Flyover from Kwai Tsing Interchange Upramp to Kwai
Chung Road
Environmental
Monitoring and Audit Manual
June 2015
Table of Contents
1.2 Project Scope and Programme
2.4 Laboratory Measurement /
Analysis
2.8 Event and Action Plan for Air
Quality
3.2 General Monitoring Requirement
and Equipment
3.3 Noise Parameters for
Construction Noise
3.4 Monitoring Locations for
Construction Noise
3.5 Baseline Monitoring for
Construction Noise
3.6 Impact Monitoring for
Construction Noise
3.8 Construction Noise Mitigation
Measures
3.9 Parameters for Operational
Traffic Noise
3.10 Monitoring Locations for
Operational Traffic Noise
3.12 Operational Traffic Noise
Impact Monitoring
3.13 Event and Action Plan for
Traffic Noise
3.14 Noise Mitigation Measures for
Traffic Noise
5. Waste Management Implication
and Land Contamination
6. LanDSCAPE and VISUAL IMPACTS
9.2 Compliance with Legal and
Contractual Requirements
10.2 Baseline Monitoring Report
10.5 Interim Notifications of
Environmental Exceedance
LIST
OF TABLES
Table 2‑1 Proposed Construction Dust Monitoring
Locations
Table
2‑2 Summary of Construction
Dust Monitoring Programme
Table
2‑3 Summary of Construction
Dust Monitoring Programme
Table
2‑4 Action and Limit (A/L)
Levels for Construction Dust Impact Monitoring
Table
2‑5 Event and Action Plan
for Construction Dust Monitoring
Table
3‑1 Proposed Construction
Noise Monitoring Locations
Table
3‑2 Action and Limit Levels
for Construction Noise
Table
3‑3 Event / Action Plan for
Construction Noise
Table
3‑4 Examples of “Quiet” PME
and Alternative Plants
Table
3‑5 Traffic Noise Monitoring
Locations
LIST
OF FIGURES
Figure 1.1 Proposed
Road Works
Figure
1.2 Project Organisation and
Lines of Communication for Environmental Works
Figure 2.1 Construction
Dust Monitoring Locations
Figure 3.1 Construction
Noise Monitoring Locations
Figure 3.2 Operational
Noise Monitoring Locations
Figure 3.3A Extent
of Proposed Noise Mitigation Measures
Figure 3.3B Section
Views of Proposed Vertical and Cantilevered Barriers
APPENDICES
Appendix
1-1 Tentative Construction
Programme
Appendix
1-2 Implementation Schedule of
Recommended Mitigation Measures
Appendix
2-1 Sample Data Record Sheet for
TSP Monitoring
Appendix
3-1 Sample
Data Record Sheet for Construction Noise Monitoring
Appendix
3-2 Sample Data Record Sheet for
Operational Traffic Noise Monitoring
Appendix
9-1 Flow Chart of Complaint
Response Procedures
Appendix
10-1 Sample Template for Interim Notification
· Provision of an additional traffic lane for the southbound traffic between KT I/C upramp and KCR;
· Modification of existing slip roads; and
· Associated environmental mitigation measures, utility diversion, street lighting, traffic aids, traffic and control surveillance, drainage works, landscaping works and other related works.
· Existing footbridge NF303 is to be demolished and be re-provided;
· Existing Public Works Regional Laboratory will be affected;
· Existing drainage reserve zone positioned alongside TWR will be affected;
· Existing bus stop outside subway NS10A is to be relocated, and
· Minor modification to the existing Kwai Chung Road involves removal of the existing planter, breaking and reinstating Kwai Chung Road with the new road marking.
· The responsibilities of the Contractor, Engineer, Environmental Team (ET), and the Independent Environmental Checker (IEC) with respect to the EM&A requirements during the course of the Project;
· The requirements with respect to the construction schedule and the EM&A programme to track the varying environmental impacts;
· The details of methodologies to be adopted, including all field laboratories and analytical procedures, and details on the quality assurance and quality control (QA/QC) programme;
· The rationale on which the environmental monitoring data will be evaluated and interpreted;
· The definition of Action and Limit levels;
· The establishment of Event and Action Plans;
· The requirements for reviewing the pollution sources and working procedures required in the event of the non-compliance with environmental criteria and complaints;
· The requirements for the presentation of EM&A data and appropriate reporting procedures; and
· The requirements for reviewing the EIA predictions and effectiveness of mitigation measures/environmental management systems and the EM&A programme.
· To supervise the Contractor’s activities and ensure the requirements in the EM&A Manual to be fully complied with;
· To inform the Contractor when action is required to reduce the environmental impacts in accordance with the Event and Action Plans;
· To lead the regular site inspections and audits attended by the Contractor and Environmental Team (ET); and
· To adhere to the procedures for carrying out the complaint investigation.
· To implement the recommendations and requirements of the EIA study;
· To provide assistance to the ET in carrying out the relevant environmental monitoring;
· To submit the proposal of mitigation measures in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans;
· To implement the mitigation measures to reduce the environmental impacts where the Action and Limit levels are exceeded until the events are resolved; and
· To adhere to the procedures for carrying out the complaint investigation.
· To monitor various environmental parameters as required in the EM&A Manual;
· To carry out regular site inspections to investigate and audit the Contractor’s site practices, equipment and work methodologies with respect to the pollution control and environmental mitigation, and anticipate the environmental issues for the proactive and practicable action before problems arising;
· To analyse the EM&A data, review the success of EM&A programme to confirm the adequacy of mitigation measures implemented, and the validity of the EIA predictions and to identify any adverse environmental impacts arising and report the EM&A results to the Independent Environmental Checker (IEC), Contractor, and Engineer;
· To prepare the reports of environmental monitoring data and site environmental conditions; and
· To review the proposals of mitigation measures by the Contractor in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans.
· To adhere to the procedures for carrying out the complaint investigation.
· To review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;
· To validate and confirm the accuracy of the monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;
· To carry out random sample checking and audit of the environmental monitoring data and sampling procedures, etc.;
· To conduct random site inspections during construction;
· To audit the recommendations and requirements of the EIA study against the status of the implementation of environmental protection measures on-site;
· To review the effectiveness of the environmental mitigation complaints and the effectiveness of corrective measures;
· On as-needed basis, to verify and certify the environmental acceptability of the EP holder’s construction methodology (both temporary and permanent works), relevant design plans and submissions under the EP;
· To verify the investigation results of the environmental complaints and the effectiveness of corrective measures;
· To verify the EM&A reports that have been certified by the ET Leader; and
· To provide feedback of the audit results to the ET/EP holder according to the Event and Action Plans in the EM&A manual.
· To adhere to the procedures for carrying out the complaint investigation.
· 0.6-1.7 m3/min (20-60 SCFM) adjustable flow range;
· equipped with a timing/control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2 (63 in2);
· flow control accuracy: ± 2.5% deviation over 24-hr sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hr period.
· the wind sensors shall be installed on masts at an elevated level 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;
· the wind data shall be captured by a data logger. The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;
· the wind data monitoring equipment shall be re-calibrated at least once every six months; and
· wind direction shall be divided into 16 sectors of 22.5 degrees each.
Table 2‑1 Proposed Construction Dust Monitoring Locations
Monitoring Location ID |
Description |
Land Uses |
AMC01 |
Lai King Catholic Secondary School |
Educational Institution |
AMC02 |
Fung King House |
Residential |
AMC03 |
HKEAA-Lai King Assessment Centre |
Educational Institution |
· at the site boundary or such locations close to the major dust emission source;
· close to the sensitive receptors; and
· take into account the prevailing meteorological conditions.
· a horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
· no two samplers shall be placed less than 2 metre apart;
· the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
· a minimum of 2 metre separation from any supporting structure, measured horizontally is required;
· no furnace or incinerator flue is nearby;
· airflow around the sampler is unrestricted;
· the sampler is more than 20 metres from the dripline;
· any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;
· permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is needed to operate the samplers.
Table 2‑2 Summary of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Parameter |
Frequency |
Baseline Monitoring |
Consecutive days of at least 2 weeks before
commencement of construction works |
1 hour TSP |
3 times per
day |
Continuous
24-hour TSP |
Daily |
Table 2‑3 Summary of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Parameter |
Frequency |
Impact Monitoring |
Throughout the construction phase |
1 hour TSP |
At least 3
times in every 6 days when the highest dust impact are likely to occur or
when one documented complaint is received |
Continuous 24-hour
TSP |
Once per 6
days |
Parameter |
Action Level* |
Limit
Level |
TSP (24-hour average) |
BL £ 200 μgm-3, AL = (BL x 1.3
+ LL)/2 BL > 200 μgm-3, AL = LL |
260 μg/m3 |
TSP
(1-hour average) |
BL £ 384 μgm-3, AL = (BL x 1.3
+ LL)/2 BL > 384 μgm-3, AL = LL |
500 μg/m3 |
* BL = Baseline Level; AL =
Action level; LL = Limit level
Table 2‑5 Event and Action Plan for Construction Dust Monitoring
EVENT |
ACTION |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
|
|
|
|
1. Exceedance
for one sample |
1. Identify
sources, investigate the causes of complaint and propose remedial measures. 2. Inform
IEC and ER. 3. Repeat
measurement to confirm finding;. 4. Increase
monitoring frequency. |
1. Check
monitoring data submitted by the ET. 2. Check
the Contractor’s working methods. |
1. Notify
the Contractor. |
1. Rectify
any unacceptable practices. 2. Amend
working methods agreed with the ER as appropriate. |
2. Exceedance
for two or more consecutive samples |
1. Identify
sources. 2. Inform
the IEC and ER. 3. Advise
the ER on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings. 5. Increase
monitoring frequency to daily. 6. Discuss
with the IEC, ER and Contractor on remedial action required. 7. If
exceedance continues, arrange meeting with the IEC, Contractor and ER. 8. If
exceedance stops, cease additional monitoring. |
1. Check monitoring
data submitted by the ET. 2. Check
the Contractor’s working methods. 3. Discuss
with the ET, ER and Contractor on possible remedial measures if required. 4. Advise
the ER on the effectiveness of proposed remedial measures if required. |
1. Notify
the Contractor. 2. Ensure
remedial measures properly implemented. |
1. Submit
proposals for remedial action to the ER within 3 working days of
notification. 2. Implement
the agreed proposals. 3. Amend
proposal as appropriate. |
Limit Level |
|
|
|
|
1. Exceedance
for one sample |
1. Identify
sources, investigate causes of exceedance and proposed remedial measures. 2. Inform
the IEC, ER, and Contractor. 3. Repeat
measurement to confirm finding. 4. Increase
monitoring frequency to daily. 5. Assess
effectiveness of the Contractor’s remedial action and keep the IEC and ER
informed of the results. |
1. Check
monitoring data submitted by the ET. 2. Check
the Contractor’s working methods. 3. Discuss
with the ET, ER and Contractor on possible remedial measures. 4. Advise
the ER and ET on the effectiveness of the proposed remedial measures. 5. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of the notification of exceedance in writing. 2. Notify
the Contractor. 3. Ensure
remedial measures are properly implemented. |
1. Take
immediate action to avoid further exceedance. 2. Submit
proposals for remedial action to the ER and copy to the ET and IEC within 3
working days of notification. 3. Implement
the agreed proposals. 4. Amend
proposal as appropriate. |
2. Exceedance
for two or more consecutive samples |
1. Notify
the IEC, ER and Contractor. 2. Identify
sources. 3. Repeat
measurements to confirm findings. 4. Increase
monitoring frequency to daily. 5. Carry
out analysis of the Contractor’s working procedures with the ER to determine
the possible mitigation to be implemented. 6. Arrange
meeting with the IEC and ER to discuss the remedial action to be taken. 7. Assess
the effectiveness of the Contractor’s remedial action and keep the IEC, EPD
and ER informed of the results. 8. If
exceedance stops, cease additional monitoring. |
1. Discuss
amongst the ER, ET and Contractor on the potential remedial action. 2. Review
the Contractor’s remedial action whenever necessary to assure their
effectiveness and advise the ER and ET accordingly. 3. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of the notification of exceedance in writing. 2. Notify
the Contractor. 3. In
consultation with the IEC and ET, agree with the Contractor on the remedial
measures to be implemented. 4. Ensure
remedial measures are properly implemented. 5. If
exceedance continues, consider what portion of works is responsible and
instruct the Contractor to stop that portion of works until the exceedance is
abated. |
1. Take
immediate action to avoid further exceedance. 2. Submit
proposals for remedial action to the ER and copy to the IEC and ET within 3
working days of notification. 3. Implement
the agreed proposals. 4. Resubmit
proposals if problems still not under control. 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
·
Every
temporary access road shall be paved with concrete, bituminous materials,
hardcores or metal plates, and kept clear of dusty materials; or sprayed with
water or a dust suppression chemical so as to maintain the entire road surface
wet.
·
Any
stockpile of dusty materials shall be covered entirely by impervious sheeting,
placed in an area sheltered on the top and the 3 sides, or sprayed with water
or a dust suppression chemical so as to maintain the entire surface wet. The
materials should be removed or backfilled or reinstated where practicable
within 24 hours of the excavation or unloading.
·
All
dusty materials shall be sprayed with water or a dust suppression chemical
immediately prior to any loading, unloading or transfer operation so as to
maintain the dusty materials wet.
·
Vehicles
used for transporting dusty materials should be covered with tarpaulin or
similar material, and the cover should extend over the edges of the sides and
tailboards.
·
Vehicle
wheel washing facilities should be provided at each construction site exit.
Immediately before leaving a construction site, every vehicle shall be washed
to remove any dusty materials from its body and wheels.
·
Where
a vehicle leaving a construction site is carrying a load of dusty materials,
the load shall be covered entirely by clean impervious sheeting to ensure that
the dusty materials do not leak from the vehicle.
·
The
speed of vehicles on unpaved road within the site should be controlled to about
10 km/hr.
·
Routing
of vehicles and positioning of construction plants should be arranged at maximum
possible distances from the sensitive receivers.
·
Every
stock of more than 20 bags of cement and dry pulverized fuel ash (PFA) shall be
covered entirely by impervious sheeting or placed in an area sheltered on the
top and the 3 sides.
·
Loading,
unloading, transfer, handling or storage of large amount of cement or dry PFA
should be carried out in a totally enclosed system or facility, and any vent or
exhaust should be fitted with the an
effective fabric filter or equivalent air pollution control system.
·
Exposed
earth shall be properly treated by compaction, turfing, hydroseeding,
vegetation planting or sealing with latex, vinyl, bitumen, shotcrete or other
suitable surface stabilizer within 6 months after the last construction
activity on the construction site or part of the construction site where the
exposed earth lies.
· Investigate the problems and causes;
· Discuss a remedial and corrective proposal with the Engineer and ET;
· Take action according to the action notes agreed with the Engineer;
· Implement the remedial and corrective action immediately;
· Re-Inspect the site conditions upon the completion of the remedial and corrective action; and
· Record
the event.
· Lingnan Dr. Chung Wing Kong Memorial Secondary School
· Lai King Catholic Secondary School
· Fung King House
· Ming King House
· HKEAA-Lai King Assessment Centre
Table 3‑1 Proposed Construction Noise Monitoring Locations
Monitoring Location ID |
Description |
Land Uses |
NMC01 |
Lai King Catholic Secondary School |
Educational Institution |
NMC02 |
Fung King House |
Residential |
NMC03 |
HKEAA-Lai King Assessment Centre |
Educational Institution |
· At locations close to the major site activities which are likely to have noise impacts;
· Close to the most affected existing noise sensitive receivers; and
· For monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance to the occupants during monitoring.
· One set of measurements between 0700-1900 hours on normal weekdays (six consecutive Leq/5min readings);
· One set of measurements between 1900-2300 hours;
· One set of measurements between 2300-0700 hours of next day; and
· One set of measurements between 0700-2300 hours on holidays.
Table 3‑2 Action and Limit Levels for Construction Noise
Time Period |
Action |
Limit |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75* dB(A) |
0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days |
60/65/70** dB(A) |
|
2300-0700 hrs of all days |
45/50/55** dB(A) |
Notes:
Construction noise during restricted hours is under the control of Noise Control Ordinance.
* reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.
** to be selected based on Area Sensitivity Rating.
Table 3‑3 Event
/ Action Plan for Construction Noise
EVENT |
ACTION |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level exceeded |
1. Notify ER, IEC and Contractor; 2. Carry out investigation; 3. Report the results of investigation to the IEC, ER and Contractor; 4. Discuss with the IEC and Contractor on remedial measures required; 5. Increase monitor frequency to check mitigation effectiveness; |
1. Review the investigation results submitted by the ET; 2. Review the proposed remedial measures by the Contractor and advise the ER accordingly; 3. Advise the ER on the effectiveness of the proposed remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the Contractor on the remedial measures to be implemented; 4. Supervise the implementation of remedial measures. |
1. Submit noise mitigation proposals to ET Leader / ER; 2. Implement noise mitigation proposals. |
Limit Level exceeded |
1. Inform IEC, ER, Contractor and EPD; 2. Repeat measurements to confirm findings; 3. Increase monitoring frequency; 4. Identify source and investigate the cause of exceedance; 5. Carry out analysis of Contractor’s working procedures; 6. Discuss with the IEC, Contractor and ER on remedial measures required; 7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the potential remedial actions; 2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the Contractor on the remedial measures to be implemented; 4. Supervise the implementation of remedial measures; 5. If exceedance continues, consider stopping the Contractor to continue working on that portion of work which causes the exceedance until the exceedance is abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC and ER within 3 working days of notification; 3. Implement the agreed proposals; 4. Submit further proposal if problem still not under control; 5. Stop the relevant portion of works as instructed by the ER until the exceedance is abated. |
· selection and optimization of construction programmes, avoidance of parallel operation of noisy PME, and/or reduction in number and/or the on-time percentage of PME during noise sensitive periods such as school examination period, and avoidance of noisy construction activities during school examination period by liaising with the school representatives;
· use of Quality Powered Mechanical Equipment (QPME) and working methods;
· use of temporary at-source noise mitigation measures such as noise barriers, noise fabric, noise enclosures, noise jacket and mufflers; and
· use of good site practice to limit noise emission from construction site.
Table 3‑4 Examples of “Quiet” PME and Alternative Plants
Identification Code in GW-TM |
Descriptions of PME |
SWL in GW-TM, dB(A) |
QPME example on QPME list [1] |
SWL of QPME, dB(A) |
CNP 004 |
Asphalt Paver |
109 |
EPD-01226 (VOLVO ABG5770) |
104 |
CNP 081 |
Excavator,
Wheeled/Tracked |
112 |
EPD-01896 (HYUNDAI R80CR-9) |
98 |
CNP 048 |
Mobile Crane |
112 |
EPD-01516 (KOBELCO CKS900) |
101 |
CNP 170 |
Poker, vibratory, hand held |
113 |
Poker, vibratory, hand held (electric) |
102 |
CNP 185 |
Road Roller |
108 |
EPD-01806 (KANTO-TK KV25DS) |
95 |
Note:
[1] QPME list available on the EPD website
· use of well-maintained and regularly-serviced plant during the works;
· plant operating on intermittent basis should be turned off or throttled down when not in active use;
· plant that is known to emit noise strongly in one direction should be orientated to face away from the NSRs;
· silencers, mufflers and enclosures for plant should be used where possible and maintained adequately throughout the works;
· where possible fixed plants should be sited away from NSRs; and
· stockpiles of excavated materials and other structures such as site buildings should be used effectively to screen noise from the works.
Table 3‑5 Traffic Noise Monitoring Locations
Monitoring Location No. |
Description |
Land Uses |
NMT01 |
Lai King Catholic Secondary School |
Educational Institute |
NMT02 |
Fung King House |
Residential |
· At locations close to the major site activities which are likely to have noise impacts;
· Close to the noise sensitive receivers; and
· For monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance to the occupants during monitoring.
· One set of measurements at the morning traffic peak hour on normal weekdays;
· One set of measurements at the evening traffic peak hour on normal weekdays;
· A concurrent census of traffic flow and percentage heavy vehicle shall be conducted for the road and the existing road network in the vicinity of each measuring point;
· Average vehicle speed estimated for Project road and the existing road network in the vicinity of each measuring points; and
· The two sets of monitoring data should be obtained within the first year of operation.
Table 3‑6 Summary of Direct Noise Mitigation Measures for Road Traffic Noise from Project Road in the EIA Report
ID |
Description |
Length (m) |
Location |
A |
5.5m high with 2.5m cantilevered barrier at 45° |
85 |
Bridge H Southbound |
B |
5.5m vertical barrier |
20 |
Bridge H Southbound |
C |
5.5m high with 2.5m cantilevered barrier at 45° |
230 |
Bridge H Southbound |
D |
5.5m high with 3.5m cantilevered barrier at 45° |
45 |
Bridge H Southbound |
- |
Low Noise Road Surfacing [1] |
- |
Bridge G & H (i.e. All Project Roads) |
Notes:
[1] Low noise road surfacing is applied on highways with speed 70kph or above in general. Such mitigation measure has been included in both unmitigated scenario and mitigated scenario in road traffic noise impact analysis.
· Investigate the problems and causes;
· Issue action notes to the Contractor who is responsible for the works;
· Implement the remedial and corrective action immediately;
· Re-inspect the site conditions upon the completion of the remedial and corrective action; and
· Record the event and discuss with the Contractor for preventive actions.
· The Contractor should notify the ER, ET and IEC;
· The ER, ET and IEC should identify the sources of pollution and recommend and agree the appropriate mitigation measures for the Contractor;
· The ER and ET should check the implementation status of the agreed mitigation measures by the Contractor;
· The ET should increase the monitoring frequency until the effluent quality is in compliance with the requirements of the discharge license; and
· The ET should record the non-compliances and propose preventive measures.
· The Contractor should be requested to submit an outline WMP prior to the commencement of construction work, in accordance with the ETWB TC(W) No.19/2005 so as to provide an overall framework of Waste Management and Reduction. The WMP should include:
- Waste management policy;
- Record of generated waste;
- Waste reduction target;
- Waste reduction programme;
- Role and responsibility of waste management team;
- Benefit of waste management;
- Analysis of waste materials;
- Reuse, recycling and disposal plans;
- Transportation process of waste products; and
- Monitoring and action plan.
· The waste management hierarchy as provided in Section 6.6.4 of the EIA report and below should be strictly followed and applied in evaluating the waste management options in order to maximise the waste reduction and often reduce costs, for example, by controlling, reducing or eliminating over-ordering of construction materials. Records of quantities and locations of wastes generated, recycled and disposal should be properly documented. The hierarchy shall be as follows:
- Avoidance and minimisation, i.e. avoiding or not generating waste through changing or improving practices and design;
- Reuse of materials, thus avoiding disposal (generally with only limited reprocessing);
- Recovery and recycling, thus avoiding disposal (although reprocessing may be required); and
- Treatment and disposal, according to relevant laws, guidelines and good practice.
· A trip-ticket system should be established in accordance with DevB TC(W) No. 6/2010 and Waste Disposal (Charges for Disposal of Construction Waste) Regulation in order to monitor the disposal of inert C&D Materials at public fill reception facilities and the remaining C&D Waste to landfills, and control fly-tipping. A trip-ticket system should be included as one of the contractual requirements and implemented by the Contractor. The ER should regularly audit the effectiveness of the system.
· A recording system for the amount and locations of waste generated, recycled and disposed should be established. The Contractor should also provide proper training to workers regarding the appropriate concepts of site cleanliness and waste management procedures, e.g. waste reduction, reuse and recycling all the time.
· If chemical wastes are to be produced at the construction site, the Contractor would be required to register with the EPD as a Chemical Waste Producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste (such as explosive, flammable, oxidizing, irritant, toxic, harmful, or corrosive).
· The Contractor should use a licensed collector to transport and dispose of the chemical wastes, to either the Chemical Waste Treatment Centre at Tsing Yi, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.
· No waste should be burnt on-site. Disposal of waste at unlicensed location e.g. natural habitat should be prohibited. The Contractor should propose the final disposal sites in the EMP and WMP for approval before implementation.
· The EIA and EM&A recommendations on the environmental protection and pollution control mitigation measures;
· On-going results of the EM&A programme;
· The works progress and programme;
· Proposals of individual works methodologies (which should include the proposal of the associated pollution control measures);
· Contract specifications on environmental protection and pollution prevention control;
· The relevant environmental protection and pollution control legislation; and
· Previous site inspection findings that were undertaken by the ET and/or others.
· To log the complaints and dates of receipt onto the complaint database to be kept by the Contractor and inform the Engineer and IEC immediately;
· To investigate with the Engineer and Contractor the complaints to determine their validity, and assess whether the source of the problems is due to the construction works activities with the support of additional monitoring frequency, stations and parameters, if necessary;
· To identify the mitigation measures if the complaints are valid and due to the construction works of the Project;
· To advise the Contractor if remedial measures are required, and to agree with IEC any additional monitoring frequency, stations and parameters, where necessary, for checking the effectiveness of remedial measures;
· To review the effectiveness of the Contractor’s responses to the identified remedial measures, and the updated situation;
· To undertake the additional monitoring and audit in order to verify the situation if necessary, and oversee that the circumstances leading to the complaints would not recur;
· If the complaint is referred by the EPD, to submit interim report to the EPD on the status of the complaint investigations and follow-up action stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, within the time frame assigned by the EPD; and
· To record the details of the complaints, results of the investigations, subsequent action taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.
(i) An Executive Summary of up to half a page;
(ii) A brief description of the project background;
(iii) Drawing showing locations of the baseline monitoring stations;
(iv) Monitoring results (in both hard and diskette copies) together with the following information:
· Monitoring methodology;
· Name of laboratory and types of equipment used and calibration details;
· Monitoring parameters;
· Monitoring locations;
· Monitoring date, time, frequency and duration; and
· QA/QC results and detection limits.
(v) Details of the influencing factors, including:
· Major activities, if any, being carried out on-site during the period;
· Weather conditions during the period; and
· Other factors which might affect the monitoring results.
(vi) Determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data which should conclude if there is any significant difference between the control and impact stations for the parameters monitored, where appropriate;
(vii) Revisions for inclusion in EM&A Manual; and
(viii) Comments, recommendations and conclusions.
(i) Executive summary (1-2 pages):
· Breaches of the Action and Limit levels;
· Complaint log;
· Notification of any summons and successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Basic project information:
· The project organisation including key personnel contact names and telephone numbers;
· The construction programme;
· The management structure; and
· Works undertaken during the reporting month.
(iii) Environmental status:
· Advice on the status of the statutory environmental compliance, e.g. EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures, etc.;
· Works undertaken during the reporting month with illustrations (e.g. location of works, etc.); and
· Drawings showing the project area, environmental sensitive receivers and locations of the monitoring and control stations.
(iv) Summary of EM&A requirements:
· All monitoring parameters;
· Environmental quality performance limits (Action and Limit levels);
· Event and Action Plans;
· Environmental mitigation measures, as recommended in the EIA report; and
· Environmental requirements in contract documents.
(v) Implementation status:
· Advice on the implementation status of environmental protection and pollution control mitigation measures as recommended in the EIA report, summarised in the updated implementation schedule.
(vi) Monitoring results (in both hard and diskette copies) together with the following information:
· Monitoring methodology;
· Name of laboratory and types of equipment used and calibration details;
· Monitoring parameters;
· Monitoring locations;
· Monitoring date, time, frequency and duration; and
· Graphical plots of the monitoring parameters in the reporting month annotated against the following information:
-
Major
activities being carried out on site during the reporting period
-
Weather
conditions during the reporting period
-
Any
other factors which might affect the monitoring results
-
QA/QC
results and detection limits
(vii) The report on the non-compliance, complaints, notifications of summons and status of prosecutions:
· Records of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
· Records of all complaints received (written or verbal), including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· Records of all notifications of summons and successful prosecutions for breaches of current environmental protection/ pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· The review of the reasons for an implications of non-compliances, complaint, summons and prosecutions including review of pollution sources and working procedures; and
· Description of the actions taken in the event of non-compliances and deficiency reporting and any follow-up procedures related to the earlier non-compliances.
(viii) Others:
· A forecast of the works programme, impact predictions and monitoring schedule for the next three months;
· An account of the future key issues as reviewed from the works programme and work method statements;
· Advice on the solid and liquid waste management status;
· Comparisons of the EM&A data in the reporting month with the EIA predictions and annotate with explanation for any discrepancies; and
· Comments (e.g. the effectiveness and effectiveness and efficiency of mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions.
(i) Executive summary (1-2 pages):
· Breaches of the Action and Limit levels;
· Complaint log;
· Notifications of any summons and successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Basic project information:
· The project organisation including key personnel contact names and telephone numbers;
· The construction programme;
· The management structure; and
· Works undertaken during the reporting month.
(iii) Environmental status:
· Advice on the status of statutory environmental compliance, status of compliance with EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;
· Works undertaken during the reporting month with illustrations (such as location of works, etc.); and
· Drawing showing the project area, environmental sensitive receivers and locations of the monitoring and control stations.
(iv) Implementation status:
· Advice on the implementation status of environmental protection and pollution control/ mitigation measures as recommended in the EIA report, summarised in the updated implementation schedule.
(v) Monitoring results (in both hard and diskette copies) together with the following information:
· Monitoring methodology;
· Name of laboratory and types of equipment used and calibration details;
· Parameters monitored;
· Monitoring locations (and depth);
· Monitoring date, time, frequency and duration; and
· Graphic plots of the monitoring parameter in the month annotated against the following information:
-
Major
activities being carried out on site during the reporting period
-
Weather
conditions during the reporting period
-
Any other
factors which might affect the monitoring results
- QA/QC results and detection limits
(vi) The report on non-compliances, complaints, notifications of summons and status of prosecutions:
· Records of all non-compliance (exceedances) of the environmental quality performance limits (action and Limit levels);
· Records of all complaints received (written or verbal), including the locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· Records of all notifications of summons and successful prosecutions for breaches of current environmental protection/ pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· The review of the reasons for and implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· Descriptions of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to the earlier non-compliances.
(vii) Others:
· A forecast of the works programme, impact predictions and monitoring schedule for the next three months;
· An account of the future key issues as reviewed from the works programme and work method statements;
· Advice on the solid and liquid waste management status;
· Comparisons of the EM&A data in the reporting month with the EIA predictions and annotate with explanation for any discrepancies; and
· Comments (e.g. the effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions.
(viii) Appendices:
· Action and Limit levels;
· Graphical plots of trends of the monitored parameters at key stations over the past four reporting periods for the representative monitoring stations annotated against the following information:
- Major activities being carried out on site during the reporting period
- Weather conditions during the reporting period
- Any other factors that might affect the monitoring results
· The monitoring schedule for the present and next reporting period;
· Cumulative statistics on complaints, notifications of summons and successful prosecutions; and
· Outstanding issues and deficiencies.
(i) Completion of construction activities and insignificant environmental impacts of the remaining outstanding construction works;
(ii) Trends analysis to demonstrate the narrow down of monitoring exceedances due to construction activities and, return of ambient environmental conditions in comparison with baseline data; and
(iii) No environmental complaint and prosecution involved.
(i) Executive summary (1-2 pages);
(ii) Drawings showing the project area environmental sensitive receivers and locations of the monitoring and control stations;
(iii) The basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of works undertaken during the course of the project or past twelve months;
(iv) A brief summary of EM&A requirements including:
· Environmental mitigation measures implemented as recommended in the EIA report
· Environmental impact hypotheses tested
· Environmental quality performance limits (Action and Limit levels)
· Monitoring parameters
· Event and Action Plans
(v) A summary of the implementation status of environmental protection and pollution control/ mitigation measures, as recommended in the EIA report, summarised in the updated environmental mitigation implementation schedule;
(vi) Graphical plots and statistical analysis of the trends of the monitored parameters over the course of the project, including the post-project monitoring for all monitoring stations annotated against:
· Major activities being carried out on site during the reporting period
· Weather conditions during the reporting period
· Any other factors which might affect the monitoring results
(vii) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
(viii) A review of the reasons for and implications of non-compliances including the review of pollution sources and working procedures as appropriate;
(ix) A description of the action taken in the event of non-compliances;
(x) A summary record of all complaints received (written or verbal), liaison and consultation undertaken, action and follow-up procedures taken;
(xi) A summary record of the notifications of summons and successful prosecutions for breaches of the current environmental protection / pollution control legislation, locations and nature of the breaches, follow-up investigation taken and results;
(xii) A review of the validity of EIA predictions and identification of shortcomings in the recommendations of the EIA study;
(xiii) Comments (e.g. a review of the effectiveness and efficiency of the mitigation measures and of the performance of the environmental management system, i.e., of the overall EM&A programme); and
(xiv) Recommendations and conclusions (e.g. a review of the success of the overall EM&A programme to cost-effectively identify deterioration and to initiate prompt effective mitigation action when necessary).