Issue
No. :
Final 1
Issue
Date :
Nov 2014
Project
No. :
1080
Environmental
Impact Assessment (EIA) Executive Summary
for
Decommissioning
of West Portion of the Middle Ash Lagoon at Tsang Tsui, Tuen
Mun
Prepared
By:
Allied
Environmental Consultants Ltd.
Project Location and Site History
Background and Need for the Project
Consideration of Alternative
Decommissioning Methods
Key Findings of the Environmental Impact Assessment
Environmental Monitoring and
Audit
Allied Environmental Consultants Limited (AEC) was
commissioned to undertake an Environmental Impact Assessment (EIA) for the
decommissioning works of the west portion and southern edge of the Middle Ash
Lagoon, Tsang Tsui followed by site formation works and construction of
drainage and construction access road works (hereinafter known as the
“Project”). The EIA study aims to evaluate the potential environmental impact
associated with the provision of buildable land at the west portion and
southern edge of the Middle Ash Lagoon, Tsang Tsui for the future development.
One of the possible future developments is the provision of Columbarium and
Garden of Remembrance by the Food and Environmental Hygiene Department (FEHD).
The Project is a designated project under Item 8 of
Part II, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO),
i.e. decommissioning of a waste disposal facility for pulverized fuel ash,
furnace bottom ash or gypsum. Hence an Environmental Permit (EP) prior to the
decommissioning works is required. The construction of Columbarium and Garden
of Remembrance, however, does not fall under a designated project and shall not
be detailed in the EIA report.
A Project Profile (PP-460/2012) for the Project was
submitted to EPD and an EIA Study Brief (No. ESB-243/2012) under the EIAO was
issued by EPD on 30 April 2012. An Environmental Impact Assessment (EIA) study
was conducted in accordance with EIA Study Brief (No. ESB-243/2012)
to provide information on the nature and extent of environmental impact which
will arise from the construction and operation of the Project and related
activities taking place concurrently.
This Executive Summary presents the key findings of
the Environmental Impact Assessment (EIA) for the Project as required under the
EIAO.
The Subject Site is located in the western part of the
Middle Ash Lagoon in Tsang Tsui, Tuen Mun. The site is being operated by Castle Peak Power
Company Limited (CAPCO) for the storage of water and pulverised fuel ash (PFA),
a by-product of burnt coal from the adjacent Castle Peak Power Station. The ash
lagoons at Tsang Tsui was formed by reclamation in the
1980s and is occupied by CAPCO exclusively. According to the current programme,
CAPCO will surrender the middle lagoon to the Government in first quarter of
2015.
The
Project consists of the Subject Site with a total area of about 30,000m2
(3.0 hectares). It comprise of 2.7ha of dry PFA platform and 0.3ha of low zone
along the northern boundary, where generally filled up with water by a man-made
water channel. The site faces Castle Peak to the south and is separated from
Shen Zhen Bay by a seawall on the north.
With reference to the approved EIA report from EPD for
the Development of the Integrated Waste Management Facilities (IWMF) Phase 1
(application no. EIA 201/2011), the area directly to the east of the Subject
Site is one of the potential sites for the IWMF Phase 1. The remaining Middle
Ash Lagoon area will be taken over by the Environmental Protection Department
(EPD) as an extension of WENT Landfill (WLES) (application no. EIA-171/2009).
Further to the east in the East Lagoon, a Sludge Treatment Facilities (STF)
(application no. EIA-155/2008) development is currently under construction which is scheduled to be
completed in 2015.
Subject
Site (Photographed on 2014.04.04)
The
potential of environmental impact induced by decommissioning of the ash lagoons
at Tsang Tsui had been evaluated in detail by previously approved EIA studies,
including Sludge Treatment Facility (EIA-155/2008), West New Territories (WENT)
Landfill Extensions (EIA-171/2009), and proposed Integrated Waste Management
Facility (EIA-201/2011).
All
these approved EIA concluded that the potential adverse environmental impact are of insignificant level to sensitive receivers.
Take into consideration the similar activities and sensitive receivers of this project
to the aforementioned EIA studies, the potential adverse environmental impact
are anticipated to be insignificant level to sensitive receivers.
Finding a solution to limited land resources has
always been in the agenda for Hong Kong. In light of the fact that the Site
Area will be surrendered by CAPCO to the government in the first quarter of
2015, it is necessary to utilize this new plot of vacant land to good use.
Before any development planning, decommissioning would
be deemed to be required for any future development due to its current use as
pulverized fuel ash storage area. The EIA had evaluated the environmental
impacts associated with the decommissioning process at the west portion of the
Middle Ash Lagoon at Tsang Tsui, Tuen Mun. One of the potential usages of this new plot of vacant
land is the development of Columbarium.
Due to its size and separation from domestic
developments, the Subject Site is considered a favourable candidate for
columbarium facility. As such, the Project aims to provide buildable land for
the future government developments, amongst them a Columbarium and Garden of
Remembrance through decommissioning of the western part of the Middle Ash
Lagoon.
The decommissioning works which consists of covering
of 1m thick general fill above the final PFA platform at the Subject Site and
Construction Access Road Area would provide environmental benefit as it
prevents potential PFA exposure to the Public and provide buildable land for
future developments on the Subject Site.
The aim of the EIA study is to evaluate the
environmental impacts related to decommissioning process of west portion of the
Middle Ash Lagoon at Tsang Tsui, Tuen Mun and its associated site formation works. A fundamental
project alternative is the option to not implement the decommissioning, site
formation, drainage and road works, which in environmental terms is referred to
be as the “Do-nothing” option. However, the provision of buildable land is
essential in order for the government to provide sufficient facilities to the
public. As such, the “Do-nothing” option is not preferred.
The decommissioning works in the Project shall mainly
involve the following:
•
Covering
of 1m thick general fill above the final PFA surface with minor levelling works
•
Formation of Construction Access Road (North) by filling and
levelling followed by layering of a 1m thick general fill above the final PFA
surface to proposed levels
•
Formation
of part of the Construction Access Road (South) by layering of a 1m thick
general fill above the final PFA surface to proposed levels, followed by
levelling and slope works along the road section approaching to the Site
In addition, associate works in the Project, which
will not involve decommissioning, include the following:
•
Minor reinstating works on part of the existing access road to
form the Construction Access Road (South)
•
Construction
of retaining structure for slope stabilization along the edge of existing water
channel near the north site boundary
•
Installation
of surface drainage outfall system for discharging the surface water out of the
complete buildable land at the north-west corner of the Subject Site
•
Installation
of site hoarding and temporary surface drainage system
The operational phase of the Project is when the
decommissioning works detailed above is completed to provide a flat
buildable land for future development by the government.
The decommissioning works will commence around
September 2015. The completion date is tentatively scheduled on March 2016.
The
Project is located in the ash lagoon areas which are currently occupied by
CAPCO for uses relating to the operation of the Castle Peak Power Stations.
Various projects have been proposed in the Nim Wan
and Tsang Tsui areas, including the STF, WLES, and the IWMF.
Potential
decommissioning methods are identified as (1) in-situ treatment such as
hardening with cement; (2) off site treatment or storage; and (3) covering with
soil.
In-situ
treatment
In-situ
treatment, such as hardening with cement could chemically and physically fix
the PFA in the cement matrix, leading to the stable ground condition. However,
this method is considered not feasible, due to the large quantity
(approximate 15,000m3) of cement is required to fix the PFA with
the Site.
Off Site Treatment
Taken
into account of the relatively stable PFA and its large quantity, disposal of
PFA to other storage facilities is not a favourable
environmental alternative since it would generate a large amount of PFA as
waste. Excavating the PFA to off-site location for recycle and treatment would
involve extensive transportation. Moreover, excavation of PFA would pose
possible environmental and health hazards to workers due to PFA dust emission
during excavation works. In addition, transportation of large amount of PFA for
disposal is not a cost-effective option. In addition, there are
currently no government-specified location for the disposal of PFA.
Recycle
for Concrete Production
Due
to the large amount of PFA, exportation of PFA for reproduction of concrete
might would require transportation of large quantity of PFA and also a long
period of time for consumption. It may cause more environmentally adverse
impacts to the public and fail to provide buildable land in the case of the
shortage of territory currently.
Covering
with Soil
Leaving
the PFA in-situ is considered as the most cost and environmental viable option.
As such, decommissioning of the Subject Site through covering of 1m thick
general fill above the final PFA surface upon minor levelling works is adopted
in this Project. Different fill materials such as broken stone, concrete, and
other hard inert material, have been considered for filling of PFA areas.
However, the import of general fill compared with the aforementioned
alternative materials is more cost-effective. Moreover, in the long run,
general fill material is easier to manage for any future developments at
Subject Site.
Preferred
Decommissioning Method
The
Project’s adopted decommissioning method of importing 1m thick general fill to
cover the PFA surface aims at cost-effectiveness while minimizing impact on the
environment. During the Project, mobilisation and
preparation/establishment will be carried out by the Contractor. Careful design
of the decommissioning works will be adopted to optimize the import of
materials. No surplus construction materials/waste is to be delivered to public
fill bank.
Slope
Stabilization Works
To
the existing water channel at the north of the Subject Site, one of the options
is to fill up the entire water channel to provide more land for future
developments. However, in view that the water channel may provided suitable
nesting grounds to Little Grebes as breeding habitat during the wet season,
filling up the water channel is deemed to cause the ecological impact. In this
connection, the decommissioned area is considered to reduce and the
construction sequence is carefully phased in order to reduce the Project’s
environmental impact to the Little Grebes.
In
the current design, slope stabilization works would be carried out to the edge
of the water channel to prevent soil loss of water channel through erosion as
well as providing a stable habitat. A surface water drainage system would be
constructed to discharge future storm water runoff from the Subject Site and
prevent adverse environmental impact to the water channel. Such works would
provide long-term environmental benefits as well as minimization of habitat
loss
Potential air quality impact associated with the
construction and operational phase of the Project have been assessed in the EIA
report. Representative Air Sensitive Receivers (ASRs) within 500m of the
Subject Site have been identified.
A total of two representative ASRs were identified for
this assessment in accordance with the criteria set out in the EIAO (TM). They
include (1) the current WENT Landfill Site office and (2) STF
Office located at over 200m from the Subject Site.
Construction
Phase
Air quality impacts from the decommissioning and
construction works for the Project would mainly be related to construction dust
from materials handling, construction access road, filling activities, wind
erosion of open sites and stockpiling areas.
Effective dust control following the requirements
given in the Air Pollution Control (Construction Dust) Regulation and in
accordance with the EM&A programme during construction are recommended.
With implementation of control measures the proposed Project would not cause
adverse cumulative air quality impact at all air sensitive receivers in the
vicinity of the Subject Site.
In
view of the large separation distance (more than 200m) of the nearby ASRs from
the Project Site, no dust monitoring is considered necessary. Yet, regular site
environmental audits during the construction phase of the Project will be
conducted to ensure that the recommended dust suppression measures are
implemented properly.
Operational
Phase
The operational phase of the Project shall be a piece
of buildable land available for future developments by the government. Since
the operational phase does not involve any equipment operation or human
activities, adverse air quality impact is not expected.
Potential health impact associated
with the construction phase of the Project have been assessed in the EIA
report.
Construction
Phase
A Human Health Risk Assessment has been conducted to
identify potential health effects from exposure to chemicals in a contaminated
environmental media. Through a systematic screening, 7 Chemicals of Particular
Concerns (COPCs) were identified: Arsenic, Cadmium, Lead, Nickel, Chromium
(VI), Manganese, and Mercury. Quantitative risk assessment was conducted for
these COPCs, and it was determined that the calculated incremental risk levels
caused by the decommissioning works would be below risk levels of 1 in 100,000
as suggested by US Environmental Protection Agency (USEPA), thus adverse health
effect is unlikely to be anticipated.
Cumulative non-carcinogenic health impact has been
assessed and compared with local and overseas guideline levels. As the
predicted COPCs concentration
are found to be lower than the corresponding guideline
levels, it
was concluded that the levels of non-carcinogenic chemicals were found to be
insignificant when compared to the adopted/derived reference levels.
The health risk arising from radon emission from PFA
has been evaluated. Quantitative assessment has been conducted to determine the
radon risks of on-site workers. It was found that the workers’ predicted annual
effective dose is less than annual limit of 1 mSv for
general public as suggested by the International Commission on Radiological
Protection (ICRP). The findings also meet the findings from various literature
researches, in which the radon health risk for the decommissioning works is of
insignificant level.
Potential noise impacts associated with the
construction and operational phase of the Project have been assessed in the EIA
report. Noise sensitive receivers were not identified within 300m of the
Subject Site. Nearest possible noise sensitive receivers identified include
village houses at Lung Kwu Sheung
Tan and Ha Pak Nai, located 3km and 2km away from the
Subject Site.
Construction
Phase
Potential construction noise impacts are likely caused
by various construction activities on site, such as, formation of construction
access road by excavation, filling and leveling
works, installation of temporary surface drainage system, site formation works
including leveling of PFA surface and filling of 1m
thick general fill.
Assessment results show that the maximum
predicted noise level associated with
the construction activities on the Subject Site to Noise Sensitive Receivers of
Lung Kwu Sheung Tan and Ha
Pak Hai would be 49dB(A), which does not exceed the noise criteria as specified
in the Technical Memorandum on Environmental Impact Assessment Process.
Good practices stipulated in relevant standards and
Technical Memorandum for the control of noise emissions from construction sites
are still recommended to further reduce any potential nuisance. Adverse noise
impact during the construction phase is not anticipated. In view of the large
separation distance of the nearby NSRs from the Project Site, no noise
monitoring is considered necessary. Yet, regular site environmental audits
during the construction phase of the Project will be constructed to ensure that
the recommended noise mitigation measures are implemented properly.
Operational
Phase
The operational phase of the Project shall be a piece
of buildable land available for future developments by the government. Since
the operational phase does not involve any equipment operation or human
activities, adverse noise impact is not expected
Potential water quality impacts associated with the
construction and operational phase of the Project have been assessed in the EIA
report. Representative Water Sensitive Receivers (WSRs) within 500m of the
Subject Site have been identified.
Three water sensitive receivers have been identified
within 500m from the site boundary of the Project. They include two moderate
sized streams (“Stream W1” and “Stream W2”) located at the southern part of ash
lagoon and discharged into a tidal channel to the east of the ash lagoon area
and Deep Bay.
Construction
Phase
Sources of water quality impact throughout the
decommissioning and construction phase include (1) drainage and construction
site-runoff from construction of retaining structures for slope stabilization
and construction of surface drainage outfall, (2) PFA contaminated surface
runoff, (3) sewage effluent produced by workforce and (4) wastewater generated
from general construction activities.
With proper implementation of construction site
mitigation measures and good site practices as followed to ProPECC
PN 1/94, such as provision of site runoff collection system and chemical
toilets, adverse water quality impacts during construction phase is not
anticipated.
A water quality monitoring programme and site environmental
inspection will be implemented to ensure the effectiveness of
the recommended mitigation measures.
Operational
Phase
The operational phase of the Project shall be a piece
of buildable land available for future developments by the government. Since
the operational phase does not involve any equipment operation or human
activities, adverse water quality impact is not expected.
Potential waste management options associated with the
construction and operational phase of the Project have been assessed in the EIA
report. Mitigation measures and good site practices were identified and were
recommended in the EIA report with reference to the applicable waste
legislations and guidelines.
Construction
Phase
The types of waste that would be generated during the
decommissioning and construction phases of the Project include construction and
demolition (C&D) materials from the construction activities, general refuse
from the workforce and chemical wastes from the maintenance of construction
equipment. The estimated amount of C&D fill material is 30,000m3
for Subject Site and 10,000m3
for Construction Access Road Area.
All PFA excavated during levelling works shall be
reused as site formation material within the site boundary. This shall be
included in contractual specifications.
Various waste management options were explored to
minimize the environmental impact. The hierarchy shall be adopted in the
following order:
–
Avoidance
and reduction;
–
Reuse
of materials;
–
Recovery
and recycling; and
–
Treatment
and disposal
The decommissioning contract has provision for how the
wastes are handled, transported and disposed of properly and good site
practices and waste reduction measures are implemented accordingly, adverse
environmental impact is not expected during the construction phase of the
Project.
Operational
Phase
The operational phase of the Project shall be a piece
of buildable land available for future developments by the government. Since
the operational phase does not involve any equipment operation or human
activities, adverse environmental impact is not expected
Potential land contamination impact associated with
the construction and operational phase of the Project have been assessed in the
EIA report. Land contamination assessment has been conducted based on
historical and current land use.
Construction
Phase
The Subject Site has been used by CAPCO for the
storage of water and PFA since the 1980s. An assessment was conducted with
reference to the checklist obtained from Annex C1 of Practice Guide for
Investigation and Remediation of Contaminated Land. The results confirmed that
no known contaminants or chemicals were found on site aside from PFA. It is
concluded that there is no adverse impact from land contamination.
Operational
Phase
The operational phase of the Project shall be a piece
of buildable land available for future developments by the government. Since
the operational phase does not involve any equipment operation or human
activities, adverse environmental impact from land contamination is not
expected.
Potential landfill gas (LFG) hazards during the
construction and operational phase of the Project have been identified. The potential impacts of LFG hazards from the
proposed WENT Landfill Extension have been assessed based on the Landfill Gas
Hazard Assessment (LFGHA) Guidance Note.
Construction
Phase
Landfill Gas Hazard Assessment Study was conducted in
accordance with the Landfill Gas Hazard Assessment Guidance Note. A
source-pathway-target analysis was conducted to assess the risk of landfill gas
hazard associated with the Project. According to the classification of risk
category, the landfill gas hazard risk for the Project was identified as MEDIUM for
both construction
workers working outdoors and site office personnel.
Nevertheless, a number of protection measures will be
implemented to safeguard the safety of the site workers and all personnel
presence of the Subject Site. Precautions should be clearly laid down and
rigidly adhered to with respect to:
–
Trenching
and excavation; and
–
Creation
of confined spaces at, near to or below ground level.
Moreover, the Contractor will be required to submit
their landfill gas monitoring plan and precautionary measures to the Project
Team for their approval before the commencement of work.
With the implementation of these projection measures,
no adverse impact of landfill gas hazard to this Project is anticipated.
Operational
Phase
The operational phase of the Project shall be an idle
buildable land to cater any future developments by the government. The
operational phase of the Project will be under an open area,
thereby adverse environmental impact arising from landfill gas hazard is not
expected. In light of the anticipation for the operation of WENT Landfill
Extension, any such future developments would render the respective project
proponent to have to undertake another set of LFG assessment based on the
respective design provisions in order to assess landfill gas hazards.
A literature review supplemented by comprehensive
ecological survey conducted during April 2012 to September 2012 was undertaken
to establish the ecological profile within the Study Area, which is delineate
by an area within 500m from the Subject Site.
Ecological resources recorded within the Study Area
include woodland, plantation, orchard/village, grassland / shrubland,
watercourse, ash lagoon, seawall, urbanized / disturbed areas and coastal
waters and its associated flora and fauna species. Woodland, natural
section of watercourse, water channel/water-filled portion of the Middle Ash
Lagoon, and West Ash Lagoons had low to moderate ecological values, whereas
other habitats had low ecological values. In accordance with the survey at
2012, 2013 and 2014, species of conservation concern recorded within the Study
Area include three flora and eighteen fauna species (including bats, birds and
dragonflies). Breeding of Little Grebe was recorded at both Middle and West Ash
Lagoon including the Subject Site.
Ecological
impacts of the proposed Project include permanent loss of about 4 hectares of
ash platform, urbanized/disturbed habitat and grassland/shrubland.
The majority of the associated habitat loss are
considered as an artificial habitat with regular disturbance from ash dumping
and pumping of water from CLP Plant. On the other hand, installation of
drainage pipes would encroach about 0.03 hectare of the man made water channel
at the north-west corner of the Subject
Site, while construction of retaining structure for slope stabilization along
the edge of the existing water channel near the north boundary will lead to an
increase of about 0.03 hectare of water channel area. Therefore, there is no
net loss of water channel surface.
During
the course of the survey, the landscape of the site changed frequently as it
was shaped by the continual storage of PFA by CAPCO. On the latest site
surveillance, water bodies were found on the northern and eastern edge of the
Middle Lagoon. The observed behavior of the little grebe suggests that their
breeding ground will be confined to those areas .
Given the absence of a large water body in the Subject Site, the impact of the
decommissioning work to the breeding of Little Grebe is considered minimal.
Nevertheless, mitigation will be in place to protect the remaining water body
on site. This entails the incorporation of the following in the site
development stage: the construction of
an embankment, the erection of 2.4m high fencing and the construction of a
landscaped buffer zone adjacent to the site.
The
construction of retaining wall for slope stabilization area shall be minimized
in scale, whereas construction period will be limited within non-breeding
season of Little Grebe. The “non-breeding season of Little Grebe” is assumed to
be dry season, which is November to March in following year, in accordance with
definition as stated in EIAO Guidance Note.
As the Project would not involve any marine works, no
direct marine or intertidal habitat loss from the Project is anticipated.
With the implementation of the mitigation measures to
keep the water body intact, the residual impacts are considered minimal and
acceptable. The overall impacts to terrestrial and freshwater habitats are
ranked as low.
Environmental monitoring and audit (EM&A)
programme will be implemented during the construction of the Project to ensure
the effectiveness of the recommended mitigation measures and compliance with
relevant statutory requirements. Details of the EM&A works have been
specified in the EM&A Manual. The EM&A Manual contains full details of
proposed baseline and compliance monitoring programme, implementation schedule
of the environmental protection / mitigation measures, EM&A reporting
procedures, and complaint handling procedures.
An EIA report has been prepared to study the
decommissioning works of the west portion and southern edge of the Middle Ash
Lagoon, Tsang Tsui followed by site formation works and construction of
drainage and road works. The EIA report has been prepared to fulfill requirements as specified in the EIA Study Brief
(No. ESB-243/2012) and the Technical Memorandum on
Environmental Impact Assessment. All the latest design information has
been incorporated into the EIA process. Where necessary and practicable,
the EIA has specified mitigation and control measures to reduce the
environmental impacts to acceptable levels.
The EIA Report has predicted that the Project would be
environmentally acceptable and with low residual impacts through the
implementation of the proposed mitigation measures. The schedule of
implementation of the recommended mitigation measures has been provided in the
EIA report. Monitoring requirements have
also been specified in a separate EM&A manual to ensure proper implementation
of the recommended mitigation measures.