In-situ
Reprovisioning of Sha Tin Water Treatment Works – South Works
Environmental Impact Assessment Executive
Summary
TABLE
OF CONTENTS
3. CONSIDERATION
OF ALTERNATIVES
4. KEY
FINDINGS OF THE ENVIRONMENTAL IMPACTS
5. ENVIRONMENTAL
MONITORING AND AUDIT
List of Tables
Table
2.1 Schedule 2 Designated Projects
in the EIA Study
Table 2.2 Construction Programme in Tabular
Form
Table 3.1 Summary of Environmental Appraisal
for In-situ Reprovisioning
Table 4.1 Summary of the Key Findings for the
Impacts
Table 5.1 Summary of EM&A Requirements
Table 6.1 Summary of Key Environmental Outcomes
and Benefits
List of Figures
Figure
2.1 Location Plan and the Major
Scope of Works
Figure
3.1 Layout Plan of Reprovisioned
Sha Tin Water Treatment Works
Figure 4.1 Locations
of Representative Air Sensitive Receivers
Figure 4.2 Locations
of Representative Noise Sensitive Receivers
Figure 4.3 Locations
of Water Sensitive Receivers
Figure
4.4 Habitat Map (Sheet 1 of 2)
Figure
4.5 Habitat Map (Sheet 2 of 2)
Figure
4.6 Landscape Resources Plan
Figure
4.7 Landscape Character Area Plan
Figure
4.8 Key Visual Sensitive Receivers
Plan (VSR)
Figure
4.9 Photomontage Viewpoint from
Hin Wan House of Hin Keng Estate
·
Isolation
and demolition of the existing facilities of the South Works in phases
comprising clarifiers, filter beds with clearwater tank underneath, filtered water pumping station (South Works), as well as common facilities for
both the South Works and the North Works including chemical house, alum saturation tanks, washwater
recovery tanks, administration building and the dangerous goods (DGs) store;
·
Construction
of the new common facilities for both the South Works
and the North
Works including an Administration
Building
cum Mainland East Laboratory with visitor facilities, pre-treatment facilities, Water
Treatment Works Logistics Centre, switchgears and power supply, South Works
Pumping Station
and washwater recovery facilities;
·
Cut-back
of the existing engineered slope located to the west of the existing clarifiers
for reprovisioning of chemical house to Water Treatment Works Logistics Centre
where Incense Tree (Aquilaria sinensis)
as listed under the Protection of Endangered Species of Animals and Plants
Ordinance (Cap. 586) was identified;
·
Construction
of new access roads for both
construction and normal operation of the plant;
·
Reprovisioning
of the South Works to the proposed output of 550,000 m3/day; and
·
Provision
of all other associated civil, geotechnical, mechanical and electrical works.
·
Section
2 presents purpose and nature of the Project.
·
Section
3 outlines information over consideration of alternatives.
·
Section
4 presents the key findings of environmental impacts.
·
Section
5 describes environmental monitoring and audit.
·
Section
6 presents the conclusion.
Designated Project |
EIAO Reference |
Remarks |
Water Extraction and Water
Supply |
E.2, Part I, Schedule 2 |
Water treatment works
with a capacity of more than 100,000m3 per day |
Construction
Activity |
Anticipated
Timing |
Retaining Wall and New
Access Road |
October 2015 – November 2016 |
Water Treatment Works
Logistics Centre |
August 2016 – July 2019 |
Demolition of Existing
South Works |
November 2016 – April 2018 |
Washwater Equalization
Facilities (North Works) |
February 2017 – March 2018 |
Demolition of Existing
Chemical House |
August 2019 – January 2020 |
Demolition of existing
Washwater Recovery Tanks |
April 2018 – June 2018 |
Administration Building
cum Mainland East Laboratory with Visitor Facilities |
July 2018 – February 2020 |
Construction of South
Works |
May 2018 – January 2021 |
Demolition of existing
Administration Building |
May 2020 – October 2020 |
Stage 2 Granular Media Filters |
March 2020 – April 2021 |
Operation of haul Road |
August 2015 – November 2016 |
Access Road Raving (for Stage
1 Haul Road) |
November 2016 |
Operation of Haul Road |
December 2016 – April 2021 |
Access Road Paving (for Stage
2 Haul Road) |
April 2021 |
Option |
Environmental
Benefits |
Environmental
Disbenefits |
Appraisal |
In-situ
Reprovisioning |
·
Less environmental impact to the already developed site; and ·
No major impact on the difficulty of acquiring the land. |
·
About 0.69ha of secondary woodland to be affected due to space
constraints on the existing site. |
This option is
environmentally more favourable. Considering the size and value of woodland
affected, the residual impact is considered to be acceptable with habitat
compensation. |
(i) Shatin to Central Link – Tai Wai to Hung Hom Section (SCL(TAW-HUH))
3.5.2 The cumulative impacts arising from above
nearby project operating concurrently have been assessed and are described in
the relevant technical section of the EIA report.
Operation
Phase
Construction
Phase
Operation
Phase
Washwater Effluent
Overflow from Treatment
Works Components
Construction Phase
Operation Phase
|
Construction
Phase |
Operation
Phase |
Air
Quality |
||
Assessment
Scope and Key Criteria |
·
500m from the boundary of the project site ·
Hong Kong Air Quality Objectives -
24-hour average TSP level: 260µg/m3 -
Annual average TSP level: 80µg/m3 ·
Annexes 4 and 12 of the EIAO-TM -
Hourly average TSP level: 500µg/m3 · Air Pollution Control (Construction Dust) Regulation |
Not anticipated |
Representative
Sensitive Receivers |
ASR-1: The Blossom Phase
4 ASR-2: The L Louey ASR-3: Hin Keng Estate –
Hin Yau House ASR-4: Hin Keng Estate –
Hin Wan House ASR-5: Hin Keng Estate –
Hin Kwai House ASR-6: Sha Tin Heights
Tunnel Administration Building |
|
Evaluation
of Major Impacts |
·
Excavation works would be carried out over a reasonable period to
minimize the daily excavated volume. With the small volume of excavated
materials generated daily and disposed off-site, the potential dust impact at
the nearby ASRs would not be significant with the effective implementation of
mitigation measures. · Given the short duration (3-18 months) and small scale of the demolition works, the potential dust impact would be minimal with the implementation of dust suppression measures. |
|
Cumulative Impacts |
No adverse cumulative
impact is anticipated due to minimal scale of the Project comparing to
SCL(TAW-HUH) in which no adverse air quality impact upon receivers was
predicted. |
|
Key
Mitigation Measures |
The
major dust suppression measures include: ·
Use of regular watering ·
Use of frequent watering ·
Side enclosure and covering ·
Tarpaulin covering of all dusty vehicle loads ·
Establishment and use of vehicle wheel and body washing facilities ·
Provision of not less than ·
Imposition of speed controls for vehicles on site haul roads ·
Routing of vehicles and positioning of construction plant at the
maximum possible distance from ASRs ·
Instigation of an environmental monitoring and auditing program |
|
Residual Impact |
No adverse impact |
|
|
Construction
Phase |
Operation
Phase |
Noise |
||
Assessment
Scope and Key Criteria |
·
300 m from the boundary of the project site ·
EIAO-TM daytime construction noise limit -
Domestic premises: 75 dB(A) -
Educational institutions (during normal teaching periods): 70dB(A) -
Educational institutions (during examination periods): 65dB(A) ·
Annexes 5 and 13 of the EIAO-TM · Noise Control Ordinance (Cap. 400) |
·
300 m from the boundary of the project site ·
IND-TM Acceptable Noise Level -
Daytime and Evening: 65 dB(A) -
Night: 55dB(A) ·
NCO and IND-TM |
Representative
Sensitive Receivers |
HK1: The L Louey ( East) HK2: The L Louey (South) HK3: Hin Keng Estate –
Hin Yau House (North) HK4 :Hin Keng Estate –
Hin Yau House (South) HK5: Hin Keng Estate –
Hin Wan House HK6: Hin Keng Estate –
Hin Kwai House HK7: C.U.H.K.F.A.A Thomas
Cheung School *HK8: Sha Tin WTW Staff Quarters |
Receivers same as
Construction Phase |
Evaluation
of Major Impacts |
·
Unmitigated scenario: exceedances by 1 to 3 dB(A) at some NSRs · Mitigated scenario: full compliance with the noise criteria |
Full compliance with the
noise criteria |
Cumulative Impacts |
No overall increase of
cumulative noise level due to the Project. |
No exceedance |
Key
Mitigation Measures |
·
Good site practice ·
Adoption of quiet PME ·
Use of movable noise barrier All practicable mitigation
measures have been exhaustively investigated and residual impact is minimized
as far as possible. |
·
Choose quieter plant ·
Include noise levels specification when ordering new plant ·
Locate fixed plant/louver away from any NSRs ·
Locate fixed plant in walled plant rooms or in specially designed
enclosures; ·
Locate noisy machines in a basement ·
Install direct noise mitigation measures · Develop and implement a regularly scheduled plant maintenance programme |
Residual Impact |
No adverse impact due to
the Project itself. |
No adverse impact |
*
The Sha Tin WTW Staff Quarters would be used as site office during the
construction of the project. It is only considered as representative noise
sensitive receivers during operational phase
|
Construction Phase |
Operation Phase |
Water
Quality |
||
Assessment
Scope and Key Criteria |
·
500m from the boundary of the project site ·
Water Quality Objectives for the Tolo Harbour and Channel Water
Control Zone · Annexes 6 and 14 of the EIAO-TM |
Scope and criteria same
as Construction Phase |
Representative
Sensitive Receivers |
Two natural streams/nullah
flow along the Project site boundary with low ecological value - one located to the
northwest of the Project boundary - one named Tin Sum
Nullah located along the southeast of the Project boundary |
Receivers same as
Construction Phase |
Evaluation
of Major Impacts |
·
Minimal impacts from wastewater generated and water pollution caused
by land-based construction activities ·
Unacceptable impacts not expected from construction site run-off and
drainage ·
Impacts could be mitigated for accidental spillage of engine oil and
lubricants when in use and storage ·
Significant impact not expected for sewage effluent from construction
workforce with provision of proper interim sewage treatment facilities, such
as chemical toilets ·
Any groundwater pumping out or from dewatering process during deep
excavation works could be potentially contaminated. No direct discharge of
contaminated groundwater would be allowed · No adverse impact envisaged for potential contaminated groundwater if any during deep excavation with mitigation measures put in place and monitoring requirements followed properly |
·
No adverse impact from the washwater effluent and no washwater to be
discharged off-site ·
No adverse impact for overflow from treatment works components and
avoidance of overflow discharge by provision of standby units and dual power
supply |
Cumulative Impacts |
No cumulative impact
expected provided that all recommended mitigation measures are implemented
properly |
Not anticipated |
Key
Mitigation Measures |
·
Site practices outlined in ProPECC PN 1/94 “Construction Site
Drainage” to follow so as to minimise surface run-off and the chance of
erosion ·
Waste Disposal (Chemical Waste) (General) Regulation to comply with
for controlling chemical wastes ·
Interim treatment facilities, such as chemical toilets, should be
properly maintained to avoid adverse impact upon the nearby water environment ·
Practices outlined in ETWB TC (Works) No. 5/2005 “Protection of
Natural Streams/Rivers from Adverse Impacts Arising from Construction Works”
to adopt · Contaminated groundwater, if any, should either be properly treated or recharged into the ground in compliance with the requirements of the TM-DSS |
· Provision of standby treatment facilities and dual power supply to prevent occurrence of overflow |
Residual Impact |
No adverse impact |
No adverse impact |
|
Construction Phase |
Operation Phase |
Waste
Management |
||
Assessment
Scope and Key Criteria |
·
Areas within the boundary of the project site ·
Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) |
Scope and criteria same
as Construction Phase |
Representative
Sensitive Receivers |
Sha Tin WTW |
Receiver same as
Construction Phase |
Evaluation
of Major Impacts |
·
The Engineer has estimated the volume of surplus C&D materials to
be approximately 242,050 m3 of inert material (i.e. public fill) and 9,980 m3
of non-inert material. No sediment requiring marine disposal ·
Building demolition may generate possible asbestos waste ·
Quantity of chemical waste would be small and in the order of a few
cubic metres per month · It is also estimated that about 128.7 kg per day of general refuse would be generated by the construction workers |
·
It is estimated that the total volume of thickened sludge after
reprovisioning would be approximately 782 m3/day. ·
Existing approach for thickened sludge transport to Sha Tin STW for
disposal after reprovisioning would remain unchanged ·
No unacceptable impact for sludge handling and disposal from the
proposed treatment process comparing to the existing one · No adverse or minimal impact for chemical waste, general refuse |
Cumulative Impacts |
No adverse impact |
Not anticipated |
Key
Mitigation Measures |
·
C&D materials would be sorted on-site and the inert portion would
be stored in different containers, skips or stockpiles to re-use. Surplus
excavated material would therefore be exported off-site ·
The Project Proponent should conduct an asbestos investigation prior
to building structure demolition. All storage of asbestos waste should be
carried out properly in a secure place isolated from other substance and bear
warning panels to alert people of the presence of asbestos waste · Amount of chemical waste generated would be quantified in the site waste management plan to be prepared by the Contractor |
·
Chemical waste store in compatible containers in designated areas on
site ·
Chemical waste to be collected and recycled by licensed collectors ·
Provision of on-site general refuse collection points together with
recycling bins · General refuse to be collected by licensed collectors |
Residual Impact |
No adverse impact |
No adverse impact |
|
Construction Phase |
Operation Phase |
Ecology |
||
Assessment
Scope and Key Criteria |
·
500m from the boundary of the project site ·
Annex 16 of the EIAO-TM ·
Protection of Endangered Species of Animals and Plants Ordinance (Cap.
586) · EIAO Guidance Note No. 6/2010, 7/2010, 10/2010, DEVB TCW No. 10/2013 |
No significant adverse
impact as the level of disturbance would be comparable to the existing
condition |
Representative
Sensitive Receivers |
·
Secondary woodland habitat occupies about half of the study area ·
Small, scattered patches of plantation habitat within the study area ·
Watercourse 1, north-west of the Sha Tin WTW. Upstream is natural,
downstream is man-made and channelized ·
Watercourse 2, south-east of the Sha Tin WTW. Man-made and channelized ·
Watercourse 3, south-east of the Sha Tin WTW. Channelized · Developed area including the Sha Tin WTW, residential areas and transportation infrastructure |
|
Evaluation
of Major Impacts |
·
Approximately 9.04 ha of habitats would be directly impacted. Of
which, about 90% of the affected habitats are within developed area and
plantation of low ecological value. These habitats are subjected to frequent
human disturbance and therefore direct impact is considered to be low. ·
Approximately 0.69 ha of secondary woodland affected permanently with
high ecological value due to cutting back of the existing engineered slope
for accommodation of WTW Logistics Centre. Direct impact is considered to be
moderate as the affected woodland portion is small in size and located at the
woodland/developed area edge · Four flora species of conservation importance (Incense Tree, Ailanthus, Lamb of Tartary, and Hong Kong Eagle’s Claw) would be directly affected |
|
Cumulative Impacts |
Potential cumulative
impact is associated with disturbance of secondary woodland and, plantation
habitat arising from the SCL’s Hin Keng tunnel portal work sites. Cumulative
increase in disturbance is considered minor and acceptable |
|
Key
Mitigation Measures |
Measures to
Avoid/Minimize Impact to Woodland ·
By retaining wall instead of soil nails for slope stabilization work
adjacent to the proposed access road at the northern boundary of works area
to reduce the amount of vegetation removal and minimize the footprint of the
slope at the woodland habitat. ·
Retaining wall behind the future WTW Logistics Centre has been adopted
under the current design to minimize impact to woodland. Measures to
Avoid/Minimize Impact to Flora Species of Conservation Importance ·
Four flora species of conservation importance include Incense Tree,
Ailanthus, Lamb of Tartary and Hong Kong Eagle’s Claw ·
Prior to the construction, a detailed vegetation survey would be
conducted to confirm its location and health condition ·
Transplantation would be recommended as far as possible to minimize
the direct impact and a transplantation proposal with location plan, details
of the transplantation methodologies and programme along with
post-transplantation monitoring would be submitted for approval prior to
transplantation Woodland Compensation ·
About 0.23 ha on-site woodland compensation considering the site
constraint of limited space ·
Approximately 0.29 ha off-site woodland compensation at Sha Tin South
Freshwater Service Reservoir nearby and northwest of Sha Tin West Service
Reservoir. · Woodland Compensation Plan would be submitted for approval prior to commencement of works |
|
Residual Impact |
Considering the size and
value of the woodland habitat affected, the residual impact is considered to
be insignificant, with the implementation of the recommended habitat
compensation. |
|
Construction
Phase |
Operation
Phase |
|
Landscape
and Visual |
|||
Assessment
Scope and Key Criteria |
·
500m from the boundary of the project site · Annexes 10 and 18 of the EIAO-TM |
Scope and criteria same
as Construction Phase |
|
Representative
Sensitive Receivers |
Landscape
Resources LR1 - Natural Hillside
Woodland LR2 - Man-made Slope
Areas LR3 - Landscape Amenity
Area at Shatin WTW LR4 - Lawn Area LR5 - Landscape Areas at
Hin Keng Estate LR6 - Hin Tin Playground
and Football field LR7 - Roadside Planting along Che
Kung Mu Rd LR8
- Walking Trail LR9
- Watercourse Landscape Character Areas (LCA) LCA1
- Tai Wai Urban Residential LCA LCA2
- Tai Wai Urban Fringe LCA LCA3
- Tai Wai Urban Upland and Hillside LCA |
Visual
Sensitive Receivers R1 - Hin Tin Estate R2
- Hin Keng Estate and Ka Tin Court R3
- Low Rise Residential along Keng Hau Road: L Louey, Angelaville, The
Blossom, Joyville, Jade Villa, Lisa Villa R4
- Parc Royale GIC1
- Union Hospital O1
- Wilson Trail O2 - Hikers on Amah Rock
at Lion Rock Country Park T1 - Travellers on East
Rail T2 - Tai Po Road |
Receivers same as
Construction Phase |
Evaluation
of Major Impacts |
· Approximately 800 existing trees would be affected. Among these 800 trees, approximately 652 trees will be felled due to the Project. About 21 nos. of Aquilaria sinensis which is protected under Cap. 586 in Hong Kong and 1 no. of Ailanthus fordii under the Forest and Countryside Ordinance. |
·
All permanent works are considered irreversible · No potential blockage of view |
|
Cumulative Impacts |
· No insurmountable cumulative impact with the implementation of mitigation measures |
Not anticipated |
|
Key
Mitigation Measures |
·
Approximately 200 nos. of heavy standard trees and 460 nos. of light
standard trees on-site and off-site to compensate for the tree to be felled. ·
It offers a compensation ratio greater than 1:1 (i.e. approximately
660 newly planted trees v.s. approximately 652 felled trees). · Approximately 2,300m2 of woodland mix planting on-site whereas about 2,900m2 off-site to compensate for the affected woodland habitat. |
·
Buffer tree and shrub planting to screen the proposed structures · Green roof to enhance landscape quality |
|
Residual Impact |
·
Substantial residual landscape impact on LR1 and moderate residual
landscape impact on LR2, LR3, LR4 and LCA2 with the implementation of
proposed mitigation measures · Moderate residual visual impact on R1, R2, R3, R4, GIC1, O1 and O2 and slight residual impact on T1 and T2 |
·
Moderate on LR1 and slight on LR2, LR3, LR4 and LCA2 in Day 1 and
reduce to slight and insubstantial in Year 10 when the proposed trees become
mature for residual landscape impact · Slight in Day 1 and reduce to insubstantial in Year 10 for residual visual impact |
|
|
Construction
Phase |
Operation
Phase |
Cultural
Heritage |
||
Assessment
Scope and Key Criteria |
·
300m from the boundary of the project site ·
Annexes 10 and 19 of the EIAO-TM · Antiquities and Monuments Ordinance (Cap. 53) |
Not anticipated |
Representative
Sensitive Receivers |
Graded
Historical Buildings ·
BH01 - Yeung Ancestral Hall, No. 7 Hin Tin, Shatin (Grade 3) ·
BH02 - Law Ancestral Hall, No. 8 Hin Tin, Shatin (Grade 3) ·
BH03 - So Ancestral Hall, No. 9 Hin Tin, Shatin (Grade 3) Government Historic Site · BH04 - Ex Kowloon-Canton Railway Beacon Hill Tunnel |
|
Evaluation
of Major Impacts |
·
Insignificant indirect vibration impact due to drilling activities on
the three graded historical buildings situated at approximately 270m from the
works area ·
No significant vibration impact for the Ex KCR Beacon Hill Tunnel
located in close proximity to the refurbishment works for four existing staff
quarters as construction site office · Ground-borne vibration not anticipated to be significant for the tunnel portal given a consideration distance (about 120m in plan) from the possible piling and drilling activities where new administration building would take place |
|
Cumulative Impacts |
Not anticipated |
|
Key
Mitigation Measures |
· As a precautionary measure, a peak particle velocity (ppv) limit of 7.5mm/s is recommended to measure at the facade wall of tunnel portal and inside the tunnel, the closest to the works area during piling and drilling works |
|
Residual Impact |
Residual impact for the
Ex KCR Beacon Hill Tunnel is considered to be acceptable with proper
implementation of mitigation measures |
|
Construction
Phase |
Operation
Phase |
Land
Contamination |
||
Assessment
Scope and Key Criteria |
·
Areas within the boundary of the project site ·
Section 3 of Annex 19 of the EIAO-TM · Practice Guide for Investigation and Remediation of Contaminated Land |
Not anticipated |
Representative
Sensitive Receivers |
Onsite construction
workers |
|
Evaluation
of Major Impacts |
· A total of 44 sampling locations proposed at the potentially contaminated hotspots for the SI works upon decommissioning and prior to the commencement of construction works |
|
Cumulative Impacts |
· No cumulative impact is anticipated |
|
Key
Mitigation Measures |
·
Based on SI findings, if contamination found, appropriate remediation
methods should be investigated · For any contamination found, in-situ remediation measures and possible recycling and reuse of remediated materials should be considered as the preferred remediation option whereas ex-situ remediation the second |
|
Residual Impact |
No adverse impact after
completion of remediation for any identified contaminated areas |
|
Construction
Phase |
Operation
Phase |
Hazard
to Life |
||
Assessment
Scope and Key Criteria |
·
Consultation Zone of Sha Tin WTW and other areas within hazard range
of the potential chlorine releases at Sha Tin WTW and along the off-site
chlorine transport route. · Annex 4 of the EIAO-TM |
· Scope and criteria same as Construction Phase |
Representative
Sensitive Receivers |
· All population within the Consultation Zone and within hazard range of the potential chlorine releases at Sha Tin WTW and along the off-site chlorine transport route. |
· All population within the Consultation Zone and within hazard range of the potential chlorine releases at Sha Tin WTW and along the off-site chlorine transport route. |
Evaluation
of Major Impacts |
·
Individual Risk complies with the Hong Kong Risk Guidelines. · Societal Risk associated with the on-site transport, storage and handling of chlorine at Sha Tin WTW and off-site transport of chlorine within the Consultation Zone, expressed in the form of FN curves, lies within the “ALARP” region of the Hong Kong Risk Guidelines |
·
Individual Risk complies with the Hong Kong Risk Guidelines · Similar to Construction Phase Societal Risk lies within the “ALARP” region of the Hong Kong Risk Guidelines |
Cumulative Impacts |
·
Cumulative Individual Risk within the Consultation Zone, combining
risks from the on-site transport, storage and use of chlorine, off-site
chlorine transport, Beacon Hill North Offtake Station, the 750mm and 500mm
gas pipelines that run through the Old Beacon Hill Tunnel, and the explosives
transport and use for SCL construction have been found in the maximum order
of 10-6 per year which complies with the Hong Kong Risk Guidelines. · The Cumulative Societal Risk lies within the “ALARP” region of the Hong Kong Risk Guidelines. |
·
Cumulative Individual Risk within the Consultation Zone, combining
risks from the on-site transport, storage and use of chlorine, off-site
chlorine transport, Beacon Hill North Offtake Station, the 750mm and 500mm
gas pipelines that run through the Old Beacon Hill Tunnel, and the explosives
transport and use for SCL construction have been found in the maximum order
of 10-6 per year which complies with the Hong Kong Risk Guidelines. · The Cumulative Societal Risk lies within the “ALARP” region of the Hong Kong Risk Guidelines. |
Key
Mitigation Measures |
·
A number of mitigation and good practice measures were considered and
recommended to minimise the chlorine risks during Construction Phase. · A number of mitigation measures, mostly related to the chlorine truck design have also been recommended for the off-site chlorine transport. |
·
No risk mitigation measures for on-site operations were found to be
practicable for Sha Tin WTW. · A number of mitigation measures, mostly related to the chlorine truck design have been recommended for the off-site chlorine transport |
Residual Impact |
·
The residual risks remain in the ALARP region ·
The Sha Tin WTW Reprovisioning is an improvement project. As a result,
the chlorine-related risks for the surrounding population will be reduced in
comparison with current levels. |
·
The residual risks remain in the ALARP region · The Sha Tin WTW Reprovisioning is an improvement project. Due to the introduction of the new treatment technologies, the reprovisioning works will lead to a permanent reduction in chlorine storage and usage at the WTW. As a result, the chlorine-related risks for the surrounding population will be reduced in comparison with current levels. |
|
Prior
to Construction |
Construction
Phase |
Operation
Phase |
Air
Quality |
O |
ü |
O |
Noise |
O |
ü |
O |
Water
Quality |
O |
ü |
O |
Waste |
O |
ü |
O |
Ecology |
O |
ü |
O |
Landscape
and Visual |
O |
ü |
O |
Cultural
Heritage |
O |
ü |
O |
Land
Contamination |
ü |
O |
O |
Hazard
to
Life |
O |
ü |
O |
Air Quality
Terrestrial
Ecology
Land
Contamination
Hazard to
Life
6.2 Overall, the EIA study for the In-situ
Reprovisioning of Sha Tin WTW (South Works) has predicted that the Project,
with the implementation of the mitigation measures, would be environmentally
acceptable with no adverse residual impacts on the population and
environmentally sensitive resources. Table 6.1
below summarises the environmental outcomes/benefits that have accrued from the
environmental considerations and analysis during the EIA process and the
implementation of environmental control measures of the Project.
The
Project Need |
·
aging of plant and equipment after more than 40 years of service
requiring major renovation or replacement; and ·
reprovision of the South Works of the existing Sha Tin WTW with a
treatment process that can continue to meet the latest treated water quality
standards and future water demands. |
Environmental/Social Benefits of the Project |
·
provision of a safe and reliable water supply; ·
Improvement in water supply reliability to the territory; ·
development of environmentally sustainable design by applying
low-carbon concept; ·
Provision of visitor facilities to the public on modern water
treatment technologies and water conservation. |
Environmentally
Friendly Design and Benefit |
·
In-situ reprovisioning of the WTW promotes re-use of land, thereby
minimising the environmental impacts and costs of developing a new site; ·
About 90% of the works area is situated within the existing Sha Tin
WTW is of low ecological value. The impact
to natural habitat is minimized; ·
Impacts to ecological sensitive areas have been minimized through the
design process (e.g. use of retaining wall instead of soil nails); ·
The adoption of new treatment processes will reduce the use of
chlorine, which presents a significant risk to adjacent communities; ·
Engineering design for fixed plant complies with the day-time, evening
time and night time noise criteria; ·
Lighting/glare control; ·
Green roof, sensitive landscaping, other sustainability features. ·
Due to the introduction of the new treatment technologies, the
reprovisioning works will lead to a permanent reduction in chlorine storage
and usage at the WTW. As a result, the
chlorine-related risks for the surrounding population will be reduced in
comparison with current levels. |
Air
Quality |
Potential air quality
impacts from the construction works of the Project would mainly be related to
construction dust from excavation, materials handling, spoil removal,
demolition and wind erosion. In view
of the nature of works, adverse dust impact at the ASRs would not be expected
from the Project. Nevertheless,
appropriate dust suppression measures as stipulated in the Air Pollution
Control (Construction Dust) Regulation should be implemented to minimize any
potential dust impact. |
Noise
Impact |
Construction Noise This assessment has
presented the construction noise impacts of the Project during normal daytime
working hours. The predicted
unmitigated noise levels at representative NSRs would range from 46 to 78 dB(A). With the adoption of quiet PME and use of
movable noise barrier, the noise levels due to the Project itself at all
representative NSRs would comply with the EIAO-TM criteria. The overall increase of
cumulative noise level and adverse residual impact, due to the Project
itself, are not anticipated. Fixed Plant Noise The noise impact
associated with the operation of the Project has been assessed. The predicted fixed plant noise levels at
the representative NSRs would be expected to comply with the day-time,
evening time and night time criteria based on the assessment using a set of
specified maximum SWLs for the newly proposed fixed plant. If there is any change in engineering
design information during detailed design stage or fitting-out stage, the
fixed source noise design should be reviewed by the Engineer/Contractor to
ensure that both the NCO and EIAO-TM criteria at NSR can be met in the
future. |
Water
Quality |
Potential water quality
impact associated with land-based construction works for the Project would be
generated from site run-off, wastewater from construction activities, and
sewage from workforce. Provided that
all the recommended mitigation measures are properly implemented, no adverse
water quality impacts would be expected during the construction phase of the
Project. Water quality monitoring of the two water courses along the Project
boundary is recommended during site clearance and foundation works to ensure
no adverse water quality impacts to these water courses. Regular site inspection is also recommended
to ensure the recommended mitigation measures are properly implemented. During operation phase of
the Project, major sources of water quality impact would be washwater
effluent and overflow from treatment works components. Proper mitigation measures will be
implemented to avoid discharge of washwater effluent and overflow into the
nearby water environment and hence no adverse water quality would be
expected. |
Waste
Management |
Waste types generated by
the construction activities are likely to include inert and non-inert C&D
materials from demolition works of existing facilities of the South Works,
construction works of new facilities for the South Works and common
facilities for the North and the South Works, slope excavation works and
construction works of new access roads, general refuse from the workforce and
chemical wastes from the maintenance of construction vehicles and
equipment. Provided that these
identified wastes would be handled, transported and disposed of using the
recommended methods and that good site practices would be strictly followed,
adverse environmental impacts are not expected. The waste management
assessment has recommended good waste management practices to ensure that
adverse environmental impacts are prevented.
The assessment concluded that no unacceptable environmental impacts
would result from the storage, handling, collection, transport and disposal
of wastes arising from the construction and operation of the project. |
Terrestrial
Ecology |
A literature review and
ecological field surveys have been conducted. Four habitat types were
identified within the study area including secondary woodland, plantation,
watercourse and developed area. The
secondary woodland habitat is considered to have high ecological value. The other habitat was regarded as of low
value. Six flora and 30 fauna species
of conservation importance were recorded from the study area during surveys. Major ecological impacts
would include direct impact on the secondary woodland habitat and the floral
species of conservation importance.
The impacts to about 0.69 ha of secondary woodland habitat would be
compensated by the creation of about 0.23 ha on-site of woodland habitat
within the Sha Tin WTW and about 0.29
ha off-site of
woodland habitat at Sha Tin South
Freshwater Service Reservoir nearby and northwest of Sha Tin West Service
Reservoir (a total of about 0.52 ha). The area of
secondary woodland habitat would be reduced by about 0.17ha. Feasible woodland compensation locations
have been exhaustively investigated and residual impact is minimised as far
as practicable. Considering the size
and value of the habitat affected, the residual impact is considered to be
insignificant, with the implementation of the recommended habitat
compensation. Four flora species of
conservation importance (Incense Tree, Ailanthus, Lamb of Tartary, and Hong Kong Eagle’s Claw) would be
directly affected by the Project.
Detailed vegetation surveys should be conducted to identify the
affected individuals within the proposed works area. Transplantation is recommended as far as
possible to minimize the direct impact of these important species. The implementation of a
mitigation strategy for Short-nosed Fruit Bat will avoid impacts to this
species, thereby resulting in no adverse impact. Indirect impacts during the construction
phase would comprise noise and human disturbance, construction dust, and
construction site runoff. With proper
implementation of good site practices and noise mitigation measures, no significant
adverse ecological impact is anticipated. The level of disturbance
during the operation phase would be comparable to the existing
condition. No significant adverse
impact is therefore expected. With the implementation
of the recommended mitigation measures, no unacceptable residual indirect
impact due to the construction and operation of the proposed Project would be
expected. The implementation of
mitigation measures would be subject to regular audit as part of the EM&A
programme. |
Landscape
and Visual |
The proposed works of the
Project at Sha Tin WTW would inevitably result in some landscape and visual
impacts during the construction and operation phases. These impacts have been minimized through
careful consideration of alternatives, minimization of works areas,
incorporation of aesthetic external designs and landscape treatments of
proposed structures. The proposed works will
be mainly located within the existing Sha Tin WTW Compound under the Other
Specified Uses (OU) of the Approved Sha Tin Outline Zoning Plan No. S/ST/30. It is considered that the proposed Project
is permitted development under the OZP and would fit in with the current and
future planning settings and would not be in conflict with the statutory town
plan. Based on a preliminary
tree survey, approximately 800 existing trees will be affected by the
proposed works. Among these 800 trees,
approximately 652
trees will be felled due to the Project.
None of these are Registered Old and Valuable Trees. There are approximately 21 nos. of Aquilaria sinensis which is protected
under Cap. 586 in Hong Kong and 1 no. of Ailanthus
fordii under the Forest and Countryside Ordinance (Cap 96). Any affected Aquilaria sinensis and Ailanthus
fordii including other trees of conservation importance are proposed to
be transplanted where possible.
Detailed tree survey and removal application will be submitted in
accordance with DEVB TCW No. 10/2013 - Tree Preservation separately. Under the proposed scheme for the Project,
opportunities for tree compensation within the project boundary have been
fully explored and incorporated in the proposed mitigation measures as much
as practicable. Due to limited
available space for tree planting within the project boundary, approximately
200 nos. of heavy standard trees and 460 nos. of light standard trees are
proposed on-site and off-site at Sha Tin South Freshwater Service Reservoir
and Sha Tin West Service Reservoir at Po Fook Shan to compensate for the tree
to be felled. It offers a compensation
ratio greater than 1:1 (i.e. approximately 660 newly planted trees v.s.
approximately 652
felled trees). Approximately 2,300m2
of woodland mix planting are proposed on-site whereas about 2,900m2
off-site to compensate for the affected woodland habitat. There would be substantial
residual landscape impact on LR1 and moderate residual landscape impact on
LR2, LR3, LR4 and LCA2 with the implementation of proposed mitigation
measures during construction phase. The residual impact of LR1 would be moderate and LR2, LR3, LR4 and
LCA2 would be slight in Day 1 operation phase and reduced to slight and
insubstantial in Year 10 of operation phase when the proposed compensatory
planting including woodland mix planting becomes mature. Because not all woodland/tree compensation will be provided
on-site, some of the woodland/tree
planting will be compensated off-site.
There would still be some slight residual impact on LR1. There would be moderate
residual visual impact on VSRs R1, R2, R3, R4, GIC1, O1 and O2 and slight
residual impact on VSRs T1 and T2 during the construction phase. The residual impact would be slight in Day
1 of Operation Phase and reduced to insubstantial in Year 10 of Operation
Phase. Although there is slight
residual impact on LR1, as a whole, it is considered that the residual landscape
and visual impacts of the proposed project is considered acceptable with
mitigation measures implemented during construction and operation phases. |
Cultural
Heritage |
Cultural heritage
resources within the study area have been identified and reviewed through
site surveys and literature review. No
archaeological potential is present within the study area. Therefore no impact to archaeology is
anticipated. Direct impact on three existing graded historic buildings at Hin Tin
village and the Ex KCR Beacon Hill Tunnel during construction phase is not
anticipated.
Considering sufficient buffer
distances between the built heritages at Hin Tin village (approximately 270
m) and the proposed works areas, there would be insignificant visual and vibration impact during construction and operation phases. Four existing staff quarters would be refurbished
to be used as construction site office located in close proximity to the west
of Ex KCR Beacon Hill Tunnel portal, and the proposed Administration Building
cum Mainland East Laboratory would also be built at about 120 m to the northwest of the portal. Due to the proposed work design and distance
between these buildings and the tunnel portal, vibration impact on the facade
wall of portal is considered to be insignificant. As precautionary measure, ppv limit of
7.5mm/s is recommended, including measuring at the facade wall of tunnel
portal and inside the tunnel where it is nearest to any construction works within
the Works Area. In
conclusion, the construction and operation of the Project would not cause
unacceptable impacts on cultural heritage resources, with implementation of
the recommended mitigation measures. |
Land
Contamination |
This assessment has
examined the potential contaminating land uses within the Project site. It also covers potential impacts of the
contamination on future use. The
assessment involved site appraisal and preparation of CAP. Site investigation will
be carried out at the decommission stage of the Project site due to site
access and sensitive nature of the water works. Based on the findings in the site
investigation, if any contamination is found, appropriate remediation
measures shall be identified and carried out before construction commences,
so as to clean up the Project site to the relevant Risk-based Remediation
Goals (RBRGs). With the remediation
and mitigation measures in place, the potential land contamination impacts to
the sensitive receptors and future use as water treatment facilities are thus
not considered to be insurmountable. As
a precaution, mitigation measures are proposed for the excavation of soil,
treatment of soil and general environmental, health and safety on site during
the construction stage. |
Hazard
to Life |
A
Hazard Assessment of the risks associated with the transport, storage and use
of chlorine at Sha Tin WTW and off-site transport of chlorine within the
Consultation Zone has been conducted for the Construction and Operational
Phases of the Project. To obtain the total chlorine risks, risks from the on-site
Sha Tin WTW chlorine transport, storage and use were combined with the
off-site chlorine transport risks. The
Sha Tin WTW Reprovisioning is an improvement project. Due to the introduction
of the new treatment technologies, the reprovisioning works will lead to a
permanent reduction in chlorine storage and usage at the WTW. As a result,
the chlorine-related risks for the surrounding population will be reduced in
comparison with current levels. The
assessment results show that for both Construction and Operational Phases,
the Individual Risk complies with the Hong Kong Risk Guidelines. The
Societal Risk lies within the As Low As Reasonably Practicable (ALARP) region
of the Hong Kong Risk Guideline (HKRG). An ALARP assessment has been carried
out to identify feasible mitigation measures and assess the cost
effectiveness of each measure in terms of risk reduction achieved and the
cost of implementing the measures, a number of recommendations have been
made. The residual risks remain in the ALARP region. Cumulative
Individual Risks within the Consultation zone were also presented by
combining risks from the on-site transport, storage and use of chlorine,
off-site chlorine transport, Beacon Hill North Offtake Station, the 750mm and
500mm gas pipelines that run through the Old Beacon Hill Tunnel, and the
explosives transport and use for SCL construction. The cumulative Individual
Risk values are low and in the maximum order of 10-6 per year
which complies with the Hong Kong Risk Guidelines. The Cumulative Societal
Risk lies within the “ALARP” region of the Hong Kong Risk Guidelines. |