Agreement No. CE 21/2012 (WS)
Desalination
Plant at Tseung Kwan O –
Feasibility Study
Environmental
Impact Assessment Report
Table of Content
Chapter
1 |
|
1.1 |
Background |
1.2 |
Purpose and Nature of the Project |
1.3 |
Purpose of the EIA |
1.4 |
Location and Scale of the Project & History of the Site |
1.5 |
The Scoping of Environmental Issues |
1.6 |
Structure of this Report |
2 |
|
2.1 |
Need of the Project |
2.2 |
Consideration of Alternative Sites – Site Selection |
2.3 |
Consideration of Alternative Development Options |
2.4 |
Consideration of Alternative Construction Methods |
2.5 |
Consideration of Works Sequences |
2.6 |
Selection of Preferred Scenario |
3 |
|
3.1 |
The Project |
3.2 |
Project Design |
3.3 |
Project Components |
3.4 |
Construction of Project |
3.5 |
Project Operation |
3.6 |
Project Summary |
3.7 |
Project Programme |
3.8 |
Concurrent Projects |
4 |
|
4.1 |
Introduction |
4.2 |
Statutory Requirements and Evaluation Criteria |
4.3 |
Baseline Condition |
4.4 |
Study Area and Identification of air Sensitive Receivers |
4.5 |
Potential Sources of Impacts |
4.6 |
Evaluation of Impacts |
4.7 |
Cumulative Impacts |
4.8 |
Mitigation Measures |
4.9 |
Residual Impacts |
4.1 |
Environmental Monitoring and Audit |
4.11 |
Conclusions |
5 |
|
5.1 |
Introduction |
5.2 |
Relevant Legislation and Guidelines |
5.3 |
Description of the Noise Environment |
5.4 |
Potential Sources of Impact |
5.5 |
Assessment Methodology |
5.6 |
Evaluation of Impacts |
5.7 |
Mitigation Measures |
5.8 |
Cumulative Impact |
5.9 |
Residual Impact |
5.1 |
Environmental Monitoring and Audit |
5.11 |
Conclusions |
6 |
|
6.1 |
Introduction |
6.2 |
Legislation Requirements and Guildline |
6.3 |
Baseline Condition |
6.4 |
Water Quality Sensitive Receivers |
6.5 |
Assessment Criteria |
6.6 |
Assessment Methodology |
6.7 |
Potential Sources of Impact |
6.8 |
Impact Assessment |
6.9 |
Mitigation Measures |
6.1 |
Residual Impact |
6.11 |
Mitigation Measures |
6.12 |
Environmental Monitoring and Audit |
6.13 |
Conclusions |
7 |
|
7.1 |
Relevant Legislative Requirements |
7.2 |
Assessment Methodology |
7.3 |
Existing Sewerage Facilities and Planned Sewerage in the Area |
7.4 |
Estimated Sewage Flow |
7.5 |
Proposed Sewerage Disposal Strategy |
7.6 |
Mitigation Measures |
7.7 |
Environmental Monitoring and Audit |
7.8 |
Conclusion |
8 |
|
8.1 |
Introduction |
8.2 |
Legislation Requirements and Evaluation Criteria |
8.3 |
Expected Waste Arisings during the
Construction Phase |
8.4 |
Expected Waste Arisings during the Operation
Phase |
8.5 |
Mitigation Measures |
8.6 |
Residual Environmental Impacts |
8.7 |
Environmental Monitoring and Audit |
8.8 |
Conclusions |
8A |
|
8A.1 |
Introduction |
8A.2 |
Legislation Requirements and Evaluation Criteria |
8A.3 |
Project Design and Site Setting |
8A.4 |
Identification of Sensitive Receivers |
8A.5 |
Assessment methodology |
8A.6 |
Land Contamination Impact Evaluation and Mitigation Measures |
8A.7 |
Conclusion |
|
|
|
|
9 |
|
9.1 |
Introduction |
9.2 |
Legislative Requirements & Evaluation Criteria |
9.3 |
Baseline Conditions |
9.4 |
Impact Identification |
9.5 |
Impact Assessment |
9.6 |
Impact Evaluation |
9.7 |
Mitigation Measures |
9.8 |
Cumulative Ecological Impact |
9.9 |
Residual Impact |
9.1 |
Environmental Monitoring & Audit (EM&A) |
9.11 |
Conclusions |
10 |
|
10.1 |
Introduction |
10.2 |
Relevant Legislation and Assessment Criteria |
10.3 |
Baseline Conditions & Fisheries Sensitive Receivers |
10.4 |
Assessment Methodology |
10.5 |
Potential Impacts & Impact Assessment on Fisheries Resources |
10.6 |
Impact Evaluation |
10.7 |
Mitigation Measures |
10.8 |
Residual Impacts |
10.9 |
Cumulative Impacts |
10.1 |
Environmental Monitoring & Audit |
10.11 |
Conclusions |
11 |
|
11.1 |
Introduction |
11.2 |
Environmental Legislation, Standards and Guidelines |
11.3 |
Scope of the Study |
11.4 |
Review of Planning & Development Control Framework |
11.5 |
Methodology - Landscape Impact Assessment |
11.6 |
Methodology - Visual Impact Assessment |
11.7 |
Landscape Baseline Conditions |
11.8 |
Visual Baseline Conditions |
11.9 |
Identification of Potential Sources of Landscape and Visual Impacts |
11.1 |
Landscape Impact Assessment |
11.11 |
Visual Impact Assessment |
11.12 |
Conclusion |
12 |
|
12.1 |
Introduction |
12.2 |
Landfill Gas Risk Assessment Methodology |
12.3 |
Nature of the SENT Landfill and TKO Stage II/III and I Restored
Landfills |
12.4 |
Proposed Desalination Plant and Fresh Water Mains |
12.5 |
Potential for the Development to Intercept Landfill Gas |
12.6 |
Qualitative Assessment of Risks due to Landfill Gas |
12.7 |
Recommended Precautionary and Protection Measures for the Construction
and Operation of the Desalination Plant and Fresh Water Mains |
12.8 |
Conclusions |
13 |
|
13.1 |
Introduction |
13.2 |
QRA for the On-site Transport, Storage and Use of Chlorine at the
Proposed Desalination Plant |
13.3 |
QRA for Off-site Transport of Chlorine |
13.4 |
QRA for Use, Storage and Transport of Sodium Hypochlorite |
13.5 |
Transport (On-site and off-site), Storage, Handling of Cryogenic and Pressurised Liquid Carbon Dioxide |
13.6 |
Other Risk Issues Associated with the Proposed Desalination Plant |
13.7 |
Cumulative Risk Assessment |
13.8 |
Uncertainty Analysis |
13.9 |
Conclusions and Recommendations |
13.1 |
References |
14 |
|
14.1 |
Introduction |
14.2 |
Objectives of EM&A |
14.3 |
Air Quality |
14.4 |
Noise |
14.5 |
Water Quality |
14.6 |
Sewerage and Sewage Implication |
14.7 |
Waste Management |
14.8 |
Land Contamination |
14.9 |
Ecology |
14.1 |
Fisheries |
14.11 |
Landscape and Visual Impact |
14.12 |
Landfill Gas Hazard |
14.13 |
Hazard to Life |
14.14 |
Summary of EM&A Measures |
15 |
|
15.1 |
Introduction |
15.2 |
Considerations of Alternatives |
15.3 |
Air Quality Impact |
15.4 |
Noise Impact |
15.5 |
Water Quality Impact |
15.6 |
Sewerage and Sewage Treatment Implication |
15.7 |
Waste Management Implication |
15.8 |
Land Contamination Assessment |
15.9 |
Ecological Impact (Terrestrial and Aquatic) |
15.1 |
Fisheries Impact |
15.11 |
Landscape & Visual Impacts |
15.12 |
Landfill Gas Hazard |
15.13 |
Hazard to Life |
15.14 |
Environmental Outcomes and Environmental Benefits of the Project |
|
|
|
Appendices
Photos
of Existing NSRs |
|
Preliminary
Construction Programme |
|
Construction
Plant Inventory (Unmitigated Scenario) |
|
Construction
Noise Assessment (Unmitigated Scenario) |
|
Construction
Plant Inventory (Mitigated Scenario) |
|
Construction
Noise Assessment (Mitigated Scenario) |
|
Water
Modelling Method Statement |
|
Result of Construction Phase Sediment Plume Modelling |
|
Detailed Result of CORMIX Modelling |
|
Result of Operational Phase Effluent Discharge Modelling |
|
Result of Operational Phase Saline Discharge Modelling |
|
Material Safety Data Sheet of Typical Antiscalant |
|
Seawater Sampling Result |
|
Result of Sediment Testing and Elutriate Test |
|
Layout Plan of Proposed Desalination Plant |
|
Details of Hydraulic Calculation |
|
Hydraulic
Modelling Results |
|
C&DMMP |
|
Sediment
Quality Result between September and October 2013 |
|
Site
Investigation Record |
|
Site Walkover
Checklist |
|
Baseline
Ecological Survey Report |
|
Supplementary
Ecological Survey Report |
|
Landfill
Gas Monitoring Result |
|
Groundwater
Monitoring Result |
|
Detailed
Record of Underground Utilities |
|
PHAST
Flat Terrain Dispersion Modelling Results for On-site Chlorine Hazard
Assessment |
|
CFD
Modelling Results for On-site Chlorine Hazard Assessment (with Offsite
Impact) |
|
CFD
Modelling Results for On-site Chlorine Hazard Assessment – 0.3 kg/s and 0.56
kg/s continuous releases |
|
Application
of Dispersion Modelling Results in QRA for On-site Chlorine Hazard Assessment |
|
Marine
Population Survey |
|
Seismic
Hazard Assessment |
|
Tsunami
Hazard Assessment |
|
Fault
Tree Analysis of On-site Chlorine Release |
|
Fault
Tree Analysis of Off-site Chlorine Release |
|
Fault
Tree Analysis of On-site Sodium Hypochlorite Release |
|
Figures
for Liquid Carbon Dioxide Assessment |
|
HAZID
Worksheet and Relevant Drawings |
|
Uncertainty
Analysis |
|
List of
Major Assumptions |
|
Implementation
Schedule of Recommended Mitigation Measures |
Drawings
Location
of the Proposed Desalination Plant at Tseung Kwan O |
|
Shortlisted
Location for Constructing a New Desalination Facility in Hong Kong |
|
Various
Options of Desalination Plant Footprint |
|
Slope
Mitigation Works - Option 1 |
|
Slope
Mitigation Works - Option 2 |
|
Slope Mitigation
Works - Option 3 |
|
Slope
Mitigation Works - Option 4 |
|
Approximate
Location of the Proposed Algnment of the Flexible
Barrier |
|
Illustration
of Hazard Mitigation Works |
|
Example
of Flexible Barrier for Natural Terrain Hazard Mitigation |
|
Illustration
of Hazard Mitigation Works |
|
Illustration
of Hazard Mitigation Works |
|
Illustration
of Hazard Mitigation Works |
|
Illustration
of Hazard Mitigation Works |
|
Proposed
Sewerage System |
|
Submarine
Outfall at Different Locations |
|
Submiarine Outfallat
Different Locations |
|
Location
of the Proposed Desalination Plant at Tseung Kwan O |
|
Dredging
Area for the Intake and Outfall Pipe |
|
Desalination
Plant Layout Plan |
|
Location
Plan for Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Location
of the Proposed Desalination Plant at Tseung Kwan O |
|
Process
Flow Diagram |
|
Location
of Representative Air Sensitive Receivers |
|
The 300m
Study Area For Noise Impact Assessment |
|
Locations
of Existing Noise Sensitive Receivers For Assessment (Page 1 of 4) |
|
Locations
of Existing Noise Sensitive Receivers For Assessment (Page 2 of 4) |
|
Locations
of Existing Noise Sensitive Receivers For Assessment (Page 3 of 4) |
|
Locations
of Existing Noise Sensitive Receivers For Assessment (Page 4 of 4) |
|
Locations
of Planned Noise Sensitive Receivers For Assessment |
|
Locations
of Pipe Jacking Works Area |
|
Locations
of Construction Areas Yielding Residual Impacts During School Hours (Sheet
No. Of 1) |
|
Locations
of Construction Areas Yielding Residual Impacts During School Hours (Sheet
No. Of 2) |
|
Locations
of Noise Enclosure for Sawcutting Pavement |
|
Locations
of Noise Enclosure for Sawcutting Pavement |
|
Locations
of Noise Enclosure for Sawcutting Pavement |
|
Indicative
Arrangement of Three Workfronts |
|
Indicative
Arrangement of Four Workfronts |
|
Water
Sensitive Receivers of the Surrounding Environment |
|
Model
Output Location |
|
Location
of Geophysical Survey Stations |
|
Indicative
Layout Plan for Deployment of Silt Cutrains For
Dredging at Seawater Intake |
|
Indicative
Layout Plan for Deployment of Silt Cutrains For
Dredging at Submarine Outfall |
|
Maximum
SS Elevation at Bottom Layer in Wet Season |
|
Maximum SS
Elevation at Bottom Layer in Dry Season |
|
Change
in Salinity at Bottom Layer in Dry Season, Spring Tide |
|
Change
in Salinity at Bottom Layer in Dry Season, Neap Tide |
|
Change
in Salinity at Bottom Layer in Wet Season, Spring Tide |
|
Change in
Salinity at Bottom Layer in Wet Season, Neap Tide |
|
Anti-scalant |
|
Existing
Sewerage System |
|
Proposed
Sewerage System |
|
Site
Layout Map |
|
Reference
Aerial Photographs |
|
Reference
Aerial Photographs |
|
Reference
Aerial Photographs |
|
Reference
Aerial Photographs |
|
Selected
Site Photographs |
|
Selected
Site Photographs |
|
Selected
Site Photographs |
|
Selected
Site Photographs |
|
Location
Plan and Protection Measures for Marsdenia Lachnostoma |
|
Location
map for Fisheries Sensitive Receivers |
|
Distribution
of Fishing Operations (all vessels) in Port Survey 2006 |
|
Distribution
of Fishing Operation (adult fish) in Port Survey 2006 |
|
Distribution
of Fishing Production (adult fish & fish fly) in Port Survey 2006 |
|
Distribution
of Fishing Production (fish fly) in Port Survey 2006 |
|
Aerial
Photograph of the Study Area |
|
Land Use
Zonings in the Study Area |
|
Landscape
Resources |
|
Representative
Photographs of Landscape Resources |
|
Representative
Photographs of Landscape Resources |
|
Landscape
Character Areas |
|
Representative
Photographs of Landscape Character Areas |
|
Representative
Photographs of Landscape Character Areas |
|
Geology
of the Study Area |
|
Representative
Photographs of Local Geology |
|
Predicted
Visual Envelope and Zone of Visual Influence (ZVI) |
|
Locations
of Predicted Visual Sensitive Receivers (VSRs) |
|
Representative
Photographs of and from select VSRs |
|
Representative
Photographs of and from select VSRs |
|
Project
Layout |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Illustrations
of Potential Slope Mitigation Works |
|
Impacts
on Landscape Resources |
|
Impacts
on Landscape Character Areas |
|
Photomontage
from VP1 (High Junk Peak Trail in Clear Water Bay Country Park, R3) |
|
Photomontage
from VP1 (High Junk Peak Trail in Clear Water Bay Country Park, R3) |
|
Photomontage
from VP2 (Island Resort, VSR H6) |
|
Photomontage
from VP2 (Island Resort, VSR H6) |
|
Photomontage
from VP3 (LOHAS Park, VSR H3) |
|
Photomontage
from VP3 (LOHAS Park, VSR H3) |
|
Photomontage
from VP4 (Tail on Knoll) |
|
Photomontage
from VP4 (Tail on Knoll) |
|
Photomontage
from VP5 (Joss House Bay, VSR R5) |
|
Photomontage
from VP5 (Joss House Bay, VSR R5) |
|
Vegetation
Survey |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Vegetation
Survey and Photographs |
|
Proposed
Greening at TKO Desalination Plant Site |
|
Consultation
Zone of the SENT Landfill, SENT Landfill Extension, TKO Stage II/III Restored
Landfill and TKO Stage 1 Restored Landfill |
|
Typical
Details of Impermeable Liner at SENT Landfill |
|
Location
of SENT Landfill Monitoring Points |
|
Location
of Restored TKO Stage II/III Landfill Monitoring Points |
|
Location
of Restored TKO Stage I Landfill Monitoring Points |
|
Sectional
Plan (Geological Cross Section A-A) |
|
Sectional
Plan (Geological Cross Section B-B) |
|
Sectional
Plan (Geological Cross Section C-C) |
|
Sectional
Plan (Geological Cross Section D-D) |
|
Consultation
Zone of the SENT Landfill Extension and Layout of Desalination Plant |
|
Sections |
|
Utilities
in SENT Landfill Consultation Zone |
|
Utilities
inTKO Stage II/III Restored Landfill Consultation
Zone |
|
Utilities
in TKO Stage I Restored Landfill Consultation Zone |