Contents
Chapter12 ENVIRONMENTAL MONITORING & AUDITING
REQUIREMENTS
12.4 Project Implementation Schedule
12.6 Environmental Management Plan
Appendix
12.1 -
Project
Implementation Schedule
12.1.1
General
·
Provision of a database against which to determine
any short-term or long-term environmental impacts of the Project;
·
Provision of an early indication that any of the
environmental control measures or other operation practices are failing to
achieve the required standards;
·
Provision of data to determine the effectiveness of
any mitigation or control measures implemented through amendments in procedures
during the life of Project;
·
Provision of data to enable an environmental audit
of the construction, operation, restoration and aftercare works to be
undertaken; and
·
Assessment of compliance with the environmental and
pollution control and operation requirements.
12.2.1.1
A project organisation consisting of the Engineer’s Representative (ER),
Independent Environmental Checker (IEC), Environmental Team (ET), Project
Proponent and Contractors should be established to take on the responsibilities
for environmental protection for the Project.
12.2.1.2
The IEC will be appointed by the Project Proponent to conduct
independent auditing on the overall EM&A programme including environmental
and operation monitoring, implementation of mitigation measures, EM&A submissions,
and any other submission required under the Environmental Permit (EP). The organisation, responsibilities of
respective parties and lines of communication with respect to environmental
protection works are given in the EM&A Manual.
12.3.1.1
EM&A is an important aspect in the EIA process which specifies the
timeframe and responsibilities for the implementation of environmental
mitigation measures. The requirements on environmental monitoring (including
baseline and impact monitoring) are given in the EM&A Manual.
12.3.1.2
An EM&A Manual specific to the Project will be prepared based on
individual contractual requirements and latest design information by the ET.
The project specific EM&A Manual will highlight the
following issues:
·
Organisation, hierarchy and responsibilities of the
Contractor, Project Proponent, ET and IEC with respect to the EM&A
requirements during construction and operational phases of the Project;
·
Information on project organisation and programming
of construction activities;
·
Requirements with respect to the construction
schedule and necessary EM&A programme to track the varying environmental
impacts;
·
Details of methodologies to be adopted, including
all field, laboratory and analytical procedures, and details on quality
assurance;
·
Procedure for undertaking on-site environmental
audits;
·
Definition of Action and Limit Levels;
·
Establishment of Event and Action Plans;
·
Requirements of reviewing pollution sources and
working procedures required in the event of non-compliance of environmental
criteria and complaints;
·
Requirements for reviewing the implementation of
mitigation measures, and effectiveness of environmental protection and
pollution control measures adopted; and
·
Presentation of requirements for EM&A data and
appropriate reporting procedures.
12.4
Project Implementation Schedule
12.4.1.1
A Project Implementation Schedule (PIS) has been prepared and included
in
Appendix 12.1 and the EM&A
Manual to summarise all the required mitigation measures need to be implemented
during the construction and operational phase of the Project. The implementation responsibilities are also
identified in the PIS. The EM&A
Manual will also present the requirements for environmental monitoring and
auditing (e.g. monitoring and audit frequency), throughout the entire
construction phase.
12.4.1.2
The Contractor should review the mitigation measures and PIS with
respect to the design developments and construction methodology. In case the Contractor needs to update the
mitigation measures and PIS, the EM&A Manual should be updated accordingly.
12.5.1.1
Detailed requirements of the EM&A programme are described in the
EM&A Manual. Measurements and
activities are summarised as follows:
·
Baseline monitoring;
·
Impact monitoring;
·
Remedial actions in accordance with the Event and
Action Plan within the timeframe in case the specified criteria in the EM&A
Manual being exceeded;
·
Logging and keeping records of monitoring results;
·
Real-time reporting of construction monitoring
data, wherever practicable, for the Project through a dedicated internet
website; and
·
Preparation and submission of Monthly and Final EM&A
Reports.
12.6
Environmental Management Plan
12.6.1.1 The Contractor shall prepare the Environmental Management Plan (EMP) (including a Waste Management Plan. WMP), Construction Method Statement prior to the commencement of construction works and obtain approval from ER and IEC and other relevant authorities to encompass the recommended environmental protection / mitigation measures with respect to their latest construction methodology and programme.
12.6.1.2
A systematic EMP shall be set up by the Contractor to ensure effective
implementation of the mitigation measures, monitoring and remedial requirements
presented in the EIA, EM&A and PIS. The Project Proponent and IEC will
audit the implementation status against the EMP and advise the necessary
remedial actions required. These remedial actions shall be enforced by the Engineer’s
Representative through contractual means.
12.6.1.3
The EMP will require the Contractor (together with it’s sub-contractors)
to define in details how to implement the recommended mitigation measures in
order to achieve the environmental performance defined in the Hong Kong
environmental legislation and the EIA documentation. The EMP would also need to
include a Waste Management Plan to demonstrate the Contractor’s proposal to
minimize the waste generation and maximize the re-use of spoil as far as practicable
12.6.1.4
The review of on-site environmental performance shall be undertaken by
the Project Proponent and IEC through a systematic checklist and audit once the
project commences. The environmental performance review programme comprises a
regular assessment on the effectiveness of the EMP.