Alternative 1 - Rock slopes at platform of +200mPD along and adjacent to the proposed carriageway of Road L1 (middle portion of existing rock slopes);
Alternative 2 - Rock slopes at platform of +200mPD adjacent to future development sites (southeastern portion of existing rock slopes); and
Alternative 3 - Rock slopes at platforms of other level higher than +200mPD.
Environmental Consideration |
Alternative 1 |
Alternative 2 |
Alternative 3 |
Recommended |
Rock Excavation Quantities |
Extra rock excavation required for
formation of loading & unloading facilities and assembly area |
Extra rock excavation required for
formation of loading & unloading facilities and assembly area |
Substantial rock excavation required for
formation of loading & unloading facilities, assembly area, vehicular
access road and pedestrian connection facilities |
No extra rock excavation required as
visitor facilities including assembly area, loading and unloading facilities
can be shared with the future Quarry Park |
Impacts to Existing Trees |
Removal of additional trees on rock slopes
required due to the site formation works of loading & unloading and
assembly area facilities |
Removal of additional trees on rock slopes
required due to the site formation works of loading & unloading and
assembly area facilities |
Removal of additional trees on rock slopes
required due to the site formation works of loading & unloading, assembly
area facilities, vehicular access road and pedestrian connection facilities |
No additional tree removal is required |
Nuisance of Operation to Nearby
Development Sites |
Close to the residential area and level of
nuisance is slightly to moderate |
No direct vehicular & pedestrian
access from public road to quarry exhibition cavern. Access will be in close
proximity to development sites.
Nuisance to nearby development sites is substantial |
Quarry exhibition cavern will be at higher
level platform of existing rock slopes and will be away from development
site. Nuisance is minor comparatively |
Quarry exhibition cavern will be within
future Quarry Park and away from the development sites. Nuisance is minimal. |
Construction Noise & Air Quality
Impacts |
Larger extent of rock excavation due to
site formation works for loading & unloading area for quarry exhibition
cavern comparing with the Recommended location. Hence, the construction noise
and air quality impacts are higher as well. |
Larger extent of rock excavation due to
site formation works for loading & unloading area for quarry exhibition
cavern comparing with the Recommended location. Hence, the construction noise
and air quality impacts are higher as well. |
Extent of site formation works and rock
excavation works will be the greatest amongst all 4 location options due to
the provision of vehicular and pedestrian accesses. Hence, the construction noise and air
quality impacts are the most significant. |
No additional rock excavation will be
required for the provision of access road and loading & unloading
facilities of the quarry exhibition cavern as they are all within the future
Quarry Park area. Hence, the
construction noise & air quality impacts are the least amongst the 4 options. |
Visual Impacts |
Insignificant |
Insignificant |
Critical as the provision of vehicular
access road and pedestrian connection facilities will involve substantial
rock excavation and tree removal at existing rock slopes |
Insignificant |
Alternative use of cavern apart from exhibition centre
Environmental Consideration |
Mechanical Excavation Method |
Chemical Expansion Agent Method |
Cardox Method |
Drill & Blast Method |
Suitability for Construction of Quarry
Exhibition Cavern |
Suitable |
Suitable but subject to rock mass
condition (not suitable for fracture and weak rock mass) |
Not suitable for granite (rock of ARQ Site
is mainly granite) |
Suitable |
Construction Duration |
Long |
Very long and the excavation rate is too
slow |
Long |
Fast for large quantity of rock
excavation. Similar construction rate
to mechanical excavation method for small quantity due to formation of
entrance & exit adits |
Construction Noise & Air Quality
Impacts |
High for open excavation but impacts are controllable
for cavern excavation since only excavation confined within cavern, noise and
dust emission can be easily controlled. |
Less impacts |
Less impacts |
High impacts due to dust and noise
emission |
Hazard to Public |
Hazard to public is minimum |
Hazard to public is minimum |
Hazard to public is minimum |
Hazard is high due to the delivery,
storage and handling of explosives |
|
Mechanical |
Drill-and-Blast |
Production rate (per 8hr shift) |
30 m³ (nominal) per 1-work site-machine [60 m³ (nominal) per 2-work site-machines, and
so on] |
> 100 m³ |
Environmental Benefits |
Controllable production rate and minmize the
adverse impact Impacts controlled inside the caverns, thus,
the dust emission and construction noise could be easily and better
controlled and hence less adverse environmental impacts. Construction is within the cavern and no
safety hazard and risk to the public during construction. |
Shorter construction time for the bulk
excavation but of similar construction rate for formation of entrance and
exit adits. Duration of construction nuisance would be
shorter. |
Environmental Disbenefits |
Slower production and longer construction time |
Handling, transportation and storage of
explosives having safetyhazards and risk to surroundings and public. Additional control/restrictions during
blastings. Dust and noise emission would be higher during
blasting. |
Permit application duration |
Not applicable |
At least 9 months |
Excavation duration |
If 2-work
site-machines deployed: 14,820 / 60 = 247 days |
14,820/ 100 = 149 days |
Total duration |
247 days |
9 months + 149 days |