Table 10.1 Implementation
Schedule of Mitigation Measures
EIA Ref. |
Environmental Protection Measures |
Location of the Measures |
Implementation Agent |
Implementation Stage |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Air Quality (Construction Phase) |
|||||||||
4.6.1 |
Watering once per hour on active construction work areas,
and the watering application intensity is estimated to be 0.152 L/m2
(tentatively) so as to achieve a dust removal efficiency of 87.5%. |
Active works area |
CEDD/Contractor |
|
ü |
|
|
EIAO-TM, AQOs |
|
4.7.1 –
4.7.2 |
To ensure compliance with the guideline level and AQO at the
ASRs, the Air Pollution Control (Construction Dust) Regulation should be
implemented and good site practices should be incorporated in the contract
clauses to minimize construction dust impact. A number of below dust
suppression measures are proposed to be implemented. Any excavated or stockpile of dusty material
should be covered entirely by impervious sheeting or sprayed with water to
maintain the entire surface wet and then removed or backfilled or reinstated
where practicable within 24 hours of the excavation or unloading;
Any dusty material remaining after a
stockpile is removed should be wetted with water and cleared from the surface
of roads;
A stockpile of dusty material should not
extend beyond the pedestrian barriers, fencing or traffic cones;
The load of dusty materials on a vehicles
leaving a construction site should be covered entirely by impervious sheeting
to ensure that the dusty materials do not leak form the vehicle;
Where practicable, vehicles washing
facilities including a high pressure water jet should be provided at every
discernible or designated vehicle exit point. The area where vehicle washing
takes place and the road section between the washing facilities and the exit
point should be paved with concrete, bituminous materials or hardcores;
When there are open excavation and reinstatement
works, hoarding of not less than 2.4m high should be provided as far as
practicable along the site boundary with provision for public crossing. Good
site practice shall also be adopted by the Contractor to ensure the
conditions of the hoardings are properly maintained throughout the
construction period;
The portion of any road leading only to
construction site that is within 30m of a vehicle entrance or exit should be
kept clear of dusty materials;
Surfaces where any pneumatic or
power-driven drilling, cutting, polishing or other mechanical breaking
operation takes place should be sprayed with water or a dust suppression
chemical continuously;
Any area that involves demolition
activities should be sprayed with water or a dust suppression chemical immediately
prior to, during and immediately after the activities so as to maintain the
entire surface wet;
Where a scaffolding is erected around the
perimeter of a building under construction, effective dust screens, sheeting
or netting should be provided to enclose the scaffolding from the ground
floor level of the building, or a canopy should be provided from the first
floor level up to the highest level of the scaffolding;
Any skip hoist for material transport
should be totally enclosed by impervious sheeting;
Every stock of more than 20 bags of cement
or dry pulverised fuel ash (PFA) should be covered entirely by impervious
sheeting or placed in an area sheltered on the top and the three sides;
Cement or dry PFA delivered in bulk should
be stored in a closed silo fitted with an audible high level alarm which is
interlocked with the material filling line and no overfilling is allowed; and
Exposed earth should be properly treated
by compaction, turfing, hydroseeding, vegetation planting or sealing with
latex, vinyl, bitumen, shortcrete or other suitable surface stabiliser within
six months after the last construction activity on the construction site or
part of the construction site where the exposed earth lies.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
|
Air Quality (Operational Phase) |
|||||||||
N/A |
N/A |
N/A |
N/A |
|
|
|
|
N/A |
|
Noise (Construction Phase) |
|||||||||
5.10.2 |
The future contractors should follow
the requirements set out in the “Recommended Environmental Pollution Control
Clauses” published by EPD and adopt the following good site practices to minimise construction noise impacts on the
surrounding environment during construction phase:
Only well-maintained plant should be operated
on-site and plant should be serviced regularly during the construction
program.
Silencers or mufflers on construction equipment
should be utilized and should be properly maintained during the construction
program.
Mobile plant, if any, should be sited as far from
noise sensitive receivers (NSRs) as possible.
Machines and plant (such as trucks) that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum.
Plant known to emit noise strongly in one
direction should, wherever possible, be orientated so that the noise is
directed away from the nearby NSRs.
Material
stockpiles and other structures should be effectively utilized, wherever practicable,
in screening noise from on-site construction activities.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
EIAO Guidance Note No. 9/2004 “Preparation of
Construction Noise Impact Assessment under the Environmental Impact
Assessment Ordinance” (GN 9/2004) |
|
Noise (Operational Phase) |
|||||||||
5.10.3 |
The following noise reduction measures are recommended to
consider as far as practicable during the processes of detailed design and
procurement for the ventilation shafts:
Choose quieter plant such as those which have been
effectively silenced.
Include noise levels specification when ordering
new plant (including chillier and E/M equipment).
Locate fixed plant/louver away from any NSRs as
far as practicable.
Locate fixed plant in walled plant rooms or in
specially designed enclosures.
Locate noisy machines in a basement or a
completely separate building.
Install direct noise mitigation measures
including silencers, acoustic louvers and acoustic enclosure where necessary.
Develop and
implement a regularly scheduled plant maintenance programme so that equipment
is properly operated and serviced in order to maintain controlled level of
noise. The programme should be
implemented by properly trained personnel.
|
Ventilation shafts of rock cavern |
CEDD/Contractor |
ü |
ü |
|
|
EIAO-TM |
|
5.12.2 |
Prior to the operational phase of the rock cavern, a
commissioning test for the ventilation shaft should be conducted to ensure
compliance with the relevant noise criteria. |
Ventilation shafts of rock cavern |
CEDD/LCSD |
|
ü |
|
|
EIAO-TM |
|
Water Quality (Construction Phase) |
|||||||||
6.9.1 – 6.9.13 |
Construction
Site Run-off and General Construction Activities Boring and Drilling Water
Water used in ground boring and drilling for site
investigation or rock / soil anchoring should as far as practicable be re-circulated after sedimentation. When
there is a need for final disposal, the wastewater should be discharged into
storm drains via silt removal facilities.
Wheel Washing Water
All vehicles and plant should be cleaned before
they leave a construction site to minimize the deposition of earth, mud,
debris on roads. A wheel washing bay should be provided at every site exit if
practicable and wash-water should have sand and silt settled out or removed
before discharging into storm drains. The section of construction road
between the wheel washing bay and the public road should be paved with
backfall to reduce vehicle tracking of soil and to prevent site run-off from
entering public road drains.
Rubbish and Litter Good site practices should be adopted to
remove rubbish and litter from construction sites so as to prevent the
rubbish and litter from spreading from the site area. It is recommended to
clean the construction sites on a regular basis.
Construction Site Run-off
The site practices outlined in ProPECC PN 1/94
“Construction Site Drainage” should be followed as far as practicable to
minimise surface run-off and the chance of erosion. The following measures are recommended to
protect water quality and sensitive uses of the coastal area, and when
properly implemented should be sufficient to adequately control site
discharges so as to avoid water quality impact:
Surface run-off from construction sites should be
discharged into storm drains via adequately designed sand/silt removal facilities such as sand
traps, silt traps and sedimentation basins. Channels or earth bunds or sand
bag barriers should be provided on site to properly direct stormwater to such
silt removal facilities. Perimeter channels at site boundaries should be
provided on site boundaries where necessary to intercept storm run-off from
outside the site so that it will not wash across the site. Catchpits and
perimeter channels should be constructed in advance of site formation works
and earthworks.
Silt removal facilities, channels and manholes
should be maintained and the deposited silt and grit should be removed
regularly, at the onset of and after each rainstorm to prevent local
flooding. Any practical options for the diversion and re-alignment of drainage should comply with both
engineering and environmental requirements in order to provide adequate
hydraulic capacity of all drains. Minimum distance of 100m should be
maintained between the discharge points of construction site run-off and the
existing saltwater intakes. No effluent will be discharged into typhoon
shelter.
Construction works should be programmed to
minimize soil excavation works in rainy seasons (April to September). If
excavation in soil cannot be avoided in
these months or at any time of year when rainstorms are likely, for the
purpose of preventing soil erosion, temporary exposed slope surfaces should
be covered e.g. by tarpaulin, and temporary access roads should be protected
by crushed stone or gravel, as excavation proceeds. Intercepting channels
should be provided (e.g. along the crest / edge of excavation) to prevent
storm runoff from washing across exposed soil surfaces. Arrangements should
always be in place in such a way that adequate surface protection measures
can be safely carried out well before the arrival of a rainstorm.
Earthworks final surfaces should be well
compacted and the subsequent permanent work or surface protection should be
carried out immediately after the final surfaces are formed to prevent
erosion caused by rainstorms. Appropriate drainage like intercepting channels
should be provided where necessary.
Measures should be taken to minimize the ingress
of rainwater into trenches. If excavation of trenches in wet seasons is
necessary, they should be dug and backfilled in short sections. Rainwater
pumped out from trenches or foundation excavations should be discharged into
storm drains via silt removal facilities.
Construction materials (e.g. aggregates, sand and
fill material) on sites should be covered with tarpaulin or similar fabric
during rainstorms.
Manholes (including newly constructed ones)
should always be adequately covered and temporarily sealed so as to prevent
silt, construction materials or debris from getting into the drainage system,
and to prevent storm run-off from getting into foul sewers. Discharge of
surface run-off into foul sewers must always be prevented in order not to
unduly overload the foul sewerage system.
Good site practices should be adopted to remove
rubbish and litter from construction sites so as to prevent the rubbish and
litter from spreading from the site area. It is recommended to clean the
construction sites on a regular basis.
Site Effluent There is a need to apply to EPD for a
discharge licence for discharge of effluent from the construction site under
the WPCO. The discharge quality must
meet the requirements specified in the discharge licence. All the runoff and wastewater generated
from the works areas should be treated so that it satisfies all the standards
listed in the TM-DSS. The beneficial
uses of the treated effluent for other on-site activities such as dust
suppression, wheel washing and general cleaning etc., can minimise water
consumption and reduce the effluent discharge volume. If monitoring of the treated effluent
quality from the works areas is required during the construction phase of the
Project, the monitoring should be carried out in accordance with the relevant
WPCO licence which is under the ambit of regional office (RO) of EPD.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
ProPECC PN 1/94 Construction Site Drainage TM-DSS Water Pollution Control Ordinance |
|
6.9.14 – 6.9.16 |
Accidental
Spillage and Potential Contamination of Surface Water and Groundwater Contractor must register as a chemical
waste producer if chemical wastes would be produced from the construction
activities. The Waste Disposal
Ordinance (Cap 354) and its subsidiary regulations in particular the Waste
Disposal (Chemical Waste) (General) Regulation, should be observed and
complied with for control of chemical wastes.
Any service shop and maintenance
facilities should be located on hard standings within a bunded area, and
sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these
discharges.
Disposal of chemical wastes should be
carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes published under the Waste Disposal
Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:
-
Suitable
containers should be used to hold the chemical wastes to avoid leakage or
spillage during storage, handling and transport;
-
Chemical
waste containers should be suitably labelled, to notify and warn the
personnel who are handling the wastes, to avoid accidents; and
-
Storage
area should be selected at a safe location on site and adequate space should
be allocated to the storage area.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Waste Disposal Ordinance Waste Disposal (Chemical Waste) (General) Regulation The Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
|
6.9.17 – 6.9.18 |
Sewage
Effluent from Construction Workforce The construction workforce on site will
generate sewage. It is recommended to
provide sufficient chemical toilets in the works areas. A licensed waste collector should be deployed
to clean the chemical toilets on a regular basis.
Notices should be posted at conspicuous
locations to remind the workers not to discharge any sewage or wastewater
into the surrounding environment.
Regular environmental audit of the construction site will provide an
effective control of any malpractices and can encourage continual improvement
of environmental performance on site.
It is anticipated that sewage generation during the construction phase
of the project would not cause water pollution problem after undertaking all
required measures.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Water Pollution Control Ordinance |
|
6.9.19 |
Construction
Works in Close Proximity of Inland
Waters The practices outlined in ETWB TC (Works)
No. 5/2005 “Protection of natural
streams/rivers from adverse impacts arising from construction works”
should also be adopted where applicable to minimize the water quality impacts
upon any natural streams or surface water systems. Relevant mitigation measures from the ETWB
TC (Works) No. 5/2005 are listed below:
-
Construction
works close to the inland waters should be carried out in dry season as far
as practicable where the flow in the surface channel or stream is low.
-
The
use of less or smaller construction plants may be specified in areas close to
the water courses to reduce the disturbance to the surface water.
-
Temporary
storage of materials (e.g. equipment, chemicals and fuel) and temporary
stockpile of construction materials should be located well away from any
water courses during carrying out of the construction works.
-
Stockpiling
of construction materials and dusty materials should be covered and located
away from any water courses.
-
Construction
debris and spoil should be covered up and/or disposed of as soon as possible
to avoid being washed into the nearby water receivers.
-
Proper
shoring may need to be erected in order to prevent soil or mud from slipping
into the watercourses.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Water Pollution Control Ordinance |
|
6.9.20 – 6.9.23 |
Infiltration
of Groundwater Appropriate measures during the cavern
construction should be implemented to minimize
the groundwater infiltration. The water control strategies include:
-
Probing
Ahead: As normal practice, the Contractor will undertake rigorous probing of
the ground ahead of excavation works to identify zones of significant water
inflow. The probe drilling results will be evaluated to determine specific
grouting requirements in line with the tunnel / cavern advance. In such zones
of significant water inflow that could occur as a result of discrete,
permeable features, the intent would be to reduce overall inflow by means of
cut-off grouting executed ahead of the tunnel / cavern advance.
-
Pre-grouting:
Where water inflow quantities are excessive, pre-grouting will be required to
reduce the water inflow into the tunnel / cavern. The pre-grouting will be
achieved via a systematic and carefully specified protocol of grouting.
-
In
principle, the grout pre-treatment would be designed on the basis of probe hole
drilling ahead of the tunnel / cavern face.
-
The
installation of waterproof lining would also be adopted after the formation
of the tunnels and caverns.
In the event of excessive infiltration
being observed as a result of the tunnelling or excavation works even after
incorporation of the water control strategies, post-grouting should be
applied as far as practicable as described below:
-
Post-grouting:
Groundwater drawdown will be most likely due to inflows of water into the
tunnel / cavern that have not been sufficiently controlled by the
pre-grouting measures. Where this occurs post grouting will be undertaken
before the lining is cast. Whilst unlikely to be required in significant
measure, such a contingency should be allowed for reduction in permeability
of the tunnel / cavern surround (by grouting) to limit inflow to acceptable
levels.
The practical groundwater control measures
stated above are proven technologies and have been extensively applied in
other past projects. These measures or other similar methods, as approved by
the Engineer to suit the works condition shall be applied to minimize the
groundwater infiltration.
In case seepage of groundwater occurs,
groundwater should be pumped out from works areas and discharged to the storm
system via silt trap. Uncontaminated
groundwater from dewatering process should also be discharged to the storm
system via silt removal facilities.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Water Pollution Control Ordinance |
|
Water Quality (Operational Phase) |
|||||||||
6.9.24 – 6.9.25 |
All the sewage and wastewater generated
from the future development should be properly collected and diverted to
public sewers for proper treatment and disposal. Discharge of any commercial
effluent to the public sewers will be subject to control under the WPCO and
the relevant dischargers shall apply to EPD for a discharge licence for
discharge of commercial effluent and the discharge quality must satisfy all
the standards listed in the TM-DSS and meet the requirements specified in the
discharge licence. The practices
outlined in ProPECC PN 5/93 for handling, treatment and disposal of Operational
stage effluent should also be adopted where applicable.
|
All works area |
CEDD/Contractor |
|
|
ü |
|
Water Pollution Control Ordinance ProPECC PN 5/93 |
|
Sewerage and Sewage Treatment (Construction) |
|||||||||
N/A |
N/A |
N/A |
N/A |
|
|
|
|
N/A |
|
Sewerage and Sewage Treatment (Operational Phase) |
|||||||||
N/A |
N/A |
N/A |
N/A |
|
|
|
|
N/A |
|
Waste Management (Construction Phase) |
|||||||||
8.6.1 – 8.6.3 |
Good
Site Practices Appropriate waste handling, transportation
and disposal methods for all waste arising generated during the construction
works for the Project should be implemented to ensure that construction
wastes do not enter the nearby streams or drainage channel.
It is anticipated that adverse impacts
would not arise on the construction site, provided that good site practices
are strictly followed. Recommendations
for good site practices during the construction activities include:
-
Nomination
of approved personnel, such as a site manager, to be responsible for good
site practices, and making arrangements for collection of all wastes
generated at the site and effective disposal to an appropriate facility.
-
Training
of site personnel in proper waste management and chemical waste handling
procedures.
-
Provision
of sufficient waste reception/ disposal points, of a suitable vermin-proof
design that minimises windblown litter.
-
Arrangement
for regular collection of waste for transport off-site and final disposal.
-
Appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers.
-
Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors.
-
A
recording system for the amount of wastes generated, recycled and disposed
(including the disposal sites) should be proposed.
-
A
Waste Management Plan should be prepared and should be submitted to the
Engineer for approval. One may make
reference to ETWB TCW No. 19/2005
for details.
In order to monitor the disposal of
C&D materials at landfills and public filling areas, as appropriate, and
to control fly tipping, a trip-ticket system should be included as one of the
contractual requirements to be implemented by an Environmental Team
undertaking the Environmental Monitoring and Audit work. One may take
reference to DEVB TCW No.6/2010 for details.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
Waste Disposal Ordinance DEVB TCW No. 6/2010, ETWB TCW No. 19/2005 |
|
8.6.4 – 8.6.5 |
Waste
Reduction Measures Good management and control of
construction site activities/ processes can minimise the generation of waste.
Waste reduction is best achieved at the planning and design stage, as well as
by ensuring the implementation of good site practices. Recommendations to
achieve waste reduction include:
-
Segregate
and store different types of construction related waste in different
containers, skips or stockpiles to enhance reuse or recycling of materials
and their proper disposal.
-
Provide
separate labelled bins to segregate recyclable waste such as aluminium cans
from other general refuse generated by the work force, and to encourage
collection by individual collectors.
-
Any
unused chemicals or those with remaining functional capacity shall be
recycled.
-
Maximising
the use of reusable steel formwork to reduce the amount of construction and
demolition (C&D) materials.
-
Prior
to disposal of C&D waste, it is recommended that wood, steel and other
metals shall be separated for re-use and / or recycling to minimise the quantity
of waste to be disposed of to landfill.
-
Adopt
proper storage and site practices to minimise the potential for damage to, or
contamination of, construction materials.
-
Plan
the delivery and stock of construction materials carefully to minimise the
amount of waste generated.
-
Minimize
over ordering of concrete, mortars and cement grout by doing careful check
before ordering.
In addition to the above measures, other
specific mitigation measures are recommended below to minimise environmental
impacts during handling, transportation and disposal of wastes.
|
All works areas |
CEDD/Contractor |
ü |
ü |
|
|
Waste Disposal Ordinance ETWB TCW No. 19/2005 |
|
8.6.6 – 8.6.8 |
Construction
and Demolition Materials The C&D materials generated from demolition works of slope and cavern should be sorted on-site into inert C&D materials (that is, public fill) and C&D waste. To minimise the impact resulting from collection and transportation of C&D materials as far as practicable. C&D waste, such as wood, plastic, steel and other metals should be reused or recycled and, as a last resort, disposed to landfill. A suitable area should be designated within the site for temporary stockpiling of C&D materials and to facilitate the sorting process. Within the stockpile areas, the following measures should be taken to control potential environmental impacts or nuisance:-
Waste
such as soil should be handled and stored well to ensure secure containment;
-
Covering
materials during heavy rainfall;
-
Stockpiling
area should be provided with covers and water spraying system to prevent
materials from wind-blown or being washed away;
-
Locating
stockpiles to minimise potential visual impacts; and
-
Minimising
land intake of stockpile areas as far as possible.
General
Refuse General refuse should be stored in
enclosed bins or compaction units separate from C&D materials. A reputable waste collector should be
employed by the contractor to remove general refuse from the site, separately
from C&D materials. An enclosed
and covered area is preferred to reduce the occurrence of 'wind blown' light
material.
Chemical
Wastes If chemical wastes were to be produced at
the construction site, the Contractor would be required to register with the
EPD as a Chemical Waste Producer, and to follow the guidelines stated in the
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.
Good quality containers compatible with the chemical wastes should be used,
and incompatible chemicals should be stored separately. Appropriate labels
should be securely attached on each chemical waste container indicating the
corresponding chemical characteristics of the waste such as explosive,
flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor
shall use a licensed collector to transport the chemical wastes. The licensed
collector shall deliver the waste to the Chemical Waste Treatment Centre at
Tsing Yi, or other licensed facility, in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation.
|
All works areas |
CEDD/Contractor |
|
ü |
|
|
Waste Disposal Ordinance Waste Disposal (Chemical Waste) (General) Regulation Public Health and Municipal Services Ordinance (Cap.
132) - Public Cleansing and Prevention of Nuisances Regulation Land (Miscellaneous Provisions) Ordinance Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes Packaging, Labelling and Storage of Chemical Wastes |
|
Waste Management (Operational Phase) |
|||||||||
8.6.9 |
Sufficient
recycling containers are recommended to be provided at suitable locations to
encourage recycling of such waste as aluminium cans, plastics and waste
paper.
|
Within
site boundary |
LCSD |
|
|
ü |
|
EIAO-TM |
|
Landscape and Visual (Construction Phase) |
|||||||||
9.8.3 |
Erection of decorative screen hoarding.
|
All works area |
CEDD/Contractor |
|
ü |
|
|
EIAO-TM |
|
Landscape and Visual (Operational Phase) |
|||||||||
9.8.3 |
Sensitive and aesthetically pleasing design
as regard to the form, height, material and finishes which should be visually
unobtrusive, non-reflective compatible with surrounding context shall be
incorporated to design of cavern entrance and associated infrastructure
facilities.
|
Within
site boundary |
CEDD/Original
maintenance/management parties of the areas concerned |
ü |
|
ü |
|
EIAO Guidance Note No. 8/2010 |
|
9.8.3 |
Landscape treatments on slope to provide
vertical greening with climber to enhance the landscape and visual amenity
value of proposed man made slope.
|
Within
site boundary |
CEDD/LCSD/HyD/LandsD/HD |
ü |
|
ü |
|
GEO publication No. 1/2011 |
|
9.8.3 |
Compensatory trees planting in accordance with ETWB TCW
No. 10/2013 and Shrubs Planting shall be incorporated to enhance
the landscape and visual amenity value of entrance area of the proposed
cavern.
|
Within
site boundary |
CEDD/LCSD |
ü |
|
ü |
|
ETWB TCW No. 10/2013 |
|