Environmental Impact
Assessment
Executive Summary
Comprehensive Development and Wetland Protection
Near Yau Mei San Tsuen
Prepared by
ENVIRON Hong Kong Limited
in association with
Handi design Limited
AEC
Limited
AECOM
Kenneth
To & Associates Ltd
Urbis Limited
Date:
March 2015
Reference
Number:
R0345_V8.F
Environmental Impact
Assessment
Executive Summary
Comprehensive Development and Wetland Protection
Near Yau Mei San Tsuen
Prepared
by:
|
|
Approved
by:
|
Henry
Ng
Senior Environmental Consultant
|
|
Tony
Cheng
Senior Manager
|
ENVIRON
Hong Kong Limited
Room
2403, Jubilee Centre,
18
Fenwick Street,
Wanchai, Hong Kong
Tel: 3465 2888
Fax: 3465 2899
E-mail: hkinfo@environcorp.com
Q:\Projects\HENYAUMEEI00\Report\Exe Summary\Executive Summary
R0345 V8.F Eng.doc
1.1.1
The Project is
proposed for comprehensive development and wetland
protection near Yau Mei San Tsuen. The Project Site, with
a
total area
of about 8.1 ha, near Fairview Park, Yuen
Long. The
site is
sandwiched by several suburban residential communities
such as Palm Springs to the north, Yau Mei San Tsuen and Royal Palms to the east, Fairview Park to the west (Figure 1).
1.1.2
Pursuant to the requirement of the
Environmental Impact Assessment Ordinance (EIAO), an Environmental Impact Assessment (EIA) has
been undertaken. It provides a detailed assessment of the nature and extent of potential environmental impacts associated with the construction and
operation of the Project, including air quality, noise, water quality, waste management, ecology,
fisheries, cultural
heritage, landscape and visual resources, and recommendations for mitigation measures to comply with
environmental legislations and standards. The impact assessments in the EIA have been conducted by qualified and
experienced environmental consultants in association with consultants in
various expert fields including ecology, fisheries, engineering, planning,
architectural, traffic, cultural heritage, landscape and urban design in
accordance with the Project EIA Study Brief requirements as well as the
technical requirements in the EIAO-TM.
1.1.3
This Executive Summary provides a summary of the key findings of the EIA
study. A non-technical
summary providing a reader-friendly understanding of the key results of the
environmental impact assessment that has been undertaken,
is provided in Appendix A for
reference.
1.2
Project Location
1.2.1
The Project
Site covers Lot Nos. 3054 BRP and 3055 in DD 104 near Yau Mei San Tsuen, Mai Po, Yuen
Long, with the total site area of about 8.1 ha. Under
the
Approved Mai Po
and Fairview Park Outline Zoning Plan (OZP) No. S/YL-MP/6,
the Project Site is zoned ¡§Other Specified Uses¡¨ annotated
¡§Comprehensive
Development and Wetland Protection Area¡¨ (i.e. ¡§OU(CDWPA)¡¨). The planning intention of the zone is
to allow comprehensive
low-density residential development/ redevelopment with the
protection and conservation of the existing continuous and contiguous fishponds
within the zone.
In brief, the site is designated by the Government for residential use
and wetland protection purpose in line with the existing and planned uses on
the adjacent sites.
1.2.2
Several existing
residential developments including Palm Springs, Royal Palms
and Yau Mei San Tsuen are located to
the further
north and east of Project Site. An existing Ngau Tam Mei Drainage
Channel is located to the south of the Project Site. While Fairview Park
and Yau Pok Road are located to the west and south, respectively. Figure
1 shows the location and environs of the Project Site. Between the southern boundary of the
Project Site and the Yau Pok Road, a cycle track linking the existing local
cycle track networks of Yuen Long to Sheung Shui will be constructed by the Government.
1.3.1
Residential or
recreational developments within Deep Bay Buffer Zones 1 or 2 are designated
projects under the EIAO, of which environmental impact
assessment (EIA) is required to be conducted. As
the Project falls within Deep Bay Buffer Zone 2 (Figure
1)
and comprises residential development, an EIA is required for the Project.
1.4.1
The Project is to transform the Project Site
into an area principally made up of wetland protection, which comprises a 3.8 ha wetland restoration
area in the north-western portion of the Project Site, and supported by a sub-urban
settlement at the south and south-eastern portion (Figure 2). The sub-urban settlement will include 3-storeys low density houses, clubhouse, swimming pool, site drainage system and ancillary
facilities.
|
|
|
|
|
|
|
|
|
Figure
2
Conceptual
Layout of the Project
|
|
2.1.1
An EIA has been undertaken for the proposed development in accordance
with the requirements stipulated in the EIAO-TM as well as that in the Project
EIA Study Brief issued by the Government in order to provide a detailed assessment of the nature and extent of potential environmental impacts associated with the construction and
operation of the Project.
2.1.2
The potential environmental
issues associated with the construction and operation of the Project, key
findings, conclusions and recommendations are summarised in the following
sections.
2.2.1
During
the construction phase of the Project, fugitive dust emissions
from the site formation works due to earth movement activities and transportation
of excavated/ fill materials are the major sources of air pollution.
According
to the assessment results, the predicted
unmitigated dust levels due to this Project would
exceed the Air Quality Objectives/ Criteria and its
stipulated No. of Exceedance Allowed.
2.2.2
However,
no unacceptable air quality impacts are anticipated
with the following mitigation measures in place:
dust control measures required under the Air
Pollution Control (Construction Dust) Regulation,
e.g. imposing hard paving on the designated haul road; spraying water on areas
with active site formation works during day-time; enclosing dump trucks when transporting
dusty materials with impervious sheeting, etc.;
good housekeeping practice by the works contractors; and the project
specific measures recommended in the EIA report
(e.g. minimizing the active working
area so that each construction site will be divided into different sub-zones
with only one sub-zone under construction in any one time, etc.). The
mitigated dust level would comply with the relevant air quality objectives/
criteria. The predicted
mitigated dust levels due to this Project are provided below:
|
TSP (1-hr avg.)
|
RSP
(24 hours avg.) *
|
RSP (Annual avg.)
|
PM2.5
(24 hours avg.) *
|
PM2.5 (Annual avg.)
|
Predicted
Range, £gg/m3
|
164 - 295
|
122 - 125
|
43.3 ¡V 44.3
|
91 - 92
|
30.7 ¡V 31.0
|
No. of Exceedance
|
n/a
|
3
|
n/a
|
2
|
n/a
|
Compliance
with Air Quality Criteria?
|
Yes
|
Yes
|
Yes
|
Yes
|
Yes
|
|
|
|
|
|
|
Air Quality Criteria, £gg/m3
|
500
|
100
|
50
|
75
|
35
|
No. of Exceedance Allowed
|
n/a
|
9
|
n/a
|
9
|
n/a
|
Remark:
* The daily levels are based on the 1st highest 24-hour average concentrations at the receivers.
Based on predicted results, the maximum predicted 24-hour
average concentrations exceed the AQO limit, but no. of exceedances concerned is still within the AQO criteria. Thus,
the dust level can comply with the relevant air quality criteria /
AQOs.
2.2.3
Nevertheless, monitoring is still recommended
during construction to ensure proper implementation of the mitigation measures,
and to minimize the construction dust level as far as practicable.
2.2.4
During operational phase
or when the residents live in these dwellings,
there will be no planned dust generating activities
from them. Given the scale of this
Project (for small houses development), vehicular emissions due to traffic of this Project
is unlikely to be significant, and the Project is unlikely contribute to any
adverse air quality impact. Sewage generated by the
proposed development will be discharged to the planned public sewerage system at Yau Pok Road.
The interim sewage treatment plant will
be enclosed and underground, and equipped with odour absorptive system, thus the Project Site itself will not contribute to any adverse air pollution or
odour nuisance. There is also no air quality
impact relating to industrial chimney emissions as no chimney is
identified within the Assessment Area. Although the Project is adjacent to
existing road network, sufficient setback distance has already been
incorporated between the development and the roads, hence the impact from
vehicular emission from the road is insignificant.
Overall,
no unacceptable air quality impact is expected to occur.
2.2.5
In brief,
with the implementation of the mitigation measures as recommended in the EIA
report, no adverse air quality impact due to the Project is anticipated.
Construction Phase
2.3.1
The use of Powered Mechanical Equipment for various construction
activities will be the primary potential noise source
during the construction phase of the Project. Without mitigation measures, the predicted unmitigated construction noise level at representative
noise sensitive receivers (NSRs) would exceed the relevant construction noise
criteria (i.e. 75dB(A) for residential uses; and 70dB(A) for educational
institutions (65B(A) during school examination
period)) at most of the NSRs. However, with the adoption of a combination of noise mitigation measures such as
use of quiet type equipment, scheduling of construction programme to avoid
concurrent works, and provision of movable and fixed temporary noise barriers, the predicted mitigated construction
noise level would only range from 60dB(A) to 74dB(A), which comply with the relevant construction
noise criteria. In addition, to ensure that the
construction noise will not affect the nearby NSRs in the Fairview Park, Palm
Springs and Yau Mei San Tsuen, short sections of temporary noise barriers (ranged
from 3m to 6m high to shield the NSRs from potential construction noise) are
proposed primarily along the Project site boundary. From the above, no adverse construction noise impact due to the Project or the nearby concurrent projects is anticipated.
Unmitigated
Noise Level, dB(A)
|
Mitigated
Noise Level, dB(A)
|
Noise
Criteria, dB(A)
|
Mitigation
Measures
|
>75
(>70 for educational institutions)
|
60 - 74
|
75dB(A)
for residential uses; and 70dB(A) for educational institutions (65B(A) during school examination period)
|
Quiet
type construction equipment; scheduling of construction programme to avoid
concurrent works; and provision of movable and fixed temporary noise
barriers.
|
2.3.2
Monitoring of the construction noise is
recommended in the EIA report to ensure proper implementation of the mitigation measures, and to
minimize the noise level as far as practicable.
Operational Phase
2.3.3
Regarding the traffic noise impact from
the adjacent roads on future residents of the Site, the proposed development has setback
from Yau Pok Road, thus the predicted road traffic noise level would range from 61dB(A) to 69dB(A) at the proposed development, which can comply with the relevant noise criteria of
70dB(A). Thus, there will be no unacceptable noise
impacts from road traffic noise.
2.3.4
An evaluation conducted on potential industrial noise from activities within open storage site to the further east
of the Project Site has found no adverse noise impacts on this Project and therefore no noise mitigation measure is necessary. The predicted noise level due to
operation of the open storage site would be 44dB(A), which complies with the relevant noise criteria of 55dB(A) (day-time) and 45dB(A) (night-time), respectively.
|
Calculated Noise Level, dB(A)
|
Noise Criteria, dB(A)
|
Road
Traffic Noise
|
61 - 69
|
70
|
Industrial
Noise
|
44
|
55
(day-time); and 45 (night-time)
|
2.3.5
From the above, it is concluded that
with the
adoption of the noise mitigation measures recommended in the EIA report, there
will be no unacceptable noise impacts.
2.4.1
The Project will involve
land-based works only, thus during construction of this
Project, the major potential water
quality
impact will be from surface runoff and soil
erosion of exposed surfaces. To alleviate the
impacts, the EIA report recommends the adoption of good site practices and construction
of a properly designed temporary drainage system within the site.
2.4.2
A peripheral
site drainage system comprising precast concrete u-channels along site boundary
together with sand/silt removal facilities and in accordance with the requirements stipulated in
Professional Persons on Environmental Consultative
Committee Practice Notes on the Site Drainage (ProPECC PN 1/94),
will be constructed in order to divert surface runoff away from the Fairview
Park Nullah and the existing drainage to the south of
Palm Springs. Similar peripheral
site drainage system will also be constructed along the edge of residential portion
during its construction. The
surface runoff will be properly treated prior to the discharge into Ngau Tam
Mei Drainage Channel (NTMDC). Pursuant
to the ¡§Water Pollution Control Ordinance¡¨, applications to the EPD for
Discharge Licences are required prior to the commencement of the construction works
and occupation of the development. In
addition, regular environmental
audits, as part of the proposed Environmental Monitoring and Audit (EM&A), including
regular water quality monitoring and site inspections will be undertaken
routinely in order to ensure there is no uncontrolled discharge of surface
runoff and that the recommended mitigation measures are properly implemented.
2.4.3
Upon occupation of the Site, all domestic sewage generated will be discharged to the public
sewerage system at Yau Pok Road. Before the concerned public sewerage
system becomes available, an interim sewage treatment plant will be used for
treatment of sewage generated from the proposed development. The discharge of
treated effluent would comply with the relevant discharge limits/ criteria in
order to ensure there will be no net increase in
pollution loading to Deep Bay areas.
The
discharge from the STP is also subject to a discharge licence under the WPCO,
and the discharge shall comply with the terms and conditions in the licence as
well as the conditions specified in the Environmental Permit (EP) of this
Project.
2.4.4
Surface runoff from the
development site will be discharged to the NTMDC.
Best
Management Practices have been proposed in order to abate first flush pollution
in stormwater runoff such as design measures to minimise soil
erosion, proper site drainage design/control; provision of devices/
facilities to control pollution and to remove pollution source; and administrative measures
for maintenance issues. Standard
design of road gullies with silt traps and oil interceptors will be
incorporated during the detailed design. Drainage outlet of covered car park
will also be equipped with oil interceptor. In addition, manhole with
sand trap will be incorporated before final discharge. With appropriate
drainage system equipped within the proposed development, there will be no
adverse water quality impact during the operation of the Project as
the increase
in surface runoff from this Project is insignificant when compared with the capacity of the trained downstream Ngau Tam Mei Drainage Channel,
which are engineered drainage channels designed for collecting stormwater. The proposed wetland restoration area (WRA) in the north-western portion of the
Project Site has been designed so that it will be self-contained and there is no outlet connecting to nearby
channel/inland water. Surface runoff will be diverted away from the WRA by drainage channels.
|
Recommended
Mitigation Measures
|
Construction Phase
|
¡P
A peripheral site drainage system comprising
precast concrete u-channels along site boundary and works area;
¡P
Equipped with sand/silt removal facilities in
accordance with the requirements stipulated in Professional Persons on Environmental
Consultative Committee Practice Notes on the Site Drainage (ProPECC PN 1/94);
¡P
Surface runoff to be diverted away from the
Fairview Park Nullah and the existing drainage channel
to the south of Palm Springs;
¡P
Collected surface runoff will be properly treated
prior to the discharge into Ngau Tam Mei Drainage Channel;
¡P
Regular environmental audits, as part of the
proposed Environmental Monitoring and Audit (EM&A), including regular
water quality monitoring and site inspections to ensure there is no uncontrolled
discharge of surface runoff and that the recommended mitigation measures are
properly implemented; and
¡P
Pursuant to the ¡§Water Pollution Control
Ordinance¡¨, applications to the EPD for Discharge Licences prior to the commencement
of the construction works and occupation of the development
|
Operational Phase
|
¡P
Domestic
sewage to be discharged into planned public sewers under the permanent disposal scheme;
¡P
A
sewage treatment plant to treat generated sewage in interim;
¡P
Treated
effluent is to comply with relevant
discharge limits in the licence and the conditions
in the EP, and there is no net increase in pollution loading to
Deep Bay areas;
¡P
Best Management Practices have
been proposed to abate first flush pollution in stormwater runoff, which
covers design measures; provision of devices/
facilities to remove pollutants; and administrative measures.
¡P
Proper drainage system to collect surface runoff from the
development with appropriate facilities and sand traps. Road gullies, car park and similar facilities installed
with oil interceptors;
¡P
WRA
is to be self-contained and surface runoff to be diverted away from WRA.
|
2.4.5
With the adoption and implementation of the mitigation measures recommended in the EIA report, no adverse water quality impact is anticipated during construction or operation of
the Project.
2.5.1
The proposed residential
development area will be located to west of the Yau Mei San Tsuen
Village. There is no existing public sewerage system in the vicinity to the
Development. The Project Area with maximum 345 people (resident and staff) will
generate a peak flow of 12 l/s additional sewage peak flow to the future public
sewerage network under PWP Nos. 4215DS and 4235DS, as permanent measure.
Hydraulic analysis shows that the future public sewerage and pumping stations
have sufficient spare capacity for conveying the overall sewage generated at
2030 which includes the additional sewage from the Project Area. The hydraulic
analysis also revealed that YLSTW after upgrade would have adequate capacity
for the overall sewage generated at year 2030.
2.5.2
Considering that the current
implementation programme of the Ngau Tam Mei Sewerage under PWP 4235DSD is
still very tentative and uncertain due to public objection. It is necessary to
consider the provision of the on-site sewage treatment facility as an interim
measure to handle the sewage generated from the development. The interim
on-site sewage treatment facility with the enhanced tertiary treatment process
of MBR/RO system will treat the 148m3/day sewage to achieve the Group
C Inland and Costal Discharge Standard of Deep Bay WCZ. Also, it is understood
there is no denitrification and effluent disinfection process at YLSTW
currently; whilst nutrient and bacterial requirements are not specified under
the current discharge license. The MBR/RO effluent will give better water
quality than the discharge effluent at YLSTW.
2.5.3
Furthermore, it is aware that the
interim treatment plant needs to fulfil the requirement of no net increase of
pollution loads to the Deep Bay under the Town Planning Board (TPB) Guidelines,
i.e. TPB PG-No.12C. Considering all the existing village houses
and associated septic tanks within the site area will be vacated and demolished
for the purpose of the proposed development, the residual pollution loads of
the on-site sewage treatment plant will be reduced by offsetting the current
pollution loads from the existing village houses after the completion of the
proposed development. It is hence evident that the proposed development will
not cause net increase of pollution load to the Deep Bay WCZ in adhere with the
pollution loads requirement under the TPB guidelines. At the same time the provision of the
interim onsite sewage treatment facilities will have positive impact on the
pollution load to Deep Bay WCZ
comparing to the existing condition and do nothing scenario.
2.5.4
Furthermore, the sewerage system
within the development area will be designed to facilitate the future
connection to the government sewerage system at Castle Peak Road. The proposed
sewerage system for the Development will be connected to Ngau Tam Mei sewerage
system once it becomes available. Adverse short-term and long-term
environmental impacts in respect of water quality, ecological, public health
and safety arising from both the long term and interim sewerage scheme are not
anticipated. No adverse sewerage impact will be incurred as a result of the
development.
|
Recommended
Measures
|
Domestic Sewage
|
¡P
A peak flow of 12 l/s sewage to
be generated;
¡P
Sewage
to be discharged into planned public sewer under permanent disposal scheme;
¡P
An
interim sewage treatment plant (STP) comprising enhanced tertiary treatment
process of MBR / RO system before planned public sewer is available;
¡P
STP
to be designed to facilitate future connection to the planned public sewer;
¡P
Maintenance
and emergency measures recommended to ensure effective operation of the STP;
¡P
Discharge
from STP will not result in net increase in pollution loading to Deep Bay by
offsetting existing pollution loads;
¡P
The discharge of treated effluent from the STP is to comply with the terms and conditions in the discharge licence under
the WPCO as well as the conditions specified in the EP of this Project.
|
2.6.1
The types and
categories of waste that would be generated during the construction phase of the
Project include site clearance, excavated soil, construction
and demolition materials, chemical waste from the
maintenance of construction plant and equipment, and general refuse from
the workforce. Opportunities for
reduction in waste generation through recovery, reuse or recycling have been
identified in the assessment.
Excavated materials and C&D materials can be reused as filling
materials where possible.
2.6.2
The appropriate disposal method
for each type of waste generated from the construction method was identified.
Opportunities for reducing construction
waste generation and maximizing re-use on-site were evaluated. Environmental mitigation measures and
good practices have been recommended in the EIA report in order to mitigate the
environmental impacts.
|
Recommendations
|
Construction Waste
|
¡P
A waste management plan to be prepared and
implemented by contractor(s) through-out construction;
¡P
Implementation of proper
trip ticket system;
¡P
Proper training on waste
management to workers;
¡P Avoidance and minimization to reduce the
potential quantity of C&D materials generated;
¡P Reuse of materials as practical as possible;
¡P Recovery and Recycling as practical as possible;
¡P Proper treatment and disposal in respect to relevant
laws, guidelines and good practice;
¡P Landfill disposal as the last resort; and
¡P Regular environmental audit and monitoring to
ensure effective implementation.
|
2.6.3
With the recommended practices
are strictly followed, no adverse impacts to the environment associated with
waste generated by the construction phase of the Project are anticipated.
2.6.4
As the
Project is not a high-density development, the development even
when fully occupied will generate limited amount of domestic waste. Standard approach that is widely adopted in
other parts of Hong Kong shall be adopted for the handling and disposal of this
small quantity of waste during the operational phase. Waste generated will be collected and
disposed of properly by a licensed contractor using refuse collection
vehicle. Thus, no adverse waste
management issues are expected to arise during operation of the Project.
2.7.1
Six habitats (pond, marsh, reedbed,
seasonally wet grassland, dry agricultural
land and grassland/shrubland) were identified within
the Project Area. A 12-month
ecological survey programme was conducted to assess the habitat characteristics
and wildlife utilization within the Project Area and adjoining areas. All
habitats of the Project Area support a low diversity of plant species, all of
which are common to very common in the territory. The overall faunal
diversity was also low. These habitats were evaluated as having ¡§Low¡¨ to ¡§Low
to Moderate¡¨ ecological value. Further site visits were undertaken in December 2014
to verify the habitat condition, and it was confirmed that the conditions of these
areas are unchanged. The major
impact of the proposed development is the residual loss of agricultural land
but the wetland habitats in the north of the project Area will be retained and
enhanced. A key element of the
project will be in the establishment of a 3.8ha Wetland Restoration Area (WRA),
including 0.2ha of Wetland and Visual Buffer; thus there will be a net increase
in the area functioned as wetland of 0.8ha (a 27% increase). Habitats to be restored/
enhanced in the WRA will include pond with deep and shallow water zones, marsh,
reed, bamboo, gravel (non-vegetated area), grassy bund and wooded bund. All
these habitats have been carefully chosen to provide suitable conditions for the
wetland fauna (waterbirds, amphibians and dragonflies) which currently use the Project
Area; hence none of these wetland fauna will be adversely affected. Indeed, during
operational stage because the WRA will be carefully designed and actively
managed for their needs, these species are expected to benefit from the
project¡¦s successful implementation.
2.7.2
The WRA will be completed before the construction works of the
residential portion commences so as to mitigate for direct and disturbance
impacts to birds during the construction phase of the Project. In addition, an
area of temporary wetland enhancement is proposed prior to the construction
period of the WRA to further reduce the potential impact of short-term habitat
loss for wildlife caused by this mitigation measure.
|
Recommendations
|
Operational Phase
|
¡P
3.8
ha of Wetland Restoration Area to be established, including 0.2ha of Wetland and Visual
Buffer;
¡P
A
net increase in area functioned as wetland ;
¡P
WRA
comprising pond with deep and
shallow water zones, marsh, reed, bamboo, gravel (non-vegetated area), grassy
bund and wooded bund;
¡P
Habitats
for wetland fauna (waterbirds, amphibians and dragonflies) enhanced;
¡P
Carefully
designed and actively managed under the scheme agreed with relevant
government authorities.
|
Construction Phase
|
¡P
WRA
to be constructed prior to construction of residential portion to mitigate
disturbance to birds;
¡P
A temporary wetland enhancement area to be provided during
the construction and establishment periods of WRA.
|
2.7.3
Overall, with the above mitigation measures in place, there would not be
significant adverse residual ecological impact from the proposed development.
Furthermore, as a net ecological gain, the project will contribute to
maintaining the integrity of the wider Deep Bay wetland ecosystem by securing
the permanent long term conservation management of wetland habitats which will
link the ponds to the north and the Ngau Tam Mei Drainage Channel to the south.
This will ensure that flight-lines for waterbirds flying between these areas
will not be impeded and will be permanently protected.
|
|
Project Site ¡V currently the developable
area consists of dry agricultural fields and
grassland/shrubland
|
|
|
|
Project Site ¡V wetlands within the site are
currently unmanaged, limiting their ecological function
|
|
2.8
Fisheries
2.8.1
There are no ponds for edible
fish aquaculture within the Project Site. The existing ponds within Project Site will be retained and
converted into wetland habitat (ponds) and managed as part of the WRA. The loss
of the potential
for redevelopment for editable fish culture is insignificant as
comparing to
the overall fish pond area (<1%). When other concurrent projects are taken
into consideration, the cumulative fisheries impact remains insignificant and
acceptable. Hence, no significant adverse fisheries impact is predicted.
Further, with the implementation of good site practices and water quality
and construction and operational sewerage and drainage measures, indirect
impacts during construction and operational phases would also be insignificant.
.
2.9.1
A Cultural Heritage Impact
Assessment has been carried out for the Project. The assessment area has been determined to contain no site of archaeological interest/
potential. Thus, no direct and
indirect impacts to any terrestrial archaeology are anticipated.
In addition, no
land use features or
declared monuments
that may carry specific cultural meanings were identified within the Project
Site, thus there is no cultural element concerned.
2.9.2
The only potential cultural resource
identified is an ancestral hall at existing Wo Shang Wai village
450m north of the Project Site beyond existing major residential developments
such as Palm Springs and Royal Palms.
The ancestral hall is not a graded historic building and has already
been modified with modern structures, which is also located beyond the Project
Area. It is concluded that no
cultural heritage resources will be affected by the Project and no specific mitigation measures would be
required
during construction and operation phases of the Project.
2.10.1
The major source of landscape and
visual impacts arising from the proposed development will be due to the removal
of existing vegetation, the presence of the construction sites/new structures,
and the enhancement works to be implemented to the existing pond
/ wetland
within the WCA portion.
2.10.2
These impacts will be mitigated
during construction by various measures.
These will include the proper preservation of existing healthy
unaffected trees, advance tree planting, the appropriate screening of
construction works, and, the control of night-time lighting. The temporary
noise barriers (approximately respectively 3m, 4.5m and 6m high) are proposed
along the southern part of the development. The temporary noise barrier design
will incorporate finishes, such as opaque and non-reflective material utilising
colours that are sympathetic to the surrounding environment. The form of treatment will be
sensitively selected to reduce visual impact and to avoid bird strikes (Figures
4 & 5).
2.10.3
When the development comes into
operation, impacts will be mitigated by new, healthy planting throughout the
development, within the landscape buffer along the boundary (Figure
3),
and the restored wetland/ pond. These
features (especially the wetland pond by enhancing the existing pond
/ wetland area) will uplift the overall landscape amenity.
2.10.4
The visual impact of the 1.8m
high
perimeter wall and 1.8m high wire mesh will be
mitigated by very careful landscape treatment (Figure 3).
2.10.5 The assessment concluded that the residual landscape and visual
impacts of the proposed development will be acceptable with mitigation measures
during construction and operation phases.
3.1.2
Details of the EM&A programme,
mitigation measures required during construction and operational phases, and
requirements are provided in the EM&A Manual of the EIA report. An Environmental Team (ET)
comprises suitably qualified staff and specialists shall be appointed to carry
out the recommended EM&A works for the project. The Independent Checker (Environment)
(IEC) shall advise the Engineer or Engineer¡¦s representative on environmental
issues related to the project
and audit ET¡¦s EM&A works. A summary of key EM&A monitoring
schedule is provided below:
EM&A
Monitoring Schedule
Environmental Aspects
|
EM&A Requirement
|
General
|
Construction Phase:
¡P Site Surveillance ¡V once per week
during construction phase by ET;
¡P Environmental complaints
investigation ¡V upon receipt of complaints by ET and IEC;
¡P Reporting ¡V baseline monitoring
report; monthly EM&A reports; quarterly EM&A summary reports; and
final EM&A reports by ET.
|
Noise
|
Construction Phase:
Monitoring noise level at nearby
sensitive receivers.
¡P Baseline Monitoring:
Monitoring for 14 days prior to commissioning of
construction works by ET.
¡P Impact Monitoring:
Weekly monitoring throughout the
construction phase by ET.
Operational Phase:
Nil
|
Air Quality
|
Construction Phase:
Monitoring dust level at nearby
sensitive receivers.
¡P Baseline monitoring by ET:
Monitoring for 14 days prior to commissioning of
construction works by ET.
¡P Impact monitoring:
Monitoring every six days and
throughout the construction phase by ET.
Operational Phase:
Nil
|
Water Quality
|
Construction Phase:
Monitoring water quality at
nearby nullah and Ngau Tam Mei Drainage Channel by
ET.
¡P Baseline Monitoring:
3 days a week and for 4 weeks
prior to commissioning of construction works by ET.
¡P Impact Monitoring:
3 days a week throughout the construction phase by ET.
Operational Phase:
Nil
|
Sewerage
|
Construction
Phase:
Nil.
Operational
Phase:
Regular sampling
and testing of treated effluent in accordance with discharge licence
requirements as well as conditions specified in the EP during operation of
the interim sewage treatment plant.
|
Waste Management
|
Construction Phase:
Monitoring on waste generation,
disposal and minimisation by ET and Engineer. Auditing on contractor(s) waste management performance.
Operational Phase:
Nil
|
Landscape and Visual
|
Detailed Design:
Monitoring design works against recommendations of
landscape and visual in the EIA during detailed design stage by a Registered
Landscape Architect.
Construction Phase:
¡P Baseline Monitoring:
Prior to construction works.
¡P Impact Monitoring:
Monitoring and auditing on the implementation of
landscape construction works and subsequent maintenance operations by a
Registered Landscape Architect.
Operational Phase:
To
be audited by a Registered Landscape
Architect during the last 12 month establishment period. Managed and maintained during
operation.
|
Ecology
|
Construction Phase (Monitored by qualified
ecologists):
¡P Baseline Monitoring:
12 months prior to the commencement of any site
clearance for wetland and/or residential construction to establish the
baseline condition of the site;
this includes bird, dragonfly/butterfly and herpetofauna.
¡P Impact Monitoring:
Monitoring of the items during the baseline
monitoring is required and weekly site visit.
¡P Advance Provision of the WRA:
The WRA should be constructed prior to the
commencement of the residential portion.
¡P Temporary Ecological Enhancement
Area:
An area at the western portion of the site is to
be managed and maintained as a temporary ecological enhancement area.
¡P Site Hoarding:
To be provided at the boundary of the Project Area.
¡P Movable noise barrier:
To be provided around machinery.
¡P Control Access:
No unauthorized access to the WRA; no dogs allowed at the
construction site.
Operational Phase (Monitored by qualified
ecologists):
¡P Ecological Monitoring:
Ongoing of ecological monitoring to evaluate the success
of the WRA;
¡P Control Access:
Implementation of a 1.8 m tall
dog-proof chain link fence.
No unauthorized access to the WRA; no dogs allowed at the
WRA.
|
Fisheries
|
Construction Phase:
Nil
Operational Phase:
Nil
|
4.1.2
Based on the results of the Assessment, the
EIA study concludes that the Project would be environmentally acceptable and would comply with all environmental
legislations and standards. The EIA Study has also predicted that after the adoption of
appropriate
mitigation measures, there would be no adverse residue impacts. An environmental
monitoring and audit
programme has been
recommended to monitor the implementation of the mitigation measures and to ensure compliance with
environmental standards.