Content |
Chapter Title
Table 19.1: Emission Inventory for 2011
scenario, 2031 (3RS) scenario and 2031 (2RS) scenario Table 19.4:__ Summary of Environmental Impacts |
ˇ
Air
quality impact
ˇ
Hazard
to human life
ˇ
Noise
impact
ˇ
Water
quality impact
ˇ
Sewerage
and sewage treatment implications
ˇ
Waste
management implications
ˇ
Land
contamination
ˇ
Terrestrial
ecology
ˇ
Marine
ecology
ˇ
Fisheries
impact
ˇ
Landscape
and visual impact
ˇ
Cultural
heritage
ˇ
Health
impact
ˇ
Assigning
the existing South Runway as standby mode wherever practicable during the
night-time period (2300 to 0659) to minimise aircraft
noise impact and its potential health impacts on the residents in North Lantau
area including Tung Chung;
ˇ
Requiring
departures to take the southbound route via West Lamma
Channel during east flow at night from 2300 to 0659, which is an arrangement
that is consistent with the existing requirement in the operation of the
two-runway system at night, subject to
acceptable operational and safety consideration;
ˇ
Relocating
arrivals to runways for west flow direction (i.e., 25 Runways) via new arrival
Track 6 from straight-in Tracks 4 and 5; and
ˇ
When
wind directions allow without compromising air traffic safety, implementing a
preferential runway use programme such that west flow
is used when departures dominate while east flow is used when arrivals dominate
during night-time.
ˇ
Implementing
relevant control measures as required in the Air Pollution Control
(Construction Dust) Regulation to minimise dust
generation
ˇ
Applying
frequent water spraying of 12 times a day or once every two hours for 24-hour working
and covering 80% of the stockpiling area with impervious sheets for effective
dust control
ˇ
Adopt
best practices as stipulated in the Guidance Note on the Best Practicable Means
for Cement Works (Concrete Batching Plant), Tar and Bitumen Works (Asphaltic
Concrete Plant) and Mineral Works (Stone Crushing Plants) for emission control
ˇ
Implementing
appropriate marine traffic management system to minimise
risk of collision
ˇ
Pigging
should be used to check the integrity of the new submarine pipeline during
testing and commission to ensure the new pipeline is fit for operation
ˇ
Regular
checking of whether any subsidence occurs along the underground pipeline to minimise the risk of leakage
ˇ
Improvement
audit to reinforce existing refuelling practices and
to achieve better compliance.
ˇ
In
addition to the aircraft noise mitigation measures that will be implemented as
standard HKIA operating procedures of the 3RS as described in Section 19.2.2.10,
consideration of land-use planning such as imposing land use constraints for
planned land use to avoid affecting new NSRs
ˇ
Providing
a noise enclosure for the engine run-up facility to reduce noise emission
ˇ
Selection
of quieter plant and use of noise barriers / acoustic shed / noise insulating
fabric during construction phase to reduce construction noise impacts to nearby
NSRs
ˇ
Limiting
construction activities at Sha Chau and providing containment around the
daylighting point to minimise runoff / leakage
ˇ
Implementing
a ‘zero discharge’policy for activities at Sha Chau to
avoid polluting the marine environment
ˇ
Use
of closed grabs for field joint excavation for diversion of submarine 11 kV
cables and construction of runway approach lights / Hong Kong International
Airport Approach Area marker beacons to minimise SS
and contaminant release
ˇ
Implementing
the mitigation measures recommended for control of suspended solids release
ˇ
Implementing
site practices as outlined in ProPECC Note PN 1/94 to
control and minimise site runoff and drainage
ˇ
Install
and maintain roadside gullies and oil / grease interceptors for removal of
pollutants from stormwater
ˇ
Implementing
a ‘spill trap containment system’ and an emergency spill response plan for minimising the
potential water quality impacts due to spillage events
ˇ
Upgrade
the existing gravity sewer, the Tung Chung Sewage Pumping Station and the Shiu Ho Wan Sewage Treatment Works to ensure proper
handling of sewage flow from the expanded airport under the worst case scenario
ˇ
Good
waste management and control practices to avoid generation of excessive amount
of waste materials
ˇ
Good
site practices to alleviate impacts related to waste management such as dust, odour and noise
ˇ
Implementation
of a trip-ticket system promulgated under DEVB TC(W) No. 6/2010 to monitor
off-site delivery of surplus inert C&D materials and to control fly tipping
ˇ
Maximise the use of suitable fill materials available
from other concurrent projects and the Government’s PFRF for the land formation
works
ˇ
Handling
of chemical wastes in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes, and disposal of chemical wastes at
licensed chemical waste recycling/ treatment facilities
ˇ
Proper
design of the artificial seawall of the expanded airport island to achieve a
shoreline without any sharp turns or abrupt indentation where floating refuse
would easily trapped or accumulated
ˇ
Employ
reputable licensed waste collectors for disposal of general refuse and floating
refuse
ˇ
The
daylighting location of the diverted submarine pipelines to be
positioned away from the boundary of the egretry on Sheung
Sha Chau Island in order to avoid direct impact to the egretry
ˇ
Timing
the pipeline connection works in the vicinity of the egretry outside the ardeid’s breeding season (April - July)
ˇ
Strict
enforcement of no-dumping policy and good site practices during construction
phase
ˇ
Pre-construction dive survey to check the status of coral to be affected
by the project and review the feasibility in translocating
the corals
ˇ
Deployment
of dolphin exclusion zone of 250 m in radius during marine works at both daytime
and night-time to minimise impacts to dolphins during
construction phase
ˇ
Noisy construction equipment mounted on steel barges to be
acoustically-decoupled to reduce its potential noise impacts on cetaceans
ˇ
Avoiding
peak calving seasons of CWD for bored piling works
ˇ
Implementing
construction vessel speed limits as well as speed restriction and route
diversion for the SkyPier high speed ferries to
alleviate the potential impacts on CWD
ˇ
Establishment of new marine park of approximately 2,400 ha
linking the existing / planned marine parks and the extended HKIAAA to
alleviate the potential impacts on CWD
ˇ
Establishment
of new marine park of approximately 2,400 ha linking the existing / planned
marine parks and the extended HKIAAA
ˇ
Minimising construction areas, construction period and
construction traffic as far as practical
ˇ
Erection
of decorative mesh screens or construction hoardings around works areas in
visually unobtrusive colours to minimise
visual intrusion
ˇ
Sensitive
landscape design of land formation edge, as well as buildings and structures
ˇ
Implement
greening measures, including vertical greening, green roofs, road verge
planting and peripheral screen planting where practical to improve the
landscape and visual aesthetics
ˇ
Compensatory
Tree Planting for all felled trees to replace affected trees
ˇ
Sensitive
design of streetscapes (e.g. paving, signage, street furniture, lighting etc.)
and viaduct structures to minimise visual intrusion
ˇ
Adverse
air quality and noise impacts on air and noise sensitive receivers within the
assessment areas have been minimised
ˇ
Approximately
270,000 residential population within the operational air quality assessment
area will not be affected
ˇ
About 370 village
houses / licensed structures along north Lantau shoreline have been protected
by provision of indirect noise mitigation measures
ˇ
An overall reduction
in future population that would be subject to annoyance and self-reported sleep
disturbance (with about 10% and 50% reduction of population affected
respectively), with implementation of the third runway in the assessment area
ˇ
1,200
ha of marine environment within the Sha Chau and Lung Kwu Chau Marine Park
ˇ
Breeding
population of ardeids at the Sha Chau egretry
ˇ
18
out of 19 nos. of LRs and 10 out of 11 nos. of LCAs within the defined
landscape study area; and 77 out of 79 nos. of potential existing and planned
VSRs within the visual envelope of the project and associated works.
ˇ
Use
of non-dredge ground improvement methods for land formation will completely avoid
bulk removal and disposal of any dredged materials and minimise
SS and contaminants release into marine environment, and hence minimised impacts on marine ecology and fisheries.
ˇ
Use
of horizontal directional drill (HDD) method for submarine fuel pipelines
diversion will completely avoid dredging of seabed, thereby eliminating any
impacts on marine water quality and marine ecology including impacts on the Sha
Chau and Lung Kwu Chau Marine Park.
ˇ
Disturbance
to the breeding ardeids in the Sha Chau egretry will
be minimised by proper selection of the daylighting
location of fuel pipeline.
ˇ
Use
of water jetting method to lay the new 11 kV cable for connection to the
existing cable at over 500 m from the boundary of the Sha Chau and Lung Kwu
Chau Marine Park will minimise generation and
disposal of any marine sediment and avoid disturbing the seabed inside the
Marine Park
ˇ
Reuse
of inert construction and demolition (C&D) materials as far as practicable
to minimise off-site delivery of surplus inert
C&D materials and the associated environmental impacts.
ˇ
Excavated
marine sediments will be treated and reused on-site as backfilling materials,
thereby avoiding the need for off-site disposal.
ˇ
Aircraft
emissions and aircraft noise will be minimised by
improved airport operational efficiency; and proper management including
control on use of runways and flight tracks; and prohibiting aircraft with
idling engines at parking stands.
ˇ
Air
quality and health impacts will be minimised by
enforcing the use of fuel-efficient airside vehicles; provision of cleanest
diesel and gasoline at the airfield; and increase use of electric vehicles and
etc.
ˇ
Impacts
on the adjacent landscape including LRs, LCAs and VSRs will be minimised by appropriate landscape and visual appearance
designs.
Table 19.1: Emission
Inventory for 2011 scenario, 2031 (3RS) scenario and 2031 (2RS) scenario
Year |
Total Annual Emission (kg) |
||
NOx |
RSP |
FSP |
|
2011 |
~ 7,500,000 |
~ 220,000 |
~ 150,000 |
2031 (3RS) |
~ 9,500,000 |
~ 220,000 |
~ 91,000 |
2031 (2RS) |
~ 6,700,000 |
~ 163,000 |
~ 67,000 |
ˇ
Continuous
improvement in engine technology to fulfil ICAO aviation emission standard;
ˇ
Improvement
in fuel efficiency;
ˇ
Banning
the use of APU at the stands; and
ˇ
Adoption
of the latest international airside and landside vehicular emission standard.
ˇ
Shifting
of dominant aircraft departure from the South Runway (2RS scenario) to the
Centre Runway (3RS scenario); and
ˇ
Assigning
the existing South Runway as standby mode wherever practicable during the
night-time period between 2300 and 0659.
Table19.2: Concentration Breakdown for the Cumulative NO2 Impact at the Key Sensitive Area under the 3RS
scenario
Area |
ASR |
Airport
Related Emission (mg/m3) |
Proximity
Infrastructure Emission (mg/m3) |
Ambient (mg/m3) |
Cumulative
Impact (mg/m3) |
Tung Chung |
TC-22 |
2 |
9 |
22 |
33 |
Tung Chung West |
TC-P7 |
2 |
6 |
22 |
30 |
Tung Chung East |
TC-P12 |
2 |
4 |
22 |
28 |
Sha Lo Wan |
SLW-1 |
12 |
4 |
20 |
36 |
Tuen Mun[1] |
TM-10 |
2 [1] |
9 |
27 |
38 |
Note:
[1] Airport
related emission is included in ambient in PATH model for Tuen Mun area.
ˇ
Banned
all idling vehicle engines on the airside since 2008, except for certain
vehicles that are exempted (This measure has already been incorporated in the
model for 2031 3RS scenario simulation)
ˇ
Banning
the use of APU for all aircraft at frontal stands by end 2014 (This measure has
already been incorporated in the model for 2031 3RS scenario simulation)
ˇ
Requiring
all saloon vehicles as electric vehicles by end 2017 (This measure has already
been incorporated in the model for 2031 3RS scenario simulation)
ˇ
Increasing
charging stations for EVs and electric GSE to a total of 290 by end 2018
ˇ
Conducting
review on existing GSE emission performance and explore measures to further
control air emissions
ˇ
Exploring
with franchisees feasibility of expediting replacement of old airside vehicles
and GSE with cleaner ones during tender or renewal of contracts
ˇ
Requiring
all new airside vehicles to be fuel-efficient and making it a prerequisite for
the licensing process;
ˇ
Providing
the cleanest diesel and gasoline at the airfield;
ˇ
Requiring
all of the AAHK’s diesel vehicles to use biodiesel (B5);
ˇ
Promoting
increased use of electric vehicles and electric ground service equipment at
HKIA by provision of charging infrastructure; and
ˇ
Providing
a liquefied petroleum gas (LPG) fuelling point for airside vehicles and ground
service equipment.
Table 19.3: Key
Assessment Assumptions, Limitations of Assessment Methodologies and Prior
Agreements
Table 19.4: Summary
of Environmental Impacts
Assessment
Points |
Results of Impact Predictions |
Relevant Standards / Criteria |
Extent of Exceedances
Predicted |
Impact Avoidance Measures
Considered |
Mitigation Measures Proposed |
Residual Impacts |
Air Quality Impact – Construction Phase |
||||||
Air Sensitive Receivers within 500 m Assessment area |
§ Compliance with the hourly TSP criterion as well as the AQOs for daily RSP and daily FSP at all ASRs under the mitigated scenario § Compliance with the AQO for annual RSP and annual FSP at all ASRs under the mitigated scenario |
§ Annexes 4 and 12 of EIAO-TM § Air Pollution Control Ordinance § AQO |
With the mitigation measures in place, the predicted cumulative TSP, RSP and FSP levels at all ASRs would comply with the relevant TSP criterion as well as the relevant AQO for RSP and FSP. |
N/A |
§ Relevant measures stipulated in Air Pollution Control (Construction Dust) Regulation § Water spraying for heavy construction activities at all active works areas, at a frequency of 12 times a day or once every two hours for a 24-hour working period § 80% of the stockpiling area covered by impervious sheets and all dusty materials sprayed with water immediately prior to any loading transfer operation § Good practices for dust control § Relevant measures stipulated in EPD’s Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) § Relevant measures stipulated in EPD’s Guidance Note on the Best Practicable Means for Tar and Bitumen Works (Asphaltic Concrete Plant) BPM 15 (94) § Relevant measures stipulated in EPD’s Guidance Note on the Best Practicable Means for Mineral Works (Stone Crushing Plants) BPM 11/1 (95) |
Adverse residual impact is not anticipated. |
Air Quality Impact – Operation
Phase |
||||||
Air sensitive receivers within 5km assessment area |
NO2, RSP, FSP SO2, and CO levels would comply with the AQO at all ASRs |
§ Annexes 4 and 12 of EIAO-TM § Air Pollution Control Ordinance § AQO |
No non-compliance of AQO was predicted on identified ASRs |
AAHK has already been implementing a number of initiatives aimed at reducing air emissions from airport activities and operations, including: § Banned all idling vehicle engines on the airside since 2008, except for certain vehicles that are exempted ; § Banning the use of APU for all aircraft at frontal stands by end-2014; § Requiring all airside saloon vehicles to be electric by end-2017; § Increasing charging stations for EVs and electric GSE to a total of 290 by end-2018; § Conducting a review on existing GSE emissions performance and exploring measures to further control air emissions; § Exploring with franchisees the feasibility of expediting replacement of old airside vehicles and GSE with cleaner ones during tender or renewal of contracts; § Requiring all new airside vehicles to be fuel-efficient, and making it a prerequisite for the licensing process; § Providing the cleanest diesel and gasoline at the airfield; § Requiring all of the AAHK’s diesel vehicles to use biodiesel (B5); and § Providing an LPG fuelling point for airside vehicles and GSE. |
N/A |
Adverse residual impact is not anticipated. |
Hazard
to Human Life – Construction Phase |
||||||
Risk due to construction works near: § Existing aviation fuel pipeline; and § Storage facilities |
§ The individual risk level is below 1 x 10-5 per year; and § Societal risk level is in the acceptable region |
Annex 4 of EIAO-TM |
N/A |
Mitigation measure is not necessary due to the fact that the societal risk level is in the acceptable region |
Although mitigation measure is not required due to the fact that the societal risk level is in the acceptable region, the following measures have been recommended for general best practice: § Precaution measures should be established to request barges to move away during typhoons; § An appropriate marine traffic management system should be established to minimise risk of collision, which could lead to sinking or dropped objects; and § Location of all existing hydrant networks should be clearly identified prior to any construction works. |
Adverse residual impact is not predicted. |
Hazard
to Human Life – Operation Phase |
||||||
Risk due to the operation of: § New aviation fuel pipelines (submarine and underground); § New fuel hydrant systems for aircraft refuelling operation at the new aircraft stands in the airport expansion area; and § Airside petrol filling station |
§ The individual risk level is below 1 x 10-5 per year; and § Societal risk level is in ALARP region |
Annex 4 of EIAO-TM |
N/A |
§ A similar coating standard shall be applied to the new submarine pipelines as for the existing pipelines § Checks on the integrity of the new submarine pipeline should be conducted during testing and commission § Before the commencement of any construction works, as-built drawings showing the alignment and level of the underground aviation fuel pipelines for the work area will be provided to the third party construction contractors § Third party construction contractors are required to undertake underground pipeline detection works to ascertain the exact alignment of the underground pipeline before the commencement of works § Monitoring of underground pipelines by the Leak Detection System should be provided § Study should be conducted to ensure the new pipeline can withstand the planned future loading § New pressure surge calculations are required for the hydrant network § Appropriate pressure drop calculations should be undertaken for the new system |
§ Improvement audit to reinforce existing refuelling practices and to achieve better compliance § During refuelling process, four cones are to be put in place to indicate the refuelling zone from aircraft fuelling point for the new fuel hydrant system where practicable. AAHK will communicate this recommendation to airlines and their refuelling operators as appropriate. Proper implementation of this recommendation will be checked in AAHK’s future safety audits. |
§ The individual risk level is below 1 x 10-5 per year; and § Societal risk level is in ALARP region. |
Noise Impact – Aircraft
Noise |
||||||
Aircraft Noise Whole Hong Kong territory |
NEF 25 and NEF 30 contours |
NEF25 for all domestic premises, hotels, educational institutions, places of worship, courts of law and hospitals; and NEF 30 for offices (Ref. Table 1A,
Annex 5 of EIAO-TM) |
A portion of land use in Lok On Pai under planning |
The following noise abatement practices currently adopted for the existing airport operation will be continued and maintained for the future airport operation: § aircraft
departing to the northeast are required to adopt the noise abatement take-off
procedures stipulated by ICAO so long as safe flight operations permit; and § all aircraft on approach to the HKIA from the northeast between 11:00 pm to 07:00 am are encouraged to adopt the Continuous Descent Approach. |
§ Putting the
South Runway on standby where possible at night between 2300 and 0659; § Requiring departures
to take the southbound route via the West Lamma
Channel during east flow at night from 2300 to 0659, subject to acceptable
operational and safety consideration. This is an arrangement that is
consistent with the existing requirement in the operation of the two-runway
system at night; § A new arrival RNP Track 6 has been
designed for preferential use in the west flow direction (i.e., runway 25 direction) between 2300 and 0659 and it is assumed
that up to 95% of flights may preferentially use this new Track 6 instead of
the existing straight-in tracks by year 2030; § Implementing a preferential runway use programme when wind conditions allow, such that west flow is used when departures dominate while east flow is used when arrivals dominate during night-time; and § Direct measures – when developing the MLP for the CDA site at Lok On Pai, the alignment of the NEF25 contour line should be taken into account to ensure that no noise sensitive uses are situated within the NEF25 contour in the planned development[1]. |
N/A |
Noise Impact – Fixed Noise
Sources |
||||||
Assessment area boundary has been established against the criteria of 70 dB(A) (for daytime/evening periods) or 60 dB(A) (for night-time period) under several worst assumptions. |
With the recommended avoidance and mitigation measures in place, the cumulative mitigated noise levels due to fixed noise sources, including ground noise sources associated with the aircraft taxiing as well as the operations of aircraft engine run-up facilities and APUs, would comply with the relevant daytime/evening and night-time criteria at all representative NSRs. |
§ Noise Control Ordinance; § EIAO-TM; relevant Guidance Notes under EIAO; and § Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites. |
With the avoidance and mitigation measures in place, no exceedance of the relevant noise criteria at any representative NSRs was predicted. |
Specification of the maximum permissible SWLs of the project’s fixed plants during daytime/evening and night-time should be followed. |
Noise enclosure with noise reduction of at least 15 dB(A) at the ERUFs is required to comply with the relevant day & evening and night-time fixed noise criteria. |
Adverse residual impact is not anticipated. |
Noise Impact –
Construction Noise |
||||||
The first layer of NSRs (nearest to the noise sources in various directions) has been selected as the assessment points. |
With the recommended avoidance and mitigation measures in place, the cumulative mitigated noise levels would comply with the daytime construction noise criterion at all representative NSRs. |
§ Noise Control Ordinance; § EIAO-TM; relevant Guidance Notes under EIAO; and § Technical Memorandum on Noise from Construction Work other than Percussive Piling. |
With the avoidance and mitigation measures in place, no exceedance of the daytime construction noise criterion at any representative NSRs was predicted. |
Good
site practice to limit noise emissions at source as follows: § Only
well-maintained plant to be operated on-site, and plant should be serviced
regularly during the construction works § Machines and
plant that may be in intermittent use to be shut down between work periods,
or throttled down to a minimum § Plant known to
emit noise strongly in one direction should, where possible, be orientated to
direct noise away from the NSRs § Mobile plant
should be sited as far away from NSRs as possible § Material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities |
§ Selection of
quieter plant § Use of movable
noise barrier § Use of noise enclosure / acoustic shed |
Adverse residual impact is not anticipated. |
Noise Impact – Traffic
Noise |
||||||
For road traffic noise, assessment shall generally include areas within 300 m from the
boundary of the project and the works of the project. For marine traffic noise, the assessment area has been established against the standard where the predicted marine traffic noise at the boundary of area is 10 dB(A) below the prevailing background noise level at the nearest NSR. |
For road traffic
noise, adverse noise impact from the proposed road alignments is not
anticipated as the nearby NSRs are all found to be located beyond the 300m
assessment area for the proposed road alignments of 3RS project For marine traffic noise, adverse noise impact is not anticipated as the nearby NSRs are all found to be located outside the assessment area. |
§ Noise Control Ordinance; and § EIAO-TM; relevant Guidance Notes under EIAO |
N/A |
N/A |
N/A |
Adverse road
traffic noise impact is not anticipated. Adverse marine traffic noise impact is not anticipated. |
Water Quality Impact – Construction Phase |
||||||
WSRs within: § North Western WCZ; § North Western
Supplementary WCZ; § Deep Bay WCZ; and § Western Buffer WCZ |
§ No exceedance of sedimentation criteria § No adverse water
quality impact due to depletion of dissolved oxygen at WSRs from submarine
cable diversion § No adverse water
quality impact due to release of contaminants from submarine cable diversion § No adverse water
quality impact due to release of contaminated pore water from DCM activities § No adverse water
quality impact due to release of contaminated pore water from surcharge § No exceedance of depth-averaged SS criteria due
to the project under the mitigated scenario; however, exceedance
of depth-averaged SS criteria at
some WSRs under the mitigated cumulative scenario (primarily due to
conservative assumptions of marine construction activities by other
concurrent projects) § For all other construction activities (e.g. drilling for submarine aviation fuel pipelines, construction / modification of stormwater outfalls, piling for new runway approach lights and HKIAAA marker beacons, construction site runoff and drainage, sewage effluent from construction workforce and general construction activities), no adverse water quality impacts are anticipated with the implementation of the proposed design / construction methods and the recommended mitigation measures where applicable. |
§ EIAO-TM Annex 6
& 14 § Water Pollution
Control Ordinance (WPCO) § North Western WCZ
WQO § North Western
Supplementary WCZ WQO § Deep Bay WCZ WQO § Western Buffer
WCZ WQO § WSD’s water
quality criteria for flushing water intake § Sediment Deposition and SS Criteria for Corals, “Standards and Criteria for Pollution Control in Coral Reef Areas” § UK Council Directive on the quality required of shellfish waters (Shellfish Waters Directive) § Directive 2008/105/EC of the European Parliament and of the Council of 16 December 2008 on environmental quality standards in the field of water policy § The US Environmental Protection Agency (USEPA) Criteria Maximum Concentration (CMC) § The USEPA Criteria Continuous Concentration (CCC) |
For
mitigated SS due to the project only: § No exceedances of
the depth-averaged SS criteria at all WSRs. For
mitigated cumulative SS, no exceedance of the depth-averaged SS criteria at
all WSRs except the following: § C20 – WSD
seawater intake at Tsing Yi – up to 2.5 mg/l above criteria (mainly due to
concurrent projects) § CR3 – Hard corals at The Brothers islands –
up to 1.26 mg/l above criteria (primarily due to conservative assumptions for
concurrent projects[2]) § C7a – cooling water intake at HKIA (North)
– up to 16.91 mg/l above criteria (no exceedance after further mitigation) § C8 – future cooling water intake at HKBCF –
up to 1.23 mg/l above criteria
(no exceedance after further mitigation) § E12 – Sham Shui Kok – up to 4.4 mg/l above criteria (primarily due
to conservative assumptions for the concurrent Lantau Logistics Park (LLP)
project. However, there is currently no implementation programme for this
concurrent project, and the future project at this site will require an EIA
which will minimise the potential water quality impacts associated with this
concurrent project) |
§ Use of non-dredge
ground improvement methods for land formation for avoidance of SS and
contaminants release; § Use of horizontal directional drill (HDD) method for submarine aviation fuel pipelines diversion; § Only welding works will be carried out on
the floating platform, and bulk storage of chemicals is not required at the
daylighting point at Sha Chau; § No dewatering of pipe at Sha Chau; § Provision of a small concrete bund wall
around the high side of the pit, and a cover to prevent rain entry at the
daylighting point at Sha Chau to prevent muddy runoff; § Drilling is conducted via a closed-loop
system at the launching point at airport island, and drilling fluid is
reconditioned and reused; § Use of water jetting method and closed
grabs for field joint excavation for diversion of submarine 11kV cables to
minimise SS and contaminant release; and § Connection works for outfalls to be
undertaken during dry season. |
§ Capping of daily
maximum production rates of relevant land formation works to those assumed in
the water quality assessment; § Restricting the
fines content for sand blanket and marine filling activities; § 200m
advanced / partially completed seawall prior to marine filling operations; § Double layer silt curtain system around selected active works areas; § Double layer silt
curtain and/or silt screen system around selected WSRs; § Use of closed
grabs and silt curtains for field joint excavation activities; § Use of closed
grabs, steel casing and silt curtains for piling activities; § Implementation of
guidelines set in Practice Note for Professional Persons on Construction Site
Drainage (ProPECC Note PN 1/94) ; § Provision of
chemical toilets for construction workforce; § Treatment of wastewater per WPCO requirements prior to discharge; § Treatment of chemical wastes in accordance to Waste Disposal (Chemical Waste) (General) Regulation and Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes; and § ‘Zero discharge’ policy for activities at Sha Chau. |
Adverse residual impact is not predicted. |
Water Quality Impact – Operation
Phase |
||||||
WSRs within: § North Western
WCZ; § North Western
Supplementary WCZ; § Deep Bay WCZ; and § Western Buffer WCZ |
§ No
adverse water quality impacts anticipated due to changes in hydrodynamics ,
but minor exceedances in water quality criteria at
some WSRs; § No
adverse water quality impacts anticipated due to embayment of water at western end of HKIA; § No
adverse water quality impacts anticipated due to sewage discharge; § No
adverse water quality impacts anticipated due to spent cooling water discharge; § No
adverse water quality impacts anticipated due to stormwater discharge; § No
adverse water quality impacts anticipated due to greywater
reuse with the proposed design measures in place; § No adverse water quality impacts anticipated due to accidental fuel spillage with the proposed design and contingency measures in place; and § No need for maintenance dredging of the navigable waters north of HKIA. |
§ EIAO-TM Annex 6
& 14 § WPCO § North Western WCZ
WQO § North Western
Supplementary WCZ WQO § Deep Bay WCZ WQO § Western Buffer
WCZ WQO § WSD’s water quality
criteria for flushing water intake § Criteria for cooling water discharge (e.g. USEPA CCC and ecotoxicology study by Ma et al. (1998)) |
Minor exceedances were predicted for the below parameters and stations: SS (monthly depth-averaged value) C3 – up to 12.0 mg/l C5 – up to 13.2 mg/l C6 – up to 14.9 mg/l TIN (annual depth-averaged value) C1 – up to 0.62 mg/l C9 – up to 1.05 mg/l E1 – up to 3.61 mg/l NH3 (annual depth-averaged
value) C9 – up to 0.026 mg/l E1 – up to 0.134 mg/l Although exceedances were predicted, they were assessed as not attributable to the implementation of the project, but due to the high background levels. |
§
Connection
of sewage of network for treatment of sewage at SHWSTW; §
Reuse
of treated greywater to reduce sewage effluent and fresh
water usage; §
Placement
of submarine aviation fuel
pipelines under seabed rocks to avoid possible damage from marine vessels and
fuel leakage; §
Appropriate
design of the land formation to avoid major changes in local and regional
hydrodynamics; and §
Restrict operation of the fuel supply and
refuelling systems to qualified and trained personnel. |
§ Treatment of
wastewater per WPCO requirements prior to discharge; § Treatment of
chemical wastes in accordance with Waste Disposal (Chemical Waste) (General)
Regulation and Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes; § Install and
maintain roadside gullies to trap and remove silt and grit from stormwater; § Install and
maintain oil/grease and oil/grease interceptors at storm drains; § Intercept and
discharge runoff from aircraft and vehicle washing activities to foul sewer
or divert to temporary storage for treatment off-site; § Fuel pipelines
and hydrant systems should be designed with adequate protection and pressure
/ leakage detection systems; § Provision of a
‘spill trap containment system’ at aircraft apron and stand areas; and § Implement an
emergency spill response plan for spillage events. |
Adverse residual impact is not predicted |
Sewerage
and Sewage Treatment Implication – Construction Phase |
||||||
Refer to the relevant parts of the Water Quality Impact – Construction Phase |
|
|
|
|
||
Sewerage
and Sewage Treatment Implication – Operation Phase |
||||||
§ Gravity sewer from airport discharge manhole to Tung TCSPS § TCSPS § Sewage rising main from TCSPS to SHWSTW § SHWSTW |
§ The existing gravity sewers from the airport discharge manhole to TCSPS would reach its full capacity by 2027 § Pump capacity of TCSPS would be exceeded in 2023 § No adverse impact to the sewage rising main from TCSPS to SHWSTW § No adverse impact to the daily treatment capacity of SHWSTW § Peak flow capacity of SHWSTW would be exceeded from year 2026 |
§ Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning Version 1.0 published by EPD (GESF) § Sewerage Manual – Part 1 published by DSD (SM1) |
N/A |
N/A |
§ The sewerage system for 3RS will be designed, operated and maintained by AAHK in accordance with all the relevant standards and guidelines published by DSD. In addition to continuing the odour control arrangements, AAHK will monitor the H2S level and adopt active septicity management measures that can effectively contain any future septicity problems in the design for the 3RS sewerage system. § AAHK undertakes to implement and complete the upgrading works for the affected gravity sewer by 2026 (allowing a buffer period of about one year before the full capacity is reached), with the planning work to commence in 2022 (assuming one year for planning plus three years for design and construction). AAHK should also monitor the sewage flow build-up as a part of the EM&A for the project and start planning construction of the upgrading works in 2022, or when the sewage flow in the affected gravity sewer exceeds 80% of the design capacity of the sewer, whichever is earlier, so as to ensure timely completion of the mitigation works before the flow would exceed the design capacity of the sewer. § A government project under Agreement No.CE6/2012 is currently underway by DSD to investigate, design and construct an additional sewage rising main between TCSPS and SHWSTW, which would enhance the operational reliability of the sewerage system. Construction is planned to commence in 2015 and complete the works by end 2022. The TCSPS is sufficient to cater for the ultimate design sewage flow arising from the project after the completion of construction under Agreement No. CE6/2012[3]. § EPD will monitor the sewage flow build-up and coordinate the necessary upgrading works for the SHWSTW when needed in due course. |
No adverse residual impacts would be anticipated. |
Waste
Management Implication – Construction Phase |
||||||
Project area |
§ Inert C&D materials of about 9,543,500m3 (in-situ volume) generated from excavation works, piling works, demolition works on the existing airport island / proposed land formation area as well as from HDD during diversion of the existing submarine pipelines; § Non-inert C&D materials of about 96,200m3 (in-situ volume) generated from site clearance of the golf course area, demolition works for the T2 expansion, and various superstructure construction works; § Marine sediment of about 10,200m3 (in-situ volume) generated from excavation at the cable field joint area; § Marine sediment of about 767,660m3 (in-situ volume) generated from the foundation / piling / excavation works for constructing various tunnels, facilities, buildings and APM depot; § Small quantity of chemical waste from maintenance and servicing of construction plant and equipment; § General refuse of maximum daily arising of up to 9,100kg from construction workforce; and § Floating refuse of about 65m3 to be collected from the newly constructed seawall per year. |
§ Annex 7 and 15 of EIAO-TM; § Waste Disposal Ordinance (Cap. 354); § Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C); § Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N); § Building Ordinance (Cap.123); § Land (Miscellaneous Provisions) Ordinance (Cap. 28); § Dumping at Sea Ordinance (Cap. 466); and § Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK). |
N/A |
§ The use of non-dredge methods for ground improvement will completely avoid bulk removal and disposal of any dredged materials; § Most sloping seawall options can allow for the reuse of rock armour from the existing northern seawall to minimise waste generation; § Priority will be given to maximise the use of suitable fill materials available from other concurrent projects and the Government’s PFRF; § Minimise the extent of excavation and maximise on-site reuse of the inert C&D materials generated as far as practicable. The relevant construction activities (particularly for the tunnel works) and construction programme have been carefully planned and developed; § All marine sediments to be generated from the foundation / piling / excavation works for constructing various tunnels, facilities, buildings and APM depot will be treated and reused on-site as backfilling materials, thus avoiding the need for disposal of the sediments; § Using HDD method to construct the new pipeline will avoid dredging of seabed; and § Use of water jetting method to lay the new cable will avoid generation and disposal of any marine sediment. |
§ Good site practices and waste reduction measures for C&D materials § Marine disposal of marine sediments from the cable field joint excavation § Handling of chemical wastes in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, and disposal of chemical wastes at licensed chemical waste recycling/ treatment facilities § Employ a reputable licensed waste collector for disposal of general refuse and floating refuse at designated landfill sites |
No adverse residual impacts would be anticipated. |
Waste
Management Implication – Operation Phase |
||||||
Project area |
§ About 46,190 tons/year of general refuse from the operation of the passenger concourse, aircraft cabins, terminal buildings, offices, commercial establishments and various airport infrastructure facilities; § Chemical waste from maintenance, servicing and repairing of various E&M equipment; § Floating refuse of about 65m3 to be collected from the new artificial seawall per year; and § About 0.23 ton/day of dewatered sludge from the proposed greywater treatment plant |
§ Waste Disposal Ordinance (Cap. 354); and § Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C). |
N/A |
§ The initiatives currently implemented at HKIA in segregating recyclable waste materials (such as cardboard, paper, metals, plastics, glass bottles, food waste, etc.) from general refuse for recycling should be extended to cover the expanded airport; and § The artificial seawall of the expanded airport island has been properly designed to achieve a shoreline without any sharp turns or abrupt indentation where floating refuse would easily be trapped or accumulated. |
§ Employ a reputable licensed waste collector to collect general refuse on a daily basis and dispose of the general refuse at designated landfill sites § Handling of chemical wastes in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, and disposal of chemical wastes at licensed chemical waste recycling/ treatment facilities § Regular cleaning of floating refuse trapped or accumulated on the artificial seawall, and disposal of the floating refuse together with general refuse at designated landfill sites § Employ a reputable licensed waste collector to dispose of the dewatered sludge (stored in tight containers or skips) at designated landfill sites |
No adverse residual impacts would be anticipated. |
Land
Contamination – Construction Phase |
||||||
Potential land contaminative areas within the project |
Land contamination impacts were identified by carrying out land contamination assessment of the past / present land uses of potential contaminative areas. The potential land contaminative areas include: § Golf course area § T2 expansion area (underground and above-ground fuel tank areas, and emergency power generation units) § Existing airside facilities (petrol filling station and fuel tank room) |
§ Section 3 of Annex 19 of EIAO-TM; § Guidance Note for Contaminated Land Assessment and Remediation; § Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management; and § Practice Guide for Investigation and Remediation of Contaminated Land. |
N/A (As all potential land contaminative areas are still under operation, all sampling and testing works will be conducted prior to commencement of any construction works at these areas.) |
N/A |
§ The contaminated soil identified (if any) should be excavated and treated on-site; and § The recommended environmental mitigation and safety measures, progress monitoring and / or confirmation sampling / testing recommended should be implemented. |
No adverse residual impacts would be anticipated. |
Land
Contamination – Operation Phase |
||||||
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Terrestrial
Ecological Impact – Construction and Operation Phases |
||||||
Tai Ho Stream
SSSI, San Tau Beach SSSI, Lung Kwu Chau, Tree Island and Sha Chau SSSI; Open sea to
the north of the existing airport island in relation to the investigation of
birds’ activities over the land formation area and the adjacent waters; All land
areas within 500 m from the coastline of North Lantau
from Sham Wat Wan to Tai Ho Wan; and All land areas
within the boundary of SCLKCMP. |
Low or negligible impacts to the
terrestrial habitats, flora and fauna species in the study area during
construction and operation phases |
§ Annexes 8 and 16
of EIAO-TM. |
N/A |
N/A |
N/A |
None |
Sha Chau
Egretry |
Sha Chau egretry: moderate impact due to
the fuel pipeline installation works; but no impact during operation phase |
§ EIAO-TM,
particularly Annexes 8 and 16. |
N/A |
§ Avoidance of
direct impact to egretry – the daylighting location should be outside egretry
boundary § Construction
activities at Sheung Sha Chau Island should avoid
night-time and the ardeid’s breeding season (April – July). |
§ Preservation of
Nesting Vegetation – the vegetation used by ardeids
for nesting should be preserved. |
None |
Marine
Ecological Impact – Construction and Operation Phase |
||||||
San Tau Beach SSSI, SCLKCMP , planned BMP and potential SWLMP, intertidal, sub-tidal hard bottom, sub-tidal soft bottom and open marine waters habitats |
Temporary/ permanent loss of habitats due to land formation and associated works: § Low-moderate for
intertidal and sub-tidal hard bottom habitats; § Moderate for open
marine waters; § Low for rocky
shore at SCLKCMP; § Insignificant to
moderate for sub-tidal soft bottom habitats; § Insignificant for
open marine waters around Sha Chau, and two ends and northwestern
waters of the 3RS Loss of carrying capacity and habitat fragmentation, changes in species distribution, abundance and patterns of habitat use: § Low impacts Release of SS and associated changes in water quality: § Low-moderate for
corals § Insignificant to low for other habitats Release of contaminants from pore water, oil/chemical spillage, change in hydrodynamics, changes in water quality associated with change in hydrodynamics, indirect disturbance of habitats due to deterioration of water quality: § Insignificant to
low impacts Importation and transportation of marine fill and filling activities, piling activities and associated underwater noise: § Low impacts Impingement and entrainment due to seawater intakes, indirect disturbance of marine fauna due to aircraft noise: § Insignificant to
low impacts |
§ Annexes 8 and 16 of EIAO-TM § WPCO § North Western WCZ
WQO § North Western
Supplementary WCZ WQO § Deep Bay WCZ WQO § Western Buffer
WCZ WQO § Sediment Deposition and SS Criteria for Corals, “Standards and Criteria for Pollution Control in Coral Reef Areas” |
No exceedances are predicted |
Relevant avoidance measures as detailed above for the water quality aspect |
§ Minimisation of land formation area § Use of construction methods with minimal risk / disturbance § Consideration of alternative alignment for pipeline diversion with minimal risk / disturbance § Consideration of alternative treatment to existing pipelines after diversion § Strict enforcement of no-dumping policy § Good construction site practices § Relevant water quality mitigation measures during construction and operation phases as detailed above § Pre-construction phase coral dive survey to review the feasibility of translocating coral species § Spill response plan § Proposed establishment of new marine park of approximately 2,400 ha linking the planned BMP and the existing SCLKCMP [4] |
No adverse residual impact is anticipated. |
CWD habitats at north of airport island, around Sha Chau, marine waters between airport and Sha Chau |
Temporary and permanent loss of dolphin habitats due to land formation and associated construction: § Low to high for marine waters north of airport island § Insignificant at other locations Loss of carrying capacity: § Moderate for marine waters and CWD habitat Habitat fragmentation: § Moderate for marine waters and CWD habitat Loss of CWD travelling area and connectivity between core CWD habitat areas: § Moderate for travel areas north of airport island Loss of prey resources for CWD as a result of temporary loss of benthic habitat: § Low for marine waters Disturbance to the CWD use of travelling area and connectivity between core CWD habitat areas: § Moderate for travel area north of existing airport island Changes to species distribution, abundance and habitat use: § Moderate Changes in water quality: § Insignificant to low Impacts to marine life from the importation and transportation of marine fill and filling activities: § Low Increased acoustic disturbance from construction works: § Insignificant for 11kV cable and fuel pipeline diversion; low for bored piling for approach lights and marker beacons; low-moderate for general construction works. Increased disturbance from night-time construction works: § Moderate Increased acoustic disturbance from changes to marine vessels and ferry traffic: § Low to moderate during construction phase, Moderate-high during operation phase Increased risk of injury/mortality to CWDs from marine traffic § Low for construction vessels; High for HSFs. Changes to CWD movement patterns as a result of marine traffic: § Low to moderate during construction phase, Moderate-high during operation phase Disturbance to the function and quality of Marine Parks: § Low-moderate for SCLKCMP; low for potential SWLMP; moderate for planned BMP Changes to the hydrodynamic regime and water quality as a result of the new land formation: § Low Secondary impacts of the proposed new marine park and extension of HKIAAA on CWDs: · Positive secondary impacts |
· Annexes 8 and 16 of EIAO-TM · WPCO · North Western WCZ
WQO · North Western
Supplementary WCZ WQO · Deep Bay WCZ WQO · Western Buffer
WCZ WQO · Sediment Deposition and SS Criteria for Corals, “Standards and Criteria for Pollution Control in Coral Reef Areas” |
N/A |
Relevant avoidance measures as detailed above for the water quality aspect |
§ Relevant water quality mitigation measures during construction and operation phases as detailed above § Acoustic decoupling of construction equipment mounted on barges § Dolphin Exclusion Zones § Avoid peak calving seasons of CWD for bored piling works § Spill response plan § Construction vessel speed limits and skipper training § Establishment of new marine park of approximately 2,400 ha linking the planned BMP and the existing SCLKCMP § SkyPier HSFs’ speed restrictions and route diversions |
No adverse residual impact is anticipated. |
Fisheries
Impact – Construction Phase |
||||||
North Western WCZ; North Western Supplementary WCZ; Deep Bay WCZ; and Western Buffer WCZ |
· Direct loss of
fishing ground from construction works are of low significance from
commencement to moderate. · Direct loss of
fisheries habitats (and resources) from construction works are of low
significance from commencement to moderate. · Direct loss of
fisheries habitats (and resources) from diversion of submarine 11 kV cables
and submarine fuel pipelines is insignificant. · Low impact significance
for the direct loss of spawning and nursery ground. · Insignificant to
low impact for indirect disturbance due to deterioration of water quality. · Insignificant for
indirect impact on aquaculture sites. · Low for the
indirect impact on artificial reef. · Low for the
impact of fishing activities. · Low impact
significance for the disturbance to fisheries resources associated with
underwater sound. |
· Annexes 9 and 17
of EIAO-TM · Fisheries
Protection Ordinance · Marine Fish
Culture Ordinance · Marine Parks
Ordinance |
N/A |
Relevant avoidance measures as detailed above for the water quality aspect |
§ Relevant water quality mitigation measures during construction phase as detailed above § Minimisation of land formation area § Use of construction methods with minimal risk / disturbance § Consideration of alternative alignment for pipeline diversion with minimal risk / disturbance § Consideration of alternative treatment to existing pipelines after diversion § Strict enforcement of no-dumping policy § Good construction site practices |
No adverse residual impact is anticipated. |
Fisheries Impact – Operation Phase |
||||||
North Western WCZ; North Western Supplementary WCZ; Deep Bay WCZ; and Western Buffer WCZ |
· Moderate impact
significance for the direct loss of fishing ground. · Low impact
significance for the disturbance of fishing activities. · Moderate impact
significance for the direct loss of fisheries habitats (and resources). · Low for the
direct loss of spawning and nursery grounds. · Low impact
significance for the change in hydrodynamics and tidal influence. · Insignificant for
the indirect disturbance of fisheries habitats due to deterioration of water
quality. · Low impact
significance for the impingement and entrainment due to seawater intakes. · Insignificant for
the indirect disturbance due to aircraft noise. · Positive impact
on fisheries resources conservation, low impact significance on fishing
activities with the implementation of the proposed new marine park together
with extension of HKIAAA for the project. |
· Annexes 9 and 17
of EIAO-TM · Fisheries
Protection Ordinance · Marine Fish
Culture Ordinance · Marine Parks
Ordinance |
N/A |
Relevant avoidance measures as detailed above for the water quality aspect |
§ Relevant water quality mitigation measures during operation phase as detailed above § Proposed establishment of new marine park of approximately 2,400 ha linking the existing/planned marine parks and the extended HKIAAA[5] |
No adverse residual impact is anticipated. |
Landscape
and Visual Impact – Construction Phase |
||||||
Identified LRs, LCAs and VSRs that may be affected by the project |
After the implementation of mitigation measures during the construction phase, all LRs and LCAs are anticipated to experience residual impacts of slight or insubstantial significance or are not anticipated to be affected by the 3RS, except the following: · Coastal waters of North Lantau and inshore water landscape are anticipated to experience residual impacts of substantial significance · Roadside amenity planting within the assessment area is anticipated to experience impacts of moderate significance After the implementation of mitigation measures during the construction phase, all VSRs are anticipated to experience residual impacts of slight or insubstantial significance or are not anticipated to be affected by the 3RS, except the followings: · Passengers / drivers of recreational marine craft in North Lantau waters and Urmston Road and recreational users of Sha Chau Islands are anticipated to experience residual impacts of substantial significance · Residents of Tung Chung, including Tung Chung Crescent, Seaview Crescent, Caribbean Coast, Area 53 to Area 56, residents along south coast of Tuen Mun, Hong Kong Gold Coast and Siu Lam; visitors to AsiaWorld Expo, Hong Kong SkyCity Marriott Hotel, Hong Kong Airport Passenger Terminal and to Regal Airport Hotel; passengers of Cable Cars of Ngong Ping 360; hikers of Nei Lak Shan, Fung Wong Shan (Lantau Peak), Tai Tung Shan (Sunset Peak), Lantau North Country Park, Lantau South Country Park and Scenic Hill are anticipated to experience residual impacts of moderate significance. · Passengers / drivers of vehicles and MTR along Cheong Wing Road; passengers of commercial aircraft, passengers / drivers of the proposed Hong Kong Link Road; and passengers of ferries in North Lantau waters and Urmston Road are anticipated to experience residual impacts of moderate significance. |
· Annexes 3, 10, 11, 18, 20 and 21 of EIAO-TM; · Hong Kong Planning Standards and Guidelines; · Hong Kong 2030 Planning Vision and Strategy Final Report; · Landscape Value Mapping of Hong Kong; · EIAO Guidance Note No. 8/2010; · Town Planning Ordinance; · Forests and Countryside Ordinance; · Country Parks Ordinance; · Foreshore and Sea-bed (reclamations) Ordinance; · Marine Parks Ordinance; · Protection of Endangered Species of Animals And Plants Ordinance; · Approved Chek Lap Kok OZP No. S/I-CLK/12; · Approved Tung Chung Town Centre Area OZP No. S/I-TCTC/18; · SILTech Publication (1991) – Tree Planting and Maintenance in Hong Kong (Standing Interdepartmental Landscape Technical Group) [11-23]; · GEO publication (1/2009) – Prescriptive Measures for Man-made Slopes and Retaining Walls; · GEO 1/2011 – Technical Guidelines on Landscape Treatment for Slopes Land Administration Office Instruction (LAOI) Section D-12 – Tree Preservation; · LDPN 7/2007 - Tree Preservation and Tree Removal Application for Building Development in Private Projects; · DEVB TC (W) No.2/2012 Allocation of Space for Quality Greening on Roads; · DEVB TC (W) No.3/2012 Site Coverage of Greenery for Government Building Projects; · DEVB TC (W) No.2/2013 Greening on Footbridges and Flyovers; · ETWB TCW No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features; · ETWB TCW No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their Preservation; · ETWB TCW No. 36/2004 The Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS); · ETWB TCW No. 5/2005 – Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction Works; · ETWB TCW No. 10/2013 - Tree Preservation; · WBTC No. 25/93 – Control of Visual Impact of Slopes; · WBTC No. 17/2000 – Improvement to the Appearance of slopes in connection with WBTC 25/93; · WBTC No. 7/2002 – Tree Planting in Public Works; · Latest Proper Planting Practices and other relevant guidelines issued by Development Bureau (Greening, Landscape and Tree Management Section); and · Latest Hong Kong International Airport Approved Plant Species List. |
N/A |
· The construction area and contractor’s temporary works areas should be minimised to avoid impacts on adjacent landscape; · Reduction of construction period to practical minimum; · Control of night-time lighting by hooding all lights and through minimising night working periods; and · All existing trees shall be carefully protected during construction. |
· Phasing of the construction stage to reduce visual impacts during the construction phase; · Construction traffic (land and sea) including construction plants, construction vessels and barges should be kept to a practical minimum; · Erection of decorative mesh screens or construction hoardings around works areas in visually unobtrusive colours; · Trees unavoidably affected by the works shall be transplanted where practical; · Avoidance of excessive height and bulk of site buildings and structures; and · Land formation works shall be followed with advanced hydroseeding around taxiways and runways as soon as practical. |
In accordance with the relevant criteria and guidelines for evaluating and assessing impacts, it is considered that the overall residual landscape and visual impacts of the project are marginally acceptable with mitigation. |
Landscape
and Visual Impact – Operation Phase |
||||||
Identified LRs, LCAs and VSRs that may be affected by the project |
After the implementation of mitigation measures during the operation phase, all LRs and LCAs are anticipated to experience residual impacts of slight or insubstantial significance or are not anticipated to be affected by the 3RS, except the following: · Impacts on coastal waters of North Lantau and inshore water landscape are anticipated to remain substantial in the operation phase. After the implementation of mitigation measures during the operation phase, all VSRs are anticipated to experience residual impacts of slight or insubstantial significance, or are not anticipated to be affected by the 3RS, except the following: · Passengers / drivers of recreational marine craft in north Lantau waters and Urmston Road and recreational users of Sha Chau Islands are anticipated to experience residual impacts of moderate significance. |
Same as for the Construction Phase. |
N/A |
Lighting units to be directional and minimise unnecessary light spill and glare. |
· Sensitive landscape design of land formation edge; · All above ground structures, including Vent Shafts, Emergency and Firemen’s Accesses etc. shall sensitively designed; · Sensitive design of buildings and structures in terms of scale, height and bulk (visual weight); · Use appropriate building materials and colours in built structures to create cohesive visual mass; · Greening measures, including vertical greening, green roofs, road verge planting and peripheral screen planting, shall be implemented; · Compensatory Tree Planting for all felled trees shall be provided to the satisfaction of relevant Government departments; · Streetscape (e.g. paving, signage, street furniture, lighting, etc.) shall be sensitively designed; · All streetscape areas and hard and soft landscape areas disturbed during construction shall be reinstated to equal or better quality (with implementation of screen planting, road verge planting etc.); · Aesthetic improvement planting of viaduct structure; and · Sensitive design of footbridges, noise barriers and enclosures with greening (screen planting / climbers / planters) and chromatic measures. |
In accordance with the relevant criteria and guidelines for evaluating and assessing impacts, it is considered that the overall residual landscape and visual impacts of the project are marginally acceptable with mitigation. |
Cultural
Heritage Impact – Construction Phase |
||||||
Cultural heritage within the marine archaeological assessment area and within the 500 m assessment area for terrestrial cultural heritage |
No impacts predicted |
Guidelines for Cultural Heritage Impact Assessment MAI Guidelines for MAI |
None |
N/A |
None required |
N/A |
Cultural
Heritage Impact – Operation Phase |
||||||
Cultural heritage within the marine archaeological assessment area and within the 500 m assessment area for terrestrial cultural heritage |
No impacts predicted |
Guidelines for Cultural Heritage Impact Assessment MAI Guidelines for MAI |
None |
N/A |
None required |
N/A |
Health
Impact – Aerial Emissions |
||||||
Human receptors within 5km Assessment area |
Levels of acute and chronic exposure due to TAP comply with the respective international guideline values. Maximum increase of carcinogenic risk due to TAP is around 1.14x10-5 which is considered acceptable. For criteria pollutants, the estimated risks of hospital admission and premature death for short-term exposure are relatively small. The estimated risk of premature death for long-term exposure is also relatively small. |
· International guidelines values (such as WHO, IRIS, OEHHA, etc.) · Health risk / impact assessment guidelines (such as WHO) |
N/A |
Those adopted for alleviating potential
air quality impacts during operation phase |
Those adopted for mitigating potential air quality impacts during operation phase |
N/A |
Health
Impact – Aircraft Noise |
||||||
Populated areas located adjacent to the NEF 25 contour line |
Changes in populations affected relative to “without project” scenario: · Annoyance: approximately 10% less · Sleep disturbance: approximately 50% less |
Health risk / impact assessment guidelines (such as WHO and EEA) |
N/A |
Those adopted for alleviating potential aircraft noise impacts |
Those adopted for mitigating potential aircraft noise impacts |
N/A |
[1] AAHK will offer the provision of window insulation and air-conditioning for all houses situated within the newly affected villages before the operation of the third runway in order to alleviate the potential aircraft noise impact on the residents.
[2] Conservative
assumptions are based on the maximum allowable SS release rates of the relevant
concurrent project. However based on the available information, the actual SS
release rates are much lower than the maximum allowable release rates.
[3]
EPD has agreed to reserve 43,500 m3/day (ADWF) at the TCSPS for the
total sewage discharge from the expanded airport, and AAHK will closely liaise
with EPD and DSD to ascertain a smooth interface with the upgrading works for
TCSPS.
[4] In
addition to the proposed mitigation
measures, environmental enhancement measures have also been recommended,
including deployment of artificial reefs;
provision of eco-enhancement designs
for part of the seawall; establishment of a marine research programme to
support conservation of marine ecology;
promotion of environmental education and eco-tourism; and setting up of environmental
enhancement fund.
[5] In
addition to the proposed mitigation measures, a number of fisheries enhancement
measures are proposed to further improve the fisheries resources in the western
Hong Kong waters and support sustainable fisheries operation, including
eco-enhancement design of part of the seawalls within the future extended
HKIAAA which restricts vessel entry including fishing vessels; potential
deployment of artificial reefs at appropriate locations to promote juvenile
fish recruitment; implementation of a FES; and setting up of a Fisheries
Enhancement Fund.