Contents
6.1 Legislation, Standards and Guidelines
6.3 Identification of Pollution Sources
6.4 Prediction and Evaluation of Impacts During
Construction Phase
6.5 Prediction and Evaluation of Impacts During
Operational Phase
6.6 Mitigation Measures during Construction Phase
6.7 Mitigation Measures during Operational Phase
Figure 6.1
Locations
of Water Quality Sensitive Receivers
6.1
Legislation, Standards and Guidelines
6.1.1 General
6.1.1.1
The relevant legislations, standards and
guidelines applicable to present study for the assessment of water quality
impacts include:
·
Water Pollution
Control Ordinance (WPCO) (Cap. 358);
·
Technical
Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland
and Coastal Waters (TM-DSS)
·
Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on
Environmental Impact Assessment Process (TM-EIAO);
·
Town Planning
Board Guidelines for Application for Developments within Deep Bay Area, Under
Section 16 of the Town Planning Ordinance, (TPB PG-NO. 12C), “No Net Increase
in Pollution Loads Requirement in Deep Bay”;
·
Hong Kong Planning
Standards and Guidelines (HKPSG); and
·
ProPECC PN 1/94
“Construction Site Drainage”
6.1.2
Water Pollution Control Ordinance (Cap. 358)
6.1.2.1 The entire Hong Kong waters are divided into ten Water Control Zones (WCZs) and four supplementary WCZs under the WPCO. Each WCZ has a designated set of statutory Water Quality Objectives (WQOs) designed to protect the inland and/or marine environment and its users. The Project is located in the Deep Bay WCZ and the corresponding WQOs are summarised in Table 6.1.
Table 6.1 Water Quality Objectives for Deep Bay Water Control Zones
Objectives |
Sub-Zone |
|
Aesthetic
appearance |
(a) Waste discharges
shall cause no objectionable odours or discolouration of the water. |
Whole zone |
(b) Tarry
residues, floating wood, articles made of glass, plastic, rubber or of any
other substances should be absent. |
Whole zone |
|
(c) Mineral oil
should not be visible on the surface. Surfactants should not give rise to a
lasting foam. |
Whole zone |
|
(d) There should
be no recognisable sewage-derived debris. |
Whole zone |
|
(e) Floating,
submerged and semi-submerged objects of a size likely to interfere with the
free movement of vessels, or cause damage to vessels, should be absent. |
Whole zone |
|
(f) Waste
discharges shall not cause the water to contain substances which settle to
form objectionable deposits. |
Whole zone |
|
Bacteria |
(a) The level of Escherichia coli should not exceed 610
per 100 mL, calculated as the geometric mean of all samples collected in one
calendar year. |
Secondary Contact
Recreation Subzone and Mariculture Subzone (L.N. 455 of 1991) |
(b) The level of Escherichia coli should be zero per
100 ml, calculated as the running median of the most recent 5 consecutive
samples taken at intervals of between 7 and 21 days. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones |
|
(c) The level of Escherichia coli should not exceed
1000 per 100 ml, calculated as the running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days. |
Yuen Long &
Kam Tin (Lower) Subzone and other inland waters |
|
(d) The level of Escherichia coli should not exceed 180
per 100 mL, calculated as the geometric mean of all samples collected from
March to October inclusive in one calendar year. Samples should be taken at
least 3 times in a calendar month at intervals of between 3 and 14 days. |
Yung Long Bathing
Beach Subzone (L.N. 455 of 1991) |
|
Colour |
(a) Waste
discharges shall not cause the colour of water to exceed 30 Hazen units. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones |
(b) Waste
discharges shall not cause the colour of water to exceed 50 Hazen units. |
Yuen Long &
Kam Tin (Lower) Subzone and other inland waters |
|
Dissolved Oxygen |
(a) Waste
discharges shall not cause the level of dissolved oxygen to fall below 4
milligrams per litre for 90% of the sampling occasions during the year;
values should be taken at 1 metre below surface. |
Inner Marine
Subzone except Mariculture Subzone |
(b) Waste
discharges shall not cause the level of dissolved oxygen to fall below 4
milligrams per litre for 90% of the sampling occasions during the year;
values should be calculated as water column average (arithmetic mean of at
least 2 measurements at 1 metre below surface and 1 metre above seabed). In
addition, the concentration of dissolved oxygen should not be less than 2
milligrams per litre within 2 metres of the seabed for 90% of the sampling
occasions during the year. |
Outer Marine
Subzone except Mariculture Subzone |
|
(c) The dissolved
oxygen level should not be less than 5 milligrams per litre for 90% of the
sampling occasions during the year; values should be taken at 1 metre below
surface. |
Mariculture
Subzone |
|
(d) Waste
discharges shall not cause the level of dissolved oxygen to be less than 4
milligrams per litre. |
Yuen Long &
Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges
Subzone, Water Gathering Ground Subzones and other inland waters of the Zone |
|
pH |
(a) The pH of the
water should be within the range of 6.5-8.5 units. In addition, waste discharges
shall not cause the natural pH range to be extended by more than 0.2 units. |
Marine waters
except Yung Long Bathing Beach Subzone |
(b) Waste
discharges shall not cause the pH of the water to exceed the range of 6.5-8.5
units. |
Yuen Long &
Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges
Subzone and Water Gathering Ground Subzones |
|
(c) The pH of the
water should be within the range of 6.0-9.0 units. |
Other inland
waters |
|
(d) The pH of the
water should be within the range of 6.0-9.0 units for 95% of samples. In
addition, waste discharges shall not cause the natural pH range to be
extended by more than 0.5 units. |
Yung Long Bathing
Beach Subzone |
|
Temperature |
Waste discharges
shall not cause the natural daily temperature range to change by more than
2.0 degrees Celsius. |
Whole Zone |
Salinity |
Waste discharges
shall not cause the natural ambient salinity level to change by more than 10% |
Whole Zone |
Suspended solids |
(a) Waste
discharges shall neither cause the natural ambient level to be raised by 30%
nor give rise to accumulation of suspended solids which may adversely affect
aquatic communities. |
Marine waters |
(b) Waste
discharges shall not cause the annual median of suspended solids to exceed 20
milligrams per litre. |
Yuen Long & Kam
Tin (Upper and Lower) Subzones, Beas Subzone, Ganges Subzone, Indus Subzone,
Water Gathering Ground Subzones and other inland waters |
|
Ammonia |
The un-ionized
ammoniacal nitrogen level should not be more than 0.021 milligram per litre,
calculated as the annual average (arithmetic mean). |
Whole Zone |
Nutrients |
(a) Nutrients
shall not be present in quantities sufficient to cause excessive or nuisance
growth of algae or other aquatic plants. |
Inner and Outer
Marine Subzones |
(b) Without
limiting the generality of objective (a) above, the level of inorganic
nitrogen should not exceed 0.7 milligram per litre, expressed as annual mean. |
Inner Marine
Subzone |
|
(c) Without
limiting the generality of objective (a) above, the level of inorganic
nitrogen should not exceed 0.5 milligram per litre, expressed as annual water
column average (arithmetic mean of at least 2 measurements at 1 metre below
surface and 1 metre above seabed). |
Outer Marine
Subzone |
|
5 day biochemical
oxygen demand |
(a) Waste
discharges shall not cause the 5-day biochemical oxygen demand to exceed 3
milligrams per litre. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones |
|
Yuen Long &
Kam Tin (Lower) Subzone and other inland waters |
|
Chemical oxygen
demand |
(a) Waste
discharges shall not cause the chemical oxygen demand to exceed 15 milligrams
per litre. |
Yuen Long & Kam
Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water
Gathering Ground Subzones |
(b) Waste
discharges shall not cause the chemical oxygen demand to exceed 30 milligrams
per litre. |
Yuen Long &
Kam Tin (Lower) Subzone and other inland waters |
|
Toxins |
(a) Waste
discharges shall not cause the toxins in water to attain such levels as to
produce significant toxic carcinogenic, mutagenic or teratogenic effects in
humans, fish or any other aquatic organisms, with due regard to biologically
cumulative effects in food chains and to toxicant interactions with each
other. |
Whole Zone |
(b) Waste
discharges shall not cause a risk to any beneficial uses of the aquatic
environment. |
Whole Zone |
|
Phenol |
Phenols shall not
be present in such quantities as to produce a specific odour, or in
concentration greater than 0.05 milligrams per litre as C6H5OH. |
Yung Long Bathing
Beach Subzone |
Turbidity |
Waste discharges
shall not reduce light transmission substantially from the normal level. |
Yung Long Bathing
Beach Subzone |
6.1.3
Technical Memorandum for Effluents Discharge into
Drainage and Sewerage Systems, Inland & Coastal Waters
6.1.3.1 Apart from the WQOs, Section 21 of the WPCO also specifies the limits to control the physical, chemical and microbial parameters for effluent discharges into drainage and sewage system at both inland and coastal waters under the TM-DSS. The discharge limits vary with the effluent flow rates and the sewage from the Project, treated after sewage treatment works, should comply with the standards for effluent discharged into inland waters, which would be used for either irrigation, pond fish culture or amenity subject to the exact locations. Group B (for irrigation), C (for pond fish culture) and D (for amenity) inland water standards in TM-DSS are therefore adopted and the effluent discharge standards are presented in Table 6.2 to Table 6.4.
Table
6.2 Standards for effluents discharged into Group B Inland Waters
Parameter |
Flowrate
(m3/day) |
|||||||
Ł 200 |
>
200 & Ł400 |
>
400 & Ł 600 |
>
600 & Ł 800 |
>
800 & Ł 1000 |
>
1000 & Ł 1500 |
>
1500 & Ł 2000 |
>
2000 & Ł 3000 |
|
pH (pH units) |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
Temperature (℃) |
35 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Colour (lovibond units) |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Suspended solids |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
BOD |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
COD |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
Oil & Grease |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
Iron |
10 |
8 |
7 |
5 |
4 |
3 |
2 |
1 |
Boron |
5 |
4 |
3 |
2.5 |
2 |
1.5 |
1 |
0.5 |
Barium |
5 |
4 |
3 |
2.5 |
2 |
1.5 |
1 |
0.5 |
Mercury |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Selenium |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.1 |
Other toxic metals individually |
0.5 |
0.5 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.1 |
Total Toxic metals |
2 |
1.5 |
1 |
0.5 |
0.5 |
0.2 |
0.2 |
0.2 |
Cyanide |
0.1 |
0.1 |
0.1 |
0.08 |
0.08 |
0.05 |
0.05 |
0.03 |
Phenols |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
Fluoride |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
3 |
Sulphate |
800 |
800 |
600 |
600 |
600 |
400 |
400 |
400 |
Chloride |
1000 |
1000 |
800 |
800 |
800 |
600 |
600 |
400 |
Total phosphorus |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
Ammonia nitrogen |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
Nitrate + nitrite nitrogen |
30 |
30 |
30 |
20 |
20 |
20 |
10 |
10 |
Surfactants (total) |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
E. coli (count/100ml) |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
Notes:
[1] All units in mg/L unless otherwise stated
Table
6.3 Standards for effluents discharged into Group C Inland Waters
Parameter |
Flowrate
(m3/day) |
|||
Ł 100 |
>
100 & Ł500 |
>
500 & Ł 1000 |
>
1000 & Ł 2000 |
|
pH (pH units) |
6-9 |
6-9 |
6-9 |
6-9 |
Temperature (℃) |
30 |
30 |
30 |
30 |
Colour (lovibond units) |
1 |
1 |
1 |
1 |
Suspended solids |
20 |
10 |
10 |
5 |
BOD |
20 |
15 |
10 |
5 |
COD |
80 |
60 |
40 |
20 |
Oil & Grease |
1 |
1 |
1 |
1 |
Boron |
10 |
5 |
4 |
2 |
Barium |
1 |
1 |
1 |
0.5 |
Iron |
0.5 |
0.4 |
0.3 |
0.2 |
Mercury |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.001 |
0.001 |
0.001 |
0.001 |
Silver |
0.1 |
0.1 |
0.1 |
0.1 |
Copper |
0.1 |
0.1 |
0.05 |
0.05 |
Selenium |
0.1 |
0.1 |
0.05 |
0.05 |
Lead |
0.2 |
0.2 |
0.2 |
0.1 |
Nickel |
0.2 |
0.2 |
0.2 |
0.1 |
Other toxic metals individually |
0.5 |
0.4 |
0.3 |
0.2 |
Total Toxic metals |
0.5 |
0.4 |
0.3 |
0.2 |
Cyanide |
0.05 |
0.05 |
0.05 |
0.01 |
Phenols |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
0.2 |
0.2 |
0.2 |
0.1 |
Fluoride |
10 |
7 |
5 |
4 |
Sulphate |
800 |
600 |
400 |
200 |
Chloride |
1000 |
1000 |
1000 |
1000 |
Total phosphorus |
10 |
10 |
8 |
8 |
Ammonia nitrogen |
2 |
2 |
2 |
1 |
Nitrate + nitrite nitrogen |
30 |
30 |
20 |
20 |
Surfactants (total) |
2 |
2 |
2 |
1 |
E. coli (count/100ml) |
1000 |
1000 |
1000 |
1000 |
Notes:
[1] All units in mg/L unless otherwise stated
Table
6.4 Standards for effluents discharged into Group D Inland Waters
Parameter |
Flowrate (m3/day) |
|||||||
≦200 |
>200 |
>400 |
>600 |
>800 |
>1000 |
>1500 |
>2000 |
|
pH (pH units) |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
Temperature (℃) |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Colour (lovibond units) |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Suspended solids |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
BOD |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
COD |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
Oil & Grease |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
Iron |
10 |
8 |
7 |
5 |
4 |
2.7 |
2 |
1.3 |
Boron |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Barium |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Mercury |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Other toxic metals individually |
1 |
1 |
0.8 |
0.8 |
0.5 |
0.5 |
0.2 |
0.2 |
Total Toxic metals |
2 |
2 |
1.6 |
1.6 |
1 |
1 |
0.5 |
0.4 |
Cyanide |
0.4 |
0.4 |
0.3 |
0.3 |
0.2 |
0.1 |
0.1 |
0.05 |
Phenols |
0.4 |
0.3 |
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Sulphate |
800 |
600 |
600 |
600 |
600 |
400 |
400 |
400 |
Chloride |
1000 |
800 |
800 |
800 |
600 |
600 |
400 |
400 |
Fluoride |
10 |
8 |
8 |
8 |
5 |
5 |
3 |
3 |
Total phosphorus |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
Ammonia nitrogen |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
10 |
Nitrate + nitrite nitrogen |
50 |
50 |
50 |
30 |
30 |
30 |
30 |
20 |
Surfactants (total) |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
E. coli (count/100ml) |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
Notes:
[1] All units in mg/L unless otherwise stated
6.1.3.2
The TM-DSS also specifies the discharge
standards into foul sewers leading into Government sewage treatment plants as Table 6.5 and Table 6.6. Subject to the flow rate of the effluents, corresponding
standards for the effluent discharge into government foul sewers should be
followed.
Table
6.5 Standards for effluents discharged into foul sewers leading into Government
sewage treatments plants
Parameter |
Flowrate (m3/day) |
||||||||||||
Ł 10 |
> 10 & Ł100 |
> 100 & Ł 200 |
> 200 & Ł 400 |
> 400 & Ł 600 |
> 600 & Ł 800 |
> 800 & Ł 1000 |
> 1000 & Ł 1500 |
> 1500 & Ł 2000 |
> 2000 & Ł 3000 |
> 3000 & Ł 4000 |
> 4000 & Ł 5000 |
> 5000 & Ł 6000 |
|
pH (pH units) |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
Temperature (℃) |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
Suspended solids |
1200 |
1000 |
900 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
Settleable solids |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
BOD |
1200 |
1000 |
900 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
COD |
3000 |
2500 |
2200 |
2000 |
2000 |
2000 |
2000 |
2000 |
2000 |
2000 |
2000 |
2000 |
2000 |
Oil & Grease |
100 |
100 |
50 |
50 |
50 |
40 |
30 |
20 |
20 |
20 |
20 |
20 |
20 |
Iron |
30 |
25 |
25 |
25 |
15 |
12.5 |
10 |
7.5 |
5 |
3.5 |
2.5 |
2 |
1.5 |
Boron |
8 |
7 |
6 |
5 |
4 |
3 |
2.4 |
1.6 |
1.2 |
0.8 |
0.6 |
0.5 |
0.4 |
Mercury |
0.2 |
0.15 |
0.1 |
0.1 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.2 |
0.15 |
0.1 |
0.1 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Copper |
4 |
4 |
4 |
3 |
1.5 |
1.5 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Nickel |
4 |
3 |
3 |
2 |
1.5 |
1.5 |
1 |
0.8 |
0.7 |
0.7 |
0.6 |
0.6 |
0.6 |
Chromium |
2 |
2 |
2 |
2 |
1 |
0.7 |
0.6 |
0.4 |
0.3 |
0.2 |
0.1 |
0.1 |
0.1 |
Zinc |
5 |
5 |
4 |
3 |
1.5 |
1.5 |
1 |
0.8 |
0.7 |
0.7 |
0.6 |
0.6 |
0.6 |
Silver |
4 |
3 |
3 |
2 |
1.5 |
1.5 |
1 |
0.8 |
0.7 |
0.7 |
0.6 |
0.6 |
0.6 |
Other toxic metals individually |
2.5 |
2.2 |
2 |
1.5 |
1 |
0.7 |
0.6 |
0.4 |
0.3 |
0.2 |
0.15 |
0.12 |
0.1 |
Total toxic metals |
10 |
10 |
8 |
7 |
3 |
2 |
2 |
1.6 |
1.4 |
1.2 |
1.2 |
1.2 |
1 |
Cyanide |
2 |
2 |
2 |
1 |
0.7 |
0.5 |
0.4 |
0.27 |
0.2 |
0.13 |
0.1 |
0.08 |
0.06 |
Phenols |
1 |
1 |
1 |
1 |
0.7 |
0.5 |
0.4 |
0.27 |
0.2 |
0.13 |
0.1 |
0.1 |
0.1 |
Sulphide |
10 |
10 |
10 |
10 |
5 |
5 |
4 |
2 |
2 |
2 |
1 |
1 |
1 |
Sulphate |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
900 |
800 |
600 |
600 |
600 |
600 |
Total nitrogen |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
100 |
100 |
100 |
100 |
100 |
100 |
Total phosphorus |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
25 |
25 |
25 |
25 |
25 |
25 |
Surfactants (total) |
200 |
150 |
50 |
40 |
30 |
25 |
25 |
25 |
25 |
25 |
25 |
25 |
25 |
Notes:
[1] All units in mg/L unless otherwise stated
Table
6.6 Standards for effluents discharged into foul sewers leading into Government
sewage treatments plants with microbial treatment
Parameter |
Flowrate (m3/day) |
||||||||||||
Ł 10 |
> 10 & Ł100 |
> 100 & Ł 200 |
> 200 & Ł 400 |
> 400 & Ł 600 |
> 600 & Ł 800 |
> 800 & Ł 1000 |
> 1000 & Ł 1500 |
> 1500 & Ł 2000 |
> 2000 & Ł 3000 |
> 3000 & Ł 4000 |
> 4000 & Ł 5000 |
> 5000 & Ł 6000 |
|
Copper |
1.5 |
1 |
1 |
1 |
0.8 |
0.6 |
0.5 |
0.4 |
0.3 |
0.2 |
0.15 |
0.1 |
0.05 |
Notes:
[1] All units in mg/L unless otherwise stated
6.1.4
Environmental Impact Assessment Ordinance (Cap.
499), Technical Memorandum on Environmental Impact Assessment Process
6.1.4.1 Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO) specifies the assessment methods and criteria for impact assessment. This Study follows the TM-EIAO to assess the potential water quality impact that may arise during both the construction and operational phases of the Project. Sections in the TM-EIAO relevant to the water quality impact assessment are:
·
Annex 6 - Criteria
for Evaluating Water Pollution; and
·
Annex 14 -
Guidelines for Assessment of Water Pollution.
6.1.5
No Net Increase in Pollution Loads Requirement in
Deep Bay
6.1.5.1 In addition to the provisions of the TM, the ‘No Net Increase in Pollution Loads Requirement’ aims to provide protection to the inland and marine water quality of the Deep Bay WCZ. According to EPD’s “Deep Bay Water Quality Regional Control Strategy Study”, the pollutions entering into Deep Bay have exceeded the assimilative capacity of the water body. Further increasing the pollution loads to the water body is therefore environmentally undesirable.
6.1.5.2 In accordance with Town Planning Board Guideline No.12C, the pollution loads of concern should be offset by equivalent reduction of current loads for new discharge into Deep Bay. The policy ensures that developments within the Deep Bay catchment areas do not result in an increase in pollution loads to both the inland and marine waters.
6.1.6
Hong Kong Planning Standards and Guidelines
6.1.6.1 Chapter 9 of the Hong Kong Planning Standards and Guidelines (HKPSG) outlines environmental requirements that need to be considered in land use planning. The recommended guidelines, standards and guidance cover the selection of suitable locations for the developments and sensitive uses, provision of environmental facilities, and design, layout, phasing and operational controls to minimise adverse environmental impacts. It also lists out environmental factors that influence land use planning and recommends buffer distances for land uses.
6.1.7
ProPECC PN 1/94 “Construction Site Drainage”
6.1.7.1 Professional Persons Environmental Consultative Committee Practice Notes (ProPECC Note PN1/94) on Construction Site Drainage provides guidelines for the handling and disposal of construction discharges. It is applicable to this study for the control of site runoff and wastewater generated during the construction phase. The types of discharges from construction sites outlined in the ProPECC Note PN1/94 include:
·
Surface runoff;
·
Groundwater;
·
Boring and
drilling water;
·
Wastewater from
concrete batching plant;
·
Wheel washing
water;
·
Bentonite
slurries;
·
Water for testing
and sterilization of water retaining structures and water pipes;
·
Wastewater from building
construction and site facilities; and
·
Acid cleaning,
etching and pickling wastewater.
6.2.1
Existing Hydrology
6.2.1.1
The Project Site falls within the Deep Bay
WCZ according to the WPCO. It is
located at Yuen Long Town Nullah between West Rail Long Ping Station and south
of Kau Yuk Road. Downstream of the project is a drainage channel along the edge
of Tai Tseng Wai and the ultimate discharge of this drainage channel is
downstream of Shan Pui River and Inner Deep Bay. Apart from Yuen Long Creek,
the inner Deep Bay was most affected by the discharges from Shenzhen River as
well as Kam Tin River and Tin Shui Wai Nullah. The WQO compliance rate of the Deep Bay WCZ in 2014 was 40%, same as from
2008 to 2013 except in 2012 (53%).
6.2.2
Baseline Water Quality Conditions
6.2.2.1 The closest water quality monitoring stations are Yuen Long Creek (YL1 – YL4) and Table 6.7 summarises the water quality monitoring data for YL1 – YL4. The locations of water quality monitoring stations are shown in Figure 6.1.
Table
6.7 Water Quality at Yuen Long Creek (YL1
– YL4) for Year 2014
Parameter |
YL1 |
YL2 |
YL3 |
YL4 |
Dissolved
oxygen (mg/L) |
5.2 |
6.5 |
3.6 |
3.8 |
(3.3 - 8.0) |
(3.3 - 9.7) |
(1.8 - 7.4) |
(1.3 - 5.6) |
|
pH |
7.3 |
7.4 |
7.3 |
7.2 |
(7.1 - 7.5) |
(7.2 - 7.5) |
(7.1 - 7.8) |
(6.9 - 8.0) |
|
SS
(mg/L) |
16 |
5 |
17 |
34 |
(5 - 450) |
(2 - 9) |
(3 - 47) |
(5 - 73) |
|
5-day
Biochemical Oxygen Demand (mg/L) |
19 |
8 |
29 |
86 |
(4 - 90) |
(2 - 13) |
(5 - 140) |
(6 - 280) |
|
Chemical
Oxygen Demand (mg/L) |
23 |
26 |
35 |
70 |
(8 - 120) |
(17 - 37) |
(12 - 140) |
(23 - 200) |
|
Oil
& grease (mg/L) |
<0.5 |
0.6 |
0.6 |
0.9 |
(<0.5 - 0.9) |
(<0.5 - 1.0) |
(<0.5 – 2.2) |
(<0.5 – 8.2) |
|
Faecal
coliforms (cfu/100mL) |
460,000 |
150,000 |
1,500,000 |
3,000,000 |
(86,000 - 2,300,000) |
(35,000 - 1,200,000) |
(240,000 - 6,600,000) |
(150,000 - 12,000,000) |
|
E. coli(cfu/100mL)[4] |
160,000 |
78,000 |
490,000 |
1,200,000 |
(49,000 - 870,000) |
(4,300 - 930,000) |
(80,000 - 2,000,000) |
(48,000 - 5,700,000) |
|
Ammonia-nitrogen
(mg/L) |
6.95 |
14.50 |
5.50 |
7.40 |
(0.98 - 15.00) |
(6.90 - 26.00) |
(1.20 - 16.00) |
(3.70 - 14.00) |
|
Nitrate-nitrogen
(mg/L) |
0.58 |
2.00 |
<0.01 |
<0.01 |
(<0.01 - 1.20) |
(0.17 - 5.90) |
(<0.01 - 1.40) |
(<0.01 - 0.76) |
|
Total
Kjeldahl nitrogen (mg/L) |
9.10 |
17.50 |
7.65 |
11.00 |
(1.50 - 26.00) |
(7.30 - 31.00) |
(2.10 - 23.00) |
(4.80 - 22.00) |
|
Ortho-phosphate
(mg/L) |
0.90 |
2.40 |
0.54 |
0.48 |
(0.17 - 3.40) |
(1.40 - 3.20) |
(0.10 - 1.70) |
(0.25 - 0.86) |
|
Total
phosphorus (mg/L) |
1.25 |
2.75 |
0.92 |
1.10 |
(0.28 - 4.40) |
(1.60 - 3.60) |
(0.26 - 2.70) |
(0.39 - 2.00) |
|
Total
sulphide (mg/L) |
0.03 |
<0.02 |
<0.02 |
0.08 |
(<0.02 - 0.09) |
(<0.02 - 0.09) |
(<0.02 - 0.33) |
(<0.02 - 0.25) |
|
Aluminium
(µg/L) |
216 |
55 |
172 |
205 |
(140 - 1,438) |
(<50 - 98) |
(72 - 332) |
(101 - 848) |
|
Cadmium
(µg/L) |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
(<0.1 - 0.4) |
(<0.1 - <0.1) |
(<0.1 - 0.1) |
(<0.1 - 0.3) |
|
Chromium
(µg/L) |
<1 |
<1 |
<1 |
<1 |
(<1 - 2) |
(<1 - <1) |
(<1 - 3) |
(<1 - 4) |
|
Copper
(µg/L) |
6 |
3 |
5 |
5 |
(3 - 23) |
(2 - 6) |
(2 - 14) |
(2 - 8) |
|
Lead
(µg/L) |
4 |
<1 |
3 |
2 |
(2 - 44) |
(<1 - 2) |
(<1 - 10) |
(<1 - 5) |
|
Zinc
(µg/L) |
48 |
30 |
42 |
47 |
(22 - 206) |
(15 - 82) |
(26 - 92) |
(24 - 88) |
|
Flow
(L/s) |
202 |
40 |
490 |
125 |
(10 - 303) |
(11 - 83) |
(160 - 1,538) |
(81 - 205) |
Notes:
[1] Data presented are in annual medians of monthly samples; except those for faecal coliforms and E. coli which are in annual geometric means.
[2] Figures in brackets are annual ranges.
[3] NM indicates no measurement taken.
[4] cfu - colony forming unit.
[5] Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits.
[6] Extracted from EPD River Water Quality in Hong Kong 2014
6.2.2.2 According to EPD’s River Monitoring Report, Yuen Long Creek’s overall compliance rate was 52% in 2014, higher than 51% in 2013. The compliance rates for upstream stations YL1 and YL2 were 58% and 60% respectively in 2014 as compared with 72% and 60% respectively in 2013. The rates for the stations in the middle of Yuen Long township (YL3 and YL4) were 57% and 33% in 2014 as compared with 42% and 30% in 2013 respectively. The river was still subject to discharges from remaining livestock farms, unsewered village house establishments and other specific uses (Storage and Workshop, and Open Storage).
6.2.2.3 The Deep Bay is located at downstream of the Yuen Long Town Nullah. As the water quality impacts on the downstream water systems depend on the scale and nature of the discharge of upstream area, the Inner Deep Bay is considered as a WSR of the Project. The closest marine water quality monitoring stations to the estuary of the downstream water system of Yuen Long Town Nullah is located at the Inner Deep Bay (i.e. DM1, DM2 and DM3). Table 6.8 summarises the water quality monitoring data for DM1 – DM3. The locations of water quality monitoring stations are shown in Figure 6.1.
Table
6.8 Water Quality at Inner Deep Bay (DM1 –
DM3) for Year 2014
Parameter |
DM1 |
DM2 |
DM3 |
Temperature (oC) |
24.2 |
24.4 |
24.4 |
(14.3 -32.1) |
(14.5 – 31.9) |
(15.1 – 32.0) |
|
Salinity |
15.5 |
17.5 |
21.2 |
(3.5 – 24.4) |
(5.6 – 25.8) |
(10.7 – 29.4) |
|
Dissolved oxygen (mg/L) |
3.7 |
4.6 |
5.5 |
(1.3 – 6.1) |
(2.6 – 6.8) |
(4.1 – 7.3) |
|
Dissolved oxygen (mg/L) (Bottom) |
N.M |
N.M |
N.M |
Dissolved oxygen (% Saturation) |
48 |
60 |
73 |
(18 – 73) |
(36 – 81) |
(60 – 88) |
|
Dissolved oxygen (% Saturation) (Bottom) |
N.M |
N.M |
N.M |
pH |
7.4 |
7.5 |
7.7 |
(7.1 – 7.7) |
(7.3 – 7.9) |
(7.5 – 7.9) |
|
Secchi Disc Depth (m) |
1.3 |
1.2 |
1.3 |
(0.7 – 1.7) |
(0.7 – 2.0) |
(0.4 – 2.0) |
|
Turbidity (NTU) |
29.5 |
20.5 |
10.2 |
(12.6 – 48.2) |
(10.3 – 40.2) |
(5.4 – 15.1) |
|
SS (mg/L) |
46.2 |
23.0 |
15.5 |
(15.0 – 95.0) |
(13.0 – 41.0) |
(4.9 – 53.0) |
|
5-day Biochemical Oxygen Demand (mg/L) |
3.1 |
2.4 |
1.0 |
(1.6 – 6.7) |
(0.8 – 6.7) |
(0.4 – 2.7) |
|
Ammonia-nitrogen (mg/L) |
2.080 |
1.410 |
0.536 |
(0.930 – 4.500) |
(0.330 – 2.800) |
(0.069 – 1.700) |
|
Unionised Ammonia (mg/L) |
0.026 |
0.025 |
0.014 |
(0.006 – 0.077) |
(0.005 – 0.076) |
(0.001 – 0.045) |
|
Nitrite-nitrogen (mg/L) |
0.367 |
0.291 |
0.184 |
(0.170 – 0.560) |
(0.100 – 0.570) |
(0.055 – 0.350) |
|
Nitrate-nitrogen (mg/L) |
1.030 |
0.918 |
0.759 |
(0.380 – 2.500) |
(0.460 – 1.800) |
(0.410 – 1.100) |
|
Total inorganic nitrogen (mg/L) |
3.48 |
2.61 |
1.48 |
(2.36 – 5.74) |
(1.56 – 3.75) |
(0.84 – 3.07) |
|
Total Kjeldahl nitrogen (mg/L) |
2.78 |
1.94 |
0.85 |
(1.00 – 6.00) |
(0.79 – 3.90) |
(0.24 – 2.40) |
|
Total nitrogen (mg/L) |
4.17 |
3.15 |
1.79 |
(2.43 – 6.80) |
(2.02 – 4.85) |
(1.12 – 3.77) |
|
Orthophosphate Phosphorus (mg/L) |
0.213 |
0.183 |
0.093 |
(0.110 – 0.320) |
(0.110 – 0.260) |
(0.045 – 0.180) |
|
Total Phosphorus (mg/L) |
0.31 |
0.27 |
0.13 |
(0.18 – 0.50) |
(0.17 – 0.41) |
(0.08 – 0.24) |
|
7.53 |
6.46 |
4.31 |
|
(4.70 – 12.00) |
(2.90 – 11.00) |
(1.40 – 8.50) |
|
Chlorophyll-a
(µg/L) |
6.4 |
7.6 |
4.7 |
(1.7 – 17.0) |
(1.8 – 31.0) |
(0.4 – 18.0) |
|
E. coli (count/100mL) |
1300 |
380 |
37 |
(72 – 140000) |
(36 – 7800) |
(<1 – 840) |
|
Faecal coliforms (count/100mL) |
3600 |
1000 |
110 |
(150 – 250000) |
(81 – 14000) |
(5 – 2700) |
Notes:
[1] Unless otherwise
specified, data presented are depth-averaged (A) values calculated by taking
the means of three depths: Surface (S), Mid-depth (M), Bottom (B).
[2] Data presented are
annual arithmetic means of the depth-averaged results except for E.coli and faecal coliforms which are
annual geometric means.
[3] Data in brackets
indicate the ranges.
[4] N.M. – not
measured.
6.2.2.4
According
to EPD’s “Marine Water Quality Monitoring
in Hong Kong in 2014”, the WQO compliance rate of the Deep Bay WCZ in 2014
was 40%, same as from 2008 to 2013 except in 2012 (53%).
6.2.2.5
Similar to
the previous years, the Deep Bay WCZ had relatively high nutrient levels in
2014. The total inorganic nitrogen (TIN) level in the Deep Bay Inner Subzone
(i.e. 1.5 – 3.5 mg/L) was higher than the respective TIN objective of 0.7 mg/L.
Non-compliance with the ammonia-nitrogen and dissolved oxygen objective was
also observed at two of the three stations in the Deep Bay Inner Subzone.
6.2.3
Water Sensitive Receivers
6.2.3.1
In order to
identify the water quality sensitive receivers (WSRs) in the vicinity, a
desktop study has been conducted. The study has reviewed the Yuen Long OZP
(S/YL/22) has been conducted together with site visits. The
identified WSR is presented in Table 6.9
and shown in
Figure 6.1.
Table
6.9 Water quality sensitive receivers
ID |
WSRs |
Status |
WSR1 |
Yuen Long Creek |
· Drainage nullah
within Yuen Long Town Centre · Discharge into
Deep Bay |
WSR2 |
Shan Pui River |
·
Downstrem of the Yuen Long Town Nullah ·
Discharge into Deep Bay |
WSR3 |
Inner Deep Bay |
·
The inner Deep Bay was most affected by the
discharges from Shenzhen River as well as unsewered villages, Kam Tin River,
Yuen Long Creek and Tin Shui Wai Nullah. |
6.3
Identification of Pollution Sources
6.3.1
Construction Phase
6.3.1.1
The main
water pollution sources of the Project during construction phase includes:
·
Construction
activities within Yuen Long Town Nullah (e.g. excavation, piling, construction
of pile cap, etc);
·
Construction
surface runoff (including accidental chemicals spillage); and
·
Sewage from site
workforce.
6.3.1.2
According
to the latest design, there is a total of 5 columns and 6 box culverts
supporting the entire elevated pedestrian corridor. As mentioned in Section 3.5.1.3 and
Figure 3.2, out of these supporting
structures, only 2 columns and 6 box culverts will be located inside the Yuen
Long Town Nullah and they would approximately occupy 720 m3 of Yuen Long Nullah which is about 1.3% of the volume
of Yuen Long Nullah for the section along the elevated pedestrian corridor. For
the construction activities within the nullah, temporary working platform and
cofferdams with water tight feature will be constructed to isolate the working
area from the flow of the nullah. Any pollutants generated from the above
sources may entering into the WSRs and pose potential water quality impact.
6.3.1.3
The
presence of the temporary working platform and cofferdams within the nullah may
also pose potential impact on the drainage characteristics, such as capacity,
flow characteristics, etc., of the nullah. Sufficient flow area will be
maintained to provide passage of a storm event in accordance with DSD Technical
Circular No. 14/2000 “Temporary Flow Diversions and Temporary Works Affecting
Capacity in Stormwater Drainage System” and DSD Practice Note No. 1/2004 “Design
Rainfall Depth for Temporary Works within the Dry Season”.
6.3.2
Operational Phase
6.3.2.1 The potential water pollution source during the operational phase would be surface runoff from the elevated pedestrian corridor. The surface runoff may contain grit, oil and debris from the pedestrians and cause potential water quality impact to the WSRs.
6.3.2.2 Similar to construction phase, the presence of columns of the proposed elevated pedestrian corridor and box culverts may also pose potential impact on the drainage characteristics of the nullah.
6.4
Prediction and Evaluation of Impacts During
Construction Phase
6.4.1
Construction activities within Yuen Long Town
Nullah
6.4.1.1 The Project will be constructed along the Yuen Long Town Nullah, which is a channelized river with a dry weather flow (DWF) channel. In dry seasons, the majority of the base flow from the catchment would utilize the DWF channel and most of the area in nullah would remain dry, except during occasional heavy rainfall. The construction works within the nullah, such as excavation and modification of the existing nullah, will be undertaken during dry seasons. Nevertheless, watertight cofferdams will be constructed to isolate the working area from the flow of nullah. Hence, these temporary cofferdams would provide sufficient measures even during heavy rainfall. Sufficient flow area, will be retained to provide passage of storm events in accordance with DSD Technical Circular No. 14/2000 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System” and DSD Practice Note No. 1/2004 “Design Rainfall Depth for Temporary Works within the Dry Season”. Water pumps would be used to collect any construction site surface runoff and ingress / seepage water within the cofferdam. The collected construction site surface runoff and ingress / seepage water would be diverted to the on-site wastewater treatment facilities for treatment to satisfactory levels before discharge. Together with the temporary platforms to be constructed, all these would constrain any SS released to the river waters during construction activities. Prior to the completion of the temporary platform, any temporary stockpile should be stored outside the nullah and at location away from the air sensitive receivers. Bunds will be installed around the stockpile area and stock material will be covered with tarpaulin to minimize leakage as practicable as possible. If storage within nullah is unavoidable, stockpile should be located within the cofferdam which will be designed to be water tight and be covered with tarpaulin. Once the temporary platform is completed, any stockpile should be stored on the temporary platforms which should be designed to be water tight to prevent leakage. The stockpile should be also removed from the site as soon as possible and overnight storage should be avoided. Therefore, adverse water quality impact is not anticipated with the implementation of the mitigation measures recommended in Section 6.6.
6.4.1.2 Box culverts at the pedestrian interchanges will be constructed within the nullah. According to the latest design, box culverts will be constructed at pedestrian interchanges at Yuen Long On Ning Road, Castle Peak Road – Yuen Long Section and Kau Yuk Road. For each pedestrian interchange, box culverts will be constructed cell by cell so that the construction activities will not be conducted concurrently. Similar to the construction of columns within the nullah, temporary cofferdams with water tight features will be used to isolate the construction site from the nullah water. Hence, release of SS into the nullah is also considered unlikely with provision of temporary watertight cofferdams during construction works. Therefore, adverse water quality impact is not anticipated with the implementation of the mitigation measures recommended in Section 6.6.
6.4.1.3
As
mentioned in Section 6.4.1.1 to Section 6.4.1.2, cofferdams and
temporary platform will be constructed during construction of columns and box
culverts to prevent release of the SS and other pollutants into the nullah
water. These cofferdams may pose potential impacts on the drainage
characteristic of the nullah.
6.4.1.4
As mentioned in Section 3.6.1.1, , the construction
activities at the eastern side, central part and western side of the nullah
would be conducted separately to minimize the potential hydraulic impact in
order to maintain sufficient capacity for the passage of flow over the entire
nullah during construction phase. Since the construction works and use of cofferdams will be
implemented in phases and hence not all the cofferdams would be in place
concurrently. Together with the fact that the construction works within the
nullah would be conducted during the dry seasons. This arrangement will ensure that the
impacts on the hydrology and water quality of the nullah would be minimized.
6.4.1.5
The Contractor would be requested to carry out detail design of the
cofferdams in accordance with the DSD Technical Circular No. 14/2000 “Temporary
Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage
System” and DSD Practice Note No. 1/2004 “Design Rainfall Depth for Temporary
Works within the Dry Season” for DSD approval in order to finalize options of
these temporary structure to avoid adverse impact to the drainage
characteristics of the nullah.
6.4.2
Construction Site Runoff
6.4.2.1
During rainstorm events, construction site runoff would come from all
over the works site. The surface runoff might be polluted by:
·
Runoff and erosion from site surfaces, earth
working areas and stockpiles;
·
Wash water from dust suppression sprays and wheel
washing facilities; and
·
Accidental chemicals spillage such as fuel, oil,
solvents and lubricants from maintenance of construction machinery and
equipment.
6.4.2.2
Construction runoff may cause physical, biological and chemical effects.
The physical effects include potential blockage of drainage channels and increase
of suspended solid levels in the Deep Bay WCZ. Runoff containing significant
amounts of concrete and cement-derived material may cause primary chemical
effects such as increasing turbidity and discoloration, elevation in pH, and
accretion of solids. A number of secondary effects may also result in toxic
effects to water biota due to elevated pH values, and reduced decay rates of
faecal micro-organisms and photosynthetic rate due to the decreased light
penetration. Therefore,
good site practices and mitigation measures would be required to minimize any
potential impact to nearby water sensitive receivers. With the implementation
of mitigation measures recommended in Section
6.6, adverse water quality impact is not anticipated.
6.4.3.1
Sewage effluents will arise from the sanitary facilities provided for
the on-site construction workforce. According to Table T-2 of Guidelines for Estimating Sewage Flows for
Sewage Infrastructure Planning, the unit flow is 0.23 m3/day/employed
population. The characteristics of sewage would include high levels of BOD5,
Ammonia and E. coli counts. Since
portable chemical toilets and sewage holding tank will be provided, no adverse
water quality impact is anticipated.
6.4.4
Cumulative Water Quality
Impact during Construction Phase
Concurrent
Projects
6.4.4.1
As
discussed in Chapter 3, the
tentative commencement year for the construction of the Project is Year 2018
with target full completion in Year 2022. Concurrent projects in the vicinity
of the Project, which may have cumulative environmental impacts, have been
discussed in Section 3.7 and shown
in
Figure 3.1. Key concurrent
projects of water quality concern during the construction phase of the Project
have been identified and are summarised in the Table 6.10. The implementation programme of these concurrent
projects are provided by the respective project proponents. Where information
is not available, references have been made to the best available information
such as EIA reports and respective project proponents’ websites.
Table 6.10 Key concurrent projects for water quality
impact assessment during construction phase
Key Concurrent Projects |
Tentative Programme |
Potential Cumulative Impact |
|
Start |
Complete |
||
West Rail Long Ping Station (North) Property Development |
2013 |
2018 |
Water
quality |
West Rail Long Ping Station (South) Property Development |
2014 |
2019 |
Water
quality |
Housing Sites in Yuen Long South[1] |
- |
- |
Water
quality |
Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan
New Village, Tai Wo, Lin Fa Tei and Ha Che |
2017 |
2022 |
Water
quality |
Notes:
[1] No
construction programme is available at the time preparing this report.
Considering the first population intake year would be Year 2026, the cumulative
water quality impact during construction phase would be also considered in this
EIA study as a conservative approach.
West Rail Long
Ping Station (North) Property Development
6.4.4.2
For the
West Rail Long Ping Station (North) Property Development, the construction
period will overlap with the Project in Year 2018.
6.4.4.3
The
property development is a land-based project. The major sources of the water
quality impact are the construction site surface runoff, accidental spillage of
chemicals and sewage from the work force. As the wastewater from the
construction site and sewage from the work force will be collected and treated to
statutory limits before discharging to the public drainage system, which is
connected to the Yuen Long Town Nullah, and sewage will be proper handled.
Hence, potential water quality impact from the project is not anticipated since
the property development are also required to comply with the relevant
environmental legislations for wastewater discharge and handling of sewage.
West Rail Long
Ping Station (South) Property Development
6.4.4.4
For the
West Rail Long Ping Station (South) Property Development, the construction
period will overlap with the Project in Year 2018 and Year 2019.
6.4.4.5
The
property development is a land-based project. The major sources of the water
quality impact are the construction site surface runoff, accidental spillage of
chemicals and sewage from the work force. As the wastewater from the
construction site and sewage from the work force will be collected and treated
to statutory limits before discharging to the public drainage system, which is
connected to the Yuen Long Town Nullah, and sewage will be proper handled.
Hence, potential water quality impact from the project is not anticipated since
the property development are also required to comply with the relevant
environmental legislations for wastewater discharge and handling of sewage.
Housing Sites in
Yuen Long South
6.4.4.6
For the Housing
Sites in Yuen Long South, there is no construction programme available at the
time preparing this report. As the first population year is Year 2026 and the
project will be developed in stages, cumulative water quality impact from the
housing developments project is also considered for conservative assessment.
6.4.4.7
According
to the project profile of the housing development project (ESB-279/2014), potential
water quality impact would be arise from various construction activities,
including site formation, sediment removal, re-alignment of stream and rivers,
concrete washings, bore piling, construction of bridges / underpasses /
buildings, construction and upgrading of road networks, site workshop or depot
and sewage effluent from the workforce. As
the wastewater from the construction site and sewage from the work force will
be collected and treated to statutory limits before discharging to the public
drainage system and sewage will be proper handled, potential water quality
impact from the project is not anticipated since EIA study will be conducted to
assess the potential water quality impact, including the potential hydraulic
impact. Mitigation measures would be recommended in the EIA study for the water
quality impact to comply with the relevant environmental legislations for
wastewater discharge and handling of sewage.
Drainage
Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai
Wo, Lin Fa Tei and Ha Che
6.4.4.8
For the Drainage Improvement Works near Four Village in Yuen Long – Sung Shan
New Village, Tai Wo, Lin Fa Tei and Ha Che, the construction period will overlap with the
Project from Year 2018 to Year 2022.
6.4.4.9
According
to the project profile of the drainage improvement works (ESB-279/2014), the major
sources of the water quality impact are the construction site surface runoff, other
potential release to the aquatic environment and effluent from the construction
workforce. As the wastewater from the construction site and sewage from the
work force will be collected and treated to statutory limits before discharging
to the public drainage system and sewage will be proper handled, potential
water quality impact from the project is not anticipated since EIA study will
be conducted to assess the potential water quality impact, including the
potential hydraulic impact. Mitigation measures would be recommended in the EIA
study for the water quality impact to comply with the relevant environmental
legislations for wastewater discharge and handling of sewage.
Cumulative
Impact during the Construction Phase
6.4.4.10
As mentioned in Section 6.4.1
to Section 6.4.3, the Project will
not generate significant water quality impact during the construction phase
with the implementation of the recommended mitigation measures, such as site
management, use of temporary cofferdams, use of portable chemical toilets, etc.
6.4.4.11
In consideration of both the Project and concurrent projects (as mentioned in Section 6.4.4.2 to Section
6.4.4.9) will
not generate significant water quality impact. Adverse cumulative water quality
impact is not anticipated.
6.5
Prediction and Evaluation of Impacts
During Operational Phase
6.5.1
Surface Runoff from the Elevated
Pedestrian Corridor
6.5.1.1
Surface runoff from the elevated pedestrian
corridor is the only source of
the water pollution from the Project during operational phase. The runoff may
contain grit, oil and debris from the pedestrians.
6.5.1.2
Proper drainage system including gratings at the gully inlets will be
provided to remove grit and debris before the runoff discharge to the public
storm water drainage system or the Yuen Long Town Nullah. As the nature of
surface runoff is similar to the existing condition and hence no adverse water
quality impact is anticipated with the provision of the drainage system.
6.5.2
Permanent Structure of the Elevated
Pedestrian Corridor
6.5.2.1
According to the latest design, the existing areas to be occupied by the
proposed elevated pedestrian corridor are already paved. Hence, the Project will not increase the surface
runoff. In addition, the catchment area of the Project is very small in
comparing with the overall Yuen Long drainage basin which has a basin area of
93 km2. Hence, the Project will not have any significant impact on the
existing surface runoff hydrographs. Furthermore, the Project will not
transverse any existing flood storage area. Therefore, there will be no loss in
flood storage arising from the Project.
6.5.2.2
While the Project will not increase the amount of surface runoff and
velocity, there are 2 footbridge columns located within the nullah. In addition,
a total of 6 box culverts will be constructed at the pedestrian interchanges
which will reduce the volume of the nullah by about 720 m3 (i.e. 1.3%)
for the section under the elevated pedestrian corridor. As these permanent
structures will decrease the cross-section area of the nullah, the water level
of the nullah will be increased, especially during high flow conditions.
6.5.2.3
According to the latest design, the maximum increase in water levels
under a 1 in 50 year peak flow event and under a 1 in 200 year peak flow event
would be over 0.5m and would not meet DSD requirements and thus may increase flood
risk. Therefore, mitigation measures, such as construction
of parapet wall, use of lens-shaped footbridge column to reduce head loss,
etc., will be
required to mitigate the flood risk generated by the Project. With the
recommended mitigation measure in Section
6.7, the flood risk can be mitigated to acceptable level and adverse water
quality impact is therefore not anticipated.
6.5.3
Cumulative Water Quality
Impact during Operational Phase
Concurrent
Projects
6.5.3.1
The
tentative commencement year for the construction of the Project is Year 2018
with target full completion in Year 2022. Concurrent projects in the vicinity
of the Project, which may have cumulative environmental impacts, have been
discussed in Section 3.7. Key
concurrent projects of water quality concern during the operation phase of the
Project have been identified and are summarised in the Table 6.11. In consideration that the sewage generated from the
occupiers of the two property development projects during operational phase
will be collected by the sewage system and treated by sewage treatment works
before discharge and the surface runoff has no difference in the nature
comparing with the existing conditions. Hence, no potential water pollution source
is identified for the property development projects during the operational
phase and no cumulative impact from these two property development projects is
therefore anticipated. The implementation programme of these concurrent
projects are provided by the respective project proponents. Where information
is not available, references have been made to the best available information
such as EIA reports and respective project proponents’ websites.
Table 6.11 Key concurrent projects for water quality
impact assessment during operation phase
Key Concurrent Projects |
Tentative Programme |
Potential Cumulative Impact |
|
Start |
Complete |
||
Improvement of Yuen Long Town Nullah (Town Centre Section) – Stage 1
Improvement Works |
3rd
quarter of 2022 |
2026 |
Water
quality and drainage characteristics |
Improvement of Yuen Long Town Nullah (Town Centre Section) – Stage 2
Beautification Works |
2027 |
2029 |
Water
quality and drainage characteristics |
Housing Sites in Yuen Long South |
- |
- |
Water
quality and drainage characteristics |
Drainage Improvement Works Near Four Village in Yuen Long – Sung Shan
New Village, Tai Wo, Lin Fa Tei and Ha Che |
2017 |
2022 |
Water
quality and drainage characteristics |
Improvement of
Yuen Long Town Nullah (Town Centre Section) – Stage 1 Improvement Works and
Stage 2 Beautification Works
6.5.3.2
According
to the drainage impact assessment of the Nullah Improvement Works, which has
been approved by DSD, the hydraulic impact of the Nullah Improvement Works
would be minimal. Further assessment on the hydraulic impact of the Nullah
Improvement Works will be conducted during the EIA study of the Nullah
Improvement Works. Suitable mitigation measures would be recommended to reduce
the hydraulic impact to acceptable level.
6.5.3.3
As
mentioned in Section 3.7.2, a dry
weather flow interception system will be constructed to intercept the polluted
dry weather flow being discharged to the Yuen Long Town Nullah from the town
centre section and upstream main nullah. Refer to Section 4.4 of the project
profile of the Nullah Improvement Works (DIR-227/2013), water quality and odour
issue in the Town Centre Section of the nullah will be alleviated once the
improvement works completed. Hence, the nullah improvement works would benefit
the water quality of the nullah during operational phase and adverse cumulative
water quality impact is therefore not anticipated.
Housing Sites in
Yuen Long South
6.5.3.4
According
to the project profile of the housing development project (ESB-246/2012), the
operation of the development will result in increases of sewage and surface
runoff and changes to the hydrological regime of the drainage basins. In
addition, nullah revitalizing works and creation of new watercourse, flood
retention facilities and reedbed are also proposed in the Stage 3 Community
Engagement Digest. The proposed works would also cause potential impact to the
hydrological regime in the vicinity.
6.5.3.5
For the
hydraulic impact, further assessment will be conducted during the EIA study of
the housing development project. Suitable mitigation measures would be
recommended to reduce the hydraulic impact to acceptable level.
6.5.3.6
For the
water quality impact, proper drainage and sewerage works, and silt and oil
traps are recommended in the project profile to serve the housing development
and to prevent ingress of pollutants to the storm water system respectively. In
addition, a sewage treatment works of tertiary treatment level is proposed in
the Stage 3 Community Engagement Digest. With the implementation of these
mitigation measures, no adverse water quality impact is anticipated during the
operational phase.
Drainage
Improvement Works Near Four Village in Yuen Long – Sung Shan New Village, Tai
Wo, Lin Fa Tei and Ha Che
6.5.3.7
According
to the Section 3.2 of the project profile of the drainage improvement works
(ESB-279/2014), the project only involves widening of existing streams and
channels and the construction of pipelines. The upgraded channels and the pipes
will be for stormwater only. Therefore, no adverse water quality impact is
anticipated during operational phase. Further assessment on the hydraulic
impact, if necessary, will be conducted during the EIA study of the drainage
improvement works. Suitable mitigation measures would be recommended to reduce
the hydraulic impact to acceptable level.
Cumulative
Impact during the Operational Phase
6.5.3.8
As
mentioned in Section 6.5.1 and Section 6.5.2, the Project will not
generate significant water quality impact during the operation phase with the
implementation of the recommended mitigation measures, such as construction
of parapet wall, use of lens-shaped footbridge column to reduce head loss,
etc..
6.5.3.9
In
consideration of both the Project and concurrent projects (as mentioned in Section 6.5.3.2 to Section 6.5.3.7) will not generate significant water quality
impact. Adverse cumulative water quality impact is not anticipated.
6.6
Mitigation Measures during Construction
Phase
6.6.1
General Site Operation
6.6.1.1
In accordance with the Practice
Note for Professional Persons on Construction Site Drainage, Environmental
Protection Department, 1994 (ProPECC PN 1/94), best management practices
should be implemented as far as practicable as below:
·
At the start of site establishment, perimeter
cut-off drains to direct off-site water around the site should be constructed
with internal drainage works. Channels (both temporary and permanent drainage
pipes and culverts), earth bunds or sand bag barriers should be provided on
site to direct stormwater to silt removal facilities.
·
Diversion of natural stormwater should be provided
as far as possible. The design of temporary on-site drainage should prevent
runoff going through site surface, construction machinery and equipment in
order to avoid or minimize polluted runoff. Sedimentation tanks with sufficient
capacity, constructed from pre-formed individual cells of approximately 6 to 8
m3 capacities, are recommended as a general mitigation measure which
can be used for settling surface runoff prior to disposal. The system capacity
shall be flexible and able to handle multiple inputs from a variety of sources
and suited to applications where the influent is pumped.
·
The dikes or embankments for flood protection
should be implemented around the boundaries of earthwork areas. Temporary
ditches should be provided to facilitate the runoff discharge into an
appropriate watercourse, through a silt/sediment trap. The silt/sediment traps
should be incorporated in the permanent drainage channels to enhance deposition
rates.
·
The design of efficient silt removal facilities
should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. The
detailed design of the sand/silt traps should be undertaken by the contractor
prior to the commencement of construction.
·
All exposed earth areas should be completed and
vegetated as soon as possible after earthworks have been completed. If excavation of soil cannot be avoided during
the rainy season, or at any time of year when rainstorms are likely, exposed
slope surfaces should be covered by tarpaulin or other means.
·
All drainage facilities and erosion and sediment
control structures should be regularly inspected and maintained to ensure
proper and efficient operation at all times and particularly following
rainstorms. Deposited silt and grit
should be removed regularly and disposed of by spreading evenly over stable,
vegetated areas.
·
If the excavation of trenches in wet periods is
necessary, it should be dug and backfilled in short sections wherever
practicable. Water pumped out from trenches or foundation excavations should be
discharged into storm drains via silt removal facilities.
·
All open stockpiles of construction materials (for
example, aggregates, sand and fill material) should be covered with tarpaulin
or similar fabric during rainstorms. Measures should be taken to prevent the
washing away of construction materials, soil, silt or debris into any drainage
system.
·
Manholes should always be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris
being washed into the drainage system and storm runoff being directed into foul
sewers.
·
Precautions to be taken at any time of year when
rainstorms are likely, actions to be taken when a rainstorm is imminent or
forecasted, and actions to be taken during or after rainstorms are summarized
in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the
control of silty surface runoff during storm events.
·
All vehicles and plant should be cleaned before
leaving a construction site to ensure no earth, mud, debris and the like is
deposited by them on roads. An
adequately designed and sited wheel washing facilities should be provided at
every construction site exit where practicable.
Wash-water should have sand and silt settled out and removed at least on
a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and
exiting from, the wheel-wash bay to the public road should be paved with
sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of
soil and silty water to public roads and drains.
·
Oil interceptors should be provided in the drainage
system downstream of any oil/fuel pollution sources. The oil interceptors
should be emptied and cleaned regularly to prevent the release of oil and
grease into the storm water drainage system after accidental spillage. A bypass
should be provided for the oil interceptors to prevent flushing during heavy
rain.
·
Construction solid waste, debris and rubbish on
site should be collected, handled and disposed of properly to avoid water
quality impacts.
·
All fuel tanks and storage areas should be provided
with locks and sited on sealed areas, within bunds of a capacity equal to 110%
of the storage capacity of the largest tank to prevent spilled fuel oils from
reaching water sensitive receivers nearby.
·
Regular environmental audit on the construction site
should be carried out in order to prevent any malpractices. Notices should be posted at conspicuous
locations to remind the workers not to discharge any sewage or wastewater into
the water bodies, marsh and ponds.
6.6.1.2
By adopting the best management practices, it is anticipated that the
impacts of general site operation will be reduced to satisfactory levels before
discharges. The details of best management practices will be highly dependent
to actual site condition and Contractor shall apply for a discharge license
under WPCO.
6.6.2
Implementation of Temporary Cofferdams
during Construction Phase
6.6.2.1
Cofferdam should be constructed to isolate the construction activities
from the nullah water. The detail design of the cofferdams will be conducted by
the Contractor during the construction phase to fulfil the requirements in DSD
Technical Circular No. 14/200 “Temporary Flow Diversions and Temporary Works
Affecting Capacity in Stormwater Drainage System for DSD approval in order to formulate
feasible options of these temporary structure.
6.6.3
Mitigation Measure for
Construction Activities / Sites in close proximity to the Dry Weather Flow
Channel
6.6.3.1
In addition to Section 6.6.1 and Section 6.6.2, following mitigation
measures are also recommended for the construction activities / sites in close
proximity to the dry weather flow channel:
·
Water pumps should be used to collect any
construction site surface runoff and ingress / seepage water within the
cofferdam. The collected construction site surface runoff and ingress / seepage
water should be diverted to the on-site wastewater treatment facilities for
treatment to satisfactory levels before discharge;
·
Prior to the completion of the temporary platform,
any temporary stockpile should be stored outside the nullah and at location
away from the air sensitive receivers. Bunds should be installed around the
stockpile area and stock material should be covered with tarpaulin to minimize
leakage as practicable as possible;
·
Stockpile should be located within the cofferdam
which will be designed to be water tight and be covered with tarpaulin if
storage within nullah is unavoidable,
·
Once the temporary platform is completed, any
stockpile should be stored on the temporary platforms which should be designed
to be water tight to prevent leakage;
·
Removal of stockpile from the site as soon as
possible and overnight storage should be avoided;
·
Avoidance of stockpiling materials near the dry
weather flow channel; and
·
Avoidance of major excavation during high stream
flow.
6.6.4
Emergency Contingency Plan
6.6.4.1
Given the construction activities will be conducted inside or above the
nullah, the nullah would be potentially affected during construction phase when
there is accidental spillage of chemicals or leakage of polluting water into
the nullah. Therefore, an emergency contingency plan should be prepared by the
Contractor to state the details of action in such an event. The Contractor
should prepare the contingency plan prior to the commencement of construction
works and for submission to IEC, Engineer and EPD for approval.
6.6.5
Sewage from Workforce
6.6.5.1
Portable chemical toilets and sewage holding tanks should be provided
for handling the construction sewage generated by the workforce. A licensed
contractor should be employed to provide appropriate and adequate portable
toilets to cater 0.23 m3/day/employed population and be responsible
for appropriate disposal and maintenance.
6.6.5.2
Notices should be posted at conspicuous locations to remind the workers
not to discharge any sewage or wastewater into the nearby environment during
the construction phase of the Project. Regular environmental audit on the
construction site should be conducted in order to provide an effective control
of any malpractices and achieve continual improvement of environmental
performance on site. It is anticipated that sewage generation during the
construction phase of the Project would not cause water quality impact after
undertaking all required measures.
6.7
Mitigation Measures during Operational
Phase
6.7.1
Surface Runoff from Elevated
Pedestrian Corridor
6.7.1.1
As discussed in Section 6.5,
adverse water quality impact is not anticipated with the proper installation of
drainage system. Hence, no specific mitigation measures would be required
during the operational phase.
6.7.2
Permanent Structure of the Elevated
Pedestrian Corridor
6.7.2.1
As discussed in Section 6.5, the
Project would provide mitigation measures to mitigate the flood risk of the
Yuen Long Town Nullah. According to the latest design, the following mitigation
measures are recommended to mitigate the impact to acceptable level:
·
construction of parapet wall, that the height is
subject to further drainage impact assessment, which is capable to containing
passage of 50 year design events with 500mm freeboard and passage of 200 year
design event;
·
adopting of lens-shaped footbridge column to reduce
head loss; and
·
connecting individual rows of supporting column at
the three existing road bridges to reduce head loss.
6.7.2.2
As mentioned in Section 3.4.3.2,
the size of permanent structure inside the nullah would be also minimized.
Width of columns and walls within nullah will not exceed 1m in width and will
be orientated in line with the nullah flow. Drainage impact assessment would be
conducted to mitigate the potential flood risk and hydraulic impact to
acceptable level.
6.8.1.1
With implementation of the recommended mitigation measures, the Project would
not generate unacceptable residual water quality impacts.
6.9.1.1
During construction phase, potential water pollution and impact sources
have been identified as construction of elevated
pedestrian corridor within Yuen
Long Town Nullah, construction site surface runoff, sewage from site workforce
and temporary structure within the nullah. With the full implementation of the
recommended mitigation measures, such as covering excavated materials and
providing sedimentation tanks on-site etc., no adverse water quality impact is
anticipated.
6.9.1.2
During the operational phase, the potential water quality impact is
mainly surface runoff from the elevated pedestrian
corridor and permanent structure
of the proposed elevated pedestrian corridor within the nullah. With the proper installation of
drainage system and recommended mitigation measures, no adverse water quality
impact is anticipated.