5.2 Environmental Legislation, Standards and Guidelines
5.3 Description of the Environment
5.4 Identification of Water Sensitive Receivers
5.5 Assessment Approach and Methodology
5.6 Identification of Potential Impacts
5.7 Prediction and Evaluation of Potential Impacts
5.9 Recommended Water Quality Mitigation Measures
5.10 Evaluation of Residual Impacts
5.11 Environmental Monitoring and Audit Requirements
LIST OF TABLES
Table 5-1 Summary of WQOs for Victoria Harbour (Phase One) WCZ
Table
5-2 WSD Standards at Flushing
Water Intakes
Table
5-3 Marine Water Quality for
Victoria Harbour (Phase One) WCZ in 2012 at VM12, VM14 and VT8
LIST OF FIGURES
Figure 5.1
Water Control Zones and Water
Sensitive Receivers
·
Annex
6 Criteria for Evaluating Water Pollution; and
·
Annex
14 Guidelines for Assessment of Water Pollution.
·
Water
Supplies Department (WSD) Water Quality Criteria;
·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS); and
·
Practice
Note for Professional Persons on Construction Site Drainage (ProPECC PN 1/94).
Table 5-1 Summary of WQOs for Victoria Harbour (Phase One) WCZ
Parameter |
Water Quality Objective |
Sub-Zone |
Offensive Odour, tints |
Not to be present |
Whole zone |
Visible Foam, Oil Scum, Litter |
Not to be present |
Whole zone |
E. coli |
Not to exceed 1,000 per 100mL, calculated
as the geometric mean of the most recent 5 consecutive samples taken at
intervals between 7 and 21 days |
Inland waters |
Colour |
Change due to human activity not to exceed 50 Hazen units |
Inland waters |
Depth-Averaged Dissolved
Oxygen (DO) |
Not less than 4.0mg/L for
90% of samples at a year |
Marine waters |
DO within 2m of the
Seabed |
Not less than 2.0mg/L for
90% of samples at a year |
Marine waters |
DO |
Not less than 4.0mg/L |
Inland
waters |
pH |
To be in the range of 6.5 to 8.5, change
due to human activity not to exceed 0.2 |
Marine waters |
Not to exceed the range of 6.0 to 9.0 due
to human activity |
Inland
waters |
|
Temperature |
Change due to human
activity not to exceed 2.0°C |
Whole zone |
Salinity |
Change due to human
activity not to exceed 10% |
Whole zone |
Suspended Solids (SS) |
Not to raise the ambient level by 30% due to caused by human activity and shall not affect aquatic communities |
Marine waters |
|
Annual median not to exceed 25mg/L due to
human activity |
Inland waters |
Un-ionised
Ammonia (UIA) |
Annual mean not to exceed
0.021mg/L as un-ionised form |
Whole zone |
Nutrients |
Shall not cause excessive
algal growth |
Marine waters |
Total Inorganic Nitrogen (TIN) |
Annual mean depth-averaged
inorganic nitrogen not to exceed 0.4mg/L |
Marine waters |
5-day Biochemical Oxygen Demand (BOD5) |
Not to exceed 5mg/L |
Inland waters |
Chemical Oxygen Demand (COD) |
Not to exceed 30mg/L |
Inland waters |
Toxic
substances |
Should not attain such
levels as to produce significant toxic effects in humans, fish or any other
aquatic organisms |
Whole
zone |
Human
activity should not cause a risk to any beneficial
use of the aquatic environment |
Whole
zone |
Table 5-2 WSD Standards at Flushing Water Intakes
Parameter (in
mg/l unless otherwise stated) |
WSD Target Limit |
Colour (Hazen Unit) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammoniacal Nitrogen (NH3-N) |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E.coli (no. per 100 ml) |
< 20,000 |
Table 5-3 Marine Water Quality Statistics for the Victoria Harbour (Phase One) WCZ in 2012 at VM12, VM14 and VT8
Parameter |
EPD’s Monitoring Station |
||
VM12 |
VM14 |
VT8 |
|
Temperature (°C) |
23.3 (15.9 - 28.3) |
23.5 (16.0 – 28.5) |
23.8 (17.4 – 28.6) |
Salinity (ppt) |
30.0 (26.0 – 32.6) |
28.9 (21.2 – 32.5) |
27.6 (18.2 – 32.0) |
Dissolved Oxygen (mg/L) |
6.0 (3.8 – 8.4) |
6.2 (3.6 – 8.1) |
6.3 (4.9 – 7.4) |
Bottom Dissolved Oxygen
(mg/L) |
6.0 (3.5 – 8.4) |
6.2 (3.3 – 8.1) |
6.1 (4.2 – 7.3) |
BOD5 (mg/L) |
0.4 (<0.1 – 1.0) |
0.4 (<0.1 – 1.0) |
0.6 (0.3 – 1.0) |
SS (mg/L) |
8.3 (2.5 – 16.0) |
5.8 (2.1 – 13.3) |
8.2 (3.0 – 16.0) |
TIN (mg/L) |
0.51 (0.34 – 0.85) |
0.56 (0.32 – 1.08) |
0.69 (0.31 – 1.15) |
NH3-N (mg/L) |
0.190 (0.113 – 0.247) |
0.159 (0.075 – 0.273) |
0.155 (0.047 – 0.270) |
Un-ionised
Ammonia (mg/L) |
0.004 (0.002 – 0.007) |
0.003 (0.001 – 0.006) |
0.003 (0.001 – 0.005) |
Chlorophyll-a (µg/L) |
1.3 (0.4 – 3.5) |
1.4 (0.4 – 4.2) |
3.4 (0.8 – 9.0) |
E.coli (count/100mL) |
410 (75 – 2,100) |
360 (51 – 5,200) |
710 (430 – 890) |
Notes:
[1] Data
presented are depth averaged (except as specified) and annual arithmetic means
except for E. coli (geometric
mean).
[2] Data in brackets indicate ranges.
[3] Underlined indicates occurrence of
non-compliance with that parameter of WQOs.
·
F1 – Kwai Chung Hospital Flushing Water Intake
·
C1 – Kwai Chung Hospital Cooling Water Intake
· C2 –
Tsuen Wan Cooling Water Intake
·
TS1 – Rambler Channel Typhoon Shelter
·
Construction site run-off during foundation piling;
·
Accidental chemical spillage; and
·
Sewage effluent produced by on-site workforce.
· Run-off
and erosion from bare soil and earth, drainage channels, earth working areas
and stockpiles;
· Wastewater
from dust suppression sprays and wheel washing facilities at site entrances;
· Fuel,
oil, solvents and lubricants from maintenance of construction machinery and
equipment.
· Construction
site run-off;
· General
construction activities and accidental spillage of chemicals; and
· Sewage
generated from on-site construction workers.
·
Run-off from exposed bare soil and earth, drainage
channels and stockpiles;
·
Release of grouting and cement materials with rain
wash;
·
Wash water from dust suppression sprays and vehicle
wheel washing; and
·
Fuel, oil and lubricant from maintenance of
construction vehicles and mechanical equipment.
·
At the establishment of works site, perimeter
drains to direct off-site water around the Site should be constructed with
internal drainage works and erosion and sedimentation control facilities
implemented. Channels
(both temporary and permanent drainage pipes and culverts), earth bunds or sand
bag barriers should be provided to divert the stormwater
to silt removal facilities. The design
of the temporary on-site drainage system will be undertaken by the Contractor
prior to the commencement of construction;
·
Dikes or embankments for flood protection should be
implemented around the boundaries of earthwork areas. Temporary ditches should be provided to
facilitate the run-off discharge into an appropriate watercourse, through a
silt / sediment trap. Silt / sediment traps should also be incorporated in the
permanent drainage channels to enhance deposition rates;
·
The design of efficient silt removal facilities
should be based on the guidelines in Appendix A1 of ProPECC
PN 1/94, which states that the retention time for silt / sand traps should be 5
minutes under maximum flow conditions. A
sedimentation basin would be required when necessary. The detailed design of
the silt / sand traps should be undertaken by the Contractor prior to the
commencement of construction;
·
The construction works should be programmed to
minimise surface excavation works during rainy seasons (April to September), as
possible. All exposed earth areas should
be completed and vegetated as soon as possible after the earthworks have been
completed. If excavation of soil cannot
be avoided during the rainy season, or at any time of year when rainstorms are
likely, exposed slope surfaces should be covered by tarpaulin or other means;
·
The overall slope of works sites should be kept to
a minimum to reduce the erosive potential of surface water flows, and all
trafficked areas and access roads should be protected by coarse stone
ballast. An additional advantage
accruing from the use of crushed stone is the positive traction gained during
the prolonged periods of inclement weather and the reduction of surface sheet
flows;
·
All drainage facilities and erosion and sediment
control structures should be regularly inspected and maintained to ensure their
proper and efficient operation at all times particularly following
rainstorms. Deposited silts and grits
should be removed regularly and disposed of by spreading evenly over stable,
vegetated areas;
·
Measures should be taken to minimise the ingress of
site drainage into excavations. If the
excavation of trenches in wet season is inevitable, they should be dug and
backfilled in short sections wherever practicable. The water pumped out from trenches or
foundation excavations should be discharged into storm drains via silt removal
facilities;
·
All open stockpiles of construction materials (for
example, aggregates, sand and fill material) should be covered with tarpaulin
or similar fabric during rainstorms.
Measures should be taken to prevent the washing away of construction
materials, soil, silt or debris into any drainage system;
·
Manholes (including newly constructed ones) should
always be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system and
storm run-off being directed into foul sewers;
·
Precautions to be taken at any time of the year
when rainstorms are likely, actions to be taken when a rainstorm is imminent or
forecasted and during or after rainstorms, are summarised in Appendix A2 of ProPECC PN 1/94.
Particular attention should be paid to the control of silty surface
run-off during rainstorm events;
·
All vehicles and plant should be cleaned before
leaving the Site to ensure no earth, mud, debris and the like is deposited by
them on roads. An adequately designed
and sited wheel washing facilities / bay should be provided at the exit of the
Site where practicable. Wash-water
should have sand and silt settled out and removed at least on a weekly basis to
ensure the continued efficiency of the process.
The section of access road leading to, and exiting from, the
wheel-washing bay to public roads should be paved with sufficient backfall toward the wheel-washing bay to prevent vehicle
tracking of soil and silty water to public roads and drains;
·
Oil interceptors should be provided in the drainage
system downstream of any oil / fuel pollution sources. Oil interceptors should be emptied and
cleaned regularly to prevent the release of oil and grease into the storm water
drainage system after accidental spillage.
A bypass should be provided for oil interceptors to prevent flushing
during heavy rain;
·
The construction solid waste, debris and rubbish
on-site should be collected, handled and disposed of properly to avoid causing
any water quality impacts. The
requirements for solid waste management are detailed in Section 6 of this EIA
report; and
·
All fuel tanks and storage areas should be provided
with locks and sited on sealed areas, within bunds with adequate storage
capacity to prevent spilled fuel oils.