1.1 Background
of the Project
1.2 Purpose
of the EIA
1.3 Scope
of the EIA
1.4 Report
Structure
2.1 Project
Alternatives
2.2 Project
Location
2.3 Project
Schedule
2.4 Description
of Project Facilities, Components and Activities
3 ECOLOGY
3.1 Introduction
3.2 Relevant
Environmental Regulatory Framework
3.3 Baseline
Conditions and Background
3.4 Identification
and Evaluation of Impacts
3.5 Proposed
Mitigation Measures
3.6 Conclusion
and Recommendations
4 AIRBORNE
OPERATIONAL NOISE IMPACT
4.1 Introduction
4.2 Relevant
Environmental Regulatory Framework
4.3 Noise
Sensitive Receiver
4.4 Identification
and Evaluation of Impact
4.5 Conclusion
5.1 Introduction
5.2 Relevant
Environmental Regulatory Framework
5.3 Baseline Conditions
5.4 Study Area and Identification of Air Sensitive
Receivers
5.5 Identification
of Impacts
5.6 Evaluation
of Impacts
5.7 Conclusion
and Recommendations
6.1 Introduction
6.2 Relevant
Environmental Regulatory Framework
6.3 Identification
of Impacts
6.4 Prediction
and Evaluation of Impacts
6.5 Proposed
Mitigation Measures
6.6 Conclusion
and Recommendations
7 OTHER
ENVIRONMENTAL CONSIDERATIONS
7.1 Water
quality
7.2 Landscape
and Visual
7.3 Other
Environmental Media from XRL EIA
7.4 Conclusion
and Recommendations
8.1 Introduction
8.2 Legislation
Requirement and Evaluation Criteria
8.3 Study
Objectives and Methodology
8.4 Facility
Details
8.5 Base
Case and Worst Case for Quantitative Risk Assessment
8.6 Population
data
8.7 Hazard
Identification
8.8 Summary
of Risks
8.9 Conclusion
and Recommendations
8.10 References
9 ENVIRONMENTAL
MONITORING & AUDIT REQUIREMENTS
9.1 Operation
and Decommissioning of the Project
9.2 Upon
Completion of the Project
10 CONCLUSION
10.1 Environmental Benefits of the Project and the
Environmental Protection Measures Recommended
10.2 Population Protection
10.3 Protection of Environmentally Sensitive Areas
10.4 Key Environmental Problems Avoided
10.5 Compensation Areas
10.6 Conclusion
AnnexES
Annex 2A ¡V Decommissioning
Plan (KEY DETAILS)
Annex
8A - FULL
HAZARD TO LIFE/ QUANTITATIVE RISK ASSESSMENT REPORT (REV 3) [AUGUST 2015]
Annex
9A ¡VIMPLEMENTATION
SCHEDULE OF RECOMMENDED MITIGATION MEASURES
Annex
10A ¡VCOMPLIANCE
CHECKLIST FOR EIA STUDY BRIEF NO. ESB-280/2014
Annex
10RtC ¡VRESPONSES
TO COMMENTS RECEIVED MINUTES OF RELEVANT DISTRICT COUNCIL MEETINGS
The
existing Tai Lam Explosives Magazine (Tai Shu Ha, Yuen Long District, New
Territories, Land Allocation GLA-TYL 1288, forthwith known as ¡¥TLEM¡¦) has been
licensed and is currently in use by the MTR Corporation Limited (MTRC) for the
construction of the Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express
Rail Link (XRL) until end of 2015 (Environmental Permit No. EP-349/2009/L),
being used by the MTR XRL 824 Contractor.
This
Project is for the continued operation of the existing TLEM at Tai Shu Ha, Yuen
Long for the Liantang/Heung Yuen Wai
Boundary Control Point (BCP) project (hereafter ¡¥HKLTH¡¦) tunnel construction
works. The TLEM will be available
for use from late 2015 or early 2016 (expected January 2016) to December 2017
and Dragages Hong Kong Limited (DHK), contracted by
Civil Engineering and Development Department (CEDD), intends to continue using
it for HKLTH.
The
Project is classified as a Designated Project under Schedule 2, Part I, item
K.10 of the Environmental Impact Assessment
ordinance (EIAO) as ¡§an explosives depot or explosives manufacturing plant
in a stand-alone, purpose built building¡¨, and art II, Item 11 of the EIAO as ¡¨decommissioning of an
explosives depot¡¨.
MTRC
will use the TLEM up to end 2015.
DHK intends to then continue using it for HKLTH therefore an application
for an Environmental Impact Assessment (EIA) Study Brief under section 5(1)(a) of the Environmental
Impact Assessment Ordinance (EIAO) was submitted on 11 September 2014 with a
project profile (No. PP-516/2014) (the Project Profile), to
enable the continued operation of TLEM.
This
EIA Report presents the results of the EIA study as detailed in the EIA Study
Brief ESB-280/2014 and provides information on the nature and extent of any
environmental impacts arising from the operation and decommissioning of the
Project and any related activities that take place concurrently.
The EIA study
covers the Project and associated works proposed in PP-516/2014 and addresses
any likely key issues. This covers:
¡P
the
use of the existing TLEM from late 2015 or early
2016 (expected January 2016)
to December 2017 with the same operation as current users;
¡P
Explosives transport from
the existing TLEM to the three worksites by DHK, using trucks approved by Civil Engineering and
Development Department (CEDD)¡¦s Mines Division
(Mines); and
¡P
Decommissioning
of the existing TLEM after operation.
The
approved Hong Kong Section of Guangzhou-Shenzhen-Hong
Kong Express Rail Link (XRL) EIA Report (No. AEIAR-143/2009) (hereafter
¡¥XRL EIA¡¦) has been reviewed specifically for the environmental impacts arising
from operation of the Tai Lam Explosive Magazine (TLEM). The scope of the XRL EIA was far broader
than just the TLEM and after review it is considered that as well as the Hazard
to Life assessment the various environmental media relevant to the TLEM are
Ecology, Airborne Noise, Air Quality and Waste Management and these are
elaborated upon further in the remainder of this EIA report. Other media covered in the XRL EIA but
considered either of minor importance or not relevant to the current Project,
are generally discussed in one collective chapter which includes Water Quality,
Landscape and Visual, Cultural Heritage, Fisheries, Ground-borne Noise, Land
Contamination, Landfill Gas Hazard and Impacts on the Restored Ngau Tam Mei
Landfill.
This EIA study
also covers the potential Hazard to Life caused by explosive storage and
transport during operation of the Project.
Finally the EIA
study also considers cumulative impacts of the Project, through interaction or
in combination with other existing, committed and planned projects in the
vicinity of the Project.
The
structure of this EIA Report is as follows:
¡P
Chapter
1 presents the introduction to
the EIA Study;
¡P
Chapter
2 presents the description of
the Project including the alternatives that have been considered for the
Project;
¡P
Chapter
3 presents potential ecological
impacts arising from the Project;
¡P
Chapter
4 presents potential airborne
noise impacts arising from the Project;
¡P
Chapter
5 presents potential air
quality impacts arising from the Project;
¡P
Chapter
6 presents potential waste
management impacts arising from the Project;
¡P
Chapter
7 discusses other potential
environmental impacts arising from the Project such as water quality and
landscape and visual resources and justifies why other environmental media
considered in the XRL EIA are not necessary for this EIA;
¡P
Chapters
8 presents the findings of the hazard to
life study.
¡P
Chapters
9 lists all the environmental monitoring
and audit requirements of the Project.
¡P
Chapters
10 summarises the overall
outcomes of the EIA report and provides the conclusion.
In
addition a number of Annexes provide information supporting the main EIA
Report, as detailed in the Table of Contents.
An
Executive Summary of the EIA report is also provided separately.
This chapter of the EIA
report presents information on the Project and its alternatives in sufficient
detail in order to describe, at a level that can be understood by a lay person,
the proposed features and activities of the Project; and facilitate a
comprehensive identification of the potential impacts on resources and
receptors that could result from Project activities.
There are no known
existing, committed and/or planned projects in the vicinity of the Project that
could potentially cause cumulative environmental impacts through their
interaction with the Project.
To enable a timely delivery
of explosives to worksites and in order to meet the proposed construction work
programme, an Explosives Storage Magazine (Magazine) is required for the Liantang / Heung Yuen Wai Boundary Control Point (BCP) Work
which connects the new BCP with Fanling Highway. The purpose of the magazine is to
maintain progress rate for construction activities, i.e. to meet multiple
blasts per day and also act as a buffer in case of delivery interruptions by
Mines from the Geotechnical Engineering Office (GEO), CEDD.
For
the XRL EIA, a long list of potential locations for explosives magazine sites
were identified, reviewed and short-listed for further detailed study and
discussion with Mines. Factors
considered included:
¡P
External
separation distance - the distance from the explosive stores to inhabited areas
and sensitive receivers. The required minimum internal and external separation
distances from the magazines should follow the requirements stated in UK Explosives Regulations 2014 published by
the UK Health & Safety Executive, a document as specified by the Hong Kong
Commissioner of Mines (CoM). In addition, it is preferable to limit
the transportation distances as far as practicable when considering the
possible location of magazine. This
is particularly pertinent given explosives are not permitted within road
tunnels, and there would be a considerable distance of about 40 km to
50 km for explosives transported from northern New Territories to Kowloon
via above ground or at grade roads, and vice versa;
¡P
Access
for Mines Division explosive delivery vehicles;
¡P
Site
constraints such as existing conditions;
¡P
Land
availability; and
¡P
Potential
environmental and heritage impacts.
The
magazine site selection process for the XRL project is documented in Working Paper No. 13A ¡VExplosives Magazine
Site Selection and two explosives magazine sites were selected as being
necessary to store the explosives for the XRL project, one being the TLEM site
(and the other at So Kwun Wat).
This
TLEM site has been selected for the current Project given: it is already
constructed so there are no construction impacts or land conversion issues; it
is being used for exactly the required purpose now under EP-349/2009/L
which
would imply any operational and decommissioning impacts associated with the
current Project will be acceptable; it is potentially available from end 2015
which suits the HKLTH
project tunnelling schedule; and its location is suitable for the HKLTH project
as elaborated upon below. In addition, since there is no requirement to build a
new magazine site, the timeline for the tunnel Project may be expedited as well
as there being no requirement to build a new magazine site which may cause more
significant environmental impacts elsewhere.
Further details of the
magazine requirement and selection are presented in Section 9.4.2 of Annex
8A.
Three possible transport routes that do not pass
through tunnels have been identified for this Project, i.e. the proposed
explosive transport route options R1, R2 and R3, from the magazine site to the
three worksites (i.e. Mid-Ventilation Adit, North
Portal and South Portal). Figure 2.1, Figure 2.2
and Figure 2.3
show plans of the proposed explosive transport route options R1, R2 and R3
respectively and more details of these routes from Tai Lam Explosives Magazine
site to the three worksites are provided in Annex
8A, Table 2.9.
In Route Options R1 and R3, the explosives delivery
truck will pass through Pok Oi
Interchange and Shap Pat Heung Interchange. During the Fourth Meeting of Traffic and
Transport Committee under Yuen Long District Council on 24 July 2014
(Thursday), members expressed concerns on the traffic conditions of Pok Oi Interchange.
Currently there is road improvement work which leads to serious traffic
jams, thus temporary road diversion and traffic control measures are
enforced. The road improvement work
is expected to be completed in 2015 but may be delayed due to the flyover
foundation. Therefore, members
generally did not prefer the use of Pok Oi
Interchange by the explosives delivery truck during the road improvement work,
and recommended to use Tong Yan San Tsuen Interchange and Yuen Long Road, which
is Route Option R2 (see Annex
10RtC
which provides relevant minutes of the July 2014 District Council Meeting).
The explosives delivery routes will be:
¡P At
early stage of this project, during road improvement work at Pok Oi Interchange (expected to be completed in 2015 but
may be delayed), Route Option R2 will be used. Route Options R1 and R3 are not feasible
since they both route via Pok Oi Interchange.
¡P
After road improvement work at Pok
Oi Interchange is completed, all three routes will be available for use. The Route Option with minimum transport
risk will be used.
Figure 2.1 Proposed
Explosive Transport Route Option R1
Figure 2.2 Proposed Explosive
Transport Route Option R2
Figure 2.3 Proposed Explosive
Transport Route Option R3
Table 2.1
provides a comparison of transport distances to each worksite between the three
proposed explosive transport route options.
Table 2.1 Transport
Distance to each worksite via different
Route Options
Worksite |
Transport
Distance (km) |
||
Route
Option R1 |
Route
Option R2 |
Route
Option R3 |
|
Mid-Ventilation Adit |
27.7 |
30.9 |
24.7 |
North Portal |
27.6 |
30.8 |
24.6 |
South Portal |
23.2 |
27.8 |
21.6 |
Figure 2.4, Figure 2.5 and Figure 2.6
below show the overall Potential Life Loss (PLL) and Fatality N and frequency f
(FN curves) for all three proposed explosive transport route options and full
details are presented in the EIA Report¡¦s
Annex 8A,
Section 8.
Figure
2.4 F-N Curve for Storage and Transport
of Explosives (Route Option R1)
Figure
2.5 F-N Curve for Storage and
Transport of Explosives (Route Option R2)
Figure 2.6 F-N Curve for Storage and
Transport of Explosives (Route Option R3)
The
Project is located at the existing TLEM in Tai Shu Ha, Yuen Long District, New Territories.
Figure 2.7
shows the location and site plan
of the Project and Figure 2.8
details
the Project Boundary.
The Tai Tong East Borrow Area was excavated in the
1990s and then subjected to reinstatement and management. To restore the borrow area, fast growing
exotic species (e.g. Acacia spp., Melaleuca quinquenervia)
were planted extensively in the area and it has been maintained by AFCD from
2003 until 2015. More recently,
native species (e.g. Machilus spp., Reevesia thyrsoidea, Schefflera heptaphylla, and Phyllanthus emblica)
were planted to increase diversity.
This Conservation Area (CA) is zoned to protect and retain the existing
natural landscape, ecological or topographical features of the area for
conservation, educational and research purposes. The zoning ordinances also separate
sensitive natural environments, such as the Tai Lam Country Park, from the adverse
effects of development.
Given
the loss of a small plantation area under the XRL project that was part of the
restoration planting in the Tai Tong East Borrow area within the CA, the XRL
EIA made provision for reinstatement
planting at the TLEM that would be carried out upon completion of the XRL
project. How this Project will
affect the reinstatement planting is further discussed in Section 3 Ecology.
The TLEM will be available
for use from late 2015 or early 2016 (expected January 2016) to December 2017
with delivery of explosives to the TLEM expected to start in January 2016 and
go through to December 2017. The decommissioning
TLEM will be conducted after the operation and is expected to be completed in
one month.
No construction activity will be
carried out at the TLEM site.
The existing TLEM is composed of
the following components as illustrated in Figure 2.9a & b:
(i) Two stores each with a capacity of
400 kg explosives and dimensions of about 4.7 m (length) x 2.7 m (width) x
2.7 m (height);
(ii) Secure fence;
(iii) CCTV system;
(iv) Guard house
(standard container office, with dimensions of about 6 m (length) x 2.4 m
(width) x 2.4 m (height)); and
(v) Street fire hydrant water tank (245 m3)
and 2 pumps.
The
magazine operation will remain the same as under the current MTR XRL 824
Contractor and the Mines Division of the CEDD (Mines) will deliver a maximum of
800 kg explosives daily to the TLEM along with initiation devices
(detonators). The transportation of
explosives by Mines either to the Magazine or directly to
sites, is under Mines¡¦ responsibility and falls outside the scope of
this EIA study. Only the amount of
explosives required for blasting work will be delivered to TLEM by CEDD Mines
Division. Explosives will then be
withdrawn by DHK as required and delivered using trucks approved by Mines, to
three HKLTH worksites located at:
¡P
Sha
Tau Kok Road ¡V Wo Hang Section (North Portal);
¡P
Po
Kat Tsai Road (Mid Ventilation Portal); and
¡P
Tong
Hang Tung Chuen (South Portal)
For this Project, explosives transport will be
scheduled with less than 200 kg of explosives per truck (North Portal: 20
- 90 kg, Mid Ventilation Portal: 40 - 70 kg, South Portal: 15 - 140 kg) and a
total of two to eight (2 ¡V 8) deliveries per day will be carried out to the
worksites (explosives are required at two to three [2 ¡V 3] worksites per day)
and maximum seven (7) days per week.
Further details of these delivery routes and scheduling can be found in Chapter 8 Hazard to Life.
Only
the amount of explosives required for blasting work will be delivered to TLEM
by CEDD Mines Division. Before the
commencement of decommissioning works, no surplus explosives will be stored at
the explosives magazine.
Based on this, no hazard to life impact is anticipated.
The key activities of the decommissioning works which
will expect to last for about one month include:
¡P
Dismantle
and remove E&M, fire services, CCTV and lighting installed for the two
explosive stores;
¡P
Demolish
the earth bunds and the two explosive stores;
¡P
Frame
cut the re-bar and remove the concrete debris;
¡P
Remove
all fire service facilities and all ground services including guard house, road
furniture and lighting;
¡P
Remove
fire hydrant water tank (245m3);
¡P
Remove
the container guard house and any temporary steel works; and
¡P
Demolish
the paved road for reinstatement of planting.
As seen from the above, work activities involved would
mainly be dismantling and removal of structures currently used for the
explosive magazine. Some of the
work activities would be conducted simultaneously, as illustrated in the
Decommissioning Plan as shown in Annex 2A. Powered mechanical equipment that would
generally be used for carrying out the abovementioned work activities is also
shown in Annex 2A.
As
the decommissioning works will only involve dismantling, demolition and removal
of the existing temporary structures, and removal of existing vegetation will
not be required, no landscape and visual impact and terrestrial ecology impact
are anticipated.
As
the site is used as a magazine for storage of explosives only, there is no
chemical store and use of lubricant or other chemicals are not required. The magazine is paved. No surplus explosives will be stored at the
explosives magazine before the commencement of the decommissioning works. Based on the above-mentioned, no land
contamination impact is anticipated due to the decommissioning works.
Due
to the small scale of decommissioning works, site runoff and drainage from the
works areas will be very minimal, and water quality impact is not anticipated
due to the decommissioning works, as discussed further in Section 7.
This
chapter presents the potential ecological impacts associated with the operation
and decommissioning of the Project in accordance with the requirement stated in
Section 3.4.2 of the EIA Study
Brief.
The
ecological findings of the previously approved XRL EIA report (No.
AEIAR-143/2009) are reviewed and updated on the understanding that the Project
Site is currently being used as an explosive magazine site for the construction
of the XRL and therefore there will be no construction phase of this project,
with no land conversion. Operation
of the site is also intended to remain similar to the current operating
procedure described in the approved XRL EIA.
Legislative
requirements concerning the protection of species and habitats of terrestrial
ecological importance such as the Wild
Animals Protection Ordinance (Cap 170), and Protection of Endangered Species of Animals and Plants Ordinance (Cap
586) are not considered of key importance to this study given there is no
construction phase and operation will remain similar to existing.
The
XRL EIA does include mitigation measures to be carried out at the site upon
completion of the XRL project and carrying out planting in the TLEM site. Therefore overall the following is
considered the key legislation for this Study.
¡P Environment Impact Assessment Ordinance (Cap. 499) and Environmental Impact Assessment Process
under the Environmental Impact Assessment Ordinance (EIAO-TM), Annexes 16 and 8;
¡P
Forests and Countryside
Ordinance (Cap 96);
and
¡P
DEVB
TCW No. 10/2013 ¡V Tree Preservation.
Details
on each of the above are presented below.
The
criteria for evaluating terrestrial ecological impacts are laid out in the EIAO-TM. Annex 16 of the EIAO-TM sets out the general approach and methodology for the
assessment of impacts to ecological resources arising from a project or
proposal, to allow a complete and objective identification, prediction and
evaluation of the potential ecological impacts. Annex
8 of the EIAO-TM recommends the
criteria that can be used for evaluating such ecological impacts.
The
Forests and Countryside Ordinance (Cap 96) prohibits the felling, cutting,
burning or destroying of trees and growing plants in forests and plantations on
Government land. The subsidiary Forestry Regulations prohibit the picking,
felling or possession of listed rare and protected plant species. The list of protected species in Hong
Kong which comes under the Forestry
Regulations was last amended on 11 June 1993 under the Forestry (Amendment) Regulation 1993 made under Section 3 of the Forests and Countryside Ordinance.
DEVB TCW No. 10/2013 ¡V Tree
Preservation supersedes ETWB TC(W) No. 3/2006 and sets out the policy on tree
preservation from feasibility, planning, design, construction to
post-construction stages of a development, the procedures for control of tree
felling, transplanting and pruning in Government projects, and departmental
responsibilities in handling proposals on tree preservation and removal. It also covers the reporting of unauthorised tree removal or damage of
trees, on both private and unleased Government land and its Appendix A details
the requirements for compensatory planting.
Figure 3.1 gives an overview of the Project Study Area, 500 m from
the Project Site boundary. The
Project falls within the Tai Tong East Borrow Area and the statutory Tai Tong
Outline Zoning Plan (S/YL-TT/16) Conservation Area (CA). It is also near (approximately
300 m from) the Tai Lam Country Park.
The Tai Tong East Borrow Area was excavated in the
1990s and then subjected to reinstatement and management. To restore the borrow area, fast growing
exotic species (e.g. Acacia spp., Melaleuca quinquenervia)
were planted extensively in the area and it has been maintained by AFCD from
2003 until 2015. More recently,
native species (e.g. Machilus spp., Reevesia thyrsoidea, Schefflera heptaphylla, and Phyllanthus emblica)
were planted to increase diversity.
This CA is zoned to protect and retain the existing
natural landscape, ecological or topographical features of the area for
conservation, educational and research purposes. The zoning ordinances also separate
sensitive natural environments, such as the Tai Lam Country Park, from the
adverse effects of development.
The habitat map in Figure 3.2 is
taken from the approved XRL EIA (No. AEIAR-143/2009) with minor revisions
following a site visit in November 2014 and shows the approach to the TLEM as
an existing tarmacked road and the area around the TLEM to be dominated by
plantation with a stream flowing nearby to the south. The key change to baseline condition
since the XRL EIA is that the area now occupied by the TLEM was previously
relatively mature plantation habitat dominated by exotic plant species with some native
species in the understorey (e.g. Melastoma candidum, Psychotria
asiatica) and this area was cleared for the
construction of the TLEM.
The construction of the TLEM was conducted under the
EP from the approved XRL EIA and
there will be no construction phase for this Project.
Operation
of the existing facility will remain similar to the existing operation as
described in the XRL EIA and the decommissioning works will only affect the
existing TLEM which classified as developed areas of negligible ecological
value, and therefore is not considered to cause any direct ecological impacts
to habitats including streams or to species.
Given
the loss of a small plantation area under the XRL project that was part of the
restoration planting in the Tai Tong East Borrow area within the CA, the XRL
EIA made provision for reinstatement planting at the TLEM that would be
carried out upon completion of the XRL project. As part of the XRL EIA and EP (latest
XRL EP no . : EP-349/2009/L) requirements, a detailed Vegetation Survey Report for Tai Shu Ha Road
West have been submitted under XRL EP condition 2.12(iii) and Tree Planting and Landscape Plan TLP-10: Works in Yuen Long District (Tai Shu
Ha), submitted under XRL EP condition 2.14, has been drawn up including
details of the reinstatement of the TLEM site. These reports under the XRL project are
publically available at the following sites http://www.epd.gov.hk/eia/register/english/permit/ep3492009/documents/vsrr1/pdf/vsrr1.pdf
and http://www.epd.gov.hk/eia/register/english/permit/vep3232010/documents/tplpyldtsh/pdf/tplpyldtsh.pdf,
and for ease of reference, the key details of these
reports are provided as Annexes 3A
& 3B to this report.
The current Project extends the operating time of the
TLEM. The XRL project use of the
TLEM was due to be up to the end of 2014 and has been extended until end
2015. Under the proposed Project
the TLEM site will remain in operation up to December 2017 i.e. reinstatement planting
will be
postponed by three years.
The reinstatement of the TLEM is principally in order
to restore the habitat back to borrow area reinstatement plantation and
relative to the whole borrow area reinstatement plantation, it is a very small
area. With respect to fauna, the area
is ecologically connected to nearby Country Parks and Conservation Areas and
may host a number of woodland species.
The XRL EIA baseline surveys recorded six species of conservation
interest with the Study Area including Little Egret Egretta
garzetta, Chinese Pont Heron Ardeola
bacchus, Red-Throated
Pipit Anthus cervinus,
Eurasian Jay Garrulus glandarius,
Pale Palm Dart Telicota colon stinga and
Chinese Pangolin Manis pentadactyla
auritus. All these species were recorded outside
the direct TLEM footprint area and with the exception of the Chinese Pangolin
all to the west off the Study Area in habitats separated from the TLEM by the
Tai Shu Ha Road West.
The Chinese Pangolin was recorded in grassland to the south of the TLEM
site but across the watercourse from the site. Though the area near the TLEM is
dominated by plantations with a canopy of mainly introduced species, it is
possible that fauna from nearby woodland habitats would occasionally use this
plantation habitat once it was reinstated but it is not considered to be a key
habitat to any particular species of conservation interest. Since there is also a relatively large
area of existing plantation in the surrounding area, to postpone the reinstatement
by three years is therefore not thought to have any adverse impact on fauna
that will use this area in the future.
With regard to the impact of postponing the
reinstatement planting by three years on habitat, this time period is
relatively small with regards to vegetation succession and establishment of
soils. Therefore assuming that the
same reinstatement plan as set out in the XRL
EIA Vegetation Survey Report for Tai Shu Ha Road West and Tree Planting and Landscape Plan TLP-10:
Works in Yuen Long District (Tai Shu Ha) can be adhered to, no adverse
impact is expected on habitats.
For the XRL EM&A no water monitoring points were
proposed for the watercourses within the TLEM Study Area. Since operation activities will remain
similar to existing it is therefore not considered necessary to carry out any
monitoring of the watercourses. Chapter 7 provides further detail on the potential impacts to water quality
from this Project.
Upon completion of the Project at the end of 2017 and
the removal of the TLEM, reinstatement planting should be carried out at the
site according to the XRL EIA Vegetation
Survey Report for Tai Shu Ha Road West (hereafter Vegetation Survey Report) and the Tree Planting and Landscape Plan TLP-10: Works in Yuen Long District
(Tai Shu Ha) (hereafter TLP).
The Vegetation
Survey Report and the TLP detail
criteria for selection of suitable vegetation species for this planting and the
selected species are listed in Table 3.1
below. Six tree species were
recommended to compensate for the loss of trees and four shrub species for the
loss of understorey
species, all being species that existed previously in the TLEM site before the
magazine construction.
Table 3.1 Recommended
Species for Reinstatement Planting at TLEM
Scientific Name |
Growth Form |
Native / Exotic to Hong Kong |
Castanopsis fissa |
Tree |
Native |
Celtis sinensis |
Tree |
Native |
Cinnamomum parthenoxylon |
Large Tree |
Native |
Litsea rotundifolia |
Shrub |
Native |
Mallotus paniculatus |
Tree |
Native |
Melastoma sanguineum |
Shrub |
Native |
Psychotria asiatica |
Tree or shrub |
Native |
Reevesia thyrsoidea |
Tree |
Native |
Rhodomyrtus tomentosa |
Shrub |
Native |
Schefflera heptaphylla |
Tree |
Native |
Other native trees/shrubs that are generally well
self-established and suitable for mitigation planting can also be considered to
further promote the flora biodiversity of TLEM site, as recommended in Table 3.2
Table 3.2 Additional
Recommended Species for Reinstatement Planting at TLEM
Scientific Name |
Growth Form |
Native / Exotic to Hong Kong |
Bischofia favanica |
Tree |
Native |
Elaeocarpus sylvestis |
Tree |
Native |
Gordonia axillaris |
Shrub or tree |
Native |
Schima suberba |
Tree |
Native |
Viburnum odoratissimum |
Shrub or tree |
Native |
In addition, the TLP provides a list of general tree/
palm species that are suitable for Native Woodland Planting (not on SIMAR
Slopes). Those not listed already
in Table
3.1 or Table
3.2,
are listed in Table
3.3.
Table 3.3 Additional
Species generally suitable for Native Woodland Planting (not on SIMAR Slopes)
Scientific Name |
Common Name |
Native / Exotic to Hong Kong |
Ailanthus fordii |
Ailanthus |
Native |
Broussonetia papyrifera |
Paper Mulberry |
Native |
Choerospondias axillaris |
Hog Plum |
Native |
Cinnamomum burmannii |
Cinnamon tree |
Native |
Cleistocalyx operculatus |
Water Banyan |
Native |
Ficus microcarpa |
Chinese banyan |
Native |
Ficus superba var. japonica |
Superb fig |
Native |
Ficus variegata var. chlorocarpa |
Common red-stem |
Native |
Ficus virens var. sublanceolata |
Big-leaved fig |
Native |
Liquidambar formosana |
Sweet gum |
Native |
Litsea glutinosa |
Pond spice |
Native |
Litsea monopetala |
Persimmon¡Vleaved Litsea |
Native |
Machilus chekiangensis |
Chekiang
Machilus |
Native |
Machilus chinensis |
Hong Kong Machilus |
Native |
Machilus pauhoi |
Many-nerved
Machilus |
Native |
Machilus thunbergii |
Red Machilus |
Native |
Phoenix hanceana |
Spiny date-palm |
Native |
Sapium discolor |
Mountain tallow |
Native |
Sapium sebiferum |
Tallow-tree |
Native |
Sterculia lanceolata |
Scarlet Sterculia |
Native |
Figure3.3a and
b
taken from the Vegetation Survey Report
and TLP show the proposed location of
tree and shrub planting respectively and include the proposed number of
individuals to be planted. These plans
should be adopted for the future reinstatement planting process.
Vegetation Survey Report, Appendix C and TLP
Appendix V also provide relevant specification for the site restoration
works at the TLEM, including restoration of the soil, to ensure suitable
conditions for planting are reached once operation of the TLEM stops and prior
to planting starting. This Vegetation Survey Report, Appendix C and
TLP Appendix V should also be adhered
to for the future reinstatement planting process.
Under the
Project Implementation Schedule of the approved XRL EIA (provided in the XRL
EIA Report Appendix A), MTR are the
party responsible for the reinstatement planting works. For the proposed Project, DHK should
liaise with MTR and will take over the responsibility of this reinstatement
planting works (as laid out in the Vegetation
Survey Report as well as the TLP,)
including application for a Further Environmental
Permit (FEP) of XRL,
to cover the planting obligation.
Reinstatement
planting at the TLEM site will be carried out upon completion of the Project in
2017 and the removal of the TLEM. Assuming that this reinstatement
planting is carried out by DHK as recommended in the approved
XRL EIA report (according to the Vegetation
Survey Report and the TLP, which
both fall under the requirements of the XRL EIA study, with approval from DEP as necessary for any revisions to these
approved documents),
no adverse impacts on ecology are expected from this Project.
This
chapter presents the potential noise impacts to the identified Noise Sensitive
Receivers (NSRs) associated with the decommissioning and operation of the
Project in accordance with the requirement stated in Section 3.4.2 of the EIA Study Brief. The findings of the previously approved
XRL EIA report (No. AEIAR-143/2009) XRL) are reviewed and updated as necessary.
The EIAO-TM and Technical Memorandum on Noise From Places
Other than Domestic Premises, Public Places or Construction Sites (IND-TM) specifies the applicable ANLs
for the fixed noise sources from the Project. The ANLs are dependent on the ASR and
the time of the day and are presented in Table 4.1.
Table 4.1 Acceptable
Noise Levels
Time Period |
LAeq 30min (dB(A)) |
||
|
ASR ¡§A¡¨ |
ASR ¡§B¡¨ |
ASR ¡§C¡¨ |
Day-time
(i.e. 07:00-19:00 hrs) |
60 |
65 |
70 |
Evening
(i.e. 19:00-23:00 hrs) |
60 |
65 |
70 |
Night-time
(i.e. 23:00-07:00 hrs of the next day) |
50 |
55 |
60 |
Fixed plant
noise is controlled under Section 13
of the NCO and the predictions will
be undertaken in accordance with the IND-TM. The noise criteria stipulated in the IND-TM are also dependent on the ASR of
the NSR. As the Project Site is located in a rural area and no influencing
factors affect the NSRs, an ASR of ¡§A¡¨ has been assigned.
The
traffic noise standards for planning purposes specified in Table 1 under Annex 5 of
the EIAO-TM was employed as the noise
limits for the road traffic noise impact assessment. The applicable road traffic noise
standards are 70dB(A)
L10, 1hr for domestic premises and 65dB(A) L10, 1hr for
education institutions and church, respectively. These noise limits were applied for the peak
hour traffic flows and for uses that rely on opened windows for ventilation.
The principal
legislation relating to the control of construction noise is the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499). The Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO,
stipulates assessment standards of Leq(30
minutes) 75
dB(A) for all domestic premises and 70/65 dB(A) for educational institutions
during normal school term/examination periods for daytime (i.e. 0700 to 1900
hours on any day not being a Sunday or general holiday) construction activities ([1]). These criteria apply to Noise Sensitive
Receivers (NSRs) relying only on openable windows for ventilation.
The
Noise Control Ordinance (NCO) (Cap 400) also provides means to assess construction noise
impacts. Various Technical
Memoranda (TMs), which stipulate control approaches and criteria during the
restricted hours, have been issued under the NCO. The following TMs
are applicable to the control of noise from construction activities:
¡P
Technical Memorandum on
Noise from Percussive Piling (PP-TM);
¡P
Technical Memorandum on
Noise from Construction Work other than Percussive Piling (GW-TM);
and
¡P
Technical Memorandum on
Noise from Construction Work in Designated Areas
(DA-TM).
The
NCO provides statutory controls on
general construction works during the restricted hours (i.e. 19:00 ¡V 07:00 hrs
of the next day, Monday to Saturday and any time on Sundays and public
holidays). The use of Powered
Mechanical Equipment (PME) for the carrying out of demolition or construction
works during the restricted hours requires a Construction Noise Permit
(CNP). The EPD is guided by the
GW-TM and DA-TM when assessing such an application.
Percussive piling is prohibited at any
time on Sundays and public holidays and during the weekday evening and
night-time hours (19:00-07:00 hrs of the next day, Monday through
Saturday). A CNP is required for
such works during the weekday daytime hours (07:00 ¡V 19:00 hrs, Monday through
Saturday). The EPD is guided by the
PP-TM in considering applications of a CNP for such works.
The Noise
Control Authority will consider a well-justified CNP application, for
construction works within restricted hours as guided by the relevant TMs issued
under the NCO. The Noise Control Authority will take
into account adjoining land uses and any previous complaints against construction
activities at the site before making a decision. Nothing in this EIA Report shall bind the Noise Control
Authority in making its decision.
The Noise Control Authority may include any conditions in a CNP that it
considers appropriate. Failure to
comply with any such conditions may lead to cancellation of the CNP and
prosecution action under the NCO.
In accordance with Table
5.5 of the XRL EIA Report, one representative Noise Sensitive Receiver
(NSR) was identified within the Study Area (i.e. within 300m of the Project
boundary) and is listed in Table 4.2. No new or planned NSRs were identified
since the approval of the XRL EIA Report.
The location of the identified NSR is presented in Figure 4.1.
NSR No. |
Description |
Type |
Distance from the Magazine Site |
No. of Storey |
TS1 |
Village
House next to Tai Shu Ha Road West |
Residential |
297 m (1) |
1 |
Note: (1) The
distance between the magazine site and the NSR was reported as 244 m in
approved XRL EIA Report. This distance is further reviewed in this ERR and is
found to be approximately 297 m. |
The magazine site comprises two magazine structures
storing 400kg of explosives each, a secure fence, CCTV system, guard house,
street fire hydrant tank (245m3) and two water pumps. Layout plan of the magazine site is
presented in Figure 4.2.
The
major activities are summarised as follows:
¡P
Dismantle
and remove E&M, fire services, CCTV and lighting installed for the two
explosive stores;
¡P
Demolish
the earth bunds and the two explosive stores;
¡P
Frame
cut the re-bar and remove the concrete debris;
¡P
Remove
all fire service facilities and all ground services including guard house, road
furniture and lighting;
¡P
Remove
fire hydrant water tank (245m3);
¡P
Remove
the container guard house and any temporary steel works; and
¡P
Demolish
the paved road for reinstatement planting.
The
normal working hours of the Contractor will be between 07:00 and 19:00 hrs from
Monday to Saturday (except public holidays). Construction activities during
restricted hours are not expected.
Should evening and night works between 19:00 and 07:00 hrs or on public
holidays (including Sundays) be required, the Contractor will submit a CNP
application which will be assessed by the Noise Control Authority.
It
is envisaged that major noise sources will be associated with various PME
including lorries, dump trucks, drills/grinders and
breakers etc to be used for the decommissioning of
the magazine site.
It is recommended that the general noise control
measures as listed in Recommended Clauses
for Construction Contracts ¡V Section 3 - Noise Control (available on EPD
website at http://www.epd.gov.hk/epd/english/environmentinhk/eia_planning/guide_ref/rpc_3.html), should
also be incorporated in the works contract to ensure that the Contractor will
adopt good site practices and minimise noise
generation. Given that the decommissioning works will
only last for 4 weeks, the nearest NSR is located at ~297 m from the magazine
site, and good site practices to minimise noise
generation will be adopted, no adverse noise impact is anticipated from the
decommissioning works.
Operation of the magazine site will remain the same as
the current XRL project. Potential
sources of noise include fixed plant noise impact from the operation of the
water pumps and street fire hydrant tank. The nearest NSR is located at
approximately 297 m from the fixed plant noise sources. As such, no adverse noise impact to the
NSR is expected.
The operational activities involve the delivery of
explosives to the Magazines by Mines Division on a daily basis and the transfer
of the explosives to the work areas by the contractors daily. Traffic generated from the site is insignificant as a
total of two to eight (2 ¡V 8) deliveries per day will be carried out to the
worksites. Three proposed explosive
transport routes have been identified for this Project, i.e. Proposed Routes
R1, R2 and R3, from the magazine site to the three worksites (i.e.
Mid-Ventilation Adit, North Portal and South Portal). Figure 2.1, Figure 2.2 and Figure 2.3 show
the proposed explosive transport routes R1, R2 and R3 respectively. With consideration of the low traffic
arising from the Project, no traffic noise impact is anticipated.
No adverse noise impacts are anticipated during
operation or decommissioning, assuming general noise control measures, as
listed in Recommended Clauses for
Construction Contracts ¡V Section 3 - Noise Control, are adopted during
decommissioning. Noise monitoring
at the NSR is not required as part of the EM&A programme
during operation and decommissioning.
This
chapter presents an assessment of the potential air quality impacts associated
with the operation of the Project in accordance with the requirement stated in Sections 3.4.2 of the EIA Study
Brief. The findings of the
previously approved Hong Kong Section of the XRL EIA report (No.
AEIAR-143/2009) were reviewed and updated in this assessment.
The
principal legislation for the management of air quality in Hong Kong is the Air Pollution Control Ordinance (APCO)
(Cap 311). The APCO Amendment was
passed in July 2013 and a set of new Air Quality Objectives (AQOs) has been
effective from 1 January 2014. The
new AQOs stipulate statutory ambient limits for air pollutants and the maximum
allowable number of exceedances over specific averaging periods. The new AQOs are presented in Table 5.1
and they
were used as the evaluation criteria for this assessment. As stipulated in Annex 4 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM), the AQOs
and other relevant standards established under the APCO should be met.
Table 5.1 Hong Kong Air
Quality Objectives (mg m-3) (a)
Air Pollutant |
Averaging Time |
Concentration (mgm-3) (a) |
No. of Exceedances Allowed per
Year |
Sulphur Dioxide (SO2) |
10 minute |
500 |
3 |
|
24-hours |
125 |
3 |
Respirable Suspended Particulates (RSP) (b) |
24-hours |
100 |
9 |
Annual |
50 |
- |
|
Fine Suspended Particulates (FSP) (c) |
24-hours |
75 |
9 |
Annual |
35 |
- |
|
Nitrogen Dioxide (NO2) |
1-hour |
200 |
18 |
|
Annual |
40 |
- |
Ozone (O3) |
8-hours |
160 |
9 |
Carbon Monoxide (CO) |
1-hour |
30,000 |
- |
|
8-hours |
10,000 |
- |
Lead |
Annual |
0.5 |
- |
Notes: (a) Measured
at 293K and 101.325 kPa. (b) Suspended
particles in air with a nominal aerodynamic diameter of 10 £gm or less (c) Suspended
particles in air with a nominal aerodynamic diameter of 2.5 £gm or less |
Annex 4
of the EIAO-TM also stipulates that
any predictive assessment of the odour impact should meet 5 odour units based
on an averaging time of 5 seconds.
The Project Site is located in rural area and no major
air emission source is identified in the area. Since the continued operation of the
magazine site for the HKLTH will commence in 2015, the hourly ambient pollutant
concentration data predicted by the PATH (Pollutants in the Atmosphere and
their Transport over Hong Kong) model for Year 2015 has been adopted to reflect
the future background air quality in the Project Site area during the operation
of the Project. Table
5.2 summarizes the annual
average concentrations of the air pollutants in 2015 predicted by the PATH
model.
Table 5.2 Annual
Averaged Concentrations of Air Pollutants in 2015 Predicted by the PATH Model
Air Pollutant |
Annual Averaged Concentration
(mg
m-3) |
|
PATH Background in 2015 (a) |
Annual AQO |
|
SO2 |
7 |
-
(c) |
NO2 |
21 |
40 |
RSP |
42 |
50 |
FSP
(b) |
30 |
35 |
Notes: (a)
The annual averaged concentrations of the air pollutants were extracted from
PATH grid (19, 35) in which the Project Site is located. (b)
FSP data are not available in the hourly PATH background concentration
results. A recommended FSP to RSP
ratio of 0.71 is applied for the estimation of annual FSP results according
to EPD¡¦s ¡§Guidelines on the Estimation
of PM2.5 for Air Quality Assessment in Hong Kong¡¨. (c)
No annual AQO for SO2. |
According to the PATH-predicted
background air quality in the Project Site area in 2015, the annual averaged
concentrations of all concerned air pollutants after commencement of operation
of the magazine site are anticipated to be below their respective AQOs.
The Study Area for the air quality impact assessment is
generally defined by a distance of 500m from the boundary of the Project Site
as shown in Figure 5.1. Air Sensitive Receivers (ASRs) were
identified based on the landuses, latest Outline
Zoning Plan (OZP) and with reference to Table 12.5 of the XRL
EIA Report. Four ASRs were
identified which are presented in Table
5.3 and their locations are
shown in Figure 5.1.
Table 5.3 Air
Sensitive Receivers
ASR |
Description |
Type of Use |
Approximate Separation Distance from the nearest site boundary (m) |
No. of storey(s) |
TSA1 |
Village
House next to Tai Shu Ha Road West |
Residential |
54 |
1 |
HKMEC |
Hong Kong
Model Engineering Club |
Recreational |
200 |
N/A |
NHT1 |
Temple at
Nam Hang Tsuen |
Temple |
338 |
1 |
NHT2 |
Village
House at Nam Hang Tsuen |
Residential |
332 |
1 |
The magazine site comprises two magazine structures storing
400kg of explosives each, a secure fence, CCTV system, guard house, street fire
hydrant tank (245m3) and two pumps.
Operation of the magazine site will remain the same as
the current XRL project. The
operational activities involve the delivery of explosives to the Magazines by
Mines Division on a daily basis and the transfer of the explosives to the work
areas by the contractors daily.
Potential sources of air quality impacts include dust emissions
from the operation of explosives delivery vehicles.
About two to eight trips per day are expected for the
transportation of explosives to the work areas.
The magazine site will be
decommissioned after the completion of the construction works for the Liantang/Heung Yuen Wai Boundary
Control Point (BCP) project.
Potential dust emissions may also arise during the decommissioning
works.
With reference to Section
12.45 of the XRL EIA Report, the major activities causing dust impacts
during operation would be the vehicles entering or leaving the magazine
site. As the roads to/from and
within the magazine site will be paved, dust impact from the operation of the
magazine sites is anticipated to be insignificant. Hence, adverse air quality impact from
the operation of the Project is not anticipated. Cumulative impact during the operation
of the Project is also not anticipated as no significant air pollution source
is identified within the Study Area.
Since no adverse air quality impact is anticipated during the operation
of the Project, no mitigation measures are deemed necessary.
Operation of the magazine site will remain the same as
the current XRL project. The
operational activities involve the delivery of explosives to and from the
Project Site on a daily basis.
Potential sources of air quality impact include dust emissions from the
operation of explosives delivery vehicles from the magazine to the work areas,
with about two to eight trips per day.
Roads to/from and within the Project Site will be paved, thus dust
impact from the operation of the magazine site is anticipated to be
insignificant. Decommissioning of
the magazine site has the potential to cause dust emissions. Since the decommissioning works will be
small scale, the potential air quality impact is expected to be minimal with
the implementation of proper dust control measures. Air quality monitoring and audit is not
considered necessary during the operation of the Project as no adverse air
quality impact is anticipated.
This
chapter presents the potential impacts from waste generated by the operation
and decommissioning of the Project.
While the previously approved Hong Kong Section of the XRL EIA report
(No. AEIAR-143/2009) XRL) covers waste management implications of the whole XRL
Project, it does not include details specifically for
the TLEM site and therefore an independent assessment of the operational and
decommissioning waste implications for the current Project have been
undertaken.
The
following legislation covers the handling, treatment and disposal of wastes in
¡P
Waste Disposal Ordinance (WDO) (Cap 354);
¡P
Waste Disposal (Charges for
Disposal of Construction Waste) Regulation (Cap 354N);
¡P
Waste Disposal (Chemical
Waste) (General) Regulation
(Cap 354C);
¡P
Land (Miscellaneous
Provisions) Ordinance (Cap
28); and
¡P
Public Health and Municipal
Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances
Regulation.
The
Waste
Disposal Ordinance (WDO) prohibits the unauthorised disposal
of wastes, with waste defined as any substance or article which is
abandoned. Construction waste is
not directly defined in the WDO but
is considered to fall within the category of ¡¥trade waste¡¦. Trade waste is defined as waste from any
trade, manufacturer or business, wasted building, civil engineering materials,
but does not include animal waste.
Under the WDO, wastes can only
be disposed of at a licensed site.
A breach of these regulations can lead to the imposition of a fine
and/or a prison sentence. The WDO also provides for the issuing of
licences for the collection and transport of wastes. Licences for the collection and
transport of construction waste or trade waste, however, are not issued
currently. For general waste there
is no charge and this needs to be disposed in a licensed facility.
The
Waste Disposal (Charges for Disposal of
Construction Waste) Regulation (Cap
354N) defines construction waste as any substance, matters or things that
is generated from construction work and abandoned, whether or not it has been
processed or stockpiled before being abandoned. It does not include any sludge,
screening or matter removed in or generated from any desludging, desilting or
dredging works. The Construction Waste Disposal Charging Scheme
entered into operation on 1 December 2005.
Starting from 1 December 2005, a main contractor who undertakes
construction work with a contract value of HK$1 million or above is required to
open a billing account solely for the contract for waste disposal. Depending on the percentage of inert
C&D materials in the waste, it can be disposed of at public fill reception
facilities. However mixed
construction waste can be disposed of at construction waste sorting facilities,
landfills and Outlying Islands Transfer Facilities which have different
disposal costs. The scheme
encourages reducing, reusing and sorting of construction waste such that the
waste producer can reduce their disposal fee. Table 8.2 summarises the government
construction and demolition waste disposal facilities and types of waste
accepted.
Table 6.1 Government Facilities
for Disposal of Construction & Demolition Waste
Government Waste Disposal
Facilities |
Type of Construction
& Demolition (C&D) Waste Accepted |
Public
fill reception facilities |
Consisting
entirely of inert C&D materials |
Sorting
facilities |
Containing
more than 50% by weight of inert C&D materials |
Landfills
|
Containing
not more than 50% by weight of inert C&D materials |
Outlying
Islands Transfer Facilities |
Containing
any percentage of inert C&D materials |
Chemical
waste as defined under the Waste Disposal
(Chemical Waste) (General) Regulation includes any substance being scrap
material, or unwanted substances specified under Schedule 1 of the Regulation,
if such a substance or chemical occurs in such a form, quantity or
concentration so as to cause pollution or constitute a danger to health or risk
of pollution to the environment.
Chemical
waste producers shall register with the EPD. Any person who contravenes this
requirement commits an offence and is liable to a fine and imprisonment. Producers of chemical wastes must treat
their wastes, utilising on-site plants licensed by the EPD or have a licensed
collector take the wastes to a licensed facility. For each consignment of wastes, the
waste producer, collector and disposer of the wastes must sign all relevant
parts of a computerised trip ticket.
The system is designed to allow the transfer of wastes to be traced from
cradle-to-grave.
The
Regulation prescribes the storage
facilities to be provided on site including labelling and warning signs. To minimise the risks of pollution and
danger to human health or life, the waste producer is required to prepare and
make available written procedures to be observed in the case of emergencies due
to spillage, leakage or accidents arising from the storage of chemical
wastes. He/she must also provide
employees with training in such procedures.
The
inert C&D materials (also called public fill) may be taken to public fill
reception facilities. Public fill
reception facilities usually form part of land reclamation schemes and are
operated by the Civil Engineering and Development Department (CEDD) and
others. The Land (Miscellaneous Provisions) Ordinance requires that individuals
or companies who deliver public fill to the public fill reception facilities to
obtain Dumping Licences. The
licences are issued by CEDD under delegated authority from the Director of
Lands.
Individual
licences and windscreen stickers are issued for each vehicle involved. Under the licence conditions, public
fill reception facilities will only accept earth, soil, sand, rubble, brick,
tile, rock, boulder, concrete, asphalt, masonry or used bentonite. In addition, in accordance with
paragraph 11 of DEVB TC(W) No. 6/2010
¡§Trip Ticket System for Disposal of Construction and Demolition Materials¡¨,
the Public Fill Committee will advise on the acceptance criteria (e.g. no
mixing of construction waste, nominal size of the materials less than 250mm, etc). The
material will, however, be free from marine mud, household refuse, plastic,
metal, industrial and chemical wastes, animal and vegetable matter and any
other materials considered unsuitable by the public fill reception facility
supervisor.
This
Regulation provides further control
on the illegal dumping of wastes on unauthorised (unlicensed) sites. The illegal dumping of wastes can lead
to a fine and/or imprisonment.
Other
'guideline' documents, which detail how the Project Proponent or Contractor
should comply with the local regulations, are as follows:
¡P
Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes (1992), EPD,
¡P
New
Disposal Arrangements for Construction Waste (1992), EPD & CED,
¡P
WBTC No. 2/93, Public Dumps, Works Branch, Hong Kong
Government;
¡P
WBTC
No. 2/93B, Public Filling Facilities, Works Branch,
¡P
WBTC Nos. 25/99, 25/99A and
25/99C,
Incorporation of Information on Construction and Demolition Material Management
in Public Works Sub-committee Papers; Works Bureau,
¡P
WBTC No. 12/2000, Fill Management; Works
Bureau,
¡P
ETWBTC(W) No. 33/2002,
Management of Construction and Demolition Material Including Rock, Environment, Transport and
Works Bureau, Hong Kong SAR Government;
¡P
ETWB TC(W) No. 19/2005
Environmental Management on Construction Site, Environment, Transport and Works
Bureau, Hong Kong SAR Government.
¡P
DEVB TC(W) No. 6/2010, Trip
Ticket for Disposal of Construction and Demolition Materials;
¡P
DEVB TC(W) No. 8/2010,
Enhanced Specification for Site Cleanliness and Tidiness;
¡P
DEVB TC(W) No.2/2011,
Encouraging the Use of Recycled and Other Green Materials in Public Works
Projects; and
¡P
DEVB TC(W) No. 9/2011,
Enhanced Control Measures for Management of Public Fill.
The major types of solid waste likely to be generated
from the operation of the Project at the magazine site, is general refuse. The operation works will involve only
a very small amount of equipment including delivery vehicles for explosives
transport and two pumps for the Street Fire Hydrant Water Tank.
The
quantities of chemical waste to be generated from regular maintenance of
equipment will be minimal. Table 6.2
indicates
the different waste types and estimated quantities generated throughout the
operation of the Project and how these will be handled and disposed of. All chemical waste will be handled in
accordance with the EPD¡¦s Code of Practice on the Packaging Labelling and
Storage of Chemical Waste and a licenced collector will be employed for the
collection of the chemical waste generated to the licenced disposal
facilities. Hence, no adverse environmental
impact is anticipated due to the management of a small quantity of chemical
waste to be generated from the Project.
Table
6.2 Waste Types
Generated throughout Operation and Decommissioning of the Project
Waste Type |
Quantity Generated |
Handling & Disposal Options |
Operation |
|
|
General
refuse |
Up to
5 kg per day |
As per (2) |
C&D
materials |
None |
n/a |
Chemical
waste |
Minimal (< 1kg/month) (regular
maintenance of equipment will be carried out offsite) |
As per (3) |
|
|
|
Decommissioning |
|
|
General
refuse |
Up to
5 kg per day |
As per (2) |
C&D
materials |
Total
350 m3 |
As per (1)
& (2) |
- Inert |
325m3 |
|
- Non-inert |
25m3 |
|
Chemical
waste |
Minimal (< 10kg) (maintenance
of equipment will be carried out offsite) |
As per (3) |
(1) Inert C&D materials
will be disposed of at Tuen Mun
Area 38 Fill Bank
(2) Non-insert C&D
materials will be disposed of at WENT Landfill
(3) General refuse will be disposed
of at WENT Landfill or via transfer station
(4) All chemical waste will be
handled in accordance with the EPD¡¦s Code
of Practice on the Packaging Labelling and Storage of Chemical Waste. Employ a licenced collector for
collection of chemical waste and disposal at the licenced disposal facilities (eg Chemical Waste Treatment Facility at Tsing Yi)
The major types of solid waste likely to be generated
from the decommissioning works include construction and demolition (C&D)
materials (both inert and non-inert materials), chemical wastes and general
refuse. No
decommissioning materials will be considered for reuse except: metal
scrap/re-bar collected by the recycler; fire extinguishers collected by the
fire service provider; and fire hydrant water tank and water pumps. Negligible
amount of rock or spoil will be generated, and only small amount of metal will
be generated from the decommissioning works. Owing to the small scale of works, the
amount of C&D materials generated will be limited, approximately 350 m3.
Currently the TLEM is operated under Contract
CV/2012/08, and all non-inert waste will be disposed at NENT landfill using the
existing billing account of the Contract i.e. NENT landfill is the designated
disposal site of the Contract. Table 6.2
indicates
the different waste types and estimated quantities generated from the
decommissioning of the Project and how these will be handled and disposed of.
Based
on the above, the potential impacts associated with the handling and disposal
of C&D materials due to the decommissioning works are considered minor.
With
proper housekeeping measures and refuse collection in place, minimal or no
impact is expected to result from refuse generated during the operational
phase.
The
decommissioning works will involve only a very small number of construction
equipment. The quantities of
chemical waste generated will also be minimal. All chemical wastes will be handled in
accordance with the EPD¡¦s Code of
Practice on the Packaging Labelling and Storage of Chemical Waste and a
licenced collector will be employed for the collection of the chemical waste
generated to the licenced disposal facilities (eg
Chemical Waste Treatment Facility at Tsing Yi). Hence, no adverse environmental impact
is anticipated due to the management of a small quantity of chemical waste to
be generated from the Project. With
proper housekeeping measures and refuse collection in place, minimal or no
impact is expected to result from refuse generated (up to about 5 kg per day)
during the decommissioning works.
The inert and non-inert C&D materials will be disposed of at Tuen Mun Area 38 Fill Bank and
WENT Landfill, respectively. The
general refuse will be disposed of at WENT Landfill or via transfer station.
To
minimise the amount of waste, careful design, comprehensive planning and good site
management practice will be adopted by the contractors of the Project and waste
on-site will be properly segregated to increase the potential for reuse and
recycling. Chemical waste generated
from equipment operation and demolition works will be properly stored in
accordance with Code of Practice on the
Packaging, Labelling and Storage of Chemical Waste published by the EPD
before collection for disposal by a licensed Chemical Waste Collector. The quantity of general refuse generated
on-site will be minimal owing to the nature of the operation activities and the
small number of workers involved during decommissioning.
The
amount of general refuse generated from the operation and decommissioning of
the magazine site is expected to be small.
General refuse will be stored and disposed of separately from chemical
waste. C&D materials from the
decommissioning will also be handled and disposed of appropriately. Provided that general refuse is removed
from the Project Site regularly during operation and decommissioning (e.g. once
per day) and C&D materials is disposed of appropriately, no adverse
environmental impact related to handling and disposal of wastes is expected.
This
section presents the potential impacts from the operation and decommissioning
of the Project on water quality.
While the previously approved Hong Kong Section of the XRL EIA report
(No. AEIAR-143/2009) XRL) covers the implication of potential water quality
impacts from the whole XRL Project, this does not include details specifically
at the TLEM site. Section 3 Ecology of the XRL EIA
addresses impacts to two watercourses in the TLEM project site, watercourse 4
and watercourse 5, and equally these are addressed in Chapter 3 Ecology of this report.
The
following relevant legislation and associated guidance are applicable to the
evaluation of water quality impacts associated with the Project:
¡P
Water Pollution Control
Ordinance (WPCO);
¡P
Technical Memorandum for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters (TM- ICW);
¡P
Environmental Impact
Assessment Ordinance (Cap. 499. S.16) and the Technical Memorandum on EIA
Process (EIAO-TM), Annexes 6 and 14.
The
Water Pollution Control Ordinance (WPCO)
is the primary legislation for the control of water pollution and water quality
in Hong Kong. Under the WPCO, Hong Kong waters are divided into
10 Water Control Zones (WCZs). Each
WCZ has a designated set of statutory Water Quality Objectives (WQOs).
All discharges during both the operation phase of the
proposed Project are required to comply with the Technical Memorandum for Effluents Discharged into Drainage and
Sewerage Systems, Inland and Coastal Waters (TM-ICW) issued under Section 21 of the WPCO.
The TM-ICW
defines acceptable discharge limits to different types of receiving
waters. Under the TM-ICW, effluents discharged into the
drainage and sewerage systems, inshore and coastal waters of the WCZs are
subject to pollutant concentration standards for specified discharge
volumes. These are defined by the
Environmental Protection Department (EPD) and are specified in license
conditions for any new discharge within a WCZ.
Under Section 16 of the EIAO, Environmental Protection
Department (EPD) issued the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM) which specifies the assessment methods and
criteria for environmental impact assessment. This section follows the EIAO-TM to
assess the potential water quality impacts that may arise during the operation
and decommission phases of the Project.
Sections in the EIAO-TM relevant to the water quality impact assessment
include: Annex 6 - Criteria for Evaluating Water Pollution; and Annex 14 -
Guidelines for Assessment of Water Pollution.
The Project is located in Tai Shu Ha, which is within
the water catchment of the Yuen Long Creek. As shown in Figure 7.1,
there are two minor watercourses within 500 m from the Project boundary. Both of these watercourses run into a
tributary of Yuen Long Creek, which is continuously monitored by EPD at YL2 and
YL3 as also shown in Figure 7.1. The 2013 river water quality at EPD
monitoring stations YL2 and YL3 downstream of the Project Site is summarized
below in Table 7.1.
Yuen Long Creek¡¦s overall compliance rate in 2013 was
51%, compared with 53% in 2012. The
compliance rate for the more upstream YL2 station (which is still downstream of
the Project Site) was 60% in 2013 as compared 62% in 2012. The compliance rate for the YL3 station
in the middle of Yuen Long township was 42% in 2013 as compared with 42% in
2012. This river is subject to
discharges from livestock farms, unsewered village
houses and industrial establishments.
Table 7.1 River Water
Quality at Yuen Long Creek Downstream to the Project Site in 2013
Parameter |
Unit |
Yuen Long Creek |
|
YL2 |
YL3 |
||
Dissolved
oxygen |
mg/L
|
6.7 (3.0
- 9.6) |
5.0 (2.6
- 6.9) |
pH |
|
7.3 (7.2
- 7.6) |
7.6 (7.1
- 8.4) |
Suspended
solids |
mg/L
|
10 (4 - 27) |
27 (9 -
140) |
5-day Biochemical Oxygen Demand |
mg/L
|
9 (4 -
40) |
38 (4 -
82) |
Chemical Oxygen Demand |
mg/L
|
29 (11 -
69) |
45 (9 -
180) |
Oil
& grease |
mg/L
|
0.6
(<0.5 - 1.6) |
1.3
(<0.5 - 5.0) |
Faecal
coliforms |
cfu/ 100mL |
<130,000
(<1,000 - 740,000) |
870,000
(250,000 - 2,800,000) |
E.
coli |
cfu/ 100mL |
<93,000
(<1,000 - 630,000) |
330,000
(71,000 - 1,200,000) |
Ammonia-nitrogen
|
mg/L
|
13.50 (0.76
- 20.00) |
2.90
(0.36 - 11.00) |
Nitrate-nitrogen
|
mg/L
|
1.85
(0.19 - 6.40) |
<0.01
(<0.01 - 1.30) |
Total Kjeldahl nitrogen |
mg/L
|
16.00
(1.30 - 23.00) |
4.10
(0.87 - 14.00) |
Ortho-phosphate
|
mg/L
|
2.40
(0.22 - 3.10) |
0.35
(<0.01 - 1.10) |
Total
phosphorus |
mg/L
|
2.45
(0.28 - 3.40) |
0.56
(0.21 - 1.90) |
Total
sulphide |
mg/L
|
<0.02
(<0.02 - 0.05) |
<0.02
(<0.02 - 0.07) |
Aluminium
|
£gg/L
|
110 (70
- 330) |
355 (134
- 520) |
Cadmium
|
£gg/L
|
<0.1
(<0.1 - 1.0) |
0.2
(<0.1 - 1.0) |
Chromium
|
£gg/L
|
<1
(<1 - <1) |
<1
(<1 - 8) |
Copper
|
£gg/L
|
4 (3 -
7) |
5 (2 -
10) |
Lead
|
£gg/L
|
<1
(<1 - 8) |
5 (1 -
17) |
Zinc
|
£gg/L
|
31 (20 -
120) |
45 (18 -
96) |
Flow
|
L/s
|
18 (10 -
504) |
450 (135
- 1,100) |
Notes:
1. Data presented are in annual
medians of monthly samples; except those for faecal
coliforms and E. coli which are in annual geometric means.
2. Figures in brackets are annual
ranges.
3. cfu -
colony forming unit.
4. Values at or below laboratory
reporting limits are presented as laboratory reporting limits.
5. Equal values for annual medians
(or geometric means) and ranges indicate that all data are the same as or below
laboratory reporting limits
The
Project Site is currently being used as an explosive magazine site for the
construction of the XRL. As such,
there will not a construction phase for this Project.
The
operation of the magazine site is expected to be similar to the previous
operation under the XRL, which involves only storage of explosive within
Project Site and transportation of explosive to / from the Project Site. Such operation activities are not
expected to involve any discharges or effluent to streams. Appropriate surface drainage has been
provided by the previous occupant of the site following the requirements
stipulated under ProPECC PN 5/93 ¡§Drainage Plans subject to Comment
by the Environmental Protection Department¡¨ and storm water would be
discharged into the surface drainage system. The nearby roads connecting the Project
Site are already paved and adverse water quality impact from storm runoff from
unpaved roads is not expected.
There will not be a significant number of staff staying at the Project Site,
with the exception of only a few security guards. One chemical toilet would be provided on
site and night soil would be regularly collected by a licensed contractor. No adverse water quality impact is
expected from the operation of the proposed magazine site.
A
brief description on the decommissioning works required is provided in Annex
2A. The decommissioning works
that may have the potential to generate silty surface runoff are expected to
include minor dismantling, demolition and removal of temporary structures. No major civil works would be
required. Adverse water quality
impact is therefore not expected with the implementation of proper site runoff control measures considering
the small scale and short duration of works activities. Water quality impact on other fresh
water courses from the works is
also unlikely. Any discharge from
the site would be expected to be in compliance with the requirements of the
Water Pollution Control Ordinance.
Appropriate
measures will be implemented in accordance with the guidelines stipulated in
EPD¡¦s Practice Note for Professional
Persons on Construction Site Drainage (ProPECC
PN1/94) during the decommissioning works to properly control site run-off
and drainage and to minimise potential water quality impacts. Major relevant measures include those
listed below
¡P
Surface
run-off from construction site should be discharged into storm drains via
adequately designed sand/silt removal facilities such as sand traps, silt traps
and sediment basins. Channels or
earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities. Perimeter channels at site boundaries
should be provided where necessary to intercept storm run-off from outside the
site so that it will not wash across the site. Catchpits and
perimeter channels should be constructed in advance of site formation works and
earthworks.
¡P
Silt
removal facilities, channels and manholes should be maintained and the
deposited silt and grit should be removed regularly, at the onset of and after
each rainstorm to ensure that these facilities are functioning properly at all
times.
¡P
Earthworks
final surfaces should be well compacted and the subsequent permanent work or
surface protection should be carried out immediately after the final surfaces
are formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting
channels should be provided where necessary.
¡P
Manholes
(including newly constructed ones) should always be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris from
getting into the drainage system, and to prevent storm run-off from getting
into foul sewers. Discharge of
surface run-off into foul sewers must always be prevented in order not to
unduly overload the foul sewerage system.
¡P
Precautions
and actions, as stipulated
in Appendix A2 of ProPECC PN1/94, should be taken at any time of
year when rainstorms are likely, when a rainstorm is imminent or forecast, or
during and after rainstorms.
In addition, to minimize erosion of
exposed soil in between the removal of paved area and the re-vegetation /
plantation, exposed soil should be covered with geotextile promptly after the
removal works.
This
section presents the potential impacts from the operation and decommissioning
of the Project on landscape and visual elements.
The
Project Site is currently being used as an explosive magazine site for the
construction of the XRL and therefore there will be no change to the current
landscape and visual elements. The
TLEM site, as well as the two one-storey stores, is largely shielded by
topography and trees in the area which Figure2.9b helps
illustrate, with Figures 2.7 and 3.1 collectively illustrating the surrounding
topography and extent of trees. No
adverse landscape and visual impacts are anticipated from the operation and
decommissioning of the proposed magazine site.
The
previously approved Hong Kong Section of the XRL EIA report (No.
AEIAR-143/2009) XRL) proposed that the magazine site be re-planted upon
completion of the XRL project, to help compensate for the felling of trees that
had been necessary initially to construct this magazine site. Chapter
3 Ecology of this report
addresses this matter.
The
scope of the approved XRL EIA was far broader than just the TLEM since it
covered a much larger area. This
EIA included assessments on impacts to Cultural Heritage, Fisheries,
Ground-borne Noise, Land Contamination, Landfill Gas Hazard and Impacts on the
Restored Ngau Tam Mei Landfill.
None of these media are considered relevant to this Project giving its
situation and size, absence of any tunnelling work nor generation of
significant waste.
No adverse water quality or landscape and visual
impacts from operation and
decommissioning of the Project are anticipated. Mitigation measures and environmental
monitoring and audit during the operational and decommissioning
phase are not considered necessary for landscape and visual impacts. Additional mitigation measures are
proposed under section 7.1.3 to
minimize any potential water quality impact from the decommissioning works
under this Project.
This Project is also considered to have no impacts on
certain environmental media covered in the XRL EIA, namely Cultural Heritage,
Fisheries, Ground-borne Noise, Land Contamination, Landfill Gas Hazard and the
Restored Ngau Tam Mei Landfill.
This chapter of the EIA presents a
summary of the analysis and findings of the Hazard to Life Assessment (also
referred as Quantitative Risk Assessment (QRA)) undertaken for the proposed
operation of the existing TLEM for this Project, in accordance with the EIA
Study Brief (ESB-280/2014), Section 3.4.3.
The TLEM operation will remain the
same as the current MTR XRL 824 Contractor with explosives delivered by DHK to
three worksites located at Sha Tau Kok Road ¡V Wo Hang
Section (North Portal), Po Kat Tsai Road (Mid Ventilation Portal) and Tong Hang
Tung Chuen (South Portal). Mines will deliver explosives and
initiation devices (detonators) to the Magazine on a daily basis and these will
be withdrawn by the contractors as required. The transportation of explosives by
Mines either to the Magazine or directly to sites is under Mines¡¦
responsibility and falls outside the scope of this EIA study.
The Hazard to Life/ QRA assessment
under this chapter of the EIA, addresses, in particular, the following:
¡P
Storage
of explosives at the proposed magazine (cartridged
emulsion, detonating cord, cast boosters and detonators) including handling of
explosives within the magazine site; and
¡P
Transport
of explosives to the three worksites.
Further details of the QRA for the
Project are presented in the Annex 8A.
The
key legislation and guidelines that are considered relevant to the Project are
as follows:
¡P
Dangerous Goods Ordinance, Chapter 295; and
¡P
Environmental Impact
Assessment Ordinance (EIAO),
Chapter 499.
The
requirement for a QRA of projects that involve the storage and transport of
dangerous goods where a risk to life is a key issue with respect to the Hong
Kong Government Risk Guidelines (HKRG) is specified in Section 12 of the Environmental
Impact Assessment Ordinance Technical Memorandum (EIAO-TM).
The
relevant authority for a QRA study relating to an explosives magazine storage
facility and the transport of the explosives is the Environmental Protection
Department (EPD), as specified in Annex
22 of the EIAO-TM.
Annex 4 of the EIAO-TM specifies the Individual and Societal Risk Guidelines.
Individual risk is the
predicted increase in the chance of fatality per year to an individual due to a
potential hazard. The individual
risk guidelines require that the maximum level of individual risk should not
exceed 1 in 100,000 per year i.e. 1 ¡Ñ 10-5 per year.
Societal
risk expresses the risks to the whole population. The HKRG is presented
graphically in Figure 8.1. It is expressed in terms of lines
plotting the frequency (F) of N or more deaths in the population from incidents
at the installation. Two F-N risk
lines are used in the HKRG that demark ¡§acceptable¡¨ or ¡§unacceptable¡¨ societal
risks. The intermediate region
indicates the acceptability of societal risk is border-line and should be
reduced to a level which is ¡§as low as is reasonably practicable¡¨ (ALARP). It seeks to ensure that all practicable
and cost effective measures that can reduce risk will be considered.
Figure 8.1 Societal Risk Criteria in
Hong Kong
The
statutory / licensing requirements with respect to the explosives (Cat. 1
Dangerous Goods) or the oxidizing substances (Cat. 7 Dangerous Goods) used to
prepare explosives at the construction work area as well as relevant government
departments/ authorities¡¦advice and practice on the proposed transport and
storage of explosives for the blasting activities are summarized below.
The
Commissioner of Mines Division is the responsible authority for this and
applicable regulations/ guidance notes include:
¡P
Supply
of detonators, cast boosters and cartridged emulsion
explosives (under the Dangerous Goods (General) Regulations Cap. 295B);
¡P
Approved
explosives for blasting in Hong Kong (under the Dangerous Goods (General)
Regulations Cap. 295B);
¡P
Blast
design (under the Dangerous Goods (General) Regulations Cap. 295B);
¡P
Blast
loading and execution (under the Dangerous Goods (General) Regulations Cap.
295B);
¡P
Removal
of explosives (under Regulation 4 of the Dangerous Goods (General) regulations
Cap. 295B);
¡P
Approval
of an explosives delivery vehicle (under CEDD¡¦s ¡§Guidance Note on Requirements
for Approval of an Explosive Delivery Vehicle¡¨ (ref.34));
¡P
Explosive
delivery vehicle design features and safety requirements (under CEDD¡¦s ¡§Guidance
Note on Requirements for Approval of an Explosive Delivery Vehicle¡¨(ref.34);
¡P
Explosive
magazine (under CEDD¡¦s document ¡§How to Apply for a Mode A Explosives Store
Licence¡¨ (ref.35));
¡P
Explosives
produced at site (under Regulation 31A of the Dangerous Goods (General)
Regulations Cap. 295B); and
¡P
Explosives
load per truck (in accordance with the Removal Permit under the Dangerous Goods
(General) Regulations Cap. 295B).
The
Fire Services Department is the responsible authority for this and applicable
regulations include:
¡P
Storage
of oxidizing agents (under Dangerous Goods (General) Regulations Cap. 295B)
The
objective of the QRA study is to assess the risk to life of the general public
from the hazards that arise from the storage and transport of the explosives of
the Project. The results of the QRA
are then compared with the HKRG.
The
detailed requirements of the study are given in Section 3.4.3 of the EIA Study Brief. The main requirements are:
¡P
Identify
hazardous scenarios associated with the storage and transport of explosives and
then determine a set of relevant scenarios to be included in a Quantitative Risk
Assessment (QRA);
¡P
Execute
a QRA of the set of hazardous scenarios, expressing population risks in both
individual and societal terms;
¡P
Compare
individual and societal risks with the criteria for evaluating hazard to life
stipulated in Annex 4 of the TM; and
¡P
Identify
and assess practicable and cost-effective risk mitigation measures.
The
methodology used in the hazard assessment is consistent with previous studies
having similar issues (e.g. Hong Kong Section of Guangzhou-Shenzhen-Hong Kong
Express Rail Link (XRL) EIA report (Register No. AEIAR-143/2009)).
The
elements of the QRA study are shown schematically in Figure 8.2 and include:
¡P
Collection
and review of relevant data for the TLEM Site, the transport from TLEM Site, as
well as population and vulnerable receptors, such as slopes, retaining walls
etc., in the vicinity of the worksites and proposed transport routes;
¡P
Hazard
identification. A review of
literature and accident databases was undertaken and updated. These formed the
basis for identifying all the hazardous scenarios for the QRA study;
¡P
Frequency
estimation. The frequencies, or the
likelihood, of the various outcomes that result from the hazards associated
with the storage and transport of explosives was taken primarily from previous
EIA studies that have been accepted by the relevant authorities;
¡P
For
all identified hazards, the frequency assessment has been documented and the
consequences of the event has been modelled;
¡P
The
consequence model employed in this study is the ESTC model (ESTC, 2000)
developed by the UK Health and Safety Commission (HSC). Although, there have
been a number of recent studies suggesting that the ESTC (2000) models should
be reviewed for applicability to explosive stores and transport, these models
are still the recommended models in the UK and have been adopted in previous
Hong Kong EIA studies;
¡P
The
same frequency model was adopted in this study as that of ERM (2009) study,
which has been derived to reflect the current Transport Department statistics,
Fire Services Department statistics, specific design features applicable for
the project and current knowledge of explosives;
¡P
The
consequence and frequency data were subsequently combined using ERM¡¦s in-house
Explosive Transport GIS Risk Assessment tool (E-TRA), which has been developed
to account for three-dimensional blast effects on buildings and the effect of
accidental explosions on elevated roads.
It also accounts for traffic jam scenarios which could occur in some
accidental scenarios as reported in the DNV (1997) study. The model is summarised in the next
section and has been validated against ERM in-house proprietary software Riskplot TM. This risk assessment tool has been
employed in the ERM (2009) study; and
¡P
Finally,
the results from the risk assessment were compared to the EIAO-TM Criteria.
Recommendations have been made where required to ensure compliance with EIAO-TM Criteria, relevant best
practice, and work to reduce the overall risk levels.
Figure 8.2 Schematic Diagram of the
QRA Process
The TLEM site and transport
route options are described in Chapter 2
Project Description and the estimated project period for explosives storage
and transport would be from late 2015 or early 2016 (expected January 2016) to
December 2017.
The
TLEM is designed to store sufficient quantities of explosives for two days so
as to allow blasting to be carried out 24 hours per day and provide a buffer in
the event of delivery interruption to the Magazine by Mines Division.
The
magazine at Tai Lam (Tai Lam Explosives Magazine or TLEM) serves three
worksites in the Northern New Territories.
The site comprises two individual magazine stores, each with a single
structure storing 400 kg of explosives such as cartridged
emulsion, cast boosters and detonating cord. A storage chamber for detonators holding
1900 detonators, equivalent to two days¡¦ supply, is provided next to each
explosives chamber. The detonators
have a very low explosive mass and contain less than 1 gram of high explosives
per detonator. Therefore, the net
explosive quantity within the detonator chamber is less than 2 kg.
Each
of the magazine buildings is a single-storey, detached and bunded
structure, which is fenced and secured in accordance with the Commissioner of
Mines¡¦ requirements. Details of the
requirements are defined in the CEDD document ¡§How to Apply for a Mode A
Explosives Store Licence¡¨ (ref.35). Surface road access suitable for 11-tonne
trucks is also provided for delivery of explosives. Mines Division will deliver explosives
to the Magazine on a daily basis, from where explosives will be transferred to
the work areas by the contractors for the daily or twice-daily blasts depending
on requirements for construction.
Loads will be limited to a maximum of 200 kg per truck or less in
accordance with the Removal Permit issued by Mines Division.
The proposed explosives
transport routes to the three worksites are shown in Figure 8.3
(Route
Option R1, Route Option R2 and Route Option R3 respectively).
In Route Options R1 and R3, the explosives delivery
truck will pass through Pok Oi Interchange and Shap Pat Heung Interchange. During the Fourth Meeting of Traffic and
Transport Committee under Yuen Long District Council on 24 July 2014
(Thursday), members expressed concerns on the traffic conditions of Pok Oi Interchange.
Currently there is road improvement work which leads to serious traffic
jams, thus temporary road diversion and traffic control measures are
enforced. The road improvement work
is expected to be completed in 2015 but may be delayed due to the flyover
foundation. Therefore, members
generally did not prefer the use of Pok Oi
Interchange by the explosives delivery truck during the road improvement work,
and recommended to use Tong Yan San Tsuen Interchange and Yuen Long Road, which
is Route Option R2.
The explosives delivery routes will be:
¡P At
early stage of this project, during road improvement work at Pok Oi Interchange (expected to be completed in 2015 but
may be delayed), Route Option R2 will be used. Route Options R1 and R3 are not feasible
since they both route via Pok Oi Interchange.
¡P After
road improvement work at Pok Oi Interchange is
completed, all three routes will be available for use. The Route Option with minimum transport
risk will be used.
In
addition to cartridged emulsion, cast boosters and
detonating cord, detonators will also be transported. Detonators will be
transported in a separate and dedicated licenced vehicle.
The
licensed explosives delivery vehicles (LGV pick-up trucks) for delivery of
explosives from the Magazine to the worksites, used as the basis for this QRA,
will have the following safety features:
¡P
Diesel
powered;
¡P
Driver¡¦s
cabin is separated by a distance of not less than 150 mm from the cargo
compartment of the vehicle;
¡P
Manual
fuel isolation switch;
¡P
The
exhaust system is located as far from the cargo compartment as possible. The
modification of the exhaust system will be approved by the Transport Department;
¡P
All
electrical wiring and fittings will be shrouded in fire resisting conduits;
¡P
Fuel
tank will be protected from accidental damage, and designed to prevent
accumulation of spilt fuel on any part of the vehicle;
¡P
The
required number of fire extinguishers shall be agreed with Mines Division;
¡P
Fire
resistant material shall be fitted between the wheel arches and the goods
compartment;
¡P
Hand-held
lightning detector provided in the vehicle for lightning detection during loading
and unloading of explosives;
¡P
Lockable
wood lined steel or aluminium receptacles mounted on the vehicle tray; and
¡P
Fold
down / up explosives warning signs and red strobe beacons.
In addition to the minimum
requirements, a fire screen will be fitted between the cab and the load
compartment, both between the cab and the load compartment and underneath the
load compartment. The fire screen shall be 3 mm; extend to 150 mm above [all
sides of] and run completely under the load compartment; to at least 100 mm
behind the cab of the vehicle.
The
explosives to be stored and transported from the Magazine to the worksites will
include detonators, detonating cord, cast boosters and cartridged
emulsion.
Cartridged emulsion, cast boosters
and detonating cord will be delivered from the explosives Magazine to the
worksites by the appointed contractor (i.e. DHK) using Mines Division licenced
trucks. These explosives are
classified as an explosive Class 1.1D under United Nation (UN) Classification
(ref.7) and as a Category 1 (Explosive and Blasting Agents) Dangerous Goods
under the Hong Kong Dangerous Goods
Ordinance.
Detonators
will also be used to initiate the blast at the working face. They are classified as Class 1.4B or
1.4S explosives under the UN classification system and Category 1 (Explosives
and Blasting Agents) under the Hong Kong
Dangerous Goods Ordinance, and will be transported from the Magazine to
worksites by a dedicated truck, which is identical to, but independent of the
truck carrying the emulsion explosives and detonating cord.
Figure
8.3 Proposed
Explosive Transport Routes Option R1, R2 and R3
Route Option R1
Route Option R2
Route Option R3
The
actual explosives requirements will depend on the construction programme and
the detailed design. It may also
depend on the actual achievable progress rates which may vary due to specific
site conditions (e.g. geology). To
consider the uncertainty in the envisaged construction programme, a Base Case,
which accounts for expected programme variations, and a Worst Case, which
presents the worst programme scenario (i.e. a 20% increase in the number of
deliveries compared to the Base Case scenario), have been considered for the
assessment.
In
this study, three Route Options have been presented as the Base Case as
summarised in Section 2.1.2 with
details found in Annex 8A
Full Hazard Assessment Report.
Based
on the envisaged construction programme and sequence of works, the annual
travel distance by explosive vehicles, carrying cartridged
emulsion, cast boosters and detonating cord, will reach a peak in the period
between March 2016 and February 2017.
Within this period, taking Route Option R1 as an example, the annual
number of deliveries is 2,100 while the explosive trucks travel distance is
around 53,165 km. This period is
referred to as the peak explosive delivery period which is taken to represent
the Base Case scenario for the Hazard to Life Assessment. The delivery frequency has been
estimated on the basis that, for a given delivery point, each delivery will be
made to each worksite independently of the other worksites even if the load
could be transported on the same truck.
This approach, although slightly conservative, accounts for expected
delivery variations during the peak delivery period, within which, separate
deliveries will be generally undertaken.
In the Base Case, it was considered
that explosives delivery could be carried out at any time of the day depending
on the blasting programme to allow for flexibility to the blasting programme.
In this project, for a particular
delivery point, it is possible that the explosive load required for each
delivery will be higher than that indicated in the envisaged programme due to
particular site conditions and blasting requirements; however, the truck load
is conservatively assumed to be 200 kg in each trip. The actual truck load is 42 ¡V 83 kg for
North Portal, 43 ¡V 65 kg for Mid-Ventilation Portal and 84 ¡V 132 kg for South
Portal, which are significantly lower than the maximum truck load of 200
kg.
In this Project, explosives transport
will be scheduled with a total of two to six deliveries per day to the three
worksites (explosives are required at two to three worksites per day) and
maximum seven (7) days per week. CEDD Mines Division will supply the explosives
to the magazine site on weekdays (Monday to Friday) and on Saturday if
necessary.
The Base Case programme is summarized
in Table
8.1.
Table 8.1 Summary of
Explosives Deliveries and Transport Quantities (Base Case)
Works Area |
Delivery |
Blast Face |
Explosive Deliveries
in Peak Period (trips/yr) |
Explosive
Load (kg/trip) |
North Portal |
Sha Tau Kok
Road |
Dual two-lane trunk road connecting
the BCP with Tolo/Fanling
Highway |
570 |
200 (Actual load is 42 ¡V 83 kg/trip) |
|
|
|
|
|
Mid-Ventilation Portal |
Po Kat Tsai Road |
Dual two-lane trunk road connecting
the BCP with Tolo/Fanling
Highway |
450 |
200 (Actual load is 43 ¡V 65 kg/trip) |
|
|
|
|
|
South
Portal |
Tai
Wo Service Road East |
Dual
two-lane trunk road connecting the BCP with Tolo/Fanling Highway) |
1080 |
200 (Actual
load is 84 ¡V 132 kg/trip) |
|
|
|
|
|
The
Hazard to Life Assessment also covers the Worst Case scenario. It addresses the possibility that, due
to construction uncertainties or contractors¡¦ methods of working, the
contractors propose an actual construction programme which differs from the
envisaged construction programme.
Such a case may result in a higher number of delivery trips. Return trips loaded with explosives will
generally be avoided, however, due to some construction uncertainties, a number
of return trips could be made.
Overall, in the worst case, a 20% increase in the number of deliveries
compared to the Base Case scenario may result based on previous project
experience.
The
Worst Case programme is summarized in Table 8.2.
Table 8.2 Summary of Explosives
Deliveries and Transport Quantities (Worst Case)
Delivery |
Blast Face |
Explosive Deliveries in
Peak Period (trips/y) |
Explosive Load (kg/trip) |
|
North
Portal |
Sha
Tau Kok Road |
Dual two-lane trunk road
connecting the BCP with Tolo/Fanling
Highway |
684 |
200 (Actual
load is 42 ¡V 83 kg/trip) |
|
|
|
|
|
Mid-Ventilation Portal |
Po Kat Tsai Road |
Dual two-lane trunk road
connecting the BCP with Tolo/Fanling
Highway |
540 |
200 (Actual load is 43 ¡V 65
kg/trip) |
|
|
|
|
|
South Portal |
Tai Wo Service Road East |
Dual two-lane trunk road
connecting the BCP with Tolo/Fanling
Highway) |
1296 |
200 (Actual load is 84 ¡V 132
kg/trip) |
|
|
|
|
|
Population
within the vicinity of the Magazine is estimated based on site surveys and
information gathered from Geographic Information System (GIS) database 2014
data (ref.22) and aerial maps.
There are no known (current or future) buildings or any other structures
in the hazard zone of the proposed Magazine.
Population
data used for the transport risk assessment have been collected by a
combination of site survey, Annual Traffic Census 2013 (ref.26), Centamap (2015) and GIS tools. For areas where information is not
available, assumptions have been used consistently with the previously approved
studies. Three types of population
have been considered.
¡P
Pedestrian population on
footpaths and pavements next to delivery routes;
¡P
Road population; and
¡P
Building population.
The
approach to modelling the risks during transport of explosives is fully
3-dimensional and GIS based. It
also accounts for the potential increased risk when explosives truck travel on
elevated roads.
The
population data adopted in the QRA is detailed in Annex 8A.
Hazard
identification consisted of a review of the following:
¡P
Explosives properties;
¡P
Scenarios presented in
previous relevant studies;
¡P
Historical accidents; and
¡P
Discussions with explosives
and blasting specialists.
Explosives
present a hazard to both property and people. This hazard manifests itself in
the following ways:
¡P
Blast
and pressure wave;
¡P
Flying
fragments or missiles;
¡P
Thermal
radiation; and
¡P
Ground
shock.
In the case of explosions,
the biggest damage is usually caused by the blast effects. The blast and pressure waves can cause
injury to sensitive human organs such as the ears and lungs. However, considerable overpressures are
required for fatalities to occur, and consequently people need to be fairly
close to the scene of the direct explosion effects to be significant.
Other effects due to the
blast or overpressure are associated with damage to buildings and other
structures/ objects or the impact of debris and fragments from damaged building
structure, and the vehicle or container in which the explosives are held.
Moreover, injury may occur when people are displaced or swept away, or due to
the violent movement of internal organs within the body.
An explosion may produce a
shock wave in the solid material with significant confinement such as rock
excavation. Considering explosive
transport and storage will be carried out aboveground with much less
confinement than rock excavation, consequence of ground shock induced by
explosion should not be of much concern compared to the hazards posed by the
overpressure wave and debris generated.
A
review of reported safety incidents involving storage, transport and disposal
of explosives (in industrial applications) was carried out. Records were
retrieved mainly from the UK Health and Safety Executive (UK HSE)¡¦s Explosives
Incidents Database Advisory Service (EIDAS) , US Mine Safety and Health
Administration (MSHA) and Western Australia¡¦s Department of Consumer and
Employment Protection (DOCEP). The
records provided are also supplemented with information obtained from various
sources. An analysis of accident
data is provided in Annex 8A, Sections 5 and Section 6.
The
following Table
8.3 provides a summary of the scenarios
considered in this QRA.
Table 8.3 Scenarios
Considered in the QRA study
Scenario |
|
Storage
of Explosives |
|
01 |
Detonation of full
load of explosives in one store in the Tai Lam Explosives Magazine Site |
02 |
Detonation of full
load of explosives in one contractor truck on the access road within Tai Lam
Explosives Magazine Site boundary |
Transport
of Explosives |
|
03 |
Detonation of full
load of explosives in one contractor truck on public roads ¡V from Tai Lam
Explosives Magazine site to Mid Ventilation Adit delivery
point |
04 |
Detonation of full
load of explosives in one contractor truck on public roads ¡V from Tai Lam
Explosives Magazine site to North Portal delivery point |
05 |
Detonation of full
load of explosives in one contractor truck on public roads ¡V from Tai Lam
Explosives Magazine site to South Portal delivery point |
|
|
Deflagration
or detonation explosion may occur during the transportation of explosives from
the Magazine to the worksites. This
accidental explosion can be caused by spontaneous fire (non-crash fire), fire after
a vehicle crash (crash fire), impact initiation in crash (crash impact), or
spontaneous explosion during the normal condition of transport which may occur
if the cargo load contains ¡¥unsafe explosives¡¦.
In
this study, a fault tree has been developed to assess the overall explosion
frequency as applicable to the Project contractors¡¦ trucks based on the latest
information available on the explosives properties, vehicle incident
frequencies provided by the Transport Department and Fire Services Department,
and the specific explosive transport vehicle design and operation to be used as
part of the Project. The details of
the frequency assessment are provided in Annex 8A, Section 6. The frequency analysis is consistent
with the approved XRL EIA QRA study.
The overall initiating event frequency within the storage
magazine is based upon the UK HSE recommended value of 1 x 10-4 per
storehouse year. Additional risk due to manual transfer of explosives,
lightning strike, aircraft crash, hill/ vegetation fire, earthquake and other
site specific considerations to this project were also considered but their
contribution was negligible (see Annex 8A,
Section 6).
The
probability of fatality due to blast over-pressure, have been estimated using
the method detailed by the UK HSE Explosives Storage and Transport Committee
(ESTC) (ref.9). The fatality
contours are calculated at 90%, 50%, 10%, 3% and 1% fatality. Details of the model and the results are
given in Annex 8A, Section 7.
Special
features such as slopes and service reservoirs along the transport routes or
near the Magazine site were identified with respect to the potential secondary
hazards. These aspects of risk were
evaluated separately, and were found either insignificant or already covered by
applying the blast overpressure-fatality model (i.e. ESTC model (ref.9)).
The individual risk (IR) contours
associated with the Project are shown in Figure 8.4,
Figure 8.5,
Figure 8.6 and Figure 8.7. In Figure 8.7, the ¡¥indoor¡¦ refers to
the population located inside buildings, and the ¡¥outdoor¡¦ refers to the
population located outside buildings i.e. in open area. At the same distance from a potential
explosion, persons located inside buildings are more vulnerable to explosion
than persons located outside buildings as they are exposed to more hazards such
as debris from broken windows, etc.
This explains a higher individual risk for indoor population.
The
Magazine is in remote areas. The
individual risk contours of 1 x 10-5 per year extend outside the
site boundary. However this impacts
only on woodland areas where there is no continuous presence of people. The presence of people in these areas
will be rare and only temporary leading to a very small presence factor. The most exposed population group will
be people potentially present adjacent to the Magazine site fence. Such persons are not expected to be present
more than 1% of the time.
Therefore, no member of the public will be exposed to an IR of 1¡Ñ10-5
per year. The actual risk to any
individual will be much less than 1¡Ñ10-5 per year and is deemed to
be acceptable.
Figure 8.4 Maximum IR for the Delivery Routes
from Tai Lam Explosives Magazine Site (Base Case Route Option R1)
Figure 8.5 Maximum
IR for the Delivery Routes from Tai Lam Explosives Magazine Site (Base Case
Route Option R2)
Figure 8.6 Maximum
IR for the Delivery Routes from Tai Lam Explosives Magazine Site (Base Case
Route Option R3)
Figure
8.7 IR of
the Tai Lam Explosives Magazine Site
Indoor Outdoor
The societal risk results for
explosives storage and transport have been combined to produce the overall
societal risk results for the Base Case and the Worst Case (Figure 8.8,
Figure 8.9
and Figure 8.10
). These include the Magazine site at Tai
Lam and the associated transport routes to the three worksites.
The Base Case represents the risks
associated with the envisaged blasting programme. It can be seen that the risks lie in the
upper ALARP region.
The Worst Case represents the maximum
risks associated with the worst blasting scenario, i.e. a 20% increase in the
number of deliveries compared to the Base Case scenario. The risks, as expected, are higher than
the base case but still within the ALARP region.
Figure 8.11,
Figure 8.12
and Figure 8.13 show the F-N curves for
the Base Case with a breakdown by storage and transport. It is observed that risks from the
Magazine are negligible compared to the transport risks since the Magazine is
located in remote area with very low population density nearby.
The
F-N curves for both Base Case and Worst Case are within the As Low as
Reasonably Practicable (ALARP) Region as per HK EIAO-TM. Therefore,
mitigation measures need to be considered to reduce the risk. The ALARP
assessment is provided in Annex 8A,
Section 9.
The
potential Loss of Life (PLL) for the base case and the worst case are given in Table
8.4, Table
8.5,
Table
8.6 and Table
8.7,
Table
8.8,
Table
8.9 respectively. The PLL for Base Case has been evaluated
at 6.75´10‑4/year, 1.30´10‑3/year, 7.83´10‑4/year for Route
Option R1, Route Option R2 and Route Option R3 respectively. The PLL value for the Worst Case is
estimated at 8.10´10‑4/year, 1.56´10‑3/year, 9.40´10‑4/year
for Route Option R1, Route Option R2 and Route Option R3 respectively.
Figure
8.8 F-N
Curve for Storage and Transport of Explosives (Route Option R1)
Figure
8.9 F-N
Curve for Storage and Transport of Explosives (Route Option R2)
Figure
8.10 F-N Curve for
Storage and Transport of Explosives (Route Option R3)
Figure
8.11 F-N Curve for the
Base Case with Breakdown by Storage and Transport (Route Option R1)
Figure
8.12 F-N Curve for the Base Case with
Breakdown by Storage and Transport (Route Option R2)
Figure 8.13 F-N Curve for the Base Case with
Breakdown by Storage and Transport (Route Option R3)
Table
8.4 PLL
for Base Case Route Option R1
Case: Base Case |
PLL
|
Contribution
(%) |
Storage of Explosives |
|
|
Tai Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport of Explosives |
|
|
Tai Lam Explosives Magazine Site to Mid-Ventilation Adit |
1.68E-04 |
24.90% |
Tai Lam Explosives Magazine Site to North Portal |
2.13E-04 |
31.55% |
Tai Lam Explosives Magazine Site to South Portal |
2.94E-04 |
43.55% |
Total |
6.75E-04 |
100.00% |
Table 8.5 PLL
for Base Case Route Option R2
Case:
Base Case |
PLL |
Contribution (%) |
Storage
of Explosives |
|
|
Tai
Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport
of Explosives |
|
|
Tai
Lam Explosives Magazine Site to Mid-Ventilation Adit |
2.83E-04 |
21.83% |
Tai
Lam Explosives Magazine Site to North Portal |
3.58E-04 |
27.61% |
Tai
Lam Explosives Magazine Site to South Portal |
6.56E-04 |
50.55% |
Total |
1.30E-03 |
100.00% |
Table 8.6 PLL
for Base Case Route Option R3
Case:
Base Case |
PLL |
Contribution (%) |
Storage
of Explosives |
|
|
Tai
Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport
of Explosives |
|
|
Tai
Lam Explosives Magazine Site to Mid-Ventilation Adit |
1.73E-04 |
22.04% |
Tai
Lam Explosives Magazine Site to North Portal |
2.18E-04 |
27.84% |
Tai
Lam Explosives Magazine Site to South Portal |
3.93E-04 |
50.12% |
Total |
7.83E-04 |
100.00% |
Table 8.7 PLL
for Worst Case Route
Option R1
Case: Worst Case |
PLL
|
Contribution
(%) |
Storage of Explosives |
|
|
Tai Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport of Explosives |
|
|
Tai Lam Explosives Magazine Site to Mid-Ventilation Adit |
2.02E-04 |
24.90% |
Tai Lam Explosives Magazine Site to North Portal |
2.56E-04 |
31.55% |
Tai Lam Explosives Magazine Site to South Portal |
3.53E-04 |
43.55% |
Total |
8.10E-04 |
100.00% |
Table
8.8 PLL for Worst Case
Route Option R2
Case: Worst Case |
PLL
|
Contribution
(%) |
Storage of Explosives |
|
|
Tai Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport of Explosives |
|
|
Tai Lam Explosives Magazine Site to Mid-Ventilation Adit |
3.40E-04 |
21.83% |
Tai Lam Explosives Magazine Site to North Portal |
4.30E-04 |
27.61% |
Tai Lam Explosives Magazine Site to South Portal |
7.87E-04 |
50.55% |
Total |
1.56E-03 |
100.00% |
Table 8.9 PLL for Worst
Case Route Option R3
Case: Worst Case |
PLL
|
Contribution
(%) |
Storage of Explosives |
|
|
Tai Lam Explosives Magazine Site |
9.03E-09 |
0.001% |
Transport of Explosives |
|
|
Tai Lam Explosives Magazine Site to Mid-Ventilation Adit |
2.07E-04 |
22.04% |
Tai Lam Explosives Magazine Site to North Portal |
2.62E-04 |
27.84% |
Tai Lam Explosives Magazine Site to South Portal |
4.71E-04 |
50.12% |
Total |
9.40E-04 |
100.00% |
Since the risks posed by the project,
for both Base and Worst Cases considered, are within the ALARP region specified
in EIAO-TM Annex 4, this implies that risk reduction measures and/ or
alternate options should be explored for the Project.
It was found that the risks arising
from explosives transport are much more significant than that of explosives
storage; hence the ALARP assessment focuses on the transportation aspects of
explosives.
Where the risk falls into the ALARP
region, the risks associated with each probable hazardous event should be
reduced to a level ¡¥as low as reasonably practicable¡¦. This firstly requires the identification
of any ¡¥practicable¡¦ options regardless of their cost. A mitigation option is considered
¡¥practicable¡¦ if an engineering solution exists and can be implemented on the
Project regardless of the cost without affecting the project construction
programme. Secondly, the extent to
which the risk should be reduced is usually measured as a trade-off between the
risk reduction, i.e. the safety benefits and the cost of the risk reduction
measure. A mitigation option is
considered ¡¥reasonable¡¦ if the cost of implementing the option is not grossly
disproportionate to the achieved safety benefits.
Risk mitigation measures may take the
form of engineered measures, controls in the zones most impacted by the
hazardous scenarios presented by this project, or operation and procedural
controls.
The approach consists of identifying
potential justifiable mitigation measures, assessing their practicability for
this project and evaluating their cost and comparing with the safety benefits
of implementing the measures. Combinations of mitigation measures are also
considered.
The safety benefits are evaluated as
follows:
Safety Benefits = Value of Preventing
a Fatality x Aversion Factor ¡Ñ Reduction in PLL value ¡Ñ Design Life of Mitigation
Measure
The Value of Preventing a Fatality (VPF)
reflects the tolerability of risk by the society and therefore the monetary
value that the society is ready to invest to prevent a fatality. For the purpose of this assessment and
for consistency with previous studies, the Value of Preventing a Fatality is
taken as HK$33M per person, which is the same figure as used in previous XRL
EIA QRA study.
Depending on the level of risk, the
value of preventing a fatality may be adjusted to reflect people¡¦s aversion to
high risks or scenarios with potential for multiple fatalities. The methodology for application of the
¡¥aversion factor¡¦ follows that developed by EPD (ref.25), in which the aversion
factor is calculated on a sliding scale from 1 (risks at the lower boundary of
the ALARP region of the Risk Guidelines) up to a maximum of 20 (risks at the
upper boundary of the ALARP region).
The adjusted VPF using the aversion factor of 20 is HK$660M. This value is a measure of how much the
society is willing to invest to prevent a fatality, where there is potential
for an event to cause multiple fatalities.
The maximum justifiable expenditure
for this Project is calculated as HK$ 2.1M assuming the design life of
mitigation measure is 2 years (Jan 2015 to Dec 2017, 24 months) based on the
Project during which storage and transport of explosives will be involved, with
the maximum PLL of 1.56 x 10-3 per year, which is obtained from the
Worst Case.
For an ¡¥achievable¡¦ mitigation measure
to be potentially justifiable, its cost should be less than the Maximum
Justifiable Expenditure.
The potential options that have been
examined in the ALARP assessment include the following categories.
¡P
Options
eliminating the need for a Magazine or eliminating the risk (eg. Use of alternative methods of construction (¡¥hard rock¡¦
TBMs));
¡P
Options
reducing significantly the quantities of explosives to be used such as use of
¡¥hard rock¡¦ TBM or alternatives to cartridged
emulsion;
¡P
Options
significantly reducing the distance run by contractors¡¦ explosive trucks such
as closer magazine site and alternative routes. The magazine and route options
considered are summarised below:
- The
alternative magazine sites to Tai Lam have been considered by DHK but they are
not available for the Project. The
existing TLEM is
the best option considering the shortest transportation distance, stakeholders¡¦
acceptance situation and its availability with the blasting schedule of the
project.
-
On-site magazines were also considered (at the Mid Ventilation Portal
and North Portal). DHK had
preliminary consultation with CEDD Mines Division. After review with the
necessary site setups and subsequent application process, Mines Divisions
advised that it would not be feasible in managing interfaces with adjacent
construction activities, safety of the site could be compromised and match with
the program of project.
- Based
on the review of the possible transport routes for this project and discussion
with Yuen Long
District Council, due to limitation imposed by the current road improvement work at Pok
Oi Interchange, (1) At early stage of this
project with road improvement work at Pok Oi
Interchange (expected to be completed in 2015 but may be delayed), Route Option
R2 will be used. Route Options R1
and R3 are not feasible during this period since they both route via Pok Oi interchange.
(2) After road improvement work at Pok Oi
Interchange is completed, all three routes will be available for use, thus
further cost-benefit evaluation is conducted. The Route Option with minimum transport
risk, i.e. Route Option R1, will be used.
Route Option R3 can only be used as a contingency alternative route in
the event that Route Option R1 is infeasible due to road blockage by traffic
accidents.
¡P
Options
reducing significantly the number of trips to be carried out by contractors¡¦
explosive trucks;
¡P
Options
considering improved explosive truck design; and
¡P
Options
considering better risk management systems and procedures.
In
summary, various options have been either recommended for implementation or
assessed comparing the implementation cost with the maximum justifiable
expenditure for the safety benefit gained.
The
PLL for Route Option R1, Route Option R2 and Route Option R3 are presented in Table 8.10.
These were used as the basis for the cost-benefit analysis/ ALARP
assessment presented in Table 8.11.
Various
options considered practicable have been either recommended for implementation
or assessed comparing the implementation cost with the maximum justifiable
expenditure. The evaluation for each
option is shown in Table 8.11. More details are available in Annex 8A, Section 9.
By adopting the feasible explosives delivery routes
with the lowest risk, the risk has been reduced as low as practicable
considering the impact of road improvement work at Pok
Oi Interchange. The risk will be further reduced by implementation of the other selected
mitigation measures.
Table
8.10 Potential Loss of Life for
all three Route Options
Case |
PLL
(Per Year) |
Route Option R1 (Worst Case) |
8.10 x 10-4 |
Route Option R2 (Worst Case) |
1.56 x 10-3 |
Route
Option R3 (Worst Case) |
9.40 x 10-4 |
|
|
Table 8.11 ALARP Assessment Results
Option
Description |
Practicability |
Implementation
Cost |
Safety
Benefits or Justifiable Expenditure |
ALARP
Assessment Result |
Use of alternative methods of construction
(TBMs) |
Not Practicable |
> HK$ 100M |
HK$ 2.1M |
Neither practicable nor justified. |
Use of Magazine Closer to the Worksites |
Not Practicable |
- |
- |
Closest
practicable Magazine site to the worksites has been selected |
Use of different explosive types (different
types of detonating cord) |
Pose some limitations |
HK$ 2.4M |
No safety benefit |
Not justified |
Alternative
Routes (at early stage of this project with road improvement
work at Pok Oi Interchange) |
Not Practicable |
- |
- |
Neither practicable nor justified. |
Alternative Routes (after road improvement work at Pok Oi Interchange is completed) |
Practicable |
< HK$ 10k |
Negative |
Route Option R1
is the preferred option. Route Option R3 can only be used as a contingency
alternative route. |
Use of Smaller Explosives Quantities |
Not Practicable |
- |
- |
Neither practicable nor justified. |
Safer explosive truck (reduced fire load) |
Practicable |
- |
- |
This option has been directly incorporated
in recommendations |
Reduction of Accident Involvement Frequency
(training programme etc.) |
Practicable |
- |
- |
This option has been directly incorporated
in recommendations |
Reduction
of Fire Involvement Frequency (better emergency response, extinguisher types
etc.) |
Practicable |
- |
- |
This
option has been directly incorporated in recommendations |
A
QRA has been carried out to assess the hazard to life issues arising from the
storage and transport of explosives from Tai Lam Explosives Magazine site to
the three blasting worksites.
The
criterion of Annex 4 of the EIAO-TM for Individual Risk is met. The assessment results show that the
societal risk lies within the ALARP region when compared to the criteria
stipulated in the EIAO-TM. A detailed ALARP assessment has been
undertaken considering a wide range of mitigation measures and the results show
compliance with the ALARP principles provided that the following
recommendations are followed.
Following
the ALARP principles, the following recommendations are justified and should be
implemented to meet the EIAO-TM
requirements.
¡P
The
truck design should comply with the Requirements for Approval of an Explosives
Delivery Vehicle (CEDD 2) and limit the amount of combustibles in the
cabin. The fuel carried in the fuel
tank should also be minimised to reduce the duration of any fire;
¡P
The
explosive truck accident frequency should be minimized by implementing a
dedicated training programme for both the driver and his attendants, including
regular briefing sessions, implementation of a defensive driving attitude. In addition, drivers should be selected
based on good safety record, and medical checks;
¡P
The
contractor should as far as practicable combine the explosive deliveries for a
given work area;
¡P
Only
the required quantity of explosives for a particular blast should be
transported to avoid the return of unused explosives to the Magazine.
¡P
Whenever
practicable, a minimum headway between two consecutive truck convoys of 10 min
is recommended;
¡P
The
explosive truck fire involvement frequency should be minimized by implementing
a better emergency response and training to make sure the adequate fire
extinguishers are used and attempt is made to evacuate the area of the incident
or securing the explosive load if possible. All explosive vehicles should be
equipped with the required amount and type of fire extinguishers and shall be
agreed with Mines Division; and
The
following general recommendation should also be considered for the storage and
transport of explosives:
¡P
The
security plan should address different alert security level to reduce
opportunity for arson/ deliberate initiation of explosives. The corresponding security procedure
should be implemented with respect to prevailing security alert status announced
by the Government.
¡P
Emergency
plans (i.e. magazine operational manual) shall be followed and amended if
necessary to address uncontrolled fire in magazine area and transport. The case of fire near an explosive
carrying truck in jammed traffic should also be covered. Drill of the emergency plan should be
carried out at regular intervals.
¡P
Adverse
weather working guideline should be followed and amended if necessary to
clearly define procedures for transport explosives during thunderstorm.
¡P
The
Magazine storage quantities need to be reported on a monthly basis to ensure
that the two day storage capacity is not exceeded.
Specific
recommendations for storage and transport of explosives are given below.
The
Magazine should be operated and maintained in accordance with Mines Division
guidelines and appropriate industry best practice. In addition, the following
recommendations should be implemented:
¡P
A
suitable work control system should be followed and amended if necessary, such
as an operational manual including Permit-to-Work system, to ensure that work
activities undertaken during the operation of the Magazine are properly
controlled.
¡P
There
should be good house-keeping within the Magazine to ensure that combustible
materials are not allowed to accumulate.
¡P
The
Magazine shall be without open drains, traps, pits or pockets into which any
molten ammonium nitrate could flow and be confined in the event of a fire.
¡P
The
Magazine building shall be regularly checked for water seepage through the
roof, walls or floor.
¡P
Caked
explosives shall be disposed of in an appropriate manner.
¡P
Delivery
vehicles shall not be permitted to remain within the secured fenced off
magazine store area.
¡P
Good
housekeeping outside the Magazine stores to be followed to ensure combustibles
(including vegetation) are removed.
¡P
A
speed limit within the magazine area should be enforced to reduce the risk of a
vehicle impact or incident within the Magazine area.
¡P
Traffic
Management should be implemented within the Magazine site, to ensure that no
more than 1 vehicle will be loading/loaded at any time, in order to avoid
accidents involving multiple vehicles within the site boundary.
General
Recommendations:
The
following measures should be considered for safe transport of explosives:
¡P
Detonators
shall not be transported in the same vehicle with other Class 1
explosives.
¡P
Separation
of vehicles should be maintained during the whole trip.
¡P
Location
for stopping and unloading from truck to be provided as close as possible to
shaft, free from dropped loads, hot work, etc. during time of unloading.
¡P
Develop
procedure to ensure that parking space on the site is available for the
explosive truck. Confirmation of
parking space should be communicated to truck drivers before delivery. If parking space on site cannot be
secure, delivery should not commence.
¡P
Ensure
lining is provided within the transportation box on the vehicle and in good
condition before transportation.
¡P
Ensure
that packaging of detonators remains intact until handed over at blasting site.
¡P
Emergency
plan to include activation of fuel and battery isolation switches on vehicle
when fire breaks out to prevent fire spreading and reducing likelihood of
prolonged fire leading to explosion.
¡P
Use
only experienced driver(s) with good safety record.
¡P
Ensure
that cartridged emulsion packages are damage free
before every trip.
¡P
Ensure
that explosives will be offloaded and stored away from the railway protection
area according to the MTRCL railway protection area plan.
Contractors
Licenced Vehicle Recommended Safety Requirements:
¡P
Battery
isolation switch;
¡P
Front
mounted exhaust with spark arrestor;
¡P
Fuel
level should be kept as far as possible to the minimum level required for the
transport of explosives;
¡P
Minimum
1 ¡Ñ 9 kg water based AFFF fire extinguisher to be provided;
¡P
Minimum
1 ¡Ñ 9 kg dry chemical powder fire extinguisher to be provided;
¡P
Horizontal
fire screen on cargo deck and vertical fire screen mounted at least 150mm
behind the drivers cab and 100mm from the steel cargo compartment, the vertical
screen shall protrude 150mm in excess of all three (3) sides of the steel cargo
compartment;
¡P
Cigarette
lighter removed;
¡P
Two
(2) battery powered torches for night deliveries;
¡P
Vehicles
shall be dedicated explosive transport vehicles and should be maintained in
good operating condition;
¡P
Daily
checks on tyres and vehicle integrity;
¡P
Regular
monthly vehicle inspections;
- Fuel system
- Exhaust system
- Brakes
- Electrics
- Battery
- Cooling system
- Engine oil leaks
¡P
Vehicle
log book in which monthly inspections and maintenance requirements are
recorded; and
¡P Mobile telephone equipped.
Recommended
Requirements for the Driver of the Explosive Vehicles:
The
driver shall:
¡P
be
registered by the Commissioner of Mines and must be over the age of 25 years
with proven accident free records and more than 7 year driving experience
without suspension.
¡P
hold
a Driving License for the class of vehicle for at least one (1) year;
¡P
adopt
a safe driving practice including having attended a defensive driving course;
¡P
pass
a medical check and is assessed as fit to drive explosives vehicles; and
¡P
not
be dependent on banned substances;
Some
of the following requirements may also apply to the vehicle attendant(s).
¡P
The
driver is required to attend relevant training courses recognized by the
Commissioner of Mines. The training
courses should include the following major subjects, but not limited to:
- the laws and Regulations relating to the transport
of explosives;
- security and safe handling during the
transport of explosives;
¡P
Attend
training courses provided by the explosives manufacturer or distributor,
covering the following:
- explosives identification;
- explosion hazards; and
- explosives sensitivity;
- the dangers which could be
caused by the types of explosives;
- the packaging, labelling and
characteristics of the types of explosives;
- the use of fire extinguishers and fire fighting procedures; and
- emergency response procedures in case of
accidents.
The
driver should additionally be responsible for the following:
¡P
The
driver shall have a full set of Material Safety Data Sheets (MSDS) for each
individual explosive aboard the vehicle for the particular journey;
¡P
The
MSDS and Removal Permit (where applicable) shall be produced to any officer of
the Mines Division of CEDD upon request;
¡P
A
card detailing emergency procedures shall be kept on board and displayed in a
prominent place on the driver¡¦s door;
¡P
Before
leaving the magazine the driver together with and/or assisted by the shotfirer shall check the following:
- Packaging integrity and labelling;
- Check that the types and quantities of explosives loaded
onto the vehicle are as stipulated in the Removal Permit(s);
- Check that the explosive load does not exceed the
quantities stated in the removal permit;
- Check the condition and integrity of the cargo
compartment or box;
- Check that detonators are not loaded in the explosives
cargo compartment and vice versa;
- Check that the cargo is secured and cannot be damaged
during the delivery;
- Ensure that the appropriate placards and a red flag are
displayed before leaving the magazine;
- Be competent to operate all equipment on board the
vehicle including fire extinguishers and the vehicle emergency cut-off
switches;
- Prohibit smoking when the vehicle is loaded with
explosives;
- When explosives are loaded, ensure the vehicle is not
left unattended;
- Be conversant with emergency response procedures.
Specific
Recommended Requirements for the Explosive Vehicle Attendants:
When
the vehicle is loaded with explosives, it shall be attended by the driver and
at least one (1) other person authorized by the Commissioner of Mines. The
vehicle attendant shall:
¡P
Be
the assistant to the driver in normal working conditions and in case of any
emergency
¡P
Be
conversant with the emergency response procedures
¡P
Be
competent to use the fire extinguishers and the vehicle emergency cut-off
switches
¡P
One
of the vehicle attendant(s) should be equipped with mobile phones and the
relevant MSDS and emergency response plan.
Type of
Explosives & their Disposal
For
explosive selection, the following should be considered
¡P
Cartridged Emulsions with perchlorate
formulation should be avoided;
¡P
Cartridged Emulsions with high water
content should be preferred.
Disposal
Recommendations:
If
disposal is required for small quantities, disposal should be made in a
controlled and safe manner by a Registered Shotfirer.
[1]
DNV,
The Risk Assessment of the Transport of Explosives in Hong Kong QRA Report,
Environmental Protection Department Hong Kong Government, 1997,
EPD CE63/94 (DNV,
1997)
[2]
Maunsell, Hazard to Life Assessment
of Explosive Storage and Handling for EIA of Ocean Park Development, 2006
(Maunsell, 2006)
[3]
ERM,
Penny¡¦s Bay Rail Link: Hazard Assessment of Explosive Magazine, 2001
(ERM, 2001)
[4]
ERM,
West Island Line: Hazard to Life Assessment for the Transport Storage and Use
of Explosives, 2008 (EIA153/2008) (ERM, 2008)
[5]
P
A Moreton, An Investigation of the Relative Risks from the Road Transport of
Blasting Explosives in Maximum Size Loads of 5te and 16te, February 1993,
SRD/HSE R596 (Moreton, 1993)
[6]
ACDS,
Risk from Handling Explosives in Ports, HSC Advisory Committee on Dangerous
Substances, HMSO, UK, 1995 (ACDS, 1995)
[7]
United
Nations, Recommendations on the Transport of Dangerous Goods ¡V Manual of Tests
and Criteria, 5th Revised Edition, 2009
(TDG-Test Manual, 2009)
[9]
HSC,
Selection and Use of Explosion Effects and Consequence Models for Explosives,
Advisory Committee on Dangerous Substances, 2000 (ESTC, 2000)
[10]
FP
Lees, Loss Prevention in Process Industries, 2nd Edition, 1996
(Lees, 1996)
[11]
US
Department of Defense,
DoD 6055.9-STD, DoD Ammunition and Explosives Safety Standards, Oct 2004 (DoD
6055.9-STD).
[12]
Health
and Safety Executive, The Peterborough Explosion ¡V A report of the investigation
by the Health and Safety Executive into the explosion of a vehicle explosives
at Fengate
Industrial Estate, Peterborough on 22 March 1989, UK, 1990 (Peterborough,
1989).
[13]
DOCEP,
Incident Log Reports retrieved from http://www.docep.wa.gov.au/resourcesSafety/Content/Dangerous_Goods/Incident_log_reports/index.htm
(DOCEP)
[14]
DOCEP,
WA Government Explosives Incident Log 2001, DGEA 01/01 (DOCEP, 2001)
[15]
Richard
J. Mainiero
and James H. Rowland III, A Review of Recent Accidents Involving Explosives
Transport, NIOSH, January 2008 (NIOSH,
2008).
[16]
R.
Merrifield, P.A. Moreton, An examination of the major-accident record for
explosives manufacturing and storage in the UK, Journal of Haz.
Mats A63 (1998) 107-118. (Merrifield, 1998)
[17]
Guidelines
for Quantitative Risk Assessment, TNO Purple Book, CPR18E 1st Ed, Committee for
the Prevention of Disasters (TNO Purple Book)
[18]
F.D.
Wayne, An economical formula for calculating the atmospheric infrared
transmissivities,
J. Loss Prev. Process Ind., 1991 Volume 4 (Wayne, 1991)
[19]
HSE,
Safety Report Assessment Guide for HFLs, http://www.hse.gov.uk/comah/sraghfl/images/hflcriteria.pdf
(HSE HFLs)
[20]
US
Bureau of Mines Bulletin 656 Blasting vibrations and their effects on
structures
(USBM 656)
[22]
Lands
Department, Geographic Information System (GIS) database, http://www.landsd.gov.hk/mapping/en/digital_map/mapprod.htm
The latest information on the GIS map of buildings from the Lands Department
used in this study comes from 2014 (LD, 2014)
[23]
Roger
R Holmberg & B Folkesson , Bulk Emulsion
Explosive ¡V A Case Study, Bulamac Patlayicilar
¡V Bir Uygulama, 615-629,
retrieved from http://www.maden.org.tr/resimler/ekler/1f5738a827405b0_ek.pdf
(Holmberg)
[24]
P
A Moreton, Controlling risks around explosives stores: Review of the
requirements on the separation distances, UK HSE 2002 (Moreton, 2002)
[25]
EPD,
Technical Note: Cost Benefit Analysis in Hazard Assessment, Environmental
Protection Department, Rev. January 1996. (EPD,
1996)
[26]
Transport
Department, Annual Traffic Census 2013 (ATC, 2013).
[27]
Byrne,
J. P., The calculation of aircraft crash risk in the UK, Health and Safety
Executive, HSE\R150, 1997. (Byrne, 1997)
[28]
Annual
review of aircraft accident data: US General Aviation, Calendar year 2001,
National Transport Safety Board. (NTSB, 2001)
[31]
International
Society of Explosives Engineers, Proceedings of the 22nd Annual
Conference on Explosives and Blasting Techniques, 4-8 Feb 1996, (ISEE, 1996)
[35]
CEDD,
How to Apply for a Mode A Store Licence for Storage of Blasting Explosives,
http://www.cedd.gov.hk/eng/services/mines_quarries/doc/gn_mode_a_store.pdf
(CEDD 3)
[38]
Expert
Review Panel Minutes, 2-3 February 2009 (ERP, 2009)
[39]
ERM,
Express Rail Link: Hazard to Life Assessment for the Transport and Storage of
Explosives, 2009 (ESB-197/2008) (ERM, 2009)
[40]
UK
Health & Safety Executive, The Explosives Regulations 2014, Statutory
Instrument 2014 No. 1638. (ER, 2014)
[41]
National
Transportation Safety Board, Safety Recommendation, Washington D.C. 20594,
1998, retrieved from http://www.ntsb.gov/Recs/letters/1998/A98_81_82.pdf (NTSB,
1998)
[42]
LegCo, Minutes of LegCo
Panel on Environmental Affairs ¡V Aircraft Noise, LC Paper No. CB(1)163/98-99,
Legislative Council, Hong Kong, Aug 1998, retrieved from
http://www.legco.gov.hk/yr98-99/english/panels/ea/minutes/ea180898.htm (LegCo, 1998a)
[43]
LegCo, LegCo
Panel on Environmental Affairs ¡V Aircraft Noise, LC Paper No.
CB(1)78/98-99(04), Legislative Council, Hong Kong, 1998, retrieved from
and
http://www.legco.gov.hk/yr98-99/english/panels/ea/papers/78_111.pdf (LegCo, 1998b)
[44]
South
Island Line (East): Hazard to Life Assessment for the Transport and Storage of
Explosives, 2010 (ERM, 2010a)
[45]
Kwun Tong Line Extension: Hazard to Life
Assessment for the Transport and Storage of Explosives, 2010 (ERM, 2010b)
[46]
ERM,
Shatin to Central Link: Hazard to Life Assessment for
the Transport and Storage of Explosives, 2011 (EIA-200/2011) (ERM, 2011)
This chapter summarises any
environmental monitoring and audit requirements that have arisen from the EIA
study.
No adverse impacts are
expected prior to mitigation for airborne noise, air quality and water quality,
and therefore there are no monitoring or audit requirements for these
environmental media.
For waste management, comprehensive planning
and good site management practice will be adopted by the contractors of the
Project during operation and decommissioning and waste on-site will be properly
segregated to increase the potential for reuse and recycling. Chemical waste generated from equipment
operation and decommissioning will be properly stored in accordance with Code of Practice on the Packaging, Labelling
and Storage of Chemical Waste published by the EPD before collection for
disposal by a licensed Chemical Waste Collector. The quantity of general refuse generated
on-site will be minimal owing to the nature of the operation and decommissioning
activities and provided general refuse is removed from the Project Site
regularly (e.g. once per day), no adverse environmental impact related to
handling and disposal of general refuse is expected.
Adverse
water quality impact is not expected during decommissioning, considering the small scale and short duration
of works activities and the implementation of proper site runoff control measures. Water quality impact on other fresh
water courses from the works is
also unlikely and any discharge from the site expected to be in compliance with
the requirements of the Water Pollution Control Ordinance. However as good practice, appropriate
measures will be implemented in accordance with the guidelines stipulated in
EPD¡¦s Practice Note for Professional
Persons on Construction Site Drainage (ProPECC
PN1/94) during the decommissioning works to properly control site run-off
and drainage and to minimise potential water quality impacts. Equally for good practice, general noise control measures, as listed in Recommended Clauses for Construction Contracts
¡V Section 3 - Noise Control will be adopted.
The Hazard To Life
assessment has recommended various measure during operation to ensure that
societal risks remain as low as is reasonably practicable (ALARP) according to
the Hong Kong Government Risk Guidelines
(HKRG), EIAO-TM Annex 4. These
include measures to be implemented around the TLEM site such as regularly
checking for water seepage through the roof, walls or floor of the magazine
building, as well as measures for the transport route such as regular monthly
vehicle inspections for fuel system, exhaust system, brakes, electrics,
battery, cooling system and engine oil leaks.
To ensure these general
measures for waste management and hazard to life are complied with throughout
operation as well as decommissioning, it is recommended that regular general
inspection by carried out by the Environmental Team and competent site staff, and
be verified by an Independent Environmental Checker.
For ecology (and also
relevant to landscape), re-instatement planting, following the approved XRL
EIA Vegetation Survey Report for Tai Shu Ha Road West and TLP
(which stated the responsibility, procedures and requirements for the
reinstatement planting and the subsequent maintenance, etc.), has
been recommended as a mitigation measure once the Project is complete and TLEM
removed.
Annex
9A provides
the Implementation Schedule of Recommended Mitigation Measures and further
details will be provided in the EM&A Manual.
This section provides a conclusion to
the EIA report and a summary of the environmental outcomes of the EIA, with Table
10.1 summarizing
any predicted environmental impacts due to the Project and the associated
recommended mitigation measures.
The existing TLEM in Tai Shu Ha, Yuen
Long District, New Territories has been licensed and is currently in use by the
MTRC for the construction of the XRL until end of 2014 (Environmental Permit
No. EP-349/2009/L). It is being
used by the MTR XRL 824 Contractor.
The TLEM will be available for use from late 2015 or early 2016
(expected January 2016) to December 2017 and DHK intends to continue using it
for the Liantang/Heung Yuen Wai
Boundary Control Point (BCP) project (hereafter ¡¥HKLTH¡¦) tunnel construction
works.
This section
provides a summary of key environmental outcomes, including the recommended
environmental protection measures, for this EIA study which has been carried
out according to EIA Brief ESB-280/2014 to
examine the continued operation and decommissioning of the existing TLEM for
the HKLTH tunnel construction works (the Project).
The EIA Report largely follows the
approved XRL EIA which assessed the impacts from the construction and operation
of the TLEM, reviewing the relevant information and updating it as
necessary. The approved XRL EIA had
a far broader scope than just assessing the environmental impacts of the TLEM
and after review of the full XRL EIA the environmental media relevant to the
TLEM are Ecology, Airborne Noise, Air Quality and Waste Management with other
media of minor importance, including Water Quality and Landscape and
Visual. A new hazard to life
assessment has also been undertaken for this EIA Report.
This section also summarizes the environmental benefits of the Project, any
population and environmentally sensitive areas that have been protected and the
key environmental problems avoided.
Since there is no construction phase
for the Project, given the TLEM has been built and its operation will remain largely the same as its use for
the current XRL project, no environmentally friendly designs have been recommended
for this Project.
No key activities are known to take
place concurrently and therefore it is assumed there will be no cumulative
impacts from the Project.
Environmental benefits of the Project
are summarised below
and any environmental monitoring and audit requirements considered necessary
during the operation and decommissioning of the Project are summarized in Chapter 10.
The selection
of the TLEM site for the current Project offers a number of environmental
benefits, namely that: it is already constructed so there are no construction
impacts or land conversion issues; and it is being used for exactly the
required purpose now under EP-349/2009/L which would imply any operational and
decommissioning
impacts associated with the current Project will be acceptable. In addition, since there is no requirement
to build a new magazine site, the timeline for the tunnel Project may be
expedited as well as there being no requirement to build a new magazine site
which may cause more significant environmental impacts elsewhere.
During operation and decommissioning
of the Project, with respect to all environmental media (including for ecology, airbourne
noise, air quality, waste, water quality and landscape and visual), adverse
impacts are minimal. Only measures
to ensure proper waste management, general noise control measures (e.g as listed in Recommended
Clauses for Construction Contracts ¡V Section 3 - Noise Control) and good
site practice (e.g. in accordance with the
guidelines stipulated in EPD¡¦s Practice
Note for Professional Persons on Construction Site Drainage [ProPECC PN1/94]) are recommended, as well as measures to ensure societal risks remain low. No specific environmental benefits of
the Project are envisaged at this stage but similarly no adverse residual environmental impacts are
expected.
Reinstatement
planting following the approved XRL EIA
Vegetation Survey Report for Tai Shu Ha Road West and TLP will be carried out at the TLEM site as soon as possible after
decommissioning of the Project.
This is a key mitigation measure that will benefit ecology
(and landscape) and will now be carried out by DHK.
The storage and transport of
explosives for the Project have been assessed in a Quantitative Risk
Assessment. Practical
route options were assessed in the study. The impact of road improvement work
at Pok Oi Interchange was
considered in route selection. The practical route option with minimum
transport risk will be used.
The criterion of the EIAO-TM for
Individual Risk is met. The assessment results show that the societal risk lies
within the As Low As Reasonably Practicable (ALARP) region when compared to the
criteria stipulated in Annex 4 of the EIAO-TM. An ALARP assessment has been
carried out by identifying all practicable mitigation measures and assessing
the cost effectiveness of each measure in terms of the risk reduction achieved
and the cost of implementing the measures.
The results show compliance with the ALARP principles and Risk
Guidelines (EIAO-TM Annex 4) provided recommendations are implemented.
This project
has the potential to influence populations including on-site workers and
drivers of the explosives vehicles, as well as populations along the proposed
explosive transport routes.
With the implementation of relevant mitigation measures, as outlined in Chapter 8 Hazard to Life and summarized
in Chapter 10, these people would be
protected from any potential hazards and not be significantly affected by the
Project.
The TLEM has
already been built and is currently in use for the XRL project. The site falls
in Conservation Area (CA) of the statutory Tai Tong Outline Zoning Plan
(S/YL-TT/16) and is also near (approximately 300 m from) the Tai Lam
Country Park. This CA is zoned to
protect and retain the existing natural landscape, ecological or topographical
features of the area for conservation, educational and research purposes and
also acts as a buffer between the more sensitive natural environment of Tai Lam
Country Park and the potentially adverse effects of development. The Project¡¦s operation will remain
largely the same as its use for the current XRL project where no particular
measure are considered necessary to protect the CA or nearby country park due
to lack of impacts to these from the Project.
The following
key environmental problems have been avoided:
¡P
Loss of
reinstatement
planting at TLEM site that was to be carried out by MTRC at the end of their
project (i.e. originally at the end of 2014 but now extended to 2015) in the
approved XRL EIA report. DHK will
now take on the responsibility of this reinstatement; and
¡P
Hazard to life impacts to
populations near the TLEM site and along the explosives transport routes, from
the storage and transport of potentially harmful explosives to the works
areas. A number of mitigation
measures as set out in Chapter 8 and
summarised in Chapter 10 minimise the
risks from these potential impacts.
Since the
Project has already been constructed and its operation will remain largely the same as its current
use for the XRL project, no new compensation areas are required. The TLEM site itself, however, forms
part of the compensation planting area for the XRL Project where re-instatement
planting would be carried out. With
the operation of the Project, reinstatement planting would be postponed and
measures have been put in place to ensure the reinstatement planting plan is
implemented as soon as possible upon completion and
decommissioning of the Project (predicted in 2017).
Overall, this
EIA study predicts that the Project, with the implementation of the mitigation
measures, would be environmentally acceptable with no adverse residual impacts
on the population and environmentally sensitive resources, as assessed in
accordance with relevant criteria stipulated in the EIAO (TM).
Table 10.1 Summary of Environmental
Impacts
Assessment Points |
Results of Impact Prediction |
Relevant Standard/ Criteria |
Extent of Exceedances Predicted |
Recommended Mitigation including Avoidance |
Residual Impacts (after mitigation) |
Ecological Impact
(Operation & Completion of Project) |
|
|
|
||
Ecological Sensitive Receivers within 500 m of
the Project Site boundary |
To restore the habitat back to borrow area reinstatement
plantation, as it was prior to the construction of the TLEM for the MTRC¡¦s
use. To ensure the proposed mitigation recommended in the approved
XRL EIA for loss of green areas affected by the XRL Project, is implemented. |
¡P
EIAO-TM; Annexes 8 &
16 ¡P
DEVB TCW No. 10/2013 ¡V
Tree Preservation (supersedes ETWB TC(W) No. 3/2006 ) ¡P
XRL EIA Vegetation Survey
Report for Tai Shu Ha Road West ¡P
Tree Planting and
Landscape Plan TLP-10: Works in Yuen Long District (Tai Shu Ha) |
|
Reinstatement
planting To be carried out at the site following the approved
XRL EIA Vegetation Survey Report for
Tai Shu Ha Road West, and TLP. |
No adverse residual
impacts are predicted |
Air Quality Impact
(Operation & Decommissioning) |
|
|
|
||
Air Sensitive Receivers within 500 m of the
Project Site boundary |
No adverse
impacts are predicted |
¡P
EIAO-TM Annex 4 & 12 ¡P
Air Pollution Control Ordinance
(APCO) (Cap 311) ¡P
Air Pollution Control (Construction Dust) Regulation |
No exceedances anticipated. |
n/a |
No adverse
residual impacts are predicted |
Noise Impact (Operation
& Decommissioning) |
|
|
|
||
Noise Sensitive Receivers within 300 m of the
Project Site boundary |
No adverse
impacts are predicted |
¡P
EIAO-TM; Annexes 5 & 13 ¡P
Noise Control Ordinance
(NCO) ¡P
Technical Memorandum on Noise
From Places Other than Domestic Premises, Public Places or Construction Sites
(IND-TM) ¡P
Technical Memorandum on
Noise from Percussive Piling (PP-TM); ¡P
Technical Memorandum on
Noise from Construction Work other than Percussive Piling (GW-TM); and ¡P
Technical Memorandum on
Noise from Construction Work in Designated Areas (DA-TM). ¡P
Recommended Clauses for Construction
Contracts ¡V Section 3 - Noise Control |
No exceedances anticipated. |
For good
practice, adopt general noise control measures, as listed in Recommended Clauses
for Construction Contracts ¡V Section 3 - Noise Control |
No adverse
residual impacts are predicted |
Waste Management (Operation Waste &
Decommissioning) |
|
|
|
||
Project Site |
No adverse
impacts are predicted |
¡P
EIAO-TM Annexes 7 &
15 ¡P
Waste Disposal Ordinance
(WDO) (Cap 354); ¡P
Waste Disposal (Charges
for Disposal of Construction Waste) Regulation (Cap 354N) ¡P
Waste Disposal (Chemical
Waste) (General) Regulation (Cap 354C); ¡P
Land (Miscellaneous
Provisions) Ordinance (Cap 28) ¡P
Public Health and
Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of
Nuisances Regulation. ¡P
Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes (1992), EPD, Hong Kong
Government |
No exceedances anticipated. |
For good measure,
during regular site inspections, ensure refuse is appropriately treated and
that general refuse is removed from the Project Site regularly (e.g. once per
day). For
decommissioning, during regular site inspections, ensure all waste is
properly segregated and different waste (e.g. general waste, chemical waste
and C&D materials (both inert and non-inert materials) are handled and
disposed of appropriately. |
No adverse
residual impacts are predicted |
Other (Operation &
Decommissioning) |
|
|
|
||
Water sensitive Receivers
within 500 m of the Project Site |
No adverse
impacts are predicted during operation. During
decommissioning, appropriate measures should be implemented to properly
control site run-off and drainage and minimise potential water quality
impacts. |
¡P
EIAO-TM Annexes 6 &
14 ¡P
Water Pollution Control
Ordinance (WPCO) ¡P
Technical Memorandum for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters (TM- ICW) ¡P
Practice Note for Professional Persons on Construction Site Drainage (ProPECC PN1/94) |
No exceedances anticipated. |
n/a during
operation. For good
measure, during decommissioning, regular site inspections ensure appropriate
measures are being implemented in accordance with stipulated guidelines. Exposed soil should be covered with geotextile before the
re-vegetation / plantation to minimize soil erosion. |
No adverse
residual impacts are predicted |
Landscape resources,
landscape character areas and Visual Sensitive Receivers within 500 m of
the Project Site |
No adverse
impacts are predicted |
¡P
EIAO-TM Annexes 10 &
18 ¡P
DEVB TCW No. 10/2013 ¡V
Tree Preservation (supersedes ETWB TC(W) No. 3/2006 ) |
No exceedances anticipated. |
n/a |
No adverse
residual impacts are predicted |
Hazard
to Life (Operation- Storage) |
|
|
|
||
Risk due to storage of explosives in the Tai Lam
Explosives Magazine. |
The Individual Risk level is below 1 ¡Ñ 10-5
per year considering low presence factor; and Societal Risk level is in the acceptable region. |
Annex 4 of EIAO-TM |
N/A |
Mitigation
measures are not necessary due to the fact that the societal risk level is in
the acceptable region. Although mitigation
measures are not required due to the fact that the societal risk level is in
the acceptable region, general measures are recommended in keeping with best
practice as presented in Section 9 of Annex 8A and
summarised in the Project Implementation Schedule in Annex 9A. |
Adverse
residue impact is not predicted. |
Hazard to Life (Operation - Transport)
|
|
|
|
||
Risk due to transport of explosives from the Tai Lam
Explosives Magazine to worksites. |
The Individual Risk level is below 1 ¡Ñ 10-5
per year; and Societal Risk level is in ALARP region. |
Annex 4 of EIAO-TM |
N/A |
Individual risk
levels are below the recommended level and societal risk level is in the
ALARP region. The
following measures are proposed after cost benefit analysis: ¡P
Follow
the proposed Routes recommended in Chapter 8 of the EIA Report (both before
and after completion of road improvement work at Pok
Oi Interchange) ¡P
Implement
improvement measures for safer explosive trucks (e.g. reduced fire load) ¡P
Reduce
Accident Involvement Frequency (e.g. training programme etc.) ¡P
Reduce
Fire Involvement Frequency (e.g. ensure appropriate emergency response
system, extinguisher types, etc.) Details of
above measures are presented in Section 9 of Annex 8A and
general measures are also recommended for general best practice in the Project
Implementation Schedule in Annex 9A. |
The Individual Risk level is below 1 ¡Ñ 10-5
per year; and Societal Risk level is in ALARP region |