Content


Chapter    Title

9.1                  Introduction

9.2                  Methodology of Sewerage Impact Assessment

9.2.1               Assessment Approach and Methodology

9.2.2               Design Reference

9.2.3               Design Standard Guideline

9.3                  Existing and Planned Sewerage Condition

9.3.1               Existing Sewerage Network of the Airport

9.3.2               Planned Sewerage Network for the Third Runway Development

9.3.3               Existing Sewerage Network of Tung Chung

9.3.4               Planned Sewerage Network in Tung Chung

9.3.5               Existing/Planned Sewage Treatment Works in North Lantau

9.4                  Assumptions and Parameters Adopted for Assessment

9.4.1               Assessment Scenarios

9.4.2               Global Unit Flow Factors (GUFF) – Gravity Sewers in Tung Chung

9.4.3               Global Unit Flow Factors (GUFF) – Sewage Treatment Works & Pumping Station

9.4.4               Peaking Factors

9.5                  Sewage Flow Estimation

9.5.1               Existing and Projected Sewage Flow from the Airport

9.5.2               Existing and Projected Sewage Flow for the Gravity Sewers Leading to TCSPS

9.5.3               Existing and Projected Sewage Flow in TCSPS and SHWSTW

9.6                  Assessment of Impact to Existing/Planned Sewerage and Sewage Treatment System

9.6.1               Overview

9.6.2               Gravity Sewers from Airport Discharge Manhole to TCSPS

9.6.3               Tung Chung Sewage Pumping Station (TCSPS) and the associated Rising Main

9.6.4               Siu Ho Wan Sewage Treatment Works (SHWSTW)

9.7                  Mitigation Measures

9.7.1               Planned Sewerage System within the Expanded Airport Island

9.7.2               Gravity Sewers from Airport Discharge Manhole to TCSPS

9.7.3               Tung Chung Sewage Pumping Station (TCSPS) and the associated Rising Main

9.7.4               Siu Ho Wan Sewage Treatment Works (SHWSTW)

9.8                  Environmental Monitoring and Audit

9.9                  Conclusion

 

Tables

Table 9.1:__ Assessment Scenarios 9-5

Table 9.2:__ Adopted Global Unit Flow Factors (GUFF) for Gravity Sewers in Tung Chung_ 9-6

Table 9.3:__ Adopted Global Unit Flow Factors (GUFF) for Sewage Treatment Works and Pumping Station_ 9-6

Table 9.4:__ Peaking Factors 9-7

Table 9.5:__ Estimated Sewage Flows from the airport Adopted for Assessment 9-8

Table 9.6:__ Estimated Sewage Flows in Different Catchment Areas in 2012_ 9-9

Table 9.7:__ Estimated Sewage Flows of Concerned PDZs for Local Gravity Sewer in 2012 and 2038_ 9-9

Table 9.8:__ Estimated Sewage Flows in Different Catchment Areasin 2038_ 9-9

Table 9.9:__ Sewerage Catchments of TCSPS and SHWSTW by PDZ (excluding the project area) 9-10

Table 9.10:_ Adjustments and Assumptions adopted in TPEDM 2009-based for Proposed Developments 9-11

Table 9.11:_ Estimated ADWF for the Relevant PDZs and airport in 2012 and 2038_ 9-11

Table 9.12:_ Estimated ADWF of TCSPS and SHWSTW in 2012 and 2038_ 9-12

Table 9.13:_ Estimated Sewage Flows for Assessment of the Gravity Sewer in 2012_ 9-12

Table 9.14:_ Estimated Sewage Flows for Assessment of the Gravity Sewer in 2038_ 9-13

Table 9.15:_ Summary of the Hydraulic Modelling Results for the Existing Gravity Sewers in 2012_ 9-14

Table 9.16:_ Summary of the Hydraulic Modelling Results for the Existing Gravity Sewers in 2038_ 9-15

Table 9.17:_ Summary of the Hydraulic Modelling Results for the Proposed Gravity Sewers in 2038_ 9-16

Table 9.18:_ Estimated Sewage Flows Handled by TCSPS in 2012, 2022 and 2038_ 9-17

Table 9.19:_ Estimated Sewage Flows Handled by SHWSTW in  2012, 2026 and 2038_ 9-18

 

 

Drawings

MCL/P132/EIA/9-001  Existing Sewage System of Airport

MCL/P132/EIA/9-002  Existing and Planned Sewerage Infrastructures in Tung Chung

MCL/P132/EIA/9-003  Gravity Sewers from Airport Discharge Manhole to Tung Chung Sewage Pumping Station (TCSPS) – Existing

MCL/P132/EIA/9-004  Existing Sewerage Catchment of Gravity Sewer from Airport Discharge Manhole to TCSPS

MCL/P132/EIA/9-005  Sewerage Sub-Catchment of Gravity Sewer from Airport to TCSPS

MCL/P132/EIA/9-006  PDZ 405 Zoning System (2009-based TPEDM)

 

 

Appendices

 

Appendix 9.1 Sewage Estimation for Airport

Appendix 9.2 Sewage Flow Estimation of Tung Chung Sewerage Catchment

Appendix 9.3 Comparison of Assumptions of 2009-based and 2011-based TPEDM

Appendix 9.4 Population Forecast and ADWF Estimation by PDZs

Appendix 9.5 Estimation of Sewage Flow for SHWSTW and TCSPS

Appendix 9.6 Hydraulic Model Results (Existing Gravity Sewer)

Appendix 9.7 Proposed Mitigation Measure for Gravity Sewers from Airport Discharge Manhole to TCSPS

 

 



9.1          Introduction

9.1.1.1      This section presents the assessment of impacts on the public sewerage, sewage treatment and disposal facilities associated with the project, according to the requirements as specified in Section 3.4.7 and Appendix D2 of the Study Brief (ESB-250/2012).

9.1.1.2      Additional sewage flow will be generated by the project. This section describes the assessment of impacts associated with the additional sewage flow arising from operation of the project to the existing / planned sewerage system in North Lantau including the sewerage catchments of Siu Ho Wan Sewage Treatment Works, and the recommended appropriate mitigation measures to mitigate any forecasted shortfalls in the sewerage system as a result of the project.

9.1.1.3      It should be noted that the construction phase sewage issues of the project, i.e., sewage generated by the construction workforce, are addressed separately in Section 8.

9.2          Methodology of Sewerage Impact Assessment

9.2.1        Assessment Approach and Methodology

9.2.1.1      The assessment has been undertaken in accordance with the criteria and guidelines for evaluating and assessing impacts on the downstream public sewerage, sewage treatment and disposal facilities which would convey and collect the sewage flow from the airport as stated in Section 6.5 in Annex 14 of the EIAO Technical Memorandum. The following approach and methodology have been adopted to assess the impact on the existing / planned public sewerage system and sewage treatment capacity arising from the project:

¡  Carry out a desktop study to collect relevant information for the assessment.

¡  Investigate and review the capacity of the existing and planned public sewerage networks and sewage treatment facilities in North Lantau.

¡  Review the maximum sewerage flows (i.e., maximum development flows) to be generated by the project in different phases.

¡  Study the need and assess the impacts of discharging sewage arising from the project to the existing / planned public sewerage systems in Tung Chung and Siu Ho Wan Sewage Treatment Works (SHWSTW).

¡  Formulate measures to mitigate any forecasted shortfalls in the sewerage system as a result of the project and provide recommendations on the design, operation and maintenance requirements for the proposed sewerage system.

9.2.2        Design Reference

9.2.2.1      A desktop study was carried out to collect the relevant background information for the assessment as summarised below:

¡  Revised Final Technical Paper (TP7) on Broad Engineering Assessment on Development Scheme Options under Agreement No. CE 32/2011 (CE) Planning and Engineering Study on the Remaining Development in Tung Chung – Feasibility Study (or the Tung Chung New Town Extension);

¡  Drainage Record Plans within the vicinity of the North Lantau from Drainage Services Department (DSD);

¡  Sewage flow generated from the Hong Kong International Airport (HKIA) in different phases;

¡  Proposed Development Layout Plan of the project;

¡  Planning Study Report under Agreement no. CE 35/2006 for Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction;

¡  Final Study Report of the Agreement No. CE32/2010 (CE) Site Formation and Associated Infrastructural Works for Proposed Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery – Feasibility Study;

¡  Final Study Report of the Agreement No. CE 1/97 for the Remaining Development in Tung Chung and Tai Ho Comprehensive Feasibility Study

¡  Environmental Impact Assessment Report under the Agreement No. CE 60/96 for the Northshore Lantau Development Feasibility; and

¡  The Technical Note on the Compilation of 2009-based Territorial Population and Employment Data Matrices (TPEDM).

9.2.3        Design Standard Guideline

9.2.3.1      The assessment of the existing/planned downstream public sewerage networks and sewage treatment facilities in North Lantau have been carried out based on the following standards,  guidelines, manuals and reports:

¡  The Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning Version 1.0 published by EPD (GESF); and

¡  Sewerage Manual – Part 1 published by DSD (SM1).

9.3          Existing and Planned Sewerage Condition

9.3.1        Existing Sewerage Network of the Airport

9.3.1.1      The existing sewerage network at the airport comprises gravity sewers, grey water pipelines, 11 nos. of sewage pumping stations and associated rising main which are maintained by AAHK. All the sewage flow within the existing airport is collected locally and conveyed to a pumping station (Pumping Station No. 1) to discharge all the sewage flow from the airport into the public sewerage system through a public sewage manhole no. FMH7042035 and then transferred to the Siu Ho Wan Sewage Treatment Works (SHWSTW). As such, there is no sewage outfall at the existing airport. The existing sewerage system of the airport is shown in Drawing No. MCL/P132/EIA/9-001.

9.3.1.2      There is an existing grey water system at the airport to collect and convey grey water from terminal building kitchens, washroom sinks, and aircraft catering and cleaning activities to a grey water treatment facility. The capacity of the existing grey water treatment facility is 6,000 m3/day. The grey water is treated with a portion used for landscape irrigation. The remaining treated grey water (i.e., surplus of treated grey water) is currently overflowed to the sewerage system within the airport and then conveyed to the pumping station to discharge into public sewerage system in North Lantau Island. It is understood that no untreated grey water is currently discharged to the sewerage system as the capacity of existing grey water treatment facility has not yet been reached.

9.3.1.3      The existing sewerage system was designed and maintained in accordance with the standards and guidelines published by DSD. The existing sewerage network is currently maintained and operated by AAHK.

9.3.2        Planned Sewerage Network for the Third Runway Development

9.3.2.1      For the proposed airport expansion, the planned sewage discharge scheme is to construct a new sewerage system to collect the extra sewage flow from the project and then convey it to the existing public sewerage manhole no. FMH7042035 for discharge via the existing sewerage system in the airport.

9.3.2.2      The existing sewerage system within the airport island will be further reviewed during the detailed design stage and, if necessary, upgraded to ensure the extra sewage flow can be properly conveyed to the public sewerage system in North Lantau. It is anticipated that the capacities of the existing sewage pumping stations (PS1, PS2 and PS12f) are not able to handle the increased flow volume collected from the network after Year 2023. The pumping stations are required to be upgraded to increase its capacity to cope with the future flow.

9.3.2.3      In addition to the possible modification of the existing sewerage system, a new sewage pumping station will be needed to serve the additional sewage capacity requirements of the third runway expansion. The new sewage pumping station will be designed with spare capacity and at least one standby pump will be provided to minimise the risk of service disruption due to accidental pump failure. In the event of total pumping failure or burst sewer, the contingency will be to transport the sewage by trucks to SHWSTW. With the standby pumping capacity and contingency plan in place, emergency sewage overflow system will not be required and there will be no emergency discharge of sewage from the airport into the marine environment. Based on these provisions, there will be no discharge of sewage effluent from HKIA into the marine environment, and no adverse water quality impact due to sewage disposal is anticipated.

9.3.2.4      The planned sewerage system will be designed in accordance with all the relevant standards and guidelines published by DSD. The planned and existing sewerage network are maintained and operated by AAHK in accordance with the Sewerage Manual published by DSD. In addition to continuing the odour control arrangements currently undertaken by AAHK, maintaining the design maximum retention time of the planned pumping station to not more than 2 hours, monitoring the (hydrogen sulphide) H2S level once the 3RS is in operation and adoption of active septicity management measures that can effectively contain any future septicity problems will be included in the design for the planned 3RS sewerage system. With the inclusion of active septicity management measures as part of the design, maintenance and operation of the planned sewerage system, no adverse impacts in respect of septicity and odour from the HKIA new sewerage system are anticipated.

9.3.2.5      Due to the scale of the project, there will be an interim operation phase after completion of the land formation whereby the existing South Runway and the new third runway will be in operation while the existing North Runway will be closed for construction. The new airside fire station and the new air traffic control tower will commence operation during the interim period, however, the new sewerage system for the third runway facilities would be under construction. Therefore, the sewage arising from these two facilities during that period will be temporarily collected by a pump sump and transported to the DSD’s sewerage treatment facilities by the licensed sewage collection contractors at least seven times per day. The estimated sewage load from these new facilities would be approximately 130 m3/day, therefore, no adverse impacts to the existing sewerage system will be caused by this interim arrangement. Upon completion of the new sewerage system for the third runway area, all sewage flow generated within the HKIA will be collected and conveyed via the sewerage network to the SHWSTW.

9.3.2.6      Based on the current scheme design, an additional grey water treatment plant with a handling capacity of 700 m3/day is proposed.  More information about the additional treatment plant is given in Chapter 8.

9.3.3        Existing Sewerage Network of Tung Chung

9.3.3.1      The existing sewerage network conveying the sewage flow from the airport to Tung Chung comprises local gravity sewers between the airport discharge manhole and the Tung Chung Sewage Pumping Station (TCSPS) rising main connecting TCSPS and SHWSTW. The locations of these sewerage infrastructures are shown in the Drawing No. MCL/P132/EIA/9-002.

9.3.3.2      The size of the existing gravity sewers conveying the sewage flow from the airport to TCSPS  ranges from 1,050 to 1,500 mm in diameter as shown in Drawing No. MCL/P132/EIA/9-003. The sewage catchment of the gravity sewers mainly cover residential establishments, commercial establishments and visitors in Tung Chung areas.

9.3.3.3      The TCSPS is currently served by a single rising main of 1,200 mm in diameter and 6 km in length, which conveys the sewage generated from the airport and Tung Chung to SHWSTW. As advised by DSD, the existing capacity of the installed pumpsets at TCSPS is about 1,840 L/s, and the existing TCSPS has 3 nos. spare dry wells reserved for the additional pumpset installation to cater the future sewage flow.

9.3.4        Planned Sewerage Network in Tung Chung

9.3.4.1      The Planning Department (PlanD) and the Civil Engineering and Development Department (CEDD) have jointly commissioned a consultancy study under the Agreement No. CE 32/2011 – Planning and Engineering Study on the Remaining Development in Tung Chung. The study has identified the development potential and opportunities for extension of the Tung Chung New Town to the east and west, which may require a new sewerage network to support the development. The overall implementation programme for the proposed Tung Chung New Town Extension (TCNTE) will be established after the reclamation scale and infrastructure requirements have been determined. According to CEDD, the reclamation and infrastructure works of the project will be carried out in phases starting from 2018 with the anticipated first population intake in 2023/24. Also, subject to the approval of EPD, CEDD is investigating the feasibility of conveying sewage collected from TCNTE to the existing TCSPS and then pumped to SHWSTW for sewage treatment. However, the associated sewerage network within the Tung Chung area for sewage collection from TCNTE is still under planning and will be confirmed at the later stage of their study.

9.3.4.2      To enhance the operation reliability of the sewerage system, a consultancy study on the construction of an additional rising main from TCSPS to SHWSTW is currently being carried out by DSD under the Agreement No. CE 6/2012 Construction of additional sewage rising mains and rehabilitation of the existing sewage rising main between Tung Chung and Siu Ho Wan – Investigation, Design and Construction. According to the latest sewerage impact assessment report from DSD, twin 1,200 mm diameter rising main will be adopted for conveying the planned sewage flow from Tung Chung and the airport to the SHWSTW. It is planned to commence the construction in 2015 and complete the works by end 2022.

9.3.5        Existing/Planned Sewage Treatment Works in North Lantau

9.3.5.1      The sewage flow generated from North Lantau, including Tung Chung, the airport and Hong Kong Disneyland, is currently discharged to SHWSTW for treatment prior to discharge to the sea through an existing submarine outfall of 1,840 mm in diameter. The SHWSTW has been expanded and upgraded to Chemically Enhanced Primary Treatment (CEPT) since March 2005. The CEPT facilities include six sedimentation tanks, a flocculation and mixing tank, a sludge dewatering house, sludge buffer tanks, deodorization facilities and chemical dosing facilities.  The allowable treatment capacity of these facilities is 180,000 m3/day with a peak flow of 3,750 L/s. At the time of preparing this assessment, no further upgrading work for SHWSTW has been confirmed.

9.4          Assumptions and Parameters Adopted for Assessment

9.4.1        Assessment Scenarios

9.4.1.1      The assessment of impacts due to the project on the public sewerage system in North Lantau has been carried out for both baseline condition and ultimate design condition of the project as summarised in Table 9.1. Where appropriate, assessment for the interim scenario has also been carried out to identify the intermediate timeframe when the existing sewerage system will become saturated and recommend the appropriate measures to mitigate the impacts on the existing public sewage system in North Lantau arising from the project.  

Table 9.1: Assessment Scenarios

Scenario Year

Description

2012

Baseline Condition

2038

Ultimate Design Condition for 3RS  (i.e., 15 years after the planned commencement of operation of the 3RS in 2023)

 

9.4.2        Global Unit Flow Factors (GUFF) – Gravity Sewers in Tung Chung

9.4.2.1      Estimation of the sewage flow in the affected gravity sewers in Tung Chung has been undertaken according to the methodology as specified in GESF. Appropriate Global Unit Flow Factors (GUFF) for domestic and commercial/institutional activities have been selected for estimating sewage flows in the sewerage catchments according to GESF respectively, as presented in Table 9.2.

9.4.2.2      With reference to the Final Study Report of the Agreement No. CE32/2010 (CE) Site Formation and Associated Infrastructural Works for Proposed Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery – Feasibility Study, a GUFF of 0.010 m3/day/person is adopted for estimating the sewage flow generated from visitors within the study area of the project.   

Table 9.2: Adopted Global Unit Flow Factors (GUFF) for Gravity Sewers in Tung Chung

Category

Unit (per)

GUFF (m3/day)

Data Source

Domestic (catchment specific)

 

 

 

Private Housing and Public Housing

person

0.230

GESF

Commercial/Institutional

 

 

 

Employed Population

employee

0.080

GESF

Commercial Activities - General

employee

0.200

GESF

Institutions/ Schools

employee

0.040

GESF

Visitors for Cable Car Terminal

person

0.010

Final Report of Agreement No. CE32/2010

9.4.3        Global Unit Flow Factors (GUFF) – Sewage Treatment Works & Pumping Station

9.4.3.1      Estimation of the sewage flow to the affected sewage treatment works and pumping station in Tung Chung and North Lantau has been undertaken according to the methodology as specified in GESF. Appropriate GUFF for domestic, commercial, industrial and institutional activities have been selected in accordance with GESF, as shown in Table 9.3.

Table 9.3: Adopted Global Unit Flow Factors (GUFF) for Sewage Treatment Works and Pumping Station

Category

Unit (per)

GUFF (m3/day)

Data Source

Domestic (catchment specific)

 

 

 

Private Housing and Public Housing

Person

0.230

GESF

Commercial/Institutional

 

 

 

J2 – Electricity Gas & Water

employee

0.250

GESF

J3 – Transport, Storage & Communication

employee

0.100

GESF

J4 – Wholesale & Retail

employee

0.200

GESF

J9 – Construction

employee

0.150

GESF

J10 – Restaurants & Hotels

employee

1.500

GESF

J11 – Community, Social & Personal Services

employee

0.200

GESF

School Student

person

0.040

GESF

Commercial Employee

employee

0.080

GESF

Industrial Activities

 

 

 

J1 – Manufacturing

 

 

 

Industrial Employee

employee

0.080

GESF

East Kowloon (overall), Sha Tin, Lantau Island (except Mui Wo)

employee

0.450

GESF

9.4.4        Peaking Factors

9.4.4.1      According to GESF, a peaking factor should be applied in determining the peak flow. As the service condition of the existing sewerage systems within the study area is not clear, the peaking factors that include stormwater allowance, which are more conservative, have been adopted in this assessment. Based on GESF, the peaking factors adopted for determination of peak flows in sewers, sewage treatment works and pumping station are based on different population ranges as shown in Table 9.4:

Table 9.4: Peaking Factors

Population Range

Peaking Factor (including stormwater allowance) for Sewers

<1000

8

1,000 – 5,000

6

5,000 – 10,000

5

10,000 – 50,000

4

>50,000

where:

N = contributing population in thousands; and

Contributing population = Calculated total average flow in m3/day  divided by 0.27 m3/day

Population Range

Peaking Factor (including stormwater allowance) for

Sewage Treatment, Preliminary Treatment Works and Pumping Stations

<1000

4

10,000 – 25,000

3.5

25,000 – 50,000

3

>50,000

where:

N = contributing population in thousands; and

Contributing population = Calculated total average flow in m3/day  divided by 0.27 m3/day

9.5          Sewage Flow Estimation

9.5.1        Existing and Projected Sewage Flow from the Airport

9.5.1.1      The maximum pumping flow rate of 628 L/s as recorded in 2012 for Pumping Station No. 1 (PS1), which collects all sewage flow of the existing airport for discharge into the public manhole no. FMH7042035, has been adopted as the existing peak flow to assess the baseline condition of the downstream sewerage network. The Average Dry Weather Flow (ADWF), including the surplus of treated grey water, in PS1 in 2012 provided by AAHK is about 18,100 m3 per day. 

9.5.1.2      Based on the long term traffic forecast compiled by the International Air Transport Association (IATA) for AAHK, various growth factors for the air traffic movements (ATM), numbers of passengers and quantities of cargo from 2012 to 2038 have been estimated for the project.  These growth factors were then applied to the baseline sewage flow in 2012 in order to estimate the sewage flow of the project during the initial operation year of 2023 and the ultimate design scenario year of 2038, the results of which are summarised in Table 9.5. As explained in Section 9.3.1, overflow of the surplus treated grey water has been included in the estimates of current sewage flow and no untreated grey water is currently discharged to the sewerage system. As the worst case scenario in this assessment, however, it is conservatively assumed that starting from 2016 when the capacity of existing grey water treatment works is predicted to be exceeded, the untreated grey water would be discharged to the sewerage system.  In other words, while it has been planned to install an additional grey water treatment facility for the project, the worst case scenario does not take into account the additional grey water treatment capacity.  Details of the sewage estimation of airport are given in Appendix 9.1.

Table 9.5: Estimated Sewage Flows from the airport Adopted for Assessment

Scenario Year

Approximate Total ADWF of the Airport (m3/day)a

Approximate Amount of Untreated Grey Water of the Airport (m3/day)a

Approximate Total ADWF of the Airport  under Worst Case Scenario (m3/day)a

2012 (baseline condition)

18,100

-

18,100

2023b

26,700

900

27,600

2038 (ultimate design condition)

40,600

2,900

43,500

Note:

a.   Approximate values rounded to the nearest hundred.

b.   The values in 2023 are provided to show the total ADWF arising from the airport during the initial operation under worst case scenario, but are not for the purpose of assessment.

9.5.2        Existing and Projected Sewage Flow for the Gravity Sewers Leading to TCSPS

9.5.2.1      In order to assess the potential impact on the local gravity sewers between the airport discharge manhole and TCSPS, sewage flows in the existing sewers have been estimated based on the population and employment data within the sewage catchment areas of the concerned sewers, including the catchment of Chung Mun Road Sewage Pumping Station (CMRSPS) and Chung Yan Road Sewage Pumping Station (CYRSPS). It is identified that the sewerage catchment of the gravity sewers comprises catchments L, K, M and the airport and the corresponding catchment and sub-catchment plan are shown in Drawing No. MCL/P132/EIA/9-004 & MCL/P132/EIA/9-005 respectively. 

9.5.2.2      The population and employment data of the concerned catchments have been estimated based on the assumption that the developments within the catchments are fully utilised. Information obtained from private sectors and the government departments such as the gross floor area (GFA) of shopping malls and numbers of flats in private and public housings have been adopted in the estimation. Due to the lack of employment information in some of the current government facilities such as Police Station, Fire Station and Tung Chung Municipal Services Building, the planning data of such facilities used in the relevant previous study, namely, Agreement No. CE 1/97 - Remaining Development in Tung Chung and Tai Ho Comprehensive Feasibility Study, has been adopted in this assessment.

9.5.2.3      Based on the aforementioned assumptions and information, the sewage flows in different catchment areas of the gravity sewers connecting to TCSPS have been estimated, as summarised in Table 9.6.  The locations for individual discharges at the gravity sewers are shown in Drawing No MCL/P132/EIA/9-003. Details of the sewage flow calculation are given in Appendix 9.2.

Table 9.6: Estimated Sewage Flows in Different Catchment Areas in 2012

Catchment Area

Approximate ADWF in 2012  (m3/day)*

Airport

18,100

K (Existing ADWF of CYRSPS)

8,800

L1 to L13

7,800

M1 to M10

7,200

Total  to TCSPS

41,900

*Note: Approximate values rounded to the nearest  hundred.

9.5.2.4      The sewerage catchments represented by the Planning Data Zones (PDZ) system from the 2009-based TPEDM for the concerned gravity sewers and TCSPS are 245, 246, 266, 282 and 396. The estimated flow generated in these zones based on the 2009-based TPEDM in Year 2012 and 2038 are summarised in Table 9.7. The total flow of 41,900 m3/day in the relevant catchments (L, K, M and the airport) in 2012 as estimated by the method mentioned in Section 9.5.2.1 and 9.5.2.2 (see Table 9.6) is found to be close to the total flow of 42,500 m3/day as estimated by summing up the sewage flows in different PDZs (245, 246, 266, 282, 396 and airport) in the same year (see Table 9.7).  Therefore, the method used to estimate the sewage flow of the gravity sewers is considered as suitable for assessing the impact of the concerned gravity sewers between the airport discharge manhole and TCSPS. 

Table 9.7: Estimated Sewage Flows of Concerned PDZs for Local Gravity Sewer in 2012 and 2038

Planning Data Zones

Approximate ADWF in 2012 (m3/day)*

Approximate ADWF in 2038 (m3/day)*

245, 246, 266, 282 and 396

24,400

37,500

247 (Airport)

18,100

43,500

Total

42,500

81,000

*Note: Approximate values rounded to the nearest  hundred.

9.5.2.5      As can be seen from Table 9.7, the estimated sewage arising from the concerned PDZs  (i.e., 245, 246, 266, 282 and 396) will be increased by approximately 54 % from 24,400 m3/day in 2012 to 37,500 m3/day in 2038. Therefore, a conservative growth factor of 1.6 has been applied to the sewage flows in different catchments in 2012 for estimating the corresponding sewage flows in 2038, as summarised in Table 9.8. 

Table 9.8: Estimated Sewage Flows in Different Catchment Areasin 2038

Catchment Area

Approximate ADWF in 2038  (m3/day)*

Airport

43,500

K (Existing ADWF of CYRSPS)

14,100

L1 to L13

12,500

M1 to M10

11,600

Total  to TCSPS

81,700

*Note: Approximate values rounded to the nearest  hundred.

9.5.2.6      As discussed in Section 9.3.4, details of the proposed TCNTE and the associated sewerage network are yet to be confirmed. Therefore, this proposed TCNTE has not been considered in the assessment of local gravity sewers under the ultimate design scenario.

9.5.3        Existing and Projected Sewage Flow in TCSPS and SHWSTW

9.5.3.1      In order to assess the impact on TCSPS and SHWSTW due to the project, the future sewage flows handled by TCSPS and SHWSTW are estimated according to the population forecast in the airport and the sewerage catchments of TCSPS and SHWSTW in different years.

9.5.3.2      The sewerage catchments represented by the Planning Data Zones (PDZ) system from the 2009-based TPEDM are shown in Drawing No. MCL/P132/EIA/9-006. The sewerage catchments of TCSPS and SHWSTW in terms of PDZ  are presented in Table 9.9.

9.5.3.3      The unit of person represents the total number of “Residents with Regular Residence in HK” within the PDZ from the “Technical Note on the Compilation of 2009-based Territorial Population and Employment Data Matrices (TPEDM).

Table 9.9: Sewerage Catchments of TCSPS and SHWSTW by PDZ (excluding the project area)

Planning Data Zones

Sewerage Catchments of TCSPS

Sewerage Catchments of SHWSTW

239

 

Yes

241

 

Yes

245

Yes

Yes

246

Yes

Yes

265

 

Yes

266

Yes

Yes

282

Yes

Yes

283

Yes

Yes

284

 

Yes

327

 

Yes

395

 

Yes

396

Yes

Yes

398

 

Yes

9.5.3.4      Although the 2011-based TPEDM was issued in July 2013, it is considered more conservative to estimate the overall sewage flows from PDZs within the sewerage catchments of SHWSTW based on the 2009-based TPEDM. Therefore, it is proposed to adopt the 2009-based TPEDM for the sewage flow estimation. Comparison of the key assumptions adopted in the 2009-based and 2011-based TPEDM is presented in Appendix 9.3.

9.5.3.5      The 2009-based TPEDM includes the population forecast in each PDZ in five discrete years, namely, 2011, 2016, 2021, 2026 and 2031. The population forecasts for years not provided by the TPEDM between 2012 and 2038 are estimated by either interpolation or extrapolation from the data of the available years. Moreover, adjustments to 2009-based TPEDM have been made for the TCNTE and other proposed development within the sewerage catchments of TCSPS and SHWSTW. The adjustments and assumptions adopted in 2009-based TPEDM are summarised in Table 9.10. Details of estimating the population forecasts in years between 2012 and 2038 are shown in the Appendix 9.4.

Table 9.10:    Adjustments and Assumptions adopted in TPEDM 2009-based for Proposed Developments

Proposed Developments

PDZs

Adjustment to PDZ / Assumption adopted

TCNTE

266, 282, 283 & 396

According to the latest assumption provided by the CEDD, the sewage estimation for TCNTE is interpolated from 0 to 39,200 m3/day in between 2023 and 2027. Therefore, the population forecast for TCNTE has been excluded from the concerned PDZs for Year 2023 to 2038. The nil increase has been assumed from Year 2023 to Year 2038 for Residential, Commercial and Educational population.

Public Rental Housing Development at Tung Chung Area 39

246

Refer to revised population information from Paper No. IDC/2013 from Islands District Council, the additional population of 3,000 has been included from Year 2018 for the Public Rental Housing Development at Tung Chung Area 39.

Lantau Logistic Park,

Sunny Bay Development,

Proposed Cross Boundary Transport Hub above Siu Ho Wan Depot

239 & 284

No update information has been included for the concerned PDZs. The population assumption for these developments is based on the TPEDM 2009 (Revised Lantau Concept Plan released in May 2007).

9.5.3.6      A domestic (Residential) population is made up of household members who are either Usual Residents and Mobile Residents with regular residence in Hong Kong within the Planning Data Zones (PDZ) from the 2009-based TPEDM (i.e. Residents with regular residence in Hong Kong). The mobile residents and transients other than usual residents present in Hong Kong (i.e. visitor) is excluded from the domestic population as the GUFF for job type J10 as shown in Table 9.3 already taken into account the sewage flow arising from customers and/or visitors.

9.5.3.7      Based on the population breakdown assigned to PDZ of TPEDM and the appropriate GUFF, ADWF of individual PDZ that are within the sewerage catchments of TCSPS and SHWSTW are estimated for the baseline and ultimate design scenario years of 2012 and 2038. Table 9.11 summarises the estimated ADWFs of PDZs and the airport.

Table 9.11:    Estimated ADWF for the Relevant PDZs and airport in 2012 and 2038

Planning Data Zones

Sewerage  Catchments

 ADWF in 2012 (m3/day)

ADWF in 2038 (m3/day)

239

SHWSTW

53

6,271

241

SHWSTW

5,861

5,792

245

TCSPS & SHWSTW

13,132

18,196

246

TCSPS & SHWSTW

10,640

17,682

265

SHWSTW

42

58

266

TCSPS & SHWSTW

107

217

282

TCSPS & SHWSTW

119

179

283

TCSPS & SHWSTW

0

Included in TCNTE

284

SHWSTW

92

3,929

327

SHWSTW

2,805

5,239

395

SHWSTW

108

4,056

396

TCSPS & SHWSTW

365

1,137

398

SHWSTW

2

3,865

TCNTE*

TCSPS & SHWSTW

0

39,200

Airport

TCSPS & SHWSTW

18,100

43,500

*Note: ADWF arising  from TCNTE for Year 2012 and Year 2038 is provided by CEDD

9.5.3.8      Based on the estimated ADWF of the various PDZ and the airport, the total ADWF of TCSPS and SHWSTW in 2012 and 2038 are calculated, as summarised in the Table 9.12. Details of the total sewage flow estimation for TCSPS and SHWSTW in 2012 and 2038 are given in Appendix 9.5.

Table 9.12:    Estimated ADWF of TCSPS and SHWSTW in 2012 and 2038

Sewage Facilities

Approximate ADWF in 2012 (m3/day)*

Approximate ADWF in 2038 (m3/day)*

Tung Chung Sewage Pumping Station (TCSPS)

42,500

120,200

Siu Ho Wan Sewage Treatment Works (SHWSTW)

51,500

149,400

*Note: Approximate values rounded to the nearest hundred

9.6          Assessment of Impact to Existing/Planned Sewerage and Sewage Treatment System

9.6.1        Overview

9.6.1.1      According to the information obtained from AAHK, the project will be in full-scale operation in 2038 and thus the sewage flow in that year will be the ultimate design flow, which has been used to assess the impacts on the following key components of the sewerage and sewage treatment system:

¡  Gravity sewers between the airport discharge manhole and TCSPS;

¡  TCSPS and the associated rising main; and

¡  SHWSTW.

9.6.2        Gravity Sewers from Airport Discharge Manhole to TCSPS

Basis of the Assessment

9.6.2.1      To assess the impacts on the existing gravity sewers from the airport discharge manhole, reference point as shown in Table 9.10, to TCSPS (see MCL/P132/EIA/9-003), the estimated sewage flows from the airport for the scenario years of 2012 and 2038 (see Table 9.5) as well as the sewage flows from different catchment areas in 2012 (see Table 9.6) are used as the basis. A summary of these estimated sewage flows  adopted for the assessment is shown in Table 9.13. Details of the sewage flow calculation are given in Appendix 9.2.

Table 9.13:    Estimated Sewage Flows for Assessment of the Gravity Sewer in 2012

Reference Point

Discharge Manhole

Sewerage Catchment

Approximate ADWF (m3/day)

Contributing Population

Peaking Factor

Peak Flow (L/s)

 

A

FMH7042035

Airport

18,100

-

3.0

628

B

FMH7042030

L1, L2 & L4

984

3,644

6.0

68

 

C

FMH7043286

L3, L5, L6, L7, L8, L9, L10, L11,L12, L13 & K

15,605

 

57,797

4.0

717

 

D

FMH7043283

M1 to M10

7,138

26,437

4.0

330

 

9.6.2.2      According to the latest information provided by the CEDD, the sewage arising from the development of Tung Chung West and Tung Chung Village, part of TCNTE, is proposed to be discharged to Point C (Manhole No.FMH7043286) which is from 0 to 10,450 m3/day in between year 2023 and year 2027. As explained in Section 9.5.2.5, the estimated sewage flows of concerned catchments L, M and K can be projected by applying the growth factor to the corresponding sewage flows in 2012 for assessment of ultimate design scenario, as summarised in Table 9.14.

Table 9.14:    Estimated Sewage Flows for Assessment of the Gravity Sewer in 2038                      

Reference Point

Discharge Manhole

Sewerage Catchment

Approximate ADWF (m3/day)

Contributing Population

Peaking Factor

Growth Factor

Peak Flow (L/s)

A

FMH7042035

 

Airport

 

43,500

 

-

 

3.0

 

1.536

1,510

 

B

FMH7042030

L1, L2 & L4

1,511

5,598

5.0

1.536

87

C

FMH7043286

L3, L5, L6, L7, L8, L9, L10, L11,L12, L13 & K

23,970

 

34,420

3.5

1.536

1,405

Tung Chung West & Tung Chung Valley

10,450

D

FMH7043283

M1 to M10

10,964

40,607

4.0

1.536

508

Hydraulic Assessment

9.6.2.3      The hydraulic assessment on the existing gravity sewers from the airport discharge manhole to TCSPS is carried by the hydraulic model, InfoWorks (CS Version 14.0), as required in the EIA Study Brief. Details of the modelling results for the existing sewers are presented in Appendix 9.6, and are discussed below.

9.6.2.4      The sewerage model network of the concerned gravity sewers was setup according to the drainage record plan published by DSD. The ground level for the node of manhole is based on the information from the Light Detection and Ranging (LIDAR) survey data.

9.6.2.5      The pipe roughness coefficient is specified as an equivalent roughness (ks) used by the Colebrook-White equation. In this hydraulic assessment, the roughness coefficient or ks value used for the existing sewer is taken as 6 mm to cater for long term operational conditions of the sewer.

9.6.2.6      According to SM1, for sewers of diameter up to 900 mm, it should be designed to achieve a self-cleansing velocity of 1.0 m/s in full pipe condition.  The baseline model has been checked against with this requirement for the scenario of 2 times of ADWF. The overall velocity for the gravity sewer between airport discharge manhole and TCSPS generally exceed 1.0m/s. Therefore, the velocity is sufficient to enable the sewage flow to achieve self-cleansing effect on the concerned sewer, hence, no sediment is assumed in the hydraulic model. The model result for checking of this requirement is presented in Appendix 9.6.

9.6.2.7      As highlighted in SM1, local head losses arisen at inlets, outlets, bends, elbows, joints, valves, manholes and other fittings are usually small in relation to the pipeline head losses and are not normally considered. Therefore, these head losses are not assumed in this hydraulic assessment.

9.6.2.8      As summarised in Table 9.15, the InfoWorks modelling results show that all the assessed sewers would not be surcharged (i.e., with surcharge ratios well below one) during the baseline scenario year of 2012.  Therefore, the existing gravity sewers between the airport discharge manhole and TCSPS are sufficient to receive all the collected sewage flow from its sewerage catchments including the airport in 2012. 

Table 9.15:    Summary of the Hydraulic Modelling Results for the Existing Gravity Sewers in 2012

Sewerage Catchments/  Upstream Manhole

Downstream Manhole

Pipe Diameter (mm)

Hydraulic Modelling Results in 2012

Freeboard at Peak Flow (mm)

Surcharge Ratio*

Airport

FMH7042035

700

-

-

FMH7042035

FMH7042031

1,050

3,135

0.60

FMH7042031

FMH7042032

1,050

3,334

0.64

FMH7042032

FMH7042033

1,050

2,860

0.64

FMH7042033

FMH7042034

1,050

3,112

0.61

FMH7042034

FMH7042030

1,050

3,621

0.60

Catchment L1, L2 & L4

FMH7042030

FMH7042061

1,050

4,217

0.60

FMH7042061

FMH7042060

1,050

3,833

0.59

FMH7042060

FMH7043290

1,050

4,261

0.54

FMH7043290

FMH7043289

1,050

4,274

0.59

FMH7043289

FMH7043288

1,050

4,820

0.59

FMH7043288

FMH7043287

1,050

5,270

0.56

FMH7043287

FMH7043286

1,050

7,931

0.50

Catchment L3, L5, L6, L7, L8, L9, L10, L11,L12, L13 & K

FMH7043286

FMH7043285

1,350

7,459

0.56

FMH7043285

FMH7043284

1,350

7,416

0.50

FMH7043284

FMH7043283

1,350

8,202

0.45

Catchment M

FMH7043283

FMH7000680 (TCSPS)

1,500

8,461

0.67

*Note: Surcharge ratio extracted from the InfoWorks Model Result (i.e. surcharge ratio > 1: the pipe is under surcharge condition)

9.6.2.9      In the ultimate design scenario year of 2038, there will be additional sewage flow of 25,400 (i.e., 43,500 18,100) m3/day from the expanded airport discharging into the gravity sewers when compared to the baseline scenario year of 2012.  The hydraulic assessment results for Year 2038 are summarised in Table 9.16.  It can be seen from the Table that some of the existing gravity sewers would be surcharged from the design flow during the ultimate design scenario (i.e., exceeded the “design capacity” of the sewer).  

9.6.2.10    The predicted freeboard of those surcharged sewers at peak flow during the ultimate design scenario year of 2038 is summarized in Table 9.16.

Table 9.16:  Summary of the Hydraulic Modelling Results for the Existing Gravity Sewers in 2038

Sewerage Catchments/  Upstream Manhole

Downstream Manhole

Pipe Diameter (mm)

Hydraulic Modelling Results in 2038

Freeboard at Peak Flow (mm)

Surcharge Ratio*

Airport

FMH7042035

700

-

-

FMH7042035

FMH7042031

1,050

1,778

2.00

FMH7042031

FMH7042032

1,050

2,150

2.00

FMH7042032

FMH7042033

1,050

1,880

2.00

FMH7042033

FMH7042034

1,050

2,308

2.00

FMH7042034

FMH7042030

1,050

2,954

2.00

Catchment L1, L2 & L4

FMH7042030

FMH7042061

1,050

3,761

2.00

FMH7042061

FMH7042060

1,050

3,484

2.00

FMH7042060

FMH7043290

1,050

3,571

0.86

FMH7043290

FMH7043289

1,050

3,742

2.00

FMH7043289

FMH7043288

1,050

4,446

2.00

FMH7043288

FMH7043287

1,050

4,925

0.90

FMH7043287

FMH7043286

1,050

7,367

0.82

Catchment L3, L5, L6, L7, L8, L9, L10, L11,L12, L13, K, Tung Chung West & Tung Chung Valley

FMH7043286

FMH7043285

1,350

6,992

0.96

FMH7043285

FMH7043284

1,350

6,982

0.84

FMH7043284

FMH7043283

1,350

7,754

0.78

Catchment M

FMH7043283

FMH7000680 (TCSPS)

1,500

8,098

0.96

*Note: Surcharge ratio extracted from the InfoWorks Model Result (i.e. surcharge ratio > 1: the pipe is under surcharge condition)

9.6.2.11    In view of the above assessment findings and in accordance with SM1 that for design purposes the full bore flow at no surcharge shall be taken as the design capacity of a sewer and sewers under surcharge are not desirable, adequate mitigation measure should be implemented in a timely manner to  eliminate the surcharged condition. AAHK therefore proposed to construct a new gravity sewer with a diameter of 1,200 mm adjacent to the existing gravity sewer (1,050 mm in diameter) and then to divert the sewage flow arising from the airport and other sub-catchment in Tung Chung to the new gravity sewer, as shown in Appendix 9.7. AAHK will consider to study the feasibility to keep the proposed abandoned sewer (i.e., the existing gravity sewer of 1,050 mm in diameter) in place as a spare sewer with an overflow system for the emergency discharge subject to future deign of the new gravity sewer by around 2022.

9.6.2.12    The sewer upgrading work will be able to provide sufficient design capacity in the sewer in order to deliver the sewage arising from the project to the TCSPS. The hydraulic assessment for the upgrading proposal is summarized in Table 9.17 and Appendix 9.7. Design and construction of the new gravity sewer shall be in accordance with relevant guidelines as set out in the Project Administration Handbook for Civil Engineering Works, Sewerage Manual published by DSD, DSD Technical Circular No. 2/2005 and DSD Practice Note No. 1/2010 to ensure smooth delivery and handing over of the new sewer to DSD for the completion of works.

9.6.2.13    Since the concerned gravity sewer is projected to reach full capacity by 2027, the sewer upgrading work shall be completed by 2026 (allowing a buffer period of about one year before the full capacity is reached), with the planning work to commence in 2022 (assuming one year for planning plus three years for design and construction).  

Table 9.17:    Summary of the Hydraulic Modelling Results for the Proposed Gravity Sewers in 2038

Sewerage Catchments/  Upstream Manhole

Downstream Manhole

Pipe Diameter (mm)

Hydraulic Modelling Results in 2038

Freeboard at Peak Flow (mm)

Surcharge Ratio*

Airport

FMH01

700

-

-

FMH01

FMH02

1,200

2,652

0.80

FMH02

FMH03

1,200

3,315

0.78

FMH03

FMH04

1,200

3,909

0.71

Catchment L1, L2 & L4

FMH04

FMH05

1,200

3,935

0.65

FMH05

FMH06

1,200

4,060

0.64

FMH06

FMH07

1,200

5,005

0.53

FMH07

FMH7043286

1,200

7,483

0.50

Catchment L3, L5, L6, L7, L8, L9, L10, L11,L12, L13, K, Tung Chung West & Tung Chung Valley

FMH7043286

FMH7043285

1,350

6,998

0.88

FMH7043285

FMH7043284

1,350

7,129

0.78

FMH7043284

FMH7043283

1,350

7,949

0.74

Catchment M

FMH7043283

FMH7000680 (TCSPS)

1,500

8,130

0.92

*Note: Surcharge ratio extracted from the InfoWorks Model Result (i.e. surcharge ratio > 1: the pipe is under surcharge condition)

9.6.2.14    While AAHK undertakes to implement and complete the mitigation works for the affected gravity sewers by 2026, the discharge of additional sewage will start upon commissioning of the project and the sewage build up may be at a more rapid rate than that predicted.  Therefore, it is recommended that AAHK should monitor the sewage flow build-up as a part of the environmental monitoring and audit (EM&A) for the project and start planning construction of the upgrading works in 2022 or when the sewage flow in the affected gravity sewer exceeds 80% of the design capacity of the sewer, whichever is earlier, so as to ensure timely completion of the mitigation works before the flow would exceed the design capacity of the sewer.

9.6.3        Tung Chung Sewage Pumping Station (TCSPS) and the associated Rising Main

9.6.3.1      The potential impact on TCSPS has been assessed based on the estimated sewage flows arising from the project in 2012 and 2038 as well as the population forecast from the 2009-based TPEDM within the catchment areas of TCSPS (see Table 9.11).  The estimated sewage flow handled by TCSPS are summarised in Table 9.18 and details of the sewage flow estimation are given in Appendix 9.5.  

Table 9.18:    Estimated Sewage Flows Handled by TCSPS in 2012, 2022 and 2038

Scenario Year

Approximate ADWF from Relevant PDZs (m3/day)a

Approximate ADWF from Airport (m3/day)a

Total ADWF (m3/day)

Contributing Population

Peaking Factor

Total Peak Flow (L/s)

Existing Design Peak Flow of TCSPS (L/s)

2012 (baseline condition)

24,400

18,100

42,500

157,271

2.8

1,380

1,840

2022b

34,400

23,100

57,500

212,937

2.8

1,832

2038 (ultimate design condition)

76,700

43,500

120,200

444,854

2.6

3,648

Note:

a.     Approximate values rounded to the nearest  hundred.

b.     While 2022 is not one of the assessment scenarios, the values in 2022 are provided to show that the design peak flow of TCSPS would be exceeded after that particular year.

9.6.3.2      As shown in Table 9.18, the total peak sewage flow from the airport and the relevant PDZ will exceed the existing design peak flow of TCSPS (1,840 L/s) during the ultimate design scenario year of 2038.

9.6.3.3      By estimating the total ADWF and peak flows between 2012 and 2038 , it can be found that the total peak sewage flow from the airport and the relevant PDZ would exceed the existing design peak flow of TCSPS after 2022 (i.e., from 2023 onwards), subject to future development of TCNTE, as presented in Table 9.18.

9.6.3.4      As mentioned in Section 9.3.4, a government project under the Agreement No.CE6/2012 is currently underway to investigate, design and construct an additional sewage rising main between TCSPS and SHWSTW to enhance the operation reliability of the sewerage system. Under the project, it is planned to commence the construction in 2015 and complete the works by end 2022. According to the latest information from DSD, twin 1,200 mm diameter rising main will be adopted for conveying the planned sewage flow from Tung Chung and the airport to the SHWSTW, which is sufficient for the estimated ultimate design sewage flow of 3,648 L/s. [Note: EPD has agreed to reserve 43,500 m3/day (ADWF) at the TCSPS for the total sewage discharge from the expanded airport and AAHK will closely liaise with EPD and DSD to ascertain a smooth interface with the upgrading works for TCSPS.]  AAHK will monitor the situation closely and take appropriate action to handle the excess sewage arising in case there is any programme mismatch.

9.6.4        Siu Ho Wan Sewage Treatment Works (SHWSTW)

9.6.4.1      The potential impact on SHWSTW has been assessed based on the estimated sewage flows arising from the project in 2012 and 2038 as well as the population forecast from the 2009-based TPEDM within the catchment areas of SHWSTW (see Table 9.11).  The estimated sewage flows handled by SHWSTW are summarised in Table 9.19 and details of the sewage flow estimation are given in Appendix 9.5.

Table 9.19:    Estimated Sewage Flows Handled by SHWSTW in  2012, 2026 and 2038

Scenario Year

Approximate ADWF from Relevant PDZ (m3/day)*

Approximate ADWF from Airport (m3/day)a

Total ADWF (m3/day)a

Contributing Population

Peaking Factor

Total Peak Flow (L/s)

Existing Treatment Capacity of SHWSTW

Peak Flow (L/s)

Daily Flow (m3/day)

2012  (baseline condition)

33,400

18,100

51,500

190,462

2.8

1,650

3,750

180,000

2026b

87,900

30,800

118,700

439,402

2.6

3,606

2038 (ultimate design condition)

105,900

43,500

149,400

553,038

2.6

4,471

Note:

a.   Approximate values rounded to the nearest hundred.

b.   While 2026 is not one of the assessment scenarios, the values in 2026 are provided to show that the design peak flow of SHWSTW would be exceeded after that particular year.

9.6.4.2      It can be seen from Table 9.19 that the estimated total ADWF and peak sewage flow to be handled by SHWSTW in 2026 would be approximately 118,700 m3/day and 3,606 L/s respectively, which are within the treatment capacity of the existing SHWSTW. However, the design peak flow (3750 L/s) of the existing SHWSTW would be exceeded after 2026. The upgrading work for SHWSTW is considered necessary to cater for the ultimate design peak flow of 4,471 L/s from the expanded airport and the relevant PDZ in 2038.

9.6.4.3      In view of the above assessment findings, it is considered that the existing SHWSTW will not be able to handle estimated peak flows from the project as well as other future development within the relevant PDZ after 2026. It is understood that the upgrading works of SHWSTW will be carried out by the relevant government departments before exceeding the capacity, and the scope and programme of the upgrading works are still under discussion among the relevant government departments subject to future development within the catchment of SHWSTW including TCNTE. It is understood that EPD will monitor the sewage flow build-up and coordinate the necessary upgrading works for the SHWSTW when needed in due course.

9.6.4.4      With the upgrading of SHWSTW to cater for the proposed development within North Lantau such as TCNTE, the project and other developments of relevant PDZs, there is no need to establish any central pre-treatment facilities or separate sewage treatment plant for the project.

9.7          Mitigation Measures

9.7.1        Planned Sewerage System within the Expanded Airport Island

9.7.1.1      The planned sewerage system will be designed in accordance with all the relevant standards and guidelines published by DSD. The planned and existing sewerage network are maintained and operated by AAHK in accordance with the Sewerage Manual published by DSD. In addition to continuing the odour control arrangements currently undertaken by AAHK, maintaining the design maximum retention time of the planned pumping station to not more than 2 hours, monitoring the H2S level once the 3RS is in operation and adoption of active septicity management measures that can effectively contain any future septicity problems will be included in the design for the planned 3RS sewerage system. With the inclusion of active septicity management measures as part of the design, maintenance and operation of the planned sewerage system, no adverse impacts in respect of septicity and odour from the HKIA new sewerage system are anticipated.

9.7.2        Gravity Sewers from Airport Discharge Manhole to TCSPS

9.7.2.1      According to the InfoWorks modelling results, it is predicted that some of the existing gravity sewers from the airport discharge manhole to TCSPS would be under surcharge condition during the ultimate design scenario year of 2038.

9.7.2.2      In view of the above assessment findings and in accordance with SM1 that for design purposes the full bore flow at no surcharge shall be taken as the design capacity of a sewer and sewers under surcharge are not desirable, adequate mitigation measure should be implemented in a timely manner to  eliminate the surcharged condition. AAHK therefore proposed to construct a new gravity sewer with a diameter of 1,200 mm adjacent to the existing gravity sewer (1,050 mm in diameter) and then to divert the sewage flow arising from the airport and other sub-catchment in Tung Chung to the new gravity sewer, as shown in Appendix 9.7. AAHK will consider to study the feasibility to keep the proposed abandoned sewer (i.e., the existing gravity sewer of 1,050 mm in diameter) in place as a spare sewer with an overflow system for the emergency discharge subject to future deign of the new gravity sewer by around 2022.

9.7.2.3      This sewer upgrading work will be able to provide sufficient design capacity in the sewer in order to deliver the sewage arising from the project to the TCSPS. The hydraulic assessment for the upgrading proposal is summarized in Table 9.17 and Appendix 9.7. Design and construction of the new gravity sewer shall be in accordance with relevant guidelines as set out in the Project Administration Handbook for Civil Engineering Works, Sewerage Manual published by DSD, DSD Technical Circular No. 2/2005 and DSD Practice Note No. 1/2010 to ensure smooth delivery and handing over of the new sewer to DSD for the completion of works.

9.7.2.4      Since the concerned gravity sewer is projected to reach full capacity by 2027, the sewer upgrading work shall be completed by 2026 (allowing a buffer period of about one year before the full capacity is reached), with the planning work to commence in 2022 (assuming one year for planning plus three years for design and construction).

9.7.2.5      While AAHK undertakes to implement and complete the mitigation works for the affected gravity sewers by 2026, the discharge of additional sewage will start upon commissioning of the project and the sewage build up may be at a more rapid rate than that predicted.  Therefore, it is recommended that AAHK should monitor the sewage flow build-up as a part of the EM&A for the project and start planning construction of the upgrading works in 2022 or when the sewage flow in the affected gravity sewer exceeds 80% of the design capacity of the sewer, whichever is earlier, so as to ensure timely completion of the mitigation works before the flow would exceed the design capacity of the sewer.  

Potential Secondary Environmental Impacts from the Proposed Upgrading Works

9.7.2.6      The design and construction of new gravity sewer for replacement of the existing sewer is anticipated to begin in early 2024 and complete by 2026, which would not overlap with the planned construction period of the 3RS project (i.e., 2015 – 2023).  The upgrading work is not of large scale, comprising a works area of about 550 m in length and 3 m in width, and would generally involve the following construction activities:

¡  Break up of road surface

¡  Excavation of soil material

¡  Laying of new sewers

¡  Steel fixing and concreting of manholes

¡  Laying of bedding material

¡  Backfilling and soil compaction

¡  Reinstatement of road surface

9.7.2.7      Potential environmental impacts from the above construction works include dust emission, noise impacts from the use of Powered Mechanical Equipment (PME), generation of construction and demolition (C&D) waste, surface run-off and tree preservation, as discussed below.

9.7.2.8      The breaking of road surface, excavation and backfilling works is expected to generate potential dust impact. Relevant dust control measures as stipulated in the Air Pollution Control (Construction Dust) Regulation should be adopted to reduce potential dust impacts. Measures to be adopted include, but are not limited to, good site management, regular water spraying at works areas, and covering dusty materials with impervious sheet. Given that the upgrading work is not of large scale and with the implementation of dust control measures, no adverse construction dust impacts are anticipated.

9.7.2.9      The use of PME such as generator, breaker and poker for the upgrading work is expected to generate potential construction noise impacts. Relevant noise mitigation measures as listed in Professional Persons Environmental Consultative Committee Practice Note (ProPECC PN) No. 1/93 and 2/93 should be adopted to miminise potential noise impacts. In addition, good site practice such as use of well-maintained plants only and shut down of machines that may be in intermittent use could also reduce noise level. Given that the upgrading work is not of large scale and with the implementation of noise mitigation measures, no adverse construction noise impacts are anticipated.

9.7.2.10    Different types of wastes would be generated during the course of the upgrading work, including inert C&D materials from road surface breaking and soil excavation; non-inert C&D materials from site clearance; chemical waste from maintenance and repairing of construction equipment as well as general refuse from site workers. The inert C&D materials would largely be reused on-site as backfill materials, with a small surplus amount requiring off-site delivery to the government’s Public Fill Reception Facilities for beneficial use by other local projects. The non-inert C&D materials may not be suitable for direct reuse on site due to its non-inert contents, and would therefore be disposed of at designated landfill site. Given that the upgrading work is not of large scale, the amount of non-inert C&D materials to be generated is expected to be minimal.  A small amount of chemical wastes may be generated from the maintenance and repairing of construction equipment, which should be properly handled, stored, labelled and disposed of at licensed facilities in accordance with the Waste Disposal (Chemical Waste) (General) Regulation and the “Code of Practice on the Packaging Labelling and Storage of Chemical Wastes” published by EPD.   A limited amount of general refuse would be generated by the construction workforce, which should be properly collected and disposed of at designated landfill site. Given that the various waste materials are handled and reused/ disposed of in accordance with the relevant legislative and recommended requirements, no adverse environmental impact due to waste arising is expected from the upgrading works.

9.7.2.11    There would be surface runoff from the works area, which may contain increased loads of suspended solids (SS) and contaminants. The relevant good site practices as given in the ProPECC PN 1/94 should be followed to minimise surface runoff and erosion. Given that the upgrading work is not of large scale and with the implementation of good site practice, no adverse water quality impact is anticipated.

9.7.2.12    There are no registered Old and Valuable Trees (OVTs) in the vicinity of the upgrading works area, however, roadside trees are observed. As stated in Technical Circular (Works) No. 10/2013 Tree Preservation, trees should be preserved as far as practicable. A detailed tree survey should be carried out and a Tree Preservation and Removal Proposal (TPRP) should be prepared during detailed design stage. The aforementioned technical circular should be strictly followed.

9.7.2.13    In addition to the above recommended mitigation measures, guidelines as given in the Technical Circular (Works) No. 19/2005 – Environmental Management of Construction Sites, should also be followed where appropriate. With implementation of good site practices and the recommended mitigation measures, the proposed gravity sewer upgrading work is not anticipated to cause adverse secondary environmental impacts.

9.7.3        Tung Chung Sewage Pumping Station (TCSPS) and the associated Rising Main

9.7.3.1      Based on the assessment findings, the total peak sewage flow from the airport and the relevant PDZ would exceed the existing design peak flow of TCSPS in 2023, subject to future development of TCNTE.

9.7.3.2      A government project under the Agreement No.CE6/2012 is currently underway to investigate, design and construct an additional sewage rising main between TCSPS and SHWSTW to enhance the operation reliability of the sewerage system. Under the project, it is planned to commence the construction in 2015 and complete the works by end 2022. According to the latest information from DSD, twin 1,200 mm diameter rising main will be adopted for conveying the planned sewage flow from Tung Chung and the airport to the SHWSTW, which is sufficient for the estimated ultimate design sewage flow of 3,648 L/s. [Note: EPD has agreed to reserve 43,500 m3/day (ADWF) at the TCSPS for the total sewage discharge from the expanded airport and AAHK will closely liaise with EPD and DSD to ascertain a smooth interface with the upgrading works for TCSPS.]  AAHK will monitor the situation closely and take appropriate action to handle the excess sewage arising in case there is any programme mismatch.

9.7.4        Siu Ho Wan Sewage Treatment Works (SHWSTW)

9.7.4.1      It has been assessed that the existing treatment capacity of SHWSTW (180,000 m3/day) is sufficient to handle the predicted total sewage flow in 2038 (i.e., 149,400 m3/day).  However, the existing design peak flow of SHWSTW (3,750 L/s) would be exceeded after 2026. It is understood that SHWSTW will be upgraded by the relevant government departments to cater for the sewage treatment demand arising from future developments within the relevant sewerage catchment areas including the expanded airport and TCNTE. It is understood that EPD will monitor the sewage flow build-up and coordinate the necessary upgrading works for the SHWSTW when needed in due course.

9.8          Environmental Monitoring and Audit

9.8.1.1      With the implementation of the recommended mitigation measures, the existing public sewerage system would be upgraded to cater for the maximum development flows arising from the project.  In order to monitor the sewage flow build-up for the project to ensure timely completion of the mitigation works for the affected gravity sewer before the flow would exceed the sewer design capacity, it is recommended to implement a regular sewage flow monitoring programme.

9.8.1.2      Moreover, in order to ensure the additional sewage generated from the 3RS project would not impose adverse impacts in respect of sewage septicity and odour issues on the existing sewerage networks including the public sewerage system, it is recommended to implement a H2S monitoring system for the sewerage system of the 3RS.

9.8.1.3      Details of the above monitoring works are given in the EM&A Manual.

9.9          Conclusion

9.9.1.1      Under the worst case scenario, the project will generate a total sewage flow of 43,500 m3/day during the ultimate design scenario year of 2038 when the project will be in full-scale operation.  On this basis, the impacts arising from the project on the existing sewerage and sewage treatment system have been assessed.

9.9.1.2      The planned sewerage system for 3RS will be designed in accordance with all the relevant standards and guidelines published by DSD. The planned and existing sewerage network are maintained and operated by AAHK in accordance with the Sewerage Manual published by DSD.  In addition to continuing the odour control arrangements currently undertaken by AAHK, maintaining the design maximum retention time of the planned pumping station to not more than 2 hours, monitoring the H2S level once the 3RS is in operation and adoption of active septicity management measures that can effectively contain any future septicity problems will be included in the design for the planned 3RS sewerage system. With the inclusion of active septicity management measures as part of the design, maintenance and operation of the planned sewerage system, no adverse impacts in respect of septicity and odour from the HKIA new sewerage system are anticipated.

9.9.1.3      According to the hydraulic assessment results, the existing gravity sewers from the airport discharge manhole to TCSPS would reach full capacity by 2027. AAHK therefore proposed to construct a new gravity sewer with a diameter of 1,200 mm adjacent to the existing gravity sewer (1,050 mm in diameter) and then to divert the sewage flow arising from the airport and other sub-catchment in Tung Chung to the new gravity sewer, as shown in Appendix 9.7. AAHK will consider to study the feasibility to keep the proposed abandoned sewer (i.e., the existing gravity sewer of 1,050 mm in diameter) in place as a spare sewer with an overflow system for the emergency discharge subject to future deign of the new gravity sewer. This sewer upgrading work will be able to provide sufficient design capacity in the sewer in order to deliver the sewage arising from the project to the TCSPS.  The sewer upgrading work shall be completed by 2026 (allowing a buffer period of about one year before the full capacity is reached), with the planning work to commence in 2022 (assuming one year for planning plus three years for design and construction).

9.9.1.4      While AAHK undertakes to implement and complete the mitigation works for the affected gravity sewers by 2026, the discharge of additional sewage will start upon commissioning of the project and the sewage build up may be at a more rapid rate than that predicted.  Therefore, it is recommended that AAHK should monitor the sewage flow build-up as a part of the EM&A for the project and start planning construction of the upgrading works in 2022 or when the sewage flow in the affected gravity sewer exceeds 80% of the design capacity of the sewer, whichever is earlier, so as to ensure timely completion of the mitigation works before the flow would exceed the design capacity of the sewer.

9.9.1.5      Based on the assessment findings, the total peak sewage flow from the airport and the relevant PDZ would exceed the existing design peak flow of TCSPS in 2023, subject to future development of TCNTE. A government project under the Agreement No.CE6/2012 is currently underway to investigate, design and construct an additional sewage rising main between TCSPS and SHWSTW to enhance the operation reliability of the sewerage system. Under the project, it is planned to commence the construction in 2015 and complete the works by end 2022. According to the latest information from DSD, twin 1,200 mm diameter rising main will be adopted for conveying the planned sewage flow from Tung Chung and the airport to the SHWSTW, which is sufficient for the estimated ultimate design sewage flow of 3,648 L/s. [Note: EPD has agreed to reserve 43,500 m3/day (ADWF) at the TCSPS for the total sewage discharge from the expanded airport and AAHK will closely liaise with EPD and DSD to ascertain a smooth interface with the upgrading works for TCSPS.]  AAHK will monitor the situation closely and take appropriate action to handle the excess sewage arising in case there is any programme mismatch..

9.9.1.6      In view of the assessment findings, it is considered that the design capacity of the existing SHWSTW is sufficient to handle the estimated total ADWF from the project and the relevant PDZ during the ultimate design scenario year of 2038. However, it is estimated that the design peak flow of SHWSTW would be exceeded after 2026. It is understood that SHWSTW will be upgraded by the relevant government departments to cater for the sewage treatment demand arising from future developments within the relevant sewerage catchment areas including the expanded airport and TCNTE. It is understood that EPD will monitor the sewage flow build-up and coordinate the necessary upgrading works for the SHWSTW when needed in due course.

9.9.1.7      With implementation of the upgrading works for the gravity sewer, TCSPS and SHWSTW, there is no need to establish any central pre-treatment facilities or separate sewage treatment plant for the project.  Provided the upgrading of the gravity sewer, TCSPS and SHWSTW will be completed by respectively 2026, end 2022 and 2026, no interim sewage treatment facilities will be required for the project.