Table of Contents

6.               Waste Management Implication and Land Contamination.. 6-1

6.1            Introduction. 6-1

6.2            Environmental Legislation and Guidelines. 6-1

6.3            Assessment Approach and Methodology. 6-4

6.4            Identification of Waste Sources. 6-4

6.5            Prediction and Evaluation of Waste Impacts. 6-4

6.6            Mitigation of Adverse Environmental Impacts. 6-13

6.7            Evaluation of Residual Impacts. 6-16

6.8            Environmental Monitoring and Audit Requirements. 6-16

6.9            Land Contamination. 6-16

6.10         Conclusion. 6-19

6.11         References. 6-19

 

 

 

LIST OF TABLES

 

Table 6-1         Summary of Estimated Quantities of Waste Arising from Construction Phase. 6-4

Table 6-2         Findings of Aerial Photographs Reviewed for the Site with Possible Excavation of Marine Sediment 6-7

Table 6-3         Tentative Estimated Timing of Waste Arising. 6-12

Table 6-4         Findings of Aerial Photographs Reviewed for Project Site. 6-17

Table 6-5         List of Registered Chemical Waste Producers. 6-18

Table 6-6         Potentially Contaminative Land Use along the Site. 6-18

 

 

 

LIST OF FIGURES

 

Figure 6.1                    Proposed Locations of Works with Possible Marine Sediment Excavation

Figure 6.2                    Location of Public Works Regional Laboratory of Tsuen Wan

 

 

APPENDICES

 

Appendix 6-1      Risk-Based Remediation Goals (RBRGs) for Soil & Soil Saturation Limit

Appendix 6-2      Aerial Photographs Interpretation

Appendix 6-3      Letters for LandsD, EPD and FSD

Appendix 6-4      Site Walkover Checklist and Photographs

Appendix 6-5      Memo between LandsD and CGE/Standards & Testing of CEDD regarding Land Contamination Issue of  Public Works Regional Laboratory of Tsuen Wan

 

 

 

 


6.                       Waste Management Implication and Land Contamination

6.1                   Introduction

6.1.1             This Chapter identifies potential environmental impact resulting from the handling, collection and disposal of the construction waste associated with the Project. It also presents an assessment of the potential for the occurrence of land contamination along the route of the Flyover.

6.1.2             The potential environmental impacts concerning their handling, collection and disposal will be assessed in accordance with the criteria and guidelines given in Annexes 7 and 15 of EIAO-TM, while the potential environmental impacts of land contamination will be assessed in accordance with the criteria and guidelines given in Sections 3.1 and 3.2 of Annex 19 of EIAO-TM.

6.1.3             Options for waste minimisation, recycling, storage, collection, and disposal of waste arising from the Project have been examined and procedures for minimising environmental impacts due to handling and disposal of waste are recommended.

6.2                   Environmental Legislation and Guidelines

General Waste Management

6.2.1             The following legislations are related to the handling, treatment and disposal of waste in Hong Kong, and will be considered in the assessment of potential impacts and waste management:

·      Waste Disposal Ordinance (Cap 354);

·      Land (Miscellaneous Provisions) Ordinance (Cap 28); and

·      Public Health and Municipal Service Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisances By-laws.

6.2.2             The following subsidiary regulations of the Waste Disposal Ordinance are also related:

·      Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C); and

·      Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N).

Waste Disposal Ordinance (Cap 354)      

6.2.3             The Waste Disposal Ordinance (WDO) prohibits any unauthorised disposal of wastes. Construction waste, defined under Cap. 354N of the WDO means any substance, matter or thing that is generated from construction works and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works.  Under WDO, waste can be disposed of only at designated waste disposal facilities licensed by the EPD.

Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

6.2.4             Chemical wastes include unwanted substances or chemicals causing pollution or impose a danger to health or risk of pollution to the environment.  A person should not produce, or cause to be produced, any chemical wastes unless he/she is registered with the EPD.  Chemical wastes must be treated using on-site plant as licensed by the EPD or with engaging a licensed collector to transport the wastes to a licensed facility. For each consignment of wastes, the waste producer, collector and disposer must sign all relevant parts of a computerised trip ticket so as to trace wastes from production to disposal.

6.2.5             This regulation also prescribes the storage facilities to be provided on-site including the labelling and warning signs.  To minimise the risks of pollution and danger to human health and life, waste producers are required to prepare and make available written emergency procedures for any spillage, leakage or accidents arising from storage of chemical wastes.  The waste producers must also provide employees with training for such procedures.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N)

6.2.6             Under the WDO and the Charging Regulation, wastes can only be disposed of at designated waste disposal facilities licensed by EPD.  Schedule 5 of Regulation defines that inert construction waste includes rock, rubble, boulder, earth, soil, sand, concrete, brick, tile, masonry or used bentonite.  According to Schedule 6 of the Regulation, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material while those to a sorting facility for disposal must contain more than 50% by weight of inert material. Whereas construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material.

6.2.7             For construction work with a value of more than HK$1 million, the main contractor is required to establish a billing account at the EPD before transporting the construction waste to the designated waste disposal facilities (for example, landfill and public fill). The vessels for delivering construction waste to the public fill reception facilities require prior approval from the Public Fill Committee (PFC).  Any breach of these regulations may lead to a fine and/or imprisonment.

Land (Miscellaneous Provisions) Ordinance (Cap 28)

6.2.8             The inert portion of Construction and Demolition (C&D) materials (including rocks, soil, broken concrete, building debris, etc.) may be taken to public fill reception facilities (PFRFs).  PFRFs usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires individuals or companies who deliver public fill to PFRFs to obtain Dumping Licences.  The licences are issued by CEDD under delegated authority from the Director of Lands.

6.2.9             Individual licences and windscreen stickers are issued for each vehicle involved.  Under the licence conditions, PFRFs will only accept inert construction waste. In addition, in accordance with paragraph 12 of the Development Bureau (DevB) Technical Circular (Works) TC(W) No.6/2010, PFC will advise on the acceptance criteria.  The material will, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the PFRF supervisor.

Public Cleansing and Prevention of Nuisances Regulation (Cap 132)

6.2.10         This regulation provides further control on the illegal dumping of litter or waste in streets and public places (including water courses, streams, channels etc).  Offence to this regulation would result in a fine and/or to imprisonment.

Other Relevant Guidelines

6.2.11         The following guidelines are also relevant to waste management in Hong Kong:

·      Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), EPD ;

·      Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site;

·      WBTC No. 2/93, Public Dumps;

·      WBTC No. 2/93B, Public Filling Facilities;

·      WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Subcommittee Papers;

·      WBTC No. 12/2000, Fill Management;

·      WBTC Nos. 6/2002 and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness;

·      WBTC No. 11/2002, Control of Site Crusher;

·      WBTC No. 12/2002, Specification Facilitating the Use of Recycled Aggregates;

·      Environment Transport and Works Bureau Technical Circular (Works) (ETWB TC(W)) No. 33/2002 Management of Construction and Demolition Material  Including Rock;

·      ETWB TC(W) No. 19/2005 Environmental Management on Construction Sites; and

·      DevB TC(W) No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials, Development Bureau.

6.2.12         The ETWB TC(W) No. 19/2005 sets out the policy and procedures requiring contractors to prepare and implement an Environmental Management Plan (EMP) to abate environmental nuisances on construction site and reduce C&D material to be disposed of during construction.

Contaminated Land

6.2.13         The following legislations are related to the land contamination issues concerning handling, treatment and disposal of contaminated materials:

·      Waste Disposal Ordinance (Cap 354);

·      Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C); and

·      Dangerous Goods Ordinance (Cap 295).

6.2.14         The following EPD publications provide guidance on the land contamination assessment in this Assignment:

·      Practice Guide for Investigation and Remediation of Contaminated Land (August 2011);

·      Guidance Note for Contaminated Land Assessment and Remediation (December 2007); and

·      Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management (August 2007).

6.3                   Assessment Approach and Methodology

6.3.1             The assessment of waste management implications has been conducted in accordance with Annexes 7 and 15 of the EIAO-TM. This includes:

·      Estimation of types and quantities of wastes generated;

·      Assessment of potential impact caused by handling (including labelling, packaging and storage), collection, and disposal of wastes with respect to potential hazard, air and odour emission, noise, wastewater discharge and public transport; and

·      Determination of practical mitigation measures for the environmental impacts.

6.4                   Identification of Waste Sources

6.4.1             Construction activities will result in the generation of a variety of wastes which can be divided into distinct categories based on their constituents, as follows:

·      Inert C&D material (inert portion of C&D material);

·      C&D Waste (non-inert portion of C&D material);

·      Marine Sediment;

·      Chemical waste; and

·      General refuse.

6.4.2             The operational phase of the proposed project is not expected to generate any waste.

6.5                   Prediction and Evaluation of Waste Impacts

Construction Phase

6.5.1             The nature and preliminary quantities of each of these waste types arising from the construction phase of the proposed works are identified below. The detailed calculations of materials and waste arising are required to be submitted to Government under the requirements of WBTC 25/99 during the detailed design. Table 6-1 summarises the estimated quantities of different types of waste arising from the Project.

Table 6-1     Summary of Estimated Quantities of Waste Arising from Construction Phase

Waste Type

Source

Total Quantity

Handling

Quantity to be Reused On-site

Quantity to be Disposed of Off-site

Inert C&D material

Excavation for foundation

4,730 m3

 

Reuse on-site or disposed off-site to public fill reception facilities in Tuen Mun Area 38 Fill Bank

4,810 m3 of inert C&D material as fill material

1,140 m3 inert C&D material [1]

 

 

Excavation for at grade road construction

100m3

 

Excavation for other works (e.g. demolition works, utility diversion)

930 m3

 

C&D Waste

Cleared vegetation; wood from formwork; unusable cement mixes; and damaged or contaminated construction materials

655 m3

Sent to WENT landfill

--

790 m3

Marine Sediment

Excavation for piling and foundation works

400m3

Treatment for decontamination, if necessary followed by cement stabilisation for treated and uncontaminated marine sediment

480m3 [2] as fill material for abutment after treatment

--

Chemical Waste

Scrap batteries, spent acid/alkali, spent mineral oil/ cleaning fluid, spent solvent, engine oil and fuel from construction plants or equipment

Few hundred litres per month

Stored on-site within suitably designed containers and collected by licensed company

--

Few hundred litres per month

General Refuse

Food waste, waste paper, aluminium cans etc generated from workforce

Few hundred kilogrammes  per day in the peak period

Sorted recyclables sent to recycling company, other non-recyclable refuse collected by on-site refuse collection point and transferred to landfill

--

Few hundred kilogrammes  per day in the peak period

Note:

[1] A factor of 1.2 is applied in the estimate of inert C&D material and C&D waste quantity to be disposed of off-site.

[2] The volume of the marine sediment after cement stabilisation will be increased by around 20%.

Inert Construction and Demolition (C&D) Material

6.5.2             Inert C&D material would be generated during the construction of proposed bridges including the foundation, substructure and superstructure works, and the reprovisioning work of the footbridge. Types of inert C&D material include soil, rock, concrete, bituminous material etc. The total quantity of the inert C&D material generated in the Project is estimated to be approximately 5,760 m3. Among this, about 4,810 m3 of inert C&D material would be reused on-site as fill material. Approximately 1,140 m3 of inert C&D material would be disposed to public fill reception facilities in Tuen Mun Area 38 Fill Bank for other beneficial uses with accounting a factor of 1.2 in the estimate of inert C&D material quantity to be disposed of off-site.

6.5.3             The site for the Public Works Regional Laboratory of Tsuen Wan (Laboratory Site), which is currently allocated to CGE/Standards & Testing of CEDD, is proposed to be the site office and stockpiling area for those inert C&D material not immediately disposed during construction phase.

C&D Waste

6.5.4             In addition to the inert C&D material that would be generated, as noted above, which are suitable for reuse on site or as public fill, some C&D waste would, also, be generated during the construction phase. These materials include:

·      Any cleared vegetation;

·      Wood from formwork;

·      Unusable cement mixes; and

·      Damaged or contaminated construction materials.

6.5.5             About 655 m3 of C&D waste would be generated during construction phase. They will be disposed to WENT Landfill. A factor of 1.2 is applied in the estimate of C&D waste quantity to be disposed of off-site and therefore the quantity of C&D waste to be disposed off-site is 790 m3.

Marine Sediment

6.5.6             According to the existing information from Geotechnical Investigation (GI) records, marine sediment has been identified in the reclamation area within the Project Site. It is estimated that approximately 400m3 of marine sediment will be excavated from the reclaimed land due to the piling works for the proposed bridges in the Project. The assessed volume will be verified during detailed design stage of the Project in future.   

6.5.7             A common way of handling marine sediment in local construction industry is disposing of it to marine dumping sites in accordance with ETWB TC No 34/2002 and Dumping at Sea Ordinance, Cap. 466 (DASO). However, recent public concerns are growing on the high levels of heavy metal contents found in some common seafood species due to serious sea water pollution.

6.5.8             One method to address this environmental issue is by treatment and reuse of the dredged marine sediment rather than disposing it to the sea.

6.5.9             With reference from overseas’ and Hong Kong’s cases, reuse of the dredged sediment on-site with treatment, if necessary, is proposed to this Project, a preliminary contamination assessment for the site of marine sediment was conducted in accordance with the following Technical Memorandum and Guidance Notes published by the EPD:

·      Practice Guide for Investigation and Remediation of Contaminated Land, August 2011 (Practice Guide);

·      Guidance Note for Contamination Land Assessment and Remediation, August 2007 (Guidance Note); and

·      Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management, December 2007 (Guidance Manual).

6.5.10         Possible ex-situ treatment and beneficial reuse options are identified to demonstrate that no environmentally unacceptable impact would be resulted from the excavation, treatment and reuse of marine sediment.

6.5.11         The preliminary contamination assessment and possible ex-situ treatment and beneficial reuse options for the marine sediment to be excavated in this Project is presented as follows:

Initial Contamination Evaluation of the Site for Marine Sediment

6.5.12         The history information of the site with possible excavation of marine sediment (Site with Marine Sediment) was obtained by reviewing the relevant aerial photographs. The aerial photographs are shown in Appendix 6-2. Table 6-2 summarises the findings of the aerial photographs reviewed.

Table 6-2     Findings of Aerial Photographs Reviewed for the Site with Possible Excavation of Marine Sediment

Year

Notes

1963

The Site with Marine Sediment comprises natural hillside and sea where there were a lot of fishing boats around the site.

1973

Extensive reclamation has taken place at the Site with Marine Sediment.

 

6.5.13         As observed from the aerial photograph of 1963 in Appendix 6-2 the Site with Marine Sediment, is located on the sea in 1963. From the aerial photograph of 1973, the site was reclaimed.

6.5.14         As the Site with Marine Sediment is located in the urban area where there was industrial development nearby from 1950s, local discharge of polluted effluent from industrial uses might impose a potential cause to contaminate the marine sediment in the sea before reclamation of the site.

6.5.15         From a conservative point of view, it is proposed to conduct a site investigation with environmental sampling and analysis during detailed design stage of this Project on the Site with Marine Sediment to identify the contamination extent of the marine sediment.

6.5.16         As the marine sediment was potentially contaminated by local discharge of polluted effluent from many unknown uses, the potential contaminants may include semi-volatile organic compounds (SVOCs), metals, polychlorinated biphenyl, petroleum carbon ranges (PCRs) and organometallics.

6.5.17         It is proposed that the samples could be collected at where the excavation of marine sediment to be conducted which are the locations for piles. Exact sampling locations and numbers shall be identified with the updated information during detailed design stage. The proposed locations of works with possible marine sediment excavation with the past geotechnical investigation records showing the locations of samples for marine sediment are shown in Figure 6-1  

6.5.18         Among the four different post-restoration land use categories, namely “Urban Residential”, “Rural Residential”, “Industrial” and “Public Parks”, “Public Park” is the most relevant use to the proposed development as flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road as they are both open space of good ventilation and with transient receivers. Therefore, it is suggested that the contamination extent of the marine sediment excavated should be checked against the RBRGs for soil for “Public Park” as the marine sediment is proposed to be re-used on-site.

6.5.19         Samples of marine sediment should be collected and analysed against the RBRGs for soil for Public Park. The RBRGs for soil is presented in Appendix 6-1.

6.5.20         A more detailed assessment and environmental investigation for marine sampling and analysis shall be carried out during the detailed design stage of this Project.

6.5.21         A Sediment Assessment Plan shall be submitted with the updated information during the detailed design stage and obtain EPD’s approval before the environmental investigation. A Sediment Assessment Report / Sediment Remediation Plan should be prepared pending the result of environmental investigation for EPD’s approval before treatment and reuse of marine sediment.

Possible Remediation Options

6.5.22         With reference from the consultancy study – FM01/2007 by CEDD on various management options for marine sediment in Hong Kong [1], the following presents possible remediation options for treatment of marine sediment exceeding the proposed RBRGs for this Project.

(a)        Mechanical Dewatering

This technique separates water from the sediments by mechanical means such as belt filter presses and centrifuge. The advantages are high capacity, and it can be easily increased by using additional presses. Also, it requires small area for installation. Moreover, dewatering is effective and efficient. However, it requires relatively high investment and operation costs. Besides, treated sediments after dewatering may be still considered contaminated which requires further treatment.

This is applied in St. Lawrence River in Canada (EC. 1995). Shallow areas that posed a navigational hazard in the St. Lawrence River at the Port of Sorel were dredged and found to contain elevated levels of metals (EC, 1995). The project utilised a rotatory press and additives to remove water and decontaminate approximately 5,000m3 of sediment along the river.  The rotary press reduced the volume of sediments 5 to 10 times and the dryness level went from 15% to 72% of total particulate matter during dewatering.[2]

(b)        Biological Remediation

This option makes use of bio-oxidation of organic matter by micro-organisms to break down Polychlorinated Biphenyls (PCBs), pesticides, and other organic constituents into less toxic compounds. It has high removal efficiency for PCRs and polycyclic aromatic hydrocarbon (PAHs) but the treatment time is relatively long. The presence of heavy metals can inhibit microbial metabolism and thus affects the removal efficiency.

The Stauffer Management Company Superfund Site is an inactive pesticide manufacturing/distribution facility in Tampa, Florida. From 1951 to 1986, the site was used to formulate organochlorine and organophosphate pesticides. From 1953 to 1973, waste materials from the facility were disposed on site, leading to pesticide contamination in soil, surface water, sediment, and groundwater. Bioremediation was adopted from 1997 to 1998 for treatment of pesticide-contaminated surface soils and sediments at the site.

.

 
Concentrations of toxaphene were reduced by more than 90% and chlordane by nearly 90%. [3]

(c)        Chemical Treatment

Oxidation, reduction, hydrolysis or neutralisation are the available technologies for chemical treatment. The benefits are low energy consumption and relatively rapid process. However, as treatment methods are specific to particular contaminants or classes of compounds, selection of method and reagent is important to the success of the process.

A research on separating the Tributyltin (TBT) contaminated seawater from the dredged marine sediment was undertaken by the Kyushu University in Japan. It is reported that TBT was successfully separated from the contaminated seawater by applying coagulant called PSl-100 as well as filtering the water through fibre sheet, sand and activated carbon. Following the treatment, the concentration of TBT was reduced from 1,200-1,450ng/L to 3ng/L.

(d)       Thermal Destruction / Incineration

It is the most widely operation used for destroying organic contaminants in which the organic contaminants are volatilised at temperatures greater than 1000°F in the presence of oxygen resulting in combustion and destruction of the contaminants. It is effective that incineration typically achieve greater than 99% destruction for organics. However this option is relatively expensive and not effective on heavy metals. Additional handling / treatment of by-products such as residue contaminants in ash, gaseous emissions and wastewater is required.

The Drake Chemical Superfund (DCS) Site included a chemical manufacturing facility that operated from 1951 to 1982, producing chemical intermediates used in dye, cosmetic, textile, pharmaceutical, pesticide and herbicide manufacturing. Drums of chemical waste, chemical sludge, and demolition debris were disposed on the ground surface and in the shallow subsurface at the site. Site soil and chemical sludge were contaminated with volatile organic compounds (VOCs), SVOCs and metals.

The incinerator was in full-scale operation from 1998 to 1999 as the remedial technology for addressing soil contamination at the site. All site soil was excavated down to the water table and treated. Treated soil and fly ash that met treatment standards were used as fill material at the site. [3]

(e)        Sediment Washing

Sediment washing is a water-based process for mechanically scrubbing excavated sediment to remove contaminant and contaminants from sediment either by dissolving or suspending them in a wash solution. A wide variety of sediment contaminated with soluble metals, halogenated solvents, aromatics, gasoline, fuel oils, PCBs, chlorinated phenols and pesticides can be treated with this method with high removal efficiency. The treatment cost is relatively high and this process cannot efficiently treat fine particles, low-permeability packed materials, or sediment with high humic content.

Advanced Sediment Washing Technology is marketed jointly by WESTON and BioGenesis, West Chester, PA. This technology is a multistaged sediment washing and organic oxidation process for decontaminating dredged sediments and producing a marketable fine-grained soil-like product for reuse after the addition of bulking materials. During the process, organic material is stripped from the solid particles and chemically oxidised. [4]

(f)         Immobilisation   / Solidification / Stabilisation

Reactive materials are mixed with the marine sediment to immobilise contaminants. Available technology in market includes microencapsulation, cement-based solidification and silicate-based solidification.  It operates most successfully in wastes with inorganics and metals and is a relatively less expensive technique. The treated sediment can be reused as fill material for construction works. Nevertheless, it is not effective on volatile organics and the effectiveness on organics or other leachables is inconclusive.

Sediments at the New York/New Jersey Harbour were contaminated with organochlorine pesticide, PAHs, PCBs, dioxins and furans and metals. Immobilisation was adopted in the treatment of the contaminated sediment. The treatment of the material was done in a barge. Stabilised materials have been used as structure fill at a parking lot and capping brownfield site in New Jersey.[5]

Sediments excavated for South Island Line (East) were sampled and tested in accordance with ETWB TC(W) No. 34/2002 and were found contaminated with copper and zinc. Cement stabilisation was adopted to treat the metal contaminated sediment. The cement stabilised materials were used as fill on-site in 2014.[6]

Treatment and Outlet of Decontaminated or Uncontaminated Marine Sediment

6.5.23         The applicant shall propose in the Sediment Assessment Report / Sediment Remediation Plan the remedial measures for decontaminating marine sediment based on the results from environmental investigation and the clean-up criteria for the contaminated marine sediment for agreement with EPD. 

6.5.24         It is proposed to locate the treatment facilities at the Laboratory Site or the area just near to the piling works where marine sediment is excavated, depending on where it is excavated and the area required for the treatment.

6.5.25         It is proposed to reuse the marine sediment as fill material for abutment of the proposed Bridge H. Unless solidification or stabilisation process is chosen as the remediation option for the contaminated marine sediment, to reuse the marine sediment as fill material, the decontaminated or uncontaminated marine sediment should undergo cement stabilisation process for improvement of the structural stability. After cement stabilisation process, it is expected the volume of the treated marine sediment will expand by 10-20%.

6.5.26         The cement stabilised marine sediment shall comply the criteria agreed upon with EPD, for example Universal Treatment Standards (UTS) and Unconfined Compressive Strength (UCS) standard, in accordance with the Practice Guide.

6.5.27         With identification of proper treatment methods for the excavated marine sediment pending the results of site investigation, no environmental impact is anticipated from the excavation, treatment and reuse of the marine sediment.

Chemical Waste

6.5.28         Chemical Waste, as defined under the Waste Disposal (Chemical Waste) (General) Regulation, includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation. A complete list of such substances is provided under the Regulation, however, substances likely to be generated by construction activities will, for the most part, arise from the maintenance of equipment. These may include, but not limited to, the followings:

·      Scrap batteries or spent acid/alkali from their maintenance;

·      Used engine oils, hydraulic fluids and waste fuel;

·      Spent mineral oils/cleaning fluids from mechanical machinery; and

·      Spent solvents/solutions, some of which may be halogenated, from equipment cleaning activities.

6.5.29         It is difficult to quantify the amount of chemical waste which will arise from the construction activities as it will be highly dependent on the Contractor's on-site maintenance intention and the number of plants and vehicles utilised. However, it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance will be small, (in the order of a couple of hundred litres per month) and will be readily accepted at the Chemical Waste Treatment Centre (CWTC) or other licensed waste oil recycling facilities. The actual amount of chemical wastes generated should be quantified and recorded in the Site Waste Management Plan to be prepared by the Contractor.

General Refuse

6.5.30         Construction site workers, site offices and canteens will result in the generation of a variety of general refuse requiring disposal. General refuse generated on site will mainly consist of food wastes, aluminium cans and waste paper.

6.5.31         The maximum number of workers and peak activities on-site are expected around the mid of Year 2019 to mid of Year 2020, hence the site will produce the highest volume of general refuse.

Operation Phase

6.5.32         The operational phase of the proposed Project is not expected to generate any waste and thus no significant waste implications during the operational phase are predicted.

Timing of Waste Generation

6.5.33         Based on the preliminary construction programme, the construction will be carried out from 2018 to 2021.  A tentative estimated timing of waste arising is shown in Table 6-3.


Table 6-3      Tentative Estimated Timing of Waste Arising

Type of Waste

Months

Construction Phase

Inert C&D Material

M1 to M37

C&D Waste

M1 to M37

Marine Sediment

M3 to M7 and M20 to M23

Chemical Waste

Entire construction phase

General Refuse

Transportation Frequency and Route

6.5.34         The peak generation of the inert C&D material and C&D waste is expected during the foundation works of Bridge H including excavated soil and construction debris such as the used formworks at the months M22-M23 of the tentative construction programme. Among this period, all the inert C&D material and C&D waste will be transported to the stockpiling area at the Laboratory Site via Kwai Chung Road and Tsuen Wan Road, pending for sorting and backfilling or disposal. Assuming 24 working days monthly, the daily generation rate of the inert C&D material and C&D waste estimated from the tentative construction programme is 33.5m3. Assuming a density of 2 tonnes/m3, approximately 7 trucks (10 tonnes loading capacity per truck) per day will be used to transport this amount of the inert C&D material and C&D waste to the stockpiling area.  

6.5.35         Backfilling of the inert C&D material will be carried out from M24 to M27, after which the remaining inert C&D material and the C&D waste stockpiled before this period will be disposed off site within M28 which is considered as the peak period for disposal. Based on the tentative construction programme, the estimated quantity of inert C&D material and the C&D waste for disposal within M28  is expected to be 1116m3 and 216m3 after applying a factor of 1.2. The inert C&D material and C&D waste for disposal would be delivered to the public fill reception facilities and the landfill respectively. Assuming 24 working days monthly, the daily disposal rate of the inert C&D material and C&D waste is 46.5m3 and 9m3 respectively. Assuming a density of 2 tonnes/m3, approximately 10 trucks (10 tonnes loading capacity per truck) per day would deliver the inert C&D material to Tuen Mun Area 38 Fill Bank and approximately 2 trucks (10 tonnes loading capacity per truck) per day would deliver the C&D waste to WENT Landfill for disposal in a month. No barging point and conveyor will be used.  Other inert C&D material and C&D waste will be generated and disposed at later time during off-peak period.

6.5.36         The inert C&D material for disposal will be transported to Tuen Mun Area 38 Fill Bank via Tsuen Wan Road, Tuen Mun Road, Lung Mun Road while the C&D waste will be further transported to WENT Landfill via Lung Kwa Tan Road and Nim Wan Road.

6.5.37         The marine sediment excavated will be transported to the treatment facilities at the Laboratory Site or the area just near to the piling works where marine sediment is excavated during the period for excavation from M3 to M7 and M20 to 23. As the choice of location depends on where the marine sediment is excavated and the area required for the treatment, the transportation frequency and route cannot be provided at this stage.

6.5.38         As the quantity of chemical waste and general refuse is small, the chemical waste will be collected by licensed company in a truck monthly while general refuse will be collected by licensed collector and sent to WENT Landfill daily via the same route as C&D waste.

6.6                   Mitigation of Adverse Environmental Impacts

6.6.1             The Contractor is responsible for the management of materials and wastes during construction. This includes control of wastes on site, removal of the waste materials from the site and the implementation of any mitigation measures to minimise waste or redress any problems that arise from waste associated with the works.

6.6.2             This section sets out the measures to be adopted to avoid or minimise potential adverse impacts associated with waste arising from the works under the headings of each waste type. The Contractor should incorporate these recommendations into a comprehensive on-site Waste Management Plan, (WMP). If, for any reason, the recommendations cannot be implemented, full justification should be given in the WMP.

6.6.3             In accordance with ETWB TC(W) No. 19/2005  – Environmental Management on Construction Sites, the WMP should be prepared and submitted for approval by the Architect/ Engineer/ Supervising Officer prior to any construction activities. During the construction period the WMP should be used as a working document to detail the on-going management procedures and to record waste arising from construction works and import of fill throughout the Contract. The WMP shall be subject to audit under the requirements of the Environmental Monitoring and Audit (EM&A) Procedures set out in the EM&A Manual accompanying this EIA Report.

Waste Management Hierarchy

6.6.4             The WMP shall be developed and implemented according to a best-practice philosophy of waste management. There are various waste management options, which can be categorised in terms of preference from an environmental viewpoint. The options considered to be more preferable have the least impacts and are more sustainable in a long-term context. The hierarchy shall be as follows:

·      Avoidance and minimisation, i.e. avoiding or not generating waste through changing or improving practices and design;

·      Reuse of materials, thus avoiding disposal (generally with only limited reprocessing);

·      Recovery and recycling, thus avoiding disposal (although reprocessing may be required); and

·      Treatment and disposal, according to relevant laws, guidelines and good practice.

6.6.5             The suitability (or otherwise) of material for reuse on site shall be detailed in the WMP. If, for any reason, the recommendations cannot be implemented, full justification should be given in the WMP for approval by Architect/Engineer/Supervising Officer according to ETWB TC(W) No. 19/2005.

Training

6.6.6             To facilitate adoption of the best-practice philosophy, training shall be provided to all personnel working on site. The training shall promote the concept of general site cleanliness and clearly explain the appropriate waste management procedures defined in the WMP. Overall, the training should encourage all workers to reduce, reuse and recycle wastes.

Records of Waste and Management

6.6.7             During construction, the WMP should be kept up-to-date on a monthly basis with records of the actual quantities of wastes generated, recycled and disposed of off-site. Quantities shall be determined by weighing each load or other methods agreed to by the Engineer’s Representative. Waste shall only be disposed of at licensed sites and the WMP should include procedures to ensure that illegal disposal of wastes does not occur. Only waste haulers authorised to collect the specific category of waste concerned should be employed and a trip ticket system shall be implemented for offsite disposal of inert C&D material and C&D waste at public fill reception facilities and landfills. Appropriate measures should be employed to minimise windblown litter and dust during transportation by either covering trucks or transporting wastes in enclosed containers.

Site Planning

6.6.8             Work site(s) shall be arranged and managed to facilitate the proper management of wastes and materials. The WMP shall include plans indicating specific areas designated for the storage of particular types of waste, reusable and recyclable materials as well as areas and management proposals for any stockpiling areas. Waste storage areas should be well maintained and cleaned regularly. Specific provisions for different types of material are outlined below. In general, these areas should be designed to avoid cross contamination of materials as well as pollution of the surrounding environment.

Inert Construction and Demolition (C&D) Material / C&D Waste

6.6.9             In order to minimise the impact resulting from collection and transportation of inert C&D material for off-site disposal, it is recommended that the excavated fill material should be reused on site as backfill material as far as possible. Also, careful design, planning and good site management should be maintained in order to minimise over ordering and generation of surplus materials such as concrete, mortars and cement grouts. The design of formwork should maximise the use of standard wooden panels so that high reuse levels can be achieved. Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse.

6.6.10         Inert C&D material should be segregated on site into different waste and material types. This will increase the feasibility of certain components of the waste stream being recycled by specialised contractors. The Contractor should clearly demonstrate in the WMP how he intends to maximise the reuse of inert C&D material on-site. Where reuse of materials on site is not feasible, the Contractor should explore opportunities for recycling materials off-site. Inert C&D material shall be reused on site as much as possible or recycled.

6.6.11         Potential opportunities for recycling and reuse of inert C&D material from the Project include:

·      Milling wastes arising from regrading of the existing pavement could be recycled on site and reused as either road-base in the new carriageways or fill for new embankments;

·      Existing marginal roadside barriers comprise pre-cast units, which may be possible to be reused in the following widening works; and

·      Existing bridge parapets comprise aluminium post and railings, which have a recyclable value and could be sold for reconditioning or reused for scrap metal.

6.6.12         Any stockpile should be sited away from existing watercourses and suitably covered to prevent wind erosion and impacts on air and water quality. Measures for impacts on air and water quality are described in Sections 3 and 5 in this report, respectively.

6.6.13         C&D waste which cannot be reused or recycled should be segregated and stored in different containers or skips from the inert C&D material and should be disposed of to landfill.

Marine Sediment

6.6.14         In order to minimise the exposure to contaminated materials, workers should, when necessary, wear appropriate personal protective equipment (PPE) when handling contaminated sediments. Adequate washing and cleaning facilities should also be provided on site.

6.6.15         In order to minimise any potential adverse impacts arising from the handling, treatment and reuse of the marine sediment, it should be excavated, transported and processed properly. Stockpiling of contaminated sediments should be avoided as far as possible. If temporary stockpiling of contaminated sediments is necessary, the excavated sediment should be covered by tarpaulin and the area should be placed within earth bunds or sand bags to prevent leachate from entering the ground, nearby drains and surrounding water bodies. The stockpiling areas should be completely paved or covered by linings in order to avoid contamination to underlying soil or groundwater. Separate and clearly defined areas should be provided for stockpiling of contaminated and uncontaminated materials. Leachate, if any, should be collected and discharged according to the WPCO.

6.6.16         The approved Sediment Assessment Plan and Sediment Assessment Report with Remediation Plan shall be incorporated to the WMP.

Chemical Waste

6.6.17         Chemical waste should be handled in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes as follows. Containers used for the storage of chemical wastes should:

·      Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;

·      Have a capacity of less than 450L unless the specifications have been approved by the EPD; and

·      Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C).

6.6.18         The storage area for chemical wastes should:

·      Be clearly labelled and used solely for the storage of chemical waste;

·      Be enclosed on at least 3 sides;

·      Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

·      Have adequate ventilation;

·      Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and

·      Be arranged so that incompatible materials are adequately separated.

6.6.19         The Contractor shall register with EPD as a Chemical Waste Producer. Waste oils and other chemical wastes as defined in the CAP 354C will require disposal by appropriate means and could require pre-notification to EPD prior to disposal. Appropriate means include disposal:

·      Via a licensed waste collector; and

·      To a facility licensed to receive chemical waste, such as the CWTC which also offers a chemical waste collection service and can supply the necessary storage containers; or

General Refuse

6.6.20         General refuse generated on-site should be stored in enclosed bins or compaction units separate from construction and chemical wastes. A reputable waste collector should be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily or every second day basis to minimise odour, pest and litter impacts. The burning of refuse on construction sites is prohibited by law.

6.6.21         General refuse is generated largely by food service activities on site, so reusable rather than disposable dishware should be used if feasible. Aluminium cans are often recovered from the waste stream by individual collectors if they are segregated or easily accessible. Therefore separate, labelled bins for their deposit should be provided if feasible.

6.6.22         Office waste can be reduced through recycling of paper if volume is large enough to warrant collection. Participation in a local collection scheme should be considered if one is available.

6.7                   Evaluation of Residual Impacts

6.7.1             The Project is likely to result in the generation of a variety of wastes and require management and disposal of inert C&D material and C&D waste, marine sediment, chemical waste and general refuse. Provided that the wastes are managed by implementing all the recommended measures, no unacceptable adverse environmental impacts arising from the handling, storage, transportation or disposal of the wastes generated by the Project would be envisaged.

6.8                   Environmental Monitoring and Audit Requirements

6.8.1             It is the Contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored, and disposed of in accordance with good waste management practices and relevant regulations and requirements. The mitigation measures recommended in Section 6.6 should form a basis of the WMP to be developed by the Contractor in the construction phase of the Project.

6.9                   Land Contamination

Methodology

6.9.1             The objective of this assessment is to identify and evaluate the potential soil contamination along the Project Site and if required, develop an assessment plan to determine the extent of any contamination present. In order to achieve this, the following has been undertaken:

·      Review of the current and historical land use of the site to evaluate whether there is the potential for any soil or groundwater contamination to have occurred;

·      Assess any potential environmental impacts arising as a result of land contamination or during future use of the land; and

·      Site visits to confirm land uses and likely impacts of any land contamination identified.

6.9.2             Site visits were undertaken on the 7 and 28 November 2013 along the road alignment to confirm land uses and identify potential land contamination sources.

Review of Aerial Photographs and Historic Land Uses

6.9.3             The site history information of the Study Area was obtained by reviewing the relevant aerial photographs. The aerial photographs are shown in Appendix 6-2. Table 6-4 summarises the findings of the aerial photographs reviewed.

 

Table 6-4      Findings of Aerial Photographs Reviewed for Project Site

Year

Notes

1963

The study area comprises natural hillside, anthropogenic terrace and sea.

1973

Extensive reclamation has taken place at the study area. Kwai Chung Road has been constructed

1982

Tsuen Wan Road and flyovers were constructed. The Tsuen Wan Line was constructed. The land between the elevated section of Tsuen Wan Road and the Tsuen Wan Line has been cleared.

1993

Container Port Road South was constructed. Temporary buildings were constructed in 1983 and removed in 1989 at the area between the elevated road and Tsuen Wan Line.

2003

The area between the elevated road and MTR lines was cleared in 1994 for development. A hard surface was provided in 1999. Slip roads were constructed on Kwai Chung Road (1995-1996). A Public Works Regional Laboratory of Civil Engineering and Development Department was built along the Container Port Road South.

2008

No further significant changes since 1999.

6.9.4             Various HKSAR Government Departments, listed below, were approached on the historical land use, chemical storage, and accident records for further identify the potential land contamination of the Site.

·      Lands Department (LandsD) - To further understand the historical land use and retrieve the past records of land contamination issues of the Premise, information request letter was sent to LandsD on 31 October 2013. Written reply from LandsD on 3 December 2013 stated that no contamination was recorded. The letters are present in Appendix 6-3.

·      Environmental Protection Department (EPD) - Letters were sent to EPD to identify the historical records of chemical spillage / leakage as well as the records of registered chemical waste producer, respectively, on 31 October 2013. Written reply from EPD on 22 November 2013 stated that there was no record for chemical spillage / leakage accident of the Site. There was one registered chemical waste producer near the proposed flyover and widening in Tsuen Wan Road. The letters are present in Appendix 6-3. Table 6-5 shows the list of registered chemical producer in the nearby areas.

·      Fire Services Department (FSD) - To identity the registration records of Dangerous Goods and the historical records of dangerous goods spillage / leakage, letter was sent to FSD on 31 October 2013. Written reply from FSD on 15 November 2013 reported there are neither records of dangerous goods licence nor incident of spillage / leakage of dangerous goods at the Site. The letters are present in Appendix 6-3.

Table 6-5       List of Registered Chemical Waste Producers

Waste Producers

Address

Nature of Business

Major Chemical Waste Type

Director of Civil Engineering

(Public Works Regional Laboratory of Tsuen Wan)

Container Port Road South, Kwai Chung, N.T.

Material Testing

Methylene Chloride

Description of Existing Environment

6.9.5             From the detailed walk over site survey on 7 November 2013 and from historical records, the Public Works Regional Laboratory of Tsuen Wan (Laboratory) has been identified as a chemical waste producer, which is a potential contaminated land use within the project boundary. Figure 6-2 shows the site boundary of the Laboratory.  Details are summarised in Table 6-6. According to Figure 6-2, although a part of the Laboratory Site is out of the project boundary currently, the whole Laboratory Site is considered in this review as it is possible for the whole Laboratory Site to be occupied as a single land lot during construction as works area.

6.9.6             Another site walk over the Laboratory Site was conducted on 28 November 2013.The Laboratory Site is located at Container Port Road South and under Tsuen Wan Road. There were three nos. of single storey buildings within Laboratory Site. The whole site is concrete paved. There are storage of fresh and waste Methylene Chloride in the Dangerous Goods Store and Chemical Waste Storage Room, respectively. Stain was found on the paved ground at the entrance of the Chemical Waste Storage Room. There is a transformer on the Laboratory Site but no emergency power generator was found. The Site Walkover Checklist and Photographs are shown in Appendix 6-4.

Table 6-6       Potentially Contaminative Land Use along the Site

No

Potentially Contaminative Land Use

Location

1

Public Works Regional Laboratory of Tsuen Wan

Container Port Road South

Implications for Road Development

6.9.7             The Laboratory Site is currently allocated to CGE/Standards & Testing, CEDD. As stated in Section 2.9.9, temporary occupation of the Laboratory Site is required during construction phase for this Project. The existing laboratory buildings will be demolished and the Laboratory Site will be reinstated at the expiry of the allocation. The current allocation period of the land is up to 23 June 2016 and its extension will be subjected to the commencement of the construction work for this Project. The implementation of the construction under this Project will tentatively commence in year 2017/2018. According to a memo between LandsD and the allocatee of the Laboratory Site (i.e. CGE/Standards & Testing, CEDD) dated on 7 June 2012, the allocatee shall ensure the Laboratory Site is free from contamination and in event of land contamination found on the Laboratory Site, the allocatee will be responsible to carry out the remediation works to remove all the contaminants from the Laboratory Site at the expiry of the allocation. The memo is presented in Appendix 6-5.    

Assessment of Land Contamination Impacts

6.9.8             The Laboratory has been identified as a chemical waste producer, which is a potential contaminated land use within the project boundary. The allocatee shall be responsible for the land contamination assessment of the Laboratory Site and ensure the Laboratory Site is free from contamination at the expiry of allocation and therefore any land contamination concern arising from past activities would have been remediated prior to the construction of the works.

6.9.9             With implementation of good site practice, land contamination at the Site arising from construction and operation phases of the Project as road upgrading works is not envisaged.

6.9.10         Thus no adverse environmental impacts on land contamination for the Project are anticipated.

6.10               Conclusion

6.10.1         The Project is likely to result in the generation of a variety of wastes and require the management and disposal of inert C&D material, C&D waste, marine sediment, chemical waste and general refuse during construction phase. It is not expected for waste generation during operation phase. Provided that the wastes are managed using approved methods described above, no unacceptable adverse environmental impacts will be envisaged.

6.10.2         The mitigation measures recommended in this Chapter should be incorporated into a WMP and applied through the contract documents to ensure that environmental nuisance does not arise.

6.10.3         The Laboratory has been identified as a chemical waste producer, which is a potential contaminated land use within the project boundary. The allocatee shall be responsible for the land contamination assessment of the Laboratory Site and ensure the Laboratory Site is free from contamination at the expiry of allocation and therefore any land contamination concern arising from past activities would have been remediated prior to the construction of the works.

6.10.4         With implementation of good site practice, land contamination at the Site arising from construction and operation phases of the Project as road upgrading works is not envisaged.

6.10.5         No adverse environmental impacts on land contamination for the Project are anticipated.

6.11               References

[1]     Ove Arup & Partners Hong Kong Ltd (2008). Agreement No. FM 01/2007 – Review of Options for Management of Contaminated Sediment in Hong Kong. Final Report (Rev A). August 2008.

[2]     Environment Canada (EC). (1995) Demonstration Project  of a Physico-Chemical Treatment Process  of Contaminated Sediment at the Port of Sorel. St. Lawrence Technologies - Contaminated Sediment. Ministry of the Environment. EM 1-17/23- 1995.

[3]     Federal Remediation Technologies Roundtable (FRTR). (2001) Abstract of Remediation Case Studies. Member Agencies of the Federal Remediation Technologies Roundtable, Volume 5, EPA 542-R-01-008, May 2001.

 [4]     Francingues, N. R., and Thompson, D. W. (2000) Innovative Dredged Sediment Decontamination and Treatment Technologies. ERDC TN-DOER-T2, DOER Technical Report, Engineer Research and Development Center, U.S. Army Corps of Engineers.

[5]     Michael R. Palermo (1997), “Integrated Sediment Decontamination for the New York/New Jersey Harbor”, Proceedings Cincinnati, OH May 13-14, 1997, National Conference on Management and Treatment of Contaminated Sediments, United States Environmental Protection Agency, Office of Research and Development Washington, DC.

[6]     EPD, Environmental Impact Assessment on South Island Line (East), 2014, Available from: http://www.epd.gov.hk/eia/english/alpha/aspd_542.html