Table of Contents
5.2 Relevant
Legislation and Guidelines
5.3 Description of
the Noise Environment
5.4 Potential
Sources of Impact
5.10 Environmental
Monitoring and Audit
This Section
assesses the potential noise impacts associated with the construction and
operation of the proposed desalination plant at Tseung
Kwan O Area 137 (the Project).
5.2
Relevant Legislation and Guidelines
The principal legislation relating to the control
of construction noise is the Environmental
Impact Assessment Ordinance (EIAO)
(Cap. 499). The Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO,
provides guidelines and noise criteria for evaluating noise impacts.
The Noise
Control Ordinance (Cap. 400) (NCO) also provides means to assess
construction noise impacts. Various
Technical Memoranda (TMs), which stipulate control approaches and criteria,
have been issued under the NCO. The
following TMs are applicable to the control of noise impacts from construction
activities:
·
Technical Memorandum on Noise from Construction
Work other than Percussive Piling (GW-TM); and
·
Technical Memorandum on Noise from Construction
Work in Designated Areas (DA-TM).
General Construction Works
Under the EIAO,
potential noise impact arising from general construction works during normal
working hours (ie 07:00 to 19:00 hrs on any day not
being a Sunday or public holiday) at the openable windows of buildings, which
rely on opened windows for ventilation, is to be assessed in accordance with
the noise criteria specified in the EIAO-TM. The EIAO-TM
noise standards are presented in Table 5.2a.
Table 5.2a EIAO-TM
Day-time Construction Noise Standards (Leq,
30 min dB(A))
Use |
Noise Standard (dB(A)) |
Domestic Premises |
75 |
Educational Institutions (normal periods) Educational Institutions (during examination
periods) |
70 65 |
Notes: (1)
The above standards apply to uses which reply on opened windows for ventilation. (2)
The above standards shall be viewed as the maximum permissible noise
levels assessed at 1m from the external façade. |
When assessing a
Construction Noise Permit (CNP) application for the use of Powered Mechanical
Equipment (PME) during the restricted hours, the Noise Control Authority will
compare the Acceptable Noise Levels (ANLs), as promulgated in GW-TM, and
the Corrected Noise Levels (CNLs) (ie after
accounting for factors such as barrier effects and reflections) associated with
the proposed PME operations. The ANLs
are related to the noise sensitivity of the area in question and different Area
Sensitivity Ratings (ASR) have been established to
reflect the background characteristics of different areas. The appropriate ASR for the Noise Sensitive
Receiver (NSR) is determined with reference to Table 5.2b.
Table 5.2b Area Sensitivity Ratings
Types of Area Containing
NSR |
Degree to which NSR is
affected by Influencing Factor (IF) |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
Rural area, including Country Parks or village type developments |
A |
B |
B |
Low density residential area consisting of low-rise or isolated
high-rise developments |
A |
B |
C |
Urban area |
B |
C |
C |
Area other than those above |
B |
B |
C |
Notes: The
following definitions apply: (a)
"Country
Park" means an area that is designated as a country park pursuant to
section 14 of the Country Parks Ordinance; (b)
"directly
affected" means that the NSR is at such a location that noise generated
by the IF is readily noticeable at the NSR and is a dominant feature of the
noise climate of the NSR; (c)
"indirectly
affected" means that the NSR is at such a location that noise generated
by the IF, whilst noticeable at the NSR, is not a dominant feature of the
noise climate of the NSR; (d)
"not
affected" means that the NSR is at such a location that noise generated
by the IF is not noticeable at the NSR; and (e)
"urban
area" means an area of high density, diverse development including a
mixture of such elements as industrial activities, major trade or commercial
activities and residential premises. |
The relevant ANLs
for each area sensitivity rating are shown in Table 5.2c.
Table 5.2c Acceptable
Noise Levels for General Construction Works (ANL, Leq,
5 min dB(A))
Time period |
Area Sensitivity Rating
(dB(A)) |
||
|
A |
B |
C |
All days during the evening (ie
19:00-23:00 hrs) and general holidays (including Sundays) during the day and evening
(ie 07:00-23:00 hrs) |
60 |
65 |
70 |
All days during the night-time (ie 23:00-07:00 hrs) |
45 |
50 |
55 |
The Noise Control Authority will consider a
well-justified CNP application for construction works within restricted hours as
guided by the relevant Technical Memorandum issued under the NCO. The Noise Control Authority will take into
account adjoining land uses and any previous complaints against construction
activities at the site before making a decision. Nothing in this EIA Report shall bind
the Noise Control Authority in making its decision. The Noise Control Authority may include any
conditions in a CNP that it considers appropriate. Failure to comply with any such conditions
may lead to cancellation of the CNP and prosecution action under the NCO.
Ground-borne Noise
Noise
arising from general construction works during normal working hours is governed
by the EIAO-TM under the EIAO as shown in Table 5.2a. The Technical
Memorandum on Noise From Places Other than Domestic Premises, Public Places or
Construction Sites (IND-TM) under the NCO stipulates that noise transmitted primarily through the
structural elements of building, or buildings, shall be 10 dB(A) less than the relevant
ANLs.
Based
on the principle for ground-borne noise criteria (i.e. taking account of the
minus 10dB(A) requirement under the IND-TM),
ground-borne construction noise levels inside domestic premises and schools
will be limited to 65dB(A) and 60dB(A) (55dB(A) during examination)
respectively, with reference to the daytime airborne noise criterion of 75dB(A)
and 70dB(A)(65dB(A) during examination) in accordance with EIAO-TM.
In
the evening (19:00 – 23:00hrs) and during nighttime (23:00 – 07:00hrs), ground-borne
noise level will be limited to 10dB(A) below the respective ANLs for the Area
Sensitivity Rating category of “A, B and C” at the NSRs along the proposed
project. A summary of these criteria is
given in Table 5.2d below.
Table 5.2d Ground-borne
Noise Criteria (ANL, Leq, 5min
dB(A))
Time
period |
Area Sensitivity Rating
(dB(A)) |
|
||
|
A |
B |
C |
|
All
days during the evening (ie 19:00-23:00 hrs) andgeneral holidays
(including Sundays) during the day and evening (ie
07:00-23:00 hrs) |
50 |
55 |
60 |
|
All
days during the night-time (ie 23:00-07:00 hrs) |
35 |
40 |
45 |
|
The
EIAO-TM and IND-TM specify the applicable ANLs for the operation
of Project. The ANLs are dependent on the
ASR and the time of the day and are presented in Table 5.2e.
Table 5.2e ANLs
to be used as Fixed Plant Noise Criteria
Time Period |
Leq 30min (dB(A)) |
||
ASR “A” |
ASR “B” |
ASR “C” |
|
Day-time
(ie 07:00-19:00 hrs) |
60 |
65 |
70 |
Evening
(ie 19:00-23:00 hrs) |
60 |
65 |
70 |
Night-time
(ie 23:00-07:00 hrs) |
50 |
55 |
60 |
Fixed
plant noise is controlled under Section 13 of the NCO and the
predictions will be undertaken in accordance with the IND-TM. The noise criteria for planning and design of
Designated Projects are set out in the EIAO-TM as follows:
·
the noise level at the facade of
the nearest NSR is at least 5 dB(A) lower than the appropriate ANL (as shown in
Table 5.2d) as specified in the IND-TM; or
·
the prevailing background noise
level (for quiet areas with a noise level 5 dB(A) below the appropriate
ANL).
Road Traffic Noise
The traffic noise standards for planning purposes
specified in Table 1 under Annex 5 of the EIAO-TM
was employed as the noise limits for the road traffic noise impact
assessment. The applicable road traffic
noise standards are 70dB(A) L10, 1hr for domestic premises and
65dB(A) L10, 1hr for education institutions and church,
respectively. These noise limits were applied
for the peak hour traffic flows and for uses that rely on opened windows for
ventilation.
5.3 Description of the Noise Environment
5.3.1
Baseline
Environmental Conditions
The Project Site consists of mainlaying
located along Tsui Lam Road, Po Hong Road, Wan Po
Road and a desalination plant site near the southern end of Wan Po Road south
of the Southeast New Territories (SENT) Landfill and the Tseung
Kwan O Industrial Estate. High-rise
residential developments and educational institutions exist along the mainlaying sections.
Background noise levels vary from a typical of a general rural
environment to a low density residential area, and there are limited numbers of
vehicles or noisy plant items operating during evening and night-time
periods. The major existing noise
sources were identified as the general noise from the existing SENT Landfill, Tseung Kwan O
Industrial Estate and the
traffic noise in the vicinity.
5.3.2
Noise Sensitive Receivers
In accordance with the requirements given in
Section 3.4.3.2 of the EIA Study Brief,
the Study Area for the noise impact assessment covered a distance of 300m from
the boundary of the Project Site. Only
the first layer of the NSRs located along Wan Po Road, Po Hong Road and Tsui Lam Road were included in the assessment as the NSRs
behind were located further away from the road and were screened. The area considered in the assessment is
shown in Figure 5.3a.
Existing NSRs that would potentially be affected by
the Project are identified as residential developments, chapels and schools
along Wan Po Road, Po Hong Road and Tsui Lam Road, as
well as the village house at Nam Tong on Tung Lung Chau which is located at
more than 1.3 km to the south-east of the Project Site boundary. The locations of the identified
representative NSRs are presented in Figures
5.3b to 5.3e. The locations of the identified
representative planned NSRs for assessment are presented in Figure
5.3f. Photos showing the
existing NSRs are presented in Annex 5A.
The
representative air-borne NSRs within the study area and their separation
distances to the Project Site are listed in Table
5.3a. Potential construction and operational noise impact
at the representative existing NSRs were assessed according to the matrix in Table
5.3a. The two
identified representative planned NSRs were not assessed for noise impacts
during construction phase as no implementation program could be found for these
developments.
Table 5.3a Representative
Air-borne Noise Sensitive Receivers Selected for Construction Noise Impact
Assessment
NSR |
Location |
Use (a) |
Approx.
Horizontal Distance to Notional Source Position(b) (m) |
Floors |
TLC1 |
Village House
at Tung Lung Chau |
Residential |
1340 |
1 |
LP1 |
Lohas Park – Phase 2 Tower 1 |
Residential |
17/2600(d) |
49 |
TB1 |
The Beaumont |
Residential |
185 |
38 |
CSS1 |
Creative
Secondary School |
Educational |
26 |
7 |
OS1 |
Oscar by the
Sea |
Residential |
84 |
32 |
TKOP1 |
Tseung Kwan O Plaza |
Residential |
24 |
45 |
BG1 |
Beverly
Garden |
Residential |
43 |
40 |
STE1 |
Sheung Tak
Estate |
Residential |
29 |
38 |
KNH1 |
Kwong Ming
Court - Kwong Ning House |
Residential |
38 |
38 |
LSTPS1 |
Leung Sing
Tak Primary School |
Educational |
268 |
7 |
NFP1 |
Nan Fung
Plaza |
Residential |
297 |
43 |
SACK1 |
St. Andrew's
Catholic Kindergarten |
Educational |
271 |
4 |
CKWPS1 |
POH Chan Kwok
Wai Primary School |
Educational |
144 |
6 |
HHCSC1 |
Haven of Hope
Christian Service Chapel |
G/IC |
54 |
2 |
DHMC1 |
Ma Chan Duen Hey Memorial College |
Educational |
100 |
7 |
MC1 |
Metro City |
Residential |
67 |
43 |
VH1 |
Verbena
Heights |
Residential |
44 |
33 |
HSG1 |
Hong Sing
Garden |
Residential |
201 |
30 |
KLC1 |
King Ling
College |
Educational |
272 |
8 |
SP1 |
Serenity
Place |
Residential |
16 |
41 |
RT1 |
Radiant
Towers |
Residential |
41 |
44 |
FP1 |
Finery Park |
Residential |
49 |
43 |
WOG1 |
Well On
Garden |
Residential |
46 |
40 |
PLKLFC1 |
PLK Laws
Foundation College |
Educational |
7 |
8 |
KTPS1 |
TKO Kei Tak
Primary School |
Educational |
14 |
8 |
CJCLS1 |
The Church of
Jesus Christ of Latter-days Saints |
G/IC |
30 |
5 |
PYH1 |
Po Lam Estate
- Po Yan House |
Residential |
132 |
35 |
TKOV1 |
TKO Village
No. 271 |
Residential |
32 |
3 |
KMC1 |
King Ming
Court |
Residential |
21 |
35 |
TLE1 |
Tsui
Lam Estate |
Residential |
21 |
22 |
SCPS1 |
School of
Continuing and Professional Education - CUHK |
Educational |
16 |
8 |
YC1 |
Youth College
(Tseung Kwan O) |
Educational |
34 |
7 |
HCMS1 |
Hong Chi Morninghill School Tsui Lam |
Educational |
66 |
5 |
LP2 |
Lohas Park – Phase 2 Tower 9 |
Residential |
66 |
56 |
A78R1(c) |
TKO Area 78
Residential Development |
Residential |
192 |
- |
A86S1(c) |
Planned
School in Area 86 |
Educational |
59 |
- |
Notes: (a)G/IC
denotes Government, Institution or Community. (b) According to the GW-TM, notional
source position refers to the position mid-way between the approximate
geographical centre of the construction site and its
boundary nearest to the NSR. (c) Representative Planned NSR (d) 17m is the separation between the
LP1 and the notional source position of the nearest workfront
of mainlaying works and 2600m is the separation
between the LP1 and the notional source position of the construction site of
the desalination plant. |
The representative ground-borne
NSRs within the study area and their separation distances to the
ground-borne noise sources of Project Site are presented in Table
5.3b.
Table 5.3b Representative
Ground-borne Noise Sensitive Receivers
NSR |
Location |
Use |
Approx.
Horizontal Distance to Notional Source Position(a) (m) |
Floors |
LP1 |
Lohas
Park – Phase 2 Tower 1 |
Residential |
72 |
49 |
LP2 |
Lohas
Park – Phase 2 Tower 9 |
Residential |
40 |
56 |
KMC1 |
King Ming Court |
Residential |
23 |
35 |
Note: (a) According to the GW-TM, notional
source position refers to the position mid-way between the approximate
geographical centre of the construction site and its
boundary nearest to the NSR. |
5.3.3
Potential Concurrent Projects
The potential concurrent projects
in the vicinity of the Project include the Cross Bay Link (CBL), TKO Area 86
Development Stages 1-3 at Lohas Park, Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) and Trunk Road
T2. The distance from the site boundary
of the Project to TKO-LTT and Trunk Road T2 is greater than 3km. Cumulative impact is not anticipated due to
large separation distances and hence not taken into account. The construction phase and study areas of the
CBL (2016 - 2020), TKO Area 86 Development (ongoing – 2020) and the proposed
desalination plant (2017 – 2020) overlap, hence, the cumulative impacts are
assessed in this report.
5.4
Potential Sources of Impact
The major activities associated with the
construction phase will involve the use of PME and they are summarised as
follows:
·
Mainlaying – concrete
breaking, excavation, pipe laying, pipe jacking, backfilling, concrete reinstatement,
asphalt reinstatement, painting of road marking; pipe jacking would be employed
as trenchless method for some sections of mainlaying
works (See Figure 5.4a);
·
Desalination
Plant Construction & Slope Mitigation Works -
site clearance and ground investigation, foundation and piling, building works,
architectural and landscaping work, submarine intake and outfall, slope
mitigation and E&M installation, testing and commissioning.
Potential sources of noise impacts during the
construction phase of the Project will mainly arise from powered mechanical
equipment (PME) operating at the construction work sites. The construction noise assessment was
undertaken based on the proposed construction works programme (see Annex
5B), and plant inventory (see Annex
5C). The plant inventory was
reviewed by the Design Engineer and was confirmed to be suitable for completing
the Assignment within the scheduled timeframe.
The
normal working hours of the Contractor will be between 07:00 and 19:00 hrs from
Monday to Saturday (except public holidays).
Construction activities during restricted hours are not expected. Should evening and night works between 19:00
and 07:00 hrs or on public holidays (including Sundays) be required, the
Contractor will submit a CNP application which will be assessed by the Noise
Control Authority.
Mainlaying
Mainlaying
is expected to be constructed under three works packages for the alignments
between the desalination plant to Shek Kok Road, Shek Kok Road to Po Shun Road and Po Shun Road to Tseung Kwan O Fresh Water Primary Service Reservoir. It is anticipated that the mains will be
constructed in segments of up to 40m in length (i.e. workfront,
see Figures
5.8a and 5.8b). Construction
works will be carried out at most three workfronts
concurrently in Section A (Desalination Plant to Shek
Kok Road) and Section C (Po Shun Road to Tseung Kwan
O Fresh Water Primary Service Reservoir) and at most four workfronts
concurrently in Section B (Shek Kok Road to Po Shun
Road). The construction activities at
one workfront will last for about one to two months
only. There are five proposed works
areas (See Figure 5.4a) where pipe jacking (trenchless tunneling) method
will be adopted. Tunneling works using
the pipe jacking method will be mainly carried out underground during the
day-time period only.
Interfacing
of Construction Activities
As mentioned above, a workfront
for the mains using trenching is up to 40m and mainlaying
works for Sections A, B & C will be carried out simultaneously. The work programme of the construction for
the sections will be properly managed such that concurrent workfronts
will be scattered away from other sections and the NSRs will not be affected by
the construction activities from two sections at any one time. For tunneling and excavation using the pipe
jacking method, the construction activities will be scheduled such that only
one works area (See Figure 5.4a) will be in operation at any one time.
Mainlaying
and desalination plant construction may be carried out at the same time. Only one identified NSR, Lohas
Park – Phase 2 Tower 1 (LP1), will be affected by both activities. Based on this, cumulative noise impact from mainlaying
and the construction of the desalination plant were assessed.
During
operation, noise will be generated from fixed plant sources, i.e. two pumping
stations proposed to be situated in the desalination plant. All equipment will be accommodated inside
plant rooms and hence fully enclosed.
Operational noise from the pumping station is assumed to be emitted
through louvres. As the nearest NSR is
located at over 1.3 km away from the desalination plant, there are considered to be no
unacceptable noise impacts during the operation of the desalination plant.
Traffic
generated from the site is insignificant as only 5 to 10 round trips per day
are expected for the transportation of chemicals to the desalination
plant. This comprises less than 0.05% of
the Annual Average Daily Traffic (AADT) on Wan Po Road and Tseung
Kwan O Tunnel Road. With consideration
of the low traffic arising from the Project, no traffic noise impact is
anticipated.
General Construction
Activities
The construction noise impact
assessment was undertaken in accordance with the procedures outlined in the GW-TM, which is issued under the NCO and the EIAO-TM. The assessment
methodology is summarised as follows:
·
Locate
representative NSRs that may be affected by the Project;
·
Determine
the plant teams for corresponding activities, based on the agreed plant
inventory;
·
Assign
sound power levels (SWLs) to the PME proposed based on the GW-TM, British Standard BS 5228([1])
and list of SWLs of other commonly used PME([2]);
·
Calculate
the correction factors based on the distance between the NSRs and the notional
noise source position of the work sites;
·
Apply
corrections in the calculations, such as potential screening effects and
acoustic reflection, if any; and
·
Predict
the construction noise levels at NSRs in the absence of any mitigation
measures.
The
construction noise assessment was undertaken based on the proposed construction
works programme and plant inventory, and appropriate utilisation rates of the
items of PME (see Annex 5C). The Project Proponent has reviewed the
programme and plant inventory, and has confirmed that they are reasonable and
practicable for completing the Project within the scheduled timeframe.
The total
SWL associated with each construction activity was established based on an
assumed plant inventory. The notional source positions were
established in accordance with the procedures stated in the GW-TM. The potential noise impacts at NSRs for a
maximum of 3 or 4 workfronts (worse-case scenario
considering the cumulative impacts of the noisiest PME) were subsequently
evaluated by comparing the predicted noise levels with the EIAO-TM day-time construction noise limits (Leq,
30min dB(A)), as outlined in Section
5.2.1.
Ground-borne Noise
The
method used to predict construction ground-borne noise is based on the U.S.
Department of Transportation “High-Speed Ground Transportation Noise and
Vibration Impact Assessment” ([3]).
The predicted ground-borne noise level (Lp) inside the noise sensitive rooms is given by
the following equation:
Lp = Lv,rms +
Cdist
+ Cdamping
+ Cbuilding
+ Cfloor + Cnoise
where
Lv,rms is the vibration level at a distance R from the source related to the
vibration source level at a reference distance R0;
Cdist is the distance attenuation;
Cdamping is the
soil damping loss across the geological media;
Cfloor is the coupling loss per floor;
Cnoise is the conversion factor from floor vibration
levels to noise levels.
Reference Vibration Sources
The
vibration velocities were determined by measurements in Peak Particle Velocity.
In such cases, a crest factor of four was applied to establish the rms level in accordance with the Federal Transit Administration’s Guidance Manual ([4]).
Reference
has been made to the Tunnel Boring Machine (TBM) employed for Kwai Tsing Tunnel of West Rail project from the EIA for
Drainage Improvement in Tsuen Wan, Kwai Chung &
Tsing Yi - Tsuen Wan Drainage Tunnel (Register No.: AEIAR-088/2005). The
geology is consisting of mainly granite. The measurements are considered the
most appropriate available information for assessing TBM ground-borne noise.
Soil damping loss
No soil
damping loss is assumed for conservative purpose.
Coupling loss into Building Structures
Coupling
loss into building structures is the change in the incident ground-surface
vibration due to the presence of the piled building foundation. The empirical
values based on the guidance set out in the Transport
Noise Reference Noise Book are given in the following Table 5.5a.
Table 5.5a Loss
Factor for Coupling into Building Foundations
Loss factor for coupling into building
foundation (dB) |
Octave
Band Frequencies (Hz) |
|||||
16 |
31.5 |
63 |
125 |
250 |
500 |
|
Large building on
Piles |
-7 |
-10 |
-12 |
-15 |
-17 |
-14 |
Single residences |
-5 |
-6 |
-6 |
-5 |
-4 |
-3 |
Coupling Loss Per Floor
Coupling
loss per floor is the floor-to-floor vibration transmission attenuation. In multi-storey
buildings, the attenuation of vibration from floor to floor is approximately
-1dB in the upper floor regions at low frequencies and greater than -3dB at
lower floors at high frequencies. Coupling loss of -1dB pre floor is assumed
for a conservative assessment.
Conversion from Floor Vibration to Noise Levels
Conversion
from floor vibration levels to indoor reverberant noise levels is based on the
standard acoustic principles. The conversion factor is depended on the surface
area of the room, the radiation efficiency, the volume of the room and the room
reverberation time. Results for residential units, school and temple are
summarised in Table 5.5b.
Table 5.5b Conversion
Factor from Floor Vibration levels to indoor reverberant noise levels
NSR Description |
Conversion Cnoise (dB re 1 x 10-6 mm/s) |
Residential Unit |
-27 |
Temple |
-27 |
School |
-24 |
Pipe
jacking would be employed as a trenchless method at five proposed sections
along the rising mains (See Figure 5.4a). The sections are
located at road junctions such that the trenchless method can reduce
interruption caused to road traffic. A micro-tunnel boring machine (micro-TBM)
with a shield diameter of not more than 1.5m would be used to construct the
trenchless tunnel sections.
No noise sensitive receivers were identified within
300m of the operational site area of the proposed desalination plant at Tseung Kwan O. In view of the above and that all equipment will
be accommodated inside plant rooms, quantitative assessment is considered not
necessary for the operation phase of the proposed desalination plant. In addition, traffic generated from the site
is insignificant as only 5 to 10 round trips per day are expected for the
transportation of chemicals along Wan Po Road via Tseung
Kwan O Tunnel Road. The Annual Average Daily Traffic Flow on Wan Po Road was
above 30,000 in 2013. It is anticipated the increase in daily traffic flow will
be less than 0.05% on Wan Po Road and the increase in road traffic noise due to
the Project will be less than 0.01dB(A). With consideration of the low traffic
arising from the Project, no traffic noise impact is anticipated.
Desalination Plant
As the representative NSRs are located at more than
1.3 km away from the Notional Source Position, the predicted noise levels at
the representative NSRs would comply with the stipulated construction noise
criteria. A summary of the predicted
construction noise levels is presented in Table
5.6a. Details of the noise
calculations are presented in Annex 5D.
Table 5.6a Predicted
Construction Noise Levels at Representative NSRs for Construction of
Desalination Plant
NSR |
Description |
Approx. Horizontal Distance to Notional Source
Position(a) (km) |
Predicted Construction Noise Levels(b), Leq, 30 min dB(A) |
LP1 |
Lohas Park – Phase 2 Tower 1 |
2.6 |
34 - 50 |
TLC1 |
Village House at Tung
Lung Chau |
1.3 |
39 - 56 |
Notes: (a) According
to the GW-TM, notional source position refers to the position mid-way between
the approximate geographical centre of the
construction site and its boundary nearest to the NSR. If the construction
site is large such that the notional source position would be greater than
50m from the point on the site boundary nearest to the NSR, the position was
taken to be a point 50m from that point on the site boundary measured along
the line between the approximate geographical centre
of the site and the point on the site boundary nearest to the NSR. (b) All
predicted noise levels were corrected with 3dB(A) for façade reflection. (c) Assessment
criterion for construction noise impact is 75 dB(A) for domestic premises. |
The predicted construction noise levels at the
representative NSRs are well below the noise criteria, hence the NSRs will not
be adversely affected by the construction of the desalination plant.
Mainlaying Works
The predicted façade noise levels during daytime
period due to the mainlaying construction works are
calculated in accordance with the methodology described in GW-TM. The results are summarised in Table
5.6b with details of the noise calculations given in Annex 5D.
Cumulative Impact
The
maximum predicted noise levels and cumulative noise impact from interfacing mainlaying and construction of the desalination plant as well as the construction
activities of the Cross Bay Link and TKO Area 86 Developments are
presented for LP1,
the NSR most proximal to the mainlaying works and the
concurrent projects. Results
indicate that the noise impact from the desalination plant and the concurrent projects
are
insignificant
and low, respectively. The maximum predicted cumulative
CNL at LP1 remains at 85 dB(A). Details
of the noise calculations are presented in Annex
5D.
Table 5.6b Predicted
Construction Noise Levels at Representative NSRs for Mainlaying
Works
NSR |
Description |
Approx.
Horizontal Distance to Notional Source Position(a) (m) |
Predicted
Construction Noise Levels(b), Leq, 30 min dB(A) |
LP1(d)(e) |
Lohas Park – Phase 2 Tower 1 |
17 - 116 |
68 - 85 |
TB1 |
The Beaumont |
185 - 201 |
42 - 70 |
CSS1 |
Creative Secondary School |
26 – 76 |
56 - 84 |
OS1 |
Oscar by the Sea |
84 – 113 |
48 - 76 |
TKOP1 |
Tseung Kwan O Plaza |
24 – 80 |
56 - 84 |
BG1 |
Beverly Garden |
43 – 90 |
52 - 80 |
STE1 |
Sheung Tak Estate |
29 – 82 |
55 - 83 |
KNH1 |
Kwong Ming Court - Kwong Ning House |
38 – 88 |
53 - 81 |
LSTPS1 |
Leung Sing Tak Primary
School |
268 – 315 |
38 - 66 |
NFP1 |
Nan Fung Plaza |
298 – 305 |
38 - 66 |
SACK1 |
St. Andrew's Catholic
Kindergarten |
278 – 288 |
38 - 66 |
CKWPS1 |
POH Chan Kwok Wai Primary
School |
144 – 165 |
44 - 72 |
HHCSC1 |
Haven of Hope Christian
Service Chapel |
54 – 70 |
50 - 78 |
DHMC1 |
Ma Chan Duen Hey Memorial College |
100 – 110 |
46 - 74 |
MC1 |
Metro City |
67 – 80 |
49 - 77 |
VH1 |
Verbena Heights |
44 – 63 |
52 - 80 |
HSG1 |
Hong Sing Garden |
201 – 205 |
40 - 68 |
KLC1 |
King Ling College |
272 – 275 |
37 - 65 |
SP1 |
Senerity Place |
16 – 45 |
58 - 86 |
RT1 |
Radiant Towers |
41 – 63 |
52 - 80 |
FP1 |
Finery Park |
49 – 65 |
51 - 79 |
WOG1 |
Well On Garden |
46 – 60 |
51 - 79 |
PLKLFC1 |
PLK Laws Foundation
College |
7 – 40 |
65 - 93 |
KTPS1 |
TKO Kei Tak Primary
School |
14 – 43 |
59 - 87 |
CJCLS1 |
The Church of Jesus
Christ of Latter-days Saints |
30 – 50 |
54 - 82 |
PYH1 |
Po Lam Estate - Po Yan
House |
132 – 143 |
43 - 71 |
TKOV1 |
TKO Village No. 271 |
32 – 65 |
53 - 81 |
KMC1(e) |
King Ming Court |
21 – 35 |
58 - 86 |
TLE1 |
Tsui Lam Estate |
21 – 48 |
56 - 84 |
SCPS1 |
School of Continuing and Professional
Studies - CUHK (Tseung Kwan O Learning Centre) |
16 – 40 |
59 - 87 |
YC1 |
Youth College (Tseung Kwan O) |
34 – 55 |
53 - 81 |
HCMS1 |
Hong Chi Morninghill School Tsui Lam |
66 – 90 |
48 - 76 |
LP2 (e) |
Lohas Park – Phase 2 Tower 9 |
48 - 119 |
49 - 78 |
Notes: (a) According to the GW-TM, notional source
position refers to the position mid-way between the approximate geographical centre of the construction site and its boundary nearest
to the NSR. (b) All predicted noise levels were corrected
with 3dB(A) for façade reflection. (c)
Assessment criterion for construction
noise impact is 75 dB(A) for domestic premises and 70dB(A) for education
institutions (65dB(A) during examinations). (d) The calculation for
cumulative CNL (Desalination plant + mainlaying + Cross Bay Link + TKO Area 86) for LP1 under
unmitigated scenario is shown in Annex 5D-3. (e) Calculation includes pipe
jacking for trenchless mainlaying method. |
Results indicate that the construction noise levels
at the majority of the representative NSRs are predicted to exceed the EIAO-TM noise criteria during day-time
period due to the mainlaying construction works. Therefore, mitigation measures will be required.
Ground-borne Noise
King Ming
Court is identified as the critical ground-borne NSR as it is the receiver with
the least horizontal separation (ie. 23m) to the
proposed tunnel section to be conducted by trenchless method. The ground-borne noise level is predicted to
be 42dB(A) at King Ming Court which comply with criterion for ground-borne
noise. The ground-borne noise calculation is shown in Annex 5D-4a.
In fact, the size of the cutter head (diameter
<1.5m) of the micro-TBM is small (ie. fewer cutter
discs and less driving power) compared with the reference source of TBM (8.7m
diameter for the TBM from the EIA for
Drainage Improvement in Tsuen Wan, Kwai Chung &
Tsing Yi - Tsuen Wan Drainage Tunnel (Register No.: AEIAR-088/2005)). In
addition, although the soil damping loss is assumed zero in the assessment for
conservative purpose, the geological condition along the rising mains is mainly
soft in nature as the rising mains will be laid at approximately 1.5m below the
ground level. The soft geology will provide significant damping of vibrations
and hence considerably reduce the transmission of ground-borne vibrations.
In addition to the five proposed sections (See Figure
5.4a) that will be constructed by micro-TBM, trenchless method may be
carried out at other sections to avoid interruption caused to road traffic
where necessary. Based on the assessment methodology in Section 5.5.1, there are minimum horizontal separations between the
NSR and the micro-TBM that shall be maintained in order to comply with the
criteria. The calculations of the minimum separations are presented in Annex 5D-4b. Safety factor of 10dB(A) is
applied in the calculation for conservatism. The minimum separations for
different types of NSR are summarized in Table 5.6c.
Table
5.6c Minimum separation between the
micro-TBM and NSR
NSR |
Daytime Ground-borne Noise Criteria, dB(A) |
Minimum Horizontal Separation, m |
Domestic Premises
and Temples |
65 |
5 |
Educational
Institutions (normal period) |
60 |
12 |
Educational Institutions (during examination period) |
50 |
23 |
Provided that the minimum separations shown in the Table 5.6c can be maintained, it is
anticipated that the ground-borne noise generated by the micro-TBM for this
Project would be insignificant and unlikely to cause adverse impact on the
nearby NSRs.
In view of the predicted noise exceedances during
the construction of the Project, the following mitigation measures have been
considered:
·
Good
construction site practice;
·
Use of
quite PME;
·
Adoption
of movable noise barriers and noise enclosures;
·
Use of
noise insulation sheet; and
·
Scheduling
of PME / construction activities.
Good Construction Site Practice
Good
construction site practice and noise management can considerably reduce the
potential noise impact of the construction activities on nearby NSRs. The noise benefits of these practices can
vary according to specific site conditions and operations. Since the effect of the good construction
site practices could not be quantified, the mitigated noise levels calculated
in the subsequent sections have not taken account of this effect. The following site practices should be
followed during the construction of the Project:
·
Only
well-maintained plant will be operated on-site and plant will be serviced
regularly during the construction phase;
·
Silencers
or mufflers on construction equipment will be utilised and will be properly
maintained during the construction phase;
·
Mobile
plant, if any, will be sited as far away from NSRs as possible;
·
Machines
and plant (such as trucks) that may be in intermittent use will be shut down
between work periods or will be throttled down to a minimum;
·
Plants
known to emit noise strongly in one direction will, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs; and
·
Material
stockpiles and other structures will be effectively utilised, wherever
practicable, in screening noise from on-site construction activities.
Use of Quiet PME
The use of
quiet PME is considered to be a practicable means to mitigate the construction
noise impact. Quiet plant is defined as
a PME having actual SWL lower than the value specified in the GW-TM. The total SWL of all plant items to be used
on-site at each works area will be specified so that flexibility is allowed for
the Contractor to select plant items to suit the construction needs. Quiet PME that have been adopted in the
assessment are summarised in Table 5.7a.
Table 5.7a Sound
Power Level of Quiet PME
PME |
EPD QPME(a) /
BS5228 (b) Reference |
Sound Power Level (dB(A)) |
Wheeled
excavator fitted with hydraulic rock breaker |
BS D8 12 |
106 |
Excavator/loader,
wheeled/tracked |
BS D3 97 |
105 |
Dump truck
(50 t) |
BS D9 39 |
103 |
Piling, vibrating
hammer |
EPD/PME/18 |
115 |
Lorry, with crane/grab, 5.5tonne < gross vehicle weight ≦ 38 tonne |
EPD/PME/36 |
112 |
Concrete truck mixer |
BS D6 35 |
100 |
Poker, vibratory, hand-held |
BS D6 40 |
98 |
Asphalt
paver |
BS D8 24 |
101 |
Paint line marker (low pressure) |
EPD/PME/22 |
87 |
Road
roller |
BS D8 27 |
104 |
Drill rig, rotary type (diesel) |
EPD/PME/12 |
110 |
Grout pump |
EPD/PME/15 |
105 |
Bull dozer |
BS D3 27 |
109 |
Mobile crane |
BS D7 114 |
101 |
Concrete pump, stationary/lorry mounted |
BS D6 36 |
106 |
Poker, vibratory, hand-held (electric) |
EPD/PME/19 |
102 |
Notes: (a) British
Standard BS 5228:2009, Part 1 - Noise and Vibration Control on Construction
and Open Sites (b) “Sound power levels of other commonly used PME” prepared
by the Noise Control Authority
(http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf
) |
Adoption of Movable Noise Barriers
The use of noise barriers will be an effective means
to mitigate the noise impact arising from the construction works, particularly
for low-rise NSRs. The use of movable
barriers could generally provide a 5 dB(A) reduction for movable PME and 10
dB(A) for stationary PME. Movable noise
barriers of 3m in height with skid footing should be used and located within a
few metres of stationary plant and mobile plant such that the line of sight to
the NSR is blocked by the barriers. The
length of the barrier should be at least five times greater than its height. With reference to A Practical Guide for the Reduction of Noise from Construction Works
by EPD, the noise barrier material should have a superficial surface density of
at least 7 kg m-2 and have no openings or gaps.
In view of the close proximity between NSRs and the
works areas, movable noise barriers will be deployed along the mainlaying sections as far as practicable. Reference has been made to EIAO Guidance Note No. 9/2010 Preparation
of Construction Noise Assessment Under the Environmental Impact Assessment
Ordinance; it is anticipated that the major noise source of movable PMEs,
such as saw/groover,
wheeled excavator fitted with hydraulic rock breaker, lorry with
crane/grab, concrete truck mixer, vibratory poker and excavator/loader, will be
located behind the movable barriers, and therefore these barriers could produce
at least a 5 dB(A) noise reduction.
Use of Noise Insulating Sheet
Noise insulating sheet would be adopted for PME
such as piling machines (Annex 5E). The noise insulating sheet should be deployed
such that there would be no opening or gaps on the joints. With reference to the approved EIA Report for
West Island Line (WIL) (Register No.:
AEIAR-126/2008 approved on 23 Dec 2008) and MTRC Contract C4420 Tsim Sha
Tsui Modification Noise Assessment Report for
Variation of Environmental Permit (July 2003) and the technical data from
the manufacturer of the noise insulating sheet, a reduction of over 10 dB(A)
could be achieved with the use of the noise insulating sheet. For a conservative assessment, a noise
reduction of 10 dB(A) for the PME with noise insulating sheet deployed was
assumed in this assessment.
Sequencing and Scheduling of PME / Construction Activities
To further alleviate the construction noise
impacts, some construction activities (e.g.
excavation/shoring, reinstatement (asphalt), and pipe jacking) will be
planned and carried out in sequence, such that items of PME proposed for these
activities will not be operated simultaneously. Grouping of PME is considered
for these activities.
Moreover, PMEs will not be used at the works areas
near educational institutions with residual impact (ie
the “influence area” within a radius of 40m) during school hours in order to
reduce impact to the educational institutions.
The locations of the influence areas are presented in Figure
5.7a and Figure 5.7b.
Use of Noise Enclosure/ Acoustic Shed
Noise enclosures or acoustic sheds would be used to
cover stationary PME such as generators.
With the adoption of noise enclosures, PMEs could be completely
screened, and noise reduction of 15 dB(A) can be achieved according to the EIAO Guidance Note No.9/2010.
The use of noise enclosures is considered to
mitigate the residual impact arising from sawcutting
pavement at some workfronts instead of use of movable
noise barrier. Portable/Movable noise enclosure made of material with
superficial surface density of at least 7 kg m-2 may be used for
screening the noise from operation of the saw/groover,
concrete. The locations where the portable noise enclosure will be required for
sawcutting pavement are presented in Figure
5.7c, Figure 5.7d and Figure 5.7e.
The above mitigation measures have been vetted and
confirmed by the Project Proponent and its Engineering Consultant as being
practicable in completing the works within the scheduled timeframe. It is considered practical to specify the
quiet PME and noise mitigation measures described in Section 5.7.1 in the contract document to mitigate the construction
noise impact. With the implementation of quiet PME, movable noise barriers and
noise enclosure for various construction activities and grouping of PME (See Annex 5E), the mitigated noise levels at
the representative NSRs were calculated and the results summarised in Table
5.7b with details of the calculations given in Annex 5F-1a. The results
indicate that the predicted façade noise levels are in the range of 38 to 75 dB(A) and 37 to 82 dB(A) at residential NSRs and educational NSRs,
respectively.
Table 5.7b Predicted
Construction Noise Levels at Representative NSRs for Mainlaying
Works (With Mitigation Measures)
NSR |
Description |
Approx.
Horizontal Distance to Notional Source Position(a) (m) |
Predicted
Construction Noise Levels(b), Leq, 30 min dB(A) |
Noise
Criteria (c) |
LP1(d), (e) |
Lohas Park – Phase 2 Tower 1 |
17 - 116 |
68 - 75 |
75 |
TB1 |
The Beaumont |
185 - 201 |
42 - 64 |
75 |
CSS1 |
Creative Secondary School |
26 – 76 |
56 - 78 |
70/65 |
OS1 |
Oscar by the Sea |
84 – 113 |
48 - 71 |
75 |
TKOP1 |
Tseung Kwan O Plaza |
24 – 80 |
56 - 73 |
75 |
BG1 |
Beverly Garden |
43 – 90 |
52 - 75 |
75 |
STE1 |
Sheung Tak Estate |
29 – 82 |
55 - 72 |
75 |
KNH1 |
Kwong Ming Court - Kwong Ning House |
38 – 88 |
53 - 70 |
75 |
LSTPS1 |
Leung Sing Tak Primary School |
268 – 315 |
38 - 61 |
70/65 |
NFP1 |
Nan Fung Plaza |
298 – 305 |
38 - 60 |
75 |
SACK1 |
St. Andrew's Catholic Kindergarten |
278 – 288 |
38 - 61 |
70/65 |
CKWPS1 |
POH Chan Kwok Wai Primary School |
144 – 165 |
44 - 66 |
70/65 |
HHCSC1 |
Haven of Hope Christian Service Chapel |
54 – 70 |
50 - 73 |
75 |
DHMC1 |
Ma Chan Duen Hey Memorial College |
100 – 110 |
46 - 68 |
70/65 |
MC1 |
Metro City |
67 – 80 |
49 - 71 |
75 |
VH1 |
Verbena Heights |
44 – 63 |
52 - 74 |
75 |
HSG1 |
Hong Sing Garden |
201 – 205 |
40 - 63 |
75 |
KLC1 |
King Ling College |
272 – 275 |
37 - 60 |
70/65 |
SP1 |
Senerity Place |
16 – 45 |
58 - 75 |
75 |
RT1 |
Radiant Towers |
41 – 63 |
52 - 69 |
75 |
FP1 |
Finery Park |
49 – 65 |
51 - 68 |
75 |
WOG1 |
Well On Garden |
46 – 60 |
51 - 74 |
75 |
PLKLFC1 |
PLK Laws Foundation College |
7 – 40 |
65 - 87 |
70/65 |
KTPS1 |
TKO Kei Tak Primary School |
14 – 43 |
59 - 82 |
70/65 |
CJCLS1 |
The Church of Jesus Christ of Latter-days Saints |
30 – 50 |
54 - 71 |
75 |
PYH1 |
Po Lam Estate - Po Yan House |
132 – 143 |
43 - 66 |
75 |
TKOV1 |
TKO Village No. 271 |
32 – 65 |
53 - 70 |
75 |
KMC1 (e) |
King Ming Court |
21 – 35 |
58 - 75 |
75 |
TLE1 |
Tsui Lam Estate |
21 – 48 |
56 - 73 |
75 |
SCPS1 |
School of Continuing and Professional Studies - CUHK (Tseung Kwan O Learning Centre) |
16 – 40 |
59 - 82 |
70/65 |
YC1 |
Youth College (Tseung Kwan O) |
34 – 55 |
53 - 70 |
70/65 |
HCMS1 |
Hong Chi Morninghill School Tsui Lam |
66 – 90 |
48 - 65 |
70/65 |
LP2 (e) |
Lohas Park – Phase 2 Tower 9 |
48 - 119 |
49 - 67 |
75 |
Notes: (a) According to the GW-TM,
notional source position refers to the position mid-way between the
approximate geographical centre of the construction
site and its boundary nearest to the NSR. (b) All predicted noise levels
were corrected with 3dB(A) for façade reflection. (c) Assessment criterion for
construction noise impact is 75 dB(A) for domestic premises and 70dB(A) for
education institutions (65dB(A) during examinations).. (d) The calculation for cumulative CNL
(Desalination plant + mainlaying + Cross Bay Link + TKO Area 86) for LP1 under mitigated
scenario is shown in Annex 5F-2. (e) Calculation includes pipe
jacking for trenchless mainlaying method as shown
in Annex 5F-1b. |
With the adoption of the recommended mitigation measures,
exceedance of the EIAO-TM noise
criteria at some of the NSRs during the daytime period is still anticipated due
to close proximity to the works sites.
The
major concurrent projects to be assessed for construction noise cumulative impacts include
the Cross
Bay Link (CBL)
and the Area 86 Development Stages 1-3 at Lohas Park. The
assessment
results show that the cumulative noise impacts of the Project with these
concurrent projects will comply with EIAO requirements.
No
cumulative impact is anticipated during the operational phase.
With
the use of practical noise mitigation measures, including the use of quiet PME,
movable noise barriers, noise insulation sheet and scheduling of construction
activities, exceedances of the construction noise criteria during normal school
hours are still predicted at some of the NSRs arising from the construction of
the mains due to the close proximity to the NSRs. Due to the nature of the construction work,
it is envisaged that the exceedances will mainly occur at four education
institution NSRs.
The
predicted residual impacts and the durations are summarised
in Table
5.9a and Table 5.9b.
Table 5.9a Predicted
Residual Construction Noise Impacts from Construction of Mains
NSR |
Description |
Predicted Residual Noise Impact from Individual Activity, dB (A) |
||||||||
|
|
a)
Sawcutting pavement |
b)
Breaking up of pavement |
c)
Excavation /shoring |
d)
Pipe laying |
e)
Backfiling |
f)
Reinstatement (concrete) |
g)
Reinstatement (asphalt) |
h)
Painting of road marking |
i) Pipe jacking |
|
|
Duration
(The duration of each construction work activity for each segment, ie 40m) |
|
|||||||
|
|
1 day |
2 days |
3 weeks |
2 weeks |
1 week |
1 – 2 days |
1 – 2 days |
Half day |
2 weeks |
|
|
Exceedance
due to the use of concrete saw only. |
Exceedance
due to the use of hydraulic breaker only. |
Exceedance
due to excavator, dump truck and sheet piling. |
Exceedance
due to the use of lorry for 30min only. |
Exceedance
due to the use of lorry to grab the soil and vibrator compactor. |
Exceedance
due to the use of concrete lorry mixer and vibratory poker. |
Exceedance
due to the use of asphalt paver, dump truck and road roller. |
Exceedance
due to the use of paint line marker only. |
Exceedance
due to excavator, dump truck and sheet piling. |
CSS1(a) |
Creative
Secondary School |
8 dB(A) |
- |
2dB(A) |
- |
2dB(A) |
- |
3dB(A) |
- |
- |
PLKLFC1(a) |
PLK
Laws Foundation College |
17dB(A) |
9dB(A) |
11dB(A) |
8dB(A) |
11dB(A) |
5dB(A) |
12dB(A) |
- |
- |
KTPS1(a) |
TKO Kei
Tak Primary School |
12dB(A) |
3dB(A) |
6dB(A) |
2dB(A) |
5dB(A) |
- |
6dB(A) |
- |
- |
SCPS1(a) |
School
of Continuing and Professional Studies - CUHK |
12dB(A) |
3dB(A) |
5dB(A) |
2dB(A) |
5dB(A) |
- |
6dB(A) |
- |
- |
Notes: (a) Use of PME at the
influence areas as identified in Figure 5.7a and Figure 5.7b will be
scheduled outside the school hours in order to reduce impact at the NSRs with residual impact. |
Table 5.9b Summary
of Residual Impact
NSR |
Land Use |
Range of exceedance, dB(A) |
Duration of residual impact,
weeks |
No. of floors exceeded noise
criteria |
No. of dwellings/classrooms
per floor |
No. Of dwellings affected |
|
1 to 4 dB(A) |
≥5 dB(A) |
||||||
CSS1(a) |
Educational |
2-8 |
4 |
1 |
7 |
5 |
- |
PLKLFC1(a) |
Educational |
5-17 |
0 |
8 |
8 |
4 |
- |
KTPS1(a) |
Educational |
2-12 |
3 |
5 |
8 |
6 |
- |
SCPS1(a) |
Educational |
2-12 |
3 |
5 |
8 |
4 |
- |
The
School of Continuing and Professional Studies – CUHK (Tseung
Kwan O Learning Centre) (SCPS1) and the TKO Kei Tak Primary School (KTPS1) are
predicted to be subject to residual impacts of 2dB(A) to 12dB(A) during normal
school hours due to sawcutting, breaking up of
pavement, excavation/shoring, pipe laying, backfilling, and reinstatement
(asphalt). Quiet PME, temporary noise
barriers and insulating fabric have been recommended as mitigation measures to
alleviate the noise emissions from PME.
The feasibility of installing substantial noise barrier/enclosure has
been reviewed. However, installation of large and substantial noise
barriers/enclosure at the sources of the exceedance would be impractical due to
the lack of space between the works sites as well as potential secondary
impacts as a consequence of building a substantial noise barrier with a large
footing. However, SCPS1 and KTPS1 have
been observed to have been installed with either split-type or window-type air
conditioners, which will further alleviate the residual impacts. Furthermore, noisy construction works will be
avoided in the influence areas near SCPS1 and KTPS1 during normal school hours
as presented in Figure 5.7b.
Creative
Secondary School (CSS1), which is predicted to be subject to residual impacts
of 2dB(A) to 8dB(A)during normal school hours.
Residual impacts are predicted during sawcutting,
excavation/shoring, backfilling, and reinstatement (asphalt) works. While quiet PME, noise barriers and
insulating fabric have been recommended as mitigation measures to alleviate the
noise emissions from the PME, given the location of the NSR in very close
proximity of the works site, installation of large and substantial noise
barriers/enclosure would be impractical due to limited space available as well
as potential secondary impacts as a consequence of building a substantial noise
barrier with a large footing. CSS1 is
observed to have been installed with split-type air conditioners, which will
further alleviate the residual impacts.
Noisy construction works will also be avoided in the influence area near
CSS1 during school hours as presented in Figure 5.7a.
Exceedance
during normal school hours of 5dB(A) to
17dB(A) is also predicted at the PLK Laws Foundation College (PLKLFC1), due to sawcutting, breaking up of pavement, excavation/shoring,
pipe laying, backfilling, and reinstatement (asphalt) and reinstatement
(concrete) works. While quiet PME, noise
barriers and insulating fabric have been recommended as mitigation measures to
alleviate the noise emissions from the PME, given the location of the NSR in
very close proximity of the works site, installation of large and substantial
noise barriers/enclosure would be impractical due to limited space available as
well as potential secondary impacts as a consequence of building a substantial
noise barrier with a large footing.
PLKLFC1 is observed to have been installed with either split-type or
window-type air conditioners, which will further alleviate the residual
impacts. In addition noisy construction
works will be avoided in the influence area near PLKLFC1 during school hours as
presented in Figure 5.7b.
In
view the duration of noise exceedance at the four schools is limited to 8
weeks, the construction work in the influence areas near the four schools shall
be scheduled during long school holidays (eg summer
holiday, Easter holiday or Christmas holiday, etc) as
far as practicable. Scheduling the construction work for the four
schools and other recommended mitigation measures will be specified in the
contract document for proper implementation.
As
such, no residual impacts are anticipated and predicted noise levels at all
NSRs are predicted to comply with the EIAO requirements.
No
residual impact is anticipated during the operational phase.
5.10
Environmental Monitoring and Audit
The recommended mitigation measures, monitoring
procedures and locations are presented in detail in the Environmental
Monitoring and Audit (EM&A) Manual.
This will facilitate the contractor to have early warning and undertake
the necessary actions to reduce noise emissions at specific areas. The effectiveness of on-site control measures
could also be evaluated through the regular site audits. All the recommended mitigation measures
should be incorporated into the EM&A programme for implementation during
construction.
Noise monitoring for the operation of the two
pumping stations in the desalination plant are considered unnecessary during
the operation phase.
A construction noise assessment has been
undertaken to predict the noise levels at the representative NSRs due to the
construction of the Project. Practicable
mitigation measures, including use of quiet construction plant, movable noise
barriers, noise insulation sheets, scheduling of construction activities and
noise enclosures, have been recommended.
No adverse noise impacts are anticipated with the implementation of the
practical mitigation measures and noise levels at all NSRs are predicted comply
with the EIAO requirements.
All
equipment will be accommodated inside the plant rooms and hence fully
enclosed. Operational noise from the
pumping station is assumed to be emitted through louvres. No adverse noise impacts are anticipated at
the representative NSRs during the operational phase due to the Project because
of the large horizontal
separation.
([1])
British Standard “Noise and Vibration
Control on Construction and Open Sites – Part I”, BS 5228: Part I
([2])
“Sound power levels of other
commonly used PME” prepared by the Noise Control Authority
(http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf
)