Table of Contents

 

1.       Introduction                                            5

1.1         Background_ 5

1.2         Project Programme 5

1.3         Purpose of this Environmental Monitoring and Audit (EM&A) Manual 6

1.4         Structure of EM&A Manual 6

2.       Project Organization                                     8

2.1         Introduction_ 8

2.2         Project Proponent 8

2.3         The Contractor 8

2.4         Engineer’s Representatives (ER) 8

2.5         Independent Environmental Checker (IEC) 9

2.6         Environmental Team (ET) 9

3.       Air Quality Impact                                       11

3.1         Introduction_ 11

3.2         Monitoring Parameters 11

3.3         Monitoring Equipment 11

3.4         Monitoring Requirements 11

3.5         Monitoring Location_ 14

3.6         Placement of Equipment 14

3.7         Baseline Monitoring 15

3.8         Impact Monitoring 15

3.9         Air Quality Performance Limit 16

3.10       Event and Action Plan_ 16

3.11       Mitigation Measures 16

4.       Noise Impact                                         18

4.1         Introduction_ 18

4.2         Monitoring Parameters 18

4.3         Monitoring Equipment 18

4.4         Monitoring Requirement 19

4.5         Monitoring Location_ 19

4.6         Baseline Monitoring 19

4.7         Impact Monitoring 20

4.8         Noise Performance Limit 20

4.9         Event and Action Plan_ 20

4.10       Mitigation Measures 20

5.       Water Quality Impact                                 22

5.1         Introduction_ 22

5.2         Construction Phase EM&A_ 22

5.3         Monitoring Equipment 24

5.4         Water Quality Performance Limit 26

5.5         Event and Action Plan_ 27

5.6         Mitigation Measures 27

6.       Waste Management                                 28

6.1         Introduction_ 28

6.2         EM&A Requirement 28

6.3         Waste Management Plan_ 28

6.4         Site Audit 29

6.5         Mitigation Measures 29

7.       Ecological Impact                                 30

7.1         Introduction_ 30

7.2         Mitigation Measures 30

8.       Landscape and Visual Impacts                       31

8.1         Introduction_ 31

8.2         Monitoring of Mitigation Measures during the Construction Phase 31

8.3         Monitoring of Mitigation Measures during the Operation Phase 32

8.4         Mitigation Measures 32

9.       site environmental audit                               33

9.1         Introduction_ 33

9.2         Site Inspection_ 33

9.3         Compliance with Legal and Contractual Requirements 34

9.4         Environmental Complaints 34

10.    reporting                                                   36

10.1       Introduction_ 36

10.2       Baseline Monitoring Report 36

10.3       EM&A Report 37

10.4       First EM&A Report 37

10.5       Subsequent EM&A Reports 39

10.6       Quarterly EM&A Summary Reports 40

10.7       Final EM&A Report 42

10.8       Data Keeping 43

10.9       Interim Notification of Environmental Quality Limit Exceedances 43

11.    Conclusion                                             44

11.1       Introduction_ 44

 

 

 

Tables

Table 3.1         Proposed Dust Monitoring Stations

Table 3.2         Action and Limit Levels for Air Quality

Table 4.1         Proposed Construction Noise Monitoring Location

Table 5.1         Marine Water Monitoring Locations in Construction Phase

Table 5.2         Analytical method and detection limit for water samples

Table 5.3         Action and Limit Levels

 

Figures

Figure 1.1        Location of Project Site

Figure 2.1        Project Organisation for Environmental Works

Figure 3.1        Proposed Air & Noise Monitoring Stations

Figure 5.1        Proposed Water Monitoring Stations

 

Appendices

Appendix A     Environmental Mitigation Implementation Schedule (EMIS)

Appendix B     Sample Data Sheet

Appendix C     Event and Action Plan

Appendix D     Interim Notifications of Exceedances

 

 

1.                    Introduction

1.1                   Background

1.1.1             Silver Mine Bay is a popular bathing beach in Mui Wo that attracted 4,550 visitors on a peak day and over 69,000 visitors utilized the beach in 2012.

1.1.2             In order to relieve the overcrowding problem and the road safety concern of Wang Tong Bridge (hereafter called “Old Bridge”), two bridges (pedestrian bridge and cycle bridge) are proposed to replace the Old Bridge. The new pedestrian bridge and the new cycle bridge (hereafter called “New Bridges”) are also designed to align with the future amenity development on the northern side of the Old Bridge.

1.1.3             The Project mainly comprises the following works:

                                i.                Construction of a new cycle bridge next to the existing bridge

                              ii.                Demolition of the existing bridge

                            iii.                Construction of a new pedestrian bridge on the same site of the existing bridge

1.1.4             Based on the current design, both the new pedestrian bridge and cycle bridge will be supported by the abutment and pier that stand above high water mark of Wang Tong River. Location and layout of the New Bridges are shown in Figure 1.1.

1.1.5             The Project consists of the following designated projects under Part I, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO):

·           Item C.12 – (a)…a dredging operation which is less than 500m from the nearest boundary of an existing…(iii) bathing beach…

1.1.6             A project profile (PP-478/2013) has been submitted to Environmental Protection Department on 28 January 2013 and a study brief (ESB- 256/2013) has been issued to HyD in March 2013.

1.1.7             As a detailed environmental impact assessment (EIA) is required under the Environmental Impact Assessment Ordinance (EIAO), HyD appointed the Joint Venture of Maurice Lee and Associates Ltd. and Cinotech Consultants Ltd. (hereinafter called the JV) to perform the EIA study.

1.2                   Project Programme

1.2.1             The construction work for this Project is expected to be commenced in mid 2017 and completed in mid 2019.

1.3                   Purpose of this Environmental Monitoring and Audit (EM&A) Manual

1.3.1             The purpose of this EM&A Manual (hereafter called the “Manual”) is to guide the establishment of an EM&A programme to assure compliance with the standards and predictions in the EIA study involving the construction and operation of the New Bridges. Environmental performance will be regularly monitored and audited for evaluating the effectiveness of the recommended mitigation measures. If necessary, needs for additional mitigation measure(s) and/or remedial action(s) will also be investigated.

1.3.2             This EM&A Manual is prepared based on the findings and recommendations in the EIA, and with reference to the requirements stipulated in Annex 21 Technical Memorandum under the Environmental Impact Assessment Ordinance (EIAO-TM):

(i)            To propose EM&A programme to monitor the environmental performance of the project

(ii)          To check the implementation status of mitigation measures to minimize construction and operational impacts on the environment

(iii)        To identify the need for additional mitigation measures

(iv)        To advise the responsibilities of different parties involved in the project and communication flow among them

(v)          To detail monitoring requirements (locations, environmental parameters, frequency, duration) before and during the construction period and in the operational period

(vi)        To propose monitoring equipment required and quality assurance

(vii)      To determine action and limit levels of each environmental parameter based on the legislative criteria and standards for compliance checking

(viii)    To set up event and action plans for remedial actions if exceedance of compliance is identified

(ix)        To devise procedures for handling complaint/consultation

(x)          To detail reporting requirement

1.4                   Structure of EM&A Manual

1.4.1             This EM&A Manual comprises the following Chapters:

l   Ch.1  Introduction

l   Ch. 2  Project Organization

l   Ch. 3  Air Quality Impact

l   Ch. 4  Noise Impact

l   Ch. 5  Water Quality Impact

l   Ch. 6  Ecological Impact

l   Ch. 7  Waste Management

l   Ch. 8  Landscape and Visual Impact

l   Ch. 9  Site Environmental Audit

l   Ch. 10  Reporting

l   Ch. 11  Conclusion

 

2.                    Project Organization

2.1                   Introduction

2.1.1             The implementation of the recommended EM&A programme requires participation of relevant parties in a correlative and collaborative manner. The project organization and lines of communication with respect to the recommended EM&A works are shown in Figure 2.1. The roles and responsibilities of the key EM&A programme participants involved are described in the following sections.

2.2                   Project Proponent

2.2.1             The Project Proponent (Highways Department) shall employ Independent Environmental Checker (IEC) to audit and check the EM&A works of the Environmental Team (ET).

2.3                   The Contractor

2.3.1             The Contractor implies all construction contractors and sub-contractors working on the project site. He should:

(i)            Engage the ET to carry out EM&A work

(ii)          Notify the ET construction activities that may have environmental concern

(iii)        Participate in the site inspection carried out by the ET and to rectify any environmental deficiency identified

(iv)        Propose and implement necessary measures to mitigate any exceedance in Action/Limit Level recorded in accordance to the Event/Action Plans

(v)          Investigate complaints according to the agreed procedures

2.4                   Engineer’s Representatives (ER)

2.4.1             The ER shall be responsible to oversee the construction work of all contractors to ensure that the contract specification can be met. He should:

(i)            Supervise the Contractor’s activities to ensure that they comply with the requirement in the EIA, EM&A Manual, Environmental Permit (EP) and the contract specifications

(ii)          Follow the agreed procedures in the Event/Action Plan in case of any exceedance and instruct the Contractor to carry out remedial actions

(iii)        Investigate complaints according to the agreed procedures and instruct the Contractor to follow up

(iv)        Assist the ET in implementation of EM&A programme when required

2.5                   Independent Environmental Checker (IEC)

2.5.1             The IEC shall be appointed by Highways Department to audit and verify the EM&A works of the ET and to oversee the environmental performance of the project site. He shall not have any association with the Contractor, ER or ET.

(i)            Review and verify EM&A Reports and submissions for EP prepared by the ET and advise for improvement

(ii)          Audit and confirm the validity and accuracy of monitoring activities and results. He may carry out random sample check and audit on monitoring data and sampling procedures, etc

(iii)        Review the implementation status and effectiveness of mitigation measures onsite and ensure that they are carried out properly

(iv)        Conduct monthly and random site inspection.

(v)          Investigate complaints according to the agreed procedures

(vi)        Review the proposal of mitigation measures by the Contractor in an event of exceedance according to the Event/Action Plan

2.6                   Environmental Team (ET)

2.6.1             The ET shall be led by the ET Leader to carry out EM&A programme and to check the Contractor’s compliance with the environmental protection requirements in the EIA, EM&A Manual and EP. He should:

(i)            Set up monitoring station to carry out monitoring, statistical analysis and compliance checking against legislative standard and guidelines

(ii)          Repeat field measurement in case of exceedance and propose mitigation measures for improvement

(iii)        Conduct weekly site inspection to audit the Contractor’s site practice on pollution prevention and the effectiveness and adequacy of mitigation measures

(iv)        Advise the Contractor rectification work required when environmental deficiency is identified

(v)          Prepare monthly and quarterly EM&A report to summarise environmental performance and to anticipate future key issues

(vi)        Review and comment on work schedule and methodology as necessary

(vii)      Support the Contractor for submissions required under the EP

(viii)    Investigate complaints and propose corrective measures according to the agreed procedures

(ix)        Liaise with the IEC on environmental performance

2.6.2             The ET Leader shall keep a contemporaneous logbook for recording each and every instance or circumstance or change of circumstances that may affect the compliance with the recommendations of the EIA report. This logbook shall be kept readily available for inspection by the IEC, and Director of Environmental Protection (DEP) or his authorised officers.

 

3.                    Air Quality Impact

3.1                   Introduction

3.1.1             Major air quality impact in construction phase would arise from demolition of Old Bridge, excavation and concreting for construction of New Bridges. With implementation of dust suppression measures, it is anticipated that the dust impact would be minimal. Regular air quality monitoring should be conducted at representative ASRs to ensure that relevant air quality standard can be met.

3.1.2             In the operational phase, the bridges will serve as walkway and cycle track. No air pollution will be generated from these activities and therefore no operational phase air quality monitoring is required.

3.1.3             This section outlines the requirements, methodology, equipment and locations for monitoring air quality impacts during the demolition of the Old Bridge and construction of the New Bridges in the construction phase.

3.2                   Monitoring Parameters

3.2.1             The ET shall evaluate the construction air quality impact by conducting 1-hour and 24-hour Total Suspended Particulates (TSP) measurements.

3.3                   Monitoring Equipment

3.3.1             1-hour and 24-hour TSP levels will be measured in accordance to the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix A.

3.3.2             Other than using high volume sampler, 1-hour TSP levels can be measured alternatively by direct reading from portable dust meters upon approval from ER. The meters should be capable of producing comparable results as that by the high volume sampling method, to indicate short event impacts.

3.4                   Monitoring Requirements

High Volume Sampler

3.4.1             The ET shall provide sufficient number of high volume samplers (HVSs) for measurement at different ASRs during each monitoring. The HVSs shall comply with the following specifications for carrying out the 1-hour and 24-hour TSP monitoring:

(a)           0.6 - 1.7 m3 per minute adjustable flow range;

(b)           equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

(c)           installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

(d)          capable of providing a minimum exposed area of 406 cm2;

(e)           flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

(f)            equipped with a shelter to protect the filter and sampler;

(g)           incorporated with an electronic mass flow rate controller or other equivalent devices;

(h)           equipped with a flow recorder for continuous monitoring;

(i)             provided with a peaked roof inlet;

(j)             incorporated with a manometer;

(k)           able to hold and seal the filter paper to the sampler housing at horizontal position;

(l)             equipped with easily changeable filter; and

(m)         capable of operating continuously for a 24-hour period.

3.4.2             Clearly labelled calibration kit and filter papers shall also be provided. The HVSs should be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals.

3.4.3             Calibration should be conducted immediately after installing the HVSs, and repeated on bi-monthly basis. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

3.4.4             The flow-rate of HVSs shall be kept constant throughout the sampling process. Both initial and final flow-rate (with the filter in position) shall be recorded in the data sheet, as shown in Appendix B.

Direct Reading Meter

3.4.5             If the ET prefers to adopt direct reading method for 1-hour TSP, he should provide adequate support to the IEC for verifying the capacity of the meter as with the HVSs in obtaining comparable measurements. The meter shall be calibrated at regular intervals in accordance to the specification in the manufacturer’s manual. The calibration certificates shall be available to the IEC for checking upon request. The validity and accuracy of the meter shall also be tested against the results by the HVS periodically.

Collection of Wind Data

3.4.6             For recording wind speed and wind direction, the ET shall install wind data monitoring equipment near the dust monitoring locations. The installation location shall be proposed by the ET and agreed with the IEC. The installation and operation of the equipment shall meet the following criteria:

(a)           The wind sensors should be installed 10 m above ground so that they are clear of obstructions or turbulence caused by buildings.

(b)           The wind data should be captured by a data logger. The data shall be downloaded for analysis at least once a month.

(c)           The wind data monitoring equipment should be re-calibrated at least once every six months.

(d)          Wind direction should be divided into 16 sectors of 22.5 degrees each.

3.4.7             If agreed by the ER and the IEC, the ET may obtain wind data using alternative method.

Laboratory Testing

3.4.8             Filter paper to be placed in the HVSs should have a size of 8" x 10" and should be clean without any pinhole. Before sampling, it should be labelled, and pre-weighed to 0.1 mg by a calibrated electronic balance after being conditioned in a constant humidity for over 24 hours. 

3.4.9             After sampling, the filter paper in the HVS will be loaded with dust. The filter paper shall be collected and immediately transferred to a clean, tightly sealed plastic bag for transporting to laboratory. It shall be reconditioned in the constant humidity condition (as before pre-weighing) for over 24 hours before weighing to 0.1 mg by a calibrated electronic balance.

3.4.10         All samples should be kept in good condition for 6 months before disposal.

3.4.11         The testing laboratory should be HOKLAS accredited. It should be clean and be able to maintain a stable temperature and humidity. Measuring and conditioning instruments should be available for handling the dust samples. It should be able to carry out result analysis, equipment calibration and maintenance.

3.4.12         If a site or non-HOKLAS laboratory will be responsible for testing, the laboratory equipment shall be approved by the ER and the procedures shall be witnessed by the IEC. Any measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER and the IEC. The IEC shall regularly audit the performance of the laboratory to ensure the accuracy of testing results. The ET Leader shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix A for his reference.

3.5                   Monitoring Location

3.5.1             Two representative Air Quality Monitoring stations (AMSs) are proposed as follows:

Table 3.1     Proposed Dust Monitoring Stations

Monitoring Stations

Location

AMS1

Silvermine Beach Resort

AMS2

1 Tung Wan Tau Road

3.5.2             The location of the stations can be found in Figure 3.1.

3.5.3             The status and locations of dust sensitive receivers may change after this manual is issued. If this happened, the ET Leader shall propose alternative monitoring locations taken into account the following considerations and seek approval from the ER and the IEC:

(a)           locate at the site boundary or such locations close to the major dust emission source;

(b)           locate close to the sensitive receivers; and

(c)           take account the prevailing meteorological conditions.

3.6                   Placement of Equipment

3.6.1             The ET shall agree with the ER in consultation with the IEC on the position of the HVS for the installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:

(a)           a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;

(b)           no two samplers should be placed less than 2 meters apart;

(c)           the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;

(d)          a minimum of 2 meters of separation from walls, parapets and penthouses is required for rooftop samplers;

(e)           a minimum of 2 meters separation from any supporting structure, measured horizontally is required;

(f)            no furnace or incinerator flue is nearby;

(g)           airflow around the sampler is unrestricted;

(h)           the sampler is more than 20 meters from the dripline;

(i)             wire fence and gate to protect the sampler should not cause any obstruction during monitoring;

(j)             permission must be obtained to set up samplers and to access to monitoring stations; and

(k)           a secured electricity supply is required for samplers to operate.

3.7                   Baseline Monitoring

3.7.1             Baseline monitoring shall be conducted to determine the existing air quality in terms of 1-hour and 24-hour TSP levels before commencement of construction work. Measurement on 24-hour TSP for 14 consecutive days shall be conducted at all monitoring stations. At least 3 sets of 1-hour TSP data shall also be collected every day during this period, at the predicted time in which greatest impact is expected.

3.7.2             During baseline monitoring, there should have no major construction or dust generating activities near the monitoring stations. The ET shall propose a monitoring schedule to the IEC, so that he can conduct onsite audit to ensure the accuracy of the measurement where necessary.

3.7.3             Alternative AMS that can give representative baseline data may be proposed for ER and IEC’s approval with justifications.

3.7.4             In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and ER to agree on an appropriate set of data to be used as a baseline reference and submit to EPD for approval.

3.7.5             The baseline monitoring data shall be reviewed once in every three months. When there is seasonal change on ambient conditions, the baseline condition may need to be updated. Repeated measurements shall be conducted when there is no dust generating activity near the AMSs. If a change in ambient condition is recorded, the baseline levels, hence the air quality criteria should be revised accordingly and agreed with the IEC and EPD.

3.8                   Impact Monitoring

3.8.1             Impact monitoring shall be conducted throughout the construction period at all AMSs. 24-hour TSP shall be sampled at least once in every 6 days, while sampling for 1-hour TSP shall be at least 3 times in every 6 days when the highest dust impact takes place. Similar to baseline monitoring, the ET shall submit a monitoring schedule to the IEC for auditing the accuracy of the monitoring result where necessary.

3.8.2             The ET shall clearly define and strictly follow the starting and ending time for 24-hour TSP monitoring for each AMS.

3.8.3             If exceedance of air quality criteria is recorded, more frequent measurements shall be done within the specified timeframe in accordance to the Action Plan. The additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified, and upon agreement with the IEC.

3.9                   Air Quality Performance Limit

3.9.1             The Air Quality Objective sets the statutory limit for 1-hour and 24-hour TSP levels, while the baseline monitoring results shall be interpreted to derive the action levels.

Table 3.2  Action and Limit Levels for Air Quality

Parameters

Action

Limit

24-hour TSP Level in µg m-3

For baseline level £ 200 µg m-3, Action level = (baseline level * 1.3 + Limit level)/2;

For baseline level > 200 µg m-3 Action level = Limit level

260 µg/m3

1-hour TSP Level in µg m-3

For baseline level £ 384 µg m-3, Action level = (baseline level * 1.3 + Limit level)/2;

For baseline level > 384 µg m-3, Action level = Limit level

500µg/m3

3.10               Event and Action Plan

3.10.1         Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Appendix C shall be carried out.

3.11               Mitigation Measures

3.11.1         The EIA proposed a number of mitigation measures to be implemented in construction phase, examples as follows:

Construction Phase

(a)    Hoarding of not less than 2.4 m high shall be erected from ground level to surround the work area except for a site entrance or exit.

(b)   Good housekeeping to minimize dust generation, e.g. by properly handling and storing dusty materials

(c)    Adopt dust control measures, such as dust suppression using water spray on exposed soil, in areas with dusty construction activities and during material handling

(d)   Minimize exposed earth after completion of work in a certain area by hydroseeding, vegetating, soil compacting or paving

(e)    Cover materials on trolleys before leaving the site

(f)    Stockpiling should be avoided. However, if found necessary, the materials should be covered by impervious materials such as tarpaulin

3.11.2         Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of these measures shall be audited through regular site inspection.

4.                    Noise Impact

4.1                   Introduction

4.1.1             In the construction phase, the major noise impact will be arisen from the use of powered mechanical equipment. With the proposed mitigation measures, construction noise impact on the representative noise sensitive receiver is predicted to comply with the noise criteria. Regular monitoring of noise level should be carried out at noise monitoring stations near representative sensitive receiver before and throughout construction work to ensure that relevant noise standard can be met.

4.1.2             The New Bridges will serve as walkway and cycle bridge as the Old Bridge. No operational phase noise monitoring is required.

4.1.3             In this section, the equipment, requirements, monitoring locations, criteria and protocols for the monitoring and audit of noise impacts during the construction of the proposed New Bridges under the Project are presented.

4.2                   Monitoring Parameters

4.2.1             Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq 30min shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq 5min shall be employed for comparison with the Noise Control Ordinance (NCO) criteria.

4.2.2             As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.3                   Monitoring Equipment

4.3.1             Sound level meters shall be employed to measure the construction noise level. It should comply with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications in accordance to the Technical Memorandum (TM) issued under the NCO.

4.3.2             An acoustic calibrator shall be used to validate the accuracy of the sound level meter before and after each noise measurement. The calibrator can generate a known sound pressure level at a known frequency. The noise record will only be accepted if the calibration level from before and after the noise measurement agrees to within 1.0 dB.

4.3.3             Sufficient number of the above equipment shall be provided by the ET, who will also be responsible for installation, operation, maintenance and dismantlement. All equipment and instrumentation shall be clearly labelled.

4.4                   Monitoring Requirement

4.4.1             Noise measurement shall normally be at a point 1 m from the exterior of the sensitive receiver building façade and be at a position 1.2 m above the ground. If the normal monitoring position cannot be accessed, an alternative position may be chosen, and a correction to the measurements shall be made. For reference, a correction of +3 dB(A) shall be made to the free field measurements. The ET shall agree with the IEC on the monitoring position and the corrections adopted. The agreed position shall be chosen in subsequent baseline and impact monitoring.

4.4.2             Noise measurements should be made in accordance with standard acoustical principles and practices in relation to weather conditions.

4.5                   Monitoring Location

4.5.1             One representative Noise Monitoring Station (NMS) is proposed near the work site as follows:

Table 4.1  Proposed Construction Noise Monitoring Location

Monitoring Stations

Location

NMS1

1 Tung Wan Tau Road

4.5.2             The location of the station can be found in Figure 3.1.

4.5.3             The status and location of noise sensitive receiver may change after this manual is issued. If this happened, the ET Leader shall propose alternative monitoring location taken into account the following considerations and seek approval from the ER and the IEC:

(a)    locate close to the major site activities which are likely to have noise impacts;

(b)   locate close to the most affected existing NSR; and

(c)    take account the possibility of minimizing disturbance to occupants at the NSR during monitoring.

4.6                   Baseline Monitoring

4.6.1             Baseline measurement shall be conducted to determine the background noise level before commencement of work. Daily measurement of A-weighted levels Leq, L10 and L90 shall be conducted for at least two weeks. The sample period shall be 30 minutes between 0700 and 1900.

4.6.2             During the baseline monitoring, there should have no major construction or noise generating activities near the monitoring stations. The ET shall propose a monitoring schedule to the IEC so that he can conduct onsite audit to ensure the accuracy of the measurement where necessary.

4.6.3             Alternative NMS that can give representative baseline data may be proposed for ER and IEC’s approval with justifications.

4.6.4             In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and ER to agree on an appropriate set of data to be used as a baseline reference and submit to EPD for approval.

4.7                   Impact Monitoring

4.7.1             For daytime construction work on normal weekdays (0700-1900 Monday to Saturday), one set of 30-min measurement shall be carried out at each NMS every week. Measurement procedures shall be referred to the Noise Control Ordinance-TM. Similar to baseline monitoring, the ET shall submit a monitoring schedule to the IEC beforehand.

4.7.2             If noise exceedance is recorded, additional noise monitoring shall be conducted in accordance to the Event Action Plan. Additional monitoring shall only be considered as not necessary if the exceedance is being rectified or proved to be from source other than the project construction work.

4.7.3             Sample data sheet can be found in Appendix B.

4.8                   Noise Performance Limit

4.8.1             The EIAO-TM sets the statutory limit for noise level produced during construction work.

Table 4.2  Action and Limit Levels for Noise

Time Period

Action Level

Limit Level

0700-1900 hrs on normal weekdays

When one documented complaint is received

75dB(A)

4.9                   Event and Action Plan

4.9.1             Should non-compliance of the noise criteria occur, actions in accordance with the Action Plan in Appendix C shall be carried out.

4.10               Mitigation Measures

4.10.1         The EIA proposed a number of mitigation measures to be implemented in construction phase, examples as follows:

(a)    Adopt good site practice, such as regular maintenance of plant equipment, throttle down unused machines

(b)   Use Quality Powered Mechanical Equipment (QPME)

(c)    Erect 3m high mobile barriers with skid footing and a small cantilevered upper portion within a few meters of stationary plants and within about 5m of more mobile plant such as hydraulic breaker. The minimum surface density of the movable noise barrier is 7 kg/m2, and with special design (e.g. with noise absorbing material) where necessary.

(d)   Orient noisy plant equipment away from NSR

(e)    Should there be concurrent project in the vicinity, continuous discussion between contractors shall be conducted to plan the location and programme of construction work to minimize cumulative impact

4.10.2         Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of these measures shall be audited through regular site inspection.

5.                    Water Quality Impact

5.1                   Introduction

5.1.1             Potential water quality impacts arising from the construction activities are expected due to falling of debris to Wang Tong River, leakage of debris from cofferdam to Wang Tong River, surface runoff, and sewage generated from workforce. These would be minimized by implementing appropriate mitigation measures and good site management practices.

5.1.2             Monitoring is proposed in construction phase to keep track of the water quality, in order to identify any unacceptable impact on sensitive receivers. Site audit shall be conducted regularly to ensure that mitigation measures recommended in the EIA Report and this EM&A Manual are implemented properly.

5.1.3             No water quality impact is expected from the use of New Bridges as walkway and cycle track in the operational phase. Therefore, no water quality monitoring is required.

5.2                   Construction Phase EM&A

Monitoring Requirement

5.2.1             Regular monitoring of water quality should be carried out at water quality monitoring stations (WMSs) downstream to the construction point (impact station) and upstream to the construction site (control stations) before and throughout the construction period.

Monitoring Parameters

5.2.2             Suspended solids (SS) and in-situ water quality data (temperature, pH, turbidity, water depth, salinity, dissolved oxygen and percentage of saturation) shall be analysed/measured.

5.2.3             Other relevant data, including monitoring location/position, time, tidal stages, weather conditions and any special observation or works in the vicinity that may affect the monitoring results, should also be recorded.

5.2.4             To ensure the robustness of in-situ measurement, parameters shall be measured in duplicate. In case the difference between duplicates is larger than 25%, a third set of measurement shall be carried out.

5.2.5             A sample data sheet can be found in Appendix B.

Monitoring Location

5.2.6             8 water monitoring stations (WMS) are proposed along Wang Tong River and in Silvermine Bay. As the direction of water flow is influenced by stream water discharge and tidal action, each monitoring station will serve as either impact or control station under different tidal periods. Impact stations are located downstream to the construction site to measure any elevation of pollutant levels (e.g. SS level) due to proposed work. Control stations are located upstream of construction site to establish baseline level. The location of the stations can be found in Figure 5.1.

Table 5.1   Marine Water Monitoring Locations in Construction Phase

Station

Description

Monitoring Period

Monitoring Station

Easting

Northing

W1

Wang Tong River

(Major tributary)

Mid-Flood

Impact

817747

814519

Mid-Ebb

Control

W2

Wang Tong River

(Major tributary)

Mid-Flood

Impact

817775

814471

Mid-Ebb

Control

W3

Wang Tong River

(Minor tributary to
Tai Wai Yuen)

Mid-Flood

Impact

817803

814537

Mid-Ebb

Control

W4

Wang Tong River

(Minor tributary to
Tai Wai Yuen)

Mid-Flood

Impact

817825

814481

Mid-Ebb

Control

W5

Silvermine Bay
(Near Silvermine Bay Beach)

Mid-Flood

Control

817909

814452

Mid-Ebb

Impact

W6

Silvermine Bay
(Near Silvermine Bay Beach)

Mid-Flood

Control

818024

814447

Mid-Ebb

Impact

W7

Silvermine Bay
(Open Water)

Mid-Flood

Control

818061

814277

Mid-Ebb

Impact

W8

Silvermine Bay
(Open Water)

Mid-Flood

Control

818224

814444

Mid-Ebb

Impact

5.2.7             Water samples shall be extracted at 1m below surface, 1m above seabed and at the mid-depth level at where the water depth is at least 6m. However, if the water depth is less than 3m, water samples shall only be collected at the mid-depth level. For stations with depth less than 6m, the mid-depth sample can be omitted.

5.2.8             As the water depth in Wang Tong River can be shallow, sampling work shall be conducted with caution to avoid disturbing the bottom sediment during movement and water extraction.

Monitoring Frequency

5.2.9             Baseline Monitoring shall be carried out 3 days per week, at mid-flood and mid-ebb tides (within ± 1.75 hour of the predicted time), for a period of 4 weeks prior to the commencement of construction works. The interval between two sets of monitoring shall not be less than 36 hours. The monitoring period should avoid concurrent marine project in the vicinity.

5.2.10         Impact monitoring shall also be conducted at the same frequency throughout the whole construction period. In case exceedance of Action/Limit Level is recorded, the frequency shall be increased as per the Event and Action Plan.

Construction Phase Site Inspection

5.2.11         Weekly site audit is recommended to monitor the implementation of the proposed water quality mitigation measures and to check the Contractor’s work practice on preventing water pollution during construction phase.

5.2.12         Should water pollution is observed (e.g. discharge of silty water into storm drains), the ET should record the environmental deficiency for investigation. The Contractor should be notified and responsible for carrying out rectification work immediately. The ET shall re-inspect the site and review the effectiveness of the remedial measure performed until satisfaction. The Contractor shall implement preventive measure(s) to avoid the same problem.

5.3                   Monitoring Equipment

Position System

5.3.1             A calibrated hand held Global Positioning System (GPS) device shall be used during water quality monitoring. The GPS device shall be calibrated at checkpoint (e.g. Quarry Bay Survey Nail at Easting 840683.49 and Northing 816709.55) before taking samples and in-situ measurements. This would ensure that monitoring works are conducted in proposed locations. .

Water Depth Detector

5.3.2             A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station.

Salinity

5.3.3             A portable salinometer which capable of recording salinity within the range of 0-40 % shall be used for salinity measurements.


Dissolved Oxygen (DO) and Temperature Measuring Equipment

5.3.4             The instrument for measuring dissolved oxygen and temperature shall be portable and weatherproof complete with cable, sensor, comprehensive operation manuals and using DC power source. It shall be capable of measuring:

·            A dissolved oxygen level in the range of 0-20 mg/L and 0-200% saturation; and

·            A temperature of 0-45 degree Celsius.

5.3.5             It shall have a membrane electrode with automatic temperature compensation complete with a cable.

5.3.6             Sufficient stocks of spare electrodes and cables shall be available for replacement where necessary.

5.3.7             Salinity compensation shall be built-in in the DO measuring equipment.

Turbidity Measurement Equipment

5.3.8             Nephelometric method shall be used in measuring turbidity in-situ. The instrument shall be portable, weatherproof complete with a cable, sensor, comprehensive operation manuals and DC power source. It shall have a photoelectric sensor capable of measuring turbidity between 0-1000 NTU and complete with a cable with at least 25 m in length. The meter shall be calibrated in order to establish the relationship between NTU units and suspended solids level. Turbidity shall be measured on split water sample collected from the same depths of suspended solid samples.

pH

5.3.9             The instrument shall consist of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device. It shall be readable to 0.1 pH in a range of pH 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 shall be used for calibrating the instrument before and after use.

Sampler

5.3.10         A water sampler, consisting of a transparent PVC or glass cylinder of a capacity of not less than two litres which can be effectively sealed with cups at both ends shall be used. The water sampler shall have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.

Sample Container and Storage

5.3.11         After sampling, samples shall be transferred and stored in high density polythene bottles with no preservatives added, stored in 4°C without being frozen, and delivered to the laboratory for analysis as soon as possible. Each sample should have sufficient volume for robust analysis.

Calibration of In-situ Instruments

5.3.12         All in-situ monitoring instruments shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and be subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme. Responses of sensors and electrodes shall be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring event.

5.3.13         For the on-site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" shall be observed.

5.3.14         Sufficient stocks of spare parts shall be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even if some equipment is under maintenance, calibration, etc.

Laboratory Analysis

5.3.15         The testing of suspended solids shall be conducted by a HOKLAS accredited laboratory with comprehensive quality assurance and control procedures in place in order to ensure the quality and the consistency of results. Analytical method and detection limit shall follow APHA 17e 2540 D or equivalent, subject to agreement with EPD.

Table 5.2 Analytical method and detection limit for water samples

Determinant

Detection Limit

Method Reference

Suspended Solids

0.5 mg/L

APHA 17e 2540 D

5.4                   Water Quality Performance Limit

5.4.1             The following table listed out the criteria for relevant water quality parameters during construction phase monitoring work.

Table 5.3   Action and Limit Levels

Parameters

Action Level

Limit Level

DO in mg/ L (Surface, Middle & Bottom)

Surface & Middle: 5 percentile of baseline data for surface and middle layers

Bottom: 5 percentile of baseline data for bottom layer.

Surface & Middle: 4 mg/L or 1 percentile of baseline data for surface and middle layers.

Bottom: 2 mg/L or 1 percentile of baseline data for bottom layer.

SS in mg/ L (depth-averaged)

95 percentile of baseline data or 120% of upstream control station's SS at the same tide of the same day.

99 percentile of baseline data or 130% of upstream control station's SS at the same tide of the same day.

Turbidity in NTU (depth-averaged)

95 percentile of baseline data or 120% of upstream control station's turbidity at the same tide of the same day.

99 percentile of baseline or 130% of upstream control station's turbidity at the same tide of the same day.

 

5.5                   Event and Action Plan

5.5.1             Should non-compliance of the water quality criteria occur, actions in accordance with the Action Plan in Appendix C shall be carried out.

5.6                   Mitigation Measures

5.6.1             Examples of construction phase mitigation measures are shown as follows:

(a)    Schedule works in water in dry season as far as possible (e.g. demolition of old pier, construction of abutment)

(b)   Construct abutment of the bridge within cofferdam

(c)    Demolish existing pier within waterproof casing

(d)   Construct temporary platform above water to prevent falling of debris during demolition and construction of bridges

(e)    Well manage construction materials, stockpiles and chemicals for proper storage and usage and to prevent accumulation onsite. Keep them away from the river and sea.

(f)    Immediately clean up contaminated soil upon chemical and oil leakage

(g)   Store fuels, chemicals and waste at designated area with locks and bunds

(h)   Register as chemical waste producer

(i)     Settle surface runoff in sedimentation tank prior to discharge

(j)     Cover slope and loose materials with tarpaulin before rainstorm and inspect the area afterwards

(k)   Cover manhole to prevent silty runoff from entering the foul sewer

5.6.2             Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of these measures shall be audited through regular site inspection.

6.                    Waste Management

6.1                   Introduction

6.1.1             This project is expected to generate inert and non-inert construction and demolition (C&D) waste from demolition of Old Bridge, excavation/dredging for pile cap and unused construction materials; marine sediment extracted from minipile; chemical waste from plant maintenance; and general refuse from workers. No adverse waste impact is expected if the mitigation measures are implemented properly. No operational waste is expected.

6.1.2             Land use in the vicinity of the Site includes residential, commercial (hotel) and bathing beach. Active agriculture in the past has now subsided. No industrial activity that may cause land contamination was identified. Previous land use as pig farm at the now Silvermine Beach Resort is evaluated to cause low contamination potential at the work site. No unacceptable land contamination impact is expected and no EM&A is proposed.

6.2                   EM&A Requirement

6.2.1             The Contractor should apply relevant licences/permits for waste disposal under the following regulations and ordinances:

(a)    Chemical Waste Permits/licenses under the Waste Disposal Ordinance (Cap 354);

(b)   Public Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap 28);

(c)    Effluent Discharge Licence under the Water Pollution Control Ordinance.

6.2.2             Reference should be made to EPD’s booklets on licences/permits. The Contractor shall also document recycling receipts/ disposal record to keep track of waste movement. The ET shall check with the Contractor that these licences/permits have been obtained. He should also review the above documentations regularly to ensure compliance with legislations and specifications.

6.3                   Waste Management Plan

6.3.1             The contractor should formulate waste management measures on waste minimization, storage, handling and disposal in a Waste Management Plan as part of Environmental Management Plan in accordance to ETWB TC (W) No.19/2005 for construction phase. Mitigation measures proposed in the EIA Report and the EM&A Manual should be adopted.

6.4                   Site Audit

6.4.1             Regular site audit shall be conducted by the ET to check the implementation status and evaluate the effectiveness of the proposed mitigation measures.

6.5                   Mitigation Measures

6.5.1             The EIA proposed a number of construction phase mitigation measures, examples as follows:

(a)    Reuse C&D waste onsite and dispose excess uncontaminated ones to public fill

(b)   Provide sufficient waste collection points for general refuse and regularly maintained to avoid accumulation. Dispose the waste at waste transfer or disposal facilities

(c)    Provide training to workers on site cleanliness, waste management (waste reduction, reuse and recycle) and chemical handling procedures

(d)   Excavated marine sediment should be treated by cement solidification and backfilled on land or disposed as public fill as the last resort. Alternatively, the solidified sediment shall be delivered to public fill reception facilities for beneficial reuse as the last resort. No marine dumping will be required.

6.5.2             Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status and the effectiveness of these measures shall be audited through regular site inspection.

7.                    Ecological Impact

7.1                   Introduction

7.1.1             The proposed Project will cause minor permanent habitat loss of sandy shore above high water mark. Indirect water quality impact which may arise from falling of debris from demolition and construction work, surface runoff or chemical leakage would be minor in construction phase. Use of powered plant equipment may bring minor noise disturbance on wildlife. No ecological impact is expected in the operational phase.

7.2                   Mitigation Measures

7.2.1             Construction noise and water quality mitigation measures proposed in the previous sections will be applicable to terrestrial and freshwater ecology. In addition, the following mitigation measures shall be carried out:

(a)    To minimize direct impact on the breeding activity of Black-collared Starling, before site clearance, the work area should be inspected by ecologist to confirm no active bird nest is present. If any active bird nest is identified, suitable size of buffer area should be established until the nest is abandoned.

(b)   Erection of hoarding, fencing or provision of clear demarcation of work zones to remind workers not to damage area outside the work boundary

7.2.2             With proper implementation of mitigation measures, un-acceptable residual impact is not expected. Detailed mitigation measures are listed out in the EMIS in Appendix A. Implementation status shall be audited through regular site inspection.

8.                    Landscape and Visual Impacts

8.1                   Introduction

8.1.1             The proposed development will generate some unavoidable residual landscape and visual impacts which are identified and addressed in the LVIA with the aim of avoiding (where practicable) and at the very least, minimising such impacts to within acceptable levels. The main impacts will be the loss of existing trees and the introduction of a new, larger bridge structure to the locality.  There are opportunities, during the project’s design, construction and operation stages, for incorporating mitigation measures which will contribute to reducing landscape and visual impacts. These include reducing the footprint of the construction phase impacts, existing tree protection and designing and implementing a new bridge which is visually integrated into the existing environment.

8.2                   Monitoring of Mitigation Measures during the Construction Phase

8.2.1             The Contractor shall employ a professionally qualified Registered Landscape Architect (RLA) to supervise and monitor the implementation of the landscape and visual mitigation measures during the construction and maintenance/establishment periods. This is necessary to ensure that all the recommended landscape and visual mitigation measures under Chapter 8 of the EIA are effectively implemented.

8.2.2             Prior to the commencement of construction works, a baseline monitoring report shall be prepared to check, record and re-confirm the status of the Landscape Resources and Landscape Character Areas within the works area.  The report shall review the proposed mitigation measures and assess their feasibility with reference to the operational requirements of the detailed project works.  Any potential conflicts between proposed mitigation measures and the proposed works shall be resolved at an early stage (prior to construction) and any necessary changes to the mitigation measures shall be incorporated into the detailed design.

8.2.3             During the construction phase, the implementation of the mitigation measures shall be monitored including minimisation of the works footprint, erection of appropriate screen hoardings, ensuring that those existing trees earmarked for retention on site or transplanting are protected, that compensatory planting works are correctly implemented and that appropriate building materials and finishes are incorporated. Site inspections by the appointed RLA shall be undertaken at monthly intervals to closely monitor all these aspects of the work. Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns regarding the implementation and effectiveness of mitigation measures highlighted.

8.3                   Monitoring of Mitigation Measures during the Operation Phase

8.3.1             The compensatory tree planting required to off-set the loss of existing trees should be checked during the 12-month Establishment Period by a professionally qualified Registered Landscape Architect (RLA) engaged by Contractor. The RLA should check the planting on a bi-monthly basis to ensure that it has become established and self-sustainable in order to provide long term landscape and visual mitigation as intended. The trees shall be managed and maintained by HyD until such time the trees are successfully handed over to Leisure and Cultural Services Department (LCSD) for future maintenance, subject to agreement with LCSD in the detailed design stage.

8.3.2             Hardworks elements including finishes and paint colours should also be monitored and checked that they are being maintained and are achieving their mitigation function.  These should be checked on a quarterly basis by the Contractor during the defects liability period and yearly thereafter by the future maintenance agent (Highways Department). No monitoring and audit under the EM&A programme is required.

8.4                   Mitigation Measures

8.4.1             Detailed landscape and visual mitigation measures are listed out in the EMIS in Appendix A. The implementation status and the effectiveness of these measures shall be audited through regular site inspection at the frequencies stated above.

9.                    site environmental audit

9.1                   Introduction

9.1.1             While a number of mitigation measures are proposed in the EIA report, regular site inspection is recommended for direct observation of the implementation progress to ensure that measures are properly implemented. Through a well-established action and reporting system, additional pollution control measures to identified environmental deficiency can be proposed and carried out at early stage. Site inspection is a useful way to enforce the environmental protection requirements onsite during construction.

9.2                   Site Inspection

9.2.1             The ET Leader will be responsible for the site environmental audit. He will design the environmental site inspection, deficiency and action reporting system and conduct regular site inspection. He should prepare a proposal on the site inspection and reporting methodology to the Contractor for agreement and to the ER for approval.

9.2.2             Weekly site inspection shall be performed by the ET within the site where environmental protection measures will be implemented and also offsite where the construction activities may directly or indirectly be impacted upon. The following shall be noted during the inspection:

(a)    environmental protection and pollution control mitigation measures proposed in the EIA, contract specification, EP and this Manual

(b)   works progress and programme

(c)    ongoing results of the EM&A programme

(d)   individual works methodology proposals (including associated pollution control measures)

(e)    relevant environmental protection and pollution control laws

(f)    previous site inspection results

9.2.3             The Contractor shall inform the ET on any update of all relevant information on the construction contract necessary for him to carry out the site inspection. After each site inspection, the ET shall submit an inspection report to the Contractor and the ER within 24 hours. It should include inspection result on any identification of environmental deficiency and corresponding mitigation recommendations for taking immediate rectification action. Follow up of identified problem from the previous inspection shall also be included. The Contractor shall report on any rectification actions after the site inspection in accordance to the procedures and timeframe proposed by the ET in the environmental site inspection, deficiency and action reporting system.

9.2.4             If significant environmental issue is identified, additional site inspection shall be performed. This may also be required upon receipt or during investigation of environmental complaint in accordance to the Action Plan for environmental monitoring and audit.

9.3                   Compliance with Legal and Contractual Requirements

9.3.1             The environmental protection and pollution control laws in Hong Kong and project contract stipulate environmental protection and pollution control requirement for construction activities.

9.3.2             As such, the Contractor should submit all work method statements for ER’s approval and ET Leader’s review on environmental compliance with the contractual requirements. Sufficient environmental protection and pollution control measures shall be demonstrated in the method statement.

9.3.3             The ET Leader should also check that the work progress and programme can comply with legal requirement on environmental terms and to prevent violation in the future.

9.3.4             The Contractor shall regularly copy relevant documents to the ET for checking, including but not limited to updated Work Progress Reports, updated Works Programme, application letters for different licence/permits under the environmental protection laws, and all valid licences/permits. The site diary shall also be available for inspection upon ET Leader’s request.

9.3.5             Should any non-compliance with the contractual and legislative requirements is identified after reviewing the documents, the ET should notify the ER and Contractor so that follow-up actions can be taken. He should also inform the ER and Contractor if the current status on licence/permit application and any environmental protection and pollution control preparation works may not meet the works programme or the construction work may lead to potential violation of environmental protection and pollution control requirements in due course.

9.3.6             The Contractor shall carry out remedial actions immediately upon receipt of ET’s advice. The ER shall check with the Contractor to ensure that appropriate actions has been taken accordingly and can satisfy the environmental protection and pollution control requirement.

9.4                   Environmental Complaints

9.4.1             Upon receipt of complaint, the ET shall be notified and investigation work shall be undertaken. He shall follow the procedures as listed below:

(a)    log complaint and date of receipt on to the complaint database

(b)   investigate the complaint to determine its validity, and to identify if the problem is caused by work activities

(c)    if the complaint is proved valid and due to works, formulate corresponding mitigation measures with the IEC

(d)   advise the Contractor on any rectification work required

(e)    evaluate the mitigation implementation progress and the updated situation

(f)    if the complaint is transferred from the EPD, submit an interim report on the complaint investigation and remediation progress to the EPD within the time frame assigned by the EPD

(g)   conduct additional monitoring and audit to verify the situation if necessary, and to determine any valid reason that the complaint will not recur

(h)   respond to the complainant by reporting the investigation result and follow-up actions taken (within the time frame set by the EPD if the complaint is made by the EPD)

(i)     record the complaint, investigation, the subsequent actions and results in the monthly EM&A reports

9.4.2             The Contractor and ER should provide necessary information and assistance to the ET for completing the investigation work. The Contractor shall implement any identified mitigation measures immediately and the ER shall ensure that the work has been carried out accordingly.

10.               reporting

10.1               Introduction

10.1.1         The ET shall prepare baseline monitoring report, monthly EM&A reports, quarterly EM&A report and final EM&A report. They shall be submitted to the EPD in paper and electronic formats in timely order.

10.2               Baseline Monitoring Report

10.2.1         Baseline monitoring of air quality, noise and water quality are proposed. The baseline monitoring report shall be submitted within 10 workings days after completion of the monitoring work. The recipients include the IEC, Contractor and ER. It should first be verified by the IEC before formal submission to the EPD. The ET shall liaise with the relevant parties on the number of copies required. The report format and monitoring data format shall be agreed with the EPD prior to submission. The baseline monitoring report generally includes but not limited to the following:

(a)    up to half a page executive summary;

(b)   brief project background information;

(c)    drawings showing locations of the baseline monitoring stations;

(d)   monitoring results (in both hard and soft copies) together with the following information:

a.       monitoring methodology;

b.      equipment used and calibration details;

c.       parameters monitored;

d.      monitoring locations (and depth);

e.       monitoring date, time, frequency and duration;

f.       quality assurance (QA) / quality control (QC) results and detection limits;

(e)    details of influencing factors, including:

a.       major activities, if any, being carried out on the site during the period;

b.      weather conditions during the period; and

c.       other factors which might affect results;

(f)    determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data;

(g)   revisions for inclusion in the EM&A Manual; and

(h)   comments, recommendations and conclusions.

10.3               EM&A Report

10.3.1         The ET Leader shall prepare monthly EM&A reports which summarize the result and findings in all EM&A work conducted in accordance to the Manual, such as monitoring and site inspection. It shall be submitted within 10 workings days of the end of each reporting month, with the first report due in the month after construction commences. The recipients include the IEC, Contractor, ER and the EPD. It should first be verified by the IEC before formal submission. The ET shall liaise with the relevant parties on the exact number of copies required and the report format for both paper and electronic format prior to submission of the first EM&A report.

10.3.2         As there may be changes in surrounding environment and nature of work in progress, the ET Leader shall review and update the number and location of monitoring stations and parameters to be monitored every 6 months or on as needed basis.

10.4               First EM&A Report

10.4.1         The first EM&A report generally includes but not limited to the following:

(a)    Executive summary (1-2 pages):

a.       breaches of Action and Limit levels;

b.      complaint log;

c.       notifications of any summons and successful prosecutions;

d.      reporting changes; and

e.       future key issues.

(b)   Basic project information:

a.       project organisation including key personnel contact names and telephone numbers;

b.      construction programme;

c.       management structure, and

d.      works undertaken during the month

(c)    Environmental status:

a.       works undertaken during the month with illustrations (such as location of works); and

b.      drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations (with co-ordinates of the monitoring locations)

(d)   A brief summary of EM&A requirements including:

a.       all monitoring parameters;

b.      environmental quality performance limits (Action and Limit levels);

c.       Event and Action Plans;

d.      environmental mitigation measures, as recommended in the project EIA Report; and

e.       environmental requirements in contract documents;

(e)    Implementation status:

a.       advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report;

(f)    Monitoring results (in both hard and diskette copies) together with the following information:

a.       monitoring methodology;

b.      equipment used and calibration details;

c.       parameters monitored;

d.      monitoring locations;

e.       monitoring date, time, frequency, and duration;

f.       weather conditions during the period;

g.      major activities being carried out on site during the period;

h.      any other factors which might affect the monitoring results; and

i.        QA/QC results and detection limits;

(g)   Report on non-compliance, complaints, and notifications of summons and successful prosecutions:

a.       record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

b.      record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

c.       record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

d.      review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

e.       description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance;

(h)   Others

a.       an account of the future key issues as reviewed from the works programme and work method statements;

b.      advice on the solid and liquid waste management status; and

c.       comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.

10.5               Subsequent EM&A Reports

10.5.1         Subsequent EM&A report generally includes but not limited to the following:

(a)    Executive summary (1 - 2 pages):

a.       breaches of Action and Limit levels;

b.      complaints log;

c.       notifications of any summons and successful prosecutions;

d.      reporting changes; and

e.       future key issues.

(b)   Basic project Information:

a.       project organization including key personnel contact names and telephone numbers;

b.      programme;

c.       management structure; and

d.      works undertaken during the month.

(c)    Environmental status:

a.       works undertaken during the month with illustrations (such as location of works etc.); and

b.      drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

(d)   Implementation status:

a.       advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA;

(e)    Monitoring results (in both hard and diskette copies) together with the following information:

a.       monitoring methodology;

b.      equipment used and calibration details;

c.       parameters monitored;

d.      monitoring locations;

e.       monitoring date, time, frequency, and duration;

f.       weather conditions during the period;

g.      major activities being carried out on site during the period;

h.      any other factors which might affect the monitoring results; and

i.        QA / QC results and detection limits.

(f)    Report on non-compliance, complaints, and notifications of summons and successful prosecutions:

a.       record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

b.      record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

c.       record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

d.      review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

e.       description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

(g)   Others

a.       an account of the future key issues as reviewed from the works programme and work method statements;

b.      advice on the solid and liquid waste management status; and

c.       comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.

(h)   Appendix

a.       Action and Limit levels;

b.      graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:

                                                              i.      major activities being carried out on site during the period;

                                                            ii.      weather conditions during the period; and

                                                          iii.      any other factors that might affect the monitoring results.

c.       monitoring schedule for the present and next reporting period;

d.      cumulative statistics on complaints, notifications of summons and successful prosecutions; and

e.       outstanding issues and deficiencies.

10.6               Quarterly EM&A Summary Reports

10.6.1         The quarterly EM&A summary report shall consist of around 5 pages (3 pages of text and tables and 2 pages of figures). It generally includes but not limited to the following:

(a)    up to half a page executive summary;

(b)   basic project information:

a.        a synopsis of the project organisation, programme;

b.      contacts of key management;

c.       proponents' contacts and any hotline telephone number for the public to make enquiries; and

d.      a synopsis of works undertaken during the quarter.

(c)    a brief summary of EM&A requirements:

a.       monitoring parameters;

b.      environmental quality performance limits (Action and Limit Levels); and

c.       environmental mitigation measures, as recommended in the EIA Report;

(d)   environmental status:

a.       a synopsis of work undertaken during the quarter;

b.      drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

(e)    implementation status:

a.          advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the EIA report, summarised in the updated implementation schedule;

(f)    graphical plots of the trends of monitored parameters over the past 4 months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against;

a.          the major activities being carried out on site during the period;

b.         weather conditions during the period; and

c.          any other factors which might affect the monitoring results;

(g)   advice on the solid and liquid waste management status;

(h)   summary of non-compliance

a.          a summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels);

b.         a brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;

c.          a summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;

d.         a summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

(i)     comments (e.g. effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions for the quarter; and

10.7               Final EM&A Report

10.7.1         A Final EM&A report shall be prepared summarizing the results and findings of the EM&A works throughout the construction period. It should be submitted within 14 working days after project completion. It generally includes but not limited to the following:

(a)    An executive summary;

(b)   Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

(c)    Basic project information:

a.       a synopsis of the project organisation;

b.      contacts of key management; and

c.       a synopsis of work undertaken during the entire construction period.

(d)   A brief summary of EM&A requirements:

a.       monitoring parameters;

b.      environmental quality performance limits (Action and Limit levels); and

c.       environmental mitigation measures, as recommended in the project EIA Report;

d.      Event and Action Plans.

(e)    A summary of the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA Report, summarised in the updated implementation schedule;

(f)    Graphical plots of the trends of monitored parameters over the construction period for representative monitoring stations, including the post-project monitoring annotated against:

a.       the major activities being carried out on site during the period;

b.      weather conditions during the period; and

c.       any other factors which might affect the monitoring results.

(g)   Summary of non-compliance:

a.       a summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

b.      a brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;

c.       a summary description of the actions taken in the event of non-compliance;

d.      a summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results;

(h)   A review of the validity of EIA predictions through comparison with the monitoring data and identification of shortcomings in EIA recommendations;

(i)     A review of the effectiveness and cost-effectiveness of the monitoring methodology

(j)     A review of the effectiveness and efficiency of the mitigation measures and of the performance of the overall EM&A programme;

(k)   Recommendations for improvement;

(l)     Evaluation on the return of environmental condition the baseline or predicted conditions in the EIA Report; and

(m) Conclusion on the environmental acceptability of the project.

10.8               Data Keeping

10.8.1         The ET shall keep the site documents (such as monitoring field records, site inspection forms etc.) in order and make available for inspection upon request. These documents do not form part of the EM&A report. The monitoring data should also be input into electronic format for checking upon request. All documents and data shall be kept for at least one year after completion of the construction contract.

10.9               Interim Notification of Environmental Quality Limit Exceedances

10.9.1         Should any exceedance in environmental quality performance limit be recorded, the ET Leader should immediately inform the IEC, ER, Contractor and EPD as appropriate in accordance to the Event and Action Plan. He should advise to the IEC, ER, Contractor and EPD the investigation result, remediation actions performed, effectiveness of the measures and proposal of further actions required. A sample interim notification template can be found in Appendix D.

11.               Conclusion

11.1               Introduction

11.1.1         This Manual lists out the EM&A requirements for environmental parameters air quality, noise, water quality, ecology, waste management and landscape and visual.

11.1.2         Environmental monitoring on air quality, noise and water quality are proposed and regular site inspection is recommended for all other parameters. Any non-compliance identified should be notified to all parties according to the Event and Action Plan and remediation measures should be carried out. Complaints received should be investigated and problems related to construction works should be solved till satisfaction. Baseline, monthly, quarterly and final EM&A reports shall be prepared to report on the continual monitoring results and evaluate the EM&A works).