Agreement
No. CE 21/2012 (WS)
Desalination
Plant at Tseung Kwan O –
Feasibility Study
Executive Summary
Table of Contents
1.2 Purpose & Nature of the Project
1.3 Purpose of this EIA Report
1.4 Justification for the Need of the
Desalination Plant
2.1 Project Components and Layout
2.4 Consideration of Alternative Sites,
Development Options, Construction Methods & Sequences
2.5 Environmental Friendly Design
3.4 Sewerage and Sewage Treatment Implication
3.9 Landscape and Visual Impact
3.12 Environmental Monitoring and Audit
Drawings
Figure 1.1 -
Location of the Proposed Desalination Plant at Tseung Kwan O
Figure 2.1 - Plant
Layout
Figure 2.2 -
Preliminary Construction Program of the Project
The Water
Supplies Department (hereinafter referred to as WSD) is proposing the
development of a medium-sized desalination plant in Hong Kong, at a site
reserved in Tseung Kwan O (TKO Area 137). The proposed desalination plant will produce
potable water with an initial capacity of 135 million liter per day (MLD),
expandable to an ultimate capacity of 270Mld in the future to provide a secure
and alternative fresh water resources complying with the World Health
Organization (WHO) standards. This
project is entitled “Desalination Plant at Tseung
Kwan O” (hereinafter referred to the Project).
Under the
Environmental Impact Assessment Ordinance (EIAO), an Environmental Permit (EP)
will be required for the construction and operation of the proposed Project. In
relation to this, WSD has prepared a Project Profile for application for an
Environmental Impact Assessment (EIA) study brief under section 5(1) of the EIAO (No. PP-497/2013). The
Project Profile was submitted to EPD on 5 December 2013. The EIA Study Brief (No. ESB-266/2013) was issued by EPD on 16 January 2014.
Black &
Veatch Hong Kong Limited (B&V) was commissioned by WSD under Agreement No.
CE 21/2012 (WS) to provide consultancy services to investigate and formulate a
detailed proposal for the Project and conduct the EIA study.
The EIA Report
addresses potential environmental impacts associated with the construction and
operation of the Project. This Executive Summary summarises the key
findings of the EIA.
The proposed
Project comprises the following:
· Construction of a new desalination plant in TKO Area 137 with a capacity of 135 Mld, expandable to 270 Mld in the future;
· Natural slope mitigation works consist of soil nailing, construction of flexible barriers and rock slope stabilization at the lower portion and toe of the natural slope within and in the close proximity of the Clear Water Bay Country Park (Figure 1.1), which overlooks the northeast boundary of the new desalination plant at TKO Area 137;
· Construction of a dedicated trunk feed system for the transfer of fresh water output from the desalination plant to the existing Tseung Kwan O Fresh Water Primary Service Reservoir (TKOFWPSR). The system consists of an about 9 km of 1200 mm diameter fresh water mains along Wan Po Road, Po Hong Road and Tsui Lam Road (fresh water main is indicated in Figure 1.1), the associated pipeworks and ancillary facilities including fittings/valves, leakage, flow and pressure monitoring facilities, and a new treated water pumping station and new treated water storage tank with estimated size about 22,500m3 located in the desalination plant; and,
· All the associated civil, structural, geotechnical, landscaping, electrical and mechanical works.
The location
of the Project and the associated works are shown in Figure 1.1.
The
following elements of the Project are classified as Designated Projects under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO)
and are addressed in this EIA Report:
· Schedule 2, Part I, Item E.2 – Water treatment works with a capacity if more than 100,000 m3 per day.
· Schedule 2, Part I, Item K.13 – A dangerous good godown with a storage capacity exceeding 500 tonnes.
· Schedule 2, Part I, Q.1 – Earthworks partly in an existing country park.
This EIA
Report is prepared in accordance with the EIA Study Brief (No. ESB-266/2013)
and the Technical Memorandum of the Environmental Impact Assessment
Process (EIAO-TM).
The purpose
of this EIA Study is to provide information on the nature and extent of
environmental impacts arising from the construction and operation of the
Project and related activities that take place concurrently. This information will contribute to decision
by the Director on:
· The acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
· The conditions and requirements for the design, construction and operation of the Project to mitigate against adverse environmental consequences; and
· The acceptability of residual impacts after the proposed mitigation measures is implemented.
The specific
objectives of the EIA Study are described in Clause 2 of the EIA
Study Brief, and the detailed requirements of the EIA Study are set out in Clause
3 of the EIA Study Brief.
As specified in the EIA Study Brief, the EIA Study has addressed
the key environmental issues associated with the construction and operation of
the Project in Hong Kong waters and land.
A secure
water supply is of utmost importance in sustaining Hong Kong’s
development. Currently, under the Dongjiang Water Supply Agreement, the Government of
Guangdong Province agrees to supply up to an ultimate annual quantity of 1,100
million m3 of freshwater to Hong Kong. However, when a severe drought happens, the
whole region of Dongjiang River Basin will likely
face water shortage. To better prepare
Hong Kong for uncertainties such as acute climate changes and low rainfall, the
Total Water Management (TWM) strategy has been promulgated by the Hong Kong SAR
Government in 2008. To this end, the WSD
has kept abreast of the latest developments in desalination technology and
prepared for the related planning and studies so that other water sources can
be tapped in good time in case of water shortage. A Feasibility Study (CE 71/2000 (WS)) and a
Pilot Plant Study (CE 97/2002 (WS)) on developing desalination facilities in
Hong Kong have been conducted in 2002 and 2007 respectively. These studies confirmed the technical
feasibility of using desalination technologies to produce potable water
complying with the World Health Organisation (WHO)
standards. WSD has assessed the
feasibility and cost effectiveness of building a medium-sized desalination plant
in Hong Kong, at a site reserved in Tseung Kwan O
(Area 137) to cope with the projected water demand.
There are a number of
benefits to develop the desalination plant for providing a secure and alternative fresh water
resource, including:
· Secure and alternative freshwater resources: the proposed desalination plant will produce up to 135 Mld during initial commissioning, which is equivalent to 22% of the mean gross yield collected from water gathering grounds over the past decade. After the expansion of the desalination plant, it can produce 270 Mld, which is equivalent to 44% of mean gross yield collected from water gathering grounds over the past decades. The proposed desalination plant can provide approximate 5% and 10% of contribution to the total freshwater demand in Hong Kong.
· Adequate freshwater resources available during climate change: as a coastal and well-developed city with scarce freshwater resources, Hong Kong has unlimited supply of seawater from the ocean that is not affected by the acute climate changes. Thus, the proposed desalination plant would be an appropriate solution to provide potable water and to provide alternative of the freshwater resources.
· Environmental Benefits: the seawater reverse osmosis technology adopted in the desalination plant is one of the low energy consumption and cost effective way to produce freshwater without imposing adverse impact to the environment than other desalination technologies.
According to
Hong Kong Observatory’s study report, climate change will bring about more
frequent extremely dry weather and increase the likelihood of the occurrence of
consecutive droughts. This will not only affect the local yield collected in
Hong Kong, but also impact on the water resources in Dongjiang
which contributes 70 – 80% of the freshwater demand in Hong Kong. Without the proposed Project, Hong Kong lacks
an alternative of freshwater resources and will be subjected to water shortage
arising from severe droughts which impact the water supply reliability in Hong
Kong. As such, the development of
proposed desalination plant is essential to secure Hong Kong’s freshwater
supplies.
Table 2.1 presents a summary of the project
details. The footprint of the proposed
desalination plant development at Tseung Kwan O Area
137 will be approximately 10 hectares (ha), with the trunk feed system
consisting of a 9.5 km of 1,200 mm in diameter of fresh water rising main along
Wan Po Road. A maximum total marine
dredging volume of 6,330 m3 (in situ) of marine sediments will be
generated from the two submarine utilities.
Natural slope mitigation works will be undertaken within 0.49 ha of the
Clear Water Bay Country Park.
The
preliminary layout plan for this Project is presented in Figure 2.1.
Table 2.1 Summary of Project Description
Details |
Preliminary
Design Information |
Submarine Utilities |
|
Area of
seabed affected by pipeline footprint |
|
·
Intake |
0.045 ha |
·
Outfall |
0.065 ha |
Marine
Dredging volume (in situ volume) |
|
·
Intake |
1,740 m3 |
·
Outfall |
4,590 m3 |
Rock fill
volume (in situ volume) |
|
·
Intake |
905 m3 |
·
Outfall |
4,320 m3 |
Length of
Submarine Utilities (m) |
|
·
Intake |
~ 200 to
250 m |
·
Outfall |
~ 300 to 350
m |
Diffuser |
|
·
Number of discharge port |
A total of
36 discharge ports with diameter of 150 mm |
·
Length of diffuser |
152 m with
port spacing of 4.2 m |
·
Configuration |
alternating
and inclined at 60° to horizontal |
Desalination Plant |
|
Area of
foundation occupied by the plant |
10 ha |
Building
parameters |
17
components with building height ranged between 2 m to 20 m |
Trunk Feed System |
|
Area of
land affected by the freshwater rising mains |
1.14 ha |
Excavation
volume |
42,733 m3 |
Length of
the freshwater rising main |
9,500 m |
Diameter
of the freshwater rising main |
1,200 mm |
Natural Slope Mitigation Works |
|
Area of
slope mitigation works |
0.49 ha
within the Clear Water Bay Country Park |
|
|
The proposed
site for the desalination plant is located in Tseung
Kwan O (TKO) Area 137 with a reserved site area of about 10 ha. TKO Area 137 is located to the south of the
Southeast New Territories (SENT) Landfill and the Tseung
Kwan O Industrial Estate. It faces the
Clearwater Bay Country Park to its east, the Joss House Bay to its south and
the Tathong Channel to its west. The nearest residential area is the LOHAS
Park which is located about 2.5 km from the site.
The site is
on reclaimed land which was reclaimed between 1998 and 2000. The natural slope overlooking the northeast
boundary of the new desalination plant at TKO Area 137 has a history of minor
landslides and contains some potentially unstable boulders.
No permanent
major infrastructure has been built in and around the proposed site. At present, three major facilities are
located in the vicinity of the site, namely a temporary public fill bank, a
temporary explosive magazine and an explosives off-loading barging pier.
The
preliminary construction programme is provided in Figure 2.2.
The construction for
the project will be separated into two major contracts. Package A is for plant and other ancillary
facilities and Package B is for mainlaying of the
trunk feed. The Package A contract is
scheduled to commence in 3rd quarter of year 2017 for
completion of the construction in 3rd
quarter of year 2020. The Package B
contract is scheduled to commence in 2nd quarter of year 2016 for
completion of the construction in 4th quarter of year 2019. The major construction activities for the
Project would comprise site clearance, excavation and backfilling, erection of
formwork and reinforcement, concreting, fabrication of steelwork, and testing
and commissioning.
An assessment was
conducted to investigate the environmental considerations of alternative sites,
development options, construction methods and sequences for this Project. Alternatives considered were as follows:
·
Site
selection: Comparing to the
western waters in Hong Kong, the eastern waters in Hong Kong is oceanic in
nature with less turbidity, lower SS levels and relatively consistent in
quality with relatively less variation in salinity, which is beneficial to the
operations of the desalination plant and should be put in a higher priority for
the development of desalination plant.
·
Desalination
technology using multi-stage flash distillation (MSF) or seawater reverse
osmosis (SWRO): Compared with MSF, SWRO technology has definite advantages of
less energy consumption, no local emission of fossil fuel consumption and
relatively economic viable. SWRO is thus
adopted as the preferred method for desalination process.
·
Construction
of submarine pipeline by dredging or trenchless method: Comparing to dredging
method, trenchless method with localized dredging will effectively reduce the
dredging volume and greatly minimize the potential impacts on water quality,
marine ecology and fisheries associated with dredging activities. Therefore, trenchless method with localized
dredging is the preferred option for the installation of submarine pipelines,
intake and outfall.
·
Alignment
of freshwater rising main along Wan Po Road or via Junk Bay: Alignment of
freshwater rising main along Wan Po Road is chosen as the preferred option for the trunk main due to the
drawbacks on marine ecology and water quality from alignment of freshwater
rising main via Junk Bay.
·
Disinfection
technologies using chlorination, ozonation or UV
radiation: For ozonation and UV disinfection, they
are not capable to provide residual disinfectant and chlorination, with lower
dosage, is still be required. Thus chlorination is the preferred option for
disinfection in the Plant.
·
Slope
mitigation by set back, passive protection, active
protection or mixed protection: Slope mitigation by set back would result in an extensive loss of usable
land for implementation of the project and is considered not viable. Slope mitigation by passive protection is not
recommended due to the unacceptable residual risk on the desalination plant and
its operators from major landslides and boulder fall hazards. For slope mitigation by active protection,
extensive disturbance to natural habitat within Country Park would be
unavoidable and thus this option is not considered due to the environmental
drawback. Mixed protection such as localized
stabilization works on the slope area will be optimized to avoid the impact to
the existing vegetation and to minimize the impact to the Country Park as much
as practicable. To
achieve minimization of environmental disturbance, slope mitigation by mixed
protection is recommended.
·
Concurrent
construction works or scheduled in multiple works package: Comparing to
concurrent construction works, the construction duration for multiple works
package will be shorter and hence reduce potential disturbance to the
environment and the local public.
The preferred
scenario of the proposed desalination plant development is presented in Section 2.1 and Figure 2.1. The selection of the preferred alternative
has brought about a series of environmental benefits to the Project, including:
· The provision of alternative potable water source and alleviate the shortage of freshwater resources due to climate change and subsequent adverse weather;
· The trunk feed system are proposed to be constructed underneath Wan Po Road to minimize disturbance to sensitive receivers and natural habitats;
· The use of localized soil nailing, localized rock stabilization and localized flexible barrier for slope mitigation has minimized the disturbance to the natural habitats at the Clear Water Bay Country Park;
· The alignment and length of submarine utilities require minimum submarine excavation works and thus the potential impacts on water quality, marine ecology and fisheries are reduced;
· The use of micro-tunnelling machine for construction of the proposed submarine utilities reduces the extent of seabed dredging and dredging volume, thereby reducing the marine footprint of this project and the potential impacts on water quality, marine ecology and fisheries; and,
· The recommended land-based construction methods are expected to avoid prolonged construction duration and hence reduce potential disturbance to the environment and the local public.
In order to preserve
the environment in the vicinity of the project, a review of the latest
development of various desalination technologies, including seawater reverse
osmosis (SWRO) and Multi-stage Flash Distillation (MSF), was conducted for
recommendation of environmental friendly design. The results indicated that SWRO is more
suitable to be adopted as the desalination technology of the proposed Project,
taking into consideration the following advantages:
· No boiler is required, thus no generation of NOx and with least energy consumption
· Proven technology with the capacity to treat large amount of seawater
· Long track record of operation
· Less land requirement for the treatment units
· Less operation complexity
· Less capital and operating costs
The potential
environmental impacts associated with the Project are summarised in the
following sections.
The air quality
impact assessment has examined construction and operation phase impacts of the
Project in accordance with the criterial and guidelines stated in the EIAO – TM Annex 4 and Air Pollution
Control Ordinance (APCO) (Cap. 311).
In accordance with
the EIA Study Brief Section 3.4.2.2
of the Project, the Study Area for the air quality impact assessment is
generally defined by a distance of 500m from the boundary of the Project
Site. A total of 20 ASRs were identified
and illustrated in Figure 4.1 of the EIA Report.
Potential dust
nuisance from construction activities and gaseous emissions from plant have
been evaluated. With the implementation
of the recommended dust control measures and good construction site practices,
it is not anticipated that the construction of the Project will cause adverse
dust and air quality impacts.
By reviewing the
process flow during the operation phase, unacceptable impacts due to gaseous
emission from the standby generator within the desalination plant and odour
nuisance from chemical sludge are not anticipated.
With the
implementation of good management practices and proper odour control measures,
no unacceptable residual impacts have been predicted to occur during the
construction and operation phases.
Regular site inspections and audits will be undertaken during the
construction phase to verify that proposed mitigation measures are being
implemented.
The potential impacts
of noise caused by construction and operation activities of this Project have
been assessed in this EIA Report. The
impacts have been identified and analysed to be in compliance with the criteria
and guidelines stated in the EIAO-TM
Annexes 5 and 13 respectively.
In accordance with
the EIA Study Brief Section 3.4.3.2
of the Project, the Study Area for the noise assessment includes all areas
within 300 m from the Project Boundary.
A total of 36 NSRs were identified and illustrated in Figure
5.3 of the EIA Report.
To minimize construction noise and disturbance to the local public and
road users, the freshwater mains shall be constructed in multiple works
packages with restricted 40m per workfront (not more
than 4 concurrent workfronts).
Since the desalination plant is located distant from the representative
noise sensitive receivers (NSRs), the predicted noise levels at the
representative NSRs would comply with the stipulated construction noise
criteria. For mainlaying
works, the predicted unmitigated noise levels would range from 37 to 93 dB(A)
at the representative NSRs. To mitigate
the noise impact, construction noise control measures such as adopting quiet
plant, use of movable noise barriers close to construction plants, noise
insulation sheets, noise scheduling of construction activities and noise
enclosure, have been recommended.
Predicted mitigated noise levels at all NSRs are in the range of 38 to 75 dB(A) and 37 to 87 dB(A) at residential NSRs and educational NSRs,
respectively. To further mitigate the residual
noise impacts at the corresponding educational NSRs during construction phase, the
construction work in the influence areas near the corresponding educational NSRs will
be scheduled during long school holidays (e.g. summer holiday, Easter holiday or
Christmas holiday, etc.) as far as practicable. No adverse noise impacts are anticipated with the implementation of the
practical mitigation measures. Full
compliance with the EIAO requirements is anticipated with proper implementation
of the proposed mitigation measures. A
systematic EM&A programme will be carried out to ensure proper
implementation of both construction phase mitigation measures and the
construction schedule of the works of freshwater rising mains.
All equipment within
the desalination plant will be accommodated inside plant room and fully
enclosed, thus no adverse noise impacts are expected during the operation phase
of the Project.
The water quality
impact assessment has examined construction and operation phase impacts of the
Project in accordance with the criterial and guidelines stated in the EIAO – TM Annexes 6 and 14, and
applicable assessment standards/ criteria.
The assessment, utilising water quality and hydrodynamic computational
models, has been examined the potential impacts caused by marine works during
construction phase and effluent discharge of reverse osmosis (RO) concentrates
during operation phase.
Trenchless method
with localised minor dredging will be adopted as the preferred option for the
construction of the proposed submarine outfall to reduce potential impacts of
the marine dredging works on water quality, marine ecology and fisheries of the
Joss House Bay.
Computational
modelling has been conducted to predict various potential water quality impacts
from the proposed marine dredging for the construction of submarine pipelines,
including sediment solids (SS) elevation, sedimentation, dissolved oxygen (DO)
depletion, release of nutrient, heavy metal and trace organic pollutants. The
estimated dredged volumes are about 1,740 m3 (seawater intake) and
4,590 m3 (submarine outfall).
Working hours are assumed to be 12 hours per day with a maximum dredging
rate of 3,500 m3/day (i.e. 0.081 m3/s). It is assumed that dredging for seawater
intake and submarine outfall would not be conducted concurrently. Only one closed grab dredger would be working
and spillage of mud from closed grab dredgers is assumed to take place
uniformly over the water column. Under
unmitigated scenario, full compliance is predicted at all identified water
sensitive receivers, with the exception of exceedance in SS elevation predicted
at four coral WSRs, including SR4 (Tai Miu Wan), SR16
(Fat Tong Chau), SR36 (Kwun Tsai) and SR37 (Tit Cham Chau). With the implementation of silt curtain
during dredging works and reduced dredging rate at seawater intake, the
predicted SS elevation at these WSRs would be in full compliance.
The
discharge of RO concentrate from the desalination process is the main
environmental concern for the Project operation. Results of the modelling works indicate that
the effluent plume of RO concentrates would be highly localized and the
elevation in salinity and other chemicals would be diluted soon after
discharging from the submarine outfall.
No observable mixing zone is predicted for most discharge scenarios for
most chemicals constituents. Where
mixing zone is predicted, it would be closely confined near the submarine
outfall and would not encroach to any nearby WSRs. Thus, impacts on water quality and hydrodynamics
are predicted to be within acceptable levels.
Water quality
monitoring is recommended for the construction and operation phases. A silt curtain efficiency test for the
combined use of floating silt curtain type and cage type silt curtain for dredging
at seawater intake will also be completed prior to intake dredging works
commencement to confirm the silt curtain reduction efficiency assumptions of
the assessment. The specific monitoring
requirements are detailed in the Environmental
Monitoring and Audit (EM&A) Manual associated with the EIA Report.
The
assessment of sewerage and sewage treatment implication is conducted in
accordance with the EIAO-TM Annex 14
and applicable assessment standards/ criteria.
Construction
of the section of gravity sewer from the plant to connect with the existing
public sewer would mainly involve conventional technology such as cut and cover
excavation techniques.
The sewerage
facilities provided as part of the proposed plant will be maintained by the
government after completion. No specific
maintenance operations are envisaged but it is considered desirable that the
facilities will be inspected regularly to ensure that these sewers can function
properly.
The detailed
design of the proposed sewerage system will be circulated to DSD, EPD and other
relevant parties for comment during planning and detailed design stage to
ensure acceptance by relevant parties.
Access for sewers, equipment and personnel for maintenance of the works
would also be adequately provided.
Therefore, no adverse residual impact on sewage treatment is anticipated.
The potential impacts
to waste management caused by construction and operational activities of this
Project have been assessed in this EIA
Report. The impacts have been
identified and analysed to be in compliance with the criteria and guidelines
stated in the EIAO-TM Annexes 7 and 15 respectively. Legislative
requirements and assessment criteria relevant to the waste management
assessment have also been presented.
The waste arisings during the construction and operation phases
include excavated material, construction and demolition material, marine
sediments from dredging works, general refuse from daily operations, chemical
waste from maintenance of plant and equipment and sludge from the desalination
plant. The quantity, quality and timing
of these waste arisings have been identified. It is estimated that the quantities of excavated
materials to be generated from the construction of the seawater intake and
outfall, desalination plant and the mains laying are
approximately 785 m3, 402 m3, 183,720 m3 and
42,733 m3, respectively. The
construction of desalination plant shall involve slope mitigation works, which will
also generate about 56 m3 of excavated materials. The total
quantity of marine sediments generated will be approximately 7,346 m3. Approximately
a total of 4,556 m3 of public fill and 1,139 m3 of
construction waste will be generated from the construction of civil structures
and buildings at the project site. With good site
practices, the potential environmental impacts associated with the storage,
handling, collection, transport and disposal of the identified waste arisings from the Project will be within acceptable limits
set out in the EIAO-TM. No adverse waste management impacts are
anticipated.
Regular site
inspections and audits will be undertaken during the construction phase to
verify that proposed mitigation measures are being implemented.
The impacts
of land contamination are assessed in accordance with the EIAO-TM Annex 19 and applicable assessment standards/ criteria.
Based on the
review of historical aerial photographs, the Temporary Magazine Storage Site
(TMS) was once part of the sea prior to reclamation finished in 2000. After the completion of the reclamation work,
the TMS was left vacant until the magazine storages and other associated
facilities were constructed in 2012.
Therefore the risk of potential land contamination due to land use prior
to the 2012 is anticipated to be low.
Before the
hand‐over of the TMS Site to WSD for further development, the owner of
TMS Site and its contractor shall ensure the TMS site is properly cleaned up before
handover to CEDD. After the TMS Site is handed over to WSD and before the
commencement of any construction work, the contractor of WSD shall prepare a
Contamination Assessment Plan (CAP) for EPD endorsement prior to the
commencement of site investigation. A
Contamination Assessment Report (CAR) shall be prepared to summarise
the results of the site investigation. If land contamination is identified, a
Remediation Action Plan (RAP) shall be prepared to identify feasible
remediation methods and a Remediation Report (RR) shall be prepared to
demonstrate completion of remedial actions for EPD endorsement
Regular site
inspections and audits will be undertaken during the construction phase to
verify that proposed mitigation measures are being implemented.
The EIA has described
the impacts on terrestrial and aquatic ecological resources associated with the
construction and operation of the proposed submarine facilities and
desalination plant. The purpose of the
assessment was to evaluate the predicted impacts to ecological resources as per
the criteria and guidelines stated in the EIAO-TM
Annexes 8 and 16 respectively.
A total of
11 habitat types were identified within the Study Area. They are terrestrial habitats (i.e. mixed
woodland, plantation, shrubland-grassland,
agricultural land, wasteland, watercourse and urbanised/disturbed
area) and coastal habitats (i.e. rocky shore, sandy shore, subtidal hard and
soft bottom habitats and artificial seawall habitat), all of the habitats are
of very low or low ecological value, except for subtidal hard and soft bottom
habitats, watercourse (natural section), mixed woodland and shrubland/grassland
of low to moderate ecological value.
Apart from this, the Clear Water Bay Country Park is the recognized ecologically
important/ sensitive sites are located within the Study Area in which 0.49 ha
of slope mitigation works will be carried out.
It is noted
that a majority (~90%) of the Desalination Plant Site consists of man‐made
habitats with very low to low ecological values. The mixed woodland and shrubland/
grassland habitats of the area for slope mitigation works were located at the
edge of Clear Water Bay Country Park with relatively low abundance and
diversity of fauna and the trees were mostly native and common species of fair
condition, as a result they are considered to be of low to moderate ecological
value. The watermain
is located on existing roads which are of no particular ecological value, and
the submarine facilities are located on the seabed with soft and hard bottom
communities typical in other similar habitats of Hong Kong.
One flora (Marsdenia lachnostoma)
and five birds (including Black Kite, Black-crowned Night Heron, White-throated
Kingfisher, Collared Scops Owl and Lesser Coucal) species of conservation interest were recorded
within the footprints of the desalination plant and slope mitigation
works. Considering the mobility of bird
species and the availability of similar habitats in the surrounding environment,
the potential impact on fauna species of conservation concern is considered to
be minimal. In addition, tree felling
has been avoided for the selected slope mitigation works, such that habitats
within slope mitigation works area remain to be available to fauna
species. The construction of flexible
barriers has the potential to directly affect the flora species of conservation
interest Marsdenia lachnostoma recorded
along the indicative alignment of the flexible barriers. All individuals of Marsdenia lachnostoma within the slope mitigation
areas shall be retained in-situ, by positioning the alignment of flexible
barriers at a minimum 1.5 m in a radius away from these individuals. No trees will be felled for the
implementation of slope mitigation works.
Temporary fencing will be installed to fence off Marsdenia lachnostoma specimens to prevent from
being damaged and disturbed during construction.
Construction
impacts to marine ecological resources have largely been avoided by optimizing
the length and alignment of the submarine facilities to avoid key ecologically
sensitive areas for coral communities, and by applying the trenchless method
for installing submarine intake and outfall and through proper planning design
and execution of the works (i.e. optimisation of
project construction schedule/ sequence, using good engineering/ industry
practice, timely completion of construction works to reduce impact duration,
etc.).
During the
construction phase, construction activities may cause direct ecological impacts
including habitat loss and vegetation removal, whereas indirect impacts on
wildlife include disturbances and changes in water quality. Potential impacts of increased human activities and
other disturbances due to the Project construction would not be significant
provided that regular checks on construction site practices and boundaries will
be conducted. In addition, in the
view of the
availability of surrounding similar habitats, the potential impact on wildlife
especially on the species of conservation interest as a result of habitat
fragmentation and isolation is considered to be minimal.
The EIA sets out
mitigation measures to reduce ecological impacts, such as regular checks in
construction site practices and boundaries, which will reduce potential
disturbance to the surrounding environment.
With the implementation of the
proposed mitigation measures, no adverse residual impact due to the land-based
and marine-based construction of proposed desalination plant, slope mitigation
works, freshwater rising main and submarine intake and outfall pipelines is
anticipated.
The EIA has described
the impacts to fisheries resources and fishing operations associated with the
construction and operation of the Project.
The purpose of the assessment was to evaluate the predicted impacts to
fisheries resources and fishing operations as per the criteria and guidelines
stated in the EIAO-TM Annexes 9 and 17 respectively.
Based on the desktop
review of baseline conditions of commercial fisheries resources and fishing
operations suggest that the surrounding waters of the Project, the potential
fisheries sensitive receivers identified include spawning and nursery ground of
commercial fisheries resources at Port Shelter, artificial reefs at Outer Port
Shelter area and Fish Culture Zone at Tung Lung Chau. The potential fisheries sensitive receivers
are located at least 1 km from the proposed submarine facilities of the
Project. Results from the literature
review indicate that fisheries importance of the Project Area and its vicinity
is low when compared to other waters of Hong Kong.
Impacts to
fisheries resources, habitats and fishing operations during construction and
operation phase are considered to be within acceptable level. The permanent loss of 0.11 ha of seabed
fisheries habitat for the installation of submarine utilities is considered to
be of negligible significance and within acceptable level.
Monitoring activities
designed to detect and mitigate any unacceptable impacts to water quality
during construction phase are also expected to serve to protect against
unacceptable impacts to fisheries. No
fisheries-specific monitoring measures are required during construction or
operation activities.
The EIA has described
the landscape and visual impacts associated with the construction and operation
of the Project as per the criteria and guidelines stated in the EIAO-TM Annexes 10 and 18 respectively.
The majority of the
Project Site falls within the existing fill bank at
Fat Tong Chau which is currently landscape of low quality with little valuable
vegetation or amenity value and therefore in general the Project at
construction and operation is considered to have little landscape impact. Based on the
broad brush tree survey, approximately
320 trees are located in the direct footprint of the slope mitigation works
area, where careful design will seek to work around them and avoid any tree
felling. However, approximately 200
trees, which are mainly native and common tree species, within the direct
footprint of the desalination plant facilities will require felling. Considering
the available space for tree planting within the project boundary,
approximately a total of 300 nos. of heavy standard trees and light standard
trees are proposed to be planted on‐site at the desalination plant site
to compensate for the tree to be felled.
If needed, off‐site compensatory planting at Siu Ho Wan water
treatment works and other waterworks facilities maintained by WSD would be
undertaken. It is
considered that given the compensatory tree planting and the proposed careful
greening of the Project Site landscape, the overall residual impact on existing
trees and greenery would be reduced to an acceptable level.
The visual impact assessment confirms that overall the
visual sensitive receivers (VSRs) will experience moderate to insignificant
visual impacts due to the construction and operation of the Project without
mitigation. With mitigation measures centred around the principles of careful detailed design of
the facilities to blend with the existing landscape, conserving existing
greenery and providing some soft landscaping (e.g. roadside planting, etc), all visual impacts are considered to be slight or
insignificant by year 10 of operation.
The landscape and visual impacts of the Project are thus considered
acceptable with mitigation measures.
The potential hazards
associated with sub-surface migration of landfill gas from the TKO Stage II/III Restored Landfill, TKO Stage
I Restored Landfill, SENT Landfill and SENT Landfill Extension have been assessed
in accordance with the EIAO-TM Annexes 7
and 19.
The
qualitative risk assessment has concluded that the potential for landfill gas
to affect the desalination plant and fresh water mains during the operational
phase is low to medium. During the
construction period, similar hazards may also arise related to the flammability
or the potential asphyxiating properties of landfill gas and/ or the
potentially toxic nature of leachate.
Given the results of the qualitative risk assessment, it should be
assumed that the risks due to the landfill gas or leachate during the
construction are low to medium.
In general,
underground rooms or voids should be avoided as far as practicable in the
design of the infrastructure area of the Project. Other precautionary and protection measures
during construction and operation phases of the Project have been
recommended. It is expected that with
the proposed precautionary measures in place, the potential risk of landfill
gas migration to the respective targets will be minimal.
Monitoring of
landfill gas shall be undertaken in all excavations, manholes, chambers and any
confined spaces prior to the entry.
Regular site inspections and audits will be undertaken during the
construction phase to verify that proposed mitigation measures are being
implemented.
A Hazard
Assessment of the risks associated with the use, storage and transport of
chlorine and dangerous goods (DGs) at the proposed Desalination Plant has been
conducted for the operational phase (Year 2036) of the Project. The cumulative risk of the Project, through
interaction or in combination with other existing, committed and planned
developments involving DGs in the vicinity of the Project has also been
assessed.
In all
cases, the Individual Risk complies with the Hong Kong Risk Guidelines and the
Societal Risk lies in the acceptable region. The societal risk expressed in the
form of FN curves, lies in the acceptable region of the HKRG for the use,
transport and storage of chlorine at the Desalination Plant.
Therefore,
the operation of the Desalination Plant is acceptable in terms of both
individual risk and societal risk as stipulated in Annex 4 of the EIAO-TM. Safeguard measures are recommended to ensure the risk
associated with the use, storage, and transport of chlorine and DGs at the
proposed Desalination Plant complies with the Hong Kong Risk Guidelines and
stays in “Acceptable” region.
Environmental
monitoring and audit requirements have been identified and recommended to
ensure the effectiveness of the recommended mitigation measures. These requirements are specified in the EM&A Manual. The monitoring requirements cover the area of
noise, water quality and landfill gas hazard.
Regular site audits throughout the construction and operation of the
Project have also been recommended.
The environmental
impact assessment (covering air quality, noise, water quality, waste
management, land contamination, sewerage, ecology, fisheries, landscape and
visual impact, landfill gas hazard, and hazard to life) has concluded that no
unacceptable environmental impacts are envisaged as a result of the
construction and operation of the Project, provided that the recommended
mitigation measures are implemented.
Recommendations for
an environmental monitoring and audit programme have been prepared to ensure
the effectiveness of the recommended mitigation measures.