4.2 Environmental
Legislation, Standards and Guidelines
4.3 Description
of the Environment
4.4 Noise
Sensitive Receivers (NSRs)
4.6 Identification
of Environmental Impacts
4.7 Prediction
and Evaluation of Environmental Impacts
4.8 Mitigation
of Adverse Environmental Impacts
4.9 Evaluation
of Residual Impacts
4.10 Environmental
Monitoring and Audit
LIST OF TABLES
Table 4‑1 Basic Noise Levels for ANLs
Table 4‑2 Construction
Noise Standards during Non-restricting Hours
Table 4‑3 Road
Traffic Noise Assessment Criteria Specified in the EIAO-TM
Table 4‑4 Identified
Representative Noise Sensitive Receivers
Table 4‑5 Road
Types of the Project Roads
Table 4‑6 Maximum
Noise Levels (dB(A)) during Construction without Noise Mitigation Measures
Table 4‑7 Predicted
Road Traffic Noise Levels at Each Identified NSR under the Unmitigated Scenario
Table 4‑8 Maximum
SWLs for Selected “Quiet” PME and Alternative Plants
Table 4‑9 Noise
Mitigation Measures for Certain PME during Construction Phase
Table 4‑10 Maximum
Noise Levels (dB(A)) during Construction with Noise Mitigation Measures Adopted
Table 4‑11 Summary
of Proposed Noise Mitigation Measures
Table 4‑12 Predicted
Road Traffic Noise Levels at Each Identified NSR under the Mitigated Scenario
Table 4‑14 Predicted
Residual Construction Noise Period during Examination Period
LIST OF FIGURES
Figure 4.1 Project Boundary, 300m Study Boundary, and Locations of Noise Sensitive Receivers
Figure 4.2 Locations of Assessment Points of Each NSR (Key Plan, Sheets 1 and 2)
Figure 4.3 Locations of Construction Work areas and Noise Assessment Points
Figure 4.4A Proposed Locations of Noise Mitigation Measures
Figure 4.4B Section Views of Proposed Vertical and Cantilevered Barriers
APPENDICES
Appendix 4-1 Photographs of Identified Noise Sensitive Receivers
Appendix 4-2 Traffic Forecast for Assessment Year 2036
Appendix 4-3 Endorsement Letter from Traffic Department regarding Traffic Forecast
Appendix 4-4 Correspondence with Highways Department regarding Existing or Planned Noise Mitigation Measures
Appendix 4-5 Road-Plots of Road Traffic Noise Model
Appendix 4-6 Correspondence for the Concurrent Project - Replacement and Rehabilitation of Water Mains Stage 4
Appendix 4-7 Detailed Construction Noise Calculations (Unmitigated Scenario)
Appendix 4-8 Detailed Predicted Road Traffic Noise Results at Each Noise Assessment Point under the Unmitigated Scenario
Appendix 4-9 Detailed Construction Noise Calculations (Mitigated Scenario)
Appendix 4-10 Detailed Predicted Road Traffic Noise Results at Each Noise Assessment Point under the Mitigated Scenario
Percussive
Piling
General
Construction Works (other than Percussive Piling) during restricted hours
Table
4‑1 Basic Noise Levels for ANLs
Time Period |
ASR |
||
A |
B |
C |
|
All
days during the evening (1900 to 2300 hours), and general holidays (including
Sundays) during the daytime and evening (0700 to 2300 hours) |
60 |
65 |
70 |
All
days during the night-time (2300 to 0700 hours) |
45 |
50 |
55 |
General
Construction Works (other than Percussive Piling) during non-restricted hours
Table 4‑2 Construction Noise Standards
during Non-restricting Hours
Uses |
Noise Standards [1]
, Leq (30 mins)
dB(A) |
|
Non-restricted
hours: 0700 to 1900 hours on any day not being a Sunday or general holiday |
Restricted
hours: 1900 to 0700 hours or any time on Sundays or general holiday |
|
All domestic premises including temporary housing
accommodation |
75 |
See Note [2] |
Hotels and hostels |
75 |
|
Educational institutions including kindergartens,
nurseries and all others where unaided voice communication is required |
70 65 (During
examinations) |
Notes:
[1] The above standards
apply to uses that rely on opened windows for ventilation.
[2] The criteria laid down in
the relevant technical memoranda under the NCO for designated areas and
construction works other than percussive piling may be used for planning
purpose. A CNP shall be required for the carrying out construction work during
the period.
Table 4‑3 Road
Traffic Noise Assessment Criteria Specified in the EIAO-TM
Uses |
Road Traffic
Noise Assessment Criteria – Peak Hour Traffic (L10,(1-hour))
/ dB(A) |
Domestic Premises |
70 |
Hotels
and Hostels |
70 |
Offices |
70 |
Educational
Institutions |
65 |
Places
of public worship and courts of law |
65 |
Diagnostic
rooms and wards of hospitals, clinics, convalescences and homes for the aged |
55 |
Table 4‑4 Identified
Representative Noise Sensitive Receivers
NSR ID |
Property Name |
Land Use |
Ground Level (mPD) |
No. of Noise Sensitive Storeys |
1st Floor Assess-ment Point (mPD) |
Assessment for Construction Phase/ Operational Phase # |
Notes |
NSR1 |
New Kwai Fong Gardens Block A |
Residential |
6.7 |
32 |
22.4 |
O |
|
NSR2 |
Lingnam Dr. Chung Wing Kong Memorial
Secondary School |
Educational Institution |
5.4 |
6 |
9.6 |
C,O |
* |
NSR3 |
Lai King Catholic Secondary School |
Educational Institution |
5.4 |
6 |
9.6 |
C,O |
* |
NSR4 |
Ha Kwai Chung Polyclinic and Special
Services Centre |
Clinic |
27.8 |
6 |
29.0 |
C,O |
* |
NSR5 |
Fung King House |
Residential |
15.3 |
14 |
19.3 |
C,O |
|
NSR6 |
Wo King House |
Residential |
15.3 |
14 |
19.3 |
C,O |
|
NSR7 |
Ming King House |
Residential |
27.4 |
15 |
31.4 |
C,O |
|
NSR8 |
Yat King House |
Residential |
27.4 |
23 |
31.4 |
C,O |
|
NSR9 |
HKEAA-Lai King Assessment Centre |
Educational Institution |
30.1 |
6 |
37.3 |
C,O |
* |
NSR10 |
Yin Lai Court - Yin Kwong House (Block
A) |
Residential |
34 |
35 |
39.2 |
C,O |
|
NSR11 |
Yin Lai Court - Yin Tak House (Block B) |
Residential |
34 |
35 |
39.2 |
C,O |
|
NSR12 |
Yuet Lai Court - Lai Hung House |
Residential |
59.7 |
22 |
63.8 |
O |
|
NSR13 |
Yuet Lai Court - Lai Ha House |
Residential |
62.6 |
22 |
63.8 |
O |
|
NSR14 |
Yuet Lai Court - Lai Wah House |
Residential |
62.6 |
22 |
63.8 |
O |
|
NSR15 |
Yuet Lai Court - Lai Wan House |
Residential |
62.9 |
22 |
63.8 |
O |
|
NSR16 |
Yeung King House (Block 5) |
Residential |
25.8 |
15 |
29.8 |
O |
|
NSR17 |
On King House (Block 6) |
Residential |
25.8 |
14 |
29.8 |
O |
|
NSR18 |
Clothing Industry Training Centre |
Educational Institution |
40.1 |
6 |
44.3 |
O |
* |
Notes:
# C
= Construction Phase, O = Operation Phase
* Air-conditioning systems were noted on site
· Location of appropriate NSRs with respect
to the work sites;
· Determination of distance
attenuation and screening effects to NSRs from notional noise source of
relevant work sites;
· Prediction of construction noise
levels at NSRs in the absence of any mitigation measures;
· Proposal of mitigation measures
and determination of their effectiveness; and
· Determination of the residual
impacts.
· “Designated Project (DP) Roads”
are the roads that are completely new or existing road sections that have major
modifications and would cause significant traffic noise impact.
· “Other Roads” are the roads that
are unchanged or subject to minor changes by the Project or roads that not
classified as a material change under the Project.
Table 4‑5 Road Types of the Project
Roads
Project Section |
Road Description |
Road Type |
Bridge G |
Minor widening of Tsuen Wan Road Flyover
near existing Kwai Tsing Interchange Upramp |
Trunk road |
Bridge
H |
A
new single lane flyover with 6.0m width from Tsuen Wan Road (southbound- fast
lane) to Kwai Chung Road |
Trunk road |
· Unmitigated scenario at assessment
year (2036); and
· Mitigated scenario at assessment
year (2036)
· Is not higher than the noise
criteria; and
· Has no significant contribution to
the overall noise from Other Roads, if the cumulative noise level (i.e. noise
from the DP Roads together with Other Roads) exceeds the noise criteria
(a)
The
predicted overall noise level exceeds the noise standard in accordance with
EIAO-TM (e.g. 70 dB(A) for domestic premises and 65 dB(A) for educational
institutions, all in L10(1hour)); and
(b)
The
predicted overall noise level is at least 1.0 dB(A) more than the prevailing
traffic noise level, i.e. the total traffic noise level existing before the
works to construct the road were commenced; and
(c)
The
contribution from the DP Roads to the increase in the predicted overall noise
level is at least 1.0 dB(A).
· Site mobilisation, and preparation
(for all Works Areas)
· Construction of Bridge H (within
Works Areas D, E & F)
· Noise barrier construction (within
Works Areas D, E & F)
· Widening works on Bridge G (within
Works Area A)
· Demolition of existing footbridge
(within Works Areas D & E)
· Reprovision of footbridge (within Works Areas
B & C)
· Relocation/modification of
existing bus lay-by (within Works Areas D & E)
· Modification of Kwai Chung Road
(outside Fung King House) (within Works Area D)
· Completion of works (for all Works
Areas)
Table 4‑6 Maximum Noise Levels (dB(A))
during Construction without Noise Mitigation Measures
NSR |
Description |
Assessment
Criteria, dB(A) [2] |
Predicted
Maximum Noise Levels, dB(A) [1] |
|||
2018 |
2019 |
2020 |
2021 |
|||
NSR2 |
Lingnam Dr. Chung Wing Kong Memorial Secondary
School |
70/65 |
70 |
70 |
68 |
68 |
NSR3 |
Lai King Catholic Secondary School |
70/65 |
79 |
80 |
75 |
79 |
NSR4 |
Ha Kwai Chung Polyclinic and Special Services Centre
[3] |
70 |
69 |
69 |
68 |
68 |
NSR5 |
Fung King House |
75 |
78 |
81 |
79 |
78 |
NSR7 |
Ming King House |
75 |
64 |
80 |
79 |
75 |
NSR8 |
Yat King House |
75 |
65 |
75 |
73 |
70 |
NSR9 |
HKEAA-Lai King Assessment Centre |
70/65 |
63 |
77 |
75 |
72 |
NSR10 |
Wo King House |
75 |
61 |
71 |
69 |
66 |
NSR11 |
Ming King House |
75 |
61 |
70 |
68 |
65 |
Notes:
[1] Predicted noise exceedance are highlighted
in bold.
[2] Construction Noise Impact Assessment
criteria for educational institutions are Leq,30min of 65dB(A)
during examination period and 70dB(A) during normal school days.
[3] For
clinic, construction noise impact assessment criteria are not available with
reference to EIAO-TM. Leq,30min of
70dB(A) is adopted for this study.
Table 4‑7 Predicted Road Traffic Noise
Levels at Each Identified NSR under the Unmitigated Scenario
NSR |
Description |
Noise Standard Under EIAO-TM, dB(A) |
Range of Predicted Noise Level
(Unmitigated) (L10(1hour), dB(A)) |
Direct Mitigation Measures Required? [1] |
|||
Overall Noise Level |
Predicted Noise Levels due to Other
Roads |
Predicted Noise Levels due to DP Roads
only |
|||||
NSR1 |
New Kwai Fong Gardens Block A |
70 |
70~77 |
70~77 |
33~56 |
No |
|
NSR2 |
Lingnam Dr. Chung Wing Kong Memorial Secondary School |
65 |
72~77 |
72~77 |
37~57 |
No |
|
NSR3 |
Lai King Catholic Secondary School |
65 |
70~81 |
70~81 |
54~66 |
Yes |
|
NSR4 |
Ha Kwai Chung Polyclinic and Special Services Centre |
55 |
69~80 |
69~80 |
51~60 |
Yes |
|
NSR5 |
Fung King House |
70 |
72~84 |
72~84 |
62~72 |
Yes |
|
NSR6 |
Wo King House |
70 |
57~76 |
57~76 |
33~57 |
No |
|
NSR7 |
Ming King House |
70 |
57~80 |
57~80 |
36~69 |
No |
|
NSR8 |
Yat King House |
70 |
55~76 |
55~76 |
35~63 |
No |
|
NSR9 |
HKEAA-Lai King Assessment Centre |
65 |
77~81 |
77~81 |
60~69 |
Yes |
|
NSR10 |
Yin Lai Court - Yin Kwong House (Block A) |
70 |
69~78 |
69~78 |
37~62 |
No |
|
NSR11 |
Yin Lai Court - Yin Tak House (Block B) |
70 |
69~78 |
69~78 |
38~61 |
No |
|
NSR12 |
Yuet Lai Court - Lai Hung House |
70 |
70~74 |
70~74 |
26~38 |
No |
|
NSR13 |
Yuet Lai Court - Lai Ha House |
70 |
67~75 |
67~75 |
32~49 |
No |
|
NSR14 |
Yuet Lai Court - Lai Wah House |
70 |
64~75 |
64~75 |
34~49 |
No |
|
NSR15 |
Yuet Lai Court - Lai Wan House |
70 |
66~74 |
66~74 |
34~48 |
No |
|
NSR16 |
Yeung King House (Block 5) |
70 |
74~78 |
74~78 |
38~53 |
No |
|
NSR17 |
On King House (Block 6) |
70 |
66~78 |
66~78 |
26~52 |
No |
|
NSR18 |
Clothing Industry Training Centre |
65 |
69~71 |
69~71 |
36~40 |
No |
Notes:
[1] Direct mitigation measures are required if (a) noise level from
DP roads only > noise standards under EIAO-TM; or (b) overall noise
level> noise standards under EIAO-TM, and difference between overall noise
levels and noise levels of Other Roads ≥ 1.0 dB(A)
· selection and optimisation of
construction programs, avoidance of parallel operation of noisy PME, and/or
reduction in the proportion of usage of PME during noise sensitive periods such
as school examination period;
· use of “quiet” PME and working
methods;
· use of temporary at-source noise
mitigation measures such as noise barriers, acoustic fabric, noise enclosures,
noise jacket and mufflers; and
· use of good site practice to limit
noise emission from construction site.
Selection and Programming of Construction Processes
Use of “Quiet” Alternative Plant and Working Methods
Table 4‑8 Maximum
SWLs for Selected “Quiet” PME and Alternative Plants
Identification
Code in GW-TM |
Descriptions of
PME |
SWL
in GW-TM, dB(A) |
“Quiet”
PME example on QPME list [1] |
SWL
of “Quiet” PME, dB(A) |
CNP
004 |
Asphalt Paver |
109 |
EPD-01226 (VOLVO
ABG5770) |
104 |
CNP
081 |
Excavator,
Wheeled/Tracked |
112 |
EPD-01896 (HYUNDAI R80CR-9) |
98 |
CNP
048 |
Mobile
Crane |
112 |
EPD-01516 (KOBELCO CKS900) |
101 |
CNP
170 |
Poker, vibratory, hand held |
113 |
Poker, vibratory, hand held (electric) |
102 |
CNP
185 |
Road Roller |
108 |
EPD-01806 (KANTO-TK KV25DS) |
95 |
Note:
[1] QPME list available on the EPD website
Temporary Noise Barriers
Table
4‑9 Noise Mitigation Measures for
Certain PME during Construction Phase
Descriptions of PME |
Mitigation Measures Proposed |
Noise Reduction, dB(A) |
Breaker, excavated
mounted |
Temporary
Noise Barrier |
5 |
Excavator/Loader,
Wheeled/Tracked |
Temporary
Noise Barrier |
5 |
Dump Truck, with grab, ≤38
tonne |
Temporary
Noise Barrier |
5 |
Lorry |
Temporary
Nosie Barrier |
5 |
Lorry with crane/grab |
Temporary
Nosie Barrier |
5 |
Mobile Crane |
Temporary
Nosie Barrier Acoustic
Fabric |
5 |
Poker, vibratory,
hand-held (electric) |
Temporary
Nosie Barrier |
5 |
Piling, large diameter
bored, grab and chisel |
Temporary
Noise Barrier[1] /Acoustic Fabric[2] |
10 |
Road Roller |
Temporary
Noise Barrier |
5 |
Concrete Lorry Mixer |
Temporary
Noise Barrier |
5 |
Saw, chain, hand-held |
Temporary
Nosie Barrier |
5 |
Concrete pump, lorry
mounted |
Temporary
Nosie Barrier |
5 |
Asphalt Paver |
Temporary
Noise Barrier |
5 |
Air Compressor |
Temporary
Noise Barrier |
5 |
Note:
[1] Temporary
Noise Barrier of height not less than the equipment height to be provided to screen
noisy part of equipment. It is anticipated that temporary noise barrier of 8m
high with skid footing and a small cantilevered upper portion can be located within a few
metres of these equipment.
[2] With
reference to Tsim Sha Tsui Station Northern Subway EIA Report, 2008, the use of
acoustic fabric can achieve 10dB(A) noise reduction for piling activities .
Good Site Practice
· use of well-maintained and
regularly-serviced plant during the works;
· plant operating on intermittent
basis should be turned off or throttled down when not in active use;
· plant that is known to emit noise
strongly in one direction should be orientated to face away from the NSRs;
· silencers, mufflers and enclosures
for plant should be used where possible and maintained adequately throughout
the works;
· where possible fixed plants should
be sited away from NSRs; and
· stockpiles of excavated materials
and other structures such as site buildings should be used effectively to
screen noise from the works.
Assessment of Noise Impacts with the Application of
Mitigation Measures
· the use of quiet plants for PME
(QPME);
· temporary noise barriers and
acoustic fabric for PME, as well as noise jacket and mufflers to cover the
noisy part of PME and at the engine exhaust of mobile plants respectively;
· limiting of the number of plants
operated concurrently.
Table
4‑10 Maximum Noise Levels (dB(A)) during
Construction with Noise Mitigation Measures Adopted
Description |
Assessment Criteria, dB(A) [2] |
Predicted Maximum Noise Levels, dB(A) [1] |
||||
2018 |
2019 |
2020 |
2021 |
|||
NSR2 |
Lingnam Dr. Chung Wing Kong
Memorial Secondary School |
70/65 |
62 |
61 |
61 |
56 |
NSR3 |
Lai King Catholic Secondary School |
70/65 |
70 |
69 |
68 |
70 |
NSR4 |
Ha Kwai Chung Polyclinic and
Special Services Centre [3] |
70 |
61 |
62 |
61 |
56 |
NSR5 |
Fung King House |
75 |
69 |
73 |
71 |
68 |
NSR7 |
Ming King House |
75 |
60 |
72 |
70 |
67 |
NSR8 |
Yat King House |
75 |
57 |
67 |
65 |
62 |
NSR9 |
HKEAA-Lai King Assessment Centre |
70/65 |
57 |
69 |
67 |
64 |
NSR10 |
Wo King House |
75 |
54 |
63 |
61 |
58 |
NSR11 |
Ming King House |
75 |
53 |
61 |
60 |
56 |
Notes:
[1] Predicted noise exceedance
are highlighted in bold.
[2] Construction Noise Impact
Assessment criteria for educational institutions to be Leq,30min of
65dB(A) during examination period and 70dB(A) during normal school days.
[3] For clinic, construction
noise impact assessment criteria are not available with reference to EIAO-TM. Leq,30min of 70dB(A) is adopted for this
study.
· treatment of source;
· alternative alignment;
· noise barrier/enclosure; and
· open-textured road surfacing (i.e.
low noise road surfacing)
(a)
Dwellings,
classrooms and other noise sensitive elements that will benefit from provision
of direct noise mitigation measures are those:
(b)
Dwellings,
classrooms and other noise sensitive elements that will be protected by
provision of direct noise mitigation measures are those:
Table 4‑11 Summary of Proposed Noise
Mitigation Measures
Proposed Noise
Mitigation Measure |
Road
Name |
Direction |
Target
NSRs |
||
ID |
Description |
Length
(m) |
|||
A |
5.5m high with 2.5m cantilevered barrier at
45° |
85 |
Bridge H |
Southbound |
Lai King Catholic Secondary School, Ha Kwai
Chung Polyclinic and Special Services Centre, and Fung King House |
B |
5.5m vertical barrier |
20 |
Bridge H |
Southbound |
Lai King Catholic Secondary School, Ha Kwai
Chung Polyclinic and Special Services Centre, and Fung King House |
C |
5.5m high with 2.5m cantilevered barrier at
45° |
230 |
Bridge H |
Southbound |
Lai King Catholic Secondary School, Ha Kwai
Chung Polyclinic and Special Services Centre, and Fung King House |
D |
5.5m high with 3.5m cantilevered barrier at
45° |
45 |
Bridge H |
Southbound |
Fung King House, HKEAA-Lai King Assessment
Centre |
- |
Low noise road surfacing [1] |
- |
Bridge H |
- |
Lai King Catholic Secondary School, Ha Kwai
Chung Polyclinic and Special Services Centre, and Fung King House, HKEAA-Lai
King Assessment Centre |
Notes:
[1] LNRS is applied on highways with speed 70kph or above in general. Such mitigation
measure has been included in both unmitigated scenario and mitigated scenario in road traffic noise impact
analysis. The above table only describes
the mitigation measures on designated project roads (Bridge H) that is under
this noise impact assessment. Although
Bridge G would not constitute any material change and is classified as non-DP
road, it is also a high-speed trunk road, LNRS will be re-provisioned after
minor widening works and be applied in noise model as well.
Table 4‑12 Predicted
Road Traffic Noise Levels at Each Identified NSR under the Mitigated Scenario
NSR |
Description |
Noise Standard Under TM-EIAO, dB(A) |
Range of Predicted Noise Level
(Mitigated) (L10(1hour), dB(A)) |
Further Mitigation Measures Required? [1] |
||
|
|
|||||
|
|
Overall Noise Level |
Predicted Noise Levels due to Other
Roads |
Predicted Noise Levels due to DP Roads
only |
||
NSR1 |
New Kwai Fong Gardens Block A |
70 |
70~77 |
70~77 |
32~52 |
No |
NSR2 |
Lingnam Dr. Chung Wing Kong Memorial Secondary School |
65 |
72~77 |
72~77 |
35~56 |
No |
NSR3 |
Lai King Catholic Secondary School |
65 |
70~81 |
70~81 |
44~59 |
No |
NSR4 |
Ha Kwai Chung Polyclinic and Special Services Centre |
55 |
69~80 |
69~80 |
44~54 |
No |
NSR5 |
Fung King House |
70 |
70~84 |
70~84 |
46~60 |
No |
NSR6 |
Wo King House |
70 |
57~76 |
57~76 |
33~42 |
No |
NSR7 |
Ming King House |
70 |
57~80 |
57~80 |
34~63 |
No |
NSR8 |
Yat King House |
70 |
55~76 |
55~76 |
35~52 |
No |
NSR9 |
HKEAA-Lai King Assessment Centre |
65 |
77~81 |
77~81 |
56~65 |
No |
NSR10 |
Yin Lai Court - Yin Kwong House (Block A) |
70 |
69~78 |
69~78 |
37~59 |
No |
NSR11 |
Yin Lai Court - Yin Tak House (Block B) |
70 |
69~78 |
69~78 |
38~58 |
No |
NSR12 |
Yuet Lai Court - Lai Hung House |
70 |
70~74 |
70~74 |
26~35 |
No |
NSR13 |
Yuet Lai Court - Lai Ha House |
70 |
67~75 |
67~75 |
32~49 |
No |
NSR14 |
Yuet Lai Court - Lai Wah House |
70 |
64~75 |
64~75 |
34~48 |
No |
NSR15 |
Yuet Lai Court - Lai Wan House |
70 |
66~74 |
66~74 |
34~47 |
No |
NSR16 |
Yeung King House (Block 5) |
70 |
74~78 |
74~78 |
37~50 |
No |
NSR17 |
On King House (Block 6) |
70 |
66~78 |
66~78 |
26~46 |
No |
NSR18 |
Clothing Industry Training Centre |
65 |
69~71 |
69~71 |
35~39 |
No |
Notes:
[1] Further direct mitigation measures are required if (a) noise level from
Project roads only > noise standards under EIAO-TM;
or (b) overall noise level> noise standards under EIAO-TM,
and difference between overall noise levels and noise levels of Other Roads ≥
1.0 dB(A).
Table 4-13 Total Number of Dwellings,
Classrooms and Other Noise Sensitive Elements that will be Benefitted from and
be Protected by Provision of the Direct Noise Mitigation Measures
NSR |
Description |
No. of Dwellings Represented |
No. of Dwellings Exceeding EIAO Noise Criteria [1] |
No. of Dwellings benefitted from
noise mitigation measures [2] |
No. of Dwellings Protected from Noise Mitigation Measures [3] |
Residential
Dwellings |
|||||
NSR1 |
New Kwai Fong Gardens Block A |
128 |
126 |
0 |
0 |
NSR5 |
Fung King House |
420 |
417 |
83 |
3 |
NSR6 |
Wo King House |
280 |
133 |
0 |
0 |
NSR7 |
Ming King House |
360 |
225 |
2 |
5 |
NSR8 |
Yat King House |
506 |
288 |
0 |
10 |
NSR10 |
Yin Lai Court - Yin Kwong House (Block
A) |
105 |
94 |
0 |
0 |
NSR11 |
Yin Lai Court - Yin Tak House (Block B) |
105 |
101 |
0 |
0 |
NSR12 |
Yuet Lai Court - Lai Hung House |
88 |
86 |
0 |
0 |
NSR13 |
Yuet Lai Court - Lai Ha House |
88 |
84 |
0 |
0 |
NSR14 |
Yuet Lai Court - Lai Wah House |
88 |
82 |
0 |
0 |
NSR15 |
Yuet Lai Court - Lai Wan House |
88 |
84 |
0 |
0 |
NSR16 |
Yeung King House (Block 5) |
210 |
210 |
0 |
0 |
NSR17 |
On King House (Block 6) |
182 |
56 |
0 |
0 |
Sub-total |
2648 |
1986 |
85 |
18 |
|
Classrooms |
|||||
NSR2 |
Lingnam Dr. Chung Wing Kong Memorial
Secondary School |
48 |
48 |
0 |
0 |
NSR3 |
Lai King Catholic Secondary School |
48 |
48 |
0 |
0 |
NSR9 |
HKEAA-Lai King Assessment Centre |
36 |
36 |
0 |
0 |
NSR18 |
Clothing Industry Training Centre |
48 |
48 |
0 |
0 |
|
Sub-total |
180 |
180 |
0 |
0 |
Other Noise Sensitive Elements |
|||||
NSR4 |
Ha Kwai Chung Polyclinic and Special
Services Centre |
48 |
48 |
0 |
0 |
|
Sub-total |
48 |
48 |
0 |
0 |
|
Total |
2876 |
2214 |
85 |
18 |
Notes:
[1] Number
of dwellings, classrooms and other noise sensitive exposed to overall road
traffic noise levels exceeding the noise standards stipulated in the EIAO-TM
(refer to Table
4‑3).
[2] Dwellings, classrooms and other noise sensitive
elements benefitted from noise mitigation measures are those exposed to overall
road traffic noise exceeding noise standards stipulated in the EIAO-TM under
unmitigated scenario and are benefited at least 1.0 dB(A) from the
implementation of the noise mitigation measures.
[3] Dwellings,
classrooms and other noise sensitive elements protected by noise mitigation
measures are those exposed to overall road traffic noise exceeding noise standards
stipulated in the EIAO-TM under unmitigated scenario and exposed to overall
road traffic noise compiling with the noise standards stipulated in the EIAO-TM
with the implementation of the noise mitigation measures.
Table 4‑14 Predicted Residual Construction
Noise Period during Examination Period
NSR |
Predicted Residual Construction Noise Impact |
||
ID |
Description |
Period [2] |
Exceedance |
NSR3 |
Lai King Catholic Secondary School [1] |
March 2018 to July 2018; December 2018 to January 2019; March to July 2019; April to July 2020; December 2020; May 2021 and July 2021 (Total 20 months) |
3-5 dB(A) 1-3 dB(A) 1-2 dB(A) 1-3 dB(A) 1 dB(A) 1-2 dB(A) |
NSR9 |
HKEAA-Lai King Assessment Centre[1] |
January 2020; April 2020 (Total 2 months) |
1-2 dB(A) 1 dB(A) |
Notes:
[1] Air-conditioning
systems were noted on site at these NSRs
[2] Examination period assumed
to be December, January, March-July of each year