Tables
Table 1.1:__ Different Phases of the Major Works for the
Decommissioning Project
Appendices
Not used
Figures
Not used
Mott
MacDonald Hong Kong Limited (MM) has been commissioned by the Civil and
Engineering and Development Department (CEDD) to undertake the detailed design
for the Alternative Ground Decontamination Works at the proposed Kennedy Town
Comprehensive Development Area (CDA) site (hereafter referred to as “the
Project”)[1].
The CDA site covers the ex-Kennedy Town Incineration Plant (KTIP), ex-Kennedy
Town Abattoir (KTA) and temporary facilities including the Cadogan Street
Temporary Garden, a temporary public car park, a bus depot and Refuse
Collection Point (RCP).
The Project forms part of the “Demolition of Buildings and Structures in the Proposed Kennedy Town Comprehensive Development Area Site” (the Decommissioning Project) in which the demolition of a municipal incinerator constitutes a designated project under the Item 3 of Part II, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO). The major works of the Decommissioning Project are divided into the following phases, as presented in Table 1.1. This Project is the Phase 2 of the Decommissioning Project.
Table
1.1: Different Phases of the Major Works for
the Decommissioning Project
Phase |
Period |
Management Party |
Description |
Status |
Phase 1 – Part 1 |
From September 2007 to July 2009 |
CEDD |
Demolition and clearance of all existing chimneys, buildings and ancillary structures above the existing concrete ground slab in the Phase 1 Site area where the former KTIP and KTA are located. The Phase 1 Part 1 also includes the removal of asbestos containing materials and dioxin/furan contaminated wastes within the Phase 1 Site. |
Completed |
Phase 1 – Part 2 |
From July 2009 to 2015 |
Mass Transit Railway Corporation Limited (MTRCL); HyD |
Temporary use of the Phase 1 Site for the construction of the West Island Line (WIL) as site office and for the storage of common construction materials, and for Highways Department’s maintenance depot. |
On-going |
Phase 2 |
From 2015 |
CEDD |
Ground decontamination works within the Project site. |
Design in Progress |
An Environmental Impact
Assessment (EIA) study under Agreement No. CE15/99
(hereafter referred to as the “Original EIA Study”) was previously conducted
for the demolition of buildings and structures in the proposed Kennedy Town CDA
site including the ground decontamination works. The EIA Report (hereafter
referred to as the “Approved EIA Report”) was approved by the Director of
Environmental Protection (DEP) on 16 April 2002 under the EIAO (EIA Register
No. AEIAR-058/2002). An Environmental Permit (EP) was
then issued and subsequently varied; the current version was issued by EPD on
15 November 2011 (Permit No. EP-136/2002/D).
As per the EP requirements, a Contamination
Confirmatory Investigation (CCI) Proposal was submitted to Environmental
Protection Department (EPD) in January 2003 to recommend further Site
Investigation (SI) including soil sampling and laboratory analysis. In 2003,
CCI and laboratory analysis were conducted in the Project site to ascertain the
extent of land contamination and volume of contaminated soil based on the CCI
Proposal. The Final SI Report is dated March 2004 and was submitted to EPD on
14 September 2006. The CCI indicated that the amount of soil requiring
remediation would be significantly larger than the quantity as predicted in the
approved EIA Report. As such, the recommended ground decontamination methods
and related mitigation measures in the approved EIA Report are no longer
applicable. Therefore, a new EIA is required for the alternative ground
decontamination works.
At the time of approval of the approved EIA
Report and the CCI Proposal, Hong Kong was using the Dutch List “B” levels of
the Netherlands (hereafter referred to as “Dutch B”) which were referenced
under the Practice Note for Professional Persons ProPECC
PN3/94 “Contaminated Land Assessment and Remediation” (ProPECC
PN3/94) issued by EPD in 1994 to interpret the levels of land contamination. In
2007, EPD promulgated the Risk-Based Remediation Goals (RBRGs) to replace Dutch
B levels as the new land contamination assessment standards for Hong Kong.
After completion of the CCI, demolition of
buildings, structures and chimneys at the KTIP and KTA sites (i.e. Phase 1,
Part 1), these two sites were handed over to Mass Transit Railway Corporation
(MTRCL) in July 2009 and are presently used as works area for the West Island
Line (WIL) construction (i.e. Phase 1 Part 2) and to Highways Department as a
maintenance depot. Ground decontamination works (i.e. Phase 2) are proposed to
commence when the WIL area and the adjoining areas are returned to Government.
In summary, the new EIA is required
because the Project includes a significantly larger
quantity of soil than the previously predicted amount requiring decontamination
in the Original EIA study approved in April 2002; and because the recommended
ground decontamination methods in the approved EIA Report are no longer
applicable.
The scope of the
This EIA Report
provides information on the nature and extent of environmental impacts arising
from the carrying out of the proposed Project and related activities taking
place concurrently and to contribute
to decisions on:
¡ The overall acceptability of adverse environmental
consequences that are likely to arise as a result of the Project, as well as
other interfacing projects in the vicinity of the Project;
¡ The conditions and requirements for the
detailed design and carrying out of the Project to mitigate against adverse
environmental consequences wherever practicable; and,
¡ The acceptability of residual impacts, if
any, after the proposed mitigation measures are implemented.
As per the
requirement in Section 3.4 of the EIA Study Brief (No.
ESB-252/2012) for the Project, the
The objectives of the EIA study as detailed in the EIA Study Brief are
as follows:
¡ to describe the Project and associated works
together with the requirements and environmental benefits for carrying out the
Project;
¡ to identify and describe the elements of the
community and environment likely to be affected by the Project, and/or likely
to cause adverse impacts to the Project, including both the natural and
man-made environment and the associated environmental constraints;
¡ to identify and quantify emission sources
and determine the significance of impacts on sensitive receivers and potential
affected uses;
¡ to identify and quantify any potential
losses or damage to flora, fauna and natural habitats;
¡ to propose the provision of infrastructure
or mitigation measures to minimise pollution, environmental disturbance and
nuisance during the carrying out of the Project;
¡ to investigate the feasibility,
effectiveness and implications of the proposed mitigation measures;
¡ to identify, predict and evaluate the
residual (i.e. after practicable mitigation) environmental impacts and the
cumulative effects expected to arise during the carrying out of the Project in
relation to the sensitive receivers and potential affected uses;
¡ to identify, assess and specify methods,
measures and standards, to be included in the detailed design and the carrying
out of the Project which are necessary to mitigate these residual environmental
impacts and cumulative effects and reduce them to acceptable levels;
¡ to design and specify the environmental
monitoring and audit requirements; and
¡ to identify any additional studies necessary to implement the mitigation measures or monitoring and proposals recommended in the EIA report.
The
¡ potential
air quality impact and the associated
health risks on air sensitive receivers due to the Project and associated
works, including construction dust emissions, odour, gaseous emissions as well
as released contaminated vapour and particulates etc.;
¡ potential noise impact on sensitive
receivers due to the Project and associated works, including impact from the
use of Powered Mechanical Equipment (PME), ground decontamination processes
(such as biopiling and cement solidification etc.) and rock crushing (if
required);
¡ potential water quality impact and the
associated risks of discharge of potentially contaminated wastewater resulting
from the ground decontamination process and surface runoff, if any, due to the
Project and associated works, including site runoff, drainage diversion, sewage
effluent from the workforce and accidental spillage of chemicals/wastes;
¡ potential waste management implications arising
from the Project;
¡ land contamination within the Project site
and the associated health and safety risks to on-site personnel during the
ground decontamination, monitoring and measurements activities;
¡ potential impact on ecological sensitive
areas due to the Project;
¡ potential fisheries impact due to the
Project;
¡ potential landscape impact, including the
impacts on existing trees within the Project site and Cadogan Street Temporary Garden,
impacts on landscape resources, such as, shrubs, grassland, water bodies, etc.
and impacts on landscape features, such as, parks, public open spaces, amenity
areas, etc. due to the Project; and,
¡ potential cumulative environmental impacts of the Project
and associated works, through interaction or in combination with other
existing, committed and planned projects in the vicinity of the Project, and
that the impacts of these
projects may have a bearing on the environmental acceptability
of the Project.
After this introductory section,
the remainder of this
¡ Section 2 presents a description of the Project;
¡ Section 3 presents the approach, methodology and findings of the Air Quality and Health Impact Assessment;
¡ Section 4 presents the approach, methodology and findings of the Noise Impact Assessment;
¡ Section 5 presents the approach, methodology and findings of the Water Quality Impact Assessment;
¡ Section 6 presents the approach, methodology and findings of the Waste Management Implications;
¡ Section 7 presents the approach, methodology and findings of the Land Contamination Assessment;
¡ Section 8 presents the approach, methodology and findings of the Ecological Impact Assessment;
¡ Section 9 presents the approach, methodology and findings of the Fisheries Impact Assessment;
¡ Section 10 presents the approach, methodology and findings of the Landscape Impact Assessment;
¡ Section 11 presents the Environmental Monitoring and Audit Requirements;
¡ Section
12 presents the Summary Information
from the
¡ Section 13 presents the Implementation Schedule.