CONTENTS
Page
1. Introduction................................................................................................................. 1
1.1 Project Background............................................................................................................................ 1
1.2 Purpose and Nature of
the Project.................................................................................... 1
1.3 Purpose and Approach of
the EIA Study......................................................................... 2
1.4 Justification for the
Need of the Project.................................................................. 2
2. PROJECT DESCRIPTION.................................................................................................... 4
2.1 Project Components and
Project Layout...................................................................... 4
2.2 Site Location and
History............................................................................................................. 4
2.3 Project Programme............................................................................................................................... 4
2.4 Consideration of
Alternative Treatment Level, Design, Layout, Outfall Alignment, Construction
Methods and Sequence of Works................................................................... 5
3. ENVIRONMENTAL IMPACTS............................................................................................ 6
3.1 Air Quality..................................................................................................................................................... 6
3.2 Noise...................................................................................................................................................................... 7
3.3 Water Quality............................................................................................................................................ 7
3.4 Waste Management and
Land Contamination........................................................ 8
3.5 Ecology.............................................................................................................................................................. 9
3.6 Fisheries........................................................................................................................................................ 11
3.7 Landscape & Visual............................................................................................................................. 11
3.8 Cultural Heritage............................................................................................................................. 13
3.9 Environmental Monitoring
& Audit................................................................................ 14
4. OVERALL CONCLUSION.................................................................................................. 14
Figures
|
Treatment Capacity
(m3/day)
|
Tentative Year of
Commissioning
|
|
Increased by
|
Total
|
Existing
|
-
|
1,660
|
-
|
Phase 1
|
3,340
|
5,000
|
2021
|
Phase 2
|
5,000
|
10,000
|
End 2030
|
1.2.2
The works for this Project in Sha Tau Kok mainly
comprises of the following items and as shown in the Layout Plan of Figure 2.1:
a)
Increase the
treatment capacity of Sha Tau Kok Sewage Treatment Works (STKSTW) to 5,000 m3/day
at Average Dry Weather Flow (ADWF) by 2021, with suitable
allowance to cater for a further increase of treatment capacity to 10,000 m3/day
at ADWF after 2030 in Phase 2;
b)
Construct a temporary sewage treatment plant (TSTP)
with a capacity of 2,500 m3/day
at ADWF;
c)
Demolish the
existing Sha Tau Kok Sewage Pumping Station (STKSPS) and decommission the
rising main between STKSPS and STKSTW;
d)
Construct approximately 520m long new gravity sewer; and
e)
Abandonment the existing submarine outfall and
construct a approximately 1700m long new submarine
outfall.
a)
Schedule 2, Part
I, Item F.2 (a) and (b)(i) - Sewage Treatment Works with an installed capacity
of more than 5,000 m3 per day; and a boundary of which is less than
200m from the nearest boundary of the an existing residential area; and
b)
Schedule 2, Part
I, Item F.6 - a submarine outfall.
1.3
Purpose and Approach of the EIA Study
a)
The overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the proposed Project;
b)
The conditions
and requirements for the detailed design, construction and operation of the
proposed Project to mitigate against adverse environmental consequences, as
practicable; and
c)
The acceptability
of residual impacts after implementation of the proposed mitigation measures.
1.3.2
The specific objectives of the EIA Study are
described in Clause 2 of the EIA Study Brief, and the detailed requirements of
the EIA Study are set out in Clause 3 of the EIA Study Brief. As specified in the EIA Study Brief, the EIA
Study has addressed the key environmental issues associated with the
construction and operation of the Project.
Existing Conditions
1.4.3
The
existing submarine outfall is discharging near-shore of Starling Inlet. The discharge point is close to the
nearby fish culture zone. A new submarine outfall and hence a new discharge
point would be required to facilitate the increase in sewage flow and to
improve the dilution of effluent by water current.
Purpose of the Project
Environmental Benefits of the Project
a)
Improve treatment
to produce effluent with better quality;
b)
Provide more
treatment capacity within the existing plant site;
c)
Cover the treatment
facilities and provide odour treatment to improve air quality;
d)
Incorporate
environmental enhancements in the new treatment facilities, including renewable
energy, energy-efficient electrical and mechanical equipment, greening, water
saving measures, etc.;
e)
Locate the
discharge point of the new submarine outfall away from sensitive receivers,
including the fish culture zones and the identified species of conservation
importance; and
f)
Demolish STKSPS
to make the land available for other beneficial purposes.
2.1.1
Table 2.1 presents a summary of the project
details. The site area of the proposed expansion of STKSTW will be
approximately 4,950 m2, with a 524m of gravity collection sewerage
system along Shun Hing Street. A maximum total dredging volume of 3,040m3
of marine sediments will be generated from the construction of diffuser for the
submarine outfall. The preliminary layout plan for this Project is presented in
Figure 2.1.
Table 2.1 Summary of Project Description
Details
|
Preliminary Design Information
|
Submarine Utilities
|
|
Excavated
Sediment volume (in situ volume)
|
|
·
Diffuser
|
3,040 m3
|
Length of
Submarine Utilities (m)
|
|
·
Outfall
|
~ 1.7 km
|
Expanded Sha Tau Kok Sewage Treatment Works
|
|
Site area
|
4,950 m2
|
Footprint of
above-ground structure
|
1,740 m2
|
Dimension of
above-ground structure
|
73m (L) x 24m (W)
|
Building
height
|
Ranged 10m
–19m
|
Site Coverage
|
35%
|
Gross Floor
Area
|
5,700m2
|
Temporary Sewage Treatment Plant
|
|
Footprint of
above-ground structure
|
774 m2
|
Dimension of
above-ground structure
|
47m (L) x 18m (W)
|
Building
height
|
10m
|
Gravity Sewer
|
|
Excavation
volume
|
4,620 m3
|
Length of the
gravity sewer
|
524 m
|
|
|
Table 2.2 Key Dates of Implementation Programme
Item
|
Tentative Date
|
Approval
of Application for Permission under
Section 16 of the Town Planning Ordinance
|
Nov 2016
|
Tender Gazette
|
Jan 2017
|
Commencement of Construction
|
May 2017
|
Completion of Construction
|
Dec 2022
|
a)
Alternative
treatment level: Secondary treatment level has been considered for STKSTW,
which is capable of removing biodegradable organic matter, suspended solids and
total nitrogen for compliance with the Water Quality Objectives of Mirs Bay
Water Control Zone. The treatment method can fulfil the Project requirements
without causing adverse water quality and ecological impact.
b)
Alternative
treatment process: Three secondary treatment processes have been investigated,
which are Membrane Bioreactor (MBR), Moving Bed Bioreactor with Dissolved Air
Floatation (MBBR+DAF) and Sequencing Batch Reactor (SBR). Compared with MBBR
and SBR, MBR can provide the best effluent quality within the same footprint.
MBR is thus adopted as the preferred treatment process for the expansion of
STKSTW
c)
Alternative new
locations for new treatment facilities: Three expansion options have been
investigated, which is utilizing new site for construction of TSTP, expansion
within the existing site and utilizing the existing police operation base for
expansion. Compared to utilizing extra land, expansion within the existing
footprint create less environmental impacts since the footprint is far from
residential area.
d)
Alternative
submarine outfall alignment: Two discharge locations have been considered, one
is discharging in the vicinity of the existing outfall discharge location and
one is discharging further away in the water near Ah Kung Au. Preliminary
modelling results showed that compliance with Water Quality Objectives of Mirs
Bay Water Control Zone maybe difficult if discharging in the vicinity of the
existing outfall discharge location and hence discharging in the water near Ah
Kung Au is preferred.
e)
Phased
installation for different flow projections: Single phase and phased
installations for E&M works have been considered. Phased installation is
preferred so as to avoid the amount of idled equipment which will increase the
energy consumption for maintenance.
f)
Alternative
designs to avoid or minimize emergency discharge: Different precautionary
measures have been investigated, such as dual power supply, backup generator,
standby equipment, provision of onsite storage and tanker away. Tanker away is not preferred because large
number of tankers required will cause additional air quality and noise impact
to the nearby residential area. It is proposed to provide dual power supply,
standby equipment and provision of onsite storage for minimizing the risk of emergency
discharge.
g)
Other
considerations: Considerations have also been given to the demolition of Sha
Tau Kok Sewage Pumping Station and new sewer alignment. It is considered to
demolish the STKSPS and replace it with a gravity collection system along Shun
Hing Street.
a)
Limit
the footprint to 5,000m2 for the construction works to the existing
STKSTW site. This is far from residential area and comparatively less
environmental impacts will be created.
b)
Provide the best effluent quality within a small footprint.
c)
Odour,
noise and visual impacts to surrounding sensitive receivers can be minimized.
d)
Fewer
sensitive receivers are immediately affected (Sha Tau Kok Chuen, Sha Tau Kok
Recreation Ground and Police Operation Base) during construction and operation in
comparison to the other option.
e)
Safeguard
water quality at Starling Inlet.
f)
Can
achieve the Water Quality Objectives of Mirs Bay Water Control Zone
g)
Proposed
outfall located further away from Sha Tau Kok Fish Culture Zone
h)
Reduce
extent of land required for construction and hence reduce the environmental
impacts to nearby sensitive receivers
i)
Reduce
the amount of idle equipment which increase energy efficiency
j)
Reduce
use of chemicals required for the maintenance of the idle equipment
k)
No
significant impact to the marine ecology in comparison to the dredging method.
Approximately 3,040m3 sediment will be removed.
3.3.6
The potential change in water quality of
an emergency discharge from the TSTP and the expanded STKSTW is transient and
reversible. Nevertheless, a number of precautionary measures have been
taken into account in the design to minimize the risk of discharge of untreated
or incompletely-treated sewage into the marine water of Starling Inlet under
emergency situation.
3.6.2
A literature review
of baseline information on commercial fisheries resources and fishing
operations surrounding the waters of the proposed Project has been undertaken.
Sensitive receivers including Fish Culture Zones at Sha Tau Kok, Ap Chau, Kat
O, O Pui Tong, Sai Lau Kong and Wong Wan (at least 1.17 km away
from the diffuser of the proposed submarine outfall), recognized spawning
and nursery ground of commercial fisheries at northeast waters (at
least 2 km away from the diffuser of the proposed submarine outfall) and artificial reefs
at Yan Chau Tong Marine Park and O Pui Tong (at
least 5.88 km away from the diffuser of the proposed submarine outfall) have been identified.
The potential fisheries sensitive receivers are located at least 1.17km from
the diffuser of the proposed submarine outfall. However, the assessment of
water quality impacts demonstrated that these areas will not be significantly
affected.
3.6.6
As a good practice, it is recommended to
establish a communication plan as a precautionary approach to inform the
mariculturists, relevant stakeholders (e.g. Sha Tau Kok District Rural
Committee) and relevant government departments (e.g. AFCD, EPD, MD) of the
emergency discharge situation at STKSTW such that appropriate response actions can
be formulated.
3.7.3
The
key sources of impacts include: site clearance for the new STKSTW site, works for
the new permanent STKSTW / TSTP, removal of existing trees, construction
activities for associated minor works of demolition of the existing STKSPS and
construction of a new gravity sewer along the vehicular access of Shun Hing
Street at Sha Tau Kok.
-
LR6.10
- Trees surrounding Sha Tau Kok Sewage Treatment Works
-
LCA4
- Boundary Crossing Facilities Landscape
-
LCA5
- Sha Tau Kok Rural Township Landscape
-
VSR
R1 - Residents in Block 42 – 45 of Sha Tau Kok Chuen
-
VSR
R2 - Residents in Ha Tam Shui Hang
-
VSR
R3 - Residents in Muk Min Tau
-
VSR
R4 - Residents in Block 13-15 of Sha Tau Kok Chuen
-
VSR
R5 - Residents at 3-17 Shun Lung Street
-
VSR
R6 - Residents of Public Housing Development at Shun Hing Street
-
VSR
O1 - Workers/Officers in Sha Tau Kok Fire Station
-
VSR
O2 - Police Operation Base
-
VSR
O3 - Workers of Sha Tau Kok Fish Culture Zone
-
VSR
T1 - Motorists on Sha Tau Kok Road
-
VSR
T2 - Marine users on Starling Inlet
-
VSR
RE1 - Recreational Users of Sha Tau Kok Chuen Area
-
VSR
RE2 - Recreational Users of Sha Tau Kok Promenade Sitting-out Area (1)
-
VSR
RE3 - Recreational Users of Land Use Zoning REC(1)
-
VSR
RE4 - Recreational Users at Yim Liu Ha
-
VSR
RE5 - Recreational Users of Sha Tau Kok Promenade Sitting-out Area (2)
3.7.6
During
the course of developing the proposed project and assessing the landscape and
visual aspects, a series of mitigation measures are carefully considered in the
project design for impact avoidance, impact minimisation and landscape and
visual enhancement as far as practical. Recommended mitigation measures include
preservation of existing trees, proper control of site construction activities,
transplantation of existing trees, suitable design of the expanded STKSTW,
compensatory planting and amenity enhancement.
3.7.9
At
Year 10 of operation, LR6.10 will receive slight beneficial impact with full
establishment of mitigation measures during the operation period. The reason for the slight beneficial
impact experienced by the LR6.10 is that there will be a net gain of tree
planting area (increased to 0.42ha from original 0.31ha) and overall planting
area (increased to 0.45ha from original 0.31ha). VSR T2 would
experience slight negative mitigated impacts during the operation phase, which
is considered within acceptable range due to the low sensitivity in nature of
the travelling type VSR, the glimpse duration of view and its panoramic quality
of views over the Starling Inset seascape. All others receivers (LCA4, LCA5, R1, R2, R3, R4, R5,
R6, T1, O1, O2, O3, RE1, RE2, RE3, RE4, RE5) will experience insubstantial impact with full establishment of
mitigation measures during the operation period.
-
LR6.10
- Trees surrounding Sha Tau Kok Sewage Treatment Works
4.1.2
Recommendations for
an environmental monitoring and audit programme have been prepared to ensure
the effectiveness of the recommended mitigation measures.