|
|||||
|
|||||
|
This report takes into account the particular It is not intended for and should
not be relied Job number |
|
|
|
||
Ove Arup & Partners
Hong Kong Ltd 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong |
9.1 Environmental Legislation and Guidelines
9.1.1 The relevant legislations, standards and guidelines applicable to the present study for the assessment of land contamination include:
(1) Annex 19 of the TM-EIA, Guidelines for Assessment of Impact Assessment Process (TM-EIA), Guidelines for Assessment of Impact On Sites of Cultural Heritage and Other Impacts (Section 3 : Potential Contaminated Land Issues), EPD, 1997;
(2) Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management, EPD, 2007.
(3) Guidance Notes for Contaminated Land Assessment and Remediation EPD, 2007 ; and
(4) Practice Guide for Investigation and Remediation of Contaminated Land, EPD, 2011.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO)
9.1.2 Under Annex 19 of the TM-EIAO, a number of potentially contaminating historical land uses should be considered, including oil installations, gas works, metal workshops, car repair and dismantling workshops, which have the potential to cause or have caused land contamination.
Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management
9.1.3 The Guidance Manual introduces the risk based approach in land contamination assessment and present instructions for comparison of soil and groundwater data to the RBRGs for 54 chemicals of concern commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary. The RBRGs for soil and groundwater are given in Tables 9.1 and 9.2 respectively.
Table 9.1: Risk-Based Remediation Goals (RBRGs) for soil & soil saturation limit
Chemical |
Risk-Based Remediation Goals
(RBRGs) for Soil |
Soil Saturation Limit (Csat) |
|||
Urban Residential |
Rural Residential |
Industrial |
Public Parks |
||
(mg/kg) |
(mg/kg) |
(mg/kg) |
(mg/kg) |
(mg/kg) |
|
VOCs |
|
|
|
|
|
Acetone |
9,590 |
4,260 |
10,000* |
10,000* |
*** |
Benzene |
0.704 |
0.279 |
9.21 |
42.2 |
336 |
Bromodichloromethane |
0.317 |
0.129 |
2.85 |
13.4 |
1,030 |
2-Butanone |
10,000* |
10,000* |
10,000* |
10,000* |
*** |
Chloroform |
0.132 |
0.0529 |
1.54 |
253 |
1,100 |
Ethylbenzene |
709 |
298 |
8,240 |
10,000* |
138 |
Methyl
tert-Butyl Ether |
6.88 |
2.80 |
70.1 |
505 |
2,380 |
Methylene
Chloride |
1.30 |
0.529 |
13.9 |
128 |
921 |
Styrene |
3,220 |
1,540 |
10,000* |
10,000* |
497 |
Tetrachloroethene |
0.101 |
0.0444 |
0.777 |
1.84 |
97.1 |
Toluene |
1,440 |
705 |
10,000* |
10,000* |
235 |
Trichloroethene |
0.523 |
0.211 |
5.68 |
69.4 |
488 |
Xylenes
(Total) |
95.0 |
36.8 |
1,230 |
10,000* |
150 |
SVOCs |
|
|
|
|
|
Acenaphthene |
3,510 |
3,280 |
10,000* |
10,000* |
60.2 |
Acenaphthylene |
2,340 |
1,510 |
10,000* |
10,000* |
19.8 |
Anthracene |
10,000* |
10,000* |
10,000* |
10,000* |
2.56 |
Benzo(a)anthracene |
12.0 |
11.4 |
91.8 |
38.3 |
|
Benzo(a)pyrene |
1.20 |
1.14 |
9.18 |
3.83 |
|
Benzo(b)fluoranthene |
9.88 |
10.1 |
17.8 |
20.4 |
|
Benzo(g,h,i)perylene |
1,800 |
1,710 |
10,000* |
5,740 |
|
Benzo(k)fluoranthene |
120 |
114 |
918 |
383 |
|
Bis-(2-Ethylhexyl)phthalate |
30.0 |
28.0 |
91.8 |
94.2 |
|
Chrysene |
871 |
919 |
1,140 |
1,540 |
|
Dibenzo(a,h)anthracene |
1.20 |
1.14 |
9.18 |
3.83 |
|
Fluoranthene |
2,400 |
2,270 |
10,000* |
7,620 |
|
Fluorene |
2,380 |
2,250 |
10,000* |
7,450 |
54.7 |
Hexachlorobenzene |
0.243 |
0.220 |
0.582 |
0.713 |
|
Indeno(1,2,3-cd)pyrene |
12.0 |
11.4 |
91.8 |
38.3 |
|
Naphthalene |
182 |
85.6 |
453 |
914 |
125 |
Phenanthrene |
10,000* |
10,000* |
10,000* |
10,000* |
28.0 |
Phenol |
10,000* |
10,000* |
10,000* |
10,000* |
7,260 |
Pyrene |
1,800 |
1,710 |
10,000* |
5,720 |
|
Metals |
|
|
|
|
|
Antimony |
29.5 |
29.1 |
261 |
97.9 |
|
Arsenic |
22.1 |
21.8 |
196 |
73.5 |
|
Barium |
10,000* |
10,000* |
10,000* |
10,000* |
|
Cadmium |
73.8 |
72.8 |
653 |
245 |
|
Chromium
III |
10,000* |
10,000* |
10,000* |
10,000* |
|
Chromium
VI |
221 |
218 |
1,960 |
735 |
|
Cobalt |
1,480 |
1,460 |
10,000* |
4,900 |
|
Copper |
2,950 |
2,910 |
10,000* |
9,790 |
|
Lead |
258 |
255 |
2,290 |
857 |
|
Manganese |
10,000* |
10,000* |
10,000* |
10,000* |
|
Mercury |
11.0 |
6.52 |
38.4 |
45.6 |
|
Molybdenum |
369 |
364 |
3,260 |
1,220 |
|
Nickel |
1,480 |
1,460 |
10,000* |
4,900 |
|
Tin |
10,000* |
10,000* |
10,000* |
10,000* |
|
Zinc |
10,000* |
10,000* |
10,000* |
10,000* |
|
Dioxins
/ PCBs |
|||||
Dioxins
(I-TEQ) |
0.001 |
0.001 |
0.005 |
0.001 |
|
PCBs |
0.236 |
0.226 |
0.748 |
0.756 |
|
Petroleum
Carbon Ranges |
|||||
C6
- C8 |
1,410 |
545 |
10,000* |
10,000* |
1,000 |
C9
- C16 |
2,240 |
1,330 |
10,000* |
10,000* |
3,000 |
C17
- C35 |
10,000* |
10,000* |
10,000* |
10,000* |
5,000 |
Other
Inorganic Compounds |
|||||
Cyanide,
free |
1,480 |
1,460 |
10,000* |
4,900 |
|
Organometallics |
|||||
TBTO |
22.1 |
21.8 |
196 |
73.5 |
|
Notes:
[1] For Dioxins, the cleanup levels in USEPA Office of Solid Waste and Emergency Response (OSWER) Directive of 1998 have been adopted. The OSWER Directive value of 1 ppb for residential use has been applied to the scenarios of "Urban Residential", "Rural Residential", and "Public Parks", while the low end of the range of values for industrial, 5 ppb, has been applied to the scenario of "industrial".
[2] Soil saturation limits for petroleum carbon ranges taken from the Canada-Wide Standards for Petroleum Hydrocarbons in Soil, CCME 2000.
[3] * indicates a 'ceiling limit' concentration. A non risk-based ‘ceiling limit’ is given as 104 mg/kg for soil and 104 mg/L for groundwater for the relatively less toxic inorganic, volatile and semi-volatile contaminants.
[4] *** indicates that the Csat value exceeds the 'ceiling limit' therefore the RBRG applies.
Table 9.2: Risk-Based Remediation Goals (RBRGs) for groundwater and solubility limit
Chemical |
Risk-Based Remediation Goals
(RBRGs) for Groundwater |
Groundwater Solubility Limit |
||
Urban Residential |
Rural Residential |
Industrial |
||
(mg/L) |
(mg/L) |
(mg/L) |
(mg/L) |
|
VOCs |
|
|
|
|
Acetone |
10,000* |
10,000* |
10,000* |
*** |
Benzene |
3.86 |
1.49 |
54.0 |
1,750 |
Bromodichloromethane |
2.22 |
0.871 |
26.2 |
6,740 |
2-Butanone |
10,000* |
10,000* |
10,000* |
*** |
Chloroform |
0.956 |
0.382 |
11.3 |
7,920 |
Ethylbenzene |
1,020 |
391 |
10,000* |
169 |
Methyl
tert-Butyl Ether |
153 |
61.1 |
1,810 |
*** |
Methylene
Chloride |
19.0 |
7.59 |
224 |
*** |
Styrene |
3,020 |
1,160 |
10,000* |
310 |
Tetrachloroethene |
0.250 |
0.0996 |
2.95 |
200 |
Toluene |
5,110 |
1,970 |
10,000* |
526 |
Trichloroethene |
1.21 |
0.481 |
14.2 |
1,100 |
Xylenes
(Total) |
112 |
43.3 |
1,570 |
175 |
SVOCs |
|
|
|
|
Acenaphthene |
10,000* |
7,090 |
10,000* |
4.24 |
Acenaphthylene |
1,410 |
542 |
10,000* |
3.93 |
Anthracene |
10,000* |
10,000* |
10,000* |
0.0434 |
Benzo(a)anthracene |
|
|
|
|
Benzo(a)pyrene |
|
|
|
|
Benzo(b)fluoranthene |
0.539 |
0.203 |
7.53 |
0.0015 |
Benzo(g,h,i)perylene |
|
|
|
|
Benzo(k)fluoranthene |
|
|
|
|
Bis-(2-Ethylhexyl)phthalate |
|
|
|
|
Chrysene |
58.1 |
21.9 |
812 |
0.0016 |
Dibenzo(a,h)anthracene |
|
|
|
|
Fluoranthene |
10,000* |
10,000* |
10,000* |
0.206 |
Fluorene |
10,000* |
10,000* |
10,000* |
1.98 |
Hexachlorobenzene |
0.0589 |
0.0234 |
0.695 |
6.20 |
Indeno(1,2,3-cd)pyrene |
|
|
|
|
Naphthalene |
61.7 |
23.7 |
862 |
31.0 |
Phenanthrene |
10,000* |
10,000* |
10,000* |
1.00 |
Phenol |
|
|
|
|
Pyrene |
10,000* |
10,000* |
10,000* |
0.135 |
Metals |
|
|
|
|
Antimony |
|
|
|
|
Arsenic |
|
|
|
|
Barium |
|
|
|
|
Cadmium |
|
|
|
|
Chromium
III |
|
|
|
|
Chromium
VI |
|
|
|
|
Cobalt |
|
|
|
|
Copper |
|
|
|
|
Lead |
|
|
|
|
Manganese |
|
|
|
|
Mercury |
0.486 |
0.184 |
6.79 |
|
Molybdenum |
|
|
|
|
Nickel |
|
|
|
|
Tin |
|
|
|
|
Zinc |
|
|
|
|
PCBs |
|
|
|
|
Dioxins
(I-TEQ) |
|
|
|
|
PCBs |
0.433 |
0.171 |
5.11 |
0.031 |
Petroleum
Carbon Ranges |
||||
C6
- C8 |
82.2 |
31.7 |
1,150 |
5.23 |
C9
- C16 |
714 |
276 |
9,980 |
2.80 |
C17
- C35 |
12.8 |
4.93 |
178 |
2.80 |
Other
Inorganic Compounds |
||||
Cyanide,
free |
|
|
|
|
Organometallics |
|
|
|
|
TBTO |
|
|
|
|
Notes:
[1] Blank indicates that RBRG could not be calculated because the toxicity or physical/chemical values were unavailable, or the condition of Henry's Law Constant > 0.00005 was not met for the inhalation pathway.
[2] Where solubilities for Petroleum Carbon Range aliphatic C9-C16 and greater than C16 generally are considered to be effectively zero and therefore the aromatic solubility for C9-C16 is used.
[3] * indicates a 'ceiling limit' concentration. A non risk-based ‘ceiling limit’ is given as 104 mg/kg for soil and 104 mg/L for groundwater for the relatively less toxic inorganic, volatile and semi-volatile contaminants.
[4] *** indicates that the solubility limit exceeds the 'ceiling limit' therefore the RBRG applies.
Guidance Note for Contamination Land Assessment and Remediation
9.1.4 In accordance with EPD’s Guidance Note for Contamination Land Assessment and Remediation, a contamination assessment evaluation should:
(1) Provide a clear and detailed account of the present land-use and the relevant past land history, in relation to possible land contamination;
(2) Identify areas of potential contamination and associated impacts, risks or hazards; and
(3) Submit a plan to evaluate the actual contamination conditions for soil and/or groundwater, if required.
Practice Guide for Investigation and Remediation of Contaminated Land
9.1.5 The EPD’s Practice Guide for Investigation and Remediation of Contaminated Land includes a summary of the general steps of a contamination assessment study, which include site appraisal, site investigation and remediation.
9.2.1 Land contamination assessment has been conducted according to the following procedures:
(1) Desktop review of site history;
(2) Site surveys to identify the potentially contaminated areas;
(3) Prepare Contamination Assessment Plan for EPD’s agreement; and
(4) Propose Environmental Site Investigation for soil and groundwater sampling and testing.
Desktop Review
9.2.2 The following information have been collated for the desktop review of site history:
(1) Hong Kong Geological Survey Map (GSMs); and
(2) Relevant aerial photos from 1963.
Site Surveys
9.2.3 Site surveys were conducted to ground truth the findings of desktop review and to identify any other land uses within the Study Area which may have the potential for causing soil and groundwater contamination. Potentially contaminating activities were identified during the site surveys in accordance with Table 2.3 of EPD’s Practice Guide for Investigation and Remediation of Contamination Land. The site surveys were conducted on 18 January and 13 June 2013.
Preparation of Contamination Assessment Plan
9.2.4 According to the findings of desktop study and site surveys, the Contamination Assessment Plan (CAP) for the Study Area was prepared and submitted to EPD and agreed by EPD in August 2013. The CAP is given in Appendix 9.1. Sampling locations for soil and groundwater within the Study Area have been proposed, and the sampling method and testing parameters of soil and groundwater samples have also been specified in the CAP.
Site Investigation and Data Interpretation
9.2.5 Upon completion of the environmental SI works at the potentially contaminated areas given in the CAP, the analytical results of the soil and groundwater shall be interpreted using RBRGs. The nature, level and extend of the land contamination in these potentially contaminated sites shall be evaluated.
9.2.6 However, as the Study Area is managed by private owner and still in operation, therefore undertaking the environmental SI at this EIA stage is not feasible. The proposed environmental SI should be carried out once the operation is terminated and the land is resumed to determine the extent of land contamination.
Preparation of Contamination Assessment Report
9.2.7 Following the completion of environmental SI and lab testing works, the Project Proponent would prepare the Contamination Assessment Report (CAR). The CAR would present the findings of the SI and evaluate the level and extent of potential contamination. If land contamination is identified during the proposed environmental SI and remediation is required, a Remediation Action Plan (RAP) will be prepared.
Aerial Photographs and historical Land Use
9.2.8 Selected
historical aerial photographs between year 1963 and 2011 of the Study Area have
been reviewed in order to ascertain any historical land uses with the potential
for land contamination. The review findings are summarized in the Table 9.3. The historical photographs
are shown in Appendix A of the CAP (Appendix
9.1).
Table 9.3: Description of historical land use of the Study Area
Year |
Description |
1963 |
Parts of the
area between the southern and western portions were exposed, which are seen that the quarry was operated. The northern and eastern parts were natural terrain. Farm
lands could be observed on the most northern area near the site boundary. Anderson
Road had been seen. |
1973 |
The area of
the quarry activities was extended
between the southern and western areas. The area next to the farm lands on
the northern portion was also exposed.
Several temporary structures could be seen within these exposed areas. The
eastern part was still natural terrain. |
1982 |
Most of the
areas between the southern and western portions were exposed and quarry-operated. Temporary structures could be seen on
the southern, western and northern areas. The layouts of the structures on
the northern area were similar to the existing
layout. Several conveyor belts could also be seen on the southern and
northern areas. Farm lands on the most northern area were replaced by the vegetation. Several village houses were erected on the western area and close to the
quarry. The eastern part was still natural terrain. |
1993 |
No significant
changes of the land use on the eastern
and southern portions as compared with Year 1982. On the northern area, more
temporary structures and offices were erected, and
suspected as industrial activities or factories. The conveyor belts on the northern
area were dismantled. The layouts
of these building were similar to the existing layout. The village houses on
the western area were dismantled. |
2001 |
No significant
changes of the land use on the southern
portions as compared with Year 1993. The quarry was further extended to the eastern area. On the southwestern and western
areas, more temporary structures were erected and
suspected as industrial activities or
factories. Several conveyor belts was also be seen on the western area. On
the northern area, the structures and office observed in Year 1993 were still
existed and no significant changes. In addition, on the most northern part of
the site, the area was exposed and a lagoon was
formed. Apart from the southern area, the layouts of the structures and office
were similar to the existing layout. |
2011 |
No significant
changes of the land use as compared with Year 2001 except the southern area,
which the temporary structures and conveyor belts were dismantled. On the
most northern part, part of the lagoon had been filled and the size was
reduced significantly as compared with Year 2001. Along the western and
southern boundary, the site formation works at the nearby construction site was
commenced and the area was exposed. |
9.3
Description of the Environment
9.3.1 The Study Area, as delineated in Figure 227724/E/0001, is located on the south-western slopes of the Tai Shueng Tok Hill at the far north-eastern edge of urban East Kowloon, and lies close to the major population centres of Kwun Tong, Lam Tin and Sau Mau Ping. Specifically, the Study Area covers an area of about 86 ha, which includes a platform area of about 40 ha.
9.3.2 The Study Area is divided into northern (ARQ-N) and southern (ARQ-S) parts by the Anderson Road. The northern and southern parts are under the management of KWP Quarry Co. Ltd. and China State Construction Ltd. (i.e. main contractor of Contract No. CV/2007/03 Development at Anderson Road), respectively, as shown in Figure 227724/E/5005 of the CAP (Appendix 9.1). Approximately 90% of the Study Area falls within the northern part.
Southern Part (ARQ-S)
9.3.3 The entire southern part (ARQ-S) managed by China State Construction Ltd. was exposed and site formation works was in progress. As advised by the Engineer, the land contamination assessment has been carried out in this area under the Agreement No. CE 55/2005 (CE) “Design and Construction of Development at Anderson Road”. The Contamination Assessment Report & Remediation Action Plan (CAR & RAP) had been prepared to present the findings and was endorsed by EPD in November 2006.
9.3.4 According to the approved CAR & RAP, it was revealed that some area was contaminated with heavy metals (i.e. copper, zinc, lead, arsenic, chromium and nickel) and total petroleum hydrocarbons (TPH). Detail of the approved CAR & RAP is given in Appendix D of the CAP (Appendix 9.1).
9.3.5 In addition, as advised by the Engineer, the remediation exercise according to the approved CAR & RAP has been completed. The organic contaminated soil was disposed of at landfill and the treated soil (i.e. after cement solidification / stabilisation of heavy metal contaminated soil) was stockpiled at the designated area for on-site backfilling. Once the backfilling works is completed, a Remediation Report (RR) will be prepared and submitted to EPD for approval under the site formation contract.
Northern Part (ARQ-N)
9.3.6 The northern part of the Study Area under the management of KWP Quarry Co. Ltd. is still under operation. Existing facilities within the northern part include quarry sites, office buildings, crushing plants, concrete block manufacturing plant, concrete and asphalt plants. As advised by the operator, existing operations are gradually withdrawing from the Study Area.
9.3.7 In order to facilitate the assessment, the northern part (ARQ-N) is divided into nine sub-sections, namely ARQ-01 to 09. As shown in Figure 227724/E/5017 of the CAP (Appendix 9.1), the facilities identified in the northern part are tabulated in Table 9.4:
Table 9.4: Summary of existing facilities in the northern part
Existing facilities |
Site ID |
KWP
Quarry Co.Ltd. |
ARQ-01
& 04 |
K.
Wah Asphalt Plant |
ARQ-02 |
K.
Wah Construction Products Ltd. |
ARQ-03 |
K.
Wah Concrete Plant |
ARQ-05 |
Anderson
Concrete Ltd. |
ARQ-06,
07 & 09 |
Pioneer
Asphalt Plant |
ARQ-08 |
9.3.8 In addition, 7 nos. of electric sub-stations were also identified within the Study Area. Among these 7 electric sub-stations, 3 of which are located within ARQ-01, 03 and 08. The locations and details of findings of each electric sub-station are summarized in Table 9.5 and shown in Figure 227724/E/5017 of the CAP (Appendix 9.1).
Table 9.5: Summary of electric sub-stations within the Study Area
Electric
sub-station ID |
Locations |
ESS-01 |
Within the area ARQ-01 |
ESS-02 |
Within the area ARQ-03 |
ESS-03 |
Between Anderson Road and the area ARQ-04 |
ESS-04 |
Next to Anderson Road and between the area
ARQ-07 and ARQ-08 |
ESS-05 |
Within the area ARQ-08 |
ESS-06 |
Next to Anderson Road and between the area
ARQ-08 and ARQ-09 |
ESS-07 |
Nearby the area ARQ-09 |
9.4.1 The RBRGs have developed four different post-restoration land uses, namely “Urban Residential”, “Rural Residential”, “Industrial” and “Public Parks”, to reflect actual settings which people could be exposed to contaminated soil or groundwater. Definitions of post-restoration land uses are given in EPD’s Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management.
9.4.2 According to the Recommended Outline Development Plan of the project, the development plan would be consisted of different facilities, such as residential buildings, schools, amenity, commercial, police and fire stations, pumping station, open space and pedestrian walkway etc. Hence, the most relevant RBRGs corresponding to its future land use should be adopted in assessing its land contamination level. Corresponding RBRGs land use of the associated facilities are defined and given in Table 9.6.
Table 9.6: Post-restoration land use and RBRGs land use
Landuse |
Corresponding RBRGs Land Use |
Commercial /
Residential · Urban High Rise · Low Rise in Rural Area |
Urban Residential Rural Residential |
Commercial / Business &
Office |
Urban Residential |
School |
Rural Residential |
|
Lower of Public Parks or Urban Residential |
Warehouse & Storage |
Industrial |
Government, Institution & Community Facilities |
Urban Residential |
Road including Pedestrian Walkway |
Lower of Industrial or Public Parks |
Railway |
Industrial |
Open Space |
Public Parks |
Public Utilities |
Industrial |
9.5 Potentially Contaminated Area
Identification of Potentially Contaminated Area
9.5.1 Based on the desktop review (i.e. historical aerial photos) and the information collected during the site surveys, potentially contaminated areas within the Study Area have been identified. The areas with those activities, posing potential for contamination, have been identified in accordance with the criteria in EPD’s Practice Guide for Investigation and Remediation of Contaminated Land.
9.5.2 After reviewing of the aforesaid information, the following areas, as summarized in Tables 9.7 and 9.8, are identified as potentially contaminated in the Study Area:
(1) Total 8 areas (i.e. ARQ-01 to 08);
(2) The area of 7 electric sub-stations (3 electric sub-stations are located in ARQ-01, 03 and 08; the remaining 4 electric sub-stations are located standalone).
Environmental Site Investigation
9.5.3 As revealed from the geological profile of the Study Area, three of the eight potentially contaminated areas (i.e. ARQ-01 to 03) are located on rock layer and penetration of the contaminants through the rock layer is unlikely, therefore the environmental SI of these areas is not required. In addition, apart from the electric sub-station (i.e. ESS-05) located in ARQ-08, all other sub-stations are also located on the rock layer, therefore environmental SI for these sub-stations is not required. The locations of the surveyed premises, electric sub-stations and its geology are shown in Figure 227724/E/5017 of the CAP (Appendix 9.1).
9.5.4 Environmental SI is recommended to be carried out in 5 areas (i.e. ARQ-04 to 08 including the electric sub-station in ARQ-08) where located on the fill materials to determine the types and quantities of contaminants.
9.5.5 The environmental SI of potentially contaminated areas is summarized in Tables 9.9 and 9.10.
Table 9.7: Summary of potential
contamination sources of the Study Area
Site ID |
Company |
Site observations |
Potentially Contamination
Sources |
Potentially Contaminated |
ARQ-S |
China State Construction Ltd. |
-
Site formation works was in progress
in entire area -
Remediation exercise was completed -
The treated soil was stockpiled at the designated
area for on-site backfilling |
-
Nil |
No |
ARQ-01 |
KWP Quarry Co. Ltd. |
-
Site
vehicles repairing and maintenance workshops -
Chemical
and chemical waste storage room -
Underground
diesel tank with fuel station -
Electric
sub-station (ESS-01) -
Site
office -
Car
park |
-
Site
vehicles repairing and maintenance workshops -
Chemical
and chemical waste storage room -
Underground
diesel tank with fuel station -
Electric
sub-station (ESS-01) |
Yes |
ARQ-02 |
K. Wah Asphalt Plant |
-
Site
vehicles repairing and maintenance workshops -
Underground
diesel tank with fuel station -
Diesel pump -
Asphalt production facilities -
Chemical
and chemical waste storage room -
Stockpiling structure |
-
Site
vehicles repairing and maintenance workshops -
Underground
diesel tank with fuel station -
Diesel
pump -
Chemical
and chemical waste storage room |
Yes |
ARQ-03 |
K. Wah Construction Products Ltd. |
-
Site
vehicles repairing and maintenance workshop -
Chemical
storage room -
Aboveground diesel tank -
Electric
sub-station (ESS-02) -
Brick production plant -
Stockpiling area |
-
Site
vehicles repairing and maintenance workshop -
Chemical
storage room -
Aboveground
diesel tank -
Electric
sub-station (ESS-02) |
Yes |
ARQ-04 |
KWP Quarry Co. Ltd. |
-
Maintenance
workshop with chemical waste storage area -
Temporary structure for stockpiling -
Screening plant -
Crushing plant |
-
Maintenance
workshop with chemical waste storage area |
Yes |
ARQ-05 |
K. Wah Concrete Plant |
-
Maintenance
workshop with chemical waste storage area -
Stockpiling area -
Concrete production facilities |
-
Maintenance
workshop with chemical waste storage area |
Yes |
ARQ-06 |
Anderson Concrete Ltd. |
-
Chemical
storage room -
Diesel
drum storage room -
Concrete production facilities -
Temporary structure |
-
Chemical
storage room -
Diesel
drum storage room |
Yes |
ARQ-07 |
Anderson Concrete Ltd. |
-
Site
vehicles repairing and maintenance workshop with chemical waste storage area -
Site office |
-
Site
vehicles repairing and maintenance workshop with chemical waste storage area |
Yes |
ARQ-08 |
Pioneer Asphalts Plant |
-
Abandoned asphalt production facilities and boiler -
Site
vehicle repairing and maintenance workshop -
Chemical
and chemical waste storage room -
Aboveground
diesel tank -
Electric sub-station (ESS-05) -
Stockpiling area -
Site office |
-
Abandoned asphalt
production facilities and boiler -
Site
vehicle repairing and maintenance workshop -
Chemical
and chemical waste storage room -
Aboveground
diesel tank -
Electric sub-station (ESS-05) |
Yes |
ARQ-09 |
Anderson Concrete Ltd. |
-
Open car park |
-
Nil |
No |
Table 9.8: Site survey findings
of electric sub-stations within the Study Area
Electric
sub-station ID |
Site observation |
Potentially Contaminated |
ESS-01 |
The condition of sub-station could not be
identified due to restricted access. |
Yes |
ESS-02 |
||
ESS-03 |
||
ESS-04 |
||
ESS-05 |
Transformer was observed in the sub-station. |
|
ESS-06 |
||
ESS-07 |
The condition of sub-station could not be
identified due to restricted access. |
Table
9.9: Summary of environmental SI of potentially contaminated
area
Site ID |
Company |
Potentially Contamination
Sources |
Geology |
Environmental SI |
ARQ-01 |
KWP Quarry Co. Ltd. |
-
Site
vehicles repairing and maintenance workshops -
Chemical
and chemical waste storage room -
Underground
diesel tank with fuel station -
Electric
sub-station (ESS-01) |
Rock |
Not required |
ARQ-02 |
K.Wah Asphalt Plant |
-
Site
vehicles repairing and maintenance workshops -
Underground
diesel tank with fuel station -
Diesel
pump within the asphalt production facilities -
Chemical
and chemical waste storage room |
Rock |
Not required |
ARQ-03 |
K.Wah Construction
Products Ltd. |
-
Site
vehicles repairing and maintenance workshop -
Chemical
storage room -
Aboveground
diesel tank -
Electric
sub-station (ESS-02) |
Rock |
Not required |
ARQ-04 |
KWP Quarry Co. Ltd. |
-
Maintenance
workshop with chemical waste storage area |
Rock and fill materials |
Required |
ARQ-05 |
K.Wah Concrete Plant |
-
Maintenance
workshop with chemical waste storage area |
Fill materials |
Required |
ARQ-06 |
Anderson Concrete Ltd. |
-
Chemical
storage room -
Diesel
drum storage room |
Fill materials |
Required |
ARQ-07 |
Anderson Concrete Ltd. |
-
Site
vehicles repairing and maintenance workshop with chemical waste storage area |
Fill materials |
Required |
ARQ-08 |
Pioneer Asphalts Plant |
-
Abandoned asphalt
production facilities and boiler -
Site
vehicle repairing and maintenance workshop -
Chemical
and chemical waste storage room -
Aboveground
diesel tank -
Electric sub-station (ESS-05) |
Fill materials |
Required |
Table 9.10: Summary of environmental SI of potentially contaminated area of electric
sub-stations
Electric
sub-station ID |
Location |
Geology |
Environmental SI |
ESS-01 |
Within the area ARQ-01 |
Rock |
Not required |
ESS-02 |
Within the area ARQ-03 |
||
ESS-03 |
Between Anderson Road and the area ARQ-04 |
||
ESS-04 |
Next to Anderson Road and between the area
ARQ-07 and ARQ-08 |
||
ESS-05 |
Within the area ARQ-08 |
Fill materials |
Required |
ESS-06 |
Next to Anderson Road and between the area
ARQ-08 and ARQ-09 |
Rock |
Not required |
ESS-07 |
Nearby the area ARQ-09 |
Proposed Site Investigation for Potentially Contaminated Areas
9.6.1 Within the five potentially contaminated areas proposed for environmental SI (i.e. ARQ-04 to 08), a total of 29 locations are proposed for soil and groundwater sampling and testing (i.e. BH-01 to 29) according to the EPD’s Practice Guide for Investigation and Remediation of Contaminated Land. The environmental SI works shall be supervised by the on-site Land Contamination Specialist.
9.6.2 The collected soil and groundwater samples would be analyzed for the parameters which have been selected with reference to the EPD’s Practice Guide for Investigation and Remediation of Contamination Land and based on the potentially contaminated sources. All soil and groundwater samples shall be analysed by a HOKLAS accredited laboratory. The details of sampling and testing strategy are given in the CAP (Appendix 9.1).
9.6.3 As the Study Area is managed by private owner and still in operation, therefore undertaking the environmental SI at this EIA stage is not feasible. The proposed environmental SI should be carried out once the operation is terminated and the land is resumed to determine the extent of land contamination.
Submission Requirements of CAR, RAP and RR
9.6.4 As mentioned in Section 9.4, the most relevant RBRGs corresponding to the future landuse should be adopted in assessing its land contamination level. Laboratory testing results from site investigation should be compared with correspondent RBRGs for the testing parameters in accordance with the EPD’s Guidance Manual for Use of RBRGs for Contaminated Land Management.
9.6.5 Following the completion of environmental SI and lab testing works, the Project Proponent would prepare the Contamination Assessment Report (CAR). The CAR would present the findings of the SI and evaluate the level and extent of potential contamination. The potential environmental and human health impact based on the extent of potential contamination identified would also be evaluated.
9.6.6 If land contamination is
identified during the proposed environmental SI and remediation is required, a Remediation Action Plan
(RAP) will be prepared. The objectives of RAP are:
(1) To undertake further site investigation where required;
(2) To evaluate and recommend appropriate remedial measures for the contaminated materials identified in the assessment;
(3) To recommend good handling practices for the contaminated materials during the remediation works;
(4) To recommend approximate handling and disposal measures; and
(5) To formulate optimal and cost-effective mitigation and remedial measures for EPD’s agreement.
9.6.7 A Remediation Report (RR)
would also be prepared to demonstrate that the clean-up works are adequate. No
construction / development works would be carried out within the potentially
contaminated areas in the Study Area prior to the agreement of the RR.
9.7
Environmental Acceptability of Schedule 2
Designated Projects
9.7.1 The engineering feasibility study of the proposed ARQ development is a
Schedule 3 Designed Project (DP) under the EIAO, whilst there will be two
Schedule 2 DPs; i.e. road improvement works and rock cavern developments under the ARQ project. Details of
these two Schedule 2 DPs are provided in Section
1.4 and
shown in Figure 227724/E/0002.
Road Improvement Works
9.7.2 Three road
improvement works were proposed at junction of (J/O) Lin Tak Road and Sau Mau Ping Road, at J/O Clear Water Bay Road and
Road L1 of Development of Anderson Road (DAR),
as well as at the new merging lane at New
Clear Water Bay Road near Shun Lee Tsuen
Road.
9.7.3 Selected
historical aerial photographs between year 1963 and 2011 of the works areas of
3 road improvement works have been reviewed, and no historical land uses with
the potential for land contamination is observed. The review findings are
summarized in the Table 9.11. The
historical photographs are shown in Appendix
9.2.
Table 9.11: Description of historical land use of the Works Areas of Road
Improvement Works
Road
Improvement Works |
Year |
Description |
Junction of
Lin Tak Road and Sau Mau Ping Road |
1963 |
The whole area
was natural terrain and water pond was seen on the northern part. |
1973 |
Sau Mau Ping
Road and Tsuen Kwan O Road were seen. The remained area was still natural
terrain and water pond was also seen on the northern part. |
|
1982 |
Tsuen Kwan O
Tunnel was under construction and part of the natural terrain on the eastern
part was exposed. A water pond was also seen on the northern part. |
|
1993 |
Tsuen Kwan O
Tunnel was in operation. Lin Tak Road was formed and connected to Sau Mau
Ping Road. |
|
2001 |
No significant
changes of the land use as
compared with Year 1993. |
|
2011 |
No significant
changes of the land use as
compared with Year 2001. |
|
Junction of
Clear Water Bay Road and Road L1 of Development of Anderson Road |
1963 |
The Clear
Water Bay Road was seen and the vegetation was along the road side. |
1973 |
No significant
changes of the land use as
compared with Year 1963. |
|
1982 |
The Clear
Water Bay Road was widened and the new junction was seen on the western part.
2 man-made slopes were found at previous vegetation area. |
|
1993 |
Tree planting
on the man-made slopes was observed. |
|
2001 |
No significant
changes of the land use as
compared with Year 1993. |
|
2011 |
No significant
changes of the land use as
compared with Year 2001. |
|
New Merging
Lane at New Water Clear Bay Road near Shun Lee Tsuen Road |
1963 |
The area was
mainly occupied by the farm lands and few village houses were observed on the
western part. |
1973 |
All farm lands
were removed and the area was exposed. Few village houses were still observed
on the western part. |
|
1982 |
The New Clear
Water Bay Road (include the junction) was formed and in operation. |
|
1993 |
No significant
changes of the land use as
compared with Year 1982. |
|
2001 |
No significant
changes of the land use as
compared with Year 1993. |
|
2011 |
Small area of
slope formation works beside New Clear Water Bay Road was observed. |
9.7.4 Since there was no
contaminative historical land use within the works areas of 3 road improvement
works as well as all road improvement works will only be carried out on
existing roads and associated rock
slopes and nature slopes, therefore land contamination issue is unlikely
to be anticipated. Notwithstanding
this, detailed land contamination assessment of this Schedule 2 DP will be
carried out in a separate EIA under the EIAO.
Rock Cavern Developments
9.7.5 The proposed cavern development are
located on the hillside of the proposed ARQ Development, where are currently
bare rock slope surface, and land contamination issue is therefore not
anticipated.
9.8.1 This land contamination assessment examined the potential contaminative land use within the Study Area and their potential impacts to future land use. The assessment involved desktop review, site surveys and proposed environmental SI.
9.8.2 The Study Area is located on top of rock surface and fill materials. According to its geological profile, environmental Site Investigation (SI) (i.e. borehole drilling, soil and groundwater sampling and testing) is recommended to be carried out for the areas located on fill material to determine the types and quantities of contaminants. A total of five potentially contaminated areas within the Study Area were proposed for environmental SI.
9.8.3 As all areas proposed for environmental SI are privately owned and still in operation, undertaking the environmental SI works at this EIA stage is not feasible. The proposed environmental SI works for these areas should commence once the operation is terminated and the land is resumed.
9.8.4 Following the completion of
the environmental SI works, a CAR will be prepared to present the findings and evaluate the level and extent of potential
contamination. If land contamination is identified and remediation is required,
a RAP will be prepared to recommend specific remediation measures. Upon
completion of the remediation works, if any, a RR that demonstrates the
clean-up works are adequate would also be prepared. CAR, RAP and RR would be
submitted to EPD for approval prior to commencement of any construction /
development works.