Content |
Chapter Title Page
Figure 2.1: Location of the
Project Site and Study Area
The "Alternative Ground
Decontamination Works at the Proposed Kennedy Town Comprehensive Development Area
(CDA) site " (hereinafter known as "the Project") is proposed by
the Civil and Engineering and Development Department (CEDD). The CDA site
covers the ex-Kennedy Town Incineration Plant (KTIP), ex-Kennedy Town Abattoir
(KTA) and temporary facilities including the Cadogan
Street Temporary Garden, a temporary public car park, a bus depot and Refuse
Collection Point (RCP).
The Project forms part
of the “Demolition of Buildings and Structures in the Proposed Kennedy Town
Comprehensive Development Area Site” (the Decommissioning Project) in which the demolition of a
municipal incinerator constitutes a designated project under the Item 3 of Part
II, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO). The major works of
the Decommissioning Project are divided into the following phases, as presented
in Table 1.1.
This Project is the Phase 2 of the Decommissioning Project.
Table 1.1: Different Phases of the Decommissioning Project
Phase |
Period |
Management Party |
Description |
Status |
Phase 1 – Part 1 |
From September 2007 to July 2009 |
CEDD |
Demolition and clearance of all existing chimneys, buildings and ancillary structures above the existing concrete ground slab in the Phase 1 Site area where the former KTIP and KTA are located. The Phase 1 Part 1 also includes the removal of asbestos containing materials and dioxin/furan contaminated wastes within the Phase 1 Site. |
Completed |
Phase 1 – Part 2 |
From July 2009 to 2015 |
Mass Transit Railway Corporation Limited (MTRCL); HyD |
Temporary use of the Phase 1 Site for the construction of the West Island Line (WIL) as site office and for the storage of common construction materials, and for Highways Department’s maintenance depot. |
On-going |
Phase 2 |
From 2015 |
CEDD |
Ground decontamination works within the Project site. |
Design in Progress |
A new Environmental
Impact Assessment (EIA) is required because the Project includes a
significantly larger quantity of soil than the previously predicted amount
requiring decontamination in the Original EIA Study (EIA Register No.
AEIAR-058/2002) approved in April 2002; and because the recommended ground
decontamination methods in the approved EIA Report are no longer applicable
This Executive
Summary presents the key findings of the EIA for the Project as required under
the EIAO.
The Project is necessary to
prepare the Kennedy Town CDA site for the proposed future land uses.
The environmental benefits of the Project are expected to be the mitigation, avoidance or otherwise reduction in the risk of pollution to air, soil, and water, and associated long-term risks to human health derived from the presence of in-situ contaminated ground at the Kennedy Town CDA site. Therefore, the Project could prepare a risk-free site for future development of Kennedy Town, for example, development of a waterfront promenade etc.
The Project site is situated next to Victoria Road and Cadogan Street
in Kennedy Town and adjacent to Victoria Harbour. The Project site boundary and EIA Study Area are shown in Figure 2.1.
The Project site has a total area of about 32,000 m2. The total estimated volume of soil requiring decontamination within the site is projected to be around 112,666 m3. Table 2.1 below shows the estimated volume of contaminated soil according to the type of contamination (Heavy Metals, Hydrocarbons, or a mixture of both).
Table 2.1: Estimated Volumes of Contaminated Soil Requiring Excavation and Decontamination, by Type
Soil Type |
Description |
Vol. (m3) |
Type A |
Soil contaminated with Heavy Metals (HM) |
57,254 |
Type B |
Soil contaminated with Hydrocarbons (HC) |
17,233 |
Type C |
Soil contaminated with both HM and HC |
38,179 |
|
Total contaminated soil volume |
112,666 |
|
Soil not requiring decontamination (including concrete slab), but needs to be excavated |
73,746 |
|
Total excavated soil volume (including concrete slab) |
186,412 |
A comparison of the ground decontamination methods is shown in Table 2.2 and the following paragraphs below.
Table 2.2: Comparison of Ground Dectonamination Methods
Cost |
Duration |
Environmental Impact |
Suitability HC |
Suitability HM |
Suitability HM & HC |
|
Biopile |
Med |
Med |
Low |
Yes |
No |
No |
Soil Vapour Extraction (SVE) |
Med |
High |
Low |
Yes |
No |
No |
Solidification/ Stabilisation (Cement Solidification) |
Med |
Med |
Low |
No |
Yes |
No |
Thermal desorption |
Med |
Med |
Med |
Yes |
No |
No |
Bioventing |
Med |
High |
Med |
Yes |
No |
No |
Chemical Methods |
High |
Low |
High |
Yes* |
Yes* |
Yes* |
Incineration |
Low |
Low |
High |
Yes |
No |
No |
In Ground Containment |
Low |
Low |
Low |
No |
Not recommended |
Not recommended |
Soil Washing |
High |
Med |
Med |
Yes |
Yes |
Yes |
Windrows |
Low |
High |
High |
Yes |
No |
No |
Excavation / Landfill |
Low |
Low |
High |
Not recommended |
Not recommended |
Not recommended |
* Dependant on COCs present and
specific method(s) adopted.
Excavation and landfill is not consistent with current Hong Kong legislation
and guidance and has been excluded. In-ground containment/ capping have also
been excluded, as this method would not lead to decontamination of the site,
and would prevent the site being approved for development. The applicability and suitability of other
decontamination methods are elaborated as follows:
Heavy Metal Contaminated Soils
Cement Solidification, Soil Washing and Chemical methods are applicable for the decontamination of HM contaminated soils.
Soil washing is not preferred, as this method would require large volumes of water in order to treat the high volume of contaminated soils present at the site, and the potential occurrence of associated water resource related environmental impacts.
Chemical methods are also
not preferred, as these approaches are not well demonstrated in Hong Kong and
would be likely to require highly specialised contractors to carry out the
works. As such, the cost of using this
approach would be likely to be high, the efficiency of decontamination is
uncertain, and the availability of suitable contractors may also be a barrier
to implementation.
Among the methods considered, cement
solidification is recommended to be the most appropriate alternative based on its technical
suitability, and its performance against cost, duration and environmental
impact criteria. This method is also considered to be an effective
decontamination method that is well established in Hong Kong.
Hydrocarbon Contaminated Soils
Windrows, Biopiling, SVE, Soil Washing, Thermal Desorption, Chemical Method, Incineration and Bioventing have been considered for the decontamination of soils contaminated with HC.
Windrows are not considered to be an appropriate method for the current project, as this method would not effectively control emissions of dust and vapours to air, and contaminated runoff/leachate. Infiltration of rain water/moisture and low/uneven aeration would also be likely to reduce the effectiveness of the process.
Bioventing is a similar process to biopiling, with the material left in-situ. However, this is not preferred as the method is only effective for soils above the water table, is more technically demanding to implement on a large scale, and the effectiveness is difficult to monitor, as the material remains in the ground. Similarly, biopiling is preferred over SVE, as it is a more established method of decontamination in Hong Kong, and the effectiveness of this approach is more easily monitored.
Soil washing is not
preferred for the current project, as this method would require large volumes
of water in order to treat the high volume of contaminated soils present at the
site, and the potential occurrence of associated water resource related
environmental impacts.
Incineration is not preferred for this project, as this method would
produce ash residues and require gas treatment system for the volatile heavy
metals. Volatile and toxic compounds would be produced if metals react with
other elements in the feed stream and results in to high impact to the
environment.
Chemical methods are not preferred, as these approaches are not well demonstrated in Hong Kong and would be likely to require highly specialised contractors to carry out the works. As such, the cost of using this approach would be likely to be high, the efficiency of decontamination is uncertain, and the availability of suitable contractors may also be a barrier to implementation.
Thermal Desorption is also
not preferred, as biopiling can be more effective at treating
contaminants, particularly considering the presence of clays and silts at the
site, and also the need to remove coarse-grained materials / rocks.
Among the methods considered, biopiling is recommended to be the most appropriate alternative based on its technical
suitability, and its performance against cost, duration and environmental
impact criteria. This method is also considered to be an effective
decontamination method that is well established in Hong Kong.
Heavy Metals and Hydrocarbon Contaminated Soils
With the same reasons as stated above, method of Biopiling followed by Cement Solidification is recommended for the decontamination of soils contaminated with both HM and HC.
For the three contaminated soil categories within the Project site the preferred decontamination methods are summarised in Table 2.3.
Table 2.3: Recommended Ground
Decontamination Methods for Contaminated Soil (Preferred Scenario)
Soil Type |
Definition of Soil Type |
Recommended Decontamination Method |
Description |
A |
Heavy metals contaminated soil |
Cement solidification |
Ex-situ immobilisation technique which treats contaminated soil by mixing soil with binding agents (i.e. cement) so that the contaminants become physically bound within a stable mass |
B |
Hydrocarbons contaminated soil |
Biopiling |
Ex-situ bioremediation method where bacteria
is grown in the piled contaminated soil and reduces the concentrations of petroleum constituents |
C |
Heavy metals and hydrocarbons contaminated soil |
Biopiling followed by cement solidification |
See descriptions for Types A and B above respectively. |
The preferred scenario
described in the table above were determined to be the most
technologically suitable and cost effective methods of decontamination, and are
considered to have relatively low environmental impacts.
The Project consists of the following key Project
components:
¡ Excavation – This includes earth
lateral support, excavation, and temporary stockpile of excavated soils.
¡ On-site Decontamination – This
includes decontamination of contaminated soil by biopiling
and/or cement solidification
¡ Final site formation – This includes deposition, compaction, surface drainage works and boundary fencing.
As the Project involves mainly ground decontamination, after which the decontaminated site will then be handed over to Lands Department for redevelopment, the Project has no operational phase.
Three Reprovisioning
Options for the existing temporary community facilities (Public Car Park, Refuse
Collection Point (RCP) and Garden) within the Project
site have been
identified as follows.
Reprovisioning Option A
– 13-year Project
duration, to take place in two stages: Stage 1 involving decontamination of approximately
80% area of the site (the whole site except Cadogan Street
Temporary Garden), with on-site reprovisioning
(by others) of the existing public car park and RCP; Stage 2 involving decontamination of the remaining
area of the site (Cadogan Street Temporary Garden) after construction of the proposed future
waterfront promenade at a decontaminated area of the site (by others).
Reprovisioning Option B
– 7-year Project
duration, involving removal of the existing public car park, temporary garden, and
RCP, and decontamination of the whole site in a single stage. Only public car park and RCP would be reprovisioned on-site (by others) during the ground decontamination works.
Reprovisioning Option C
– 4.5-year Project
duration, involving removal of the existing public car park, temporary garden, and RCP,
and decontamination of the whole site in a single stage. There would be no reprovisioning of temporary community facilities under this
Option.
The environmental impacts of
each of these Reprovisioning Options have been
assessed for the Project.
The following potential concurrent and interfacing projects under planning have been identified and included in the assessment for the Project:
¡ Residential Development at the
Ka Wai Man Road and Ex-Mount Davis Cottage Area
¡ Reprovisioning of Kennedy Town Saltwater Pumping Station
¡ Development within the Kennedy Town CDA site (for Reprovisioning Option A only).
The effects to air quality from Project
activities were assessed under the three Reprovisioning
Options. Total Suspended Particulate (TSP), Respirable
Suspended Particulates (RSP), Fine Suspended Particles (FSP) and Heavy Metals
(HM) and Hydrocarbon (HC) concentrations were modelled using the Fugitive Dust Model (FDM) and ISCST3 models. For fugitive dust impact assessment, the hypothetical Tier 1
screening scenario (for hourly TSP, daily RSP/FSP and annual RSP/FSP) with the
assumption of 100% active area at all times and the Tier 2 modelling scenario
(for annual RSP) which also had conservative assumptions, e.g. active areas are
located closest to ASR assessed for annual RSP averages, are very conservative
approaches, the results of which can represent any of three Reprovisioning
Options for different sequencing and phasing of the works. With implementation of the recommended
mitigation measures, i.e. dust suppression by regular
water spraying as well as the
relevant control requirement as stipulated in Air Pollution Control (Construction Dust) Regulation, it has been
assessed that even under the very conservative
modelling approach there would not
be non-compliance at the ASRs with any Air Quality Objectives for RSP/ FSP or
the TSP criterion for any of three Reprovisioning
Options.
In addition, the cumulative maximum
concentrations of all identified Toxic Air Pollutants (TAPs) (hydrocarbon and heavy metals) have been assessed for different modelling scenarios that represent
different excavation rates under the three Reprovisioning
options. The predicted cumulative maximum
concentrations for all non-criteria pollutants under each of the three Reprovisioning Options are lower than their corresponding reference values and
therefore the associated non-carcinogenic health risks are considered to acceptable.
The total incremental lifetime cancer risks associated with the KTCDA ground
decontamination works have been estimated as 3.14 x 10-7 to 3.99 x
10-7 for the three Reprovisioning options.
In other words, there would be less than four in ten million cancer risks
associated with the heavy metal and hydrocarbon emissions from the Project,
which is well below the risk guideline value of one in million. Hence, the
incremental cancer risks due to the Project are considered to be negligible.,
The noise impact from
Project activities, taking into account other potential concurrent
projects, were assessed under the
three Reprovisioning Options.
Having exhausted practicable mitigation measures in the form of quiet plant,
movable noise barrier and insulting fabric, the construction noise levels at
most of the representative Noise
Sensitive Receivers (NSR) are predicted to comply with the noise
standards stipulated in the EIAO-TM.
Residual construction noise impact was predicted at one representative NSR of educational use. However, this NSR has already been implemented with noise insulation works and therefore significant noise impact is not anticipated during the carrying out of the Project. Notwithstanding this, it is recommended that particularly noisy activities should be scheduled to avoid examination periods of the educational NSR as far as practicable.
Potential water quality impact would be generated from site run-off, sewage
from workforce, and generation of wastewater from various Project
activities. With the implementation of
the recommended mitigation measures, no adverse water quality impact from the
Project works is anticipated.
Wastes
generated by the Project are likely to include construction and demolition (C&D) material from site clearance within the
Project boundary, chemical waste from the maintenance of plant and equipment,
as well as general refuse from the workforce. Provided that these identified
waste arisings are handled, transported and disposed
of using approved methods, and that the recommended good site practices are
strictly followed, significant adverse environmental impacts would not be
expected during the Project works.
The land contamination assessment has been carried
out which included a review of historical/ current land uses, desktop review and site inspection. Other relevant
information was also collected from related Government Departments during this assessment.
Based on the findings of the site appraisal on the
existing and historical land uses in the EIA Study
Area, the presence of potential land contamination and groundwater impacts
associated with the proposed Project works has been identified and assessed.
Areas within the Study Area with contaminated soil exceeding certain Risk-Based Remediation
Goals (RBRGs) have been identified. Additional site Investigation (SI) has been conducted, and the
laboratory results are provided. The estimated volumes of soil to be excavated
and decontaminated are calculated based on an evaluation of the results of the
original EIA study SI, previous SI and additional SI. Treatment of contaminated
soil by cement solidification and/ or biopiling has been recommended, depending on the types of
contaminants found in the soil in each designated grid.
Sensitive receivers, health and
safety risks and migration pathways associated with the proposed
decontamination works have been identified, and mitigation measures for
handling of contaminated materials and regular site audits are recommended to
minimise the potential adverse impacts on sensitive receivers’ health and safety.
The habitat of the whole Project site and the nearby area is a developed area
which is heavily disturbed. Patches of trees are found within the Cadogan
Street Temporary Garden while some individual trees are scattered over the
remaining areas of the Project site. Although four individuals of the
protected plant species Aquilaria sinensis were
recorded within the Project site, they were not
naturally occurring but instead being planted on a contaminated site. No
adverse ecological impact is therefore anticipated for the felling of this
small number of planted Aquilaria sinensis and other planting in the developed area.
Owing to the low ecological value of developed area
within the Project site and the commonness of the recorded fauna which are
adaptive to similar habitats in the vicinity, no potential adverse ecological
impact is identified resulting from the Project under any of the three Reprovisioning Options. Nevertheless, compensatory tree planting will
be provided; recommendation
concerning the inspection of the possibility of active bird nest and bat roost
present within the Project site prior to site clearance works has been made as
ecological precautionary measure.
It is
identified that no fish pond is present within the Project site or in the
vicinity, and no marine fish culture zone is present within the Victoria Harbour
Phase Three Water Control Zone. Only capture fisheries activities are recorded
at the offshore water of Kennedy Town. Port Survey results
showed that the offshore water of Kennedy Town had low fisheries
production.
The Project will not directly affect
any fishing or aquaculture activities, fisheries resources or habitats, or
aquaculture sites. No
potential adverse fisheries impact is identified resulting from the Project as
no marine works or potential adverse deterioration of marine water quality is
predicted under the three Reprovisioning
Options.
With the implementation of
proposed mitigation measures, the anticipated landscape impacts are generally
slight negative under Reprovisioning
Option A, and
moderate negative under Reprovisioning
Options B and C
during the carrying out of the Project due to the unavoidable removal of the
existing Cadogan Street Temporary Garden (Landscape Resource 1) and removal of roadside vegetation (Landscape Resource 2) for the proposed decontamination works within the Project
site. However, the predicted impact will be
temporary. Compensatory tree planting
with a minimum ratio of 1:1 in terms of quantity in the proposed future
waterfront promenade will be provided.
The Project site after
decontamination will be handed over to Lands Department for future development
with potential overall landscape improvement.
The overall residual landscape impact in year 10 following completion of
the Project is therefore considered to be insubstantial under Reprovisioning Option A when the compensatory tree planting in the
proposed future waterfront promenade will have already reached a size that
could largely compensate for the loss of the felled trees, and slight negative
under Reprovisioning Options B and C when compensatory tree planting in
the proposed future
waterfront promenade will have become mature.
Overall, in terms of Annex 10, Clause 1.1 (c) of the EIAO – TM, the
landscape impacts are acceptable with mitigation measures.
A summary of key environmental outcomes for Reprovisioning Options A, B and C is presented in Table 3.1.
Table 3.1: Summary of Key Environmental Outcomes for Reprovisioning Options A, B and C
Issue |
Environmental Impact for Reprovisioning Option A |
Environmental Impact for Reprovisioning Option B |
Environmental Impact for Reprovisioning Option C |
Air Quality and Health Impact |
Hydrocarbon emissions show the worst case pollutant to be benzo(a)pyrene which is predicted to be up to 82% of the relevant criteria for the conservative worst case at external Air Sensitive Receivers (ASRs) in Stage 1. Benzo(a)pyrene which is predicted to be up to 77% of the relevant criteria for the conservative worst case for internal planned ASRs in Stage 2. It has been assessed that there would be no exceedance of any of the relevant criteria for dust, heavy metals or hydrocarbons. |
Hydrocarbon emissions show the worst case pollutant to be benzo(a)pyrene which is predicted to be up to 82% of the relevant criteria for the conservative worst case at external Air Sensitive Receivers (ASRs). It has been assessed that there would be no exceedance of any of the relevant criteria for dust, heavy metals or hydrocarbons. |
Hydrocarbon emissions show the worst case pollutant to be benzo(a)pyrene which is predicted to be up to 82% of the relevant criteria for the conservative worst case at external Air Sensitive Receivers (ASRs). It has been assessed that there would be no exceedance of any of the relevant criteria for dust, heavy metals or hydrocarbons. |
|
With
implementation of the recommended mitigation measures as well as the relevant
control requirement as stipulated in Air Pollution Control (Construction
Dust) Regulation, it has been assessed that there would be no exceedance of any of the relevant criteria for dust,
heavy metals or hydrocarbons.
The human health risks at the identified sensitive receivers were also
assessed to be acceptable under the three Reprovisioning
Options. |
||
Noise Impact |
Residual noise impact was predicted at one educational Noise Sensitive Receiver (NSR KT-N7), namely “SKH Lui Ming Choi Memorial Primary School”, during examination periods. The predicted exceedance for NSR KT-N7 during examination periods is 1-4 dB(A) for a duration of 44 weeks within the 13 years construction period. |
Residual noise impact was predicted at one educational Noise Sensitive Receiver (NSR KT-N7), namely “SKH Lui Ming Choi Memorial Primary School”, during examination periods. The predicted exceedance for NSR KT-N7 during examination periods is 1-4 dB(A) for a duration of 19 weeks within the 7 years construction period. |
Residual noise impact was predicted at one educational Noise Sensitive Receiver (NSR KT-N7), namely “SKH Lui Ming Choi Memorial Primary School”, during examination periods. The predicted exceedance for NSR KT-N7 during examination periods is 1-5 dB(A) for a duration of 13 weeks within the 4.5 years construction period. |
|
All practicable mitigation measures including movable barrier, insulating fabric and quiet plants have been proposed and exhausted to minimise the noise impact. In addition, it is noted that noise insulation works have been installed at this school. Therefore, significant noise impact would not be anticipated. |
||
Water Impact |
With the implementation of the recommended mitigation measures, no adverse water quality impact from the Project works is anticipated for all three Reprovisioning Options. |
||
Waste Management Implications |
Provided that the identified waste arisings are handled, transported and disposed of using approved methods, and that the recommended good site practices are strictly followed, significant adverse environmental impacts would not be expected during the Project works of three Reprovisioning Options. |
||
Land Contamination |
Mitigation measures for handling of contaminated materials and regular site audits are recommended to minimise the potential adverse impacts on workers’ health and safety and disposal of potential contaminated materials for the three Reprovisioning Options. |
||
Ecological Impact |
Evaluations of ecological impacts addressed have confirmed there are no adverse ecological impacts resulting from the Project under any of the three Reprovisioning Options. |
||
Fisheries Impact |
Evaluation of fisheries impact addressed has confirmed there is no adverse fisheries impact resulting from the Project under the three Reprovisioning Options. |
||
Landscape Impact |
With the implementation of proposed mitigation measures including the provision of the proposed future waterfront promenade (by others) prior to the removal of the existing Cadogan Street Temporary Garden, the anticipated landscape impacts are generally slight negative during the carrying out of the Project due to the unavoidable removal of the existing Cadogan Street Temporary Garden (LR1) and removal of roadside vegetation (LR2) for the proposed decontamination works. The overall residual landscape impact in year 10 following completion of the Project is considered to be insubstantial when the compensatory tree planting in the proposed future waterfront promenade will have already reached a size that could largely compensate for the loss of the felled trees. |
With the implementation of proposed mitigation measures, the anticipated landscape impacts are generally moderate negative during the carrying out of the Project due to the unavoidable removal of the existing Cadogan Street Temporary Garden (LR1) and removal of roadside vegetation (LR2) for the proposed decontamination works. The overall residual landscape impact is slight negative when compensatory tree planting in the proposed future waterfront promenade will have become mature. |
With the implementation of proposed mitigation measures, the anticipated landscape impacts are generally moderate negative during the carrying out of the Project due to the unavoidable removal of the existing Cadogan Street Temporary Garden (LR1) and removal of roadside vegetation (LR2) for the proposed decontamination works. The overall residual landscape impact is slight negative when compensatory tree planting in the proposed future waterfront promenade will have become mature. |
Notwithstanding that all three re-provisioning options have been
assessed and confirmed to be environmentally acceptable, Re-provisioning Option
A is not quite as environmentally friendly as Options B and C in view of the
substantially longer exposure period of potential environmental impacts (such
as air quality, noise and health risk) on local residents. Moreover,
Re-provisioning Option A would result in a long lead time of site availability
for redevelopment there (such as future waterfront promenade). Overall, a
re-provisioning option with a shorter programme is more desirable and should be
pursued subject to local responses.
An environmental monitoring and audit (EM&A) programme will be
implemented during the carrying
out of the Project to check the effectiveness of the
recommended mitigation measures and compliance with relevant statutory
requirements. Details
of the EM&A works have been specified in the
EM&A Manual. The EM&A Manual contains details of the proposed EM&A
requirements, implementation schedule of the environmental protection /
mitigation measures, EM&A reporting procedures and complaint handling
procedures.
This EIA study has identified and assessed the potential environmental impacts that may arise from the carrying out of the Project in accordance with the guidelines of the EIAO-TM and the EIA Study Brief. Cement solidification and biopiling are the preferred decontamination methods for soil contaminated with heavy metals and hydrocarbons respectively. Based on the results of assessments of the three Reprovisioning Options, the EIA study concludes that with implementation of the recommended mitigation measures, the potential impacts arising from the Project are considered to be environmentally acceptable and the Project would be in compliance with the environmental legislation and standards. No significant adverse residual impacts from the Project are anticipated. A comprehensive EM&A programme will be implemented to check the implementation of mitigation measures and environmental compliance.