Page
6.2 Environmental Legislation, Standards and Criteria
6.4 Description of the Project Area
6.5 Identification of Potential Land Contamination Concern
6.6 Prediction and Evaluation of Environmental Impacts
6.7 Mitigation of Adverse Environmental Impacts
6.8 Evaluation of Residual Impacts
LIST OF TABLES
Table
6.1 Summary of Hotspots within STSTW
LIST OF FIGURES
60334056/EIA/6.01 Project
Location and Works Area
60334056/EIA/6.03 General
Site Layout of Existing STSTW and Proposed Sampling Locations
LIST OF APPENDICES
Appendix
6.01 Contamination Assessment
Plan (CAP)
¡P Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)
¡P Guidance Note for Contaminated Land Assessment and Remediation (Guidance Note)
The Guidance Note sets out the requirements for proper assessment and management of potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling stations), gas works, power plants, shipyards / boatyards, chemical manufacturing / processing plants, steel mills / metal workshops, car repairing / dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be conducted and analysed and suggests practical remedial measures that can be adopted for the clean-up of contaminated sites.
¡P Practice Guide for Investigation and Remediation of Contaminated Land (Practice Guide)
This guide outlines typical investigation methods and remediation strategies for the range of potential contaminants typically encountered in Hong Kong.
¡P Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (Guidance Manual)
The Guidance Manual introduces the risk based approach in land contamination assessment and present instructions for comparison of soil and groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary.
¡P Relevant ground investigation reports from CEDD civil engineering library;
¡P Hong Kong Geological Survey Map (Series HGM20) ¡V Sheet No. 7 (1:20,000);
¡P Aerial photographs and topographic maps;
¡P Records (if any) on dangerous goods, chemical wastes, chemical spillage/leakage and fire incidents from the identified potentially contaminated sites from EPD or Fire Services Department (FSD); and
¡P AECOM, Final Report under Agreement No. CE 43/2011 (DS) ¡§Relocation of Sha Tin Sewage Treatment Works to Caverns ¡V Feasibility Study, May 2014.
(i) Existing STSTW
The area included the existing STSTW but excluded WSD Salt Water Pumping Station to the north of STSTW which is not part of the Project Area (refer to Figure No. 60334056/EIA/6.02).
(ii) Part of Existing Vehicle Detention Centre (VDC) and its surrounding areas
The area comprises part of existing VDC (i.e. the temporary works area on Area 73) and its surrounding areas (refer to as ¡¥Area A¡¦). The areas are shown in Figure No. 60334056/EIA/6.02. Surrounding areas of VDC mainly include a small section of A Kung Kok Street near the entrance of THEES portal, vacant area adjacent to VDC, landscape area south of VDC (between Ma On Shan Road and A Kung Kok Road), and cycling tracks and footpaths northeast of VDC.
(iii) Nui Po Shan North
The area mainly covered the northern portion of existing Nui Po Shan, bounded to the north by Mui Tsz Lam Road and northwest by A Kung Kok Street, including the proposed A Kung Kok Shan Road surface magazine site (refer to Figure No. 60334056/EIA/6.02).
Table 6.1 Summary
of Hotspots within STSTW
Location (Site Area) |
Concerned Area (approx. area) |
Summary of Site Appraisal |
Necessity and Rationale for Intrusive Site
Investigation (SI) |
Proposed Borehole ID* |
Existing STSTW (280,000m2) (Inspection Date: 7 Nov 2014 & 28 Jan 2015) |
Chemical Wastes Store (26 m2) |
- Empty chemical containers
are stored on shelf in the Chemical Waste Store. The floor of the store is
concrete paved and were observed in good condition without stain. - Chemicals observed
included spent sulfuric acid, nitric acid and alkali. |
1 sampling location proposed. COCs includes metals, VOCs, SVOCs and PCRs. |
ENV-BH01 |
|
Dangerous Goods (DG) Store (28m2) |
- No report of spillage or
leakage of dangerous goods was reported from FSD records - The floor of the DG Store
is concrete paved and was observed in good condition. - The DG containers are
observed to be in good condition. - Chemicals stored include
paints and thinner. |
1 sampling location proposed. COCs includes metals, VOCs, SVOCs and PCRs. |
ENV-BH02 |
|
Chemical Waste Area (42 m2) |
- The Chemical Waste Area
has a metal roof and the floor of the area is concrete paved with bunding.
The concrete pavement and bunding are in good condition. - Empty lubrication oil,
grease container, bleach drum and waste battery are temporary stored in this
area until collection by registered chemical waste collector. |
1 sampling location proposed. COCs includes metals, VOCs, SVOCs and PCRs. |
ENV-BH03 |
|
Scrap Iron Storage Area (21m2) |
- Metal scraps such as
machine parts are temporary stored in this area till collection by
contractor. The area is paved with intact concrete. |
1 sampling location proposed. COCs includes metals, VOCs, SVOCs and PCRs. |
ENV-BH04 |
|
Chemical Waste Collecting Tank (34 m2) |
- The chemical waste
collecting tank is placed on top of a concrete paved area with concrete
bunding to prevent spilling and leakage. - Chemical containers and
oil drums would be emptied to this collecting tank before placing them in the
chemical waste store and chemical waste area. |
1 sampling location proposed. COCs includes metals, VOCs, SVOCs and PCR. |
ENV-BH05 |
|
Mechanic
Workshop (1090 m2) |
- The workshop is concrete
paved with no oil stain observed. Repair and maintenance of valve bodies,
spindles pumps and other light machine take place in the workshop. - Typical maintenance may
include greasing and lubrication involving lubrication oil. |
6 sampling locations proposed according to the area. COCs includes metals,
VOCs, SVOCs and PCRs. |
ENV-BH06 ENV-BH07 ENV-BH08 ENV-BH09 ENV-BH10 ENV-BH11 |
|
Administration
and Laboratory Buildings, CLP Transformer No. 1, Transformer No. 19 and No.
20 |
- The area housed offices
and laboratory. The laboratory is located on the first floor of the
Laboratory Building. - The ground floor of the
Laboratory Building is used only as an exhibition centre and general
storeroom (e.g. brand new plastic tubes and wooden sticks). No chemicals were
found. - There are a total of 3
transformers (labelled as ¡¥CLP Transformer No. 1¡¦ and ¡¥Transformer No. 19¡¦
and ¡¥No. 20¡¦) in the area. - CLP Transformer No. 1 is
operated by CLP and located within the substation. Ground are concrete paved
and without stains. - Transformer No. 19 and
No. 20 are housed within the transformer rooms. The transformer rooms are elevated on
an approximately 0.5m concrete platform. |
No land contamination was
found within the ground floor of the Administration and Laboratory Buildings.
Intrusive SI was considered not necessary. 3 sampling location is proposed for the transformer CLP No.
1, No.19 and No. 20 COCs includes metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH12 ENV-BH12A ENV-BH12B |
|
Chemical
Store (166 m2) |
- The Chemical Store is
fully enclosed and the floor of the store is concrete paved. No sign of
spillage or stain was observed. - Mainly lubrication oil
was stored in the area. |
3 sampling locations proposed based on the area. COCs include metals,
VOCs, SVOCs and PCRs |
ENV-BH13 ENV-BH14 ENV-BH15 |
|
Fuel
Oil Tanks |
- There are two 1000 L above-ground
diesel storage tanks to fuel the nearby generators. - The 2 storage tanks are
placed on concrete paved ground with bunding. The paved ground and bunding
are observed to be in good condition. - A diesel filling point
was also observed near the diesel storage tank. |
3 sampling locations are proposed (2 at each storage tank
and 1 at the diesel filling point). COCs include metals,
VOCs, SVOCs and PCRs. |
ENV-BH16 ENV-BH17 ENV-BH18 |
|
Power House + Transformer No. 21 and No. 22 (2470 m2) |
- The Power House consisted
of a (i) generator room, (ii) control room / office and (iii) air blower
rooms. - The generator room
(approximately 1,525 m2) housed 6 generators. Lubrication oil bottles and oil drums
are observed at the temporary chemical waste collecting point (approx. 6m2),
at the southern corner of the generator room. The room is tiled and paved
with concrete. No stains were
observed. - The air blower rooms
(approximately 675 m2) housed 5 air blowers and are located at the
northern portion of the building.
The room is paved with intact concrete with no stains observed. - Two transformers
(labelled as ¡¥Transformer No. 21¡¦ and ¡¥22¡¦) were located at the western side
of the Power House. |
14 sampling locations proposed (6 for generator room, 5 for
the air blower room, 2 for each of the transformers and 1 for the chemical
waste collecting point). COCs include metals,
VOCs, SVOCs, PCRs and PCBs (for transformer only). |
ENV-BH19 ENV-BH20 ENV-BH21 ENV-BH22 ENV-BH23 ENV-BH24 ENV-BH25 ENV-BH26 ENV-BH27 ENV-BH28 ENV-BH29 ENV-BH30 ENV-BH31 ENV-BH32 |
|
Transformer No. 11 to No. 18 |
- There are 8 transformers
(labelled as Transformer No. 11 to 18) near the Power House for the operation
of the Power House and Boiler House. - All 8 transformers are
housed within the transformer rooms.
The transformer rooms are elevated on an approximately 1.0m concrete
platform. No stains were observed on the floor. |
8 sampling locations proposed for each of the transformer. COCs include metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH-T1 ENV-BH-T2 ENV-BH-T3 ENV-BH-T4 ENV-BH-T5 ENV-BH-T6 ENV-BH-T7 ENV-BH-T8 |
|
Sludge Thickening House (890m2) + Transformer No. 5, No. 6
and Transformer A. |
- 6 set of consolidated
sludge pumps were situated in the basement of the building. - The building is fully
concrete paved (included the basement), pipe lines, centrifuge feed tanks,
thickened sludge receiving tanks and cold water receiving tanks were observed
on the ground floor. - There are 3 transformers
(labelled as Transformer No. 5, No. 6 and A) near the Sludge Thickening
House. The transformers are on an elevated concrete platform of approximately
1.0m thick. No stains were observed on the floor. |
9 sampling locations (6 for the consolidated sludge pumps in
the basement and 3 for each of the transformers). COCs include metals,
VOCs, SVOCs, PCRs and PCBs (for transformers only). |
ENV-BH33 ENV-BH33A ENV-BH34 ENV-BH34A ENV-BH35 ENV-BH35A ENV-BH36 ENV-BH36A ENV-BH36B |
|
Air Blower House (1307 m2) + Transformer No. 1 to No. 4 |
- The Air Blower House
consisted of air blower room to the east and switch / transformer room to the
west. - The air blower room
(approximately 504 m2) housed 6 air blowers. Diesel and lubrication oil were used
for their operation. - Temporary oil drums
storage were observed to the north of the air blower room. The room is paved
with concrete and no stains were observed. - The switch room is
located to the north of the switch / transformer room whereas the transformer
room is located to the south. There are 4 transformers (labelled as
Transformer No. 1 to No. 4). The room is paved with concrete and no stains
were observed. |
11 sampling locations proposed (6 for air blower room, 4 for
each of the transformers and 1 for the temporary oil drums storage). COCs include metals,
VOCs, SVOCs, PCRs and PCBs (for transformers only). |
ENV-BH37 ENV-BH38 ENV-BH39 ENV-BH40 ENV-BH40A ENV-BH41 ENV-BH41A ENV-BH42 ENV-BH42A ENV-BH43 ENV-BH43A |
|
Switchgear House (288 m2) + Transformer No. 7 to 10 + CLP
Transformer No. 2 |
- Reported by the site
supervisor, the switchgear house were rarely been used. - Control panels were
placed at the southeastern half of the building whereas 4 transformers
(labelled as Transformer No. 7 to 10) were housed at the northwestern portion
of the building. - The transformer rooms
were concrete paved and no stains were observed on the floor. - There is a CLP Substation
(labelled as ¡¥CLP Transformer No. 2¡¦) near the Switchgear House. The substation was locked at the time
of site inspection and access were not available. |
5 sampling locations proposed for Transformer No. 7 to No.
10 and CLP Transformer No. 2. COCs include metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH44 ENV-BH45 ENV-BH46 ENV-BH47 ENV-BH48 |
|
Effluent Pumping Station (619 m2) + Transformer No. 25 and
No. 26 |
- Four effluent pumps are
situated in the station with size approximately 100m2 (Water pump) - Site supervisor reported
turbines that required use of lubricant is on the first floor and, the part
based on ground floor is only use as a pipe for water transfer - There are 2 transformers
(labelled as Transformer No. 25 to No. 26) near the Effluent Pumping Station.
The transformers are on an elevated concrete platform of approximately 0.5m
thick. No stains were observed on the floor. |
No land contamination was
found within the Effluent Pumping Station. 2 sampling locations proposed for Transformer No. 25 and No.
26. COCs include metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH49 ENV-BH50 |
|
Water Reclamation House (312 m2) + Transformer No. 23 and
No. 24 |
- Major part of the
building is used as information centre for visitor. - The remaining portions
are used for water reclamation (e.g. ultrafiltration and reverse osmosis
system). - There are 2 transformers
(labelled as Transformer No. 23 and 24) for the Water Reclamation House. The
transformers are on an elevated concrete platform of approximately 0.5m
thick. No stains were observed on the floor. |
No land contamination was
found within the Water Reclamation House. 2 sampling locations proposed for Transformer No. 23 and No.
24. COCs include metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH51 ENV-BH52 |
|
General Area of STSTW (280,000m2) |
- |
31 sampling locations, based on 100m sampling grid size, were
proposed for STSTW in general. COCs include metals,
VOCs, SVOCs and PCRs. |
ENV-G1 to ENV-G31 |
Part of Existing VDC
within the Project boundary (approx.36,000m2) (Inspection Date: 14 Nov
2014 & 30 Nov 2015) |
Temporary Storage Area of Spent Batteries (100 m2) |
- The whole area was paved
with additional layer of concrete above the concrete ground - No stain and stressed
vegetation were observed and no past records of leakage of battery solution. |
3 sampling location proposed for the temporary storage area
of spent batteries. COCs include metals. |
ENV-BH53 ENV-BH54 ENV-BH55 |
Storage area of seized goods (100 m2) |
- Only empty containers
were stored in the area. - The whole area was
concrete paved. - No stain and stressed
vegetation were observed and no past records of leakage of chemicals. |
3 sampling locations proposed for the storage areas of
seized goods. COCs include metals,
VOCs, SVOCs, PCRs and PCBs. |
ENV-BH56 ENV-BH57 ENV-BH58 |
¡P Urban residential
¡P Rural residential
¡P Industrial
¡P Public parks
¡P Prior to the commencement of the SI works, review the CAP to confirm whether the proposed SI works (e.g. sampling locations, testing parameters etc.) are still valid and to confirm the appropriate RBRGs land use scenario for the development;
¡P Submit supplementary CAP(s), presenting the findings of the above review for EPD endorsement. If land contamination issues were identified within David Camp and the proposed A Kung Kok Shan Road magazine site in the further site walkover, findings of the site walkover and the proposal for SI works should also be presented in the supplementary CAP(s);
¡P Carry out SI works according to the supplementary CAP endorsed by EPD;
¡P Submit CAR(s), detailing findings of the SI works and nature/extent of any soil/groundwater contamination, and, if contaminated identified, RAP(s) discussing the appropriate remedial methods and mitigation measures, for the identified contamination, for EPD agreement; and
¡P Carry out soil/groundwater remediation works according to EPD agreed RAP and submit RR(s) afterwards for EPD agreement. The remediation works and agreement of RR should be completed prior to re-development.
¡P Excavation profiles must be properly designed and executed with attention to the relevant requirements for environment, health and safety;
¡P Excavation shall be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils;
¡P Supply of suitable clean backfill material (or treated soil) after excavation;
¡P Stockpiling site(s) shall be lined with impermeable sheeting and bunded. Stockpiles shall be fully covered by impermeable sheeting to reduce dust emission. If this is not practicable due to frequent usage, regular watering shall be applied. However, watering shall be avoided on stockpiles of contaminated soil to minimise contaminated runoff.
¡P Vehicles containing any excavated materials shall be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates shall be sealed to prevent any discharge during transport or during wet conditions;
¡P Speed control for the trucks carrying contaminated materials shall be enforced;
¡P Vehicle wheel and body washing facilities at the site¡¦s exist points shall be established and used; and
¡P Pollution control measures for air emissions (e.g. from biopile blower and handling of cement), noise emissions (e.g. from blower or earthmoving equipment), and water discharges (e.g. runoff control from treatment facility) shall be implemented and complied with relevant regulations and guidelines.
<End of Section 6>