Table of Contents
1. Introduction
1.1. Background
1.2. Objectives
of the EIA Study
1.3. Detailed
Requirements of the EIA study
1.4. Approach
of Assessment
1.1.1. Allied Environmental Consultants Limited (AEC) was commissioned to undertake an Environmental Impact Assessment for the decommissioning works of the west portion and southern edge of the Middle Ash Lagoon at Tsang Tsui, Tuen Mun followed by site formation works and construction of site drainage system and construction of access road (hereinafter known as the ¡§Project¡¨). The Project will provide buildable land for future developments on the site location. The future development is planned to be the provision of Columbarium and Garden of Remembrance by the Food and Environmental Hygiene Department (FEHD). The proposed location of the Project is shown in Figure 1.1. The Environmental Impact Assessment (EIA) study aims to evaluate the potential environmental impact associated with the provision of buildable area at Tsang Tsui, Tuen Mun.
1.1.2. The Project is a designated project under Item 8 of Part II, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO), i.e. decommissioning of a waste disposal facility for pulverized fuel ash, furnace bottom ash or gypsum. An Environmental Permit (EP) is required for its decommissioning, construction and operation. An application for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) (a) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by the Applicant on 26 March 2012 with Project Profile (No. PP-460/2012). The decommissioning works of the west portion and southern edge of the Middle Ash Lagoon, site formation works and construction of site drainage and construction access road works are considered as a part of Designated Project and shall be covered in this Environmental Impact Assessment Report.
¡P The
acceptability of adverse environmental consequences that are likely to arise as
a result of the project;
¡P The
conditions and requirements for the detailed design and/or proposed
decommissioning works to mitigate against adverse environmental consequences
and;
¡P The
acceptability of residual impacts after the proposed mitigation measures is
implemented.
1.2.1. The objectives of the EIA study are as follows:
¡P To
describe the Project and associated works together with the requirements and
environmental benefits for implementing the Project;
¡P To
identify and describe the elements of the adjacent community and environment
likely to be affected by the Project, and/or likely to cause adverse impacts to
the Project, including both natural and man-made environments and the
associated environmental constraints;
¡P To
identify and quantify: all environmental sensitive receivers, emission sources,
determine the significance of impacts on sensitive receivers and potential
affected uses, and to propose measures to mitigate these impacts;
¡P To
identify and quantify any potential losses or damage to flora, fauna and
natural habitats; good
¡P To
propose the provision of infrastructure or mitigation measures to minimize
pollution, environmental disturbance and nuisance during the decommissioning
activities, related site formation works and other construction works; good
¡P To
investigate the feasibility, effectiveness and implications of the proposed mitigation
measures; good
¡P To
identify, predict and evaluate the residual (i.e. after practicable mitigation)
environmental impacts and the cumulative effects expected to arise from the
decommissioning works in relation to the sensitive receivers and potential
affected uses;
¡P To
identify, assess and specify: methods, measures and standards to be included in
the decommissioning works which are necessary to mitigate these residual
environmental impacts and cumulative effects to reduce them to acceptable
levels;
¡P To
design and specify the environmental monitoring and audit requirements; and
¡P To
identify any additional studies necessary to implement the mitigation measures
or monitoring and proposals recommended in the EIA report.
1.3.1. Detailed requirements of the EIA study are set out in Section 3 of the EIA Study Brief (No. ESB-243/2012). As specified in the EIA Study Brief (No. ESB-243/2012), the EIA study has addressed the key environmental issues associated with the decommissioning and construction of the Project in Hong Kong waters and land.
¡P The
potential air quality impacts from the decommissioning and construction works;
¡P The
potential health impacts from the Project including radon emissions from
pulverized fly ash within the Ash Lagoon due to the decommissioning and
construction works;
¡P The
potential sound pollution as a result of
the decommissioning and construction works;
¡P The
potential water quality impact from the decommissioning and construction works;
¡P The
potential waste management issues and impacts arising from the decommissioning
and construction works;
¡P The
potential land contamination arising from the decommissioning and construction
works;
¡P The
potential ecological impact arising from the decommissioning and construction
works including the loss of habitats, removal of vegetation and disturbance of
wildlife;
¡P The
potential risks of landfill gas during the decommissioning and construction
works due to the proposed West New Territories (WENT) Landfill Extensions; and
¡P The
potential cumulative environmental impacts of the Project and associated works,
through interaction or in combination with other existing, committed and
planned projects in their vicinity, and that those impacts may have a bearing
on the environmental acceptability of the Project.
¡P Description
of the environment;
¡P Impact
prediction;
¡P Impact
evaluation; and
¡P Impact
mitigation.
1.4.2. The characteristics of the existing environment are reviewed for identification and prediction of environmental impacts. Where necessary, baseline surveys would be conducted to determine the existing environmental conditions on the Subject Site and in any environs likely to be affected by the Project. The baseline conditions of the key issues as identified in the EIA Study Brief (No. ESB-243/2012) includes: air quality, noise, water quality, waste management, health risk, land contamination, landfill gas and ecology are described in the assessment.
1.5.1. The structure of this EIA study is outlined below for ease of reference:
Section |
Title |
Aims |
1 |
Introduction |
To provide project background, purpose and scope of the EIA study and
to define the EIA Study Area |
2 |
Description
of the Project |
To describe the project requirements, consideration of alternative and
major activities in the Project |
3 |
Air
Quality Impact |
To assess the potential air quality impact of the Project and suggest
mitigation measures |
4 |
Health
Impact |
To assess the potential health impact of the Project and suggest
mitigation measures |
5 |
Noise
Impact |
To assess the potential noise impact of the Project and suggest
mitigation measures |
6 |
Water
Quality Impact |
To assess the potential water quality impact of the Project and
suggest mitigation measures |
7 |
To assess the potential waste management implications of the Project and
suggest mitigation measures |
|
8 |
Land Contamination |
To assess the potential land contamination impact of the Project and suggest mitigation measures |
9 |
Ecological
Impact |
To assess the potential ecological impacts of the Project and suggest mitigation
measures |
10 |
Landfill
Gas Hazards |
To assess the potential hazards arising from landfill gas migration
and suggest precautionary measures |
11 |
Summary
of Environmental Outcomes |
To contain a summary of the key environmental outcomes arising from
the EIA study |
12 |
Environmental
Monitoring and Audit Requirements |
To define the scope of the EM&A requirements for the Project |