11            Conclusions  

11.1.1    This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available at this stage. 

11.1.2    The assessment has been conducted, in accordance with the EIA Study Brief (No. ESB –269/2014) under the EIAO for the Project, covering the following environmental issues:

·                         Air Quality Impact

·                         Noise Impact

·                         Water Quality Impact

·                         Sewerage and Sewage Treatment Implication

·                         Waste Management Implication

·                         Landscape and Visual Impacts

11.1.3    The findings of this EIA study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operation phases.  The Implementation Schedule listing the recommended mitigation measures is presented in Section 10.

11.1.4    Overall, the EIA study for the Rock Cavern Development has predicted that the Project, with the implementation of the mitigation measures, would be environmentally acceptable with no adverse residual impacts on the population and environmentally sensitive resources.  Table 11.1 below summarises the environmental outcomes/benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project.

 

Table 11.1             Summary of Key Environmental Outcomes and Benefits

The Project Need

·      Using rock cavern to accommodate suitable land uses to serve this area e.g. G/IC facilities and/or commercial development into rock cavern.

·      Retaining some of the features of the past quarry operation (i.e. more than 50 years) to reflect the history and for educational or tourism functions.

Environmental/Social Benefits of the Project

·      Releasing precious land resources in other areas for residential development.

·      The proposed cavern development will only affect very small amount / extent of the existing vegetation.

·      Retaining some of the features of the past quarry operation (i.e. more than 50 years) to reflect the history and for educational or tourism functions.

Environmentally Friendly Design

·      The compact design and proposed usage of the exhibition cavern can reduce the C&D materials/wastes quantity arising from the construction stage comparing to the other option.

·      The proposed exhibition centre cavern is located within the proposed quarry park such that some common facilities (e.g. visitor reception counter, loading and unloading facilities and access road, etc.) could be shared between the quarry park and the exhibition centre cavern. This would reduce rock excavation and hence C&D materials/wastes quantity arising from the construction stage, minimize tree removal as well as construction noise and air quality impacts amongst other options.

·      The adoption of mechanical excavation method can avoid the use of explosive, which presents a significant risk to adjacent communities.

·      As the excavation works will be conducted within the cavern space.  The impacts (i.e. construction noise and dust) to the outside receivers are under control for the mechanical excavation method.

Air Quality

Construction Phase

Fugitive dust impact assessment for hourly TSP, daily RSP/FSP and annual RSP/FSP with the assumption of 100% active area at all times, has been conducted. With the provision of suitable dust mitigation measures, results indicate that all ASRs would comply with the 1-hour TSP EIAO-TM, 24-hour average RSP/FSP and annual average RSP/FSP criteria under AQOs.

Operational Phase

Air pollutants emissions from the exhibition area/resource centre would be not anticipated.  In addition, the project-induced daily traffic flow of 50 vehicle/day would not induce adverse air quality impact to the nearby ASRs.

The potential air quality emission sources to the proposed exhibition area/resource centre would be vehicular emissions from nearby local roads and a small-scaled PTI which locates at about 40m at the south of the Project site.  With reference to the predicted air quality condition in the vicinity of the cavern development of previous approved Schedule 3 EIA Report for Anderson Road Quarry Development, the air quality at the proposed exhibition area/resource centre is anticipated to comply with the AQOs.

Noise Impact

Construction Phase

Noise impacts arising from the construction activities of the Project are assessed for the representative NSRs in the assessment area.  Cumulative unmitigated construction noise levels at the representative NSRs are predicted to be in the range of 61 to 72 dB(A), complying with the construction noise criterion of 75 dB(A). No adverse construction noise impact is therefore anticipated.

Notwithstanding the above, the future contractors should still follow the good site practices and requirements set out under the "Recommended Pollution Control Clauses for Construction Contracts” published by EPD.

Operational Phase – Fixed Plant Noise

The maximum permissible sound power levels of the fixed noise sources, i.e. ventilation shaft(s), of the cavern are determined. With proper selection of plant and adoption of acoustic treatment, the NSRs would not be adversely affected.

If there is any change in engineering design information during detailed design stage or fitting-out stage, the fixed source noise design should be reviewed by engineer/contractor to ensure that both the relevant noise criteria can still be met at the NSRs in future.

Water Quality

Construction Phase

The key issue from the land-based construction activities would be the potential for release of wastewater from surface works areas, open cut excavation and groundwater infiltration during the formation of rock cavern. Minimisation of water quality deterioration could be achieved through implementing adequate mitigation measures. A water quality monitoring and audit programme will be implemented to ensure the effectiveness of the proposed water quality mitigation measures.

Operational Phase

The key source of potential impact on water quality during the operational phase will be the sewage and wastewater generated from the rock cavern development. However, no adverse water quality impact associated with the operational phase would be anticipated, provided that adequate sewerage and sewage treatment facilities are properly implemented to accommodate all the sewage effluents.

Sewerage and Sewage Treatment

The proposed sewer network in the ARQ development will be designed to cater for future residential development, commercial activities and sewage flow arising from the cavern development.

The sewage flow from the cavern development is estimated to be 8.4m3/day, which is around 0.1% of the total sewage flow of ARQ (i.e. 8,863m3/day), and has been taken in account in the design of ARQ sewerage system. Therefore, sewerage and sewage implications arising from cavern development are not anticipated.

Waste Management

Waste types generated by the construction activities are likely to include inert and non-inert C&D materials from excavation works for museum cavern (i.e. Main Museum, Entrance/Exit Adits and M&E Niches), general refuse from the workforce and chemical wastes from the maintenance of construction vehicles and equipment. Provided that these identified wastes would be handled, transported and disposed of using the recommended methods and that good site practices would be strictly followed, adverse environmental impacts are not expected.

The waste management assessment has recommended good waste management practices to ensure that adverse environmental impacts are prevented. The assessment concluded that no unacceptable environmental impacts would result from the storage, handling, collection, transport and disposal of wastes arising from the construction and operation of the project.

Landscape and Visual

Rock cavern development is an educational development to exhibit the geological importance of the quarry. For the whole planning of ARQ, improvement of landscape area and visual experience will benefit the overall existing condition which is a highly distributed area. Rock cavern development is part of the ARQ development and will benefit to the planning as well.

Although the proposed rock cavern development will be constructed inside the rock face, approximately 30 trees in front of the proposed rock cavern development and on the slope platform directly above the proposed rock cavern development will need to be felled. However, no impact will be made to the hillside woodland. The scale and the extent of RCD are small and will not enclose, block or reduce depth of the current view. Visual impact to the VSRs is slight and will be reduced to insubstantial after operation with mitigation measures.

The landscape and visual impacts due to the rock cavern development are considered to be acceptable with the implementation of appropriate mitigation measures. Impact will be insubstantial in the future after mitigation. The improvement of landscape area will further be beneficial to the whole area in long term.

11.1.5    The various sections of this EIA Report have presented the measures to minimise the potential environmental impacts associated the Project in construction and operational phases. The key measures to minimise the environmental impacts are summarised in Section 10.

11.1.6    Environmental monitoring and audit (EM&A) requirements have been recommended, where necessary, to check on project compliance of environmental legislation and standards. These are presented in a separate, stand-along EM&A manual.