TABLE OF CONTENTS
Page
1............ Introduction. 3
1.1......... Project Background. 3
1.2......... Purpose of this
Executive Summary. 4
2............ Project description. 5
2.1......... Project Scope. 5
2.2......... Need of the Project 6
2.3......... Benefits of the Project 7
2.4......... Project Programme. 7
2.5......... Summary of Designated
Projects. 7
2.6......... Concurrent Projects. 8
3............ Consideration of
Alternative Options. 9
3.1......... Consideration of
Alternative Site Locations. 9
3.2......... Consideration of
Alternative Plant Layout Arrangement 9
3.3......... Consideration of Alternative
Plant Design. 10
3.4......... Consideration of
Alternative Construction Methods and Sequence of Works. 12
4............ Key Findings of the
environmental impact Assessment (EIA) 14
4.1......... Approach to the EIA. 14
4.2......... Air Quality Impact 14
4.3......... Noise Impact 15
4.4......... Water Quality Impact 17
4.5......... Land Contamination. 19
4.6......... Hazard to Life. 19
4.7......... Ecological Impact
(Terrestrial and Marine) 20
4.8......... Fisheries Impact 21
4.9......... Landscape and Visual
Impacts. 22
4.10....... Cultural Heritage
Impact 23
4.11....... Waste Management
Implications. 23
4.12....... Health Impact 24
5............ Environmental
monitoring and audit (EM&A) 25
6............ Conclusion. 28
List of tables
Table 4.1.......... Summary
of predicted construction dust levels (in £gg/m3) at representative
air sensitive receivers during construction of relocated STSTW.. 15
Table 4.2.......... Summary
of predicted construction dust levels (in £gg/m3) at representative
air sensitive receivers during demolition of existing STSTW.. 15
Table 5.1.......... Summary
of EM&A Requirements. 25
List of DIAGRAMS
Diagram 2.01... Sewage Treatment Process Schematic
Flow Diagram.. 6
LIST OF Figures
Figure No. 60334056/ES/1.01 Project Layout Plan
Figure No. 60334056/ES/1.02 3-D View and Typical
Sections of CSTW
Figure No. 60334056/ES/1.03 Layout Plan of the Proposed
Sewage Treatment Works in Caverns
Figure No. 60334056/ES/4.01 Representative Air
Sensitive Receivers for Construction Dust Impact
Figure No. 60334056/ES/4.02 Representative Air
Sensitive Receivers for Operational Odour Impact
Figure No. 60334056/ES/4.03 Locations of
Representative Noise Sensitive Receivers for Construction Noise and Operation
Fixed Plant Noise
Figure No. 60334056/ES/4.04 Locations of
Representative Noise Sensitive Receivers for Ground-Borne Noise during
Construction Phase
Figure No. 60334056/ES/4.05 Habitat
Map (Sheet 1 of 2)
Figure No. 60334056/ES/4.06 Habitat
Map (Sheet 2 of 2)
Figure No. 60334056/ES/4.07 Visual
Envelope and Visually Sensitive Receivers
Figure No. 60334056/ES/4.08 Photomontage
P1
Figure No. 60334056/ES/4.09 Photomontage
P2
Abbreviation
ADWF
|
Average Dry Weather Flow
|
AGS
|
Aerobic Granular Sludge
|
AHM
|
Artificial Hard Materials
|
ALARP
|
As Low As is Reasonably Practicable
|
ASRs
|
Air Sensitive Receivers
|
AQOs
|
Air Quality Objectives
|
C&D
|
Construction and Demolition
|
CAP
|
Contaminated Assessment Plan
|
CAR
|
Contamination Assessment Report
|
CAS
|
Conventional Activated Sludge
|
CCTV
|
Closed-Circuit Television
|
CEDD
|
Civil Engineering Development Department
|
CSTW
|
Cavern Sewage Treatment Works
|
DO
|
Dissolved Oxygen
|
DP
|
Designated Project
|
DSD
|
Drainage Services Department
|
EIA
|
Environmental Impact Assessment
|
EIAO
|
Environmental Impact Assessment Ordinance
|
EIAO-TM
|
Technical Memorandum on Environmental Impact
Assessment Process
|
EM&A
|
Environmental Monitoring and Audit
|
ES
|
Executive Summary
|
FCZs
|
Fish Culture Zones
|
FSP
|
Fine Suspended Particulates
|
GB
|
Green Belt
|
HP
|
High Pressure
|
HRs
|
Human Receptors
|
IFAS
|
Integrated Fixed Film Activated Sludge System
|
IGEM
|
Institution of Gas Engineers and Managers
|
KTN
|
Kai Tak Nullah
|
LCA
|
Landscape Character Area
|
MBBR
|
Moving Bed Biofilm Reactor
|
MLE
|
Modified Ludzack-Ettinger
|
NCO
|
Noise Control Ordinance
|
NSR
|
Noise Sensitive Receiver
|
OVT
|
Old and Valuable Tree
|
OZP
|
Outline Zoning Plan
|
PME
|
Powered Mechanical Equipment
|
ProPECC PN 1/94
|
Professional Persons on Construction Site
Drainage
|
QRA
|
Quantitative Risk Assessment
|
RAP
|
Remediation Action Plan
|
RR
|
Remediation Report
|
RSP
|
Respirable Suspended Particulates
|
SS
|
Suspended Solids
|
SSSI
|
Sites of Special Scientific Interest
|
STEPS
|
Sha Tin Effluent Pumping Station
|
STSTW
|
Sha Tin Sewage Treatment Works
|
TAP
|
Toxic Air Pollutant
|
TBM
|
Tunnel Boring Machine
|
THEES
TIN
|
Tolo Harbour
Effluent Export Scheme
Total Inorganic Nitrogen
|
TM-DSS
|
Technical Memorandum on Standards for
Effluents Discharged into Drainage and Sewerage Systems
|
TPEPS
|
Tai Po Effluent Pumping Station
|
TPSTW
|
Tai Po Sewage Treatment Works
|
TSP
|
Total Suspended Particulates
|
USEPA
|
US Environmental Protection Agency
|
UV
|
Ultra Violet Light
|
VSRs
|
Visually Sensitive Receivers
|
1.1.1
To support the social and economic development
of Hong Kong, there is a pressing need to optimise
the supply of land for various uses.
Rock cavern development is a sustainable and innovative approach to do
so. The Policy Agenda of the 2016
Policy Address has stated that works for the relocation of the Sha Tin Sewage
Treatment Works (STSTW) is to commence as soon as possible for vacating the
existing STSTW site for development purpose.
1.1.2
The existing STSTW, with a design sewage
treatment capacity of 340,000 m3 per day, is the largest secondary
sewage treatment works in Hong Kong serving Sha Tin and Ma On
Shan. Relocating STSTW to caverns can release its existing site of about 28
hectares for other beneficial and more compatible uses. This
will also enhance the living environment of the surrounding areas.
1.1.3
In November 2013, the Project Proponent, Drainage
Services Department (DSD) consulted the Health and Environment Committee of the
Sha Tin District Council on the findings and recommendations of the
¡§Feasibility Study on Relocation of Sha Tin Sewage Treatment Works to Caverns¡¨,
and the Committee generally supported the Government to proceed with the
investigation and design of the Project.
1.1.4
In September 2014, DSD appointed AECOM Asia Co
Ltd. to carry out detailed investigation, design and construction supervision of
the Project under Agreement No. CE 30/2014 (DS) ¡§Relocation of Sha Tin
Sewage Treatment Works to Caverns: Caverns and Sewage Treatment Works ¡V
Investigation, Design and Construction¡¨ (the Assignment).
1.1.5
The Project is a Designated Project (DP) under
the Environmental Impact Assessment Ordinance (EIAO). An application for an Environmental
Impact Assessment (EIA) Study Brief under section 5(1)(a)
of the EIAO was submitted on 12 May 2014 with a Project Profile (No.
PP-508/2014) for the Project. An
EIA Study Brief (No. ESB-273/2014) was issued on 24 June 2014. An EIA for the Project was
then undertaken,
as part of the Assignment, in accordance with the
EIA Study Brief and the Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM).
1.1.6
A series of public consultation/engagement
activities have been conducted to gather
comments and views from the public on the Project since 2012. Activities organised
include a public forum, focus group meetings,
community group meetings, roving exhibitions, site visits to Stanley Cavern
Sewage Treatment Works, demonstrations
of de-odourisation
equipment and physical models. These covered a broad spectrum of
stakeholders including local residents and representatives, members of the
District Council,
professional bodies, environmental groups, the
media and statutory bodies. Views collected during the public engagement
activities have been taken into consideration in the feasibility study and
investigation phases of the Project in formulating
the design and arrangement. The Project Proponent would
continue to engage
the
stakeholders and the public to enhance mutual understanding and thereby the efficaciousness of the
Project.
1.1.7
The purpose of the EIA is to provide information
on the nature and extent of environmental impacts arising from the construction
and operation of the Project and associated works that will take place
concurrently. This information will contribute to decisions by the Director of
Environmental Protection on:
The overall acceptability of any
potential environmental consequences that are likely to arise as a result of
the Project;
The conditions and requirements for
the detailed design, construction, operation and associated works of the
Project to mitigate against potential environmental consequences wherever
practicable; and
The acceptability of residual
impacts after the proposed mitigation measures are implemented.
1.2.1
The purpose of this EIA Executive Summary (ES)
is to present the summary of the findings, conclusions and recommendations in
the EIA Report prepared in accordance with the requirements of the EIAO. This
ES contains the following information:
Section 2 presents purpose and nature of the Project;
Section 3 presents the consideration of alternative options for the site location, plant layout
arrangement, plant design and construction methods;
Section 4 presents the key findings of environmental impacts;
Section 5 describes environmental monitoring and audit for the Project; and
Section
6 gives the conclusions.
2.1
Project Scope
(i) Construction of caverns at Nui Po Shan for
housing the Sha Tin Cavern Sewage Treatment Works (CSTW);
(ii) Construction of a secondary sewage treatment
works including sludge treatment facilities inside the caverns, with a design
capacity of 340,000 m3/day at average dry weather flow (ADWF);
(iii) Construction of the main and secondary
access tunnels and portals for access to the CSTW;
(iv) Construction of ancillary facilities to the
caverns, including ventilation system, fire services, safety measures,
communication systems, utilities, etc;
(v) Site formation and construction of
ancillary facilities including a multi-storey administration building with
laboratories, workshops, staff office, visitor facilities, etc,
ventilation building, electrical substation, and other minor buildings and
internal access road at the main portal located on A
Kung Kok Street;
(vi) Site formation and construction of ancillary
facilities including a ventilation building, electrical substation and
internal access road at the secondary portal located on
Mui Tsz Lam Road;
(vii) Construction of pipelines from the CSTW for
connection to the existing emergency submarine outfall of the existing
STSTW;
(viii)Construction
of new effluent tunnels and pipelines for the discharge of treated effluent
from the relocated STSTW to the existing Tolo Harbour Effluent Export Scheme (THEES)
tunnel;
(ix) Associated slope stabilisation and natural
terrain hazard mitigation and geotechnical works;
(x) Landscaping and architectural works;
(xi) Construction of a ventilation adit connecting the CSTW to a
ventilation shaft located in
Nui Po Shan, together with a surface access of around 500m length leading from the end of
A Kung Kok Shan Road;
(xii) Construction of a temporary project
specific magazine at Nui Po Shan next to the location for the Ventilation Shaft, with
access from A Kung Kok Shan Road,
for storage of explosives for up to a few days¡¦ use for construction of the CSTW, and decommissioning
of it after the completion of blasting works;
(xiii)Operation
and maintenance of the CSTW; and
(xiv)
Decommissioning
and demolition of the existing STSTW.
2.1.2
Figure No.
60334056/ES/1.01
shows the location and boundary of the Project. A 3-D view to better illustrate
the CSTW with typical cross sections is shown on Figure No.
60334056/ES/1.02. A
preliminary layout plan of the proposed sewage treatment works in caverns is
presented on Figure No. 60334056/ES/1.03.
2.1.3
Following detailed population projection and flow assessment of the broad Sha
Tin area, the design treatment capacity and effluent standards of the relocated
STSTW have
been set as follows, which would be the same as those of the existing STSTW:
Design
Treatment Capacity
|
340,000m3/day
(ADWF)
|
|
|
|
Determinand:
|
Percentile Standard
|
Upper Limit
|
Suspended Solids (mg/L)
|
30*
|
60
|
Biochemical Oxygen Demand
(5 days, 20oC) (mg/L)
|
20*
|
40
|
Total Nitrogen (mg/L)
|
20#
|
35
|
Ammonia Nitrogen (mg/L)
|
5#
|
10
|
E. coli
(count/100 mL)
|
1,000^
|
15,000*
|
Notes: *
at 95-percentile
#
annual average
^
monthly geometric mean
2.1.4
In order to meet the required discharge quality standard,
biological treatment will have to be provided. The sewage treatment process to be
adopted for the
CSTW will generally comprise the following components, but the detailed
sequencing and configuration may vary from process to process (e.g. batch reactor
processes may combine several functions in a single tank): (1) preliminary
treatment including fine screening and grit removal; (2) primary treatment; (3)
biological treatment; (4) solid/liquid separation; and (5) Ultra Violet Light
(UV) disinfection. Diagram 2.01 below presents a schematic flow diagram of the treatment process:
Diagram 2.01 Sewage Treatment Process Schematic
Flow Diagram.
2.1.5
Sewage arriving at the inlet of the sewage
treatment works will enter the preliminary treatment process, including
mechanical bar screens and a grit removal system to remove large solid debris, sand and grit
materials. Preliminarily treated
effluent may then be directed to the primary treatment process where the
suspended solids (SS) are settled out and removed as primary sludge. The primary effluent will then be
conveyed to the biological treatment where micro-organisms will assimilate and
remove pollutants in the sewage.
Finally the secondary effluent will be disinfected by UV before
discharge to the THEES tunnel.
2.1.6
A small portion of treated effluent, not
exceeding 1,500 m3/day (0.4% of the design capacity of the CSTW),
would be reused for non-potable uses including use in the laboratory, polymer
solution preparation, irrigation and toilet flushing inside the CSTW. Before reuse, this treated effluent will
undergo a polishing step based on membrane filtration and/or reverse osmosis to
meet the required
necessary design standard.
2.1.7
A temporary project specific explosive magazine,
which consist of above ground single-storey structures, is
proposed to be built on Nui Po Shan next to the location of the Ventilation
Shaft. The magazine will be
accessed from A Kung Kok Shan Road and used for
short-term ¡V in the order of a few days ¡V storage of explosives that will be
used for construction of the CSTW. The explosive magazine will be decommissioned
after the completion of construction of caverns for the Project.
2.1.8
Under the context of EIA Study Brief No.
ESB-273/2014, the ¡§Project¡¨, as described above, is referring to the ¡§Sha Tin
Cavern Sewage Treatment Works¡¨ (CSTW). Any environmental impacts that may arise from future developments on the
site of the existing STSTW after its decommissioning are outside and
independent from the present EIA.
2.2
Need of the Project
There
is a need to optimise the supply of land by
sustainable and innovative approaches to support the social and economic
development of Hong Kong.
Relocating STSTW to caverns can release its present site for other
beneficial uses.
2.3.1
Upon relocation of the STSTW to caverns, 28 ha of land in Sha Tin
with sea frontage can be released for re-development to meet the needs of
the society.
2.3.2
The living environment of the surrounding area
would be improved.
The common potential impacts of a sewage treatment works, particularly odour and visual impacts, can be very effectively
controlled and minimised. Odour
management of the STSTW would be greatly enhanced since the caverns would serve
as very effective natural barriers.
2.3.3
Advanced technologies can be adopted for the new
sewage treatment facilities to enhance operation process performance,
resilience and reliability, as well as operation efficiency.
2.3.4
Subject to subsequent planning, the released
STSTW site will provide opportunities for developing a green and vibrant
waterfront living environment with ample open space, a continuous promenade and
recreational facilities such as amenity areas, cycle tracks and other leisure
purposes could be created.
2.3.5
The development opportunities of the surrounding
area adjacent to the existing STSTW site would be enhanced after completion of
the Project and the accessibility of the area would be improved by improving
transport infrastructure at the area.
2.3.6
The project location is rich in granite. Excavation of caverns will produce a large amount of hard granitic
rocks, which are valuable natural resources for construction use. Rocks produced under this Project would
become a local source to support the construction industry.
2.4
Project Programme
The
Project construction works are anticipated to commence in 2018 with completion
of the Project by 2028.
2.5.1
The Project components that constitute a DP
under the EIAO are listed as follows:
¡P
DP1
¡V
|
Sewage treatment works with an installed
capacity of more than 15,000 m3 per day under Item F.1 in Schedule
2 Part I;
|
¡P
DP2
¡V
|
Sewage treatment works under
Item F.2 in Schedule 2 Part I---
¡± With an installed capacity of more than
5,000 m3 per day; and
¡± A boundary of which is less than 200m
from the nearest boundary of an existing or planned residential area,
educational institution and health care institution.
|
¡P
DP3
¡V
|
An activity for the reuse of treated sewage
effluent from a treatment plant under Item F.4 in Schedule 2 Part I;
|
¡P
DP4
¡V
|
Underground rock caverns under Item Q.2 in
Schedule 2 Part I;
|
¡P
DP5
¡V
|
An explosives depot in a stand‑alone, purpose built building under Item K.10 in Schedule 2 Part I;
and
|
¡P
DP6
¡V
|
Decommissioning of an explosives depot under Item 11 in Schedule 2
Part II.
|
2.6
Concurrent Projects
2.6.1
Nine concurrent projects in the vicinity of
the Project site are identified and their cumulative impacts have been
assessed. Amongst the identified
concurrent projects, it is found that the following two concurrent projects
will have cumulative impacts on this Project. It should be noted that the status of
these concurrent projects is based on the available information at the time of
submission of this Report and the implementation of individual projects would
be subject to further development and subsequent actions of the
respective
project proponents.
(a)
Proposed
works for Upstream Sewerage Facilities for the Relocation of Sha Tin Sewage
Treatment Works ¡V this is a DSD project and include construction of a new
pumping station and modification of existing pumping stations as well as
sewerage works in order to convey sewage to the CSTW for treatment. All works are expected to start at 2021
for completion in 2026.
(b)
Tolo
Harbour Sewerage of Unsewered Areas, Stage II - This
project covers the provision of sewerage to a number of unsewered
areas in Sha Tin. Works are
on-going and expected to be completed by 2020.
The
design of the Project has undergone a detailed evaluation of different
arrangement to arrive at the optimum planning, engineering and environmental
solutions which fit together in a coherent manner. The following sections summarise the evaluation criteria and the consideration of
various alternative options.
Consideration of
Alternative Sites
3.1.1
When conducting the review of the proposed
relocation site, five areas adjacent to the existing STSTW were identified and
evaluated. These five areas are:
Nui Po Shan at A Kung Kok, Shek Mun,
Ma On Shan, Kau To Shan
South and Kau To Shan North.
3.1.2
The review confirmed that Nui Po Shan is the
preferred site for the relocation of the STSTW. To sum up, the Nui Po Shan site has the
following merits and is more favorable than the others:
The geology of this area,
belonging to hard granite with no obvious weak zones and faults, is most
suitable for construction of large caverns;
This area is located in the
proximity of the existing STSTW and THEES effluent export tunnel which conveys
the treated effluent from the STSTW to Kai Tak Nullah
(KTN) (Kai Tak River after completion of re-construction and upgrading works)
in Wong Tai Sin for discharge. As
such, relocating the STSTW to this area will minimise the disturbance to the
whole Sha Tin District, reducing the extent of construction works due to
modification of upstream sewerage and shortening the construction period;
No private land resumption is
needed; and
This area is close to Ma On Shan Road.
With appropriate measures, the traffic impact due to the relocation of
the STSTW is the minimum.
3.1.3
Although the direct environmental impacts
related to all five areas are similar, suitable geology and close to existing high-speed
road in Nui Po Shan Sites will shorten the construction period and haul route
that will also have less indirect environmental impacts than other options.
3.1.4
Furthermore, the position and orientation of the
CSTW will avoid encroaching into the boundaries of Ma On
Shan Country Park and Mui Tsz Lam and Mau Ping Priority Sites for Enhanced
Conservation.
Consideration
of Supporting Facilities Locations
3.2.1
There are two options in locating the supporting
facilities: (1) at both Main Portal and Area 73, or (2) at the Portals
only. Option 1 was the original
arrangement proposed in the Feasibility Study Stage to limit the extent of site
formation works at the portal area. However, this option will take up a
considerable area of Area 73 reducing the versatility of the site. Furthermore,
the connectivity with the CSTW and operation effectiveness is affected. Considering the demerits of Option 1,
Option 2 was developed and aimed to relocate the facilities in Area 73 under
Option 1 to the Main Portal as well.
The extent of site formation works in Option 2 will increase. In return,
connectivity among the facilities, buildings and the sewage treatment works is
much improved. The portal area will be flexibly utilised by integration of the sewage treatment works ancillary
facilities with the THEES Tunnel Portal.
Area 73 will not need to be reserved for any permanent facility of the
CSTW.
Consideration
of Ventilation Shaft Locations
3.2.2
Different options have also been considered in
determining the location of the ventilation shaft. The Feasibility Study Stage has
originally proposed the ventilation shaft to be located at the south-west
corner of the CSTW. The outlet of
the ventilation shaft will be at an uphill area at approximately 240mPD and is
far from all major residential developments and villages, the closest one being
more than 700m away on plan. On the
other hand, to allow construction of the ventilation shaft, an access road
approximately 1,200m in length leading from the upper end of A Kung Kok Shan Road will need to be laid. The ventilation shaft location was then
revised in subsequent design development, and lies approximately 500m to the
south-west of the original location.
It is also very remote from all major residential developments and
villages, the closest one being more than 1,000m away. The outlet of the
ventilation shaft will be in an uphill area at approximately 180mPD. At this location, the access road
leading from the top end of A Kung Kok Shan Road can
be much shortened to about 500m in length, which will generate less soft spoil
and require less tree felling. Odour impact assessment indicates that residual odour impacts from both options are minimal and are in full
compliance with the EIAO-TM requirements.
In view of the shorter access road consequently less volume of
construction works for the shaft and tree felling, the revised location is
therefore considered preferable.
Consideration
of Alternative Emergency Outfall Options
3.2.3
Under normal operation, treated effluent from
the relocated STSTW will be conveyed by the THEES effluent tunnel for ultimate
discharge into Victoria Harbour. In other or emergency situations, same
as for the existing STSTW, an emergency outfall is needed for bypass of treated
or partially treated effluent to Tolo Harbour.
Various options of an emergency outfall for the relocated STSTW have
been considered, namely (1) continued utilization of the existing emergency
submarine outfall, (2) construction of a new emergency submarine outfall and
(3) construction of a new seawall outfall.
After evaluation, Option (1) should have the best water quality
performance during the operation stage because its location will have the best
effluent dispersion effect during emergency bypass. The connection pipes to the existing
outfall would be constructed by trenchless method so that no disturbance to
marine or riverbed sediments would be induced. This option makes the most use of the
existing facilities and involves the least amount of works and will incur the
least environmental impact in terms of marine ecology and water quality during
construction. Hence, Option (1) is
the most favourable.
Consideration
of Alternative Treatment Level
3.3.1
The treatment level of a sewage treatment work
is dependent on its environmental settings and the mode of discharge. The aim is to achieve satisfactory water
quality meeting relevant stipulations. The level of treatment of a
sewage treatment work will determine the effluent quality, and the mode of
discharge will affect the subsequent processes including dilution, dispersion
and diminution of any residual pollutants.
Hence for a given environmental setting, the treatment level and the
mode of discharge are closely related ¡V a lower treatment level will require a
better mode of discharge, e.g. a longer submarine outfall, and vice versa.
3.3.2
The treatment level of the existing STSTW is
secondary plus disinfection, and is able to fulfil the relevant water quality
requirements. For the relocated
STSTW, maintaining the treatment level the same as that of the existing STSTW
will result in a water quality at least not inferior to the present situation. Raising the treatment level to tertiary
treatment will give higher quality effluent but at the same time will incur
significantly higher construction and operation costs. On the other hand, a lower treatment
level will result in a lower water quality in the receiving waters.
3.3.3
The whole Sha Tin District adopts seawater
flushing. Switching the use of
seawater to treated effluent will require a higher level of treatment than
secondary to meet flushing water standard, with much higher construction and
operation costs, as well as operation power consumption owing to the additional
treatment processes. The benefits,
nonetheless, are not apparent as such a switching will not give rise to
conservation of freshwater resources.
3.3.4
In light of the adequacy of the current
treatment level in meeting water quality requirements, it is both
environmentally and economically acceptable to maintain the current level of
secondary treatment plus disinfection for the CSTW.
Consideration
of Alternative Treatment Processes
3.3.5
In order to meet the required discharge quality
standard, biological treatment will have to be provided. The sewage treatment process employed in
the existing STSTW is the Modified Ludzack-Ettinger
(MLE) process, a relatively conventional activated sludge technology based
solely on suspended growth, which has a lot of operation experience
locally. This Conventional
Activated Sludge (CAS) is one of the options for the sewage treatment process
for the CSTW.
3.3.6
There are other technologies available that, by making
use of attached growth or granular forms of activated sludge, will reduce the
required hydraulic retention time and thus give an overall more compact process
than CAS. For the purpose of
discussion here these will be called Compact-type technologies. They include the Moving Bed Biofilm
Reactor (MBBR); Integrated Fixed Film Activated Sludge System (IFAS); the
Aerobic Granular Sludge (AGS), etc.
3.3.7
Both CAS and the Compact-type technologies will
provide secondary biological treatment capable of achieving the required
effluent standards when coupled with UV disinfection. In terms of environmental impact there
is no significant difference in the nature of impacts between the two options. On the other hand, owing to higher
tankage volume, CAS will involve a considerably larger volume of excavation
works and higher construction period during which environmental impacts will be
generated. Hence Compact-type
technologies are the preferred option.
Consideration
of Alternative Sludge Treatment Process
3.3.8
Sludge from the future CSTW will be conveyed to
the Sludge Treatment Facility in Tuen Mun for incineration, similar to the arrangement for the
existing STSTW. Prior to conveyance
to the Sludge Treatment Facility, a number of alternative handling options are
considered:
Dewatering with prior anaerobic
digestion, with digesters located inside the caverns
Dewatering with prior anaerobic
digestion, with digesters located outside the caverns
Direct Dewatering without
digestion
3.3.9
Anaerobic digestion would reduce the volume of
the sludge to be disposed of to the Sludge Incineration Facility, and allow the
recovery of heat and energy from the biogas generated for utilization in the
sewage treatment works. Yet as
biogas is inflammable, its generation inside caverns is as a matter of
principle not acceptable under the prevailing fire safety policy. Open-top design (i.e. the top of the
digester protrudes above the hill surface) is not viable for the Project owing
to the CSTW being located deep under the steep topography of Nui Po Shan.
3.3.10
The available space at the cavern portal area is
very limited and is not sufficient to accommodate any sludge digestion
facilities in addition to the other necessary supporting facilities of the
CSTW. Extensive site formation
including substantial setting back of the existing green belt area would be
required if space sufficient for the sludge digestion facilities is to be made
available. This, however, would
cause significant adverse environmental impact in terms of tree felling,
significantly increased geotechnical and slope stabilisation
works, additional excavated materials to be disposed as well as noise and air
emission due to the additional excavation works.
3.3.11
In view of the issues arising from the inclusion
of anaerobic digestion at the relocated STSTW, either inside or outside the
caverns, direct dewatering option is the most feasible option for this
Project.
Consideration
of Alternatives to Minimise Emergency Discharges
3.3.12
In the
relocated STSTW, sufficient standby units will be provided for all major
treatment units and Electrical and Mechanical (E&M) equipment to cater for
equipment breakdown and maintenance needs, which in turn will minimize the risk
of inadequately treated effluent or emergency discharge. Dual power supply from two separate
electrical sub-stations will be arranged in order to further minimise any possible disruption to operation due to
suspension of power supply. Furthermore, commissioning of the relocated STSTW
is planned to be carried out in stages.
A portion of the total flow will first diverted to the relocated plant
to enable the treatment process to be tested, refined and adjusted to the
required performance before the remaining sewage is diverted to the relocated
STSTW.
Construction
Methods for Tunnels and Caverns
Consideration
of Alternative Temporary Explosive Magazine Arrangements
3.4.2
The scenario of not having an on-site temporary
magazine has been considered. Under
such a situation, explosives availability at the works fronts will be dependent
totally upon explosives delivery by the Mines Division of Civil Engineering and
Development Department (CEDD), which normally is limited to once per day and in
any case would be subjected to resources limitations of the Mines
Division. For a project with
multiple large-scale caverns like the CSTW, this will pose a serious constraint
on the construction programme and unnecessarily prolong the construction
period, with a significant delay in realizing the environmental benefits of the
relocation Project. This scenario
is therefore undesirable in environmental aspects. The option of shared use of other
existing magazine sites with other contracts have also been considered. However, there are actually very few
such magazines, and all of them are subject to different constraints or
uncertainties which make this option infeasible. A much more environmentally sound and
technically viable alternative is the provision of a temporary on-site
explosives magazine. The future
CSTW complex will comprise a vertical ventilation shaft opening to a remote
uphill area on Nui Po Shan.
Construction of the shaft will necessitate the installation of an access
road from the upper end of A Kung Kok Shan Road. Adjacent to the location of the
ventilation shaft opening is a small flat area. This is considered a very suitable site
for the temporary explosives magazine, as it is remote from most population and
the community.
3.4.3
To ensure the security during storage of
explosives, security fences complete with overhang covered in barbed wire will
be installed around the store. Security guards will be on duty 24
hours and only registered authorised persons will be
allowed to enter the compound. Furthermore, a Closed-circuited Television
(CCTV) system will be installed to provide 24 hours surveillance and video
recording.
Construction
Methods for THEES Connection Works
3.4.4
The current arrangement of discharging STSTW
treated effluent to KTN through the THEES tunnel would be maintained after the
relocation. To convey the treated
effluent of the future CSTW to the tunnel, two options have been
considered:
Option 1: the connection point
will be outside the THEES tunnel at its Sha Tin portal. A short section of tunnel will be
constructed between the CSTW and the THEES tunnel inlet chamber.
Option 2: the connection point
will be at a point along the THEES tunnel several hundred metres downstream of
its Sha Tin portal.
3.4.5
Both Options will inevitably require temporary
suspension of the THEES tunnel at certain times for constructing the
connection, during which treated effluent in the THEES will be temporarily
bypassed into Tolo Harbour. For Option 1, the connection works
involve modifications to the existing inlet chamber to the THEES tunnel; while
for Option 2, the connection will involve breaking into the existing THEES
tunnel for a T-junction and making good the tunnel lining afterwards. Both the
number of times and duration of temporary suspension will be less for Option 1
than Option 2. Option 1 is
therefore the preferred alternative.
Furthermore, it is assessed that the connection works of Option 1 can be
split into a number of steps for synchronized implementation with THEES
maintenance, thereby avoiding the need for additional temporary suspension of
the THEES.
4
Key Findings of the environmental impact Assessment (EIA)
4.1.1
The EIA process provides a means of identifying,
assessing and reporting the environmental impacts associated with the
construction and operation of the Project based on the engineering design
information available at this stage.
It is an iterative process that has been followed in parallel with the
design process to identify the potential environmental effects of various
design options, and develop alternatives as well as mitigation measures to be
incorporated into the design, construction and operation of the Project. Feedbacks and advices obtained from
various public engagement activities have been considered and incorporated into
the design and EIA process where appropriate. The Project Proponent has also
come up with measures that can avoid some potential environmental impacts,
while others are minimized or mitigated to acceptable levels.
4.1.2
The findings of this EIA study have determined the
likely nature and extent of the following environmental impacts predicted to
arise from the construction and operation of the Project:
Air Quality Impact;
Noise Impact;
Water Quality Impact;
Land Contamination;
Hazard to Life;
Ecology Impact (Terrestrial and
Marine);
Fisheries Impact;
Landscape and Visual Impacts;
Cultural Heritage Impact;
Waste Management Implications;
and
Health Impact.
Assessment Scope
and Key Criteria
4.2.1
Potential air quality impacts associated with
the construction and operational phases of the project have been assessed in
accordance with the criteria and guidelines as stated in the requirements given
in Section 3.4.1 and Appendix B of the EIA Study Brief, as well as Annex 4 and
Annex 12 of the EIAO-TM. The assessment
area for construction dust impact assessment is within 500m from the boundary
of the Project site. Regarding
operational odour impact by CSTW, potentially
affected air sensitive receivers (ASRs) are generally identified within 500m
study boundary from the ventilation shaft, portal facilities and CSTW. In light that odour is a key concern of the local community, ASRs outside
the 500m study boundary are also identified to investigate the impact in a
longer range.
Construction Phase
4.2.2
Potential air quality impacts from the
construction works (including construction of CSTW and demolition of existing
STSTW) of the Project would mainly be related to construction dust from
excavation, materials handling, spoil removal and wind erosion. Quantitative fugitive dust assessments
have been conducted, taking into account the cumulative impact caused by nearby
concurrent sources within 500m from the boundary of the Project site. With the implementation of mitigation
measures specified in the Air Pollution Control (Construction Dust) Regulation
together with the recommended dust suppression measures including watering 8
times a day on active works areas, exposed areas and unpaved haul roads, using
dust collector with 99% removal efficiency for rock crusher and adopting good
site practices, and Environmental Monitoring and Audit (EM&A) programme, the predicted dust impact at ASRs (locations of
ASRs refer to Figure No. 60334056/ES/4.01)
would comply with the hourly, daily and annual particulate criteria stipulated
in the Air Quality Objectives (AQOs) and EIAO-TM. The predicted cumulative
1-hour average Total Suspended Particulates (TSP), daily and annual average
Respirable Suspended Particulates (RSP), daily and annual average Fine Suspended
Particulates (FSP) are summarised in Table 4.1
and Table 4.2
below.
Table 4.1 Summary of
predicted construction dust levels (in £gg/m3)
at representative air sensitive receivers during construction of relocated
STSTW
|
TSP
|
RSP
|
FSP
|
Max. 1-hour
|
24-hour
(10th highest)
|
Annual
|
24-hour
(10th highest)
|
Annual
|
Concentrations at ASR (Unmitigated)
|
248 ¡V 14,458
|
75 - 443
|
38 - 55
|
55 - 118
|
26 - 34
|
Concentrations at ASR (Mitigated)
|
132 - 471
|
72 - 100
|
37 - 41
|
53 - 60
|
26 - 29
|
Criteria
|
500
|
100
|
50
|
75
|
35
|
Table 4.2 Summary of
predicted construction dust levels (in £gg/m3)
at representative air sensitive receivers during demolition of existing STSTW
|
TSP
|
RSP
|
FSP
|
Max. 1-hour
|
24-hour
(10th highest)
|
Annual
|
24-hour
(10th highest)
|
Annual
|
Concentrations at ASR (Unmitigated)
|
228 ¡V 4,567
|
74 ¡V 221
|
37 - 45
|
55 ¡V 68
|
26 ¡V 29
|
Concentrations at ASR (Mitigated)
|
132 - 491
|
72 - 85
|
37 - 41
|
53 - 59
|
26 - 29
|
Criteria
|
500
|
100
|
50
|
75
|
35
|
Operational Phase
4.2.3
Potential air quality impacts during operational
phase would come from odour emission from the ventilation
shaft of the CSTW (locations of ASRs refer to Figure No.
60334056/ES/4.02). Cavern is an
effective natural barrier and the sewage treatment facilities which would pose odour emission would be enclosed. Odour emitted
from these enclosed sewage treatment facilities would all be treated in the deodourizing units with odour
removal efficiency of 80 ¡V 97% before venting to the ambient via the
ventilation shaft which is located at a remote area on Nui Po Shan. In addition, negative pressure would be
applied inside caverns preventing the odour leakage
through the access tunnels. Odour management of the sludge transportation would also be
enhanced.
4.2.4
With the implementation of odour
control measures, the odour impact assessment results
show that the predicted odour concentration at all
ASRs located in the vicinity of CSTW would comply with the odour
criterion (5 odour units based on an averaging time
of 5 seconds) stipulated in the EIAO-TM.
The Project is considered to have considerable improvement on the air
quality condition at the Study Area as comparing with the situation with the
operation of existing STSTW.
Assessment Scope
and Key Criteria
4.3.1
Potential noise impacts associated with the
construction and operational phases of the project have been assessed in
accordance with the criteria and guidelines as stated in the requirements given
in Section 3.4.2 and Appendix C of the EIA Study Brief, as well as Annex 5 and
Annex 13 of the EIAO-TM. The study
area for noise impact assessment is defined by a distance of 300m from the site
boundary of the Project.
Construction Phase
4.3.2
Construction airborne noise is expected from the
use of Powered Mechanical Equipment (PME) during various construction
activities, such as excavation, concreting, compaction works, demolition
activities, material handling activities etc, at all
land-based works areas including the existing and relocated STSTW, improvement
measures at A Kung Kok Street, alternative accessed
to and from the relocated STSTW and temporary explosives magazine site at A
Kung Kok Shan.
Noise impact arising from construction activities of the Project is
assessed. The predicted maximum
unmitigated construction airborne noise levels at the representative Noise Sensitive
Receivers (NSRs) (locations refer to Figure No. 60334056/ES/4.03)
in the vicinity of the Project work sites would be 70 ¡V 89 dB(A). With the implementation of all
practicable mitigation measures including adoption of quiet PME, use of movable
noise barrier/acoustic mat, and limitation of the number of on-time operating
PMEs within 120m of the Neighbourhood Advice-Action
Council Harmony Manor during construction of the access road to temporary
magazine site, the predicted
maximum construction airborne noise levels at the representative NSRs in
the vicinity of the Project work sites would comply with the EIAO-TM criteria
of 75 dB(A) for residential NSRs and 70 dB(A) for educational NSRs during
normal teaching hours (65 dB(A) during examination period) except occasional
exceedance of noise criterion for examination period by 1 dB(A) at S.K.H. Ma On
Shan Holy Spirit Primary School during examination period in January and June
2021, January and June in 2022, and January 2023. As this NSR is located in
close vicinity of the construction work areas, all practical mitigation
measures have been exhausted. With
reference to the latest examination schedule of this school, the affected
period would be limited to 3 days in each affected examination month. In addition, the affected educational
NSR has been noise insulated with air conditioners. It is therefore considered
that the residual noise impact is in short term period and could be
significantly reduced by keeping the windows closed during the affected
examination periods. To further
reduce the noise impact, it is recommended that the Contractor should closely
liaise with the schools to avoid scheduling the noisy construction works during
examination period as far as practicable.
4.3.3
During the actual construction period, as much
as practically possible, measures should be done to reduce the construction
noise, and on-going liaison with all concerned parties and site monitoring
should also be conducted during the course of the construction period. A construction noise EM&A programme is recommended to check the compliance of the
noise criteria during normal daytime working hours.
4.3.4
Ground-borne construction noise impacts
pertinent to the use of hydraulic breaker, hand-held breaker, drill rig and TBM
would comply with criteria of EIAO-TM.
The predicted maximum construction ground-borne noise levels associated
with the PME use at open works areas at the representative NSRs (locations of
NSRs refer to Figure No. 60334056/ES/4.04) in the vicinity of the work sites would be 40 ¡V 53
dB(A), hence
comply with the EIAO-TM criterion.
No adverse ground-borne construction noise impacts is predicted and therefore no noise
mitigation measure and noise monitoring are proposed.
4.3.5
For the temporary modification works at the
merging point of Ma On Shan Road and temporary access haul road, the provision
of 220m length of noise
barrier of
a height at 10mPD on the
temporary access haul road to replace the existing 150m length of noise barrier at 9.2mPD to 10mPD height on Ma On Sha Road would pose
negligible difference in the overall traffic noise level at the sensitive
facades in the vicinity. Once the
construction work is completed, the noise barrier on the concerned road section
of Ma On Shan Road would be re-installed according to
the existing configuration.
Operational Phase
4.3.6
The noise impact associated with the operation
of the Project has been assessed. The
predicted fixed plant noise levels at the representative NSRs (locations of
NSRs refer to Figure No. 60334056/ES/4.03)
would comply with the criteria based on the plant design information provided
by the Engineer at the time of the assessment. If there is any change in engineering
design information during detailed design stage or fitting-out stage, the fixed
source noise design should be reviewed by the Engineer/Contractor to ensure
that both the Noise Control Ordinance (NCO) and EIAO-TM criteria at the NSRs
can be met in the future. Prior to
the operational phase of the Project, a commissioning test for the equipment in
ventilation buildings, the ventilation shaft, ventilation fan for chiller plant
room and cooling tower at the administration building would be conducted to
ensure compliance with the relevant allowable maximum sound power levels.
Assessment Scope and Key Criteria
4.4.1
The Study area for water quality impact
assessment covered the Victoria Harbour Water Control
Zone (WCZ) and Tolo Harbour
and Channel WCZ as designated under Water Pollution Control Ordinance (WPCO),
including inland water bodies within 500m from the site boundary. Key assessment criteria include Annexes
6 and 14 of the EIAO-TM, Water Quality Objectives (WQO) for Victoria Harbour WCZ and Tolo Harbour and Channel WCZ, Hong Kong Planning Standards and
Guidelines, Water Supplies Department (WSD) target seawater quality objectives,
Technical Memorandum on Standards for Effluents Discharged into Drainage and
Sewerage Systems, Inland and Coastal Waters (TM-DSS), Practice Note for
Professional Persons on Construction Site Drainage (ProPECC
PN 1/94), Section 3.4.3 and Appendix D of the EIA Study Brief.
Representative Sensitive Receivers
4.4.2
In Victoria Harbour
WCZ, major Water Sensitive Receivers (WSRs) identified are WSD flushing water
intakes, cooling water intakes, typhoon shelters and potential water sports
area at Kai Tak. In Tolo Harbour and Channel WCZ,
major WSRs identified are marine water including flushing water intakes,
cooling water intake, bathing beach, typhoon shelter, corals, mangroves, Fish
Culture Zones (FCZs), Sites of Special Scientific Interest (SSSI) and nursery
area for commercial fisheries resources; inland water bodies within 500m from
the site boundary including Shing Mun River, Ma Tai
Stream, and streams along Mui Tsz Lam Road and in Nui Po Shan, water gathering
grounds as well as secondary contact recreation subzone for water recreational
uses.
Construction Phase
Land-based
Construction
4.4.3
Minor water quality impact would be associated
with land-based construction. Impacts may result from surface runoff,
accidental spillage, sewage from on-site construction workers and groundwater
infiltration. Impacts could be
controlled to comply with the WPCO standards by implementing the recommended
mitigation measures.
THEES
Connection Works
4.4.4
Both the Tai Po Sewage Treatment Works (TPSTW)
and existing STSTW are secondary treatment plants with disinfection process.
Under normal operation of the THEES, the Tai Po Effluent Pumping Station
(TPEPS) would pump the secondarily treated and disinfected effluent from TPSTW
via a rising main and a submarine pipeline to the Sha Tin Effluent Pumping Station (STEPS). The STEPS would receive the
secondarily treated and disinfected effluent from both TPSTW and STSTW for
combined discharge to the KTN in the Victoria Harbour
WCZ
via the THEES effluent tunnel.
4.4.5
In order to maintain the current arrangement in
discharging effluent to KTN through THEES tunnel, the provision of a dry construction
zone within the THEES tunnel to allow connection from the CSTW would be essential for
the Project. During the connection works, the THEES Tunnel needs to be
temporarily suspended from its normal operation with effluent bypass into the Tolo Harbour.
4.4.6
To minimize water quality
impact to Tolo Harbour, the
necessary THEES connection works required for this Project will be split
into a number of steps for sequential
and synchronized implementation with THEES maintenance, thereby avoiding
the need for additional temporary suspension of the THEES. Each suspension will
not be longer than 4 weeks and
will be outside the algae blooming season (January to May), and the frequency will be no more
than once per year during the construction phase of the Project. Therefore, no additional water quality
effect on the Tolo Harbour
waters would result from the proposed THEES connection works. No cumulative or residual impact would
be expected during the construction phase of the Project with the recommended
mitigation measures properly implemented.
Operational Phase
4.4.7
The CSTW effluent together with the TPSTW effluent will be discharged
to the Victoria Harbour via the THEES during normal operation.
Compared with the
existing STSTW,
the CSTW has the same design flow capacity and effluent standard. Hence, this Project will not induce any
change to the flow and loading of THEES effluent to the Victoria Harbour.
4.4.8
Maintenance of the THEES tunnel is required to
ensure proper functioning and integrity of the tunnel. During the inspection or
maintenance of the THEES tunnel, temporary suspension of the normal THEES
operation with effluent bypass into the Tolo Harbour is unavoidable in order to provide a safe and dry
zone within the THEES tunnel. It
should be noted that such temporary effluent bypass during THEES
maintenance is
part and parcel of the existing THEES regardless of whether the Project
is implemented or not.
4.4.9
Mathematical modelling was undertaken under this
EIA to study the water quality impact arising from a 4-week THEES maintenance
discharge. The model results
indicated that even
for such a discharge in the algae blooming season (January to May) under
the ultimate development scenario,
the increase
in pollution level in Tolo Harbour
would still
be transient
and reversible.
4.4.10
With the
design capacity, effluent standards and effluent discharge points being the
same as
those of the existing STSTW, this
Project will not change the flow, load and discharge point of the THEES effluent to Victoria Harbour and Tolo Harbour.
4.4.11
In order to further minimize water quality
impact, it is recommended under this Project to schedule the THEES maintenance
outside the algae blooming season (January to May). Water quality modelling
indicates that
the pollution elevation in Tolo Harbour
and the associated recovery period would be significantly reduced and alleviated as compared to the case of inside the algae blooming season (January
to May). An event and action plan
and a water quality monitoring programme (presented
in the standalone EM&A Manual) is proposed for the THEES maintenance events
during both construction and operational phases to minimize water quality
impacts.
4.4.12
A contingency plan has also been formulated to
minimize the impact of emergency discharges and facilitate subsequent
management of the situation. An event and action plan and a water
quality monitoring programme (as presented in the
standalone EM&A Manual) is also proposed for the emergency discharge events
during operational phase to minimize the water quality impacts. No cumulative or residual impact is expected during the operational
phase of the Project with the recommended mitigation measures properly
implemented.
4.5.1
The land contamination assessment is conducted
in accordance with the criteria and guidelines as stated in the requirements
given in Section 3.4.4 and Appendix F of the EIA Study Brief, as well as Annex
19 of the EIAO-TM.
4.5.2
Based on the site appraisal, within
the Project boundary, the existing STSTW and the
temporary works area on Area 73, currently part of a Vehicle
Detention Centre, are considered to be areas with potential
land contamination concerns.
4.5.3
A sampling and testing programme,
targeting the existing STSTW and the temporary works area on Area 73,
has been proposed.
Since the sites will continue to be in use until the
full commissioning of the relocated STSTW, the proposed Site
Investigation works and any necessary remediation action are recommended to be
carried out after decommissioning of the existing STSTW and when
the Area 73 temporary works area is vacated, but prior to re-development.
4.5.4
In addition, two sites (the David Camp and
proposed A Kung Kok Shan Road surface magazine site)
within the Project boundary are inaccessible or yet to be constructed. Further
site walkover is recommended within the sites when access to the camp site is
available and before the decommissioning of the surface magazine site to
confirm the presence of any land contamination. If land contamination were
present, detailed land contamination assessment and remediation would be
required prior to the re-development.
4.5.5
Further site walkover, assessment and
remediation (if necessary), including the submission
of Supplementary Contamination Assessment Plan (CAP(s)), Contamination
Assessment Report/ Remediation Action Plan (CAR(s)/RAP(s)) and Remediation
Report (RR(s)) would follow Environmental Protection Department¡¦s prevailing
guidelines and recommendation in the EIA Study.
4.5.6
With the implementation of further site
walkover, land contamination assessment and, if required, remediation works for
the Project Site, any soil/groundwater contamination would be identified and
properly treated prior to re-development.
Land contamination impacts are therefore considered surmountable to
future occupants.
4.6.1
The hazard to life assessment is conducted in
accordance with the criteria and guidelines as stated in the requirements given
in Section 3.4.5 and Appendix G of the EIA Study Brief, as well as Annex 4 of
the EIAO-TM.
Storage, Transport and Use of Explosives
4.6.2
As discussed in Section
3.4.1 of this ES, to ensure the timely completion
of the Project, Drill-and-Blasting method for rock excavation is proposed. As
further discussed in Section 3.4.2 of this ES,
in view of the large quantity of rock to be excavated, the provision of a temporary
magazine would provide a more reliable explosive supply, allow flexible
blasting time and multiple faces under different excavation sequence and
give maximum tunnel production rates. A Quantitative Risk Assessment
(QRA) for the storage, transport and use of explosives relates to the
construction stage of the Project has been carried out. Since no explosives
will be handled during the operational stage, no QRA would be conducted for the
operational stage.
4.6.3
A robust site selection process has been
undertaken for the proposed temporary magazine. A surface-type
magazine is proposed to be constructed at the location next to the
proposed ventilation shaft with access from the end of A Kung Kok Shan Road. The criteria of the EIAO-TM
for Individual Risk will be met. The assessment results
show that the Societal Risk lies within the ¡§As Low As
Reasonably Practicable (ALARP)¡¨ region in respect of the criteria stipulated
in Annex 4 of the EIAO-TM. All practicable mitigation measures have been identified, including the use of cast boosters and
reduction of explosives quantities to be transported in
each trip. The cost effectiveness of each justifiable mitigation measure has
been assessed. The results show compliance with the ALARP principles and Risk
Guidelines (EIAO-TM Annex 4) provided recommendations are implemented.
High Pressure (HP) Underground Town Gas Transmission Pipelines
4.6.4
The transport route of explosives is close to an
HP underground town gas transmission pipeline. A QRA has therefore been conducted
to assess the increased societal risk arising from the incremental population
during both construction and operational phases of the Project. The individual
risk complies with both the Hong Kong Risk Guidelines and the Institution of
Gas Engineers and Managers (IGEM) Risk Guidelines. The societal risk lies in
the lower ¡§ALARP¡¨ region of the Hong Kong Risk Guidelines for both construction
stage and operational stage scenarios. Compared to the ¡§without Project¡¨
scenarios for both construction and operational stages, it is found that the
ALARP is due to the background population instead of the population induced by
the Project.
4.7.2
Literature review and ecological field surveys
have been conducted.
Terrestrial habitats identified within the assessment area include woodland,
fung shui wood, plantation, shrubland,
cultivated land, developed area, and stream. (Refer to Figure No.
60334056/ES/4.05 and Figure No.
60334056/ES/4.06) Marine habitats within the assessment
area include subtidal hard substrata, soft bottom habitats, and intertidal
habitats. The ecological values of
the identified habitats are rated between low and moderate to high. No sites of conservation importance will
be directly affected.
4.7.3
Direct impacts arising from the proposed land-based
works include permanent loss and temporary loss of some woodland, plantation,
and shrubland, as well as minor habitat fragmentation
of woodland and plantation in Nui Po Shan.
Given the relatively low to moderate ecological values of the habitats
and the small area affected, impacts are anticipated to be generally minor in
nature. The permanent loss of
woodland (0.65 ha) will be mitigated by compensatory planting (approximately
0.92 ha) of native species, while all temporarily affected works area will be
reinstated. A Woodland Compensation
Plan should be prepared to form the basis (e.g. implementation details,
management requirement, and monitoring requirements) and submitted for approval
from EPD at least three months before commencement of compensatory woodland
planting. All temporarily affected
works area will be reinstated.
Avoidance measures would be implemented to preserve a natural stream in
vicinity of the proposed access road on Nui Po Shan (e.g.
provision of an elevated
section at the stream crossing).
4.7.4
Some plant species of conservation importance
were recorded within the Project boundary. To minimise
impacts, a Detailed Vegetation Survey should be conducted prior to the
commencement of construction works to identify potentially affected plant
species. All identified species
would be labelled and fenced off on site for better preservation or, in case of unavoidable loss, for
transplantation according to the Protection and Transplantation Proposal.
4.7.5
There would be no disturbance to marine or
riverbed sediments under the Project and hence loss of marine habitat is
avoided. According to the water
quality impact assessment, no unacceptable ecological impact is anticipated on
marine ecological resources.
Nevertheless, an event and action plan and a water quality monitoring programme should be implemented during construction and
operation phases to verify whether or not impact predictions are
representative, and to ensure that it would not result in unacceptable
impacts. During operation phase,
monitoring of the treated effluent quality from the CSTW should be carried out
to ensure that the effluent quality would comply with the design
standards.
4.7.6
Construction site runoff and other disturbance
impacts resulting from the proposed aboveground works may potentially result in
indirect impact on the streams, wildlife, and some fauna species of
conservation importance. Standard
mitigation measures such as good site practice, control of glare / lighting, minimisation of groundwater infiltration, and water quality
impact control measures are proposed.
4.7.7
Excavation in rock would have relatively minor
potential impacts on groundwater as compared to excavation in soft ground. The rock itself is a natural barrier
with very low permeability which can prevent potential groundwater drawdown in
any soil and aquifer layers above the rock stratum. Thus it would not adversely affect the
groundwater level within the soil layer as well as the water level of the
adjacent streams. Since the
majority of the CSTW is situated in very competent rock stratum in Nui Po Shan,
the impact on groundwater would be minor.
Nonetheless, precautionary measures would be taken in cavern design and
construction to minimize the potential impacts from the change in groundwater
level. Preventive measures such as
pre-grouting and post-grouting, which have been successfully applied in other
tunnel projects in Hong Kong, would be conducted to minimize any impact from
the cavern construction activities to the adjacent groundwater table. Surface water level or groundwater level
near the caverns will be closely monitored during the construction stage to
ensure that the surrounding groundwater level will not be adversely affected
due to the cavern construction activities and presence of the caverns. Post-construction monitoring of
groundwater for 1 year will also be carried out after completion of excavation
works.
4.7.8
With the proper implementation of mitigation
measures, no adverse residual ecological impacts are expected from the
Project. The implementation of
mitigation measures would be subject to regular audit as part of the EM&A programme.
4.8
Fisheries Impact
4.8.1
Potential impacts on fisheries have been
assessed in accordance with Section 3.4.7 and Appendix I of the EIA study brief
as well as Annex 9 and Annex 17 of the EIAO-TM.
4.8.2
No important spawning or nursery grounds were
identified in the immediate vicinity of the existing STSTW, while the nearest
important nursery area for commercial fisheries resources is located in Three
Fathoms Cove in Tolo Channel (approximately 6.5 km
from the existing STSTW). The
nearest FCZs (Yim Tin Tsai FCZ and Yim Tin Tsai (East) FCZ) are located approximately 4.5 km
away from the existing STSTW. The importance of capture
fisheries resources in the vicinity of the existing STSTW was identified
as low in terms of both production weight
and value. Fish fry production was low in the immediate
vicinity of the existing STSTW in Tolo Harbour.
4.8.3
The Project will only involve land-based
construction works. There will be
no disturbance to marine or riverbed sediments. Under the Project design, any Project
effluent bypass to the Tolo Harbour
will be discharged separately through the existing emergency outfalls of the TPSTW and STSTW. Construction of the connection pipes to
existing emergency outfall of STSTW was proposed to be by trenchless method
underneath Shing Mun River. This construction method would not cause disturbance to the marine
sediment and hence no impact
to or loss of fishing ground is anticipated.
4.8.4
During the construction phase, THEES connection
works required for this Project will be arranged to be synchronized with the
THEES maintenance,
such
that no additional water quality impact, and hence fisheries impact from
changes of water quality,
will be induced by the proposed THEES connection works.
4.8.5
Despite
not being specifically induced by this Project, the scenario of THEES
maintenance or bypass under extreme emergency situations during the operation
phase of the Project as
mentioned in Sections 4.4.6 and 4.4.10 have been considered. Indirect
fisheries impacts due to deterioration of water quality are expected during
these abnormal operation periods.
Changes in water quality (e.g. SS, dissolved oxygen (DO), total
inorganic nitrogen (TIN), chlorophyll-a) at Yim Tin Tsai FCZ, Yim Tin Tsai
(East) FCZ, potential subzone of Yim Tin Tsai FCZ, Yung Shue Au FCZ, Lo Fu Wat
FCZ and the nursery area for commercial fisheries resources at Three Fathoms
Cove are expected during these scenarios.
However, no significant changes in water quality parameters are
predicted as the pollution elevation associated with the discharge would be
reversible and hence no unacceptable water quality impacts are expected. With the implementation of mitigation
measures for water quality, no unacceptable fisheries impacts are
expected.
4.9.1
A landscape and visual impact assessment has
been carried out in accordance with Section 3.4.8 and Appendix J of the EIA
study brief, and Annexes 10 and 18 of the EIAO-TM.
4.9.2
The Project will inevitably result in changes
to the existing landscape in the vicinity of the portal areas, the
ventilation shaft outlet and the access road leading to it, during
construction and operation phases. Associated
landscape and visual impacts have been minimized through careful
consideration of alternatives, minimization of works areas, incorporation
of aesthetic external designs and landscape treatments of proposed aboveground
structures.
4.9.3
The Project is generally located within Green
Belt (GB) Zones of the Approved Sha Tin Outline Zoning Plan (OZP) No. S/ST/32
(11.12.2015) and, for a small part,
on the Approved Ma On Shan OZP No.
S/MOS/22 (15.1.2016). It is
recommended that both the Sha Tin OZP and Ma On Shan
OZP shall be amended to incorporate the latest changes arising from the
Project.
4.9.4
Based on a broad brush estimate, approximately
828 existing trees in the three landscape resources (i.e. Amenity Planting
Area in the existing STSTW, Roadside Planting Areas along Ma On
Shan Road and Woodland on Slopes of Nui Po Shan) will be affected by the
proposed works. The affected trees
shall be considered for transplanting in accordance with Development Bureau
Technical Circular (Works) No. 7/2015 - Tree Preservation and the latest
Guidelines on Tree Preservation.
Many of the affected trees are of semi-mature to mature size. None of these are Registered Old and
Valuable Trees (OVTs). Under the proposed scheme for the Project, opportunities
for tree compensation within the Project boundary has been fully explored and
incorporated in the proposed mitigation measures as much as practicable. Approximately 330 nos. of heavy standard
trees and 10,000 nos. of tree whips can be compensated for the loss of existing
trees due to the Project. Tree
Preservation and Removal Proposals including compensation planting scheme shall
be submitted in accordance with the above mentioned technical circular.
4.9.5
Under the Project, there would be temporary loss
of 59,900m2 of existing vegetation on Slopes of Nui Po Shan. With the proposed compensation and
reinstatement woodland mix planting proposals (approximately 34,700 m2),
there would be a net permanent loss of 25,200m2 of vegetation in
Woodland on Slopes of Nui Po Shan.
4.9.6
With the implementation of proposed mitigation
measures, it is predicted that there would be substantial to slight residual
impact on the above listed landscape resources in Section
4.9.4 during construction,
and moderate to insubstantial impact on day 1 of operation. The residual impact on these landscape
resources would be further reduced to slight to insubstantial when the proposed
compensatory planting, buffer planting and woodland mix planting become mature
in year 10 of operation.
4.9.7
It is predicted that there would be substantial
to slight residual impact on four landscape character areas (i.e. Sha Tin
Waterfront Industrial Landscape Character Area (LCA), Ma On Shan Transportation
Corridor LCA, A Kung Kok and Tai Shui
Hang Miscellaneous Urban Fringe LCA and A Kung Kok
Settled Valley LCA) during construction, and moderate to insubstantial impact
on day 1 of operation. The residual impact on these landscape character areas
would be further reduced to slight to insubstantial when the proposed
compensatory planting, buffer planting and woodland mix planting become mature
in year 10 of operation.
4.9.8
Regarding visual impact, it is predicted that
there would be moderate residual impact on residential Visually Sensitive
Receivers (VSRs) in Chevalier Garden (R-01) and Kam Tai Court (R-12) (locations
of VSRs refer to Figure No. 60334056/ES/4.07).
The residual impact on these VSRs would remain moderate on
day 1 of operation and would be reduced to slight when the proposed tree
planting becomes mature in year 10 of operation. (Photomontages refer to Figure No.
60334056/ES/4.08 and Figure No. 60334056/ES/4.09.)
There would be slight to insubstantial residual impact on other VSRs within the
visual envelope during the construction and operation of the Project.
4.9.9
As a whole, the residual landscape and visual
impacts of the proposed Project is considered acceptable with the
proposed mitigation measures implemented during construction and
operation phases.
4.10.1
The Cultural Heritage Impact Assessment is
conducted in accordance with the criteria and guidelines as stated in the
requirements given in Section 3.4.9 and Appendix K of the EIA Study Brief, as
well as Annexes 10 and 19 of the EIAO-TM.
The assessment area includes areas within a distance of 50m from the
site boundary of the Project.
4.10.2
It has assessed current condition and potential
impact on cultural heritage resources within the study area. As no terrestrial and marine
archaeological potential is identified, it is considered that there is no
impact on archaeology and mitigation measures are not required.
4.10.3
Two built heritage resources in Tai Shui Hang
(both are Grade 3 historic buildings) as well as the Pak Kong-Mui Tsz Lam
Trackway (Site of Archaeological Interest) are identified outside the 50m study
area from the site boundary of the Project. Thus, no potential direct or indirect
impact to these cultural heritage resources is anticipated, and therefore no
mitigation measures are required.
4.11.1
The wastes impact assessment is conducted in
accordance with the criteria and guidelines as stated in the requirements given
in Section 3.4.4 and Appendix E of the EIA Study Brief, as well as
Annex 7 and Annex 15 of the EIAO-TM.
Construction
Phase
4.11.2
Construction and Demolition (C&D) materials
will be generated from excavation of rock caverns (at the CSTW site and the
potential explosive magazine site), tunnels, adits,
ventilation/shafts buildings, site formation works and the demolition of the
existing STSTW. These C&D materials comprise both inert and non-inert
components, such as soil, Artificial Hard Materials (AHM), rocks, wood and
metals. Based on the latest layout, the volume of surplus C&D materials is
estimated to be approximately 6,000,000 m3 of inert material and
124,000 m3 of non-inert material (i.e. C&D waste). About 3,740,000 m3 of total
excavated materials is rock, which would be generated from the cavern
constructions. An estimated volume
of 595,000 m3 is soft materials while 1,669,000 m3 would
be AHM (i.e. concrete).
4.11.3
Soft inert C&D materials from the above
construction works will be sorted and reused as filling material as much as
possible. The surplus will be transported to Tuen Mun Area 38 Fill Bank for reuse by other projects. Hard inert C&D material includes
Grade III granitic rock and Grade I & II granitic rock. The Grade III granitic rock and AHM will
be re-used on site as much as possible and the surplus will be transported to Tuen Mun Area 38 Fill Bank for
reuse by other projects. The Grade I & II rock will be transported to Lam Tei Quarry for recycling as useful aggregates for
construction use by other projects.
Non-inert waste will be recycled as far as possible before disposed to
landfill. Opportunities in minimisation of generation and maximisation
of reuse would be continually investigated during the detailed design and
construction phases. With the
implementation of the recommended good site practices and mitigation measures
for the handling, transportation and disposal of the identified waste arising,
adverse environmental impacts is not anticipated.
4.11.4
Other waste materials, including general refuse
and chemical waste,
will also be generated throughout construction. Provided that these
identified wastes will be handled, transported and disposed of using the
recommended methods and that good site practices would be followed, adverse
environmental impacts are not expected.
Operational
Phase
4.11.5
The main waste types to be generated during the
operation phase would be grit and screenings, and sewage sludge. The collection, transportation and
disposal practices of the grit and screenings would follow the existing
arrangements currently in operation at the existing STSTW. The dewatered sludge would be disposed
of to the proposed Sludge Treatment Facilities. Provided proper handling
procedures and disposal method are adopted, adverse environmental impacts are
not expected during the operation phase.
4.12.1
Potential health impact in relation to Toxic Air
Pollutants (TAPs) emissions associated with activities during the operation of
the CSTW have been assessed in accordance with the requirements
given in Section 3.4.10 of EIA Study Brief.
4.12.2
Literature review was conducted to identify the
sewage treatment related TAPs of potential concern for further assessment, and
determine the acceptable toxicity values for non-carcinogenic and carcinogenic
risks assessment.
4.12.3
The risk arising from exposure to TAPs
associated with the emissions of the relocated STSTW is evaluated. The
non-carcinogenic and carcinogenic health impact of the TAPs imposed to the
impacted human receptors (HRs) were assessed and compared with international
guideline levels. The assessment findings revealed that the levels of TAPs at
HRs would be extremely small when compared to the derived reference levels. The
highest incremental cancer risk arising from the operation of CSTW is predicted
to be 7.1 E-08 which is far below the guidance level of 1E-06 adopted by United
States Environmental Protection Agency (USEPA) and it is considered that the
Project would not present an unacceptable risk and no further analysis is
necessary. For the criteria of air pollutants, while it is not possible to rule
out the additional potential health effects from the operation of CSTW with
complete certainty, the impact on health from extremely small additional air
pollutants is likely to be very small and unlikely to be quantifiable.
4.12.4
A minor
portion of treated effluent would be reused but would be limited to
non-potable uses inside the plant and therefore the general
public is not expected to be exposed to the treated effluent. Thus, there is no
health risk to the general public caused from the reuse of treated effluent.
5
Environmental monitoring and audit (EM&A)
5.1.1
An EM&A programme
has been prepared for air quality, noise, water quality, land contamination,
ecology (terrestrial and marine), fisheries, landscape and visual, and waste
management during construction phase.
A summary of the EM&A requirements by each of the environmental
parameters is presented in Table
5.1 below.
Table 5.1 Summary of
EM&A Requirements
|
Prior
to Construction
|
Construction
Phase
|
Operational
Phase
|
Air Quality Impact
|
ü
|
ü
|
ü
|
Noise Impact
|
ü
|
ü
|
ü
|
Water Quality Impact
|
ü
|
ü
|
ü
|
Land Contamination
|
O
|
ü
|
O
|
Hazard to Life
|
O
|
ü
|
O
|
Ecology (Terrestrial and
Marine) Impact
|
ü
|
ü
|
O
|
Fisheries
|
O
|
O
|
O
|
Landscape and Visual Impacts
|
ü
|
ü
|
O
|
Cultural Heritage
|
O
|
O
|
O
|
Waste Management Implication
|
O
|
ü
|
O
|
Health Impact
|
O
|
O
|
O
|
Air Quality Impact
5.1.2
EM&A for potential dust impacts would be conducted
during the construction phase of the Project so as to check compliance with
legislative requirements. Baseline
and impact monitoring of 1-hour average TSP at representative locations are
recommended.
5.1.3
No adverse impact would be generated during the
operational phase of this Project. However, odour monitoring is proposed to be conducted at the deodorizing units in
the first three years upon commissioning of CSTW to determine whether
the deodorizing units can meet the odour removal
performance requirement. An Odour Complaint Registration System is also proposed in the
EM&A programme to ascertain whether the ASRs
experience odour nuisance as a result of emissions
from CSTW.
Noise Impact
5.1.4
An EM&A programme
has been proposed to be established according to the expected occurrence of
noisy activities during construction phase. All the recommended mitigation measures
for daytime normal working activities would be incorporated into the EM&A programme for implementation during construction.
5.1.5
No adverse impact would be generated during the
operational phase of this Project. Prior to the operational phase of the
Project, a commissioning test for the ventilation buildings, the ventilation
shaft, ventilation fan for chiller plant room at administration building and
cooling tower at the administration building would be conducted to ensure
compliance with the relevant allowable maximum sound power levels.
Water Quality Impact
5.1.6
A baseline monitoring programme
at Tolo Harbour is proposed
prior to the commencement of the Project construction works to establish the
baseline water quality conditions.
An event and action plan and a water quality monitoring programme for the THEES maintenance events are proposed
during the construction phase of the Project. Regular site inspections during
the construction phase is also recommended
to be undertaken to inspect the construction activities and works areas
in order to ensure the recommended mitigation measures are properly
implemented.
5.1.7
A water quality monitoring programme
at KTN is proposed after commissioning of this Project to verify if there is
any adverse water quality impact from
the Project. An event and action plan and water
quality monitoring programme for the THEES
maintenance or emergency discharge events are also proposed for the operational phase of the
Project.
Land Contamination
5.1.8
Remediation works, if necessary, would be
carried out during construction phase but prior to commencement of any
construction works. All the mitigation measures as recommended in the EIA Study,
EM&A Manual and future RAP(s) would be implemented during the remediation
works. Regular site inspection during the construction phase have been proposed
to ensure the recommended mitigation measures are properly implemented.
5.1.9
As any contaminated soil / groundwater would be
identified and properly treated prior to re-development, land contamination
during the operational phase is not expected. As such, EM&A during operational
phase is considered not necessary.
Hazard to
Life
5.1.10
Blasting activities regarding storage, transport
and use of explosives should be supervised and audited by competent site staff
to ensure strict compliance with the blasting permit conditions.
Ecological Impact (Terrestrial and
Marine)
5.1.11
Implementation of the recommended mitigation
measures during construction phase would be regularly audited.
5.1.12
No adverse ecological impact during operational
phase is anticipated as the level of disturbance would be comparable to the
existing condition. EM&A during operational phase is considered not
necessary.
Fisheries Impact
5.1.13
No unacceptable residual fisheries impact is
expected from the Project. No monitoring program specific for
fisheries is required. However, an event and action plan and a water
quality monitoring programme is proposed for the
THEES maintenance events during the construction and operational phases of the
Project. Regular site inspections during the construction phase is also
recommended to be undertaken to inspect the construction activities and works
areas in order to ensure the recommended mitigation measures are properly
implemented.
Landscape and Visual Impacts
5.1.14
The EM&A for the implementation of
recommended mitigation measures during construction phase would be regularly
conducted.
5.1.15
No significant adverse impact during operational
phase is anticipated after implementation of the mitigation measures. Therefore, the EM&A works related to
landscape and visual impacts for the operational phase are considered not
necessary.
Cultural
Heritage
5.1.16
No cultural heritage resources are located
within the 50m study area from the site boundary of the Project and no direct
or indirect impact to these cultural heritage resources is anticipated. On this basis, EM&A programme is considered not necessary.
Waste Management Implications
5.1.17
There are stringent regulations, legislations
requirements and contract requirements on the handling, storage, and disposal
of construction waste. Regular site
inspections during the construction phase is proposed to be undertaken to
inspect the construction activities and works areas in order to ensure the
recommended mitigation measures are properly implemented.
5.1.18
Adverse environmental impacts generated from
handling, storage and disposal of waste are not expected from the operation of
the Project with the implementation of good waste management practices.
Therefore, waste monitoring and audit programme for
the operation phase of the Project would not be required.
Health
Impact
5.1.19
Since no adverse health impact is expected from
the Project, EM&A programme for health impact is
not required.
6.1.1
The EIA provides information on the nature and
extent of the environmental impacts likely to arise from the construction and
operation of the CSTW and decommissioning of existing STSTW. The EIA has, where
appropriate, identified mitigation measures to ensure compliance with
environmental legislations and standards.
6.1.2
Overall, the EIA concluded that the Project
would comply with the requirements of the EIAO and EIAO-TM with the implementation
of the proposed mitigation measures during the construction and operational
phases of the CSTW and decommissioning of existing STSTW. The schedule of
implementation of the proposed mitigation measures has been provided in the EIA
Report. An EM&A programme has also been
recommended to check the effectiveness of the proposed mitigation measures.