Chapter Title Page
Tables
Table 4.1:__ Noise Standards for Daytime Construction Activities
Table 4.2:__ Representative Noise Sensitive Receivers Identified
for the Assessment
Table 4.3:__ Unmitigated Construction Airborne Noise Impact of
Reprovisioning Option A
Table 4.4:__ Unmitigated Construction Airborne Noise Impact of
Reprovisioning Option B
Table 4.5:__ Unmitigated Construction Airborne Noise Impact of
Reprovisioning Option C
Table 4.6:__ Quieter PME Recommended for Adoption during the
Carrying out of the Project
Table 4.7:__ Noise Mitigation Measures for Certain PME during the
Carrying out of the Project
Table 4.8:__ Mitigated Construction Airborne Noise Impact of
Reprovisioning Option A
Table 4.9:__ Mitigated Construction Airborne Noise Impact of
Reprovisioning Option B
Table 4.10:_ Mitigated Construction Airborne Noise Impact of
Reprovisioning Option C
Table 4.11:_ Cumulative Construction Airborne Noise Impact of
Reprovisioning Option A
Table 4.12:_ Cumulative Construction Airborne Noise Impact of
Reprovisioning Option B
Table 4.13:_ Cumulative Construction Airborne Noise Impact of
Reprovisioning Option C
Table 4.14:_ Evaluation of Residual Noise Impacts during
Construction Phase
Figures
Figure 4.1 Noise
Study Area and Locations of Representative Noise Sensitive Receivers
Figure 4.2 Photos
of Existing Noise Sensitive Receivers
Figure 4.3 Schematic
Configuration of Movable Noise Barrier for PME
Appendices
Appendix 4.1 Unmitigated Construction Plant Inventory
Appendix 4.2 Unmitigated Construction Noise Impact of Reprovisioning
Option A
Appendix 4.3 Unmitigated Construction Noise Impact of Reprovisioning
Option B
Appendix 4.4 Unmitigated Construction Noise Impact of Reprovisioning
Option C
Appendix 4.5 Mitigated Construction Plant Inventory
Appendix 4.6 Mitigated Construction Noise Impact of Reprovisioning
Option A
Appendix 4.7 Mitigated Construction Noise Impact of Reprovisioning
Option B
Appendix 4.8 Mitigated Construction Noise Impact of Reprovisioning
Option C
This
section presents an assessment of the potential noise impacts associated with
the carrying out of the Project under three different Reprovisioning
Options. As
the Project involves mainly ground decontamination works, after which the
remediated site will then be handed over to LandsD
for redevelopment, the Project has no operation phase.
Recommendations for mitigation measures have been made, where necessary, to reduce the identified noise impacts to an acceptable level.
Control over the generation of construction noise in Hong Kong is governed by the Noise Control Ordinance (NCO) and the Environmental Impact Assessment Ordinance (EIAO) and their subsidiary requirements. Various Technical Memoranda (TMs) have been issued under the NCO and the EIAO to stipulate criteria and control approaches. These TMs prescribe the maximum permitted noise levels for the use of Powered Mechanical Equipment (PME) and certain construction activities and processes, according to the type of equipment or activity, the perceived noise climate of the area, and the working hours of equipment operation and usage. The TMs applicable to the control of noise from construction activities of proposed construction works are:
Ą TM on Environmental Impact Assessment Process (EIAO-TM)
Ą TM on Noise from Construction Work other than Percussive Piling (GW-TM)
Ą TM on Noise from Construction Work in Designated Areas (DA-TM)
Noise impact arising from general construction activities other than percussive piling during the daytime period (07:00 19:00 hours of any day not being a Sunday or general holiday) are assessed against the noise standards tabulated in Table 4.1 below.
Table 4.1: Noise Standards for Daytime Construction Activities
Noise sensitive Uses |
0700 to 1900 hours on any day
not being a Sunday or general holiday, Leq
(30min), dB(A) |
All domestic premises including temporary housing accommodation |
75 |
Hotels and hostels |
|
Educational institutions including kindergarten, nurseries and all others when unaided voice communication is required |
70 65 during examination |
Source: EIAO-TM, Annex 5, Table 1B Noise Standards for Daytime Construction Activities
Note: (i) The above noise standards apply to uses, which rely on opened windows for ventilation
(ii) The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facade
(iii) The above standards shall be met as far as possible. All practicable mitigation measures shall be exhausted and the residual impacts are minimised
Noise impacts arising from general construction
activities (excluding percussive piling) conducted during the restricted hours
(19:00-07:00 hours on any day and anytime on Sunday or general holiday) and
percussive piling during anytime are governed by the NCO.
For undertaking general construction activities
involving the use of PME within restricted hours, a Construction Noise Permit
(CNP) is required from the Authority under the NCO. The noise criteria and the
assessment procedures for issuing a CNP are specified in Technical Memorandum
on Noise from Construction Work Other Than Percussive Piling (GW-TM) under the
NCO.
The use of Specified PME (SPME) and/or the carrying
out of Prescribed Construction Work (PCW) within a Designated Area (DA) under
the NCO during the restricted hours are also prohibited without a CNP. The relevant technical details in Technical
Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO
can be referred.
Designated areas, in which the control of SPME and
PCW will apply, are established through the Noise Control (Construction Work
Designated Areas) Notice made under Section 8A (1) of the NCO. According to the Designated Area defined under
the NCO, all part of the works area of this project will fall within these
areas where construction works would be carried out.
Regardless of any description or assessment made in
the EIA Report, in assessing a filed application for a CNP the Authority will
be guided by the relevant Technical Memoranda. The Authority will consider all
the factors affecting their decision taking into account contextual situations
and conditions. Nothing in the EIA
Report will pre-empt the Authority in making their decisions, and there is no
guarantee that a CNP will be issued. If
a CNP is to be issued, the Authority may include conditions as appropriate and
such conditions are to be followed while the works covered by the CNP are being
carried out. Failing to do so may lead to cancellation of the permit and
prosecution action under the NCO.
According to the construction programme, the
proposed decontamination works will be carried out during non-restricted
hours. In case of any activities during
restricted hours, it is the Contractors responsibility to ensure compliance
with the NCO and the relevant TMs. The Contractor will be required to submit
CNP application to the Noise Control Authority and abide by any conditions
stated in the CNP, should one be issued.
In accordance with Clause 3.4.4.2 of the EIA Study
Brief, the Study Area is defined as within 300m of the site boundary of the
Project for noise impact assessment. The Study Area has been identified and is
shown in Figure 4.1.
The Project will be situated next to Victoria
Road and Cadogan Street, Kennedy Town, adjacent to
Victoria Harbour, with a site area of about 32,000 m2.
NSRs have been identified in accordance with Annex
13 of the EIAO-TM. The NSRs have included existing, planned / committed noise
sensitive developments and relevant uses earmarked on the relevant Outline
Zoning Plans, Development Permission Area Plans, Outline Development Plans,
Layout Plans and other relevant published land use plans, including plans and
drawings published by Lands Department.
For the purpose of noise assessment, the first
layer of residential premises located close to the site boundary have been
selected as assessment points/ identified representative NSRs within the Study
Area for prediction of the noise impact levels.
According to the Outline Zoning Plans (S/H1/19
Kennedy Town & Mount Davis), the Study Area mainly comprises zoning of
Other Specified Uses and Residential. Existing NSRs in the residential zones
located close to the site boundary have been identified and selected as
representative NSRs. Three planned NSRs are identified within the Study Area.
Descriptions of selected representative existing
NSRs are tabulated in Table
4.2. The
locations of representative noise sensitive receivers are shown in the Figure 4.1. Photos of
existing noise sensitive receivers are shown in Figure 4.2.
Table 4.2: Representative Noise Sensitive Receivers Identified for the Assessment
No. |
NSR ID |
Description |
Use |
Existing/ Planned |
No. of Storeys |
|
1 |
KT-N1 |
Cheong Kat Mansion |
Residential |
Existing |
25 |
|
2 |
KT-N2 |
The Merton (Block 2) |
Residential |
Existing |
45 |
|
3 |
KT-N3 |
Centenary Mansion |
Residential |
Existing |
27 |
|
4 |
KT-N4 |
Cayman Rise |
Residential |
Existing |
31 |
|
5 |
KT-N5 |
Bayanihan Kennedy Town Centre |
Philippine Overseas Worker Training School |
Existing |
6 |
|
6 |
KT-N6 |
Kennedy Town Jockey Club Clinic |
Medical Clinics |
Existing |
3 |
|
7 |
KT-N7 |
SKH Lui Ming Choi Memorial Primary School |
Educational |
Existing |
7 |
|
8 |
KT-N8 |
No. 60 Victoria Road |
Residential |
Existing |
29 |
|
9 |
KT-N9 |
No.37A Cadogan Street |
Residential |
Planned |
44 |
|
10 |
KT-N10* |
Development within Kennedy Town CDA site |
Residential (under planning, assumed use subject to review) |
Planned |
-- |
|
11 |
KT-N11* |
Development within Kennedy Town CDA site |
Residential (under planning, assumed use subject to review) |
Planned |
-- |
|
Remarks: (*) NSR is not included in Reprovisioning Options B & C since the development will commence only after completion of Project period of such reprovisioning options.
Assessment approach to the noise impact is in line with the Guidance Note titled Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance (GN-9/2010).
In addition, the assessment of construction noise impact is based on standard acoustic principles, and the guidelines given in GW-TM issued under the NCO where appropriate. Where no sound power level (SWL) can be found in the relevant TM, reference has been made to BS 5228 Part 1:2009[1] or noise emission levels measured for PME used in previous projects in Hong Kong. The general approach is summarised below:
Ą Formulate a typical construction schedule / programme;
Ą Identify a typical project-specific equipment inventory for each work stage together with the number of equipment;
Ą Obtained from GW-TM, the SWL for each PME assumed in the equipment inventory;
Ą Select representative NSRs for the construction noise impact assessment;
Ą Calculate the unmitigated Predicted Noise Level (PNL) and correct it for facade reflection to obtain the Corrected Noise Level (CNL) at the representative NSRs;
Ą If necessary, re-select typical project-specific silenced equipment and calculate the mitigated noise impact;
Ą Compare the mitigated CNL with the noise standards to determine acceptability and the need for further mitigation.
The calculation methodology is estimated with the following standard formula (1):
SPL = SWL DC + FC (1)
where
SPL: Sound Pressure Level in dB(A)
SWL: Sound Power Level in dB(A)
DC: Distance Attenuation in dB(A)
= 20 log D + 8 [where D is the distance between NSR and noise source in m]
FC: Facade Correction in dB(A)
= +3 dB(A)
Excavation and backfilling are involved in the
proposed Project. No tunnelling works would be involved underground. Hence
potential ground-borne noise impact to existing NSRs and planned/committed
noise sensitive developments is not anticipated. In view of this situation,
ground-borne noise impacts arising from the proposed Project works to the
planned NSRs are not anticipated.
With reference to Chapter 2, there are 3 Reprovisioning Options, namely Option A, Option B, and Option C, that are being considered for the Project. The construction noise impact assessment has been conducted under these three Reprovisioning Options.
The potential source of noise impact during the carrying out of the Project would be the use of PME for various activities, including excavation and decontamination processes, removal of spoil and backfilling in the Project site. PME likely to be used include breaker, excavator, lorry, air compressor, and generator etc.
Under normal conditions, activities for the Project would be carried out during non-restricted hours (0700 1900 hours) on normal working dates. In the case of any activities that have to be carried out during restricted hours, it is the Contractors responsibility to ensure compliance with the NCO as well as the relevant TMs. The Contractor will be required to submit an application for the CNP and abide by the conditions set out by the Noise Control Authority. For carrying out of any general activities involving the use of any PME within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in GW-TM under the NCO.
Alternative ground
decontamination works at the proposed Kennedy Town CDA site are expected to
commence in 2015. Based on the latest available information, the following
planned concurrent and interfacing projects have been identified for the
Project, as shown in Figure 2.4.
Ą Residential Development at the Ka Wai Man Road & Ex-Mount Davis Cottage Area
Ą Reprovisioning of Kennedy Town Saltwater Pumping Station
Ą Development within the Kennedy Town CDA site (for Reprovisioning Option A only)
Where construction programmes are known, cumulative assessment has been conducted. However, the Reprovisioning of Kennedy Town Saltwater Pumping Station project is generally in early development and there is currently no information available regarding the construction programme and plant to be used in this project. This project is therefore not assessed in this EIA and would need to be included in studies conducted by the project proponent.
The construction noise impact associated with two potential developments at the Ka Wai Man Road & Ex-Mount Davis Cottage Area and within the Kennedy Town CDA site has been assessed in construction noise impact assessment. Residential Development at the Ka Wai Man Road and Ex-Mount Davis Cottage Area is currently underway and is assumed to have population intake starting from 2021. Potential development within the Kennedy Town CDA site is conservatively assumed to be a concurrent project throughout the Years 2024 to 2028 for Stage 2 of Reprovisioning Option A.
The type and quantity of Powered Mechanical Equipment (PME) likely to be used for this Project and their Sound Power Levels (SWLs) are shown in Appendix 4.1.
The
predicted noise levels of Reprovisioning Option A are
presented in Table 4.3. Details of the construction noise impact at
the representative NSRs are shown in Appendix 4.2.
Table 4.3: Unmitigated Construction Airborne Noise Impact of Reprovisioning Option A
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Mitigation Measure Required? |
KT-N1 |
Residential |
59-85 |
75 |
Yes |
Yes |
KT-N2 |
Residential |
58-85 |
75 |
Yes |
Yes |
KT-N3 |
Residential |
60-84 |
75 |
Yes |
Yes |
KT-N4 |
Residential |
64-82 |
75 |
Yes |
Yes |
KT-N5 |
Philippine Overseas Worker Training
School |
58-80 |
70 |
Yes |
Yes |
KT-N6 |
Medical Clinics |
62-85 |
75* |
Yes |
Yes |
KT-N7 |
Educational |
62-81 |
70/65 |
Yes |
Yes |
KT-N8 |
Residential |
55-77 |
75 |
Yes |
Yes |
KT-N9 |
Residential |
58-82 |
75 |
Yes |
Yes |
KT-N10 |
Residential (under planning, assumed
use subject to review) |
67-85 |
75 |
Yes |
Yes |
KT-N11 |
Residential (under planning, assumed
use subject to review) |
66-85 |
75 |
Yes |
Yes |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
Bold figure denotes exceedance
of relevant noise criteria.
The
predicted noise levels of Reprovisioning Option B are
presented in Table 4.4. Details of the construction noise impact at
the representative NSRs are shown in Appendix 4.3.
Table 4.4: Unmitigated Construction Airborne Noise Impact of Reprovisioning Option B
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Mitigation Measure Required? |
KT-N1 |
Residential |
59-86 |
75 |
Yes |
Yes |
KT-N2 |
Residential |
58-86 |
75 |
Yes |
Yes |
KT-N3 |
Residential |
60-82 |
75 |
Yes |
Yes |
KT-N4 |
Residential |
67-82 |
75 |
Yes |
Yes |
KT-N5 |
Philippine Overseas Worker Training
School |
63-80 |
70 |
Yes |
Yes |
KT-N6 |
Medical Clinics |
72-85 |
75* |
Yes |
Yes |
KT-N7 |
Educational |
68-81 |
70/65 |
Yes |
Yes |
KT-N8 |
Residential |
60-77 |
75 |
Yes |
Yes |
KT-N9 |
Residential |
58-81 |
75 |
Yes |
Yes |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
Bold figure denotes exceedance
of relevant noise criteria.
The
predicted noise levels of Reprovisioning Option C are presented in Table 4.5. Details of the construction noise impact at
the representative NSRs are shown in Appendix 4.4.
Table 4.5: Unmitigated Construction Airborne Noise Impact of Reprovisioning Option C
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Mitigation Measure Required? |
KT-N1 |
Residential |
65-85 |
75 |
Yes |
Yes |
KT-N2 |
Residential |
64-84 |
75 |
Yes |
Yes |
KT-N3 |
Residential |
66-84 |
75 |
Yes |
Yes |
KT-N4 |
Residential |
72-83 |
75 |
Yes |
Yes |
KT-N5 |
Philippine Overseas Worker Training
School |
71-81 |
70 |
Yes |
Yes |
KT-N6 |
Medical Clinics |
76-85 |
75* |
Yes |
Yes |
KT-N7 |
Educational |
72-82 |
70/65 |
Yes |
Yes |
KT-N8 |
Residential |
67-78 |
75 |
Yes |
Yes |
KT-N9 |
Residential |
64-82 |
75 |
Yes |
Yes |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
Bold figure denotes exceedance
of relevant noise criteria.
The prediction results indicate that the noise impact of unmitigated construction activities from this Project would cause exceedance of the relevant daytime construction noise criteria. Mitigation measures are therefore required for these NSRs in order to alleviate the noise impacts generated during the carrying out of the Project.
Mitigation measures for construction activities are detailed below. The following forms of mitigation measures are recommended and should be incorporated into the Contract Specifications:
Ą good site practice to limit noise emissions at source;
Ą selection of quieter plant;
Ą use of movable noise barrier;
Ą use of noise insulating fabric; and
Ą scheduling of construction works outside school examination periods.
While it is recognised that the Contractor may develop a different package of mitigation measures to meet the required noise standards, the following suite of practical and implementable measures demonstrate an approach that would be feasible to reduce noise to acceptable levels.
Good Site Practice
Good site practice and noise management can significantly reduce the impact of site activities on nearby NSRs. The following package of measures should be followed while carrying out of the Project:
Ą only well-maintained plant to be operated on-site and plant should be serviced regularly during the works;
Ą machines and plant that may be in intermittent use to be shut down between work periods or should be throttled down to a minimum;
Ą plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
Ą mobile plant should be sited as far away from NSRs as possible; and,
Ą material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities.
Selection of Quieter Plant
The Contractor may be able to obtain particular models of plant that are quieter than the standards given in the GW-TM. This is one of the most effective measures and is increasingly practicable because of the availability of quiet equipment.
Quiet plant is defined as Quality Powered Mechanical Equipment (QPME) whose actual SWL is less than the value specified in GW-TM for the same piece of equipment. Examples of SWLs for specific silenced PME taken from EPDs QPME Inventory, BS 5228 Part 1:2009[2] and Sound Power Levels of Other Commonly Used PME are presented in Table 4.6. It should be noted that various types of silenced equipment can be found in Hong Kong.
Table 4.6: Quieter PME Recommended for Adoption during the Carrying out of the Project
PME |
Power Rating/ Size, Weight |
Reference |
SWL, dB(A) |
Crane, mobile |
213kW |
EPD-01516 |
101 |
Dump truck |
50 tonne |
BS 5228 Table D9-39 |
103 |
Excavator, wheeled/tracked |
112.5kW |
EPD-01230 |
99 |
Lorry |
20 tonne |
BS 5228 Table D9-19 |
102 |
Roller, vibratory |
23kW |
EPD-00591 |
105 |
Poker, vibratory, handheld (electric) |
-- |
EPD document Sound Power Levels of Other Commonly Used PME |
102 |
Whilst quieter PME are listed, the Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM.
Use of Movable Noise Barriers
Movable noise barriers can be very effective in screening noise from particular items of plant when implementing the Project. Noise barriers located along the active works area close to the noise generating component of a PME could produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided the direct line of sight between the PME and the NSRs is blocked. A schematic configuration of a single movable noise barrier for PME is shown in Figure 4.3.
Use of Noise Insulating Fabric
Noise insulating fabric can also be adopted for certain PME (e.g. pilling machine etc.). The Fabric should be lapped such that there are no openings or gaps on the joints. According to the approved Tsim Sha Tsui Station Northern Subway EIA Report (Register No.: AEIAR-127/2008), a noise reduction of 10 dB(A) can be achieved for the PME lapped with the noise insulating fabric.
The noise screening benefit for each item of plant considered in this assessment is listed in Table 4.7.
Table 4.7: Noise Mitigation Measures for Certain PME during the Carrying out of the Project
PME |
Mitigation Measures Proposed |
Noise Reduction dB(A) |
|
Piling, vibrating hammer |
Noise insulating fabric |
10 |
|
Piling, large diameter bored, grab and chisel |
Noise insulating fabric |
10 |
|
Piling, large diameter bored, oscillator |
Noise insulating fabric |
10 |
|
Piling, large diameter bored, reverse circulation drill |
Noise insulating fabric |
10 |
|
Piling, earth auger, auger |
Noise insulating fabric |
10 |
|
Piling rig |
Noise insulating fabric |
10 |
|
Drill rig, rotary type (diesel) |
Noise insulating fabric |
10 |
|
Air compressor |
Movable noise barrier |
10 |
|
Generator |
Movable noise barrier |
10 |
|
Breaker, mini-robot mounted |
Movable noise barrier |
10 |
|
Saw, circular, wool |
Movable noise barrier |
10 |
|
Welding plant |
Movable noise barrier |
10 |
|
Cutter, circular, steel |
Movable noise barrier |
10 |
|
Water pump |
Movable noise barrier |
10 |
|
Ventilation fan |
Movable noise barrier |
10 |
|
Bar bender and cutter |
Movable noise barrier |
10 |
|
Concrete pump, stationary/ lorry mounted |
Movable noise barrier |
5 |
|
Excavator |
Movable noise barrier |
5 |
|
Mobile crane |
Movable noise barrier |
5 |
|
Roller, vibratory |
Movable noise barrier |
5 |
|
Poker, vibratory, hand-held |
Movable noise barrier |
5 |
|
These noise barriers should be free of gaps and made of materials having a surface mass density in excess of 10 kg/m2. To improve the effectiveness of noise reduction, non-flammable absorptive lining can be adhered on the inner surface of the noise barriers. The barrier can be in the form of vertical or bend top barrier with an effective height to block the line of sight to NSRs.
Scheduling of Construction Works outside School Examination Periods
The daytime construction noise criterion during school examination period is 65 dB(A), which is lower than the normal daytime school criterion of 70 dB(A). During the carrying out of the Project, the contractor should liaise with the educational institution (NSR KT-N7) to obtain the examination schedule and avoid the noisy construction activities during school examination periods. A Construction Noise Mitigation Measures Plan for educational institution (i.e. NSR KT-N7) will be provided to address the potential noise exceedance during examination period.
Mitigated Construction Noise Impacts of Reprovisioning Option A
The effect of the use of quieter plant, movable barriers and noise insulating fabric has been investigated for the practicable construction activities. The predicted results of Reprovisioning Option A are presented in Table 4.8. Mitigated Construction Plant Inventory and details of the mitigated construction noise impact are shown in Appendix 4.5 and Appendix4.6 respectively.
Table 4.8: Mitigated Construction Airborne Noise Impact of Reprovisioning Option A
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
49-73 |
75 |
No |
No |
KT-N2 |
Residential |
48-73 |
75 |
No |
No |
KT-N3 |
Residential |
50-73 |
75 |
No |
No |
KT-N4 |
Residential |
54-70 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
48-68 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
52-73 |
75* |
No |
No |
KT-N7 |
Educational |
52-69 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
45-65 |
75 |
No |
No |
KT-N9 |
Residential |
48-70 |
75 |
No |
No |
KT-N10 |
Residential (under planning, assumed
use subject to review) |
57-73 |
75 |
No |
No |
KT-N11 |
Residential (under planning, assumed
use subject to review) |
56-73 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance
of relevant noise criteria.
With the incorporation of quieter plants, the use of movable barriers and noise insulating fabric, the results indicated that the mitigated noise impact associated with the construction of the Project would comply with the daytime construction noise criterion at most of the representative NSRs. Residual construction noise impact was predicted at one educational NSR during examination periods, namely KT-N7. During the examination periods, the predicted exceedance for this NSR is 1-4 dB(A).
Mitigated Construction Noise Impacts of Reprovisioning Option B
The predicted results of Reprovisioning Option B are presented in Table 4.9. Mitigated Construction Plant Inventory and details of the mitigated construction noise impact are shown in Appendix 4.5 and Appendix 4.7 respectively.
Table 4.9: Mitigated Construction Airborne Noise Impact of Reprovisioning Option B
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
49-73 |
75 |
No |
No |
KT-N2 |
Residential |
48-73 |
75 |
No |
No |
KT-N3 |
Residential |
50-70 |
75 |
No |
No |
KT-N4 |
Residential |
57-70 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
53-68 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
62-72 |
75* |
No |
No |
KT-N7 |
Educational |
58-69 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
50-65 |
75 |
No |
No |
KT-N9 |
Residential |
48-69 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance
of relevant noise criteria.
With the incorporation of quieter plants, the use of movable barriers and noise insulating fabric, the results indicated that the mitigated noise impact associated with the construction of the Project would comply with the daytime construction noise criterion at most of the representative NSRs. Residual construction noise impact was predicted at one educational NSR during examination periods, namely KT-N7. During the examination periods, the predicted exceedance for this NSR is 1-4 dB(A).
Mitigated Construction Noise Impacts for Reprovisioning Option C
The predicted results of Reprovisioning Option C are presented in Table 4.10. Mitigated Construction Plant Inventory and details of the mitigated construction noise impact are shown in Appendix 4.5 and Appendix 4.8 respectively.
Table 4.10: Mitigated Construction Airborne Noise Impact of Reprovisioning Option C
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
53-73 |
75 |
No |
No |
KT-N2 |
Residential |
53-72 |
75 |
No |
No |
KT-N3 |
Residential |
54-72 |
75 |
No |
No |
KT-N4 |
Residential |
60-71 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
61-69 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
65-73 |
75* |
No |
No |
KT-N7 |
Educational |
61-70 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
57-68 |
75 |
No |
No |
KT-N9 |
Residential |
53-70 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance
of relevant noise criteria.
With the incorporation of quieter plants, the use of movable barriers and noise insulating fabric, the results indicated that the mitigated noise impact associated with the construction of the Project would comply with the daytime construction noise criterion at most of the representative NSRs. Residual construction noise impact was predicted at one educational NSR during examination periods, namely KT-N7. During the examination periods, the predicted exceedance for this NSR is 1-5 dB(A).
The overall cumulative construction noise levels from Reprovisioning Option A and the concurrent projects are presented in Table 4.11. The predicted noise levels have included the cumulative impacts from other potentially concurrent projects. Details of the cumulative mitigated construction noise impact of Reprovisioning Option A are shown in Appendix 4.6.
Table 4.11: Cumulative Construction Airborne Noise Impact of Reprovisioning Option A
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
54-73 |
75 |
No |
No |
KT-N2 |
Residential |
53-73 |
75 |
No |
No |
KT-N3 |
Residential |
56-73 |
75 |
No |
No |
KT-N4 |
Residential |
62-71 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
65-69 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
64-75 |
75* |
No |
No |
KT-N7 |
Educational |
63-69 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
60-70 |
75 |
No |
No |
KT-N9 |
Residential |
54-71 |
75 |
No |
No |
KT-N10 |
Residential (under planning, assumed
use subject to review) |
71-75 |
75 |
No |
No |
KT-N11 |
Residential (under planning, assumed
use subject to review) |
70-75 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA report (Register No.: AEIAR-130/2009) NSR N12 Sir
Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance of
relevant noise criteria.
Based on the results shown in the table above, residual cumulative construction noise impact was predicted at one educational NSR, namely KT-N7 during examination period. The predicted exceedance for this NSR is 1-4 dB(A). All practicable mitigation measures including movable barrier, insulating fabric and quiet plants have been proposed and exhausted to minimise the noise impact. In addition, it is noted that noise insulation works have been installed at this school and therefore significant noise impact would not be anticipated.
The overall cumulative construction noise levels from Reprovisioning Option B and the concurrent projects are presented in Table 4.12. Details of the cumulative mitigated construction noise impact of Reprovisioning Option B are shown in Appendix 4.7.
Table 4.12: Cumulative Construction Airborne Noise Impact of Reprovisioning Option B
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
54-73 |
75 |
No |
No |
KT-N2 |
Residential |
53-73 |
75 |
No |
No |
KT-N3 |
Residential |
56-70 |
75 |
No |
No |
KT-N4 |
Residential |
62-70 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
65-69 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
64-72 |
75* |
No |
No |
KT-N7 |
Educational |
63-69 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
67-70 |
75 |
No |
No |
KT-N9 |
Residential |
54-69 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009)
NSR N12 Sir Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance of
relevant noise criteria.
Based on the results shown in the table above, residual cumulative construction noise impact was predicted at one educational NSR, namely KT-N7 during examination period. The predicted exceedance for this NSR is 1-4 dB(A). All practicable mitigation measures including movable barrier, insulating fabric and quiet plants have been proposed and exhausted to minimise the noise impact. In addition, it is noted that noise insulation works have been installed at this school and therefore significant noise impact would not be anticipated.
The overall cumulative construction noise levels from Reprovisioning Option C and the concurrent projects are presented in Table 4.13. Details of the cumulative mitigated construction noise impact of Reprovisioning Option C are shown in Appendix 4.8.
Table 4.13: Cumulative Construction Airborne Noise Impact of Reprovisioning Option C
NSR ID |
Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of Noise Criteria? |
Residual Noise Impact? |
KT-N1 |
Residential |
57-73 |
75 |
No |
No |
KT-N2 |
Residential |
55-72 |
75 |
No |
No |
KT-N3 |
Residential |
58-72 |
75 |
No |
No |
KT-N4 |
Residential |
64-71 |
75 |
No |
No |
KT-N5 |
Philippine Overseas Worker Training School |
66-70 |
70 |
No |
No |
KT-N6 |
Medical Clinics |
66-74 |
75* |
No |
No |
KT-N7 |
Educational |
65-70 |
70 / 65 |
Yes |
Yes^ |
KT-N8 |
Residential |
67-70 |
75 |
No |
No |
KT-N9 |
Residential |
56-70 |
75 |
No |
No |
Remarks: (*) Construction
noise criteria 75 dB(A) for medical clinics are
referred to approved Kai Tak Development EIA
report (Register No.: AEIAR-130/2009) NSR
N12 Sir Robert Black Health Centre.
(^) Residual impact is only
expected during examination period (typical examination period in January,
March, June and October) of educational institution.
Bold figure denotes exceedance of
relevant noise criteria.
Based on the results shown in the table above, residual cumulative construction noise impact was predicted at one educational NSR, namely KT-N7 during examination period. The predicted exceedance for this NSR is 1-5 dB(A). All practicable mitigation measures including movable barrier, insulating fabric and quiet plants have been proposed and exhausted to minimise the noise impact. In addition, it is noted that noise insulation works have been installed at the school. Therefore, significant noise impact would not be anticipated.
Residual noise impact was predicted at one
educational NSR, namely KT-N7
during examination periods. According to school calendar in website of SKH Lui Ming Choi Memorial Primary School[3], January, March, June and October are
examination periods. The examination period is only last for 1
week in each month. The predicted exceedance for NSR
KT-N7 during examination periods is 1-4 dB(A) for a
duration of 44 weeks within the 13 years construction period. All practicable
mitigation measures including movable barrier, insulating fabric and quiet
plants have been proposed and exhausted to minimise the noise impact. In
addition, it is noted that noise insulation works have been installed at this
school and therefore significant noise impact would not be anticipated.
Residual
noise impact was predicted at one educational NSR, namely KT-N7 during examination periods. The predicted exceedance for NSR KT-N7 during examination periods is 1-4 dB(A) for a duration of 19 weeks within the 7 years
construction period. All practicable mitigation measures including movable
barrier, insulating fabric and quiet plants have been proposed and exhausted to
minimise the noise impact. In addition, it is noted that noise insulation works
have been installed at this school and therefore significant noise impact would
not be anticipated.
Residual
noise impact was predicted at one educational NSR, namely KT-N7 during
examination periods. The predicted exceedance for NSR
KT-N7 during examination period is 1-5 dB(A) for a
duration of 13 weeks within the 4.5 years construction period. All practicable mitigation
measures including movable barrier, insulating fabric and quiet plants have
been proposed and exhausted to minimise the noise impact. In addition, it is
noted that noise insulation works have been installed at the school.
Therefore, significant
noise impact would not be anticipated.
The
daytime construction noise criterion is 65 dB(A)
during school examination periods, which is lower than the normal daytime
school criterion of 70 dB(A). In this regard, scheduling of works outside
school examination period to less intrusive periods would help reduce the
overall noise impacts at the NSR. The examination period of the NSR should only
last for 1 week. By scheduling the works to avoid the examination period, the
adverse residual impact should be minimised. The Contractor shall liaise with
the school representative(s) to obtain the examination schedule and avoid noisy
activities during school examination period.
The residual impacts are evaluated in
accordance with Section 4.4.3 of the TM-
Table 4.14: Evaluation of Residual Noise Impacts during Construction Phase
Criteria |
Assessment |
Effects on public health and health of biota or risk of life |
The extent of noise nuisance would be unlikely to induce public health concern |
Magnitude of the adverse environmental impacts |
The predicted exceedance of construction noise for NSR KT-N7 is 1-5 dB(A) during examination period. All practicable measures have been proposed and exhausted to minimise the noise impact. In addition, it is noted that noise insulation works have been installed at this school. |
Geographic extent of the adverse environmental impact |
The geographic extent of the
adverse impact from noise is anticipated to be limited to NSR KT-N7 during
examination period. |
Duration and frequency of the adverse environmental impacts |
The predicted exceedance
durations of construction noise for NSR KT-N7 are 44 / 19 / 13 weeks for Reprovisioning Options A / B / C, respectively during
examination period. All practicable
measures have been proposed and exhausted to minimise the noise impact. |
Likely size of the community or the environmental that may be
affected by the adverse impacts |
NSR KT-N7 would be temporarily
affected by residual construction noise during examination period. |
Degree to which the adverse environmental impacts are reversible or
irreversible |
Not Applicable in noise section. |
Ecological context |
Not Applicable in noise section |
Degree of disruption to sites of cultural heritage |
Not Applicable in noise section |
International and regional importance |
The impacts are localized and not
of international and regional importance |
Likelihood and degree of uncertainty of adverse environmental impact |
The impacts predicted are based
upon worst case assumptions and as such, would not occur to the extent predicted
on all occasions. |
Based on the above, all practicable measures
have been proposed and exhausted to minimise the noise impact..
The noise impact assessment has been made based on the best available information, taking into account other expected concurrent projects. Having exhausted practicable mitigation measures in the form of quiet plant, movable noise barrier and insulting fabric, the construction noise levels at most of the representative NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM. Residual construction noise impact was predicted at one representative NSR of educational use. However, this NSR has already been implemented with noise insulation works and therefore significant noise impact is not anticipated during the carrying out of the Project. Notwithstanding this, it is recommended that particularly noisy activities should be scheduled to avoid examination periods of the educational NSR as far as practicable.
[1] British Standard BS 5228-1: 2009 Code of Practice for Noise and Vibration Control on Construction and Open Sites Part 1: Noise
[2] British Standard BS 5228-1: 2009 Code of Practice for Noise and Vibration Control on Construction and Open Sites Part 1: Noise
[3] http://www.skhlmcmps.edu.hk/main.htm