor |
No. of dwellings/
classroom per floor assumed [4] |
ARQ - Planned |
|||||||
R2-1 – R001 ~ R005 |
R |
70 |
55 ~ 67 |
55 ~ 67 |
8.1 ~ 63.1 |
- |
- |
R2-2 – R002 ~ R012 |
R |
70 |
24 ~ 67 |
47 ~ 67 |
0.0 ~ 58.6 |
- |
- |
R2-3 – R001 ~ R009 |
R |
70 |
61 ~ 67 |
61 ~ 67 |
24.4 ~ 42.6 |
- |
- |
R2-4 – R001 ~ R009 |
R |
70 |
54 ~ 68 |
54 ~ 68 |
14.6 ~ 67.5 |
- |
- |
R2-5 – R001 ~ R009 |
R |
70 |
35 ~ 69 |
40 ~ 69 |
0.2 ~ 57.3 |
- |
- |
R2-6 – R001 ~ R010 |
R |
70 |
55 ~ 69 |
55 ~ 69 |
29.3 ~ 68.1 |
- |
- |
R2-7 – R001 ~ R011 |
R |
70 |
56 ~ 69 |
56 ~ 69 |
30.1 ~ 48.3 |
- |
- |
R2-8 – R003 ~ R022 |
R |
70 |
55 ~ 70 |
55 ~ 70 |
8.8 ~ 53.0 |
- |
- |
R2-9&10 –
R001 ~ R019 |
R |
70 |
52 ~ 68 |
52 ~ 70 |
1.3 ~ 49.6 |
- |
- |
RS-1 – R001 ~ R010 |
R |
70 |
48 ~ 69 |
48 ~ 69 |
4.0 ~ 38.4 |
- |
- |
E-1 – R002 ~
R003 [5] |
E |
65 |
63 ~ 65 |
63 ~ 65 |
36.0 ~ 38.4 |
- |
- |
E-2 – R001
~ R002 [6] |
E |
65 |
50 ~ 65 |
50 ~ 65 |
16.9 ~ 29.0 |
- |
- |
E-3 – R001 ~ R002 |
E |
65 |
53 ~ 59 |
56 ~ 59 |
2.1 ~ 25.7 |
- |
- |
DAR – Under Construction |
|||||||
Site A&B – R102 ~ R906 |
R |
70 |
14 ~ 64 |
56 ~ 75 |
0.0 ~ 1.4 |
- |
- |
Site A&B –
School 01 ~ 02 |
E |
65 |
28 ~ 55 |
69 ~ 78 |
0.0 ~ 0.1 |
- |
- |
Site C1 – R1001 ~ R1105 |
R |
70 |
47 ~ 63 |
65 ~ 72 |
0.0 ~ 1.1 |
- |
- |
Site C2 – R101 ~ R103 |
R [7] |
70 |
68 ~ 76 |
68 ~ 76 |
6.7 ~ 37.3 |
1/F ~ 6/F |
N/A |
Site C2 –
School 02 ~ 05 |
E |
65 |
52 ~ 75 |
52 ~ 75 |
0.6 ~ 41.6 |
4/F ~ 8/F |
N/A |
Site E – R501 ~ R1004 |
R |
70 |
34 ~ 67 |
36 ~ 70 |
0.0 ~ 34.3 |
- |
- |
Site E – School |
E |
65 |
47 ~ 54 |
55 ~ 59 |
0.7 ~ 1.9 |
- |
- |
Existing |
|||||||
CYCS – 01 |
W |
65 |
< 40 |
< 40 |
< 40 |
- |
- |
Lung Wo Tsuen
01 ~ 02 |
R |
70 |
0 ~ 16 |
25 ~ 45 |
0.0 ~ 0.6 |
- |
- |
TSV-01 |
R |
70 |
< 40 |
< 40 |
< 40 |
- |
- |
Leighton
Pavilion 01 ~ 02 |
R |
70 |
12 |
57 ~ 68 |
0.0 |
- |
- |
Fat Yuen Temple |
W |
65 |
41 |
62 ~ 63 |
0 ~ 0.1 |
- |
- |
Haven of Hope Sunnyside School |
E |
65 |
52 ~ 54 |
66 ~ 68 |
0.1 ~ 0.2 |
- |
- |
Ma Yau Tong Village |
R |
70 |
51 ~ 53 |
66 ~ 68 |
0.1 ~ 0.2 |
- |
- |
Ma Yau Tong Village No.1 |
R |
70 |
57 |
71 ~ 72 |
0.1 ~ 0.2 |
- |
- |
Missionary Society of St. Columban |
W |
65 |
52 ~ 55 |
68 ~ 69 |
0.2 |
- |
- |
Holm Glad
Primary School 01 ~ 02 |
E |
65 |
36 ~ 44 |
63 ~ 74 |
0.0 |
- |
- |
Sau Ching House
01 ~ 02 |
R |
70 |
21 ~ 49 |
70 ~ 74 |
0.0 ~ 0.1 |
- |
- |
Sau Fai House |
R |
70 |
29 ~ 39 |
76 ~ 79 |
0.0 |
- |
- |
Sau Hong House |
R |
70 |
40 ~ 60 |
66 ~ 73 |
0.0 ~ 0.5 |
- |
- |
Sau Lok House |
R |
70 |
41 ~ 59 |
65 ~ 73 |
0.0 ~ 0.4 |
- |
- |
Sau Nga House 01 ~ 02 |
R |
70 |
42 ~ 58 |
64 ~ 74 |
0.0 ~ 0.4 |
- |
- |
Sau Yee House 01 ~ 02 |
R |
70 |
34 ~ 59 |
62 ~ 72 |
0.0 ~ 0.4 |
- |
- |
Sau Yin House 01 ~ 02 |
R |
70 |
20 ~ 42 |
68 ~ 74 |
0.0 ~ 0.1 |
- |
- |
Sau Ming
Primary School 01 ~ 02 |
E |
65 |
34 ~ 42 |
60 ~ 71 |
0.0 ~ 0.1 |
- |
- |
Lee Foo House |
R |
70 |
0 ~ 14 |
71 ~ 75 |
0.0 |
- |
- |
Shun Lee General Out-patient Clinic |
C |
55 |
14 |
74 |
0.0 |
- |
- |
Kwun Yam Temple |
W |
65 |
42 ~ 43 |
69 |
0.0 ~ 0.1 |
- |
- |
Ning Po No.2 College |
E |
65 |
34 ~ 43 |
71 ~ 73 |
0.0 |
- |
- |
Tin Wan House
01 ~ 02 |
R |
70 |
28 ~ 46 |
64 ~ 75 |
0.0 ~ 0.1 |
- |
- |
Planned City God Temple |
W |
65 |
32 ~ 34 |
69 |
0.0 |
- |
- |
Planned Monkey King Temple |
W |
65 |
28 ~ 29 |
68 |
0.0 |
- |
- |
Sau Mau Ping Catholic Primary School |
E |
65 |
36 ~ 44 |
56 ~ 74 |
0.0 |
- |
- |
Tat Cheung House 01 |
R |
70 |
20 ~ 27 |
71 ~ 76 |
0.0 |
- |
- |
Tat Chui House |
R |
70 |
42 ~ 59 |
56 ~ 69 |
0.1 ~ 0.7 |
- |
- |
Tat Fung House |
R |
70 |
40 ~ 55 |
58 ~ 70 |
0.0 ~ 0.2 |
- |
- |
Tat Hong House 01 ~ 02 |
R |
70 |
28 ~ 55 |
43 ~ 69 |
0.0 ~ 0.3 |
- |
- |
Tat Yan House |
R |
70 |
40 ~ 59 |
58 ~ 69 |
0.0 ~ 0.7 |
- |
- |
Tat Yi House |
R |
70 |
40 ~ 60 |
62 ~ 70 |
0.0 ~ 0.7 |
- |
- |
Tin Hau Temple |
W |
65 |
29 |
68 |
0.0 |
- |
- |
Notes:
[1] R – residential; E – educational; C – clinic/ home for the aged/hospital; W – worship
[2] Bold figure denotes the noise level from Project Roads is over the relevant TM-EIAO noise criteria.
[3] Bold figure denotes the noise exceedance which is over the relevant TM-EIAO noise criteria and the contribution from new roads to the overall noise level is equal to or higher than 1.0 dB(A).
[4] N/A denotes the number of dwellings / classroom cannot be determined due to planned uses.
[5] According to the latest assessment, no non-sensitive structure is required between the school and the road.
[6] A non-sensitive structure of approximately 60m long and 9m height is adopted between the school and the road.
[7] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
5.7.4 The predicted cumulative road traffic noise level for the residential NSRs at Site C2 - R101, Site C2 - R102 and Site C2 - R103 is 69 – 76 dB(A) which exceed the stipulated noise criterion of 70dB(A) and significant contribution from project roads is predicted. Noise mitigation measures are required for these receivers.
5.7.5 The predicted cumulative
road traffic noise level for the educational institutions NSRs at Site C2 - School 02, Site C2 -
School 03, Site C2 - School 04 and Site C2 - School 05 is 52 – 75 dB(A) which exceed the stipulated noise
criterion of 65dB(A) and
significant contribution from project roads is predicted. The predicted noise levels from project roads
at Site C2 - School 02, Site C2 - School 03, Site C2 - School 04 and Site C2 - School 05 has
already exceed the noise criterion of 65dB(A).
Noise mitigation measures are required for these receivers.
Recommended Noise Mitigation Measures
5.7.6 Exceedance of noise criteria are found in various sensitive receivers for both existing and planned uses, noise mitigation measures should therefore be required. According to the Section 6.1, Annex 13 of TM-EIAO, noise mitigation measures starting from direct ones should be considered and evaluated. Direct mitigation measure as listed below are recommended in the proposed development:
(1)
Setback
from road;
(2)
Provision
of non-openable windows/ maintenance window that are not opened for
ventilation;
(3)
Use of
non-sensitive structure;
(4)
Building
orientation; and
(5)
Noise
barrier/ enclosure.
Setback from road
5.7.7 During the planning stage of ARQ development, it is proposed to provide setback distance away from the nearby road network within the ARQ. A setback distance could help to reduce the road traffic noise impact to future resident. Different setback distances of 5m, 8m and 10m from the nearest site boundary is recommended in different residential sites.
Provision of non-openable windows/ maintenance window that are not
opened for ventilation
5.7.8 Non-openable windows are window designs that do not include any sections of the window that are configured to open and close. The future resident would not be impacted by the road traffic noise.
Use
of non-sensitive structure
5.7.9 A non-sensitive structure in between the
road traffic and the noise sensitive receivers could block the propagation of
the road traffic noise and hence reduce the noise impact.
Building
Orientation
5.7.10 The sensitive buildings could be oriented
such that the non-sensitive use such as kitchen, bathroom or store room of
residential and staircase or store room of schools are located to the road
traffic. Those sensitive uses such as bedrooms/ living
rooms of residential and classroom of schools could be oriented away from the
road traffic. These could reduce the road traffic noise impact.
Noise
barrier/enclosure
5.7.11 In view of practicability, the erection of noise barrier/ semi-enclosure along the new road sections are considered as effective mitigation measures in tackling the road traffic noise impact to sensitive receivers.
5.7.12 Permanent noise mitigation measure in form of semi-enclosure will be provided prior to operation. The location of noise mitigation measures are described in the following paragraph.
5.7.13 For the Road
L4 of ARQ, given the close proximity to planned G/IC
uses including the planned schools (Site C2 – School 02 ~ 05) and planned
Ancillary Facilities Building (Site C2 – R101 ~ R103). A semi-enclosure covering northbound with
opening at east is therefore recommended.
Overall
Noise Mitigation Measures
5.7.14 Table
5.20 below summarised the recommended noise mitigation
measures including the setback from road, provision of non-openable windows/
maintenance window that are not opened for ventilation, use of non-sensitive
structure, building orientation and semi-enclosure. The recommended noise mitigation measures
are shown in Figures 227724/E/2210 and
227724/E/2220. The typical
cross section of the proposed semi-enclosure along Road L4 is shown in Figure 227724/E/2221.
Table 5.20: Recommended noise mitigation
measures for road traffic noise impact
Location |
Type of Noise
Mitigation Measures |
Benefited NSRs |
Representative Planned
NSR |
||
R2-1,
R2-2, R2-3, R2-5 |
· 5m building setback from nearest site boundary |
R2-1,
R2-2, R2-3, R2-5 |
R2-6 |
· 8m
building setback |
R2-6 |
R2-7
(facing north) |
· 8m
building setback |
R2-7
(facing north) |
R2-7
(facing east) |
· 8m
building setback; and · Non-openable
windows/ maintenance window that are not opened for ventilation |
R2-7
(facing east) |
R2-8
(facing north) |
· 8m
building setback; and · Non-openable
windows/ maintenance window that are not opened for ventilation |
R2-8
(facing north) |
R2-8
(facing east) |
· 8m
building setback |
R2-8
(facing east) |
R2-9&10 |
· 8m
building setback; and · Non-openable
windows/ maintenance window that are not opened for ventilation |
R2-9&10 |
RS-1 |
· 10m
building setback |
RS-1 |
E-1 |
· Proper
orientation of L-shaped standard design school layout |
E-1 |
E-2 |
· Proper
orientation of L-shaped standard design school layout; · Use
of non-sensitive structure for noise screening; and · Non-openable
windows/ maintenance window that are not opened for ventilation |
E-2 |
Road L4 of ARQ |
· Semi-enclosure with opening at east: - Height above road level : 7m - Approximate Length : 265m |
Site C2 –
School 02 ~ 05 Site C2 –
R101 ~ R103 |
Evaluation of
Mitigated Road Traffic Noise Impact
5.7.15 With the implementation of recommended noise mitigation measures as shown in the table above, the predicted road traffic noise levels at the representative NSRs within the Study Area are summarized in Table 5.21 below. Appendix 5.10 shows the detailed breakdown of road traffic noise impacts. Appendix 5.12 shows the road plot of noise model and sample calculations of road traffic noise.
Table 5.21: Mitigated road traffic noise impact
in Year 2041
NSR ID |
Uses [1] |
Noise Criteria L10(1
hr) dB(A) |
Predicted Project Road Noise Level L10 (1hr)
dB(A) |
Predicted Overall Noise Level L10 (1hr)
dB(A) |
Contribution from
Project Roads, L10 (1hr) dB(A) |
Site C2 –
R101 ~ R103 |
R [2] |
70 |
46 ~ 68 |
53 ~ 70 |
0.9 ~ 23.2 |
Site C2 –
School 02 ~ 05 |
E |
65 |
42 ~ 61 |
45 ~ 65 |
0.1 ~ 24.1 |
Notes:
[1] R – residential; E – educational
[2] According to the building layout provided by Housing Department, a dormitory use of the Ancillary Facilities Building is facing the Road L4.
Evaluation
of Eligibility of Indirect Technical Remedies
5.7.16 As mentioned in Section 5.5.25, in the case where NSRs are still exposed to noise levels exceeding the relevant noise criteria after the implementation of all direct mitigation measures, the total number of existing dwellings, classrooms and other noise sensitive elements which may qualify for indirect technical remedies should be identified. However, for those NSRs with cumulative noise level exceed the relevant noise criteria, i.e. 70 dB(A) for residential and 65 dB(A) for educational institutions, the noise contribution from “Project Road” would be lesser than 1.0 dB(A). The assessment result of the prevailing scenario is shown in Appendix 5.11. Hence, irrespective of the prevailing noise level, all the NSRs would not satisfy the eligibility assessment criteria.
Evaluation of Protected
and Benefited Noise Sensitive Uses with the Noise Mitigation Measures
5.7.17 To study the noise performance of the project, traffic noise levels at the residential, schools and other noise sensitive uses including hospital/ clinic and place of worship which have a direct line of sight to the Project have been predicted. The numbers of dwellings, classrooms and other noise sensitive uses that would be benefited from and be protected by the provision of noise mitigation measures have been calculated. The definition of “exposed”, “benefited” and “protected” noise sensitive uses are defined as follow:
(1)
Exposed – Noise
sensitive uses with unmitigated noise level greater
than relevant noise criteria
(2) Benefited – Exposed noise sensitive uses with a noise reduction of 1.0 dB(A) or greater in overall noise level with the noise mitigation measures in place
(3) Protected – Exposed noise sensitive uses with an overall noise level not greater than relevant noise criteria with the noise mitigation measures in place
5.7.18 Number of dwellings and classrooms that would be benefited from and be protected by the provision of noise mitigation measures have
been identified for existing
residential and schools respectively.
Moreover, the planned noise sensitive uses do not have detailed numbers
of dwellings/ classrooms, the benefited/ protected have been identified as the number of
floors. Results of planned noise sensitive uses are presented in Table
5.22 below.
Table 5.22: Summary of protected and benefited noise sensitive uses (planned uses)
Noise Sensitive Uses |
Total No. of Floors of
Dwellings/ Classrooms/ Noise Sensitive Uses Considered |
Unmitigated Scenario |
Mitigated Scenario |
||
No. of Exposed Floors of Dwellings/ Classrooms/ Noise Sensitive Uses |
No. of Exposed Floors of
Dwellings/ Classrooms/ Noise Sensitive Uses |
Protected Floors of Dwellings/ Classrooms/ Noise Sensitive Uses |
Benefited Floors Dwellings/ Classrooms/ Noise Sensitive Uses |
||
Dwellings [1] |
6 |
6 |
0 |
6 |
6 |
Classrooms [1] |
16 |
9 |
0 |
9 |
9 |
Notes:
[1] Number of floors
5.8 Fixed Plant Noise Assessment
Inventory of Noise Sources
5.8.1 A summary of the fixed noise sources affecting the project area and the
receivers in the vicinity is summarized below:
(1)
Proposed
Pumping Station for saltwater and freshwater;
(2)
Proposed Public
Transport Terminus; and
(3)
Planned
Rock Cavern (+190mPD, +200mPD, +310mPD).
5.8.2 A summary of the fixed noise sources for ARQ is summarized in below sections. The locations of fixed noise sources are shown in Figures 227724/E/2300 - 2310. It should be noted that there are no existing /planned fixed noise sources is identified within 300 assessment area. The proposed DSD detention tank in ARQ site is also not a fixed noise source as pumping facility is not required for the detention tank.
Proposed pumping station
for saltwater and freshwater
5.8.3 Pumping station for saltwater and freshwater is a planned facility located at the northern-west boundary of the Study Area at ARQ as shown in Figure 227724/E/2310 to cater for the demand increase in water supply. This pumping station would need to be operated during both daytime and night-time periods. The pumping station would be located at 180m from the planned ARQ NSR (R2-1-R006) and 125m from the planned DAR NSR (Site A&B - R203). As there is no information on the planned pumping station for saltwater and freshwater, the maximum SWL has been determined by backward calculation based on the separation distance and noise criteria taking into account the façade and tonality corrections.
Proposed
public transport terminus
5.8.4 Fixed noise sources in public transport terminus are primarily due to
the ventilation fans, idling engine and manoeuvring vehicle, etc. However, the public transport terminus would be
designed to no direct
line-of-sight of the noise sources at the noise sensitive uses in accordance to
the HKPSG. The no
direct line-of-sight would be
achieved by providing rooftop of public transport terminus and proper mitigation measures such as barrier, silencer, louvers
orientation, etc. External ventilation openings can
be equipped with sound attenuators or acoustic louvers for proper noise control
design. Hence, noise impacts are not expected from the public transport
terminus during operational phase. In addition, the location of ingress and
egress of the facilities should be planned in order to avoid adverse noise
impacts to the adjacent area in detail design stage.
Planned
rock caverns (+190mPD,
+200mPD, +310mPD)
5.8.5 The planned cavern developments are located on the hillside of the proposed
ARQ Development. Ventilation shafts may be required for the cavern development
despite the future landuse of the caverns is yet confirmed. Fixed plant noise
from the louvers of the ventilation shafts would be the major noise sources. The planned
rock cavern (+190mPD) would be located at 45m from the planned ARQ NSR (R2-7-R009);
the planned rock cavern (+200mPD) would be located at 80m from the planned ARQ
NSR (R2-1-R006); and the planned rock cavern (+310mPD) would be located at 135m
from the planned ARQ NSR (RS-1-R001). As there is no information on the planned
rock caverns at +190mPD, +200mPD and +310mPD, the maximum SWLs are therefore
determined by backward calculation based on the separation distance and noise
criteria taking into account the façade and tonality corrections.
Evaluation of Fixed Plant Noise Impact
5.8.6 The predicted maximum allowable Sound Power Levels (SWLs) is summarized in Table 5.23 below. Detailed calculations are presented in Appendix 5.13.
Table 5.23: Maximum allowable
SWLs for the fixed noise sources
Plant Item |
Maximum allowable Sound Power Level, dB(A) |
|
Daytime/ Evening |
Night-time |
|
Pumping
station for saltwater and freshwater |
97 |
94 |
Rock
cavern +190mPD |
88 |
81 |
Rock
cavern +200mPD |
93 |
86 |
Rock
cavern +310mPD |
99 |
92 |
5.8.7 The equipment should be free of the characteristics of tonality, impulsiveness and intermittency. If the selected equipment could not be free of characteristics of tonality, impulsiveness and intermittency, the maximum SWL should be reduced in accordance with the correction factors, in the range of 3 to 6 dB(A), as given in Section 3.3 of TM-Places.
5.8.8 It should be noted that the detailed design of the pumping station for saltwater and freshwater, and the rock caverns (e.g. the louver details) are yet to be developed. Hence, the Contractor shall review the latest design and update the noise assessment to ensure that the stipulated facade noise levels in Table 5.10 can be achieved.
5.8.9 The Contractor shall
install acoustic silencers, noise barriers and acoustic louvers where
appropriate to ensure that the specified maximum SWLs shown in Table 5.23
above would not be exceeded.
Mitigation Measures
5.8.10 The detailed design should incorporate the following good practice in order to minimize the nuisance on the neighbouring NSRs. In case the Contractor would change the design and locations of the louvers, they would need to comply with the legislative maximum impacts at the receivers.
(1)
Louvres
should be orientated away from adjacent NSRs, preferably onto main roads which
are less sensitive.
(2)
Direct
noise mitigation measures including silencers, acoustic louvers and acoustic
enclosures should be allowed for in the design for the pumping station for
saltwater and freshwater.
(3) The façade for the pumping station for saltwater and freshwater should have adequate sound insulation properties to minimise the noise emanating through the building fabric.
5.9
Assessment of Side Effects and Constraints
5.9.1 The adopted mitigation
measures have been designed to balance between feasibility and effectiveness.
The scheme has avoided blockage to the entrance way of the existing and planned
premises. The induced impacts from noise barrier have been separately discussed in
Air Quality and LVIA chapters.
5.10
Evaluation of Constraints on Planned Noise
Sensitive Developments/ Land Uses
5.10.1 Given the assumed building layout plan with the ARQ development, constraints
on the planned noise sensitive development/land uses are not anticipated. The
recommendations for noise mitigation measures under the Planning Study including
the setback distance and/ or non-openable windows/ maintenance window that are
not opened for ventilation facing the road networks have been assessed and
examined that these mitigation measures are engineering feasible. Therefore, no additional measures within the
planned noise sensitive uses are required.
5.10.2 However, given the building layout plan,
especially those five concerned sites (i.e. private development sites R2-7 to
R2-10 and school development site E-2, refer to Figure No. 227724/E/2210 and Table
5.20) with non-openable
windows/ maintenance window that are not opened for ventilation,
and another school development site (i.e. E-1, refer to Figure No. 227724/E/2210 and
Table 5.20) with assumed L-shape layout and orientation, might be changed
by the future developers and school operators, a noise impact assessment for
the future development should be carried out prior to the commencement of the
construction works in order to meet the noise criteria. This requirement would
be set as a proposed land lease condition of the land lots. The requirement of
setback distance ranged from 5 to 10m as noise mitigation measures for other
sites (i.e. refer to Figures No.
227724/E/2210 and Table 5.20)
would also be set as a proposed land lease condition of the land lots. The proposed noise mitigation measures for two
planned school sites E-1 and E-2 have also been accepted by Architectural
Services Department (ArchSD) and Education Bureau (EDB). The correspondences between CEDD, Lands
Department and ArchSD/EDB are given in Appendix
5.14.
5.11.1 Construction noise impact at most noise sensitive receivers arising from
the Project could be properly mitigated by implementing the proposed noise
control measures such as barrier and quiet plant. However, there would be some
receivers still exceeding the respective noise criteria. The noise level would exceed the noise
criterion of 75 dB(A) by 1 – 2 dB(A) for about 9 – 10 months at residential
premises. For the educational institutions, there would be exceedance of the
noise criterion of 70 dB(A) during normal period of 1 – 3 dB(A) for about
6 –
13 months and
exceedance of the noise criterion of 65 dB(A) during examination period of 1 – 9 dB(A) for about 6 – 8 months. Given the transient
nature of the residual impact, the residual impact is considered as acceptable.
5.11.2 During the operational phase, the impact arising from the Project can be
properly mitigated by implementing the proposed noise control measures such as
barrier, enclosure and silencer. Residual noise impacts are not anticipated. In
order to ensure compliance of the operational noise level with the stipulated
noise standards in TM, noise commissioning tests for all major fixed noise
sources should be included in the Contract Document.
5.12
Environmental Acceptability of Schedule 2
Designated Projects
5.12.1 The engineering feasibility study of the proposed ARQ development is a
Schedule 3 Designed Project (DP) under the EIAO, whilst there will be two
Schedule 2 DPs; i.e. road improvement works and rock cavern developments under the ARQ project. Details of
these two Schedule 2 DPs are provided in Section
1.5 and shown in Figure 227724/E/0002.
Road
Improvement Works
5.12.2 Three road improvement works was proposed at junction of (J/O) Lin Tak
Road and Sau Mau Ping Road, at J/O Clear Water Bay Road and Road L1 of
Development of Anderson Road (DAR), as well as at the new merging lane at New
Clear Water Bay Road near Shun Lee Tsuen Road. The operation year of these three road improvement
works are 2022, 2021 and 2019 respectively.
5.12.3 During operational phase, road traffic noise would be the dominate noise
source to the nearby sensitive receivers, the impact on the identified NSRs is
assessed following the criteria and guidelines set out in Annexes 5 and 13 of
the TM-EIAO. The
identified noise sensitive receivers of the road improvement works are
summarised in Table 5.24 and shown
in the figures attached in Appendix 5.15.
Table 5.24: Identified noise sensitive
receivers for the road improvement works
Road Improvement
Works |
Noise Sensitive
Receivers |
Junction of Lin Tak Road and Sau Mau Ping Road |
Choi Tin House
and Yee Hong House |
Junction of Clear Water Bay Road and Road L1 of
Development of Anderson Road (DAR) |
Tai Pan Court |
New merging lane at New Clear Bay Road |
Block 5, Shun
Lee Disciplined Services Quarters |
5.12.4 Predicted road traffic
noise is calculated in accordance to the UK methodology for
the Calculation of Road Traffic Noise (CRTN) published by Department of
Transport, UK. The assessment year of the future
road traffic noise shall be calculated based on peak hour traffic flow in
respect of maximum traffic projection within the next 15 years upon commencement
of operation of the road improvement works.
Year 2037 which is Year 2022 + 15 is selected for the three road
improvement works as worst case assumption.
5.12.5 A boardbrush road traffic noise assessment of these three road
improvement works has been carried out at the identified noise sensitive
receivers. Table 5.25 below shows the predicted road traffic noise level at
these noise sensitive receivers. The
boardbrush road traffic noise assessment is presented in Appendix 5.15.
Table 5.25: Predicted road traffic
noise level at Year 2037
Road Improvement Works |
Noise Sensitive Receivers |
Noise Criteria, L10(1 hr) dB(A) |
Predicted Project Road Noise Level, L10
(1hr) dB(A) |
Junction
of Lin Tak Road and Sau Mau Ping Road |
Choi Tin House |
70 |
75 |
Yee Hong House |
78 |
||
Junction
of Clear Water Bay Road and Road L1 of Development of Anderson Road (DAR) |
Tai Pan Court |
76 |
|
New
merging lane at New Clear Bay Road |
Block 5, Shun Lee Disciplined Services Quarters |
78 |
5.12.7 Nevertheless, the detailed noise impact of this Schedule 2 DP will be
further investigated in a separate EIA under the EIAO.
Rock Cavern Developments
5.12.8 The proposed cavern developments are
located on the hillside of the proposed ARQ Development. There may have ventilation shafts for the
cavern developments. Fixed plant noise
from the louvers of the ventilation shafts would be the major noise
sources. To minimise the potential noise
impact from the fixed noise sources, the following good practices should be
adopted:
·
Louvres should be oriented away from adjacent
NSRs; and
·
Direct noise mitigation measures including
silencers, acoustic louvers and acoustic enclosures should be allowed for in
the design of the ventilation shafts.
5.12.9
Insurmountable noise impact is not
anticipated with the implementation of appropriate mitigation measures. Nevertheless, the detailed noise impact of this Schedule 2 DP will be
further investigated in a separate EIA under the EIAO.
5.13.1 Construction noise assessment has been conducted. All practicable mitigation measures have been exhausted to minimise the noise impacts. These mitigation measures include the optimisation of construction methodology (i.e. schedule of using PME), quiet plant, temporary noise barrier and good site practices. However, given the site constraints, some of the receivers (See Table 5.14) would still be subject to residual impacts exceeding the construction noise criterion.
5.13.2 Residual impacts exceeding the construction noise criterion have been assessed and considered the impacts are temporary and reversible. With all the proposed mitigation measures, the residual impact exceeding the construction noise criterion has been reduced to be minimal.
5.13.3 For the operational phase,
mitigation measures including setback from
road, provision of non-openable windows/ maintenance window that are not opened
for ventilation, use of non-sensitive structure and building orientation are required to fulfil the EIAO criteria. Besides, a semi-enclosure is also required
along Road L4 for mitigating the traffic noise impact, and approximately of 6 floors of planned dwellings and 9 floors of planned classrooms would be benefited from and protected
by the semi-enclosure.
5.13.4 Maximum sound power levels
allowed to be emitted from louvers of fixed noise sources at pumping
station for saltwater and freshwater and planned rock cavern developments were predicted. The public transport terminus would also be
designed to no direct line-of-sight of the noise
sources at the noise sensitive uses.
With the proper selection of plant and adoption of noise control measure
such as acoustic silencers, noise barriers, acoustic louvers, the NSRs located
in the vicinity of these fixed noise sources would not be affected.