Contents

 

                                             

6            WATER QUALITY IMPACT   3

6.1           Legislation, Standards and Guidelines  3

6.2           Baseline Conditions  13

6.3           Identification of Pollution Sources  16

6.4           Prediction and Evaluation of Impacts During Construction Phase  17

6.5           Prediction and Evaluation of Impacts During Operational Phase  21

6.6           Mitigation Measures during Construction Phase  24

6.7           Mitigation Measures during Operational Phase  27

6.8           Residual Impacts  28

6.9           Conclusion  28

 

 

              Figures

              Figure 6.1            Locations of Water Quality Sensitive Receivers

 

 

 

 

 

 


6                              WATER QUALITY IMPACT

6.1                         Legislation, Standards and Guidelines

6.1.1                  General

6.1.1.1                The relevant legislations, standards and guidelines applicable to present study for the assessment of water quality impacts include:

·         Water Pollution Control Ordinance (WPCO) (Cap. 358);

·         Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters (TM-DSS)

·         Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO);

·         Town Planning Board Guidelines for Application for Developments within Deep Bay Area, Under Section 16 of the Town Planning Ordinance, (TPB PG-NO. 12C), “No Net Increase in Pollution Loads Requirement in Deep Bay”;

·         Hong Kong Planning Standards and Guidelines (HKPSG); and

·         ProPECC PN 1/94 “Construction Site Drainage”

6.1.2                  Water Pollution Control Ordinance (Cap. 358)

6.1.2.1                The entire Hong Kong waters are divided into ten Water Control Zones (WCZs) and four supplementary WCZs under the WPCO. Each WCZ has a designated set of statutory Water Quality Objectives (WQOs) designed to protect the inland and/or marine environment and its users. The Project is located in the Deep Bay WCZ and the corresponding WQOs are summarised in Table 6.1.

Table 6.1 Water Quality Objectives for Deep Bay Water Control Zones

Parameters

Objectives

Sub-Zone

Aesthetic appearance

(a) Waste discharges shall cause no objectionable odours or discolouration of the water.

Whole zone

(b) Tarry residues, floating wood, articles made of glass, plastic, rubber or of any other substances should be absent.

Whole zone

(c) Mineral oil should not be visible on the surface. Surfactants should not give rise to a lasting foam.

Whole zone

(d) There should be no recognisable sewage-derived debris.

Whole zone

(e) Floating, submerged and semi-submerged objects of a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be absent.

Whole zone

(f) Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits.

Whole zone

Bacteria

(a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in one calendar year.

Secondary Contact Recreation Subzone and Mariculture Subzone (L.N. 455 of 1991)

(b) The level of Escherichia coli should be zero per 100 ml, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

(c) The level of Escherichia coli should not exceed 1000 per 100 ml, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

(d) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.

Yung Long Bathing Beach Subzone (L.N. 455 of 1991)

Colour

(a) Waste discharges shall not cause the colour of water to exceed 30 Hazen units.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

(b) Waste discharges shall not cause the colour of water to exceed 50 Hazen units.

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

Dissolved Oxygen

(a) Waste discharges shall not cause the level of dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling occasions during the year; values should be taken at 1 metre below surface.

Inner Marine Subzone except Mariculture Subzone

(b) Waste discharges shall not cause the level of dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling occasions during the year; values should be calculated as water column average (arithmetic mean of at least 2 measurements at 1 metre below surface and 1 metre above seabed). In addition, the concentration of dissolved oxygen should not be less than 2 milligrams per litre within 2 metres of the seabed for 90% of the sampling occasions during the year.

Outer Marine Subzone except Mariculture Subzone

(c) The dissolved oxygen level should not be less than 5 milligrams per litre for 90% of the sampling occasions during the year; values should be taken at 1 metre below surface.

Mariculture Subzone

(d) Waste discharges shall not cause the level of dissolved oxygen to be less than 4 milligrams per litre.

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground Subzones and other inland waters of the Zone

pH

(a) The pH of the water should be within the range of 6.5-8.5 units. In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.2 units.

Marine waters except Yung Long Bathing Beach Subzone

(b) Waste discharges shall not cause the pH of the water to exceed the range of 6.5-8.5 units.

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

(c) The pH of the water should be within the range of 6.0-9.0 units.

Other inland waters

(d) The pH of the water should be within the range of 6.0-9.0 units for 95% of samples. In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.5 units.

Yung Long Bathing Beach Subzone

Temperature

Waste discharges shall not cause the natural daily temperature range to change by more than 2.0 degrees Celsius.

Whole Zone

Salinity

Waste discharges shall not cause the natural ambient salinity level to change by more than 10%

Whole Zone

Suspended solids

(a) Waste discharges shall neither cause the natural ambient level to be raised by 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities.

Marine waters

(b) Waste discharges shall not cause the annual median of suspended solids to exceed 20 milligrams per litre.

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Ganges Subzone, Indus Subzone, Water Gathering Ground Subzones and other inland waters

Ammonia

The un-ionized ammoniacal nitrogen level should not be more than 0.021 milligram per litre, calculated as the annual average (arithmetic mean).

Whole Zone

Nutrients

(a) Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants.

Inner and Outer Marine Subzones

(b) Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.7 milligram per litre, expressed as annual mean.

Inner Marine Subzone

(c) Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 milligram per litre, expressed as annual water column average (arithmetic mean of at least 2 measurements at 1 metre below surface and 1 metre above seabed).

Outer Marine Subzone

5 day biochemical oxygen demand

(a) Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 3 milligrams per litre.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones


(b) Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 5 milligrams per litre.

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

Chemical oxygen demand

(a) Waste discharges shall not cause the chemical oxygen demand to exceed 15 milligrams per litre.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones

(b) Waste discharges shall not cause the chemical oxygen demand to exceed 30 milligrams per litre.

Yuen Long & Kam Tin (Lower) Subzone and other inland waters

Toxins

(a) Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to toxicant interactions with each other.

Whole Zone

(b) Waste discharges shall not cause a risk to any beneficial uses of the aquatic environment.

Whole Zone

Phenol

Phenols shall not be present in such quantities as to produce a specific odour, or in concentration greater than 0.05 milligrams per litre as C6H5OH.

Yung Long Bathing Beach Subzone

Turbidity

Waste discharges shall not reduce light transmission substantially from the normal level.

Yung Long Bathing Beach Subzone

6.1.3                  Technical Memorandum for Effluents Discharge into Drainage and Sewerage Systems, Inland & Coastal Waters

6.1.3.1                Apart from the WQOs, Section 21 of the WPCO also specifies the limits to control the physical, chemical and microbial parameters for effluent discharges into drainage and sewage system at both inland and coastal waters under the TM-DSS. The discharge limits vary with the effluent flow rates and the sewage from the Project, treated after sewage treatment works, should comply with the standards for effluent discharged into inland waters, which would be used for either irrigation, pond fish culture or amenity subject to the exact locations. Group B (for irrigation), C (for pond fish culture) and D (for amenity) inland water standards in TM-DSS are therefore adopted and the effluent discharge standards are presented in Table 6.2 to Table 6.4.

Table 6.2 Standards for effluents discharged into Group B Inland Waters 

Parameter

Flowrate (m3/day)

Ł 200

> 200 & Ł400

> 400 &  Ł 600

> 600 &  Ł 800

> 800 &  Ł 1000

> 1000 & Ł 1500

> 1500 & Ł 2000

> 2000 & Ł 3000

pH (pH units)

6.5-8.5

6.5-8.5

6.5-8.5

6.5-8.5

6.5-8.5

6.5-8.5

6.5-8.5

6.5-8.5

Temperature ()

35

30

30

30

30

30

30

30

Colour (lovibond units)
(25mm cell length)

1

1

1

1

1

1

1

1

Suspended solids

30

30

30

30

30

30

30

30

BOD

20

20

20

20

20

20

20

20

COD

80

80

80

80

80

80

80

80

Oil & Grease

10

10

10

10

10

10

10

10

Iron

10

8

7

5

4

3

2

1

Boron

5

4

3

2.5

2

1.5

1

0.5

Barium

5

4

3

2.5

2

1.5

1

0.5

Mercury

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

Cadmium

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

Selenium

0.2

0.2

0.2

0.2

0.2

0.1

0.1

0.1

Other toxic metals individually

0.5

0.5

0.2

0.2

0.2

0.1

0.1

0.1

Total Toxic metals

2

1.5

1

0.5

0.5

0.2

0.2

0.2

Cyanide

0.1

0.1

0.1

0.08

0.08

0.05

0.05

0.03

Phenols

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

Sulphide

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

Fluoride

10

10

8

8

8

5

5

3

Sulphate

800

800

600

600

600

400

400

400

Chloride

1000

1000

800

800

800

600

600

400

Total phosphorus

10

10

10

8

8

8

5

5

Ammonia nitrogen

5

5

5

5

5

5

5

5

Nitrate + nitrite nitrogen

30

30

30

20

20

20

10

10

Surfactants (total)

5

5

5

5

5

5

5

5

E. coli (count/100ml)

100

100

100

100

100

100

100

100

Notes:

[1] All units in mg/L unless otherwise stated

Table 6.3 Standards for effluents discharged into Group C Inland Waters 

Parameter

Flowrate (m3/day)

Ł 100

> 100 & Ł500

> 500 & Ł 1000

> 1000 & Ł 2000

pH (pH units)

6-9

6-9

6-9

6-9

Temperature ()

30

30

30

30

Colour (lovibond units)
(25mm cell length)

1

1

1

1

Suspended solids

20

10

10

5

BOD

20

15

10

5

COD

80

60

40

20

Oil & Grease

1

1

1

1

Boron

10

5

4

2

Barium

1

1

1

0.5

Iron

0.5

0.4

0.3

0.2

Mercury

0.001

0.001

0.001

0.001

Cadmium

0.001

0.001

0.001

0.001

Silver

0.1

0.1

0.1

0.1

Copper

0.1

0.1

0.05

0.05

Selenium

0.1

0.1

0.05

0.05

Lead

0.2

0.2

0.2

0.1

Nickel

0.2

0.2

0.2

0.1

Other toxic metals individually

0.5

0.4

0.3

0.2

Total Toxic metals

0.5

0.4

0.3

0.2

Cyanide

0.05

0.05

0.05

0.01

Phenols

0.1

0.1

0.1

0.1

Sulphide

0.2

0.2

0.2

0.1

Fluoride

10

7

5

4

Sulphate

800

600

400

200

Chloride

1000

1000

1000

1000

Total phosphorus

10

10

8

8

Ammonia nitrogen

2

2

2

1

Nitrate + nitrite nitrogen

30

30

20

20

Surfactants (total)

2

2

2

1

E. coli (count/100ml)

1000

1000

1000

1000

Notes:

[1] All units in mg/L unless otherwise stated

Table 6.4 Standards for effluents discharged into Group D Inland Waters 

Parameter

Flowrate (m3/day)

200

200
and
400

400
and
600

600
and
800

800
and
1000

1000
and
1500

1500
and
2000

2000
and
3000

pH (pH units)

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

Temperature ()

30

30

30

30

30

30

30

30

Colour (lovibond units)
(25mm cell length)

1

1

1

1

1

1

1

1

Suspended solids

30

30

30

30

30

30

30

30

BOD

20

20

20

20

20

20

20

20

COD

80

80

80

80

80

80

80

80

Oil & Grease

10

10

10

10

10

10

10

10

Iron

10

8

7

5

4

2.7

2

1.3

Boron

5

4

3.5

2.5

2

1.5

1

0.7

Barium

5

4

3.5

2.5

2

1.5

1

0.7

Mercury

0.1

0.05

0.001

0.001

0.001

0.001

0.001

0.001

Cadmium

0.1

0.05

0.001

0.001

0.001

0.001

0.001

0.001

Other toxic metals individually

1

1

0.8

0.8

0.5

0.5

0.2

0.2

Total Toxic metals

2

2

1.6

1.6

1

1

0.5

0.4

Cyanide

0.4

0.4

0.3

0.3

0.2

0.1

0.1

0.05

Phenols

0.4

0.3

0.2

0.1

0.1

0.1

0.1

0.1

Sulphide

1

1

1

1

1

1

1

1

Sulphate

800

600

600

600

600

400

400

400

Chloride

1000

800

800

800

600

600

400

400

Fluoride

10

8

8

8

5

5

3

3

Total phosphorus

10

10

10

8

8

8

5

5

Ammonia nitrogen

20

20

20

20

20

20

20

10

Nitrate + nitrite nitrogen

50

50

50

30

30

30

30

20

Surfactants (total)

15

15

15

15

15

15

15

15

E. coli (count/100ml)

1000

1000

1000

1000

1000

1000

1000

1000

Notes:

[1] All units in mg/L unless otherwise stated

 

6.1.3.2                The TM-DSS also specifies the discharge standards into foul sewers leading into Government sewage treatment plants as Table 6.5 and Table 6.6. Subject to the flow rate of the effluents, corresponding standards for the effluent discharge into government foul sewers should be followed.  


Table 6.5 Standards for effluents discharged into foul sewers leading into Government sewage treatments plants

Parameter

Flowrate (m3/day)

Ł 10

> 10 & Ł100

> 100 & Ł 200

> 200 & Ł 400

> 400 & Ł 600

> 600 & Ł 800

> 800 & Ł 1000

> 1000 & Ł 1500

> 1500 & Ł 2000

> 2000 & Ł 3000

> 3000 & Ł 4000

> 4000 & Ł 5000

> 5000 & Ł 6000

pH (pH units)

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

6-10

Temperature ()

43

43

43

43

43

43

43

43

43

43

43

43

43

Suspended solids

1200

1000

900

800

800

800

800

800

800

800

800

800

800

Settleable solids

100

100

100

100

100

100

100

100

100

100

100

100

100

BOD

1200

1000

900

800

800

800

800

800

800

800

800

800

800

COD

3000

2500

2200

2000

2000

2000

2000

2000

2000

2000

2000

2000

2000

Oil & Grease

100

100

50

50

50

40

30

20

20

20

20

20

20

Iron

30

25

25

25

15

12.5

10

7.5

5

3.5

2.5

2

1.5

Boron
Barium

8
8

7
7

6
6

5
5

4
4

3
3

2.4
2.4

1.6
1.6

1.2
1.2

0.8
0.8

0.6
0.6

0.5
0.5

0.4
0.4

Mercury

0.2

0.15

0.1

0.1

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

Cadmium

0.2

0.15

0.1

0.1

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

0.001

Copper

4

4

4

3

1.5

1.5

1

1

1

1

1

1

1

Nickel

4

3

3

2

1.5

1.5

1

0.8

0.7

0.7

0.6

0.6

0.6

Chromium

2

2

2

2

1

0.7

0.6

0.4

0.3

0.2

0.1

0.1

0.1

Zinc

5

5

4

3

1.5

1.5

1

0.8

0.7

0.7

0.6

0.6

0.6

Silver

4

3

3

2

1.5

1.5

1

0.8

0.7

0.7

0.6

0.6

0.6

Other toxic metals individually

2.5

2.2

2

1.5

1

0.7

0.6

0.4

0.3

0.2

0.15

0.12

0.1

Total toxic metals

10

10

8

7

3

2

2

1.6

1.4

1.2

1.2

1.2

1

Cyanide

2

2

2

1

0.7

0.5

0.4

0.27

0.2

0.13

0.1

0.08

0.06

Phenols

1

1

1

1

0.7

0.5

0.4

0.27

0.2

0.13

0.1

0.1

0.1

Sulphide

10

10

10

10

5

5

4

2

2

2

1

1

1

Sulphate

1000

1000

1000

1000

1000

1000

1000

900

800

600

600

600

600

Total nitrogen

200

200

200

200

200

200

200

100

100

100

100

100

100

Total phosphorus

50

50

50

50

50

50

50

25

25

25

25

25

25

Surfactants (total)

200

150

50

40

30

25

25

25

25

25

25

25

25

Notes:

[1]         All units in mg/L unless otherwise stated

Table 6.6 Standards for effluents discharged into foul sewers leading into Government sewage treatments plants with microbial treatment

Parameter

Flowrate (m3/day)

Ł 10

> 10 & Ł100

> 100 & Ł 200

> 200 & Ł 400

> 400 & Ł 600

> 600 & Ł 800

> 800 & Ł 1000

> 1000 & Ł 1500

> 1500 & Ł 2000

> 2000 & Ł 3000

> 3000 & Ł 4000

> 4000 & Ł 5000

> 5000 & Ł 6000

Copper

1.5

1

1

1

0.8

0.6

0.5

0.4

0.3

0.2

0.15

0.1

0.05

Notes:

[1]         All units in mg/L unless otherwise stated

 

 


6.1.4                  Environmental Impact Assessment Ordinance (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process

6.1.4.1                Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO) specifies the assessment methods and criteria for impact assessment. This Study follows the TM-EIAO to assess the potential water quality impact that may arise during both the construction and operational phases of the Project. Sections in the TM-EIAO relevant to the water quality impact assessment are:

·         Annex 6 - Criteria for Evaluating Water Pollution; and

·         Annex 14 - Guidelines for Assessment of Water Pollution.

6.1.5                  No Net Increase in Pollution Loads Requirement in Deep Bay

6.1.5.1                In addition to the provisions of the TM, the ‘No Net Increase in Pollution Loads Requirement’ aims to provide protection to the inland and marine water quality of the Deep Bay WCZ. According to EPD’s “Deep Bay Water Quality Regional Control Strategy Study”, the pollutions entering into Deep Bay have exceeded the assimilative capacity of the water body. Further increasing the pollution loads to the water body is therefore environmentally undesirable.

6.1.5.2                In accordance with Town Planning Board Guideline No.12C, the pollution loads of concern should be offset by equivalent reduction of current loads for new discharge into Deep Bay. The policy ensures that developments within the Deep Bay catchment areas do not result in an increase in pollution loads to both the inland and marine waters.

6.1.6                  Hong Kong Planning Standards and Guidelines

6.1.6.1                Chapter 9 of the Hong Kong Planning Standards and Guidelines (HKPSG) outlines environmental requirements that need to be considered in land use planning. The recommended guidelines, standards and guidance cover the selection of suitable locations for the developments and sensitive uses, provision of environmental facilities, and design, layout, phasing and operational controls to minimise adverse environmental impacts. It also lists out environmental factors that influence land use planning and recommends buffer distances for land uses.

6.1.7                  ProPECC PN 1/94 “Construction Site Drainage”

6.1.7.1                Professional Persons Environmental Consultative Committee Practice Notes (ProPECC Note PN1/94) on Construction Site Drainage provides guidelines for the handling and disposal of construction discharges. It is applicable to this study for the control of site runoff and wastewater generated during the construction phase.  The types of discharges from construction sites outlined in the ProPECC Note PN1/94 include:

·         Surface runoff;

·         Groundwater;

·         Boring and drilling water;

·         Wastewater from concrete batching plant;

·         Wheel washing water;

·         Bentonite slurries;

·         Water for testing and sterilization of water retaining structures and water pipes;

·         Wastewater from building construction and site facilities; and

·         Acid cleaning, etching and pickling wastewater.

6.2                         Baseline Conditions

6.2.1                  Existing Hydrology

6.2.1.1                The Project Site falls within the Deep Bay WCZ according to the WPCO. It is located at Yuen Long Town Nullah between West Rail Long Ping Station and south of Kau Yuk Road. Downstream of the project is a drainage channel along the edge of Tai Tseng Wai and the ultimate discharge of this drainage channel is downstream of Shan Pui River and Inner Deep Bay. Apart from Yuen Long Creek, the inner Deep Bay was most affected by the discharges from Shenzhen River as well as Kam Tin River and Tin Shui Wai Nullah. The WQO compliance rate of the Deep Bay WCZ in 2014 was 40%, same as from 2008 to 2013 except in 2012 (53%).

6.2.2                  Baseline Water Quality Conditions

6.2.2.1                The closest water quality monitoring stations are Yuen Long Creek (YL1 – YL4) and Table 6.7 summarises the water quality monitoring data for YL1 – YL4. The locations of water quality monitoring stations are shown in Figure 6.1.

Table 6.7 Water Quality at Yuen Long Creek (YL1 – YL4) for Year 2014

Parameter

YL1

YL2

YL3

YL4

Dissolved oxygen (mg/L)

5.2

6.5

3.6

3.8

(3.3 - 8.0)

(3.3 - 9.7)

(1.8 - 7.4)

(1.3 - 5.6)

pH

7.3

7.4

7.3

7.2

(7.1 - 7.5)

(7.2 - 7.5)

(7.1 - 7.8)

(6.9 - 8.0)

SS (mg/L)

16

5

17

34

(5 - 450)

(2 - 9)

(3 - 47)

(5 - 73)

5-day Biochemical Oxygen Demand (mg/L)

19

8

29

86

(4 - 90)

(2 - 13)

(5 - 140)

(6 - 280)

Chemical Oxygen Demand (mg/L)

23

26

35

70

(8 - 120)

(17 - 37)

(12 - 140)

(23 - 200)

Oil & grease (mg/L)

<0.5

0.6

0.6

0.9

(<0.5 - 0.9)

(<0.5 - 1.0)

(<0.5 – 2.2)

(<0.5 – 8.2)

Faecal coliforms (cfu/100mL)

460,000

150,000

1,500,000

3,000,000

(86,000 - 2,300,000)

(35,000 - 1,200,000)

(240,000 - 6,600,000)

(150,000 - 12,000,000)

E.  coli(cfu/100mL)[4]

160,000

78,000

490,000

1,200,000

(49,000 - 870,000)

(4,300 - 930,000)

(80,000 - 2,000,000)

(48,000 - 5,700,000)

Ammonia-nitrogen (mg/L)

6.95

14.50

5.50

7.40

(0.98 - 15.00)

(6.90 - 26.00)

(1.20 - 16.00)

(3.70 - 14.00)

Nitrate-nitrogen (mg/L)

0.58

2.00

<0.01

<0.01

(<0.01 - 1.20)

(0.17 - 5.90)

(<0.01 - 1.40)

(<0.01 - 0.76)

Total Kjeldahl nitrogen (mg/L)

9.10

17.50

7.65

11.00

(1.50 - 26.00)

(7.30 - 31.00)

(2.10 - 23.00)

(4.80 - 22.00)

Ortho-phosphate (mg/L)

0.90

2.40

0.54

0.48

(0.17 - 3.40)

(1.40 - 3.20)

(0.10 - 1.70)

(0.25 - 0.86)

Total phosphorus (mg/L)

1.25

2.75

0.92

1.10

(0.28 - 4.40)

(1.60 - 3.60)

(0.26 - 2.70)

(0.39 - 2.00)

Total sulphide (mg/L)

0.03

<0.02

<0.02

0.08

(<0.02 - 0.09)

(<0.02 - 0.09)

(<0.02 - 0.33)

(<0.02 - 0.25)

Aluminium (µg/L)

216

55

172

205

(140 - 1,438)

(<50 - 98)

(72 - 332)

(101 - 848)

Cadmium (µg/L)

<0.1

<0.1

<0.1

<0.1

(<0.1 - 0.4)

(<0.1 - <0.1)

(<0.1 - 0.1)

(<0.1 - 0.3)

Chromium (µg/L)

<1

<1

<1

<1

(<1 - 2)

(<1 - <1)

(<1 - 3)

(<1 - 4)

Copper (µg/L)

6

3

5

5

(3 - 23)

(2 - 6)

(2 - 14)

(2 - 8)

Lead (µg/L)

4

<1

3

2

(2 - 44)

(<1 - 2)

(<1 - 10)

(<1 - 5)

Zinc (µg/L)

48

30

42

47

(22 - 206)

(15 - 82)

(26 - 92)

(24 - 88)

Flow (L/s)

202

40

490

125

(10 - 303)

(11 - 83)

(160 - 1,538)

(81 - 205)

Notes:

[1]   Data presented are in annual medians of monthly samples; except those for faecal coliforms and E. coli which are in annual geometric means.

[2]   Figures in brackets are annual ranges.

[3]   NM indicates no measurement taken.

[4]   cfu - colony forming unit.

[5]   Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits.

[6]   Extracted from EPD River Water Quality in Hong Kong 2014

 

6.2.2.2                According to EPD’s River Monitoring Report, Yuen Long Creek’s overall compliance rate was 52% in 2014, higher than 51% in 2013. The compliance rates for upstream stations YL1 and YL2 were 58% and 60% respectively in 2014 as compared with 72% and 60% respectively in 2013. The rates for the stations in the middle of Yuen Long township (YL3 and YL4) were 57% and 33% in 2014 as compared with 42% and 30% in 2013 respectively. The river was still subject to discharges from remaining livestock farms, unsewered village house establishments and other specific uses (Storage and Workshop, and Open Storage).

6.2.2.3                The Deep Bay is located at downstream of the Yuen Long Town Nullah. As the water quality impacts on the downstream water systems depend on the scale and nature of the discharge of upstream area, the Inner Deep Bay is considered as a WSR of the Project. The closest marine water quality monitoring stations to the estuary of the downstream water system of Yuen Long Town Nullah is located at the Inner Deep Bay (i.e. DM1, DM2 and DM3).  Table 6.8 summarises the water quality monitoring data for DM1 – DM3. The locations of water quality monitoring stations are shown in Figure 6.1.

Table 6.8 Water Quality at Inner Deep Bay (DM1 – DM3) for Year 2014

Parameter

DM1

DM2

DM3

Temperature (oC)

24.2

24.4

24.4

(14.3 -32.1)

(14.5 – 31.9)

(15.1 – 32.0)

Salinity

15.5

17.5

21.2

(3.5 – 24.4)

(5.6 – 25.8)

(10.7 – 29.4)

Dissolved oxygen (mg/L)

3.7

4.6

5.5

(1.3 – 6.1)

(2.6 – 6.8)

(4.1 – 7.3)

Dissolved oxygen (mg/L) (Bottom)

N.M

N.M

N.M

Dissolved oxygen (% Saturation)

48

60

73

(18 – 73)

(36 – 81)

(60 – 88)

Dissolved oxygen (% Saturation) (Bottom)

N.M

N.M

N.M

pH

7.4

7.5

7.7

(7.1 – 7.7)

(7.3 – 7.9)

(7.5 – 7.9)

Secchi Disc Depth (m)

1.3

1.2

1.3

(0.7 – 1.7)

(0.7 – 2.0)

(0.4 – 2.0)

Turbidity (NTU)

29.5

20.5

10.2

(12.6 – 48.2)

(10.3 – 40.2)

(5.4 – 15.1)

SS (mg/L)

46.2

23.0

15.5

(15.0 – 95.0)

(13.0 – 41.0)

(4.9 – 53.0)

5-day Biochemical Oxygen Demand (mg/L)

3.1

2.4

1.0

(1.6 – 6.7)

(0.8 – 6.7)

(0.4 – 2.7)

Ammonia-nitrogen (mg/L)

2.080

1.410

0.536

(0.930 – 4.500)

(0.330 – 2.800)

(0.069 – 1.700)

Unionised Ammonia (mg/L)

0.026

0.025

0.014

(0.006 – 0.077)

(0.005 – 0.076)

(0.001 – 0.045)

Nitrite-nitrogen (mg/L)

0.367

0.291

0.184

(0.170 – 0.560)

(0.100 – 0.570)

(0.055 – 0.350)

Nitrate-nitrogen (mg/L)

1.030

0.918

0.759

(0.380 – 2.500)

(0.460 – 1.800)

(0.410 – 1.100)

Total inorganic nitrogen (mg/L)

3.48

2.61

1.48

(2.36 – 5.74)

(1.56 – 3.75)

(0.84 – 3.07)

Total Kjeldahl nitrogen (mg/L)

2.78

1.94

0.85

(1.00 – 6.00)

(0.79 – 3.90)

(0.24 – 2.40)

Total nitrogen (mg/L)

4.17

3.15

1.79

(2.43 – 6.80)

(2.02 – 4.85)

(1.12 – 3.77)

Orthophosphate Phosphorus (mg/L)

0.213

0.183

0.093

(0.110 – 0.320)

(0.110 – 0.260)

(0.045 – 0.180)

Total Phosphorus (mg/L)

0.31

0.27

0.13

(0.18 – 0.50)

(0.17 – 0.41)

(0.08 – 0.24)

Silica (as SiO2) (mg/L)

7.53

6.46

4.31

(4.70 – 12.00)

(2.90 – 11.00)

(1.40 – 8.50)

Chlorophyll-a (µg/L)

6.4

7.6

4.7

(1.7 – 17.0)

(1.8 – 31.0)

(0.4 – 18.0)

E.  coli (count/100mL)

1300

380

37

(72 – 140000)

(36 – 7800)

(<1 – 840)

Faecal coliforms (count/100mL)

3600

1000

110

(150 – 250000)

(81 – 14000)

(5 – 2700)

Notes:

[1]     Unless otherwise specified, data presented are depth-averaged (A) values calculated by taking the means of three depths: Surface (S), Mid-depth (M), Bottom (B).

[2]     Data presented are annual arithmetic means of the depth-averaged results except for E.coli and faecal coliforms which are annual geometric means.

[3]     Data in brackets indicate the ranges.

[4]     N.M. – not measured.

6.2.2.4                According to EPD’s “Marine Water Quality Monitoring in Hong Kong in 2014”, the WQO compliance rate of the Deep Bay WCZ in 2014 was 40%, same as from 2008 to 2013 except in 2012 (53%).

6.2.2.5                Similar to the previous years, the Deep Bay WCZ had relatively high nutrient levels in 2014. The total inorganic nitrogen (TIN) level in the Deep Bay Inner Subzone (i.e. 1.5 – 3.5 mg/L) was higher than the respective TIN objective of 0.7 mg/L. Non-compliance with the ammonia-nitrogen and dissolved oxygen objective was also observed at two of the three stations in the Deep Bay Inner Subzone.

6.2.3                  Water Sensitive Receivers

6.2.3.1                In order to identify the water quality sensitive receivers (WSRs) in the vicinity, a desktop study has been conducted. The study has reviewed the Yuen Long OZP (S/YL/22) has been conducted together with site visits. The identified WSR is presented in Table 6.9 and shown in Figure 6.1.

Table 6.9 Water quality sensitive receivers

ID

WSRs

Status

WSR1

Yuen Long Creek

·   Drainage nullah within Yuen Long Town Centre

·   Discharge into Deep Bay

WSR2

Shan Pui River

·   Downstrem of the Yuen Long Town Nullah

·   Discharge into Deep Bay

WSR3

Inner Deep Bay

·   The inner Deep Bay was most affected by the discharges from Shenzhen River as well as unsewered villages, Kam Tin River, Yuen Long Creek and Tin Shui Wai Nullah.

6.3                         Identification of Pollution Sources

6.3.1                  Construction Phase

6.3.1.1                The main water pollution sources of the Project during construction phase includes:

·         Construction activities within Yuen Long Town Nullah (e.g. excavation, piling, construction of pile cap, etc);

·         Construction surface runoff (including accidental chemicals spillage); and

·         Sewage from site workforce.

6.3.1.2                According to the latest design, there is a total of 5 columns and 6 box culverts supporting the entire elevated pedestrian corridor. As mentioned in Section 3.5.1.3 and Figure 3.2, out of these supporting structures, only 2 columns and 6 box culverts will be located inside the Yuen Long Town Nullah and they would approximately occupy 720 m3 of Yuen Long Nullah which is about 1.3% of the volume of Yuen Long Nullah for the section along the elevated pedestrian corridor. For the construction activities within the nullah, temporary working platform and cofferdams with water tight feature will be constructed to isolate the working area from the flow of the nullah. Any pollutants generated from the above sources may entering into the WSRs and pose potential water quality impact.

6.3.1.3                The presence of the temporary working platform and cofferdams within the nullah may also pose potential impact on the drainage characteristics, such as capacity, flow characteristics, etc., of the nullah. Sufficient flow area will be maintained to provide passage of a storm event in accordance with DSD Technical Circular No. 14/2000 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System” and DSD Practice Note No. 1/2004 “Design Rainfall Depth for Temporary Works within the Dry Season”.  

6.3.2                  Operational Phase

6.3.2.1                The potential water pollution source during the operational phase would be surface runoff from the elevated pedestrian corridor. The surface runoff may contain grit, oil and debris from the pedestrians and cause potential water quality impact to the WSRs.

6.3.2.2                Similar to construction phase, the presence of columns of the proposed elevated pedestrian corridor and box culverts may also pose potential impact on the drainage characteristics of the nullah.

6.4                         Prediction and Evaluation of Impacts During Construction Phase

6.4.1                  Construction activities within Yuen Long Town Nullah

6.4.1.1                The Project will be constructed along the Yuen Long Town Nullah, which is a channelized river with a dry weather flow (DWF) channel. In dry seasons, the majority of the base flow from the catchment would utilize the DWF channel and most of the area in nullah would remain dry, except during occasional heavy rainfall. The construction works within the nullah, such as excavation and modification of the existing nullah, will be undertaken during dry seasons. Nevertheless, watertight cofferdams will be constructed to isolate the working area from the flow of nullah. Hence, these temporary cofferdams would provide sufficient measures even during heavy rainfall. Sufficient flow area, will be retained to provide passage of storm events in accordance with DSD Technical Circular No. 14/2000 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System” and DSD Practice Note No. 1/2004 “Design Rainfall Depth for Temporary Works within the Dry Season”. Water pumps would be used to collect any construction site surface runoff and ingress / seepage water within the cofferdam. The collected construction site surface runoff and ingress / seepage water would be diverted to the on-site wastewater treatment facilities for treatment to satisfactory levels before discharge. Together with the temporary platforms to be constructed, all these would constrain any SS released to the river waters during construction activities. Prior to the completion of the temporary platform, any temporary stockpile should be stored outside the nullah and at location away from the air sensitive receivers. Bunds will be installed around the stockpile area and stock material will be covered with tarpaulin to minimize leakage as practicable as possible. If storage within nullah is unavoidable, stockpile should be located within the cofferdam which will be designed to be water tight and be covered with tarpaulin. Once the temporary platform is completed, any stockpile should be stored on the temporary platforms which should be designed to be water tight to prevent leakage. The stockpile should be also removed from the site as soon as possible and overnight storage should be avoided. Therefore, adverse water quality impact is not anticipated with the implementation of the mitigation measures recommended in Section 6.6.

6.4.1.2                Box culverts at the pedestrian interchanges will be constructed within the nullah. According to the latest design, box culverts will be constructed at pedestrian interchanges at Yuen Long On Ning Road, Castle Peak Road – Yuen Long Section and Kau Yuk Road. For each pedestrian interchange, box culverts will be constructed cell by cell so that the construction activities will not be conducted concurrently. Similar to the construction of columns within the nullah, temporary cofferdams with water tight features will be used to isolate the construction site from the nullah water. Hence, release of SS into the nullah is also considered unlikely with provision of temporary watertight cofferdams during construction works. Therefore, adverse water quality impact is not anticipated with the implementation of the mitigation measures recommended in Section 6.6.

6.4.1.3                As mentioned in Section 6.4.1.1 to Section 6.4.1.2, cofferdams and temporary platform will be constructed during construction of columns and box culverts to prevent release of the SS and other pollutants into the nullah water. These cofferdams may pose potential impacts on the drainage characteristic of the nullah.

6.4.1.4                As mentioned in Section 3.6.1.1, , the construction activities at the eastern side, central part and western side of the nullah would be conducted separately to minimize the potential hydraulic impact in order to maintain sufficient capacity for the passage of flow over the entire nullah during construction phase. Since the construction works and use of cofferdams will be implemented in phases and hence not all the cofferdams would be in place concurrently. Together with the fact that the construction works within the nullah would be conducted during the dry seasons. This arrangement will ensure that the impacts on the hydrology and water quality of the nullah would be minimized.

6.4.1.5                The Contractor would be requested to carry out detail design of the cofferdams in accordance with the DSD Technical Circular No. 14/2000 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System” and DSD Practice Note No. 1/2004 “Design Rainfall Depth for Temporary Works within the Dry Season” for DSD approval in order to finalize options of these temporary structure to avoid adverse impact to the drainage characteristics of the nullah.

6.4.2                  Construction Site Runoff

6.4.2.1                During rainstorm events, construction site runoff would come from all over the works site. The surface runoff might be polluted by:

·         Runoff and erosion from site surfaces, earth working areas and stockpiles;

·         Wash water from dust suppression sprays and wheel washing facilities; and

·         Accidental chemicals spillage such as fuel, oil, solvents and lubricants from maintenance of construction machinery and equipment.

6.4.2.2                Construction runoff may cause physical, biological and chemical effects. The physical effects include potential blockage of drainage channels and increase of suspended solid levels in the Deep Bay WCZ. Runoff containing significant amounts of concrete and cement-derived material may cause primary chemical effects such as increasing turbidity and discoloration, elevation in pH, and accretion of solids. A number of secondary effects may also result in toxic effects to water biota due to elevated pH values, and reduced decay rates of faecal micro-organisms and photosynthetic rate due to the decreased light penetration.  Therefore, good site practices and mitigation measures would be required to minimize any potential impact to nearby water sensitive receivers. With the implementation of mitigation measures recommended in Section 6.6, adverse water quality impact is not anticipated.

6.4.3                  Sewage from Workforce

6.4.3.1                Sewage effluents will arise from the sanitary facilities provided for the on-site construction workforce. According to Table T-2 of Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning, the unit flow is 0.23 m3/day/employed population. The characteristics of sewage would include high levels of BOD5, Ammonia and E. coli counts. Since portable chemical toilets and sewage holding tank will be provided, no adverse water quality impact is anticipated.

6.4.4                  Cumulative Water Quality Impact during Construction Phase

Concurrent Projects

6.4.4.1                As discussed in Chapter 3, the tentative commencement year for the construction of the Project is Year 2018 with target full completion in Year 2022. Concurrent projects in the vicinity of the Project, which may have cumulative environmental impacts, have been discussed in Section 3.7 and shown in Figure 3.1. Key concurrent projects of water quality concern during the construction phase of the Project have been identified and are summarised in the Table 6.10. The implementation programme of these concurrent projects are provided by the respective project proponents. Where information is not available, references have been made to the best available information such as EIA reports and respective project proponents’ websites.

Table 6.10 Key concurrent projects for water quality impact assessment during construction phase

Key Concurrent Projects

Tentative Programme

Potential Cumulative Impact

Start

Complete

West Rail Long Ping Station (North) Property Development

2013

2018

Water quality

West Rail Long Ping Station (South) Property Development

2014

2019

Water quality

Housing Sites in Yuen Long South[1]

-

-

Water quality

Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che

2017

2022

Water quality

Notes:

[1]   No construction programme is available at the time preparing this report. Considering the first population intake year would be Year 2026, the cumulative water quality impact during construction phase would be also considered in this EIA study as a conservative approach.

West Rail Long Ping Station (North) Property Development

6.4.4.2                For the West Rail Long Ping Station (North) Property Development, the construction period will overlap with the Project in Year 2018.

6.4.4.3                The property development is a land-based project. The major sources of the water quality impact are the construction site surface runoff, accidental spillage of chemicals and sewage from the work force. As the wastewater from the construction site and sewage from the work force will be collected and treated to statutory limits before discharging to the public drainage system, which is connected to the Yuen Long Town Nullah, and sewage will be proper handled. Hence, potential water quality impact from the project is not anticipated since the property development are also required to comply with the relevant environmental legislations for wastewater discharge and handling of sewage.

West Rail Long Ping Station (South) Property Development

6.4.4.4                For the West Rail Long Ping Station (South) Property Development, the construction period will overlap with the Project in Year 2018 and Year 2019.

6.4.4.5                The property development is a land-based project. The major sources of the water quality impact are the construction site surface runoff, accidental spillage of chemicals and sewage from the work force. As the wastewater from the construction site and sewage from the work force will be collected and treated to statutory limits before discharging to the public drainage system, which is connected to the Yuen Long Town Nullah, and sewage will be proper handled. Hence, potential water quality impact from the project is not anticipated since the property development are also required to comply with the relevant environmental legislations for wastewater discharge and handling of sewage.

Housing Sites in Yuen Long South

6.4.4.6                For the Housing Sites in Yuen Long South, there is no construction programme available at the time preparing this report. As the first population year is Year 2026 and the project will be developed in stages, cumulative water quality impact from the housing developments project is also considered for conservative assessment.

6.4.4.7                According to the project profile of the housing development project (ESB-279/2014), potential water quality impact would be arise from various construction activities, including site formation, sediment removal, re-alignment of stream and rivers, concrete washings, bore piling, construction of bridges / underpasses / buildings, construction and upgrading of road networks, site workshop or depot and sewage effluent from the workforce.  As the wastewater from the construction site and sewage from the work force will be collected and treated to statutory limits before discharging to the public drainage system and sewage will be proper handled, potential water quality impact from the project is not anticipated since EIA study will be conducted to assess the potential water quality impact, including the potential hydraulic impact. Mitigation measures would be recommended in the EIA study for the water quality impact to comply with the relevant environmental legislations for wastewater discharge and handling of sewage.

Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che

6.4.4.8                For the Drainage Improvement Works near Four Village in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che, the construction period will overlap with the Project from Year 2018 to Year 2022.

6.4.4.9                According to the project profile of the drainage improvement works (ESB-279/2014), the major sources of the water quality impact are the construction site surface runoff, other potential release to the aquatic environment and effluent from the construction workforce. As the wastewater from the construction site and sewage from the work force will be collected and treated to statutory limits before discharging to the public drainage system and sewage will be proper handled, potential water quality impact from the project is not anticipated since EIA study will be conducted to assess the potential water quality impact, including the potential hydraulic impact. Mitigation measures would be recommended in the EIA study for the water quality impact to comply with the relevant environmental legislations for wastewater discharge and handling of sewage.

Cumulative Impact during the Construction Phase

6.4.4.10            As mentioned in Section 6.4.1 to Section 6.4.3, the Project will not generate significant water quality impact during the construction phase with the implementation of the recommended mitigation measures, such as site management, use of temporary cofferdams, use of portable chemical toilets, etc.

6.4.4.11            In consideration of both the Project and concurrent projects (as mentioned in Section 6.4.4.2 to Section 6.4.4.9) will not generate significant water quality impact. Adverse cumulative water quality impact is not anticipated.  

6.5                         Prediction and Evaluation of Impacts During Operational Phase

6.5.1                  Surface Runoff from the Elevated Pedestrian Corridor

6.5.1.1                Surface runoff from the elevated pedestrian corridor is the only source of the water pollution from the Project during operational phase. The runoff may contain grit, oil and debris from the pedestrians.

6.5.1.2                Proper drainage system including gratings at the gully inlets will be provided to remove grit and debris before the runoff discharge to the public storm water drainage system or the Yuen Long Town Nullah. As the nature of surface runoff is similar to the existing condition and hence no adverse water quality impact is anticipated with the provision of the drainage system.

6.5.2                  Permanent Structure of the Elevated Pedestrian Corridor

6.5.2.1                According to the latest design, the existing areas to be occupied by the proposed elevated pedestrian corridor are already paved.  Hence, the Project will not increase the surface runoff. In addition, the catchment area of the Project is very small in comparing with the overall Yuen Long drainage basin which has a basin area of 93 km2. Hence, the Project will not have any significant impact on the existing surface runoff hydrographs. Furthermore, the Project will not transverse any existing flood storage area. Therefore, there will be no loss in flood storage arising from the Project.

6.5.2.2                While the Project will not increase the amount of surface runoff and velocity, there are 2 footbridge columns located within the nullah. In addition, a total of 6 box culverts will be constructed at the pedestrian interchanges which will reduce the volume of the nullah by about 720 m3 (i.e. 1.3%) for the section under the elevated pedestrian corridor. As these permanent structures will decrease the cross-section area of the nullah, the water level of the nullah will be increased, especially during high flow conditions.

6.5.2.3                According to the latest design, the maximum increase in water levels under a 1 in 50 year peak flow event and under a 1 in 200 year peak flow event would be over 0.5m and would not meet DSD requirements and thus may increase flood risk. Therefore, mitigation measures, such as construction of parapet wall, use of lens-shaped footbridge column to reduce head loss, etc., will be required to mitigate the flood risk generated by the Project. With the recommended mitigation measure in Section 6.7, the flood risk can be mitigated to acceptable level and adverse water quality impact is therefore not anticipated.

6.5.3                  Cumulative Water Quality Impact during Operational Phase

Concurrent Projects

6.5.3.1                The tentative commencement year for the construction of the Project is Year 2018 with target full completion in Year 2022. Concurrent projects in the vicinity of the Project, which may have cumulative environmental impacts, have been discussed in Section 3.7. Key concurrent projects of water quality concern during the operation phase of the Project have been identified and are summarised in the Table 6.11. In consideration that the sewage generated from the occupiers of the two property development projects during operational phase will be collected by the sewage system and treated by sewage treatment works before discharge and the surface runoff has no difference in the nature comparing with the existing conditions. Hence, no potential water pollution source is identified for the property development projects during the operational phase and no cumulative impact from these two property development projects is therefore anticipated. The implementation programme of these concurrent projects are provided by the respective project proponents. Where information is not available, references have been made to the best available information such as EIA reports and respective project proponents’ websites.

Table 6.11 Key concurrent projects for water quality impact assessment during  operation phase

Key Concurrent Projects

Tentative Programme

Potential Cumulative Impact

Start

Complete

Improvement of Yuen Long Town Nullah (Town Centre Section) – Stage 1 Improvement Works

3rd quarter of 2022

2026

Water quality and drainage characteristics

Improvement of Yuen Long Town Nullah (Town Centre Section) – Stage 2 Beautification Works

2027

2029

Water quality and drainage characteristics

Housing Sites in Yuen Long South

-

-

Water quality and drainage characteristics

Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che

2017

2022

Water quality and drainage characteristics

Improvement of Yuen Long Town Nullah (Town Centre Section) – Stage 1 Improvement Works and Stage 2 Beautification Works

6.5.3.2                According to the drainage impact assessment of the Nullah Improvement Works, which has been approved by DSD, the hydraulic impact of the Nullah Improvement Works would be minimal. Further assessment on the hydraulic impact of the Nullah Improvement Works will be conducted during the EIA study of the Nullah Improvement Works. Suitable mitigation measures would be recommended to reduce the hydraulic impact to acceptable level.

6.5.3.3                As mentioned in Section 3.7.2, a dry weather flow interception system will be constructed to intercept the polluted dry weather flow being discharged to the Yuen Long Town Nullah from the town centre section and upstream main nullah. Refer to Section 4.4 of the project profile of the Nullah Improvement Works (DIR-227/2013), water quality and odour issue in the Town Centre Section of the nullah will be alleviated once the improvement works completed. Hence, the nullah improvement works would benefit the water quality of the nullah during operational phase and adverse cumulative water quality impact is therefore not anticipated.

Housing Sites in Yuen Long South

6.5.3.4                According to the project profile of the housing development project (ESB-246/2012), the operation of the development will result in increases of sewage and surface runoff and changes to the hydrological regime of the drainage basins. In addition, nullah revitalizing works and creation of new watercourse, flood retention facilities and reedbed are also proposed in the Stage 3 Community Engagement Digest. The proposed works would also cause potential impact to the hydrological regime in the vicinity.

6.5.3.5                For the hydraulic impact, further assessment will be conducted during the EIA study of the housing development project. Suitable mitigation measures would be recommended to reduce the hydraulic impact to acceptable level.

6.5.3.6                For the water quality impact, proper drainage and sewerage works, and silt and oil traps are recommended in the project profile to serve the housing development and to prevent ingress of pollutants to the storm water system respectively. In addition, a sewage treatment works of tertiary treatment level is proposed in the Stage 3 Community Engagement Digest. With the implementation of these mitigation measures, no adverse water quality impact is anticipated during the operational phase.

Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che

6.5.3.7                According to the Section 3.2 of the project profile of the drainage improvement works (ESB-279/2014), the project only involves widening of existing streams and channels and the construction of pipelines. The upgraded channels and the pipes will be for stormwater only. Therefore, no adverse water quality impact is anticipated during operational phase. Further assessment on the hydraulic impact, if necessary, will be conducted during the EIA study of the drainage improvement works. Suitable mitigation measures would be recommended to reduce the hydraulic impact to acceptable level.

Cumulative Impact during the Operational Phase

6.5.3.8                As mentioned in Section 6.5.1 and Section 6.5.2, the Project will not generate significant water quality impact during the operation phase with the implementation of the recommended mitigation measures, such as construction of parapet wall, use of lens-shaped footbridge column to reduce head loss, etc..

6.5.3.9                In consideration of both the Project and concurrent projects (as mentioned in Section 6.5.3.2 to Section 6.5.3.7) will not generate significant water quality impact. Adverse cumulative water quality impact is not anticipated.

6.6                         Mitigation Measures during Construction Phase

6.6.1                  General Site Operation

6.6.1.1                In accordance with the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94), best management practices should be implemented as far as practicable as below:

·         At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works. Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities.

·         Diversion of natural stormwater should be provided as far as possible. The design of temporary on-site drainage should prevent runoff going through site surface, construction machinery and equipment in order to avoid or minimize polluted runoff. Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal. The system capacity shall be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped.

·         The dikes or embankments for flood protection should be implemented around the boundaries of earthwork areas. Temporary ditches should be provided to facilitate the runoff discharge into an appropriate watercourse, through a silt/sediment trap. The silt/sediment traps should be incorporated in the permanent drainage channels to enhance deposition rates.

·         The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. The detailed design of the sand/silt traps should be undertaken by the contractor prior to the commencement of construction.

·         All exposed earth areas should be completed and vegetated as soon as possible after earthworks have been completed.  If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means.

·         All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms.  Deposited silt and grit should be removed regularly and disposed of by spreading evenly over stable, vegetated areas.

·         If the excavation of trenches in wet periods is necessary, it should be dug and backfilled in short sections wherever practicable. Water pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.

·         All open stockpiles of construction materials (for example, aggregates, sand and fill material) should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

·         Manholes should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers.

·         Precautions to be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecasted, and actions to be taken during or after rainstorms are summarized in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events.

·         All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and sited wheel washing facilities should be provided at every construction site exit where practicable.  Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

·         Oil interceptors should be provided in the drainage system downstream of any oil/fuel pollution sources. The oil interceptors should be emptied and cleaned regularly to prevent the release of oil and grease into the storm water drainage system after accidental spillage. A bypass should be provided for the oil interceptors to prevent flushing during heavy rain.

·         Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid water quality impacts.

·         All fuel tanks and storage areas should be provided with locks and sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank to prevent spilled fuel oils from reaching water sensitive receivers nearby.

·         Regular environmental audit on the construction site should be carried out in order to prevent any malpractices.  Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the water bodies, marsh and ponds. 

6.6.1.2                By adopting the best management practices, it is anticipated that the impacts of general site operation will be reduced to satisfactory levels before discharges. The details of best management practices will be highly dependent to actual site condition and Contractor shall apply for a discharge license under WPCO.

6.6.2                  Implementation of Temporary Cofferdams during Construction Phase

6.6.2.1                Cofferdam should be constructed to isolate the construction activities from the nullah water. The detail design of the cofferdams will be conducted by the Contractor during the construction phase to fulfil the requirements in DSD Technical Circular No. 14/200 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System for DSD approval in order to formulate feasible options of these temporary structure.

6.6.3                  Mitigation Measure for Construction Activities / Sites in close proximity to the Dry Weather Flow Channel

6.6.3.1                In addition to Section 6.6.1 and Section 6.6.2, following mitigation measures are also recommended for the construction activities / sites in close proximity to the dry weather flow channel:

·         Water pumps should be used to collect any construction site surface runoff and ingress / seepage water within the cofferdam. The collected construction site surface runoff and ingress / seepage water should be diverted to the on-site wastewater treatment facilities for treatment to satisfactory levels before discharge;

·         Prior to the completion of the temporary platform, any temporary stockpile should be stored outside the nullah and at location away from the air sensitive receivers. Bunds should be installed around the stockpile area and stock material should be covered with tarpaulin to minimize leakage as practicable as possible;

·         Stockpile should be located within the cofferdam which will be designed to be water tight and be covered with tarpaulin if storage within nullah is unavoidable,

·         Once the temporary platform is completed, any stockpile should be stored on the temporary platforms which should be designed to be water tight to prevent leakage;

·         Removal of stockpile from the site as soon as possible and overnight storage should be avoided;

·         Avoidance of stockpiling materials near the dry weather flow channel; and

·         Avoidance of major excavation during high stream flow.

6.6.4                  Emergency Contingency Plan

6.6.4.1                Given the construction activities will be conducted inside or above the nullah, the nullah would be potentially affected during construction phase when there is accidental spillage of chemicals or leakage of polluting water into the nullah. Therefore, an emergency contingency plan should be prepared by the Contractor to state the details of action in such an event. The Contractor should prepare the contingency plan prior to the commencement of construction works and for submission to IEC, Engineer and EPD for approval.

6.6.5                  Sewage from Workforce

6.6.5.1                Portable chemical toilets and sewage holding tanks should be provided for handling the construction sewage generated by the workforce. A licensed contractor should be employed to provide appropriate and adequate portable toilets to cater 0.23 m3/day/employed population and be responsible for appropriate disposal and maintenance.

6.6.5.2                Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the Project. Regular environmental audit on the construction site should be conducted in order to provide an effective control of any malpractices and achieve continual improvement of environmental performance on site. It is anticipated that sewage generation during the construction phase of the Project would not cause water quality impact after undertaking all required measures.

6.7                         Mitigation Measures during Operational Phase

6.7.1                  Surface Runoff from Elevated Pedestrian Corridor

6.7.1.1                As discussed in Section 6.5, adverse water quality impact is not anticipated with the proper installation of drainage system. Hence, no specific mitigation measures would be required during the operational phase.

6.7.2                  Permanent Structure of the Elevated Pedestrian Corridor

6.7.2.1                As discussed in Section 6.5, the Project would provide mitigation measures to mitigate the flood risk of the Yuen Long Town Nullah. According to the latest design, the following mitigation measures are recommended to mitigate the impact to acceptable level:

·         construction of parapet wall, that the height is subject to further drainage impact assessment, which is capable to containing passage of 50 year design events with 500mm freeboard and passage of 200 year design event;

·         adopting of lens-shaped footbridge column to reduce head loss; and

·         connecting individual rows of supporting column at the three existing road bridges to reduce head loss.

6.7.2.2                As mentioned in Section 3.4.3.2, the size of permanent structure inside the nullah would be also minimized. Width of columns and walls within nullah will not exceed 1m in width and will be orientated in line with the nullah flow. Drainage impact assessment would be conducted to mitigate the potential flood risk and hydraulic impact to acceptable level.

6.8                         Residual Impacts

6.8.1.1                With implementation of the recommended mitigation measures, the Project would not generate unacceptable residual water quality impacts.

6.9                         Conclusion

6.9.1.1                During construction phase, potential water pollution and impact sources have been identified as construction of elevated pedestrian corridor within Yuen Long Town Nullah, construction site surface runoff, sewage from site workforce and temporary structure within the nullah. With the full implementation of the recommended mitigation measures, such as covering excavated materials and providing sedimentation tanks on-site etc., no adverse water quality impact is anticipated.

6.9.1.2                During the operational phase, the potential water quality impact is mainly surface runoff from the elevated pedestrian corridor and permanent structure of the proposed elevated pedestrian corridor within the nullah. With the proper installation of drainage system and recommended mitigation measures, no adverse water quality impact is anticipated.