TABLE OF CONTENTS

 

1       Introduction.. 1

1.1       Background. 1

1.2       Project Description. 1

1.3       Purpose of the Manual 2

1.4       Project Organisation. 3

1.5       Structure of the EM&A Manual 5

2       Air Quality Impact.. 7

2.1       Introduction. 7

2.2       Audit Requirement 7

2.3       Mitigation Measures. 7

3       Noise Impact.. 9

3.1       Introduction. 9

3.2       Construction Noise. 9

3.3       Operational Fixed Plant Noise. 9

3.4       Mitigation Measures. 9

4       Water Quality Impact.. 10

4.1       Introduction. 10

4.2       Water Quality Parameters. 10

4.3       Monitoring Location. 10

4.4       Baseline Monitoring. 11

4.5       Impact Monitoring. 11

4.6       Site Audits. 11

4.7       Field Log. 12

4.8       Monitoring Equipment and Procedures. 12

4.9       Laboratory Measurement / Analysis. 13

4.10     Event and Action Plan. 14

5       Sewerage and sewage treatment.. 17

5.1       Introduction. 17

6       Waste Management Implication.. 18

6.1       Introduction. 18

6.2       Mitigation Measures. 18

6.3       Audit Requirement 18

7       Landscape and Visual Impacts. 19

7.1       Introduction. 19

7.2       Mitigation Measures. 19

7.3       Audit Requirement 20

8       environmental Auditing.. 22

8.1       Site Inspection. 22

8.2       Compliance with Legal and Contractual Requirements. 22

8.3       Environmental Complaints. 23

9       Reporting.. 24

9.1       Introduction. 24

9.2       Baseline Monitoring Report 24

9.3       Monthly EM&A Reports. 24

9.4       First Monthly EM&A Report 25

9.5       Subsequent Monthly EM&A Reports. 26

9.6       Final EM&A Review Report – Construction Phase. 28

9.7       Date Keeping. 29

9.8       Interim Notification of Environmental Quality Limit Exceedances. 29

 

 

List of tables

 

Table 4.1         Proposed Water Quality Monitoring Station. 10

Table 4.2         Analytical Methods to be Applied to Water Quality Samples. 13

Table 4.3         Action and Limit Levels for Water Quality. 14

Table 4.4         Event and Action Plan for Water Quality. 15

Table 7.1         Construction Phase Mitigation Measure. 19

Table 7.2         Operational Phase Mitigation Measure. 19

Table 7.3         Event and Action Plan for Landscape and Visual 21

 

Lists of FIGUREs

 

Figure 1.1              Site Location Plan

Figure 1.2              Project Organization

Figure 4.1              Location of Water Quality Monitoring Station

Figure 7.1              Compensatory Tree Planting Plan

 

Appendices

Appendix A          Construction Programme

Appendix B          Implementation Schedule and Recommended Mitigation Measures

Appendix C          Sample Data Record Sheet

Appendix D          Sample of the Interim Notification

 

 

                             


1              Introduction

1.1          Background

1.1.1       The engineering feasibility study of the Anderson Road Quarry (ARQ) Development in East Kowloon has been conducted under the Agreement No. CE18/2012 (CE) “Development of Anderson Road Quarry - Investigation” (the FS) to ascertain the feasibility of implementing the development proposal.  The FS was classified as a designated project under the Schedule 3 of the Environmental Impact Assessment Ordinance (EIAO). Hence, as a part of the study, an environmental impact assessment (EIA) report titled “Development of Anderson Road Quarry“ has been submitted and approved under the EIAO (Register: AEIAR-183/2014) on 28 July  2014. 

1.1.2       Community engagement was conducted under the FS and public views were collected. There was no strong view from the public on the cavern development and some of the LegCo members recommended promoting business opportunity or educational purposes in making use of the cavern. It was recommended in the FS to construct and operate cavern development within the boundary of the ARQ Development.

1.1.3       Subsequently, a Project Profile No. PP-501/2014 was submitted for the EIA study brief under section 5(1)(a) of the EIAO. An EIA Study Brief No. ESB 269/2014 “Development of Anderson Road Quarry Site – Rock Cavern Developments” was issued to Civil Engineering and Development Department for carrying the environmental impact assessment for the Project presented in this EIA Report on 10 March 2014.

1.1.4       This Project comprises the construction of a cavern located on the rock slopes in the northeast side of the ARQ Development.

1.2          Project Description

1.2.1       The locations of the proposed cavern for quarry exhibition area/resource centre and the omitted caverns are shown in Figure 1.1.

1.2.2       The scope of the works of the proposed cavern for quarry exhibition will comprise the following activities:

Ÿ   Mobilization of construction plant and site clearance;

Ÿ   Removal of existing trees;

Ÿ   Slope excavation and stabilization works at cavern portal;

Ÿ   Rock excavation by drill and break method and temporary installation for cavern;

Ÿ   Permanent lining and portal construction for cavern; and

Ÿ   Landscaping works.

1.2.3       The construction works of the Project are anticipated to commence on site in early 2018, with completion of the Project by 2020.  A construction programme is presented in Appendix A for reference.

1.2.4       During this period of construction for the quarry exhibition cavern, the concurrent projects with construction works in the vicinity (500m from the site of cavern construction) will include the followings:

Project Item

Works Components

Time Line

1

Site formation and infrastructure (drainage, sewerage, water supply systems, landscaping works and internal roads with associated public transport terminus works of ARQ Site Development Phase 2 (northern portion of ARQ Site)

Cumulative impacts for construction phase and operational phase have been assessed.

Early 2018 – end 2020

2

Flood attenuation facilities (drainage retention tank and artificial lake, etc) within Quarry Park area

Cumulative impacts for construction phase have been assessed.

 

Early 2018 – end 2020

3

Salt and fresh water pumping stations at northern portion of ARQ Site

Cumulative impacts for construction phase has been assessed.

Mid 2018 – end 2020

4

Service reservoirs at +250mPD platform of rock slopes at the northern portion of ARQ Site

Cumulative impacts for construction phase has been assessed.

Mid 2018 – end 2020

5

Road improvement works at junction of Clear Water Bay Road and On Sau Road

Cumulative impacts for construction phase and operational phase have been assessed.

End 2016 - mid 2020

1.2.5       The cumulative impacts for construction phase and operational phase for these concurrent projects have been assessed respectively in the EIA.

1.2.6       Detailed EIA assessments have been conducted and presented in the EIA report. Mitigation measures have also been identified and recommended. The Project Implementation Schedule is given in Appendix B. It specifies the extent, locations, time frame and responsibilities for the implementation of the environmental mitigation measures identified.

1.3          Purpose of the Manual

1.3.1       The purpose of this Environmental Monitoring and Audit (EM&A) Manual is to guide the set-up of an EM&A programme to check on compliance with the Environmental Impact Assessment (EIA) study recommendations of the Project, to assess the effectiveness of the recommend mitigation measures, and to identify any further need for additional mitigation measures or remedial actions.

1.3.2       This EM&A Manual aims to provide systematic procedures for monitoring, auditing and minimizing environmental impacts associated with the activities of the Project. It outlines the monitoring and audit programme for the Project.

1.3.3       Hong Kong environmental regulations have served as environmental standards and guidelines in the preparation of this Manual. In addition, the EM&A Manual has been prepared in accordance with the requirement stipulated in Annex 21 of the Technical memorandum on Environmental Impact Assessment Process (EIAO-TM).

1.3.4       This Manual contains the following information:

Ÿ   Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), the Environmental Team (ET), and the Independent Environmental Checker (IEC) with respect to the environmental monitoring and audit requirements during the course of the Project;

Ÿ   Project organisation for the Project;

Ÿ   Requirements with respect to the construction programme schedule and the necessary environmental monitoring and audit programme to track the varying environmental impact;

Ÿ   Details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;

Ÿ   The rationale on which the environmental monitoring data will be evaluated and interpreted;

Ÿ   Definition of Action and Limit levels;

Ÿ   Establishment of Event and Action Plans;

Ÿ   Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints;

Ÿ   Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures; and

Ÿ   Requirements for reviewing the EIA predictions and the effectiveness of the mitigation measures / environmental management systems and the EM&A programme.

1.3.5       This EM&A Manual is a dynamic document that should be reviewed regularly and updated as necessary during the construction and operation of the Project.

1.4          Project Organisation

1.4.1       The roles and responsibilities of the various parties involved in the EM&A process and the organisational structure of the organisations responsible for implementing the EM&A programme are outlined below. The proposed project organisation and lines of communication with respect to environmental protection works are shown in Figure 1.2.

Environmental Team (ET)

1.4.2       The Environmental Team should be led and managed by the ET leader. The ET leader shall be independent party from the Contractor and has relevant professional qualifications, or have sufficient relevant EM&A experience subject to approval of the ER and EPD. The ET Leader shall have at least 7 years of experience in conducting EM&A for infrastructure projects. His / Her qualification shall be vetted by the ER. The ET should monitor the mitigation measures implemented by the Contractor on regular basis to ensure the compliance with the intended aims of the measures. The duties and responsibilities of the ET are:

Ÿ   Set up all the required environmental monitoring stations;

Ÿ    Monitor various environmental parameters as required in the EM&A Manual;

Ÿ   Analyse the EM&A data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;

Ÿ   Carry out site inspection and investigate and audit the Contractors’ site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and take proactive actions to pre-empt problems;

Ÿ   Liaison with IEC on all environmental performance matters, and timely submission of all relevant EM&A proforma for IEC’s approval;

Ÿ   Prepare reports on the environmental monitoring data and site environmental conditions;

Ÿ   Report on the EM&A results to the IEC. Contractor, the ER and EPD or tis delegated representative;

Ÿ   Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans;

Ÿ   Give advice to the Contractor on environmental improvement, awareness, enhancement matters, etc. on site;

Ÿ   Undertake regular and ad-hoc on-site audits / inspections and report to the Contractor and the ER of any potential non-compliance;

Ÿ   Follow up and close out non-compliance actions, and

Ÿ   Adhere to the procedures for carrying out environmental complaint investigation.

Engineer or Engineer’s Representative (ER)

1.4.3       The Engineer is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contractual requirements. The duties and responsibilities of the Engineer with respect to EM&A may include:

Ÿ   Supervise the Contractor’s activities and ensure that the requirements in the EM&A Manual are fully complied with;

Ÿ   Inform the Contractor when action is required to reduce environmental impacts in accordance with the Event and Action Plans;

Ÿ   Participate in joint site inspections and audits undertaken by the ET; and

Ÿ   Adhere to the procedures for carrying out complaint investigations.

The Contractor

1.4.4       The Contractor should report to the ER. The duties and responsibilities of the Contractor are:

Ÿ   Implement the EIA recommendations and requirements;

Ÿ   Provide assistance to the ET in carrying out relevant environmental monitoring;

Ÿ   Submit proposals on mitigation measures in case of exceedances of Action and Limit levels, in accordance with the Event and Action Plans;

Ÿ   Implement measures to reduce environmental impacts where Action and Limit levels are exceeded until the events are resolved; and

Ÿ   Adhere to the procedures for carrying out environmental complaint investigation in accordance with Section 8 of this Manual.

Independent Environmental Checker (IEC)

1.4.5       The IEC should advise the ER on environmental issues related to the Project. The IEC should possess at least 7 years of experience in EM&A. The duties and responsibilities of the IEC are:

Ÿ   Review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;

Ÿ   Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

Ÿ   Audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site;

Ÿ   Report the audit results/findings of site inspections and other environmental performance reviews to the ER and EPD in parallel;

Ÿ   Review the effectiveness of environmental mitigation measures and project environmental performance;

Ÿ   On as-needed basis, verify and certify the environmental acceptability of the Environmental Permit (EP) holder’s construction methodology, relevant design plans and submissions under the EP;

Ÿ   Carry out random sample check and audit on monitoring data and sampling procedures, etc;

Ÿ   Conduct random site inspection;

Ÿ   Verify the investigation results of environmental complaint cases and the effectiveness of corrective measures;

Ÿ   Verify EM&A report that has been certified by the ET leader; and

Ÿ   Provide feedback on the audit results to the ET or the EP holder according to the Event and Action Plans in the EM&A Manual.

1.5          Structure of the EM&A Manual

1.5.1       Following the introductory section, the remainder of the Manual is set out as follows:

Ÿ   Section 2 – Sets out EM&A requirement for air quality;

Ÿ   Section 3 – Sets out EM&A requirement for noise;

Ÿ   Section 4 – Details auditing requirement for water quality;

Ÿ   Section 5 – Sets out EM&A requirement for sewerage and sewage treatment;

Ÿ   Section 6 – Details auditing requirement for waste management;

Ÿ   Section 7 – Details auditing requirement for landscape and visual;

Ÿ   Section 8 – Describes scope and frequency of environmental site audits and sets out the general requirements of the EM&A programme; and

Ÿ   Section 9 – Details the EM&A reporting requirements

 


2              Air Quality Impact 

2.1          Introduction

2.1.1       In accordance with the EIA Report, with the proposed dust suppression measures in place, no adverse air quality impact is expected during the construction phase of the Project.  The impact from the Project itself contributed to the cumulative air quality impact is minimal, therefore, environmental monitoring for construction phase of the Project is considered unnecessary.  However, regular inspections of the construction activities and works areas should be conducted during the construction phase to ensure proper implementation of the recommended mitigation measures.

2.2          Audit Requirement

2.2.1       The ET shall conduct site audit to inspect the construction activities and works sites at least on a weekly basis to ensure the mitigation measures to be properly implemented.

2.2.2       Site audits should be based on the mitigation measures for the air pollution control as recommended in EIA Report.  In the event that the recommended mitigation measures are not fully or properly implemented, the ET should report the deficiency to the Engineer and the Contractor.  The Contractor shall implement the remedial and corrective action immediately.  The ET shall re-inspect the site conditions upon the completion of the remedial and correction action.

2.3          Mitigation Measures

2.3.1       Mitigation measures for dust control have been recommended in the EIA Report.  The Contractor shall be responsible for the design and implementation of these measures.              Recommended mitigation measures to minimise the adverse impacts on air quality during construction phases are detailed in Section 2.3.2 below.

2.3.2       To ensure compliance with the guideline level and AQO at the ASRs, the Air Pollution Control (Construction Dust) Regulation should be implemented and good site practices should be incorporated in the contract clauses to minimize construction dust impact. A number of below dust suppression measures are proposed to be implemented.

Ÿ   Watering once per hour on active construction work areas, and the watering application intensity is estimated to be 0.152 L/m2 so as to achieve a dust removal efficiency of 87.5%;

Ÿ   Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting or sprayed with water to maintain the entire surface wet and then removed or backfilled or reinstated where practicable within 24 hours of the excavation or unloading;

Ÿ   Any dusty material remaining after a stockpile is removed should be wetted with water and cleared from the surface of roads;

Ÿ   A stockpile of dusty material should not extend beyond the pedestrian barriers, fencing or traffic cones;

Ÿ   The load of dusty materials on a vehicles leaving a construction site should be covered entirely by impervious sheeting to ensure that the dusty materials do not leak form the vehicle;

Ÿ   Where practicable, vehicles washing facilities including a high pressure water jet should be provided at every discernible or designated vehicle exit point. The area where vehicle washing takes place and the road section between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

Ÿ   When there are open excavation and reinstatement works, hoarding of not less than 2.4m high should be provided as far as practicable along the site boundary with provision for public crossing. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period;

Ÿ   The portion of any road leading only to construction site that is within 30m of a vehicle entrance or exit should be kept clear of dusty materials;

Ÿ   Surfaces where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation takes place should be sprayed with water or a dust suppression chemical continuously;

Ÿ   Any area that involves demolition activities should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after the activities so as to maintain the entire surface wet;

Ÿ   Where a scaffolding is erected around the perimeter of a building under construction, effective dust screens, sheeting or netting should be provided to enclose the scaffolding from the ground floor level of the building, or a canopy should be provided from the first floor level up to the highest level of the scaffolding;

Ÿ   Any skip hoist for material transport should be totally enclosed by impervious sheeting;

Ÿ   Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the three sides;

Ÿ   Cement or dry PFA delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line and no overfilling is allowed; and

Ÿ   Exposed earth should be properly treated by compaction, turfing, hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen, shortcrete or other suitable surface stabiliser within six months after the last construction activity on the construction site or part of the construction site where the exposed earth lies.

2.3.3       The implementation schedule for the recommended air quality mitigation measures is presented in Appendix B.


3              Noise Impact

3.1          Introduction

3.1.1       The EIA has considered the potential noise impacts associated with the construction and operational phases of the Project. This section summarises EM&A requirement on noise.

3.2          Construction Noise

3.2.1       The EIA Report has predicted no adverse construction noise impacts from the Project, and therefore construction phase noise monitoring is not necessary under the EM&A programme. Nevertheless, regular site inspection during construction phase is recommended to ensure the effectiveness of implementation of proposed mitigation measures presented in the implementation schedule in Appendix B.

3.3          Operational Fixed Plant Noise

3.3.1       The maximum permissible sound power levels for the fixed noise sources of the cavern, i.e. the ventilation shaft(s), were determined in the EIA Report.  To ensure that the noise generated from the fixed plant operations would comply with the noise standards stipulated in the EIAO-TM, the specified sound power levels should be strictly observed by the Project Proponent and/or Contractor and the recommended mitigation measures in Appendix B should be implemented.  To ensure compliance with the fixed plant noise criteria, a commissioning test for the fixed plant of the ventilation shaft(s) should be conducted.

3.4          Mitigation Measures

3.4.1       The recommended mitigation measures for noise impacts are presented the implementation schedule in Appendix B.

3.4.2       In the event of complaints, or non-compliance being observed, the ET and the Contractor should review the effectiveness of these mitigation measures, design alternative or additional mitigation measures as appropriate and propose to ER for approval, and implement these alternative or additional measures.


4              Water Quality Impact

4.1          Introduction

4.1.1       As recommended in the EIA Report, inland water quality monitoring should be carried out during the site clearance and slope excavation works of the Project to ensure that any unacceptable increase in suspended solids / turbidity and decrease in dissolved oxygen in the nearby inland waters due to the construction activities could be readily detected and timely action be taken to rectify the situation.  It is also recommended that regular site inspections during the entire construction phase should be undertaken to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.

4.1.2       Adverse water quality impacts associated with the operation of the Project are not expected.  Thus, no water quality monitoring and audit programme is required during the Project operation.

4.1.3       This section describes the requirement of water quality monitoring during site clearance and slope excavation works of the Project.

4.2          Water Quality Parameters

4.2.1       Dissolved oxygen (DO), turbidity, suspended solids (SS) level and pH should be monitored at designated inland water quality monitoring station. 

4.2.2       The levels of DO, turbidity and pH should be measured in situ whereas SS should be determined by laboratory analysis.

4.3          Monitoring Location

4.3.1       One water quality monitoring station, namely Station G, is proposed in the upstream tributary of Tseng Lan Shue Stream near the Project works as listed in Table 4.1 and also shown in Figure 4.1. As the whole Tseng Lan Shue Main Stream and all its tributaries are located at the downstream of the Project works, no upstream control monitoring station can be defined for this Project.   The selected monitoring station is considered the most practical station for water sampling in terms of its accessibility and water depth.  The water courses further upstream (or closer to the Project site) are only small open ditches mainly collecting rainwater from the hill side, which are either difficult to be accessed or have very low flow.

4.3.2       Sampling should be taken at the water surface of Station G.  The monitoring station should not be influenced by any local pollution source so that representative data could be sampled. The ET Leader shall further review the status and suitability of the water quality monitoring station prior to the commencement of the monitoring works, and where necessary, propose with justification for changes to monitoring location or other requirements of the EM&A programme, and seek approval from the IEC and EPD.

Table 4.1               Proposed Water Quality Monitoring Station

Station

River

Description

Easting

Northing

G

Tseng Lan Shue Stream

Baseline and Impact Station

842562

821506

4.4          Baseline Monitoring

4.4.1       Baseline conditions at the designated monitoring station should be established and agreed with EPD prior to the commencement of construction works.  The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the works and to demonstrate the suitability of the proposed monitoring station.  The baseline conditions should normally be established by measuring the water quality parameters including DO, turbidity, SS and pH as specified in Section 4.2.

4.4.2       The baseline monitoring should be taken at the designated monitoring station, three days per week, for at least 4 weeks prior to the commencement of construction works. Temporal and spatial variations should be taken into account. There should not be any construction activities in the vicinity of the station during the baseline monitoring. The interval between 2 sets of monitoring should not be less than 36 hours. Replicate in-situ measures should be carried out in each sampling event.

4.4.3       Baseline monitoring schedule should be submitted to EPD at least 4 weeks prior to the commencement of baseline monitoring.  EPD should also be notified immediately for any changes in schedule.

4.4.4       The baseline monitoring report should be submitted to EPD at least 4 weeks before the commencement of the construction works for agreement.  The baseline monitoring report should be certified by the IEC before submission to EPD.

4.5          Impact Monitoring

4.5.1       During the site clearance and slope excavation works of the Project, impact monitoring should be undertaken three days per week with sampling / measurement at the designated monitoring station.  Upon completion of the site clearance and slope excavation works, the monitoring exercise at the designated monitoring location should be continued for four weeks in the same manner as the impact monitoring.  The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased.

4.5.2       Replicate in-situ measurements should be carried out in each sampling event.  The monitoring probes should be retrieved out of water after the first measurement and then redeployed for the second measurement.  Where the difference in value between the first and second readings of DO, turbidity or pH is more than 25% of the value of the first reading, the reading should be discarded and further readings should be taken. 

4.5.3       The water quality monitoring schedule should be submitted to EPD at least 1 week before the first day of the monitoring month.  EPD should be notified immediately of any changes in schedule.  If the monitoring data collected at the designated station indicate that the Action or Limit Levels as shown in Table 4.3 are exceeded, appropriate actions should be taken in accordance with the Event and Action Plan in Table 4.4.

4.6          Site Audits

4.6.1       Implementation of regular site audits aim to ensure that the recommended mitigation measures are properly undertaken during proposed construction works.  It can also provide an effective control of any malpractices and therefore achieve continual improvement of environmental performance on site.

4.6.2       Site audits shall be carried out by the ET and shall be based on the mitigation measures for water pollution control recommended in the implementation schedule as presented in Appendix B.  In the event that the recommended mitigation measures are not fully or properly implemented, deficiency shall be recorded and reported to the site management.  Suitable actions are to be carried out to:

Ÿ   investigate the problems and the causes;

Ÿ   issue action notes to the Contractor who is responsible for the works;

Ÿ   implement remedial and corrective actions immediately;

Ÿ   re-inspect the site conditions upon completion of the remedial and corrective actions; and

Ÿ   record the event and discuss with the Contractor for preventive actions.

4.7          Field Log

4.7.1       Other relevant data should also be recorded, such as: monitoring location / position, time, water depth, weather conditions and any special phenomena underway near the monitoring station.  A sample data record sheet is shown in Appendix C for reference.

4.8          Monitoring Equipment and Procedures

Dissolved Oxygen and Temperature Measuring Equipment

4.8.1       The instrument should be a portable and weatherproof DO measuring instrument complete with cable and sensor, and use a DC power source.  The equipment should be capable of measuring:

Ÿ   a DO level in the range of 0 ‑ 20 mg/L and 0 ‑ 200% saturation; and

Ÿ   a temperature of 0 ‑ 45 degree Celsius.

Turbidity Measurement Instrument

4.8.2       The instrument should be a portable and weatherproof turbidity-measuring instrument using a DC power source.  It should have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument).

pH Measurement Instrument

4.8.3       The instrument should consist of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device.  It should be readable to 0.1pH in a range of 0 to 14.  Standard buffer solutions of at least pH 7 and pH 10 should be used for calibration of the instrument before and after use.

Sampler

4.8.4       A water sampler is required.  It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

Sample Containers and Storage

4.8.5       Water samples for SS should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection.  Sufficient volume of samples should be collected to achieve the detection limit stated in Table 4.2.

Calibration of In-Situ Instruments

4.8.6       The DO meter and turbidimeter should be checked and calibrated before use.  DO meter and turbidimeter should be certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring.  Responses of sensors and electrodes should be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location.

4.8.7       Sufficient stocks of spare parts should be maintained for replacements when necessary.  Backup monitoring equipment should also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.9          Laboratory Measurement / Analysis

4.9.1       Analysis of SS should be carried out in a HOKLAS or other international accredited laboratory.  Sufficient water samples should be collected at the monitoring station for carrying out the laboratory determinations. The determination work should start within 24 hours after collection of the water samples.  The analyses should follow the American Public Health Association (APHA) Standard Methods for the Examination of Water and Wastewater or an equivalent method subject to the approval of EPD.  Analytical methods and detection limits for SS are present in Table 4.2.

Table 4.2               Analytical Methods to be Applied to Water Quality Samples

Parameters

Analytical Method

Detection Limit

Suspended Solids

APHA 2540D *

1 mg/L

* APHA  American Public Health Association Standard Methods for the Examination of Water and Wastewater

4.9.2       The testing of SS should be HOKLAS accredited (or if not, approved by EPD) and comprehensive quality assurance and control procedures in place in order to ensure quality and consistency in results.

4.9.3       Detailed testing methods, pre-treatment procedures, instruments use, Quality Assurance / Quality Control (QA/QC) details (such as blank, spike recovery, number of replicate samples per batch, etc.), detection limit and accuracy shall be submitted to EPD for approval prior to the commencement of monitoring programme.  EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance.  The QA/QC shall be in accordance with the requirements of HOKLAS or international accredited scheme.  The QA/QC results shall be reported.  The testing methods and related proposal should be checked and certified by IEC before submission to EPD for approval.

4.9.4       Additional replicate samples may be required by EPD for inter-laboratory calibration.  Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required.  If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD.  In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes.  The laboratory should prepare to demonstrate the programme to DEP or his representatives when requested.

4.10        Event and Action Plan

4.10.1    The water quality criteria, namely action and limit levels, are shown in Table 4.3.  These criteria should be applied to ensure that any deterioration of water quality is readily detected and timely action is taken to rectify the situation.  Should the monitoring results of the water quality parameters at any designated monitoring station exceed the water quality criteria, the actions in accordance with the Event and Action Plan summarized in Table 4.4 shall be carried out.

4.10.2    The ET Leader should assess the potential impacts on the water sensitive receiver based on the monitoring data.  The performance of the environmental management system (i.e. of the overall EM&A programme) should be reviewed by the ET Leader on a quarterly basis.  The findings of this review should be included in the quarterly EM&A summary reports, together with any recommendations to improve the performance of the EM&A programme.

Table 4.3               Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

Surface DO in mg/L

5 percentile (%-ile) of baseline data

4 mg/L or 1%-ile of baseline data

Surface SS in mg/L

95 %-ile of baseline data

25 mg/L or 99 %-ile of baseline data

Surface Turbidity in NTU

95 %-ile of baseline data

99 %-ile of baseline data

Surface pH

Beyond the range 6.6 to 8.4

Beyond the range of  6.5 to 8.5

Notes:   

1.     For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

2.     For pH, action should be taken if the measured pH falls outside the specified range.

3.     For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

4.10.3    Mitigation measures for water quality control have been recommended in the EIA Report.  The Contractor should be responsible for the design and implementation of these measures.

4.10.4    Recommended mitigation measures to minimize the adverse impacts on water quality during the construction activities are listed in the implementation schedule given in Appendix B.

4.10.5    In the event of complaints or non-compliance / area of improvement being observed, the ET and the Contractor should review the effectiveness of these mitigation measures, design alternative or additional mitigation measures as appropriate and propose to the IEC for approval and implement these alternative or additional measures.

 


Table 4.4               Event and Action Plan for Water Quality

Event

ET Leader

IEC

ER

Contractor

Action level being exceeded by one sampling day

·         Repeat in situ measurement to confirm findings;

·         Identify reasons for non-compliance and source(s) of impact;

·         Inform IEC and Contractor;

·         Check monitoring data, all plant, equipment and Contractor's working methods;

·         Discuss mitigation measures with IEC and Contractor;

·         Repeat measurement on next day of exceedance.

·         Discuss with ET and Contractor on the mitigation measures;

·         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·         Assess the effectiveness of the implemented mitigation measures.

·         Discuss with IEC on the proposed mitigation measures;

·         Make agreement on the mitigation measures to be implemented.

·         Assess the effectiveness of the implemented mitigation measures.

·         Inform the ER and confirm notification of the non-compliance in writing;

·         Rectify unacceptable practice;

·         Check all plant and equipment;

·         Consider changes of working methods;

·         Discuss with ET and IEC and propose mitigation measures to IEC and ER;

·         Implement the agreed mitigation measures.

Action level being exceeded by more than one consecutive sampling day

·         Repeat in situ measurement to confirm findings;

·         Identify reasons for non-compliance and source(s) of impact;

·         Inform IEC and Contractor;

·         Check monitoring data, all plant, equipment and Contractor's working methods;

·         Discuss mitigation measures with IEC and Contractor;

·         Ensure mitigation measures are implemented;

·         Prepare to increase the monitoring frequency to daily;

·         Repeat measurement on next day of exceedance.

·         Discuss with ET and Contractor on the mitigation measures;

·         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·         Assess the effectiveness of the implemented mitigation measures.

·         Discuss with IEC on the proposed mitigation measures;

·         Make agreement on the mitigation measures to be implemented;

·         Assess the effectiveness of the implemented mitigation measures.

·         Inform the ER and confirm notification of the non-compliance in writing;

·         Rectify unacceptable practice;

·         Check all plant and equipment;

·         Consider changes of working methods;

·         Discuss with ET and IEC and propose mitigation measures to IEC and ER within three working days;

·         Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

·         Repeat in situ measurement to confirm findings;

·         Identify reasons for non-compliance and source(s) of impact;

·         Inform IEC Contractor and EPD;

·         Check monitoring data, all plant, equipment and Contractor's working methods;

·         Discuss mitigation measures with IEC, ER and Contractor;

·         Ensure mitigation measures are implemented;

·         Increase the monitoring frequency to daily until no exceedance of Limit level.

·         Discuss with ET and Contractor on the mitigation measures;

·         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·         Assess the effectiveness of the implemented mitigation measures.

·         Discuss with IEC, ET and Contractor on the proposed mitigation measures;

·         Request Contractor to critically review the working methods;

·         Make agreement on the mitigation measures to be implemented;

·         Assess the effectiveness of the implemented mitigation measures.

·         Inform the ER and confirm notification of the non-compliance in writing;

·         Rectify unacceptable practice;

·         Check all plant and equipment;

·         Consider changes of working methods;

·         Discuss with ET, IEC and ER and propose mitigation measures to IEC and ER within three working days;

·         Implement the agreed mitigation measures.

Limit level being exceeded by more than one consecutive sampling day

·         Repeat in situ measurement to confirm findings;

·         Identify reasons for non-compliance and source(s) of impact;

·         Inform IEC Contractor and EPD;

·         Check monitoring data, all plant, equipment and Contractor's working methods;

·         Discuss mitigation measures with IEC, ER and Contractor;

·         Ensure mitigation measures are implemented;

·         Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days.

·         Discuss with ET and Contractor on the mitigation measures;

·         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·         Assess the effectiveness of the implemented mitigation measures.

·         Discuss with IEC, ET and Contractor on the proposed mitigation measures;

·         Request Contractor to critically review the working methods;

·         Make agreement on the mitigation measures to be implemented;

·         Assess the effectiveness of the implemented mitigation measures;

·         Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

·         Inform the ER and confirm notification of the non-compliance in writing;

·         Rectify unacceptable practice;

·         Check all plant and equipment;

·         Consider changes of working methods;

·         Discuss with ET, IEC and ER and propose mitigation measures to IEC and ER within three working days;

·         Implement the agreed mitigation measures;

·         As directed by the ER, to slow down or to stop all or part of the construction activities.


5              Sewerage and sewage treatment

5.1          Introduction

5.1.1       The assessment of potential sewerage impacts arising from the proposed cavern development has been assessed and the details are given in Section 7 of the EIA Report.

5.1.2       The total estimated Average Dry Weather Flow (ADWF) for the cavern is about 8.4m3/day which is about 0.1% of the total ADWF generated in ARQ Site. Thus, the additional ADWF of the cavern will not have any discernible impacts to the trunk sewerage network for the ARQ Site.

5.1.3       Furthermore, no sewage treatment facilities, sewage pumping station and rising main are proposed to be constructed in the cavern in view of the small quantity sewage. The sewage flow from the cavern has been taken in account in the design of ARQ sewerage system. Therefore, sewerage and sewage implications arising from cavern development are not anticipated and no EM&A requirement is considered necessary.


6              Waste Management Implication 

6.1          Introduction

6.1.1       Construction and Demolition (C&D) materials, general refuse from workforce and chemical waste would be generated during the construction phase. It is the Contractor’s responsibility to ensure all the waste arising from the Project is handled, stored and disposed of in accordance with good waste management practices, relevant legislation and waste management guidelines. Provided that the waste is handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts would not be expected.

6.2          Mitigation Measures

6.2.1       The mitigation measures recommended in EIA Report should from the basis of the site Waste management Plan (WMP) to be developed by the Contractor during the construction stage.

6.2.2       It is recommended that the waste generated during the construction activities should be audited regularly by the ET to determine if waste is being managed in accordance with approved procedures and the site WMP. The audit should look at all aspects of on-site waste management practices including waste management practices including waste generation, storage, recycling, transport and disposal. Apart from site inspection, documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation and contract requirements. In addition, the routine site inspections should check the implementation of the recommended good site practices and other waste management mitigation measures. In order to monitor the disposal of C&D material at landfills and public filling areas, as appropriate, and to control fly tipping, a trip-ticket system should be included as one of the contractual requirements to be implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work.

6.2.3       With the appropriate handling, storage and disposal of waste arising from the construction works as recommended in Appendix B, the potential of adverse environmental impacts would be minimized. During the site inspections, the ET should pay special attention to the issues relating to waste management and check whether the Contractor has implemented the recommended good site practices and mitigation measures.

6.3          Audit Requirement

6.3.1       Regular audits and site inspections should be carried out during construction phase by the ER, ET and Contractor to ensure that the recommended good site practices and the recommended mitigation measures in Appendix B are properly implemented by the Contractor. The audits should concern all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal. Apart from site inspection, documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation and contract requirements.

6.3.2       The requirements of the environmental audit programme are set out in Section 8 of this Manual. The audit programme will verify the implementation status and evaluate the effectiveness of the mitigation measures.


7              Landscape and Visual Impacts

7.1          Introduction

7.1.1       The EIA has recommended landscape and visual mitigation measures to be undertaken during both the construction and operational phases of the Project.  The design, implementation and maintenance of landscape mitigation measures should be checked to ensure that any potential conflicts between the proposed landscape measures and any other works of the project would be resolved as early as practical without affecting the implementation of the mitigation measures.

7.2          Mitigation Measures

7.2.1       The proposed mitigation measures of landscape and visual impacts are summarised in the Implementation Schedule of Mitigation Measures in Appendix B. The landscape and visual mitigation measures proposed should be incorporated in the detailed landscape and engineering design. The construction phase mitigation measures should be adopted from the commencement of construction and should be in place throughout the entire construction period. Mitigation measures for the operational phase should be adopted during the detailed design and be built as part of the construction works so that they are in place on commissioning of the Project. 

7.2.2       The landscape and visual mitigation measures are elaborated in Tables 7.1 and 7.2. The plan for compensatory tree planting is indicated in Figure 7.1.

 

Table 7.1          Construction Phase Mitigation Measure

ID No.

Construction Phase Mitigation Measures

Funding / Implementation

Maintenance / Management Agency

CM1(3)

Erection of decorative screen hoarding.

CEDD

CEDD

 

Table 7.2          Operational Phase Mitigation Measure

ID No.

Operational Phase Mitigation Measures

Funding / Implementation

Maintenance / Management Agency

OM1

Sensitive and aesthetically pleasing design as regard to the form, height, material and finishes which should be visually unobtrusive, non-reflective compatible with surrounding context shall be incorporated to design of cavern entrance and associated infrastructure facilities.

CEDD

 

Original maintenance/management parties of the areas concerned

OM2(1)(2)

Landscape treatments on slope to enhance the landscape and visual amenity value of proposed man made slope.

CEDD

Proposed maintenance/management party of the respective slopes: LCSD/HyD/LandsD/HD (responsible parties will be further discussed with government departments in detailed design stage)

OM3(1)

Compensatory trees planting in accordance with ETWB TCW No. 10/2013 and shrubs planting shall be incorporated to enhance the landscape and visual amenity value of entrance area of the proposed cavern.

CEDD

 

LCSD

(Responsible parties for trees will be further discussed with government departments in accordance with Technical Circular DEVB TCW No. 2/2004 in detailed design stage)

            Note:

(1)    The maintenance of the interim greening measures will be undertaken by contractor for the first 12-month establishment period. In the case that the site is still not allocated after the establishment period, CEDD would liaise with relevant government departments to agree on the subsequent maintenance agent of the interim greening measures. Contractor would be responsible for the maintenance of the interim greening measures before any agreement is made.

 

(2)    The management and maintenance agencies of mitigation measures have been identified in accordance with ETWB TC 2/2004. The agreement and approval of the implementation, management and maintenance agencies of the Project will be sought from relevant parties during detailed design stage of the project. Contractor would be responsible for maintenance and management of trees, vegetation and the associated facilities (e.g. irrigation system) within the permanent site boundary. The maintenance matrix and responsible parties for trees outside the permanent site boundary are yet to be confirmed. To facilitate with the confirmation process, CEDD would be responsible for the maintenance works before any agreement is made.

 

(3)     Mitigation measures refer to Good Site Practices.

 

7.3          Audit Requirement

7.3.1       Site audits should be undertaken during the construction and operational phase of the Project to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives.  Site audits should be undertaken by the ET at least once every two weeks during the construction period.  The audits shall concern tree preservation, transplanting, compensation, night-time glare control, management of work sites facilities and the implementation of permanent landscape works in accordance with the proposed mitigation measures in the Table 9.7, Table 9.8 and Figures 9 - 12 of the EIA report and the implementation schedule in Appendix B.

7.3.2       In the event of non-compliance, the responsibilities of the relevant parties are detailed in the Event/Action plan provided in Table 7.3.


Table 7.3               Event and Action Plan for Landscape and Visual

Event

ET Leader

IEC

ER

Contractor

Non-conformity on one occasion

·      Identify source(s);

·      Inform the Contractor, IEC and ER;

·      Discuss remedial actions with IEC, ER and Contractor;

·      Monitor remedial actions until rectification has been completed

·      Check inspection report;

·      Check contractor’s working method

·      Discuss with ET, ER and Contractor on possible remedial measures;

·      Advise ER on effectiveness of proposed remedial measures;

·      Check implementation of remedial measures

·      Confirm receipt of notification of non-conformity in writing

·      Review and agree on the remedial measures proposed by the Contractor;

·      Supervise implementation of remedial measures

·      Identify source and investigate the non- conformity

·      Implement remedial measures

·      Amend working methods agreed with ER as appropriate

·      Rectify damage and undertake any necessary replacement

Repeated Non- conformity

·      Identify source(s)

·      Inform the Contractor, IEC and ER;

·      Discuss inspection frequency

·      Discuss remedial actions with IEC, ER and Contractor

·      Monitor remedial actions until rectification has been completed;

·      If non- conformity stops, cease additional monitoring

·      Check inspection report

·      Check Contractor’s working method

·      Discuss with ET, ER and Contractor on possible remedial measures

·      Advise ER on effectiveness of proposed remedial measures

·      Supervise implementation of remedial measures

·      Notify the Contractor

·      In consultation with the ET and IEC, agree with the Contractor on the remedial measures to be implemented

·      Supervise implementation of remedial measures

·      Identify source and investigate the non- conformity

·      Implement remedial measures

·      Amend working methods agreed with ER as appropriate

·      Rectify damage and undertake any necessary replacement. Stop relevant portion of works as determined by ER until the non- conformity is abated.


8              environmental Auditing

8.1          Site Inspection

8.1.1       Site inspection is one of the most effective tools to enforce the environmental protection requirements at the works area by providing a direct mean to trigger and enforce specified environmental protection and pollution control measures. Site inspection should be undertaken regularly during the construction phase to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented for the activities associated with the Project.

8.1.2       The ET leader should be responsible for formulating the environmental site inspection programme as well as the deficiency and remedial action reporting system, and for carrying out the site inspections. The proposal for rectification, if any, should be prepared and submitted to the ET Leader and IEC by the Contractor.

8.1.3       Regular site inspections should be carried out and led by the ER and attended by the Contractor and ET at least once per week during the construction phase. The areas of inspection should not be limited to the environmental conditions and the pollution control and mitigation measures within the works area, it should also review the environmental conditions of locations that are beyond the boundary of the works area but are likely to be affected directly or indirectly by the construction site activities of the Project. During the inspection, the following information should be referred to:

Ÿ   The EIA Report and EM&A recommendations on environmental protection and pollution control mitigation measures;

Ÿ   Ongoing results of the EM&A programme;

Ÿ   Works progress and programme;

Ÿ   Individual works methodology proposals (which should include the proposal on associated pollution control measures);

Ÿ   Contract specifications on environmental protection and pollution prevention control;

Ÿ   Relevant environmental protection and pollution control legislations; and

Ÿ   Previous site inspection results undertaken by the ET and others

8.1.4       The Contractor should keep the ER and ET Leader updated with all relevant environmental related information on the construction contract necessary for him/her to carry out the site inspections. Site inspection results and associated recommendations for improvements to the environmental protection and pollution control efforts should be recorded and followed up by the Contractor in an agreed time-frame. The Contractor should follow the procedures and time-frame stipulated in the environmental site inspection, and the deficiency and remedial action reporting system to be formulated by the ET Leader, to report on any remedial measures subsequent to the site inspections.

8.1.5       The ER, ET and the Contractor should also carry out ad hoc site inspections if significant environmental problems are identified. Inspections may also be required subsequent to receipt of an environmental complaint, or as part of the investigation work, as specified in the Event and Action Plan for the EM&A programme.

8.2          Compliance with Legal and Contractual Requirements

8.2.1       There are statutory and contractual requirements on environmental protection and pollution control with which construction activities must comply.

8.2.2       To ensure that the workers are in compliance with the contractual requirements, all method statements of works should be submitted by the Contractor to the ER for approval and to the ET Leader for vetting to determine if sufficient environmental protection and pollution control measures have been included. The implementation schedule of mitigation measures is summarized in Appendix B.

8.2.3       The ER and ET Leader should also review the progress and programme of the works to check that relevant environmental legislations have not been violated, and that any foreseeable potential for violating laws can be prevented.

8.2.4       The Contractor should provide the update of the relevant documents to the ET Leader so that works checking could be carried out effectively. The document should at least include the updated Works Progress Reports, updated Works Programme, any application letters for licences / permits under the environmental protection legislations, and copies of all valid licences / permits. The site diary should also be available for the inspection by the relevant parties.

8.2.5       After reviewing the documentation, the ET Leader should advise the Contractor of any non-compliance with contractual and legislative requirements on environmental protection and pollution control so that they can timely take follow-up actions as appropriate. If the follow-up actions may still result in violation of environmental protection and pollution control requirements, the ER and ET should provide further advice to the Contractor to take remedial actions to resolve the problem.

8.2.6       Upon receipt of the advice, the Contractor should undertake immediate action to remedy the situation. The ER and ET should follow up to ensure that appropriate action has been taken in order to satisfy contractual and legal requirements.

8.3          Environmental Complaints

8.3.1       The following procedures should be undertaken upon receipt of any environmental complaint:

i)        The Contractor to log complaint and date of receipt onto the complaint database and inform the ER, ET and IEC immediately;

ii)       The Contractor to investigate, with the ER and ET, the complaint to determine its validity, and assess whether the source of the problem is due to construction works of the Project with the support of additional monitoring frequency and stations, if necessary;

iii)      The Contractor to identify remedial measures in consultation with the IEC, ET and ER if a complaint is valid and due to the construction works of the Project;

iv)     The Contractor to implement the remedial measures as required by the ER and to agree with the ET and IEC any additional monitoring frequency and stations, where necessary, for checking the effectiveness of the remedial measures;

v)      The ER, ET and IEC to review the effectiveness of the Contractor’s remedial measures and the updated situation;

vi)     The ET/Contractor to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur;

vii)    If the complaint is referred by the EPD, the Contractor to prepare interim report on the status of the complaint investigation and follow-up action stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD; and

viii)   The ET to record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.


9              Reporting

9.1          Introduction

9.1.1       Types of reports that the ET should prepare and submit include Baseline Monitoring Report, Monthly EM&A Reports and Final EM&A Review Report. In accordance with Annex 21 of the EIAO-TM, a copy of the monthly and final review EM&A reports should be made available to the Director of Environmental Protection.

9.1.2       Reports can be provided in an electronic medium upon agreeing the format with the ER and EPD.

9.2          Baseline Monitoring Report

9.2.1       The ET should prepare and submit a Baseline Environmental Monitoring Report for water quality at least 4 weeks before the commencement of construction works for the Project. Copies of the Baseline Environmental Monitoring Report should be submitted to the IEC, ER and EPD. The ET should liaise with the relevant parties on the exact number of copies require.

9.2.2       The Baseline Monitoring Report should include at least the following information:

Ÿ   Up to half a page of executive summary;

Ÿ   Brief description of project background information;

Ÿ   Drawings showing locations of the baseline monitoring stations;

Ÿ   Monitoring results (in both hard and diskette copies) together with the following information:

-       Monitoring methodology

-       Name of the laboratory and types of equipment used and calibration details

-       Parameters monitored

-       Monitoring locations (and depth)

-       Monitoring date, time, frequency and duration

-       QA/QC results and detection limits

Ÿ   Details of influencing factors, including:

-       Major activities, if any, being carried out n the Project site during the period

-       Weather conditions during the period

-       Other factors which might affect the monitoring results

Ÿ   Determination of the Action and Limit Levels (AL levels) for each monitoring parameter and statistical analysis of the baseline data;

Ÿ   Revisions for inclusion in the EM&A Manual; and

Ÿ   Comments and conclusions

9.3          Monthly EM&A Reports

9.3.1       The results and findings of all EM&A works required in this Manual should be recorded in the monthly EM&A reports prepared by the ET and endorsed by the IEC. The first Monthly EM&A Report should be prepared and submitted to EPD within a month after the major construction works commences with the subsequently Monthly EM&A Reports due in 10 works day of the end of each reporting month. Copies of each monthly EM&A report should be submitted to each of the three parties: ER, IEC and EPD. Before submission of the first monthly EM&A Report, the ET should liaise with the parties on the exact number of copies and format of the monthly reports in both hard copy and electronic copies.

9.3.2       The ET Leader should review the number and location of monitoring stations and parameters every six months, or on as needed basis, in order to cater for any changes in the surrounding environment and the nature of works in progress.

9.4          First Monthly EM&A Report

9.4.1       The first Monthly EM&A Report should include at least but not limited to the following:

i)        Executive summary (1-2 pages):

Ÿ  Breaches of Action and Limit levels;

Ÿ  Complaint log;

Ÿ  Notifications of any summons and successful prosecutions;

Ÿ  Reporting changes; and

Ÿ  Future key issues.

ii)       Basic project information:

Ÿ  Project organization including key personnel contact names and telephone numbers;

Ÿ  Construction programme;

Ÿ  Management structure; and

Ÿ  Works undertaken during the reporting month.

iii)      Environmental status:

Ÿ  Advice on the status of statutory environmental compliance, such as the status of compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;

Ÿ  Works undertaken during the reporting month with illustrations (e.g. location of works, etc); and

Ÿ  Drawings showing the Project area, any environmental sensitive receivers and the locations of the monitoring stations.

iv)     Summary of EM&A requirements:

Ÿ  All monitoring parameters;

Ÿ  Environmental quality performance limits (action and Limit levels);

Ÿ  Event and Action Plans;

Ÿ  Environmental mitigation measures, as recommended in the EIA Report; and

Ÿ  Environmental requirements in contract documents.

v)      Implementation status:

Ÿ  Advice on the implementation status of environmental protection and pollution control/mitigation measures as recommended in the EIA Report.

vi)     Monitoring results (in both hard and diskette copies) together with the following information:

Ÿ  Monitoring methodology;

Ÿ  Name of laboratory and types of equipment used and calibration details;

Ÿ  Monitoring parameters;

Ÿ  Monitoring locations;

Ÿ  Monitoring date, time, frequency and duration;

Ÿ  Graphical plots of the monitoring parameters in the reporting month annotated against the following;

-          Major activities being carried out on site during reporting period;

-          Weather conditions during the reporting period;

-          Any other factors which might affect the monitoring results; and

-          QA/QC results and detection limits.

vii)    Report on non-compliance, complaints, notifications of summons and status of prosecutions:

Ÿ  Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

Ÿ  Record of all complaints received (written or verbal), including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

Ÿ  Record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

Ÿ  Review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and

Ÿ  Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

viii)   Others:

Ÿ  An account of the future key issues as reviewed from the works programme and method statements of works;

Ÿ  Advice on the solid and liquid waste management status;

Ÿ  A forecast of the works programme, impact predictions and monitoring schedule for the next three months;

Ÿ  Compare the EM&A data in the reporting month with the EIA predictions and annotate with explanation for any discrepancies; and

Ÿ  Comments (e.g. the effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.

9.5          Subsequent Monthly EM&A Reports

9.5.1       Subsequent monthly EM&A Reports during the construction phase should include the following information:

i)        Executive summary (1-2 pages):

Ÿ  Breaches of Action and Limit levels;

Ÿ  Complaint log;

Ÿ  Notifications of any summons and successful prosecutions;

Ÿ  Reporting changes; and

Ÿ  Future key issues

ii)       Basic project information:

Ÿ  Project organization including key personnel contact names and telephone numbers;

Ÿ  Construction programme;

Ÿ  Management structure; and

Ÿ  Works undertaken during the reporting month.

iii)      Environmental status:

Ÿ  Advice on the status of statutory environmental compliance, the status of compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;

Ÿ  Works undertaken during the reporting month with illustrations (such as location of works, etc); and

Ÿ  Drawings showing the Project area, any environmental sensitive receivers and the locations of the monitoring stations.

iv)     Implementation status:

Ÿ  Advice on the implementation status of environmental protection and pollution control/mitigation measures as recommended in the EIA Report.

v)      Monitoring results (in both hard and diskette copies) together with the following information:

Ÿ  Monitoring methodology;

Ÿ  Name of the laboratory and types of equipment used and calibration details;

Ÿ  Monitoring parameters;

Ÿ  Monitoring locations (and depth);

Ÿ  Monitoring date, time, frequency and duration;

Ÿ  Graphical plots of the monitoring parameters in the reporting month annotated against the following;

-       Major activities being carried out on site during the reporting period;

-       Weather conditions during the reporting period;

-       Any other factors which might affect the monitoring results; and

-       QA/QC results and detection limits.

vi)     Report on non-compliance, complaints, notifications of summons and status of prosecutions:

Ÿ  Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

Ÿ  Record of all complaints received (written or verbal), including the locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

Ÿ  Record of all notification of summons and successful prosecutions for the breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

Ÿ  Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

Ÿ  Descriptions of the actions taken in the event of non-compliances and deficiency reporting and any follow-up procedures related to earlier non-compliance.

vii)    Others:

Ÿ  An account of the future key issues as reviewed from the works programme and method statements of works;

Ÿ  Advice on the solid and liquid waste management status;

Ÿ  A forecast of the works programme, impact predictions and monitoring schedule for the next three months;

Ÿ  Compare the EM&A data in the reporting month with the EIA predictions and annotate with explanation for any discrepancies; and

Ÿ  Comments (e.g. the effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.

viii)   Appendix:

Ÿ  Action and Limit levels;

Ÿ  Graphical plots of trends of the monitoring parameters over the past four reporting periods for the representative monitoring stations annotated against the following:

-       Major Project activities being carried out on site during the reporting period;

-       Weather conditions during the reporting period; and

-       Any other factors that might affect the monitoring results.

Ÿ  Monitoring schedule for the present and next reporting period;

Ÿ  Cumulative statistics on complaints, notifications of summons and successful prosecutions;

Ÿ  Outstanding issues and deficiencies.

9.6          Final EM&A Review Report – Construction Phase

9.6.1       The EM&A programme should be terminated upon completion of those construction activities that have the potential to result in a significant environmental impact.

9.6.2       Prior to the proposed termination, the proposed termination should be implemented after the proposal has been endorsed by the IEC, the Engineer and the Project Proponent followed by final approval from the Director of Environmental Protection.

9.6.3       The ET Leader should prepare and submit the Final EM&A Report which should contain at least the following information:

i)        Executive summary (1-2 pages);

ii)       Drawings showing the Project area, environmental sensitive receivers and locations of the monitoring stations;

iii)      Basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of works undertaken during the course of the Project;

iv)     A brief summary of EM&A requirements including;

Ÿ  Environmental mitigation measures, as recommended in the EIA Report;

Ÿ  Environmental impact hypotheses tested;

Ÿ  Environmental quality performance limits (Action and Limit levels);

Ÿ  All monitoring parameters; and

Ÿ  Event and Action Plans;

v)      A summary of the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report, summarised in the updated implementation schedule;

vi)     Graphical plots and the statistical analysis of the trends of monitoring parameters over the course of the Project, including the post-project monitoring for all monitoring stations annotated against:

Ÿ  The major activities being carried out on site during the reporting period;

Ÿ  Weather conditions during the reporting period; and

Ÿ  Any other factors which might affect the monitoring results;

vii)    A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

viii)   A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;

ix)     A description of the actions taken in the event of non-compliance;

x)      A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

xi)     A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection / pollution control legislation, locations and nature of the breaches, investigation follow-up actions taken and results;

xii)    A review of the validity of EIA predictions and identification of shortcomings of the recommendations proposed in the EIA Report; and

xiii)   Comments (for example, a review of the effectiveness and efficiency of the mitigation measures and of the performance of the environmental management system, that is, of the overall EM&A programme);

xiv)   Recommendations and conclusions (for example, a review of success of the overall EM&A programme to cost-effectively identify deterioration and to initiate prompt effective mitigation action when necessary).

9.7          Date Keeping

9.7.1       No site-based documents (such as monitoring field records, laboratory analysis records, site inspection forms, etc) are required to be included in the EM&A reporting documents. However, any such document should be properly maintained by the ET and be ready for inspection upon request. All relevant information should be clearly and systematically recorded in the document. Monitoring data should also be recorded in magnetic media form, and the software copy must be available upon request. All documents and data should be kept for at least one year following the completion of the construction phase EM&A for each construction contract.

9.8          Interim Notification of Environmental Quality Limit Exceedances

9.8.1       With reference to the Event and Actions Plans, when the environmental quality performance limits are exceeded and if they are proven to be valid, the ET should immediately notify the IEC and EPD, as appropriate. The notification should be followed up with advice to the IEC and EPD on the results of the investigation, proposed actions and success of the actions take, with any necessary follow-up proposals. A sample template for interim notification is presented in Appendix D.