Agreement No. CE31/2014 (CE)

Engineering Study for Police

Facilities in Kong Nga Po –

Feasibility Study

 

 

 

Environmental Impact Assessment Report

 

July 2016

 

 

Civil Engineering and Development Department

 

 

Contents

Chapter    Title                                                                                                                          

1                      Introduction

1.1                  Background

1.2                  Designated Projects under the EIA Ordinance

1.3                  Purpose of the EIA Study

1.4                  Objectives of the EIA Study

1.5                  Scope of the EIA Study

1.6                  Structure of the EIA Report

 

2                      Project Description

2.1                  Introduction

2.2                  Project Location and History

2.2.1               Project Location

2.2.2               Site History

2.3                  Project Scope

2.4                  Need of the Project

2.4.1               Police Facilities

2.4.2               Access Road to be Constructed or Improved

2.4.3               Benefits of the Project

2.5                  Consideration of “Without Project” Alternative

2.6                  Consideration of Alternative Siting and Layout

2.6.1               Development Siting

2.6.2               Development Layout Options

2.6.3               Access Options

2.7                  Consideration of Alternative Construction Methods

2.7.1               Site Formation and Road Works

2.7.2               Retaining Walls and Slope Works

2.7.3               Building Works

2.8                  Programme and Sequence of Works

2.9                  Concurrent Projects

 

3                      Air Quality Impact

3.1                  Introduction

3.2                  Environmental Legislation, Standards and Guidelines

3.3                  Project Site

3.4                  Study Area and Air Sensitive Receivers

3.5                  Identification of Pollution Sources and Key Pollutants

3.6                  Air Quality Modelling Methodology

3.7                  Odour Impact Assessment Methodology

3.8                  Evaluation and Assessment of Air Quality Impacts

3.9                  Mitigation of Adverse Environmental Impact

3.10                Evaluation of Residual Impact

3.11                Environmental Monitoring and Audit

3.11                Conclusion

 

 

4                     Noise Impact

4.1                  Introduction

4.2                  Relevant Legislation and Guidelines

4.3                  Description of the Noise Environment

4.4                  Construction Noise Impact Assessment

4.5                  Road Traffic Noise Impact Assessment

4.6                  Fixed Plant Noise Impact Assessment

4.7                  Helicopter Noise Impact Assessment

4.8                  Environmental Monitoring and Audit

4.9                  Conclusion

 

5                     Water Quality Impact

5.1                  Introduction

5.2                  Environmental Legislation, Standards and Guidelines

5.3                  Assessment Area, Water Sensitive Receivers and Background Conditions

5.4                  Assessment Methodology

5.5                  Identification and Evaluation of Water Quality Impacts

5.6                  Mitigation of Adverse Water Quality Impacts

5.7                  Evaluation of Cumulative and Residual Impact

5.8                  Environmental Monitoring and Audit

5.9                  Conclusion

 

6                      Sewerage and Sewage Treatment Implications

6.1                  Introduction

6.2                  Environmental Standards and Guidelines

6.3                  Assessment Methodology

6.4                  Existing Sewerage Conditions

6.5                  Estimation of Project-related Sewage Flows

6.6                  Evaluation of Sewerage Impacts

6.7                  Mitigation Measures to Minimise Adverse Sewerage Impacts

6.8                  Environmental Monitoring and Audit

6.9                  Conclusion

 

 

7                      Waste Management Implications

7.1                  Introduction

7.2                  Environmental Legislation, Standards and Guidelines

7.3                  Assessment Methodology

7.4                  Identification, Prediction and Evaluation of Environmental Impact

7.5                  Mitigation of Adverse Environmental Impact

7.6                  Evaluation of Residual Impact

7.7                  Environmental Monitoring and Audit Requirements

7.8                  Conclusion

 

 

8                      Land Contamination

8.1                  Introduction

8.2                  Environmental Legislation, Standards and Guidelines

8.3                  Assessment Methodology

8.4                  Identification of Potential Environmental Impacts

8.5                  Prediction and Evaluation of Environmental Impacts

8.6                  Recommendation of Mitigation Measures

8.7                  Evaluation of Residual Environmental Impacts

8.8                  Environmental Monitoring and Audit Requirements

8.9                  Conclusion

 

 

9                      Ecological Impact (Terrestrial and Aquatic)

9.1                  Introduction

9.2                  Environmental Legislation, Standards and Guidelines

9.3                  Study Area and Methodology

9.4                  Baseline Condition and Ecological Sensitive Receivers

9.5                  Evaluation of Ecological Importance of Habitats and Species

9.6                  Identification and Evaluation of Ecological Impacts

9.7                  Precautionary and Mitigation Measures

9.8                  Evaluation of Residual Ecological Impact

9.9                  Ecological Monitoring and Audit Requirements

9.10                Summary

9.11                References

 

10                   Landscape and Visual Impacts

10.1                Introduction

10.2                Landscape and Visual Legislation, Standard and Guidelines

10.3                Assessment Area

10.4                Methodology for Assessment of Landscape and Visual Impacts

10.5                Review of Relevant Guidelines on Landscape Strategies and Framework and Land Use Zoning

10.6                Existing Trees within the Project Boundary

10.7                Landscape Baseline Study

10.8                Visual Baseline Study

10.9                Option Assessment

10.10              Potential Sources of Landscape and Visual Impact

10.11              Landscape Impact Assessment

10.12              Visual Impact Assessment

10.13              Visual Enhancement and Landscape Mitigation Measures

10.14              Residual Landscape Impact

10.15              Residual Visual Impact

10.16              Cumulative Impact

10.17              Summary and Conclusion

 

11                   Impact of Hazard to Life

11.1                Introduction

11.2                Population Adopted For the Assessment

11.3                Modelling Approach and Calibration

11.4                Hazard Identification

11.5                Frequency Assessment

11.6                Consequence Assessment

11.7                Risk Assessment

11.8                Environmental Monitoring & Auditing

11.9                Conclusion

11.10              Reference

 

12                   Conclusion

12.1                General

12.2                Summary of Key Environmental Outcomes

12.3                Air Quality Impact

12.4                Noise Impact

12.5                Water Quality Impact

12.6                Sewerage and Sewage Treatment Implications

12.7                Waste Management Implications

12.8                Land Contamination

12.9                Ecological Impact

12.10              Landscape and Visual Impacts

12.11              Impact of Hazard to Life

12.12              Summary of Environmental Impacts

 

13                   Environmental Monitoring and Audit Requirements

13.1                General

13.2                Air Quality Impact

13.3                Noise Impact

13.4                Water Quality Impact

13.5                Sewerage and Sewage Treatment Implications

13.6                Waste Management Implications

13.7                Land Contamination

13.8                Ecological Impact

13.9                Landscape and Visual Impacts

13.10              Impact of Hazard to Life

 

14                   Project Implementation Schedule

14.1                General

List of Tables

Table 2.1:__ Comparison between the Refinement Options and Preliminary Layout

Table 2.2:__ Summary of Preliminary Development Parameters for Preferred Option

Table 2.3:__ Summary of Concurrent Project Considered for Cumulative Impacts

Table 3.1:__ Hong Kong Air Quality Objectives

Table 3.2:__ Air Quality Monitoring Data at Tai Po Station (Year 2011 – 2015)

Table 3.3:__ Background concentrations for 1-hour average NO2 and 10-minute average SO2 (Year 2011 – 2015)

at Tai Po Station 

Table 3.4:__ Background concentrations for 24-hour average RSP, FSP and SO2 (Year 2011 – 2015) at Tai Po Station

Table 3.5:__ Representative ASRs Identified for Air Quality Impact Assessment

Table 3.6:__ Summary of concurrent projects during construction and operation phase

Table 3.7:__ Key Dust Emission Factors Adopted in the Assessment

Table 3.8:__ Vehicle Classification in the EMFAC-HK Model

Table 3.9:__ Operational Emissions of the OWTF2 CHP

Table 3.10:_ Operational Emissions of the OWTF2 odour treatment units            

Table 3.11:_ Operational Emission of the OWTF2 flare

Table 3.12:_ Summary of Years 2015 and 2020 Hong Kong Emission Inventory for the PATH Model           

Table 3.13:_ Locations of air sample collection for odour testing            

Table 3.14:_ Odour patrol and sampling dates and locations

Table 3.15: Summary of Predicted Cumulative Maximum Hourly Average TSP Concentration and 10th Highest Daily

Average RSP and FSP Concentrations (Tier 1 Unmitigated and Mitigated            

Table 3.16:_ Summary of Predicted Cumulative Annual Average RSP and FSP Concentrations (Unmitigated and Mitigated)

Table 3.17:_ Summary of Predicted Cumulative Modelling Results during Operation Phase           

Table 3.18:_ Summary of historical odour complaints related to the existing pig farms and firing ranges

Table 3.19:_ Summary of odour testing results

Table 4.1:__ Noise Standards for Daytime Construction Activities

Table 4.2:__ Relevant Road Traffic Noise Standards for Planning Purposes

Table 4.3:__ Area Sensitivity Rating               

Table 4.4:__ Acceptable Noise Level for Fixed Noise Source

Table 4.5: __ Measured Background Noise Levels

Table 4.6:__ Representative Construction Noise Sensitive Receivers Identified for the Assessment

Table 4.7:__ Summary of Concurrent Projects

Table 4.8:__ Unmitigated Construction Airborne Noise Impact

Table 4.9:__ Quieter PME Recommended for Adoption during the Construction Phase of the Project

Table 4.10:_ Noise Mitigation Measures for Certain PME during the Construction Phase of the Project        

Table 4.11:_ Mitigated Construction Airborne Noise Impact

Table 4.12:_ Mitigated Cumulative Construction Airborne Noise Impact

Table 4.13:_ Representative Road Traffic Noise Sensitive Receivers Identified for the Assessment

Table 4.14:_ Unmitigated Road Traffic Noise Impact in Year 2038

Table 4.15:_ Predicted Noise Impacts quantified by Number of Dwellings (Unmitigated)

Table 4.16:_ Representative Fixed Noise Sensitive Receivers Identified for the Assessment

Table 4.17:_ Noise Criteria of Planned Fixed Noise Sources

Table 4.18:_ Measurement Results for Vehicle Sirens / Simulation Shooting

Table 4.19:_ Measurement Results for Normal Driving

Table 4.20:_ Measurement Results on Tyre Noise, Skidding Noise and Braking Noise

Table 4.21:_ Summary of Fixed Noise Sources

Table 4.22:_ Maximum Permissible SWLs of the Fixed Plant

Table 4.23:_ Number of Shots in 30-minute Period during a Training Day

Table 4.24:_ Predicted Fixed Noise Impact from Planned Noise Sources

Table 4.25:_ Cumulative Fixed Noise Impact from Existing and Planned Noise Sources

Table 4.26:_ HKPF Day-time Training

Table 4.27:_ Frequency of using Lo Wu Range Helicopter Landing Site

Table 4.28:_ Representative Helicopter Noise Sensitive Receivers Identified for the Assessment

Table 4.29:_ Helicopter Noise Data (with Lateral Movements)

Table 4.30:_ Helicopter Noise Data (without Lateral Movements)

Table 4.31:_ Summary of Different Operation Modes

Table 4.32:_ Predicted Helicopter Noise Impact at All Representative NSRs

Table 5.1:__ Water Quality Objectives for Deep Bay WCZ

Table 5.2:__ Annual Summary of Water Quality Data for EPD Monitoring Stations IN1, IN2 and GR1 (2013)

Table 5.3:__ Water Quality Data for Nearby Water Sensitive Receivers (from 15 April 2013)

Table 6.1:__ Peaking Factors Adopted to Estimate Project-related Sewage Flows

Table 6.2:__ Sewage Flows for the Project

Table 6.3:__ Summary of Sewage Flows generated by the Project to SWHSTW

Table 7.1:__ Summary of Waste Arising during Construction Phase

Table 7.2:__ Estimation of General Refuse Generation during Operation Phase

Table 8.1:__ Review of Aerial Photographs

Table 8.2:__ Summary of Potential Land Contamination Impact            

Table 9.1:__ Ecological Field Survey Schedule

Table 9.2:__ Aquatic habitats of the sampling points

Table 9.3:__ Habitats Present in the Study Area (excluding the Project Site)

Table 9.4:__ Habitats Present in the Project Site

Table 9.5:__ Avifauna species of conservation interest recorded within Study Area

Table 9.6:__ Nest numbers, species type and plant species used as nesting substrate at Man Kam To Road Egretry

(MKT Egretry) and its satellite (MKT Satellite Egretry) recorded between April and July 2015          

Table 9.7:__ Mammal species of conservation interest recorded within the Study Area

Table 9.8:__ Herpetofauna species of conservation interest recorded within the Study Area           

Table 9.9:__ Butterfly species of conservation interest recorded within the Study Area

Table 9.10:_ Ecological Evaluation of Plantation

Table 9.11:_ Ecological Evaluation of Orchard            

Table 9.12: _ Ecological Evaluation of Shrubland

Table 9.13:_ Ecological Evaluation of Secondary Woodland

Table 9.14:_ Ecological Evaluation of Grassland/Shrubland

Table 9.15:_ Ecological Evaluation of Grassland

Table 9.16:_ Ecological Evaluation of Seasonally Wet Grassland          

Table 9.17:_ Ecological Evaluation of Agricultural Land

Table 9.18:_ Ecological Evaluation of Watercourse   

Table 9.19:_ Ecological Evaluation of Channelised Watercourse           

Table 9.20:_ Ecological Evaluation of Pond 

Table 9.21:_ Ecological Evaluation of Developed Area             

Table 9.22:_ Ecological Evaluation of Flora Species of Conservation Interest

Table 9.23:_ Ecological Evaluation of Fauna Species of Conservation Interest recorded during Field Survey within

the Project Site    

Table 9.24:_ Ecological Evaluation of Fauna Species of Conservation Interest recorded during Field Survey within

the Study Area (excluding the Project Site)   

Table 9.25:_ Ecological Evaluation of Fauna Species of Conservation Interest recorded within

the Study Area from Literature Review

Table 9.26:_ Summary of Habitat Loss within the Project Site in the worst case scenario 

Table 9.27:_ Evaluation of Habitat Loss        

Table 9.28:_ Direct Impact on Flora Species of Conservation Interest   

Table 9.29:_ Evaluation of Disturbance Impact on Fauna Species of Conservation Interest             

Table 9.30:_ Evaluation of Disturbance Impact on Man Kam To Egretry               

Table 9.31:_ Evaluation of Reduction of Ecological Carrying Capacity  

Table 9.32:_ Evaluation of Indirect Ecological Impacts of Potential Changes in Water Quality as a result of Surface Runoff

Table 9.33:_ Evaluation of Disturbance Impact during Operation Phase               

Table 10.1:   Impact significance – relationship between sensitivity and magnitude of change       

Table 10.2:   Impact significance – relationship between sensitivity and magnitude of change       

Table 10.3:   Summary of existing trees within the Project Site (in order of decreasing abundance)

Table 10.4:  Summary of existing trees within and adjacent to the Project boundary along Kong Nga Po Road

(in order of decreasing abundance)               

Table 10.5:_ Sensitivity of Identified Landscape Resources

Table 10.6:_ Sensitivity of Identified Landscape Character Areas

Table 10.7:_ Sensitivity of Visually Sensitive Receivers            

Table 10.8:_ Potential Landscape Impacts of Individual Refinement Layout Options         

Table 10.9:_ Potential Landscape Impacts of Access Options

Table 10.10: Magnitude of Change in Views for VSRs_            

Table 10.11: Proposed Visual Enhancement and Landscape Mitigation Measures – Construction Phase

Table 10.12: Proposed Visual Enhancement and Landscape Mitigation Measures – Operation Phase

Table 10.13: Indicative Mitigation Planting

Table 10.14: Significance of Landscape Impacts in Construction and Operation Phases

Table 10.15: Significance of Visual Impacts in Construction and Operation Phases

Table 11 1:_ Meteorological Data (1996)

Table 11 2:_ Meteorological Data (2011-2014 average data)

Table 11 3:_ Population within the proposed site

Table 11 4:_ Latest Schedule of OWTF2

Table 11 5:_ The change of major population group in consultation zone

Table 11 6:_ Definition of Time periods

Table 11 7:_ Traffic Variation at Different Time Periods at Major Traffic Stations (ATC 2014)

Table 11 8:_ Physical Properties of petrol and diesel

Table 11 9:_ Properties of kerosene (Jet A1)

Table 11 10: Event frequencies with Implementation of Previous Identified Risk Mitigation Measures

Table 11 11: Accident rate summary from IATA report 2014    

Table 11 12: Percentage of accidents related to Takeoff/climb and approach/landing phase of a flight

Table 11 13: Air Traffic Movements at HKIA 

Table 11 14: Helicopter crash frequencies for different equipments in OWTF2

Table 11 15: Serious and Fatal Vehicle involvements for Medium /Heavy Goods Vehicles

Table 11 16: Spontaneous failure frequencies as adopted from OWTF2 EIA report

Table 11 17: Assumptions used in FTA

Table 11 18: Result of Fault Tree Analysis    

Table 11 19: Ignition and Explosion Probabilities for Biogas Releases  

Table 11 20: Ignition Probability of petrol

Table 11 21: Release scenarios to be included in this HA

Table 11 22: Chlorine toxicity relationship

Table 11 23: Cloud Height Adopted for Release Events

Table 11 24: End Point Criteria for explosion risk

Table 11 25: Consequence distances adopted from OWTF2 EIA report

Table 11 26: Maximum pool radius for an un-bunded pool fire in DG store

Table 11 27: Consequence distances for the hazardous scenarios of kerosene road tanker

Table 11 28: Consequence distances for the hazardous scenarios of petrol/diesel filling station

Table 11 29: Summary of uncertainty analysis

Table 11 30: Summary of uncertainty analysis for OWTF2

Table 11 31: Summary of uncertainty analysis for proposed police facility

Table 12.1:   Summary of Environmental Impacts of Police Facilities in Kong Nga Po

Table 14.1:   Implementation Schedule of Recommended Mitigation Measures 

List of Figures

 

Figure 2.1              Project Layout

Figure 2.1a            Indicative Police Facilities Layout Arrangement

Figure 2.2              Existing Police Facilities to be Relocated

Figure 2.3              Preliminary Layout

Figure 2.4              Refinement Layout – Option 1

Figure 2.5              Refinement Layout – Option 2

Figure 2.6              Refinement Layout – Option 3

Figure 2.7              Access Options

Figure 2.8              Location of Concurrent Projects


 

 

Figure 3.1              Location of Air Sensitive Receivers Outside Project Site

Figure 3.2              Location of Air Sensitive Receivers Within Project Site

Figure 3.3              Relevant ASRs Located at Relevant PATH Grids

Figure 3.4              Location of Potential Construction Dust Emission Area Sources (Tier 1)

Figure 3.5              Location of Potential Construction Dust Emission Line Sources (Tier 1)

Figure 3.6              Location of Potential Dust Emission Sources from Concurrent Projects

Figure 3.7              (Not used)

Figure 3.8              (Not used)

Figure 3.9              (Not used)

Figure 3.10           Road Links within 500m Assessment Area

Figure 3.11           Location of ISCST3 Emission Sources

Figure 3.12           Location of Air Sampling Points

Figure 3.13           (Not used)

Figure 3.14           Cumulative Result – Contour of Tier 1 Hourly TSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Unmitigated)

Figure 3.15           Cumulative Result – Contour of Tier 1 10th Maximum Daily RSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Unmitigated)

Figure 3.16           Cumulative Result – Contour of Tier 1 10th Maximum Daily FSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Unmitigated)

Figure 3.17           Cumulative Result – Contour of Tier 1 Hourly TSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Mitigated)

Figure 3.18           Cumulative Result – Contour of Tier 1 10th Maximum Daily RSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Mitigated)

Figure 3.19           (Not used)

Figure 3.20           (Not used)

Figure 3.21           (Not used)

Figure 3.22           (Not used)

Figure 3.23           (Not used)

Figure 3.24           Cumulative Result – Contour of Annual RSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Unmitigated)

Figure 3.25           Cumulative Result – Contour of Annual FSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Unmitigated)

Figure 3.26           Cumulative Result – Contour of Annual RSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Mitigated)

Figure 3.27           Cumulative Result – Contour of Annual FSP Concentration (µg/m3) at 1.5m above ground during Construction Phase (Mitigated)

Figure 3.28           (Not used)

Figure 3.29           Cumulative Result– Contour of 19th Maximum Hourly NO2 Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP of OWTF2)

Figure 3.30           Cumulative Result– Contour of 19th Maximum Hourly NO2 Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare of OWTF2)

Figure 3.31           Cumulative Result– Contour of Annual NO2 Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP of OWTF2)

Figure 3.32           Cumulative Result– Contour of Annual NO2 Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare of OWTF2)

Figure 3.33           Cumulative Result– Contour of 10th Maximum Daily RSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP and Odour Treatment Unit of OWTF2)

Figure 3.34           Cumulative Result– Contour of 10th Maximum Daily RSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare and Odour Treatment Unit of OWTF2)

Figure 3.35           Cumulative Result– Contour of Annual RSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP and Odour Treatment Unit of OWTF2)

Figure 3.36           Cumulative Result– Contour of Annual RSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare and Odour Treatment Unit of OWTF2)

Figure 3.37           Cumulative Result– Contour of 10th Maximum Daily FSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP and Odour Treatment Unit of OWTF2)

Figure 3.38           Cumulative Result– Contour of 10th Maximum Daily FSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare and Odour Treatment Unit of OWTF2) 

Figure 3.39           Cumulative Result– Contour of Annual FSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With CHP and Odour Treatment Unit of OWTF2)

Figure 3.40           Cumulative Result– Contour of Annual FSP Concentration (µg/m3) at 1.5m above ground during Operational Phase (With Flare and Odour Treatment Unit of OWTF2) 

Figure 3.41           Odour Testing Results and Wind Directions on Two Typical Hot Days

Figure 3.42           Topography of Existing Condition and the Project Development

Figure 3.43           Cross-Section of Topography of Existing Condition and the Project Development


 

Figure 4.1             Noise Impact Assessment Area and Locations of Representative Noise Sensitive Receivers (Fixed Noise)

Figure 4.2             Noise Impact Assessment Area and Locations of Representative Noise Sensitive Receivers (Construction Noise)

Figure 4.3             Photos of Representative Noise Sensitive Receivers (NSRs)

Figure 4.4             Schematic Configuration of Movable Noise Barrier for PME

Figure 4.5             Schematic Configuration of Full Noise Enclosure for PME

Figure 4.6             Noise Impact Assessment Area and Locations of Representative Noise Sensitive Receivers (Road Traffic Noise)

Figure 4.7             Locations of Proposed Fixed Plant Noise Sources

Figure 4.8             Noise Impact Assessment Area and Locations of Representative Noise Sensitive Receivers (Helicopter Noise)

Figure 4.9             Noise Contours for Helicopter Noise Impacts (Day-time – Operation Mode 1-8)


Figure 5.1             Water Quality Impact Assessment Area and Water Sensitive Receivers

Figure 5.2             Indicative Drainage Routing during Construction Phase

 

 

Figure 6.1             Existing Sewerage System

Figure 6.2             Proposed Sewerage System

 

 

Figure 8.1             Location of Site Photographs

Figure 9.1             Project Site, Assessment Area, Survey Transect and Sampling Location

Figure 9.2a-d        Habitat Map and Species of Conservation Significance

Figure 9.3             Indicative Extent of Egretry

 

 

Figure 10-01         Aerial Photograph

Figure 10-02         Future Planning Context

Figure 10-03         Landscape Resources Plan

Figure 10-04         Landscape Resource Photographs

Figure 10-05         Landscape Resource Photographs

Figure 10-06         Landscape Character Area Plan

Figure 10-07         Landscape Character Area Photographs

Figure 10-08         Landscape Character Area Photographs

Figure 10-09         Landscape Character Area Photographs 

Figure 10-10         Landscape Character Area Photographs

Figure 10-11         Visual Envelope and Visually Sensitive Receivers

Figure 10-12         Visual Envelope and Visually Sensitive Receivers

Figure 10-13         Existing VSR Views

Figure 10-14         Existing VSR Views

Figure 10-15         Existing VSR Views

Figure 10-16         Existing VSR Views

Figure 10-17         Existing VSR Views

Figure 10-18         Existing VSR Views

Figure 10-19         Preliminary Landscape Master Plan 

Figure 10-20         Preliminary Landscape Master Plan

Figure 10-21         Landscape and Visual Mitigation Measures – Plan

Figure 10-22         Landscape and Visual Mitigation Measures – Plan

Figure 10-23         Landscape and Visual Mitigation Measures – Plan

Figure 10-24         Landscape and Visual Mitigation Measures – Oblique Aerial View

Figure 10-25         Landscape and Visual Mitigation Measures – Sections

Figure 10-26         Landscape and Visual Mitigation Measures – Sections

Figure 10-27         Landscape and Visual Mitigation Measures – Sections

Figure 10-28         Landscape and Visual Mitigation Measures – Sections

Figure 10-29         Landscape and Visual Mitigation Measures – Sections

Figure 10-30         Landscape and Visual Mitigation Measures – Sections

Figure 10-31         Landscape and Visual Mitigation Measures – Sections

Figure 10-32         Landscape and Visual Mitigation Measures – Sections

Figure 10-33         Landscape and Visual Mitigation Measures – Sections

Figure 10-34         Landscape and Visual Mitigation Measures – Sections

Figure 10-35         Residual Impacts on Landscape Resources during Construction and Operation

Figure 10-36         Residual Impacts on Landscape Character Areas during Construction and Operation

Figure 10-37         Residual Visual Impacts during Construction and Operation

Figure 10-38         Vantage Points for Photomontages

Figure 10-39         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-40         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-41         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-42         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-43         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-44         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-45         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-46         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-47         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-48         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-49         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-50         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-51         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-52         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-53         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-54         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-55         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-56         Landscape and Visual Mitigation Measures – Photomontage

Figure 10-57        Proposed Viaduct Section along Improved Kong Nga Po Road

 

Figure 11.1           Detailed location arrangement inside the proposed site

Figure 11.2           QRA Flow Chart  

Figure 11.3           Societal Risk Guidelines   

Figure 11.4           Road Markings within SSWTW

Figure 11.5           Barrier in the north-western corner of SSWTW

Figure 11.6           Wind rose adopted in this study (2011-2014 average)

Figure 11.7           Padding material to prevent bouncing back of ricochet

Figure 11.8           Fuel road tanker transport route to be assessed

Figure 11.9           Aircraft Crash Coordinate System

Figure 11.10         Distance between proposed helipad and OWTF2 storage        

Figure 11.11         Relative Position of non-fuel gas facilities within the site

List of Appendices

 

Appendix 2.1        Tentative Construction Programme

Appendix 3.1        Calculation of Dust Suppression Efficiency

Appendix 3.2        Estimation of Particle Size Distribution

Appendix 3.3        Details of Dust Emission Sources for 1-hour TSP, Daily RSP and Daily FSP (Tier 1)

Appendix 3.4        Estimation of Active Area Percentages for Key Construction Activities (Annual)

Appendix 3.5        (Not used)

Appendix 3.6        Data Input file for Hourly TSP, Daily RSP and Daily FSP (Tier 1)

Appendix 3.7        (Not used)

Appendix 3.8        Details of Dust Emission Sources for Annual RSP and Annual FSP

Appendix 3.9        Data Input file for Annual RSP and Annual FSP

Appendix 3.10      Letter from Transport Department regarding Traffic Forecast Data

Appendix 3.11      24-Hour Traffic Pattern

Appendix 3.12      Vehicle Age Distribution in Base Year 2010

Appendix 3.13      Road Profile of Road Links within 500m Study Area

Appendix 3.14      24-hour VKT values for All Vehicle Classes in each of the Model years 2023, 2028, 2033 and 2038

Appendix 3.15      Trip Estimation

Appendix 3.16      24-hour Variations of Annual Averages of Temperature and Relative Humidity

Appendix 3.17      24-hour Speed Fractions

Appendix 3.18      Calculation of Emission Factors for Each Model year

Appendix 3.19      Composition Emission Factor in Year 2023

Appendix 3.20      Letter from EPD regarding Chimney

Appendix 3.21      Model Parameters for ISCST3

Appendix 3.22      (Not used)

Appendix 3.23      Detail Odour Patrol and Testing Report

Appendix 3.24      Tier 1 Hourly TSP, Daily RSP and Daily FSP Screening Results for Unmitigated and Mitigated Scenarios

Appendix 3.25      (Not used)

Appendix 3.26      Annual RSP and FSP Results for Unmitigated and Mitigated Scenarios

Appendix 3.27      (Not Used)

Appendix 3.28      Cumulative Results for NO2, RSP and FSP during Operational Phase (for Year 2023 Vehicular and Chimney Emission and Year 2020 Background Concentration)

Appendix 4.1        Unmitigated Construction Plant Inventory and Noise Impact Assessment

Appendix 4.2        Mitigated Construction Plant Inventory and Noise Impact Assessment

Appendix 4.3        Extent of Proposed Project Road

Appendix 4.4        Letter from Transport Department regarding Traffic Forecast Data

Appendix 4.5        Traffic Forecast Data and Key Plan for Road Traffic Noise Impact Assessment

Appendix 4.6        Predicted Road Traffic Noise Levels for Unmitigated Scenario (Year 2038)

Appendix 4.7        Correspondence between Mott MacDonald and HKPF

Appendix 4.8a      Gunshot Noise Measurement Results

Appendix 4.8b      Fixed Noise Sources Impact Assessment

Appendix 4.9        Correspondence between Mott MacDonald and GFS

Appendix 4.10      Helicopter Noise Impact Assessment

Appendix 4.11      Literature Review of Overseas / International Noise Criteria for Emergency Helicopter Operations during Evening and Night-time Periods

Appendix 6.1        Proposed Sewer Pipeline Design

Appendix 8.1        Representative Historical Aerial Photographs

Appendix 8.2        Responses from Government Departments on Relevant Information

Appendix 8.3        Site Photographs

Appendix 9.1        Plates

Appendix 9.2        List of Flora recorded within the Study Area

Appendix 9.3        List of Fauna recorded within the Study Area

Appendix 10.1      Broad-Brush Tree Survey

Appendix 11.1      Some Information Extracted from the Reassessment Study

Appendix 11.2      Kerosene Transport Route

Appendix 11.3      Photos of Kerosene Truck used by GFS

Appendix 11.4      Fault Tree Analysis

Appendix 11.5      Event Tree Analysis in OWTF2

Appendix 11.6      Population Considered in this Assessment

Appendix 11.7      Individual Risk Results

Appendix 11.8      Societal Risk Results

Appendix 11.9      Cumulative Risk Assessment Result


 

Abbreviations

 

ADWF

Average Dry Weather Flows

AFCD

Agriculture, Fisheries and Conservation Department

ALARP

As Low As Reasonably Practicable

ANLs

Acceptable Noise Levels

APCO

Air Pollution Control Ordinance

APR

Approach

AQOs

Air Quality Objectives

AQUALINE

 

ArchSD

Architectural Services Department

ASR

Air Sensitive Receiver (Air quality)

Area Sensitive Rating (Noise)

ATC

Annual Traffic Census

BCP

Border Crossing Point

BLEVE

Boiling Liquid Expanding Vapour Explosion

BOD5

5-Day Biochemical Oxygen Demand

C&D

Construction and Demolition

CAP

Contamination Assessment Plan

CAR

Contamination Assessment Report

CBD

United Nations Convention on Biological Diversity

CEDD

Civil Engineering and Development Department

CFA

Court of Final Appeal

CFD

Computational Fluid Dynamics

CHP

Combined Heat and Power

CIA

Chemical Industry Association

CITES

Convention on International Trade in Endangered Species of Wild Fauna and Flora

CNL

Corrected Noise Level

CNP

Construction Noise Permit

CO

Carbon Monoxide

COD

Chemical Oxygen Demand

CPLD

Committee on Planning and Land Department

CRTN

Calculation of Road Traffic Noise

C&SD

Census and Statistics Department

CWPs

Chemical Waste Producers

CZ

Consultation Zone

DC

Distance Attenuation

DG

Dangerous Goods

DNV

Det Norske Veritas

DO

Dissolved Oxygen

DRIFT

Dense Releases Involving Flammables or Toxics

E.coli

Escherichia coli

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EIAO-TM

Technical Memorandum on Environmental Impact Assessment Process

EM&A

Environmental Monitoring and Audit

EMSD

Electrical and Mechanical Services Department

EPD

Environmental Protection Department

ETA

Event Tree Analysis

EU

European Union

EV

Electric Vehicle

FC

Façade Correction

FCA

Frontier Closed Area

FDM

Fugitive Dust Model

FLN

Fanling North

FLN NDA

Fanling North New Development Area

FN

Frequency/Number of Fatality

FNFSR

Fanling North Freshwater Service Reservoir

FRP

Fire Resistant Rating

FSD

Fire Services Department

FSP

Fine Suspended Particulates

FTA

Fault Tree Analysis

GB

Green Belt

GESF

Guidelines for Estimated Sewage Flow

GFS

Government Flying Service

GMP

Greening Master Plan

GMPNET

Greening Master Plan for Northwest New Territories

GW-TM

Technical Memorandum on Noise from Construction Work other than Percussive Piling

HA

Hazard Assessment

HAZOP

Hazard and Operability Study

HKBWS

Hong Kong Bird Watching Society

HKIA

Hong Kong International Airport

HKO

Hong Kong Observatory

HKPF

Hong Kong Police Force

HKPSG

Hong Kong Planning Standards and Guidelines

HKSAR

Hong Kong Special Administrative Region

HOKLAS

Hong Kong Laboratory Accreditation Scheme

HQ

Head Quarter

HSE

Health and Safety Executive

HyD

Highways Department

IATA

International Air Transport Association

ICAO

International Civil Aviation Organization

ICL

Initial Climb

IFs

Influencing Factors

I/M

Inspection and Maintenance

IND-TM

Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites

ISCST3

Industrial Source Complex – Short Term Version 3

JSP

Joint Service Publication

KNP

Kong Nga Po

KTN

Kwu Tung North

LCAs

Landscape Character Areas

LD

Lethal Dose

LIA

Landscape Impact Assessment

LND

Landing

LPG

Liquefied Petroleum Gas

LRs

Landscape Resources

LWFR

Lo Wu Firing Range

MHIDAS

Major Hazard Incident Data Service

MMIS

Modified Mercalli Intensity Scale

MTLFR

Ma Tso Lung Firing Range

NCO

Noise Control Ordnance

NT North

New Territories North

NTNE

New Territories North East

NENT NDA

North East New Territories New Development Area

NO2

Nitrogen Dioxide

NOx

Nitrogen Oxides

NOISE

National Organization to Insure a Sound-controlled Environment

NRMM

Non-road mobile machinery

NSR

Noise Sensitive Receiver

O3

Ozone

OLM

Ozone Limiting Method

OVT

Old and Valuable Tree

OWTF2

Organic Waste Treatment Facilities Phase 2

OZP

Outline Zoning Plan

PATH

Pollutants in the Atmosphere and their Transport over Hong Kong

PC

Private Cars

Pcif

Catchment Inflow Factor

PD&TTF

Police Driving and Traffic Training Facilities

PDAs

Potential Development Areas

PFC

Public Fill Committee

PFRFs

Public Fill Reception Facilities

PHI

Potentially Hazardous Installation

PME

Powered Mechanical Equipment

PNL

Predicted Noise Level

PRC

People’s Republic of China

PRD

Pearl River Delta

PRDEZ

Pearl River Delta Economic Zone

PS

Pumping Station

PTF

Proposed Police Training Facility

PTU

Police Tactical Unit

QRA

Quantitative Risk Assessment

RAP

Remediation Action Plan

RBRGs

Risk-based Remediation Goals

RC

Reinforced Concrete

RCV

Refuse Collection Vehicle

RR

Remediation Report

RSP

Respirable Suspended Particulates

TD

Transport Department

TPDM

Transport Planning and Design Manual

TSP

Total Suspended Particulate

SE

South-east

SBF

Second Boundary Fence

SIL(E)

South Island Line (East)

SPL

Sound Pressure Level

SO2

Sulfur Dioxide

SS

Suspended Solids

SSSI

Site of Special Scientific Interest

SULFR

San Uk Ling Firing Range

SSWTW

Sheung Shui Water Treatment Works

SWHSTW

Shek Wu Hui Sewage Treatment Works

SWL

Sound Power Level

TM-DSS

Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems

TOF

Takeoff

UFF

Unit Flow Factors

USEPA

US Environmental Protection Agency

US FAA

US Federal Aviation Agency

VE

Visual Envelope

VOCs

Volatile Organic Compounds

VKT

Vehicle Kilometre Travelled

VSRs

Visual Sensitive Receivers

WCZs

Water Control Zones

WDO

Waste Disposal Ordinance

WMP

Waste Management Plan

WPCO

Water Pollution Control Ordinance

WQOs

Water Quality Objectives

WSD

Water Supplies Department

WTF

Weapons Training Facilities

VPs

Vantage Points

ZVIs

Zones of Visual Influence